PART-1: PREAMBLE
Manual holders shall update their copies upon receipt of revisions. Revised pages shall be
inserted in the Manual and record revision table given below shall be completed. Removed
pages must be discarded immediately to avoid any confusion.
Insertion
Edition Revision Issue Date
Date By
0 AUG-2009
1
1 JAN-2011
2 0 DEC-2011
1 MAR-2012
2 AUG-2012
3 MAR-2013
PART – 1: PREAMBLE
Chapter Sub-Chapter Page No. Edition Revision Issue Date
1-0 1 of 2 2 1 March-2012
2 of 2 2 1 March-2012
1-1 1 of 2 2 1 March-2012
2 of 2 2 1 March-2012
1-2 1 of 2 2 3 March-2013
2 of 2 2 3 March-2013
1-3 1 of 4 2 3 March-2013
2 of 4 2 3 March-2013
3 of 4 2 3 March-2013
4 of 4 2 3 March-2013
1-4 1 of 2 2 0 December-2011
2 of 2 2 0 December-2011
1-5 1 of 2 2 3 March-2013
2 of 2 2 3 March-2013
2-0 1 of 2 2 0 December-2011
2 of 2 2 0 December-2011
2-1 1 of 6 2 3 March-2013
2 of 6 2 3 March-2013
3 of 6 2 3 March-2013
4 of 6 2 3 March-2013
5 of 6 2 3 March-2013
6 of 6 2 3 March-2013
2-2 1 of 2 2 0 December-2011
2 of 2 2 0 December-2011
2-3 1 of 2 2 0 December-2011
2 of 2 2 0 December-2011
2-4 1 of 2 2 3 March-2013
2 of 2 2 3 March-2013
3-0 1 of 2 2 0 December-2011
2 of 2 2 0 December-2011
3-1 1 of 4 2 3 March-2013
2 of 4 2 3 March-2013
3 of 4 2 3 March-2013
4 of 4 2 3 March-2013
3-2 1 of 2 2 0 December-2011
2 of 2 2 0 December-2011
3-2-1 1 of 4 2 3 March-2013
2 of 4 2 3 March-2013
3 of 4 2 3 March-2013
4 of 4 2 3 March-2013
3-2-2 1 of 2 2 3 March-2013
2 of 2 2 3 March-2013
3-2-3 1 of 4 2 3 March-2013
2 of 4 2 3 March-2013
3 of 4 2 3 March-2013
4 of 4 2 3 March-2013
3-2-4 1 of 2 2 3 March-2013
2 of 2 2 3 March-2013
3-2-5 1 of 2 2 0 December-2011
2 of 2 2 0 December-2011
3-2-6 1 of 4 2 0 December-2011
2 of 4 2 0 December-2011
3 of 4 2 0 December-2011
4 of 4 2 0 December-2011
3-2-7 1 of 4 2 0 December-2011
2 of 4 2 0 December-2011
3 of 4 2 0 December-2011
4 of 4 2 0 December-2011
3-2-8 1 of 4 2 0 December-2011
2 of 4 2 0 December-2011
3 of 4 2 0 December-2011
4 of 4 2 0 December-2011
3-2-9 1 of 2 2 0 December-2011
2 of 2 2 0 December-2011
3-2-10 1 of 2 2 0 December-2011
2 of 2 2 0 December-2011
3-2-11 1 of 2 2 0 December-2011
2 of 2 2 0 December-2011
3-2-12 1 of 2 2 0 December-2011
2 of 2 2 0 December-2011
4-0 1 of 2 2 0 December-2011
2 of 2 2 0 December-2011
4-1 1 of 28 2 3 March-2013
2 of 28 2 3 March-2013
3 of 28 2 3 March-2013
4 of 28 2 3 March-2013
5 of 28 2 3 March-2013
6 of 28 2 3 March-2013
7 of 28 2 3 March-2013
8 of 28 2 3 March-2013
9 of 28 2 3 March-2013
10 of 28 2 3 March-2013
11 of 28 2 3 March-2013
12 of 28 2 3 March-2013
13 of 28 2 3 March-2013
14 of 28 2 3 March-2013
15 of 28 2 3 March-2013
16 of 28 2 3 March-2013
17 of 28 2 3 March-2013
18 of 28 2 3 March-2013
19 of 28 2 3 March-2013
20 of 28 2 3 March-2013
21 of 28 2 3 March-2013
22 of 28 2 3 March-2013
23 of 28 2 3 March-2013
24 of 28 2 3 March-2013
25 of 28 2 3 March-2013
26 of 28 2 3 March-2013
27 of 28 2 3 March-2013
28 of 28 2 3 March-2013
4-2 1 of 4 2 0 December-2011
2 of 4 2 0 December-2011
3 of 4 2 0 December-2011
4 of 4 2 0 December-2011
1-4.1 INTRODUCTION
1-4.2 STRUCTURE
Engineering Procedures Manual has been structured, for ease of use, as follows:
PART-1 Preamble
PART-2 Divisional Organisation, Facilities & Workscope
PART-3 Functions, Duties & Responsibilities
PART-4 Processes & Documents
a) External Distribution
b) Internal Distribution
The MOC Division will ensure that in respect of all work performed under the terms of this
Organizational Approval, adequate human resources, appropriate facilities and proper
equipment are utilized and the approved procedures are adopted.
