You are on page 1of 14

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/317081354

Statistical Distributions for the Corrosion Rates of Conventional and


Prestressing Steel Reinforcement Embedded in Chloride Contaminated
Mortar

Article  in  Corrosion -Houston Tx- · May 2017


DOI: 10.5006/2330

CITATIONS READS

0 1,113

2 authors:

Jayachandran K Radhakrishna Pillai


Aditya Birla Group Indian Institute of Technology Madras
14 PUBLICATIONS   14 CITATIONS    96 PUBLICATIONS   280 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

National Centre for Safety of Heritage Structures View project

Chloride Threshold of Prestressing Steel in Cementitious Systems with Ordinary Portland Cement, Fly Ash, and Corrosion Inhibitors View project

All content following this page was uploaded by Radhakrishna Pillai on 25 January 2018.

The user has requested enhancement of the downloaded file.


CORROSION SCIENCE SECTION

Statistical Distributions for the Corrosion


Rates of Conventional and Prestressing
Steel Reinforcement Embedded in Chloride
Contaminated Mortar

J. Karuppanasamy* and R.G. Pillai‡,*

ABSTRACT INTRODUCTION
Many concrete structures are built using plain mild (PM) and The service life of structures can be defined as the
cold-twisted deformed (CTD) steel rebars. Also, quenched and duration for which the structure is able to meet the
self-tempered (QST) and prestressing (PS) steels are exten-
desired performance and safety. Most of the infra-
sively used in today’s construction. For estimating the corrosion
structure projects are designed and built by considering
propagation period (tp) of concrete structures, the current
practice is to assume that the corrosion rate (icorr) of different a particular service life (or design life). However, many
steels are equal to that of PM steel—leading to erroneous of the reinforced concrete structures are showing the
estimation of tp. This paper provides icorr data from a 33-month signs of premature distress because of overloading,
experiment on PM, CTD, QST, and PS steels embedded in aging of materials, aggressive environmental conditions,
chloride contaminated mortar. Linear polarization resistance inadequate maintenance, etc. The presence of oxy-
test was adopted for icorr measurement. A total of 100 spe- gen, moisture, and chlorides at the surface of embedded
cimens were tested. It was found that the CTD and QST steels steel reinforcing bars (i.e., rebar) can lead to the
exhibit higher icorr than the PM and PS steels. The paper also
initiation of corrosion. Because of prolonged corrosion,
provides statistical distributions for icorr of these four steels. For
the cover concrete can crack and spall. This can lead
PM, CTD, QST, and PS steel embedded in chloride contami-
nated mortar, and exposed to wet-dry conditions, these are
to further deterioration and reduction in the structural
found to be ∼Weibull (2.5, 20.7, 0) μA/cm2, ∼Lognormal (0.45, load carrying capacity. This increase in deterioration
3.2, 0) μA/cm2, ∼Gamma (6.8, 3.5, 0) μA/cm2, and ∼Weibull is indicated by the increase in the slope of the curve in
3P (1.3, 6.5, −0.02) μA/cm2, respectively. Similar distribu- Figure 1. The corrosion propagation period (tp) can be
tions for dry condition are also presented. These statistical tools defined as the time required to initiate crack in the cover
would help engineers in estimating residual service life and concrete and depends on the corrosion rate (icorr) of
scheduling repair activities. the embedded steel. Sometimes, the time available to
KEY WORDS: cold-twisted deformed, concrete, corrosion
repair the corroding structural elements is very short,
propagation, corrosion rate, quenched and self-tempered (QST), once the corrosion is initiated. In order to avoid the
plain mild steel, prestressing steels, statistical distribution, unexpected/sudden failure and facilitate precau-
thermomechanically treated tionary measures, the estimation of tp and frequent
monitoring of icorr for these structures are essential.
This paper focuses on determining the probabi-
Submitted for publication: November 9, 2016. Revised and accepted:
listic icorr and tp for the systems with the following four
May 18, 2017. Preprint available online: May 18, 2017, http:// types of steel reinforcement that are widely used in
dx.doi.org/10.5006/2330. the concrete structures. These are: (1) plain mild (PM),

Corresponding author. E-mail: pillai@iitm.ac.in.
*
Department of Civil Engineering, Indian Institute of Technology (2) cold-twisted deformed (CTD), (3) quenched and
Madras, Chennai, India. self-tempered (QST), and (4) prestressing (PS) steel
ISSN 0010-9312 (print), 1938-159X (online)
CORROSION—Vol. 73, No. 9 17/000185/$5.00+$0.50/0 © 2017, NACE International 1119
CORROSION SCIENCE SECTION

f(t10%) such complicated mathematical models may not be


10% area loss of steel rebar preferred by the practicing engineers as they require
many input parameters and additional skills to
estimate tp. A few other researchers have attempted to
develop simple mathematical models and empirical
formula to predict tp. Parameters required for the
tp models developed by various researchers for different
Crack initiation at concrete surface
Deterioration Level

