You are on page 1of 134

TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT

Method Statement – PLEM Installation

CONTENTS
1 INTRODUCTION....................................................................................................................... 3
1.1 Project Description .........................................................................................................3
1.2 Scope..................................................................................................................................3
1.3 Purpose..............................................................................................................................3
2 DEFINITIONS AND ABBREVIATIONS ................................................................................ 4
2.1 Definitions .........................................................................................................................4
2.2 Abbreviations and Other Definitions .........................................................................4
3 REFERENCES .......................................................................................................................... 5
3.1 Standards and Client / Project Specifications.........................................................5
3.2 Project Reference Drawings.........................................................................................6
3.3 Project Method Statements ..........................................................................................7
3.4 Project Inspection and Test Plans..............................................................................8
4 HEALTH, SAFETY & ENVIRONMENT................................................................................. 8
5 RESPONSIBILITIES ................................................................................................................ 9
6 EQUIPMENT............................................................................................................................ 11
6.1 Vessels and Plant..........................................................................................................11
6.2 Installation Aids, Rigging and Tools........................................................................12
7 PERMANENT MATERIALS.................................................................................................. 13
7.1 General Characteristic .................................................................................................13
7.2 Tolerances.......................................................................................................................14
7.3 Weather Limitation........................................................................................................14
8 PROCEDURE .......................................................................................................................... 14
8.1 Work Sequence..............................................................................................................14
8.2 Typical Preparation.......................................................................................................14
8.3 Installation.......................................................................................................................16
9 QUALITY .................................................................................................................................. 17
10 RECORDS AND REPORTS ................................................................................................. 18
11 CONTINGENCIES .................................................................................................................. 18
12 APPENDICES.......................................................................................................................... 18
12.1 Appendix 1 – Risk Assessment.....................................................................................18
12.2 Appendix 2 - Inspection and Test Plan ........................................................................18
12.3 Appendix 3 – Drawings and Sketches .........................................................................19
12.4 Appendix 4 – Data Sheets and Other Supporting Documents.................................20

Mar 2012 Page 2 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

1 INTRODUCTION

1.1 Project Description


Tanzania Port Authority (TPA) has selected Leighton Offshore Pte Ltd to carryout the
Engineering, Procurement & Construction of a Single Point Mooring (SPM) System, to replace
their existing SPM system, including offshore and onshore pipelines and the removal/
abandonment of the existing SPM and pipelines. The project is located South East of the port of
Dar Es Salaam harbor entrance channel and comprises the development up to and including
pre-commissioning and delivery of an offshore terminal for the Import of crude oil and white
products, capable of mooring tankers in the range of 40k DWT to 150k DWT
Leighton Offshore Pte Ltd has been awarded the EPC Contract for the marine facilities project.
Leighton’s scope of work will be carried out in two phases as outlined below:

Phase I

 Pre Engineering survey of the offshore/onshore fields for obtaining field data for design of
dredging, SPM, PLEM, Pipeline and other accessories etc;
 Detailed Engineering of SPM & PLEM system, Offshore/Onshore Pipelines, and accessories
including installation engineering for SPM/PLEM and pipelines;
 Procurement of line pipes, SPM /PLEM system, complete with anchors, chains, subsea
hoses, floating hoses and mooring hawser;

Phase II

 De-commissioning and removal / abandonment of existing pipeline and SPM system;


 Installation of new 28” crude oil and 24” white product pipelines in 3.6Km offshore and
4.3Km onshore sections between the SPM location and the tank farm;
 Installation of a SPM & PLEM System (at approx. 25 m water depth) including installation of
anchors, anchor chains and tensioning of anchor chains, installation of PLEM and SPM,
connecting subsea and floating hoses with SPM & PLEM system;
 Testing and pre-commissioning of the complete system.

1.2 Scope

This Method statement details the minimum requirements for performance and procedure of
the PLEM Installation for the Tanzania SPM & Pipelines Replacement EPC Project.

1.3 Purpose

The purpose of this work method statement is to ensure that:-


 All works involved with the PLEM Installation are in accordance with project
requirements and LOPL safety policies.
 Provides a systematic procedure for PLEM Installation respectively in a safe and
timely manner.

Mar 2012 Page 3 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

2 DEFINITIONS AND ABBREVIATIONS

This following definitions and abbreviations shall apply to this document

2.1 Definitions

Employer : Tanzania Port Authority (TPA)


Project Management Consultant : INTECSEA B. V., Holland
Contractor : Leighton Offshore Pte Ltd, the EPC Contractor
Subcontractor : The party who has a contract with the
Contractor to carry out a part to the work in the
Contract, which includes work on the Site
For this particular scope the Main
Subcontractor will be the PLEM Supplier
which is SBM Offshore
Third Party Certifying Agency (TPCA) : The Third Party Inspection and Certification
Agency who shall have full responsibility for
the work of certification which shall be
sufficient and correct for the design,
manufacturer, installation and operation of a
complete functional System
For this particular scope the Third Party
Inspection and Certification Agency will be
Det Norske Veritas (DNV)