Office Attendant
Store Attendant
Store Attendant
Aircraft Engineer
I/c Engineering Budget I/c Catalogue Group I/c Avionics Group I/c Boeing Group
(Manager) (Sr Planning Officer) (Sr Planning Officer) (Sr Planning Officer)
Assistant Manager Sr. Planning Officer Sr. Planning Officer Planning Officer
Sr. Planning Officer Officer Engineering Planning Officer Material Plng Suprv
Admin Officer Material Plng Suprv Material Plng Suprv Material Plng Suprv
Material Planner Material Plng Suprv Material Plng Suprv Material Plng Suprv
Material Planner Material Planner Material Planner Material Planner
Office Attendant Material Planner Engineering Assistant Engineering Assistant
I/c CMP/PNE Group I/c Engine Group I/c Commercial Group I/c Airbus Group
(Sr Planning Officer) (Assistant Manager) (Sr Planning Officer) (Sr Planning Officer)
Technician
Office Attendant
Engineering
Supervisor
Engineering
Assistant
Office Attendant
Material Controller
PAY GROUPS
No. Designation
SPL X IX VI/VII/VIII VIII VII VI V IV III I/II/III LOC TOTAL
1 Chief Engineer 1 1
2 Deputy Chief Engineer 4 4
3 Aircraft Engineer 3 3
4 Manager 2 2
5 Assistant Manager 8 8
6 Officer Engineering 4 4
7 Sr. Planning Officer 11 11
8 Planning Officer 16 16
9 Admin Officer 3 3
Computer Operator
10 System Coordinator 1 1
11 Trainee Engineer 1 1
12 Senior Technician 1 1
13 Engineering Supervisor 10 10
14 Material Planning Supervisor 10 10
15 Technician 3 3
16 Engineering Assistant 11 11
17 Material Controller 2 2
18 Material Planner 13 13
19 Engineering Helper 6 6
20 Office Attendant 4 4
21 Driver 2 2
GROUP WISE TOTAL 1 4 7 2 8 14 18 22 29 12 116
2-3 FACILITIES
8
Power Plant
Overhaul
9
7 Fokker
6 Hanger
Wide Body
Hanger
4
LM-II
3
Hanger
2
12
11
13
LM-I Hanger
LEGEND
NUMBER AREA
1 Chief Engineer (MOC) Office
2 Chief Engineer (MOC) Secretariat
3 DCE (Repair Abroad) Office
4 Invoice Cell
5 DCE (Rotable Planning) Office
6 DCE (S&CP) Office
7 Material Management (CMP / PNE Provisioning Group)
8 Material Management (Engine Provisioning Group)
9 Material Management Secretariat
10 Material Management (Radio Overhaul Shop Group)
11 Material Management (Instrument Overhaul Shop Group)
12 Material Management (Electrical Overhaul Shop Group)
13 Parts Control Section
U
2-4 WORKSCOPE
2-4.1 GENERAL
MOC Division shall act as coordinator for all Divisions to ensure effectiveness of
major production planning activities in the Organization.
PREMESIS WORKSCOPE
MOC Ensure that all personnel and Management of the Division are fully
Secretariate aware of Organizational Procedures.
Maintain Database of applicable Tooling / Test Equipment required by
Maintenance.
Conduct Pre-Dock Meetings for review prior to the aircraft Base Check.
Coordinate with Divisional Heads for cost analysis to finalize proposal
on the annual budget.
Conduct regular meetings to ensure effective coordination of Sectional
activities.
Repair Explore new suitable sources for buying and selling of Repair and
Abroad Engineering Services.
Conduct Engineering & Maintenance Commettee (EMC) Meetings
under Chaired by Director (E&M).
Initial Provisioning
(Provisioining of LRUs for Aircraft newly inducted in PIA Fleet)
Provisioning against SRC
(Provisioining of LRUs against float scarapped at PIA Engineering Overhaul Shop / Vendor facility)
Enhancement in spare float
(Provisioining of LRUs against enhancement in spare float)
Provisioning gainst AOG
(Provisioining of LRUs against AOG demand by Maintenance / Aircraft held-up at Outstation)
NIL Expeditors / Flight Pack shortages intimation to Overhaul Shops / Repair
Abroad to replenish stock.
Establish Initial Provisioning Levels for spares associated with the purchase of new
equipment and ensure that purchase orders are placed and spares have arrived before the
new equipment or new aircraft does.
Coordinate with the Procurement & Logistic Department for receipt of spares.
Maintain and up-to-date record of components held-up awaiting spares and expedite
deliveries from Suppliers in co-operation with the Technical Purchase Section of the
Procurement & Logistic Department.
Prepare budgets for aircraft spares and once approved, control expenditures against the
budget during the course of the year.
Ensure that adequate overall control is maintained over the components which are sent
abroad to the repair agencies for repair, modification, testing, overhaul etc.
Ensure the proper framing and administration of Engineering Contracts, including warranty
and guarantee agreements, in the most beneficial manner for the Company for all sub-
contract work done by PIA on aviation equipment for customers within and outside
Pakistan.
Monitors the Market Research to explore new suitable sources for buying and selling of
Repair and Engineering Services.
Ensure on time processing of Invoices which are then submitted to Finance (ENGG)
Section for making the timely payment.
Ensure the Repair Abroad personnel are in possession of correct skills, are given
appropriate training are up-to-date on the latest methods, procedures and requirements
and of sufficient strength to accomplish their work effectively.
Assist in development of procedure for new aircraft / equipment in PIA and handles new
projects as directed. Monitor the cost of projects against approved budgets and highlight
any deviation.
To forecast and schedule fleet maintenance checks specifying the location and duration of
fleet heavy maintenance with the available resources and to utilize maintenance capacity
for fulfillment of PIA and other third party maintenance requirements.