models are listed in Table 1.6-10 Each model requires


different input parameters as per the assumed
corrosion mechanism and cracking process in con-
Corrosion initiation in steel crete cover. In this paper, the Wang and Zhao5 model
that uses some of the most commonly and easily
f(tp) available parameters was considered for the estimation
of tp.
Wang and Zhao5 have developed an empirical
Corrosion Initiation Phase Corrosion Propagation Phase
model with an assumption of constant corrosion rate
FIGURE 1. Representation of probabilistic corrosion propagation to estimate tp. This model assumes that the tp ends
period. when the first corrosion-induced crack occurs, as
defined earlier in this paper. It is assumed that first
crack occurs in concrete when the corrosion product
reinforcement. The QST reinforcement is also known reaches a certain quantity. Equation (1) gives the
as thermomechanically treated (TMT) reinforcement, empirical formula suggested by Wang and Zhao5 to
especially in the Indian subcontinent. estimate tp.
This paper is organized as follows. A review of the
approaches for estimating the corrosion propagation H
tp = (1)
period (tp) is provided next. Then, reviews of icorr of Pr
various steel reinforcement and corrosion propagation
models available in the literature are provided. Fol- " #
Δ Δ
lowing this, the significance of this research and the H= =  0.565 (2)
details on the experimental program adopted to de- γ 0.33 CDv f 1.436
cu
termine the icorr are provided. Then, the experimental
results and statistical distributions of icorr of steels
embedded in mortar and exposed to cyclic wet-dry and  
W
dry environments are provided. The probabilistic Pr = i (3)
Fρst corr
estimations on tp (i.e., until crack initiation) and the
time required for 10% and 15% reduction in tensile
strength of PM, CTD, QST, and PS steel reinforcement where tp is time between corrosion initiation and the
are provided. first cracking of cover concrete (y), H is the critical
depth of rebar penetration (mm), Δ is the critical
Corrosion Propagation Models thickness of corrosion product (mm), icorr is the av-
Life 365† is a commonly used software program to erage corrosion rate (A/mm2), γ is the corrosion product
estimate the service life and life-cycle cost of concrete expansion coefficient, D is initial diameter of the rebar
structures exposed to chloride environments.1 This (mm), Cv is the thickness of concrete cover (mm), fcu
software program assumes that tp is equal to 6 y for all is the cube strength of concrete (N/mm2), Pr is the
structures irrespective of steel and concrete used. penetration rate (mm/s), W is the equivalent weight of
This may not be conservative in many cases. Also, steel (g), F is the Faraday’s constant (C), and ρst is the
considering the random nature of corrosion process, density of steel (g/mm3). Wang and Zhao5 model as-
a probabilistic approach for estimating tp for different sumed that the corrosion products will fill the steel/
types of steel/cementitious system is required. Many cementitious interface and develop an expansive pres-
corrosion propagation models are available in the sure or tensile stress on the cover concrete, which will
literature. crack when the exerted tensile stress from the expansive
Each estimation model may vary in their choice of corrosion product exceeds the tensile strength of the
input parameters and their approach of estimation. For concrete.5 This is empirically related to the compressive
example, the cracking behavior of concrete caused by strength. The tp can be predicted using this model
the corrosion of steel was used in the nonlinear fracture using the icorr data measured from the field and
models and/or finite element analysis.2-5 However, laboratory.
Andrade, et al.,6 derived an empirical formula

Trade name. (Equation [4]) which uses the icorr to calculate the

1120 CORROSION—SEPTEMBER 2017


CORROSION SCIENCE SECTION

TABLE 1
Input Parameters Required for Different Propagation Models
Sl. No Parameters Considered Wang and Zhao5 Bazant6 Morinaga7 Liu and Weyers8 Stratfull9 Clear10

1 Initial diameter of steel rebar ✓ ✓ ✓ ✓


2 Corrosion rate of steel rebar ✓ ✓ ✓ ✓
3 Density of steel rebar ✓ ✓ ✓
4 Equivalent weight of steel rebar ✓ ✓ ✓
5 Faraday’s constant ✓ ✓ ✓
6 Perimeter of steel rebar ✓ ✓
7 Bar hole flexibility ✓
8 Poisson ratio of concrete ✓
9 Elastic modulus of concrete ✓
10 Concrete creep coefficient ✓
11 Thickness of cover concrete ✓ ✓ ✓
12 Crack expansion coefficient of concrete ✓
13 Cube strength of concrete ✓
14 Depth of rebar penetration ✓
15 Density of corrosion product ✓
16 Thickness of corrosion products to generate ✓
the tensile stress on concrete
17 Mass of steel rebar corroded ✓
18 Thickness of pore band around steel/concrete ✓
interface
19 Chloride concentration at surface ✓ ✓
20 Water-cement ratio ✓ ✓
21 Time of exposure ✓

reduction in the diameter of steel rebar after long- represent the corrosion propagation mechanism that
term exposure. occurs in field conditions.

0t = =00
= − 0.023 × icorr × t (4) Corrosion Rates of Steel Reinforcement
Many researchers have been following the gravi-
metric mass loss method to obtain the average corrosion
0t
= is the diameter of the rebar at time “t” after cor-
rate over the period of exposure (say, in mm/y).
rosion initiation and =00 is the initial diameter of rein-
Nowadays, with the advancement of technology, the
forcement. Note that Equation (4) considers constant
icorr. However, this icorr can vary with time, depending on linear polarization resistance (LPR) tests can be con-
the relative humidity (RH) and temperature variations ducted to represent the instantaneous corrosion rate or
prevailing in the different exposure conditions and corrosion current density (say, in μA/cm2). Table 2
inside concrete. Therefore, the prediction of tp must shows the icorr for different steel reinforcement reported
consider the duration of wet and dry seasons prevailing in literature.13-21 These reported values exhibit sig-
at site in order to get realistic estimates. nificant scatter. The possible reasons for such huge

Average Annual Corrosion Rate in the Field


In the current test program, icorr data were TABLE 2
measured at the end of each wet cycle followed by a dry Corrosion Rates of Different Steel Reinforcement Reported
period measurement. The icorr at field conditions can in Literature(A)
vary as a function of the length of the annual rainy/ Steel
sunny seasons (i.e., wet and dry periods). By con- Type Corrosion Rate Reference
sidering the seasonal effects, icorr,wet and icorr,dry, the
BS 2.54 μm/y Spellman and Stratfull13
weighted average of annual corrosion rate (icorr,annual) BS 94 μm/y Clear14
is calculated as given in Equation (5):13 BS 16 to 32 μm/y Hladky, et al.15
BS 0.025 to 1.620 μm/y Ismail and Ohtsu16
BS 1 to 2 μm/y Hansson and Sorensen17
icorr,annual = α × icorr,wet þ ð1 − αÞ × icorr,dry (5) BS 0.026 to 1.575 μA/cm2 Berke, et al.18
CTD 3 to 4.2 μA/cm2 Pradhan and Bhattacharjee19
CTD 0.7 to 2.6 μA/cm2 Firodiya, et al.20
where icorr,wet = corrosion rate in wet conditions, MS 0.5 to 1.7 μA/cm2 Firodiya, et al.20
icorr,dry = corrosion rate in dry conditions, and α = ratio PS 3 to 9 μA/cm2 Karuppanasamy and Pillai21
(A)
of the duration of rainy-to-sunny season per year. BS: black steel. CTD: cold-twisted deformed. MS: mild steel.
The tp estimated based on the icorr,annual may better PS: prestressing steel.

