PROJECT CHARTER
4. Budget Information
All the funds will be covered by the beneficiary Party I.e. Institute of
International Management and Science. The majority of cost will be the labor. All
the hardware will be made available by beneficiary party.
5. Project Manager:
Awins Poudel (977)9843557852, awinspoudel@gmail.com
6. Project Objectives:
The objective is to release the first final version in 5-month Duration.
8. Approach
Create the Work Breakdown Structure (WBS) within 1-month time and prepare
a Gantt chart detailing the work required to complete the project.
Manage all the hardware resources and workspace within 1 week of WBS
1
release.
Hold the weekly progress review meetings with the core project team and
sponsor
Conduct through software testing as per the approved test plans