2.2 Abbreviations and Other Definitions

AHT Anchor Handling Tug


BH Bore Hole
CALM Catenary Anchor Leg Mooring
DES Dar Es Salaam
DNV Det Norske Veritas
HSE Health, Safety and Environment
ITP Inspection Test Plan
LOPL Leighton Offshore Pte. Ltd.
mtr Meter
OD Outside Diameter
PLEM Pipeline End Manifold

Mar 2012 Page 4 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

SBMO Single Buoy Mooring Offshore


SPM Single Point Mooring
SMYS Specified Minimum Yield Strength
T Tonnes
TPA Tanzanian Port Authority
USBL Ultra Short Base Line
Work Barge Stealth

3 REFERENCES

3.1 Standards and Client / Project Specifications

Table 3.1 Reference Documents


Document No. Title

31043501-003-SOW-001 Scope of Work for EPC of SPM and Pipeline System

31043501-002-SP-001 Specification for Overall System Performance

31043501-002-SP-004 Specification for SPM System

S393-SPM-SBM-ENG-SPEC-
CALM Buoy - General Specification (SZM92003)
2001

S393-SPM-SBM-ENG-SPEC-
PLEM - Piping Material - Specification (SPM84010)
2024

S393-SPM-SBM-ENG-SPEC- PLEM - Piping Fabrication - Specification


2025 (SPM84011)

S393-SPM-SBM-ENG-SPEC- PLEM - Subsea Ball Valve Actuator - Specification


2026 (SPM84042)

S393-SPM-SBM-ENG-RPT- PLEM - Structure - Installation Calculation


2013 (CSM84031)

S393-SPM-SBM-ENG-RPT-
PLEM - Piping Stress - Calculation (CPM84012)
2014

S393-SPM-SBM-ENG-RPT- PLEM - Cathodic Protection Design - Calculation


2016 (CSM06012)

Mar 2012 Page 5 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

S393-SPM-SBM-ENG-RPT-
PLEM - Structure - In place Calculation (CSM84032)
2023

S393-SPM-SBM-ENG-RPT-
PLEM Foundation Calculation (CIU84001)
2028

0 S393-PL-ZEE-ENG-RPT-1203 Mooring Analysis

S393-SPM-CGS-ENG-RPT-
SPM System Transportation Manual
2103

3.2 Project Reference Drawings

Table 3.2 Reference Documents


Document No. Title

S393-PL-LYE-ENG-DWG-
Overall Pipeline Schematic
1002

S393-SPM-SBM-ENG-DWG-
CALM Buoy - General - Field Layout (DUM86023)
2001

S393-SPM-SBM-ENG-DWG- PLEM - Structure - General Arrangement


2041 (DSM84001)

S393-SPM-SBM-ENG-DWG-
PLEM - Structure - Detail Sheet 1 (DSM84002)
2042

S393-SPM-SBM-ENG-DWG-
PLEM - Structure - Detail Sheet 2 (DSM84003)
2043

S393-SPM-SBM-ENG-DWG-
PLEM - Piping - General Arrangement (DPM84007)
2045

S393-SPM-SBM-ENG-DWG-
PLEM - Piping – Isometric (DPM84008)
2046

S393-SPM-SBM-ENG-DWG- PLEM - Cathodic Protection Design – Detail


2047 (DSM06003)

S393-SPM-SBM-ENG-DWG- PLEM - Valves Actuation Controls Interface -


2048 General Arrangement (DMM19002)

Mar 2012 Page 6 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

S393-SPM-SBM-ENG-DWG- PLEM - Valves Actuation Controls Interface – Detail


2050 (DMM19005)

S393-SPM-SBM-ENG-DWG-
PLEM - Structure – Protection Cage (DSM84005)
2053

S393-SPM-SBM-ENG-DWG-
PLEM - General – Arrangement (DSM84000)
2054

S393-SPM-SBM-ENG-DWG-
PLEM - Lifting - General Arrangement (DSM84006)
2055

S393-SPM-SBM-ENG-DWG-
PLEM - Piping - Support (DPM84009)
2056

3.3 Project Method Statements

Table 3.3 Reference Documents


Document No. Title

S393-SUR-OSS-OPR-MS-
Method Statement for Offshore Survey
3301

S393-SUR-OSS-OPR-MS-
Method Statement for Barge Positioning Survey
3302

S393-PL-LOPL-OPR-MS- Method Statement for Offshore Tie-In Spools


1306 Installation

S393-SPM-LOPL-OPR-MS-
Method Statement for Subsea Hose Installation
2306

S393-SPM-SBM-ENG-GDL-
CALM System Installation Guidelines
2001

S393-PCM-LOPL-OPR-MS- Method Statement – Pre-commissioning of Offshore


5301 Pipelines and SPM System Leak Test

S393-GEN-LOPL-OPR-MS-
Method Statement for Vessel Anchor Handling
6303

S393-GEN-LOPL-OPR-MS-
Method Statement for Diving Operation - Pipeline
6304A

Mar 2012 Page 7 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

S393-GEN-LOPL-OPR-MS- Method Statement for Diving Operation – SPM


6304B System

3.4 Project Inspection and Test Plans

Table 3.4 Reference Documents


Document No. Title

S393-SPM-LOPL-QAM-ITP-
Inspection and Test Plan For PLEM Installation
2301

4 HEALTH, SAFETY & ENVIRONMENT

The activities detailed in this document shall be undertaken in accordance with approved
Leighton safety plan and the specific risk assessments and safety analysis conducted prior
to commencement of the Work.