CORROSION—Vol. 73, No. 9 1121


CORROSION SCIENCE SECTION

scatter are the differences in (i) chemical composition Electrical lead


of steel, (ii) specimen design, (iii) test methods,
(iv) experimental setup, (v) exposure conditions, etc.,
across the studies. For example, Soylev and Richard- Rebar (epoxy coated)
son22 exposed the black steel rebar to 2%, 3%, and 4%
of sodium chloride solution and found the icorr as
5.7 μA/cm2, 6 μA/cm2, and 10.7 μA/cm2, respectively. Mortar cover around the bar
Pradhan and Bhattacharjee19 reported that the icorr of
CTD reinforcement embedded in ordinary Portland Rebar (exposed to NaCl)
420 mm 50 mm
cement (OPC) concrete with various water-cement
ratios and different dosages of pre-mixed chlorides
ranged from 3 μA/cm2 to 4 μA/cm2. Pradhan and
Bhattacharjee14 also reported icorr for the QST steel Epoxy coating at mortar joint
325 mm
reinforcement embedded in concrete is within the range
of 2.5 μA/cm2 to 6 μA/cm2. Thus, the literature Repair mortar
confirms that the icorr may vary for different steel types,
40 mm
cementitious system, exposure conditions, and testing
methods. Also, the statistical distribution of icorr of
16 mm
various steels are necessary for realistic estimation
of tp. Note: For prestressing steel specimens, the diameter of the steel
piece and mortar cylinder were 5.2 mm and 29.2 mm, respectively.
FIGURE 2. Corrosion test specimen with a steel bar embedded in
RESEARCH SIGNIFICANCE
mortar.
Service life of a structure can be defined as a
sum of corrosion initiation period (ti) and corrosion
propagation period (tp). Most of the reinforced 24 months. Every month, at the end of wet period, the
concrete structures are built or being built using corrosion rate (icorr,wet) of each specimen was measured
either PM, CTD, QST, or PS steel as reinforcement. using linear polarization technique. Also, the speci-
The statistical distribution of icorr is necessary for mens were then allowed to dry in the standard labo-
probabilistic estimation of tp. However, very limited ratory environment until the end of the 33rd month.
information is available on the icorr of PM, CTD, The corrosion rate (icorr,dry) was measured at the 27th
QST, and PS steel reinforcement, making it difficult and 33rd month. These data were used to develop a
to estimate the tp. Current practice is to assume statistical distribution of icorr,wet and icorr,dry, which were
similar icorr for PM, CTD, QST, and PS steel, which later used to estimate probabilistic tp. The details of
may give erroneous estimations of probabilistic tp. the materials used, casting, exposure conditions, test
In addition, many software programs inadequately procedure, etc., are described next.
assume deterministic values for tp, irrespective of the
type of materials used in the structure. This paper Materials Used
provides experimental data and statistical distribu- The mortar with water:cement:sand ratio of
tions for icorr of PM, CTD, QST, and PS steel rein- 0.55:1:2.75 and an average compressive strength of
forcement embedded in chloride contaminated about 30 MPa was used. The initial and final setting
mortar. These statistical distributions and proba- time of the 53 Grade OPC cement was 52 min and
bility density function (PDF) developed can be very 265 min, respectively. The fineness value was
valuable to budget and plan the maintenance, 310 m2/kg, as per ASTM C204.23 The oxide composition
monitoring, and repair activities for the structures of the OPC cement was determined by x-ray fluo-
experiencing corrosion.
rescence spectroscopy (see Table 3). Standard silica
sand (known as Ennore sand in India) of Grades I,
EXPERIMENTAL PROGRAM II, and III, as classified in IS:38324 was used. Distilled
water was used for preparing the mortar and chloride
Overview solutions. Table 4 shows the chemical composition
A comprehensive corrosion test program was (determined using optical emission spectroscopy)
conducted to determine the probabilistic corrosion rate of PM, CTD, QST, and PS steel reinforcement used for
(icorr) of four types of steel reinforcement. Schematic of this study.
the test specimen is shown in Figure 2. Twenty-five
specimens of each steel type, adding to a total of 100
specimens, were cast. The cast specimens were cured Specimen Design and Preparation
for 28 d and then subjected to cyclic wet-dry exposure The schematic of the specimen is shown in
using 3.5% sodium chloride solution for a period of Figure 2. The PM, CTD, and QST reinforcement (with