To monitor life of aircraft major components like engine, propeller and landing gear for their
necessary removal for overhaul, also prepare and issue bill of work for Base Maintenance.
To file and reimburse warranty cases for the SB accomplishment on PIA fleet.
Performance analysis of heavy maintenance and engine overhauling activities carried out
on PIA fleet.
Manage positioning / retrieval of HAJJ Inventory in liason with P&L, Repair Abroad and
Overhaul Shops.
Initial Provisioining of LRUs for new Aircraft inducted in PIA Fleet as per RSPL
recommendations and IATA Calculating formula through P&L.
Initiate Requisition to Purchase Orders against SRC / Spare Float Enhancement / AOG.
Remain abreast of developments in the field of inventory control techniques and theory for
possible appropriation based upon the feed back from the Maintenance Planning
Section/Development Engineering for forward Planning.
Maintain liaison with the Data Processing Department concerning the operation of
computer based inventory control systems.
Establish initial provisioning levels for spares associated with the purchase of new
equipment and ensure that purchase orders are placed and spares received before the
new equipment or new aircraft does.
Co-ordinate with the Stores & Purchasing Department for receipt of spares and the issue of
spares from stores to the floor or to the overhaul shops.
Identify & take Management’s decision against surplus inventory and co-ordinate with
Logistic Division for competitive disposal.
Assist Manager Financial Planning in budget preparation for Engineering and once
approved, control expenditures against the budget during the course of the year.
Ensure that adequate overall control is maintained over the components which are sent
abroad to the repair agencies for repair, modification, testing, overhaul etc.
Assist in development of procedure for aircraft / equipment in PIA and handle new projects
as directed. Monitor the cost of projects against approved budgets and highlight any
deviation.
Ensure EMC Meeting for approval of the cases as per laid down procedures and within
EMC financial limits.
Ensure data collection of special tools and equipment and enter in the data base.
Review demand, price and frequency of use of tools and equipments required by different
section.
Check for tools and equipments available in use in other section of Engineering and
Maintenance.
Purchase tools through P&L or borrow on loan basis depending on the requirement.
Search market and explore suitable sources for buying and selling aircraft parts and repair
services.
Plan all long term heavy maintenance of the fleet both those overhauls undertaken by the
department and those sub-contracted to other operators.
Convert the Corporate Plan into maintenance, aircraft overhaul and engine overhaul plan
which is then issued to concerned sections of the department.
Plan maintenance checks, prepare and issue the bill of work and maintain a record of
elapsed time for each check.
Work with other sections to find to reduce elapsed time for each type of maintenance
service and incorporate these improvements in the maintenance schedules.
Performance analysis of heavy maintenance and engine overhauling activities carried out
on PIA fleet.
Assist Dy. Chief Engineer in carrying out functions of spare parts ordering, parts control
day to day office activities.
Negotiate and finalize technical handling contracts at Out Stations for PIA Fleet. This
includes new stations opened by PIA or where current Technical Handling Agents give
Termination Notice.
Negotiate and finalize contracts for technical handling of foreign carriers operation
through Pakistan.
Submission of Biodata of Technical Handling Agents and their Engineers for fresh /
renewal of PCAA approval to PIA Quality Assurance.
Maintain records of Loan / Borrowed items for PIA Fleet and their earliest return.
To verify Billing of Technical Handling Services and Loan of Parts for PIA Fleet.
Maintain updated Technical Handling contact list and sent to all concerned through E-
mail.
Close co-ordination with DCE Material Management for the Development in the field of
inventory control techniques and theory for possible appropriation based upon the feed
back from the Maintenance Planning Section / PO O/H Division / O/H Shops Technical
Planning & Development Engineering for forward Planning.
Maintain liaison with the Data Processing Department concerning the operation of
computer based inventory control systems.
Establish initial provisioning levels for spares associated with the purchase of new
equipment and ensure that purchase orders are placed and spares received before the
new equipment or new aircraft does.
Co-ordinate with the Stores & Purchasing Department for receipt of spares and the issue of
spares from stores to the hangar floor or to the overhaul shops.
Identify surplus inventory and co-ordinate with the Logistics Division for competitive
disposal.
Assist Manager Financial Planning in budget preparation for Engineering and once
approved, control expenditures against the budget during the course of the year.
Ensure that the aircraft maintenance activity is supported by maximum availability of spare
parts and components through efficient material provisioning stock control and
development of inventory management policies, procedures and systems.
Maintain record of rotables / repairables component removed from aircraft, loaded to/from
Overhaul Shops and concerned stock room.
Upon receiving input from Flight Pack Section for flight pack requirement, the same is
highlighted to concern for necessary action.
All E-mail messages relating to rotable / repairable are properly taken care of and
auctioned.
To expedite AOG & Critical demands against aircraft requirements of maintenance for
Rotable / Repairable availability within PIA network and send Expeditor to concerned
Overhaul Shops / Repair Abroad.
The spares loaned to other Airlines at Karachi and Line Stations are returned to Karachi.
To obtain spares from other airlines and agencies on AOG during weekly-off / holidays.
Coordinate with Motor Transport Section for all Vehicles when sent for maintenance.
General cleanliness / maintenance of Parts Control area, specially during various audits.
There are four distinct areas in Material Management i.e. Airframe, Engine, O/H Shops and
Catalogue/Commercial, which are being looked after by their respective Assistant
Managers. Following are their duties & responsibilities:
Keep close co-ordination with Users & Purchasing Department and resolves all queries.
Maintain close co-ordination with all working Cells in existing Material Provisioning Section
specially with Catalogue Section.
Initiate the purchase of spare parts by placing indents on the Technical Purchasing section
of Logistic Division as re-order levels are reached or a requirement develops.
