CLIENT: RENAULT NISSAN ORAGADAM

PROJECT: SPRINKLER SYSTEM FOR CKD WAREHOUSE


CONTRACTOR:METEC DESIGN AND CONSTRUCTION ENGINEERS INDIA PVT LTD
Fabrication Date 24-02-2019
BOQ Previous Yesterday Cummulative
SL.NO DESCRIPTION Units
QTY complition complition complition

Internal work pipe fabrication


a Edge preparation (Grooving/threading)
150NB 1550 mtrs 1386 1386
50NB 7600 mtrs 180 240 420
25NB 60 mtrs

b Marking & Hole making


150NB 372 nos 90 26 116
50NB 2350 nos

c O-let fixing & welding


50NB 2350 nos

d Cleaning & primer painting


150NB 1550 mtrs 522 90 612
50NB 7600 mtrs
25NB 60 mtrs

e Painting 1st coat


150NB 1550 mtrs 432 132 564
50NB 7600 mtrs
25NB 60 mtrs

f Painting 2nd coat


150NB 1550 mtrs 432 132 564
50NB 7600 mtrs
25NB 60 mtrs

g Internal work support fabrication


support fabrication for 150 NB @ grid 1 & grid 3 60 nos 60 60
support fabrication for 150 NB @ grid 2 60 nos 60 60

c External work pipe fabrication


250 NB edge preparation 420 mtrs

d External work support fabrication


support for 250 NB 100 nos

Page 1 of 1 METEC DESIGN, TAMILNADU