1122 CORROSION—SEPTEMBER 2017


CORROSION SCIENCE SECTION

TABLE 3 with sodium chloride solution. This container was


Chemical Composition of 53 Grade Ordinary Portland covered with a plastic lid to avoid evaporation. During
Cement (OPC) Used the dry period, the specimens were placed outside of
Ingredients Concentration (%) this container. The wet-dry exposure was continued for
a period of 24 months under the laboratory envi-
CaO 66.67 ronment. Later, the specimens were allowed to
SiO2 18.91
Fe2O3 4.94 completely dry and the corrosion rates were mea-
Al2O3 4.51 sured at the 27th month and 33rd month.
SO3 2.5 Unfortunately, after 10 months of exposure, the
MgO 0.87 2-layer epoxy coating at the bottom end portion of
K2O 0.43
the steel specimens (a lower region with no mortar
Na2O 0.12
Loss of ignition 1.05 cover; see Figure 2) failed/cracked and led to severe
underfilm or crevice corrosion (i.e., beneath the
epoxy layer). This was a result of the poor long-
TABLE 4 term performance of epoxy coating; the specimens
Chemical Composition of PM, CTD, QST, and PS Steel exhibited large scatter in the icorr data. The icorr data
Reinforcement Used(A) obtained during this period do not truly represent
the actual corrosion rate at the predefined exposed
Element PM CTD QST PS
surface (center 50 mm long) of the specimen.
Cu 0.27 0.09 0.16 0.02 Therefore, the damaged epoxy coating and the
Co – 0.01 0.02 0.01 underfilm or crevice corrosion products were re-
Al – 0.01 0.03 0.04 moved by following the procedure given in ASTM
Ni 0.09 0.07 0.15 0.02
Mo 0.02 0.01 0.06 0.00 G1-16 (Designation C.3.5 in Table A1.1)25 and re-
Cr 0.08 0.07 0.24 0.27 coated with two new layers of epoxy. To avoid further
S 0.05 0.27 0.01 0.00 failure/cracking of the epoxy coating, the bottom
P 0.06 0.09 0.08 0.06 part of the epoxy coated steel was covered with
Mn 0.64 0.45 0.63 0.83
cement mortar (denoted as “repair mortar” in
Si 0.26 0.23 0.24 0.29
C 0.19 0.13 0.2 0.84 Figure 2). The interface between the old and new
Fe Re. Re. Re. Re. mortar was also sealed with epoxy. After 28 d of
(A) curing of the repair mortar, the repaired specimens
Re.: Remaining.
were again exposed to cyclic wet-dry conditions
using 3.5% sodium chloride solution and corrosion
16 mm diameter and 420 mm long) and king wire rate measurement was resumed after the 18th
(5.2 mm diameter and 420 mm long) removed from a month. During the period from the 10th month to the
7-wire PS strand were used to prepare the test spe- 18th month of exposure, the specimens were stored
cimens. The steel reinforcement was cleaned by im- in the laboratory environment (∼65% RH and ∼25°C).
mersing in ethanol and using an ultrasonic cleaner However, it should be noted that only the icorr
measured from the 19th month to the 24th month was
for 5 min—to maintain “as-received condition.” To
used for the development of statistical distribution
facilitate corrosion measurements, an insulated
in this paper.
copper wire (300 mm long) was fastened to one end of
the steel specimen using a metallic screw. Then, the
steel bar (except the 50 mm length at the center) and the Corrosion Test Setup and Corrosion Rate
screw were coated with two thin layers of a low vis- Measurements
cosity epoxy (Sikadur®-52 UF†). The steel reinforcement Figure 3 shows the three-electrode corrosion cell
was then embedded in mortar. with a working electrode (WE), a counter electrode (CE),
and a reference electrode (RE). All of the electrodes
were placed in a glass beaker with 3.5% sodium chloride
Curing and Exposure Conditions solution. Then the corrosion cell setup was connected
The test specimens were cured in a laboratory to a potentiostat and computer. The central 50 mm
environment (ambient temperature = 25±3°C and RH = long uncoated region of the steel piece was considered
65±5%) for 24±1 h after casting. After this, the spe- as the WE. A 90 mm diameter and 50 mm long
cimens were immersed/cured by immersing in satu- pipe (annular setup) made of Nichrome wire mesh
rated limewater for additional 27 d. Then, the cured (24 wires of 0.5 mm diameter per in) was used as the CE.
specimens were subjected to cyclic wet-dry exposure The test specimen was placed at the center of the
(i.e., 7 d wetting followed by 7 d drying) using 3.5% annular CE. The saturated calomel electrode (SCE) was
sodium chloride solution and in a laboratory environ- used as the RE and placed near the surface of mortar
ment with ∼65% RH and ∼25°C. During the wet cylinder (near the uncoated steel portion at the
period, the specimens were kept in a plastic container center 50 mm).

CORROSION—Vol. 73, No. 9 1123


CORROSION SCIENCE SECTION

B B
Counter electrode (CE) icorr = = (6)
Reference electrode (RE) R p ðΔE=ΔiÞE→Ecorr
Glass beaker

where B is the Stern-Geary coefficient, Rp is the


Mortar cover (12 mm)
polarization resistance, E is the applied potential, and
Steel specimen (WE)
Top View i is the measured corrosion current density. B is
Connecting wire
assumed as 26 mV for all of the measurements.
Corrosion Rate Measured During the Wet-Dry Cycle
and the Dry Period — The specimens were exposed to
7 d wet and 7 d dry cycle. The icorr values measured at
Reference electrode (RE)
the end of every 2nd wet cycle from the 19th month to
(SCE)
the 24th month are used as the corrosion rate during
Working electrode (WE)
(Steel specimen) wet period (denoted as icorr,wet). From the 25th month
to the 33rd month, the specimens were allowed to
Counter electrode (CE) dry in a laboratory environment (temperature = 25±3°C
(Nichrome mesh) and RH = 65±5%) and the icorr were measured at
the 27th month and the 33rd month. These were
3.5% NaCl solution
considered as the corrosion rate for dry period
(denoted as icorr,dry). Note that the dry specimens
were wetted by placing in a glass beaker with 3.5%
sodium chloride solution for 30 min prior to the
electrochemical testing. Only the icorr,wet, and icorr,dry
data were used for estimating tp, provided later in
Front View this paper.

FIGURE 3. Schematic of the three-electrode corrosion cell setup.


RESULTS AND DISCUSSION

Measured Corrosion Rate of Different Steels


Measured Corrosion Current Density,

Rp in Laboratory
1E–6 1 As mentioned earlier, this paper focuses only on
Tangent of the curve
tp, which mainly depends on the icorr of embedded steel
0 reinforcement embedded in mortar. Figure 5 shows
the average OCP of PM, CTD, QST, and PS steel rein-
μA/cm2)

forcement measured until the 33rd month. After 2


–1E–6 Observed LPR curve months of exposure, corrosion potential (Ecorr) values
icorr (μ

were more negative than −276 mVSCE (equivalent to


–2E–6 −350 mVCu/CuSO4 electrode) and exhibited a significant
B
icorr = B/Rp = reduction in OCP when compared to initial readings.
(ΔE/Δi)E→Ecorr
This indicates that the specimens are possibly
–3E–6
–0.17 –0.16 –0.15 –0.14 experiencing “active” corrosion. Also, all of the steels
exhibited similar OCP values. Figure 6 shows the av-
Applied Potential vs. SCE, E (V)
erage icorr of the different steels exposed to chloride
FIGURE 4. A typical LPR curve. environment. After 5 months of exposure, the icorr of
steel specimens started showing huge scatter in the
measured icorr. This phenomenon is a result of the
failure of the epoxy coating provided at the bottom
Corrosion measurements were made at the end of portion of the steel bar. Later, the specimens were
the alternate wetting period (say, once in a month). repaired as described in the Curing and Exposure
At first, the open-circuit potential (OCP) of the steel Conditions section. The corrosion testing was resumed
specimen was measured. Immediately after measuring from the 18th month onward until 33 months. At the
the OCP, the LPR test was conducted with a scan end of 33 months of exposure, corrosion stains were
range of 15 mV to −15 mV with respect to the measured visible on the surface of test specimens. However,
OCP and at a scan rate of 0.1667 mV/s. The mea- they did not exhibit cracking—even with severe
sured corrosion current density (i) was plotted with corrosion. The probable reasoning could be as fol-
respect to the applied potential (E) to generate the LPR lows. The overall/effective permeability of concrete
curve (see Figure 4 for a typical LPR curve). The icorr was could be less than that of mortar with similar paste
calculated as follows. quality, because of the presence of impermeable coarse

1124 CORROSION—SEPTEMBER 2017


CORROSION SCIENCE SECTION

0
CTD
(–276 mVSCE)
Average OCP (mVSCE)
QST
–150 or PM

observed due to possible

Specimen were repaired


failure of epoxy coating
(–350 mVCSE) PS
–300

Huge scatter was

during this time


–450

–600

0 3 6 9 12 15 18 21 24 27 33
Exposure Period After 28 d of Curing (month)
FIGURE 5. Average corrosion potential of PM, CTD, QST, and PS bars.