Co-ordinate with the Logistic Division for receipt of spares and with user for issue of spare.
Identify surplus inventory and co-ordinate with the Stores & Purchasing Department for
competitive disposal.
Prepare Engineering and control expenditure during the course of the year.
Ensure that the aircraft maintenance activity is supported by maximum availability of spare
parts and components through efficient material provisioning stock control and
development of inventory management policies, procedures and systems
First check the comp histrory of lru to meet the warranty or not.
After checking of warranty generate the repair order with “w” marked.
Track & monitor all evaluation notice issued by Development Engineering warranty
remedies are available in notices. We claim to manuafacturers for Lab / man hours
consumed in mod.
Assists in negotiation of component overhaul / repair work sub contracted to outside repair
agencies for which facilities do not exist in PIA.
Organize and administers all functions related to work sub contracted as per contractual
arrangement.
Certifies invoices for items repaired abroad and records expenses incurred.
Monitor maintenance of components status cards for each movement along with its
dispatch and receipt details
Works under the administrative and functional control of DCE (Repair Abroad) Component
Control.
Highlight the Base / Line Maintenance IOR / AOG demand in LMD (Line Maintenance
Demand) in PAMMIS.
Coordinate with Stores for ensuring dispatch of spares to outstations in case of aircraft
grounded due non-availability of spares.
Coordinate for removal of all pool / loan components borrowed at Line Stations on arrival of
aircraft at Karachi in Coordination with Maintenance.
Manage dispatch of components through Stores / Logistics to outside Repair Agencies and
maintain records as necessary.
Act as Provisioning Group Incharge, initial Spares Provisioning and subsequent material
planning of spares.
Ensure that abnormalities, such as, excessive issues, nils, rack life expiry, price variations,
delayed supplies, re-order levels, re-provisioning policy, etc., are highlighted promptly and
corrective actions taken.
To co-ordinate between user & P&L and also attends queries from consumers,
stockrooms, foreign purchase, etc., and takes prompt and proper action.
Expedite critical materials required by shop sections in coordination with the concerned
shop.
Take necessary action on spares for which components get held up in the shops or for
which aircraft is liable to be grounded and maintain up-to-date and complete records of the
hold-ups of his group.
Familiarize himself with the Operating and Technical Plans and the revisions thereto,
issued by the sections concerned and convert the same for planning purposes.
Review maintenance and overhaul spares, not initially stocked, well in advance before the
Overhaul is due on the aircraft, in the light of Overhaul's anticipated requirements and past
experience and take necessary provisioning action in time.
Meet any campaign programme requirements, takes necessary material planning action, if
required, well in advance. Also study and takes necessary action on Service Bulletins,
Modifications, Technical Orders, Technical Notices, Manufacturer's Revisions and
Bulletins, etc.
Primarily responsible to ensure that the estimates of future annual consumption are made
as accurately as possible.
Maintain close co-ordination with all other working cells in the existing Material Planning
Section, such as, the Catalogue Section, Central Document Control Section and Material
Planning Analysis Section etc.
Organize and administer all functions related to work sub contracted as per contractual
arrangements.
Works under the administrative and functional control of Assistant Manager (Component
Control).
To maintain daily attendance, yearly leave roster, leave record and to maintain daily diary
receipt/dispatch.
Responsible for clean and neat maintenance of all records pertaining to attendance, leave,
files and correspondence.
Record all Normal/Priority Purchase Orders on daily dispatch register for delivery to
Logistic Division.
Assist and provide all necessary information to Dy.Chief Engineer Material Management
respect of Personnel matters.
Maintain complete statement of all ACRs, Airport Entry Passes, delivered to Personnel
Department and individual employee of the section.
Coordinate for removal of all pool / loan components borrowed at Line Stations on arrival of
aircraft at Karachi in Coordination with Maintenance.
Locate spares on loan from other Airlines for grounded aircrafts at Karachi and outstations.
Assist Manager Rotable Planning in negotiation of contracts with International Agencies for
Technical Handling of PIA aircrafts.
Assist Manager Rotable Planning to update the contact list of technical handling agents
and intimate the updates to Line Stations.
Liason and communication for return of all spare parts removed at Line Stations to the
Base.
Highlight the Base / Line Maintenance IOR / AOG demand in LMD (Line Maintenance
Demand) in PAMMIS.
Prepare procurement cases of rotables against SRC / SFE for Management approval.
Ensure that abnormalities, such as, excessive issues, nils, rack life expiry, price variations,
delayed supplies, re-order levels, re-provisioning policy, etc., are highlighted promptly and
corrective actions taken.
Act as a liaison and also attend queries from consumers, stockrooms, foreign purchase,
etc., and takes prompt and proper action.
Expedite critical materials required by shop sections in coordination with the concerned
shop.
Take necessary action on spares for which components get held up in the shops or for
which aircraft is liable to be grounded and maintain up-to-date and complete records of the
hold-ups of his group.
Review Engineering spares, well in advance before the Block Overhaul or MBC is due on
the aircraft, in the light of Block Overhaul's / MBC's anticipated requirements and past
experience and takes necessary provisioning action in time.
Meet any campaign programme requirements; take necessary material planning action, if
required, well in advance.
Lodge Warranty/ Insurance claim with Manufacture/Insurance for defective / damage / lost
Spares & parts of the aircraft.
Reviews the claims before submission and correspondence with Manufacture / Insurance /
clarifying their quires.
Negotiates with the Manufacturers / Insurance Surveyor for pending claims. Coordinates
with overhaul shops for claims submission.
Insurance Work order(s) are opened immediately in case of damage to PIA Aircraft /
Engines / Components due to accident / incident / FOD.
To inform Manager Insurance in writing the initial accident / incident / FOD details giving the
claim number.
Aircraft Station of Accident.
Engine Type / ESN (in case of damage / FOD to engine)
Tracking & Monitor tech delay reports / incident report / CAA form 055 / Monthly Bird Strike
/ FOD and items Lost.
Review, work out any delay, and file claims on Insurance and quick settlement.
Recover the Repair Cost / Losses of Aircraft / Engine / Spares form Insurance / under
writers.
Settlement of Spares Claims for the items lost during transit in specified period.
Constant review of the renewal of our aircraft HULL & liabilities Insurance policy for the
period 2008-2009.
Assists in negotiation of component overhaul / repair work sub contracted to outside repair
agencies for which facilities do not exist in PIA.
Organize and administers all functions related to work sub contracted as per contractual
arrangement.
Monitor maintenance of components status cards for each movement along with its
dispatch and receipt details
Certifies invoices for items repaired abroad and records expenses incurred.
Works under the administrative and functional control of Assistant Manager (Component
Control).
First check the comp histrory of LRU to meet the warranty or not.
After checking of warranty generate the repair order with “w” marked.
Incase of denied the warranty by any vendor. We are checking the warranty throughly and
request to vendor for repair (FOC).
In case of liability accepted by vendor. We submit a alaims to vendor for foc replacment or
credit amountre-inbursement.
Track & monitor all evaluation notice issued by Dev. Engg warranty remedies are available
in notices. We claim to manuafacturers for Lab / man-hours consumed in mod.
Review of agreements from Boeing / ATR Vendor and sign the in-house repair
agreements. To repair the new aircraft components in PIA Overhaul Shops for realizing the
foreign exchange.
By save do on time of removed components from aircraft and dispatch to OEM for repair
under warranty to reduce the TAT in number of days.
Maintain close co-ordination with various shops and Sections. Determine reasons for non-
availability of spares in his area and takes remedial action as per procedure.
Attend all enquiries from stock rooms, foreign purchases and Shops.
Assist and provides all necessary information to Officer Material Planning / Sr. Material
Planner in respect of hold-up of spares.
Ensure proper and timely movement of all serviceable / unserviceable components to and
from Line / Base maintenance and Overhaul Shops.
Collect serviceable components from shops, prepare stock return vouchers and hand them
over to respective Stock Rooms.
Assist Sr. Planning Officer for removal of loan items from the aircraft and return as soon as
possible.
Receive Scrap Rejection Certificates (SRC) from various overhaul shops and pass it on to
concerned Planning Officer for their procurement process.
Prepare (Bill of work) list of Cardex Controlled items for the PIA fleet (B743, B742, B777,
B737, A310 & ATR) in co-ordination with Cardex Section / Technical Record Section /
WBHM Planning / LM-I & LM-II & all concerned shops. Major Checks 20 days before
grounding of Aircarft and 2 Months before grounding in smaller checks prepare.
Co-ordination daily basis and correspondence with concerned Bays, Shops and sections
for days work & review for task left over briefing with DCE (S&CP),
MIC Sheet from LM-I & LM-II / Cardex for Major checks & smaller checks and MIC Sheets
review on daily basis for concerned aircrafts.
Works under the administrative and functional control of DCE (Repair Abroad) (Component
Control).
Ensure proper and timely movement of all serviceable / unserviceable components to and
from Line / Base Maintenance and Overhaul Shops.
Collect serviceable components from Shops, prepare Stock Return Vouchers and
handover to respective Stock Rooms.
Proper and timely movement of all unserviceable / serviceable components to and from
respective Stock Rooms and Overhaul Shops.
Receive unserviceable items with work order tags / sheets and routes them to respective
Overhaul Shops.
Collect serviceable components from Shops, prepares Stock Return Vouchers and
handover to respective Stock Rooms.
Distribution, collection & delivery of all out going & incoming mails.
Keep him self familiar with the regulations as prescribed by Civil Aviation Authority and
follow their rules properly.
Submit daily report regarding serviceability and un-serviceability of the vehicles under him
to Sr. Planning Officer (Parts Control)
Maintenance
Parts Control
If found damaged
Unserviceable item(s) must be checked by Parts
Control personnel for any abnormality / damage.
Maintenance
Parts Control
Airlines are contacted for required component * * In case of Weekly Off / Holidays
/ Off Duty Hours, Parts Control
shall handle the loan issues
PCAA Approval
In the mean time PIA Quality Assurance and PCAA perform Audit of Handling
Agency Facilities. On satisfactory performance, permanent approval is
granted by PCAA.
Latest Aircraft Technical Literature’s CDs (IPC, AMM, AWM, ASM, TSM,
ACRT etc) and Transit Check Sheets are delivered to PIA Technical Handling
Agents at outstations as per Mailing List provided by Rotable Planning and in
the flight pack of all PIA Fleet by Technical Publication.
4-1.4 PROCEDURE FOR PROVIDING SPARE FOR AIRCRAFT HELD UP AT LINE STATIONS
YES
Available in
PK Inventory
NO
YES
A
A
Parts Control
4-1.6 REPROVISIONING
MATERIAL MANAGEMENT
The Model Calculates Economical Order Quantity (EOQ) & Re-order Level (ROL):
MATERIAL MANAGEMENT
MATERIAL MANAGEMENT
AOG /
HOLD-UPS?