50
PM QST Wet data used for analysis
PS
μA/cm2)

CTD
40

Specimens were repaired


observed due to possible Dry data
failure of epoxy coating used for
30
Average icorr (μ

analysis
Large scatter was

20 during this period

10

0 3 6 9 12 15 18 21 24 27 33
Exposure Period After 28 d of Curing (month)
FIGURE 6. Average corrosion current density of PM, CTD, QST, and PS bars.

aggregates occupying about 70% of volume. In the 6 μA/cm2 and COV of 0.77. The results showed
case of test specimens, the corrosion products could higher icorr,wet values when compared to the value
easily permeate through the relatively more perme- reported in literature. However, the average icorr in the
able 12 mm thick mortar cover without building up real structure would be different from the instanta-
expansive pressure and cracking. Although the neous corrosion rate measured in the severe labo-
pressure buildup and eventual cracking mechanisms ratory conditions. This is taken into consideration
(in the bulk cover material) are different in the steel- during the estimation of tp later in this paper (see
mortar and steel-concrete systems, the corrosion rate Parametric Studies and Probability Density Function
(an interface property) from steel-mortar systems can of tp section)
be used for estimating the corrosion propagation time in
steel-concrete systems. icorr,dry Measurements
Figure 7(b) shows the dot plot of the measured
icorr,wet Measurements icorr,dry of PM, CTD, QST, and PS steel reinforcement. The
Figure 7(a) shows the dot plot of the measured average icorr,dry of PM steel reinforcement is about
icorr,wet of PM, CTD, QST, and PS steel reinforcement 5.3 μA/cm2 with a COV of 0.63. The icorr,dry data obtained
measured at the end of each wet period during cyclic for CTD steel reinforcement exhibited huge scatter
wet-dry exposure from the 19th month to the 24th with a mean of 7 μA/cm2 and COV of 0.43. The icorr,dry
month. The average icorr,wet of PM steel reinforcement data obtained for QST steel reinforcement exhibited a
is about 19 μA/cm2 with coefficient of variation (COV) of mean value of 8.6 μA/cm2 and COV of 0.74. Similarly,
0.44. The icorr,wet data obtained for CTD steel rein- the PS steel reinforcement showed the average icorr,dry
forcement exhibited huge scatter with a mean of of 2.5 μA/cm2 with COV of 0.7. In short, the icorr,wet was
27 μA/cm2 and COV of 0.44. The icorr,wet data ∼2.5 times higher than the average of icorr,dry for QST
obtained for QST steel reinforcement exhibited a mean and PS steel reinforcement. Similarly, the average icorr,wet
value of 24 μA/cm2 and COV of 0.38. Similarly, the PS was ∼3 and 4 times higher than icorr,dry for PM and
steel reinforcement showed the average icorr,wet of CTD steel reinforcement, respectively.

CORROSION—Vol. 73, No. 9 1125


CORROSION SCIENCE SECTION

(a) From 19 month to 24 month (b) Only during 27th month and 33rd month
Average Corrosion Current Density, icorr,wet

80

Average Corrosion Current Density, icorr,dry


μ = 19 μ = 29 μ = 24 μ = 06
80
σ = 8.12 σ = 11.7 σ=9 σ = 4.6
70 COV = 0.44 COV = 0.45 COV = 0.38 COV = 0.77 70

60 60

50 50
μA/cm2)

(μA/cm2)
40 40

30 30

20 20

10 10

0 0
PM CTD QST PS PM CTD QST PS
FIGURE 7. Corrosion rates of various steels.

The CTD steel reinforcement experienced higher Parametric Studies and Probability Density Function
average corrosion rates than QST steel reinforcement. of tp section.
This may be because the CTD steel reinforcement
is strain-hardened or cold-twisted during the Statistical Distributions of Corrosion Rate of
manufacturing process to increase the yield strength. Different Steels
This process can lead to residual stresses and surface For simulation purpose, icorr should be treated as
defects (at the microstructure level), which can lead to a positive real number. Hence, choosing a normal dis-
corrosion when exposed to aggressive environments. tribution for the icorr is mathematically incorrect. This
The PM and PS steel reinforcement have smooth is because the random data generated using a normal
surfaces (i.e., without any ribs), and no residual stresses distribution might have negative numbers and can
at the surface. Hence, they show less icorr when cause mathematical difficulties during simulation
compared to other steels. The difference in chemical studies.26 Also, Shapiro-Wilkinson normality tests on
composition may be another reason for the low cor- the icorr,wet and icorr,dry data sets for PM, CTD, QST, and
rosion rate. PS steel reinforcement concluded that the data sets
do not follow a normal distribution. To find appropriate
Average Annual Corrosion Rate in the Field statistical distributions, the software package Easy-
By considering the seasonal effects, icorr,wet, and Fit†,22 was used. Based on the Kolmogorov-Smirnov
icorr,dry, the weighted average of annual corrosion rate (K-S) goodness of fit test (see Table 5), the data sets
(icorr,annual) is calculated as given in Equation (6). The tp were ranked with different statistical distributions that
was estimated based on the icorr,annual, which may are commonly used (e.g., Gaussian, Weibull, Gamma,
better represent the corrosion propagation mecha- Normal, and Lognormal) The measured icorr,wet data for
nism that occurs in field conditions. Thus, the icorr,annual PM, CTD, QST, and PS steel reinforcement fit well
is used for the case study presented later in the with Weibull, Lognormal, Gamma, and Weibull 3P

TABLE 5
Goodness of Fit for icorr of PM, CTD, QST, and PS Steel Reinforcement(A)
icorr,wet icorr,dry
PM CTD QST PS PM CTD QST PS

Normal 4 7 7 7 6 2 7 1
Lognormal 7 1 5 6 5 6 5 7
Lognormal 3P 2 3 2 5 1 3 3 2
Weibull 1 6 4 3 3 7 4 3
Weibull 3P 3 5 6 1 4 1 2 4
Gamma 5 2 1 2 2 5 6 5
Gamma 3P 6 4 3 4 7 4 1 6
(A)
Wet data measurements from the 19th through 24th months. Dry data measurements from the 27th and 33rd month.

1126 CORROSION—SEPTEMBER 2017


CORROSION SCIENCE SECTION

(a) icorr,wet (b) icorr,dry


0.4 0.25
PM: icorr,wet ~ WB(σ, μ) PM: icorr,dry ~ LN3P(σ, μ, γ)
0.3 ~ WB(2.5, 20.7) μA/cm2 0.20 ~ LN3P(0.4, 2.1, –3.1) μA/cm2
0.15
f(icorr)

f(icorr)
0.2
0.10
0.1 0.05
0.0 0.00

0.4 0.25
CTD: icorr,wet ~ LN(σ, μ) CTD: icorr,dry ~ WB3P(σ, μ, γ)
~ LN(0.45, 3.2) μA/cm2 0.20
0.3 ~ WB3P(4.6, 13.3, –5.0) μA/cm2
0.15
f(icorr)

f(icorr)
0.2
0.10
0.1
0.05

0.0 0.00
0.4 0.25
QST: icorr,wet ~ GM(σ, μ) QST: icorr,dry ~ GM3P(σ, μ, γ)
0.20
0.3 ~ GM(6.8, 3.5) μA/cm2 ~ GM3P(1.2, 6.1, 1.1) μA/cm2
f(icorr) 0.15
f(icorr)

0.2 0.10
0.05
0.1
0.00
0.0
0.4 0.25
PS: icorr,wet ~ WB3P(σ, μ, γ) PS: icorr,dry ~ N(σ, μ, γ)
0.3 ~ WB3P(1.3, 6.5, –0.02) μA/cm2 0.20
~ N(1.9, 2.6, 0) μA/cm2
0.15
f(icorr)
f(icorr)

0.2
0.10
0.1 0.05

0.0 0.00
0 10 20 30 40 50 60 0 5 10 15 20 25
μA/cm2)
Corrosion Current Density (μ Corrosion Current Density (μA/cm2)
FIGURE 8. Distributions for icorr,wet and icorr,dry of various steel reinforcement.

TABLE 6 TABLE 7
Summary of Distributions Based on the Corrosion Rate of Summary of Distributions Based on the Corrosion Rate
Different Steel Reinforcement Exposed from 19 to 24 Months of Different Steel Reinforcement Measure at 27th
Parameter and 33rd Month
Steel Type Distribution (D) ∼D (σ, μ, γ) in μA/cm2 Parameter ∼D (σ, μ, γ) in
Steel Type Distribution (D) μA/cm2
PM Weibull ∼WB (2.5, 20.7, 0)
CTD Lognormal ∼LN (0.45, 3.2, 0) PM Lognormal 3P ∼LN3P (0.4, 2.1, −3.1)
QST Gamma ∼GM (6.8, 3.5, 0) CTD Weibull 3P ∼WB3P (4.6, 13.3, −5)
PS Weibull 3P ∼WB3P (1.3, 6.5, −0.02) QST Gamma 3P ∼GM3P (1.2, 6.1, 1.1)
PS Normal ∼N (1.9, 2.6, 0)

distributions, respectively. Similarly, icorr,dry data for


PM, CTD, QST, and PS steel reinforcement fit well with QST, and PS steel reinforcement. Tables 6 and 7 show
Lognormal 3P, Weibull 3P, Gamma, and Normal the statistical parameters for icorr,wet and icorr,dry arrived
distributions, respectively. for each steel type. A significant difference is observed
Figures 8(a) and (b) show the histograms and the between the icorr,wet and icorr,dry. The variation in the type
PDFs for icorr,wet and icorr,dry, respectively, of PM, CTD, of distribution and the change in the statistical

CORROSION—Vol. 73, No. 9 1127


CORROSION SCIENCE SECTION

TABLE 8 compressive strength (fcu) as the major influencing


Parameters Considered for Estimating ti Using parameters to estimate tp.5 In this analysis, the sta-
Wang and Zhao5 tistical distributions of icorr,annual for different steel was
Parameters Unit Value used, which was calculated from icorr,wet and icorr,dry
using Equation (4). The input parameters required for
Cover depth (Cv) mm 50
Wang and Zhao5 model are listed in Table 8. The tp for
Compressive strength MPa 30
of concrete (fcu) concrete systems with different steel reinforcement
Initial steel diameter (D) mm 16 for PM, CTD, was estimated using the model by Wang and Zhao.5
QST; 5.2 for PS A typical south Indian climate, in which 1 y can be
Equivalent weight of steel (W) g 27.92 divided into 3 month of wet season and 9 month of dry
Faraday’s constant (F) Coulombs 96,500
Density of steel (ρst) gm/cm3 7.85 season is considered for this parametric study.
Crack expansion coefficient 3.02 Figure 9 shows the PDF of tp obtained for the
of concrete (γ) systems with PM, CTD, QST, and PS steel reinforce-
ment. Note that these PDFs are skewed to the right.
For skewed distributions, the median is a better statistic
than the mean or average and the vertical lines within
0.5 the PDF curves indicate the median values, which are
Assumptions
Probability Density Function, f(tp)