MATERIAL MANAGEMENT
MATERIAL MANAGEMENT
Based on:
MTBR/MTBUR
Estimated Service Life
Construction Material
Usage relevant to Maint/Overhaul both
QPA (Quantity per Aircraft)
SPC
MATERIAL MANAGEMENT
Spares
MATERIAL MANAGEMENT
MATERIAL MANAGEMENT Requirement is established as per shop
arising provided by Shop Planning
Establish new set-up parts on computer concerned.
Raise Source 70/75 Cross Checking of RSPL & SMM
Dispatch to catalogue section requirement with on-line system with
consideration to Alternate Part Numbers, No
set-up items & ordered quantities.
Establish Part Number quantities required
MATERIAL MANAGEMENT
This procedure defines PIA Engineering & Maintenance policy regarding contracts managemengt for
outsourced maintenance services.
Maintenance services may be contracted to PCAA Approved Technical Handling Agents at line stations,
under technical handling agreement, to ensure that aircraft is fit for intended flight. Contract shall be based
on effective IATA Standard Ground Handling Agreement.
Substantial maintenance such as heavy aircraft maintenance and engine / APU / landing gear overhaul may
be outsourced under maintenance contracts to maintenance providers, holding valid PCAA Approval.
Other aircraft components and tooling / test equipment shall be sent for repair / calibration to service
providers, approved by PIA Engineering Quality Assurance.
Unless otherwise not possible or not in interest of Organisation, maintenance contracts shall be non-
exclusive. For all contracts (exclusive / non-exclusive), final authority shall be in accordance with the
effective Schedule of Powers.
Chief Engineer (Maintenance Operation Centre), in consultation with Chief Engineer (Quality Assurance),
shall manage maintenance contracts for outsourced substantial maintenance such as heavy aircraft
maintenance and engine / APU / landing gear overhaul, in addition to technical handling agreements.
Deputy General Manager (Finance) Engineering shall provide expertise on financial issues. Draft contract
shall be submitted to obtain clearance from Legal department, if deemed necessary.
Once finalised, Chief Engineer (Maintenance Operation Centre) shall sign maintenance contract on behalf of
PIA Engineering & Maintenance, being integral part of the Operator.
It shall be ensured by the Signatory that maintenance contract, made with maintenance provider
(Contractor), identify specifically industry standard to be used during maintenance and certification activities.
Contracts shall further include:
Qualification of Contractor is based on quality of maintenance services, provided to PIA Engineering &
Maintenance. Tehcnical / administrative issues of outsourced maintenance shall be reviewed in PIA
Engineering Coordination and PIA Reliability Review Board meetings. Achievement of maintenance in
accordance with maintenance contarcts is assessed by Deputy Chief Engineer (Technical Services
Engineering) concerned through review of technical records, received from maintenance services provider.
Whenever deviation from any clause / sub-clause is observed during validity period of maintenance service
contarct or advice from above-mentioned activities is received, Chief Engineer (Maintenance Operation
Centre) shall report such deviation immediately to Chief Engineer (Quality Assurance for root cause analysis
and further action required thereof.
4-1.9 CANNIBALIZATION
PURPOSE
This procedure describes the policy / conditions and methods to be observed when it becomes necessary to
cannibalize component to meet an emergency need of an aircraft.
GENERAL
The following terms with explanation stated below shall be used in this procedure.
Robbed Part: The required part removed from a donor unit to service a recipient unit.
Donor Unit: The unit from which the robbed part is removed. It shall have the parts breakdown.
Recipient Unit: The unit which uses the robbed part. It is most likely an aircraft or engine and less
frequently other compoenents.
Robbed Position: The position on the donor part from which the robbed part has been removed.
PROCEDURE
1- Unless operational requirements justify the necessity, cannibalization action shall be as far as
possible avoided.
2- Cannibalization action may be initiated only if the requisition (issue voucher) submitted for the
required part has been confirmed by stores as “NIL IN STOCK”.
3- However if because of urgent operational requirements, the cannibalization action must be
performed first, then the Maintenance personnel shall after the departure of the aircraft take the
necessary subsequent action to ensure that stores is informed to procure the replacement part
through Rotable Planning.
4- The approval of the Dy. Chief Engineer (Line / Base Maintenance) OR Shift Incharge must be
obtained before cannibalization may be initiated.
5- Maintenance Personnel shall fill Part ‘A’ & ‘B’ of Form # DE/92/003 and forward it to Rotable
Planning for providing required part details i.e. spare float detail, Shop detail if part is lying in
Overhaul Shop.
6- DCE (Rotable Planning) filled the Part ‘D’ on behalf of Chief Engineer (MOC) for final action.
i. Send intimatation to DCE (Repair Abroad) to retrieve the required compoenent from Vendor
facility as soon as possible, and ask for advance exchange unit if repair unit lead time is long.
ii. Obtain EMC approval for spare float enhancement and initiate the procurement process.
iii. Send intimation to concerned Overhaul Shop to serviceable the compoenent on urgent basis.
Release / Shop-out immediately if the required component is repair abroad unit.
Pre Cannibalization Action
Cannibalization Data along with a list of HOT components is being formulated indicating that the
demand of these components prevails throughout the year.
The same is forwarded to respective Shops on daily basis indicating the Stock position as well.
Based on this, the Shop Production and Shop Planning define the spares requirement. Which is
then forwarded to Material Management for Provisioning. Plan staggered over the year which is
ultimately processed and forwarded to P&L Department for procurement. So that the availability of
HOT Items is ensured throughout the year.
After review, some parts found to be needed are retained and rest all parts declared surplus, DPS prepared
Final Listing stock-room-wise for onward dispatch to Manager (Stores Technical) for transferring surplus
material to Stock Room – 20.