Cover depth = 50 mm herein denoted as M(tp). The model by Wang and


0.4 Comp. strength of concrete = 30 MPa Zhao5 estimates that the M(tp) for concrete structures
PM with PM, CTD, QST, and PS steel reinforcement are
CTD 4.5, 2.4, 2.7, and 8.5 y, respectively.
0.3
QST
PS
M(tp)
Probabilistic Estimation of tp for a Particular
0.2
Reduction in Cross-Sectional Area (tp,Δ%)
In reinforced concrete structures, when the loss
0.1 in the cross-sectional area of steel reinforcement
exceeds ≈10% of the nominal cross-sectional area, the
0.0 structure may reach an unsafe level and major repair/
0 2 4 6 8 10 12 14 replacement of steel is needed. That is, 10% loss in
Time Required for Cracking After Corrosion Initiation (y) cross-sectional area is approximately equal to 10%
FIGURE 9. Estimated crack initiation period based on icorr,annual. reduction in tensile strength of steel rebars. When
such a state is reached, repair/rehabilitation/
retrofitting work is recommended because of the
limited safety margins. Thus, the reduction in tp with
parameters clearly shows that the use of same corrosion the corresponding percent reduction in the cross-
rate and considering a normal distribution for all of sectional area (Δ%) of the rebar is studied and repre-
the steel types will lead to an erroneous estimation of tp. sented as tp,Δ%. The study was conducted for Δ% of 5,
10, and 15% and the PDF for the four steel were
Parametric Studies and Probability Density developed.
Function of tp Once the crack is initiated, the rate of corrosion
Probabilistic Estimation of tp to Initiate Crack in Cover propagation may vary significantly, as the availability of
Concrete — As mentioned earlier in Table 1, Wang and moisture and oxygen is expected to be high. However, in
Zhao5 considered the icorr, cover depth (Cv), and this study, the tp,5%, tp,10%, and tp,15% were estimated

Median
25th percentile
75th percentile

0.2 tp,1
5%
f(tp)

0.1 15
tp,1
0%
0.0 )
tp,5 10
gth (%
10 %
t ren
Corrosio 20 in S
n Propag 30 ion
ation Peri 5 d uct
o d (tp in y
)
40 Re

FIGURE 10. tp,5%, tp,10%, and tp,15% loss in PM steel rebar with reference to exposure period.

1128 CORROSION—SEPTEMBER 2017


CORROSION SCIENCE SECTION

25th percentile
Median
75th percentile
0.4
tp,1
0.3 5%
f(tp)
0.2
15
0.1 tp,1
0%
0.0 )
10 h (%
2
4 tp,5
r e ngt
6 %
St
Corrosio
n Propag
8
10 tio n in
12
ation Peri 14 5 duc
od (t in
p y) Re

FIGURE 11. tp,5%, tp,10%, and tp,15% loss in CTD steel rebar with reference to exposure period.

25th percentile
Median

0.3 tp,1 75th percentile


5%
f(tp)

0.2
15
0.1
tp,1
0%
0.0 %)
10 th (
2
4 tp,5 t r eng
6 % S
Corrosio
n Propag
8
10 tio n in
ation Peri 12
14 5 duc
od (t in
p y) Re

FIGURE 12. tp,5%, tp,10%, and tp,15% loss in QST steel rebar with reference to exposure period.

25th percentile
Median
0.1 tp,1 75th percentile
5%
f(tp)

15
tp,1
0%
0.0 )
%
tp,5 10 th (
10 %
t r eng
20 S
Corrosio
n Propag 30
tio n in
ation Peri 40 5 duc
od (t in
p y)
50 Re

FIGURE 13. tp,5%, tp,10%, and tp,15% loss in PS steel rebar with reference to exposure period.

using Equation (4)6 by assuming a linear corrosion Figure 10 shows the probability of M(tp,5%),
propagation mechanism and constant icorr,annual deter- M(tp,10%), and M(tp,15%) for PM steel reinforcement after
mined from icorr,wet and icorr,dry using Equation (4). the corrosion initiation. Based on the probabilistic
Figures 10 through 13 shows the probability of M(tp,5%), estimation, the M(tp,5%), M(tp,10%), and M(tp,15%) for a
M(tp,10%), and M(tp,15%) for different steel reinforcement concrete system with PM steel is about 4.5, 9, and
after the corrosion initiation. In the PDFs, the vertical solid 15 y, respectively. Figure 11 shows the probability of
line from the abscissa denotes the median (50th per- M(tp,5%), M(tp,10%), and M(tp,15%) for CTD steel rein-
centile), which is M(tp) and the dotted vertical lines along forcement after the corrosion initiation. The concrete
the left and right side of the solid line denotes the 25th system with CTD steel reinforcement may have
percentile and 75th percentile, respectively, of the esti- M(tp,5%), M(tp,10%), and M(tp,15%) as 2.5, 5, and 7.5 y,
mated corrosion propagation period. respectively. The concrete system with QST steel may