DGM (Logistics) / Manager Inventory Control shall obtain approval from Competent Authority for declaration
of disposable surplus items as per Schedule of Power Para 12.56.
The stocks declared surplus and listed in the Surplus Sales existing shall be treated and accounted for as
“Inactive Inventory” and shall not be intermixed with the current Inventory. DPS shall take necessary action
for segregation on computer files.
All out efforts shall be made by Inventory Control Section to dispose-off Surplus Aircraft Items by sale to
Users and other Agencies handling such items. Results achieved shall be reviewed annually by the
Management to examine the desirability to write-off unsold material with the cocurrence of the Competent
Authority.
Inspite of all efforts if the surplus items are left unsold, the write-off action shall be initiated, after a review by
the Management and disposed-off through local auction by Manager Inventory Control Section.
Component Available NO
and determined that Regret through E-mail
unit could be spared
for loan.
YES
NO
Unit receive with Unit sends to Overhaul
serviceable tag Shop for rectification
NO
Route unit to Overhaul Inhouse facility
Shop for packing available
YES
YES YES
NO NO
Rotable Consumable
Availability Availability
Normal Procurement
Spare Float
Scrapped Unit Enhancement
Procurement
against
AOG Procurement
Spare Float
Scrapped Unit Enhancement
Procurement
against
Raise Indent in favor of OEM / Aircraft Raise Indent in favor of OEM / Aircraft
Manufacturer and send it to P&L for Manufacturer send it to P&L for
procurement action with remarks procurement action with remarks CES
“CES / Management Approval to / EMC regularization / Management
follow basis Approval to follow basis
SRC retrieved from P.O is placed to OEM / Case submit in EMC for
concerned Overhaul Shop Aircraft Manufacturer for spare float enhancement
Procurement action
Management approval /
CES send to P&L for EMC Approval /
Regularization Management Approval /
CES send to for
Regularization
YES NO
Spare Float
Exists
Procurement
In Repair Arrange required
Circuit In Shop
Loaner
Unit Location Required
A Action
Intimate Repair Intimate Overhaul Shop Follow the Remove U/S item Procees as per
Abroad for earliest for earliest release of the Loaner unit & get it repaired on procedure
possible retrieval unit from Shop procedure 4-1.2 priority if AOG/Normal
from repair circuit circumstances Procuremtents
allow 4-1.14 & 4-1.15
YES NO YES NO
If authorized SF is greater
YES NO YES NO than Existing Float. RSPL
also supports
Exchange Unit Loaner Unit
Available Available
Initiate the SF
enhancement case &
present in EMC
Unit received Rotable Follow the
and available Planning to Loaner
in Stock arrange for a Process 4-1.2 After EMC Approval take
Room loaner unit management approval &
budget allocation on CES
YES NO
Inform Engineering
Management and follow the Raise indent & send
Loaner Unit Management instruction Management approval
Available either ground the aircraft CES to P&L for
OR procure the unit as per procurement
process 4-1.14 & 4-1.15
NO
Recoupment
required
YES
Refer Procurement
against SRC Process
4-1.14 & 4-1.15
Readiness Log
sends to AWM
Alternate Part
NO ascertaining
Document
Provided
Readiness Log
provided to
Inspection Cardex
YES
Cross check by
Contacting Vendor,
Website
Readiness Log
provided to
Sanitation Cell
CMM / IPC
Reference Attached
INTRODUCTION
Hangar Visit Plan is a year wise plan to forecast and schedule fleet maintenance checks. It gives overview of
all major checks / heavy maintenance to accomplish in the upcoming year. It also specifies the location and
duration of accomplishment of these maintenance activities.
As multiple checks of aircraft may fall simultaneously or closely one after the other, it is mandatory to
schedule the aircraft grounding in such a way that its maximum work done with minimum grounding time.
Furthermore, there are multiple aircraft to be maintained in the small number of maintenance bays. Every
aircraft requires airworthy condition to continue its operation.
Hangar Visit Plan is prepared for the whole year, however, quarterly revisions are issued. In addition, brief
monthly hangar visit plans are also issued.
PURPOSE
The purpose of this procedure is to describe the development process of Hangar Visit Plan to cater for the
fleet heavy maintenance with the available resources.
PROCEDURE
1. The beginning point of hangar visit plan preparation is; database containing information about due
dates of all the maintenance checks due in the upcoming year. The due dates are calculated from
the inputs mentioned below.
• Preambles of all aircraft types – gathered from AWM. Preamble specifies the interval of the
maintenance check. The check interval can be specified in terms of flight cycles, flight
hours, aircraft landings or the calendar time.
• Current Flight Hours, Cycles and Landings of every aircraft – gathered through PAMMIS.
• Average utilization of every aircraft – gathered through PAMMIS.
2. Based upon the due dates, aircraft is assigned a slot in approved bay for specified maintenance
activity with appropriate grounding time.
3. The SB/AD due in the upcoming year, third party business and aircraft pending maintenance tasks
(if any), are catered for in the plan as they may affect the grounding schedule.
• Evaluation Notice of SB/AD issued by AWM. An SB/AD can also be MTB. SB can limit the
scope of maintenance to single component, or it may expand to engine and whole airframe
as well.
• In addition to above, third party business is also considered in this plan. This information is
provided by EBD.
• There can be some pending or carried forward tasks to be accomplished in heavy
maintenance. Major item replacement may also be planned during the check. This
information is obtained from various sections of production planning.
4. The interim plan is circulated to the approved list of recipients to collect their inputs / feedback.
5. After reviewing inputs / feedback and incorporating necessary changes (if any), the final plan is
approved and circulated to the approved list of recipients.
DISTRIBUTION LIST
2- MARKETING DEPARTMENT
2.1- Marketing
INTRODUCTION
Insurance coverage is provided against certain incidents / accidents occurring on PIA fleet. The purpose of
insurance management is to provide risk coverage to PIA assets. By policy, all PIA assets are insured and
any damage can be claimed.
S&CP acts as coordinator between Engineering Department and PIA Insurance. The concerned section is
PIA Manager Insurance & Terminal Benefits. S&CP collects all data required for Insurance claim from
Engineering Department and forwards it to Manager Insurance & Terminal Benefits. Insurance section
contacts the Insurance Company for claim.
PURPOSE
The purpose of this procedure is to provide guidelines to file insurance claims. This procedure is laid down
with the specific objective that no insurable damage is overlooked.
PROCEDURE
Initial Information
S&CP receives intimation of incident/accident occurred anywhere at PIA fleet. There can be any source of
this intimation to S&CP.
Information Verification
- The verification request contains all above mentioned points. The details may be received in the
series of emails. The initial reply should contain the nature of damage and incident report at the
minimum.
Claim Initialization
- Upon verification, the information is passed to PIA Insurance section who contacts the Insurance
Company for claim.
- PIA Insurance forwards the CTA queries to S&CP.
- S&CP coordinates with the concerned DCEs to reply/sort out the query.
- S&CP also coordinates with the surveyor, if any is appointed by the Insurance Company.
- As further details are received, provisional claim bill is developed.
- Once the work is completed, the final claim bill is prepared by S&CP.
- The Insurance Company works with insurance broker for proposal of settlement.
- The proposed settlement is sent to S&CP, who coordinates with the respective sections for final
approval and submitted to PIA Insurance.
- Final Memorandum of Settlement is developed and copy is sent to S&CP.
- Claim stands closed.
INTRODUCTION
Aircraft manufacturer gives warranty of its purchased aircraft. The manufacturer issues Service Bulletins,
Service Letter and Airworthiness Directives for design inspections and modification. Some of the documents
offer warranty remedies too. Boeing 777 aircraft has 4 years of warranty and warranty can be claimed for
following heads consumed in accomplishment of SB.
– Man-hours
– Material
– Freight charges
– Shop Supplies
– Technical Assistance
– Others
Warranty claim can only be filed after SB has been accomplished on at least one aircraft in the effected
fleet.
PURPOSE
The purpose of this procedure is to provide guideline to monitor SB accomplishment for its timely claims.
This procedure will ensure that all required data is collected and complete claim is filed for reimbursement.
PROCEDURE
SB Evaluation
- AWM circulates an email about SB evaluation meeting. The agenda includes the title of SBs along
with their brief description and warranty status. The complete text of SB can be viewed at
www.myboeingfleet.com -> Maintenance Documents.
- S&CP is invited in evaluation meeting. Go prepared about SB details required to file warranty claim.
- Sometimes, a modification is subject to inspection findings. In such case, the consumed man-hours
need proper recording to claim the correct man-hours. In Evaluation meeting, S&CP requests AWM
to design feedback performa and attach it with related Task Card or Engineering Order.
- AWM circulates Evaluation Notice to all concerned, including S&CP. It contains all information
related to scheduling, man-hours and material requirements of SB. In case of inspection SB, Task
Card # is also mentioned in the Evaluation notice.
SB Accomplishment
- S&CP monitors the SB accomplishment status on PAMMIS at defined screen. The procedure is
attached at the end.
- Though man-hours are mentioned in SB and Evaluation Notice too, still in case of ambiguous
information in both, particularly when man-hours are inspection findings dependent, correct man-
hours data is gathered from AWM Avionics or Aerospace Group against feedback performa.
- POSS provides Import No of particular PO. Import No. is provided to COMAT / FRS / P&L for freight
data collection.
- COMAT provides source and destination address and shipment weight of consignment.
- Freight charges are collected from CARGO rate manual (document attached) provided by CARGO /
Marketing.
4.1. PURPOSE
This procedure gives guidelines to establish the effectiveness of base / heavy maintenance performance.
4.2. PROCEDURE
st
1. The base maintenance performance report shall be generated bi-annually. The 1 half yearly report
shall be generated after 5 months of end of HAJJ Operation. The final annual report shall be
generated after start of next HAJJ Operation.
a. Collection of data related to hangar visit plan and actual maintenance activities. There are
two main fields required in this data.
• Capacity Utilization
• Order Fulfillment
• Percentage of Planned Ground Time Compliance
• Product and Process Data Accuracy
Basic Definitions
• Activity
– The smallest activity of heavy maintenance (e.g. Check C) whose duration is 15 days and
above is considered as a unit activity.
– All the remaining activities are defined in terms of that smallest activity e.g.
• Check C – 25 Working Days – 1 Activity
• Check D – 45 Working Days – 1.8 Activity
• Capacity is the availability level of heavy maintenance facility e.g. 261 days in a year.
• Capacity Utilization indicates the duration of time, the maintenance hangar was occupied.
• High capacity utilization means more occupancy of maintenance hangar.
• It is calculated including both PIA and third party maintenance activities.
• Planned Capacity Utilization = Total Working Days Planned / Total Capacity * 100
• Actual Capacity Utilization = Total Working Days Actual / Total Capacity * 100
• In case, the duration of completed activity is different from the planned duration, the planned
duration will be used in calculation.
• An activity which was not planned but completely carried out by base, will be included in order
fulfillment.