CORROSION—Vol. 73, No. 9 1129


CORROSION SCIENCE SECTION

have M(tp,5%), M(tp,10%), and M(tp,15%) of 3, 5.5, and 9 y, Sengupta, Prof. Surendra P. Shah, Ms. Payal Firodiya,
respectively, as shown in Figure 12. As shown in staff and fellow students in the Building Technology
Figure 13, the M(tp,5%), M(tp,10%), and M(tp,15%) in the and Construction Management Division, Department
concrete system with PS steel reinforcement is of Civil Engineering, IIT Madras for their support and
around 8.5, 17, and 26 y, respectively. timely help.
Therefore, instead of assuming tp as 6 y, it is
recommended that the probabilistic distributions for
icorr,wet and icorr,dry presented in this paper and a REFERENCES
suitable model may be used to estimate tp for structures
1. Life-365™ v2.2.1, Life-365 Consortium III, 2014.
with different steel reinforcement. 2. D. Chen, S. Mahadevan, Cem. Concr. Compos. 30 (2008): p. 227-
238.
3. D. Cusson, Z. Lounis, L. Daigle, “Improving Performance Prediction
CONCLUSIONS of Corroding Concrete Bridges with Field Monitoring,” Proceedings
of the 6th International Conference on Concrete Under Severe
Based on the experimental results and the cor- Conditions Environment and Loading, held June 7-9, 2010
(Merida, Mexico: CRC Press, 2010).
rosion propagation models discussed in this paper, the 4. C. Suwito, Y. Xi, Struct. Infrastruct. Eng. 4 (2008): p. 177-
following conclusions are drawn. 192.
v When embedded in similar cementitious system to 5. X.M. Wang, H.Y. Zhao, “The Residual Service Life Prediction of RC
Structures,” Proceedings of the 6th International Conference on
that used in the present experiment and when subjected Durability of Building Materials and Components, ed. S. Nagataki
to a wet cycle exposure to chloride environment, the (Omiya, Japan: DBMC, 1993).
corrosion rate, icorr,wet, of PM, CTD, QST, and PS steel 6. Z.P. Bazant, J. Structural Division 105 (1979): p. 1137-1153.
7. S. Morinaga, “Prediction of Service Lives of Reinforced Concrete
reinforcement can be statistically expressed as follows: Buildings Based on the Corrosion Rate of Reinforcing Steel,”
I. PM: ∼Weibull (2.5, 20.7, 0) μA/cm2. Proceedings of the Fifth International Conference on Durability of
II. CTD: ∼Lognormal (0.45, 3.2, 0) μA/cm2. Building Materials and Components (Brighton, United Kingdom:
Taylor & Francis, 1990).
III. QST: ∼Gamma (6.8, 3.5, 0) μA/cm2. 8. Y. Liu, R. Weyers, ACI Mater. J. 95, 6 (1998): p. 675-681.
IV. PS: ∼Weibull 3P (1.3, 6.5, −0.02) μA/cm2. 9. R.F. Stratfull, Corrosion 13 (1957): p. 43-48.
v When embedded in similar cementitious system to 10. K.C. Clear, “Time to Corrosion of Reinforcing Steel in Concrete
Slabs,” FHA, interim report FHWA-RD-76-70, 1976.
that used in the present experiment and when subjected 11. C. Andrade, C. Alonso, J.A. González, “Approach to the Calculation
to a dry exposure, the corrosion rate, icorr,dry, of PM, of the Residual Service Life in Corroding Concrete Reinforcements
Based on Corrosion Intensity Values,” Proceedings of the
CTD, QST, and PS steel reinforcement can be statisti-
9th European Congress on Corrosion 89 (Utrech, Netherlands:
cally expressed as follows: EFC, 1989).
I. PM: ∼Lognormal (0.4, 2.1, −3.1) μA/cm2. 12. “An Approach Document for Assessment of Remaining Life of
Concrete Bridges,” IRC SP: 60-2002 (New Delhi, India: Indian
II. CTD: ∼Weibull 3P (0.46, 13.3, −5) μA/cm2. Roads Congress, 2002).
III. QST: ∼Gamma 3P (1.2, 6.1, 1.1) μA/cm2. 13. D.L. Spellman, R.F. Stratfull, “Chlorides and Bridge Deck Deteri-
IV. PS: ∼Normal (1.9, 2.6, 0) μA/cm2. oration,” California State Division of Highways, Materials and
Research Department, Committee on Effect of Ice Control,
v Using the statistical distributions mentioned 49th Annual Meeting, 1968.
above and the Wang and Zhao5 model, the median time 14. K.C. Clear, Transportation Research Record 1211 (1992):
required to crack the cover concrete M(tp) is about p. 28-38.
15. K. Hladky, D.G. John, J.L. Dawson, “Development in Rate of
1.5 times higher in the case of PM and PS steel rein- Corrosion Measurements for Reinforced Concrete Structures,”
forcement than that in the case of CTD and QST steel CORROSION 1989, paper no. 169 (Houston, TX: NACE Interna-
reinforcement. tional, 1989).
16. M. Ismail, M. Ohtsu, Constr. Build. Mater. 20 (2006):
v The median time required for 10% reduction in p. 458-469.
tensile strength is around 1.2 times higher in PM and PS 17. C.M. Hansson, B. Sorensen, “The Threshold Concentration of
steel reinforcement when compared to CTD and QST Chloride in Concrete for the Initiation of Reinforcement Corrosion,”
in Corrosion Rates of Steel in Concrete, eds. N.S. Berke, V. Chaker,
steel reinforcement. D. Whiting, ASTM STP 1065 (Philadelphia, PA: American Society for
The content of this paper can help the engineers to Testing and Materials, 1990), p. 3-16.
18. N.S. Berke, D.F. Shen, K.M. Sundberg, “Comparison of the
schedule and strategize suitable repair activities to
Polarization Resistance Technique to the Macrocell Corrosion
avoid severe damage and possible structural failures. Technique,” in Corrosion Rates of Steel in Concrete, eds.
N.S. Berke, V. Chaker, D. Whiting, ASTM STP 1065
(Philadelphia, PA: American Society for Testing and Materials,
ACKNOWLEDGMENTS 1990), p. 38-51.
19. B. Pradhan, B. Bhattacharjee, Constr. Build. Mater. 23 (2009):
p. 2346-2356.
The authors acknowledge the financial assistance 20. P. Firodiya, A. Sengupta, R.G. Pillai, J. Perform. Constr. Facil. 29
from the New Faculty Seed Grand received from (2015): ID 579.
21. J. Karuppanasamy, R.G. Pillai, “Probabilistic Estimation of
Indian Institute of Technology Madras and Fast Track Corrosion Propagation Period for Prestressed Concrete Structures
grant (Sanction No. SR/FTP/ETA-0119/2011) from Exposed to Chlorides,” 4th International Conference on Durability
Department of Science and Technology (DST), Gov- of Concrete Structures (ICDCS 2014), held July 24-26, 2014 (West
Lafayette, IN: Purdue University, 2014).
ernment of India. The authors acknowledge Prof. 22. T.A. Soylev, M.G. Richardson, Constr. Build. Mater. 22 (2008):
Ravindra Gettu, Prof. Manu Santhanam, Prof. Amlan K. p. 609-622.

1130 CORROSION—SEPTEMBER 2017


CORROSION SCIENCE SECTION

23. ASTM C204-2011, “Standard Test Methods for Fineness of 25. ASTM G1-2011, “Standard Practice for Preparing, Cleaning, and
Hydraulic Cement by Air-Permeability Apparatus” (West Evaluating Corrosion Test Specimens” (West Conshohocken, PA:
Conshohocken, PA: American Society of Testing and Materials, American Society of Testing and Materials, 2011).
2011). 26. R.J. Detwiler, D.A. Whiting, E.S. Lagergen, ACI Mater. J. 96 (1999):
24. IS:383-2002, “Specification for Coarse and Fine Aggregates from p. 670-675.
Natural Sources for Concrete” (New Delhi, India: Bureau of Indian 27. EasyFit©, MathWave Technologies, 2014.
Standards, 2002).

CORROSION—Vol. 73, No. 9 1131


View publication stats

You might also like