Mar 2012 Page 8 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

5 RESPONSIBILITIES

5.1 Project Manager


Project Manager will report to the Project Director on all aspects of progress and
performance of the project. Construction Manager, Engineering Manager, QA/QC & Systems
Manager and HSE Manager will report to the Project Manager. The Project Manager will
coordinate and monitor all the project related activities.

5.2 Construction Manager


Construction Manager will report to the Project Manager. He is responsible for all aspects of
the performance and progress of the construction works of the project. He will ensure that
Project / Field Engineer, Superintendent, Foreman and other related Supervisory staff is
familiar with the procedure and safety requirements for the activity.

5.3 Engineering Manager


Engineering Manager will report to the Project Manager. He works closely with Construction
Manager and QA/QC & Systems Manager. He is the main liaison for all Engineering matters
with Client and responsible for Engineering within the Project.

5.4 QA/QC & Systems Manager


QA/QC & Systems Manager will report to the Project Manager. He shall be responsible for
coordinating the documentation and implementation of the Project Quality Management
Systems on this project. He will establish systems to monitor the performance of internal and
subcontractors to ensure compliance with the Inspection and Test Plan. He will liaise with
the Employer Project team, Third Party Certification Agency and other authorities with
respect to quality – acceptance criteria.

5.5 HSE Manager


HSE Manager will be responsible for the development, communication and implementation
of an effective, strategic health, safety and environment program. He will make sure that we
have, at all times, the capability and resources to operate safely and with no harm to health,
and will make sure that our Health, Safety and Environment Policy and procedures are
implemented properly at all levels. He will coordinate and monitor activities relating to health,
safety and environment at all working locations, promote safety awareness and device
safety training and education for Project team members and Sub-contractors. He will also
liaise with the Environmental Agency and other local authorities on Environmental and
Safety aspects of the project.

5.6 Project Engineer / Field Engineer


Engineer will report to the Barge Superintendent. Ensure that all equipments and tools
involved in the project are certified by competent authority and fit for the service. Conduct
daily inspection of tools and tackles and ensure that tools and tackles are in good condition
at all times during construction activities. Ensure that statutory permissions are available
prior to commencement of any work. He will be responsible to carry out all the activities as

Mar 2012 Page 9 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

per the approved drawings. Ensure HSE compliance on site and coordinate with site HSE
Manager.

5.7 Lead QA/QC Engineer & QA/QC Engineer


QA/QC Engineer will report to the QA/QC & Systems Manager. He will ensure that
Construction team and Subcontractor team are fully aware of quality standards, working to
approved procedures and inspection records are produced and signed off in a timely
manner. He will identify and assist in close out of the Non Conformances issued by him,
Client or TPI prior to commencement of other activities.

5.8 Barge Superintendent


Barge Superintendent will report to the Construction Manager. He is responsible for all
aspects of the performance and progress of the construction works on the Work Barge
(offshore).. He will ensure that Project / Field Engineer, Foreman and other related Barge
Crew is familiar with the procedure and safety requirements for the activity.

5.9 Barge Foremen / Crew


Barge Foreman will report to the Barge Superintendent. He is responsible for the
construction works on the Work Barge (offshore) and supervise the Barge Crew. He will
ensure that the Barge Crew is familiar with the procedure and safety requirements for the
activity.

5.10 Party Chief Surveyor


Party Chief will report to the report to the Barge Superintendent, and work closely with the
Project Engineer and Barge Foreman. He will be responsible of all the survey activities, and
will ensure with the Construction Manager that all the resource and equipment are adequate
for the work. The Party Chief Surveyor will supervise all calibration and installation of
equipment and all survey data is correctly logged and processed.

5.11 Diving Supervisor


Diving Supervisor will report to the report to the Barge Superintendent, and work closely with
the Project Engineer and Barge Foreman. He shall be responsible for the diving team, diving
equipment and consumables related to diving operation. He shall ensure the diving team
understands the task to be carried out as per agreed Project Diving Activities and Barge
Superintendent’s requirements / instructions. He will ensure all diving works are conducted
and completed in a safe and efficient manner.

Mar 2012 Page 10 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

6 EQUIPMENT

6.1 Vessels and Plant

NO DESCRIPTION
1 Work Barge - Stealth
Basic Characteristic
Class : ABS – A1 Accomodation Work Barge, Helideck
LOA : 100mtr (330ft)
Breadth : 30mtr (100ft)
Depth : 6mtr (20ft)
Draft : 2.5mtr to 4.5mtr
Deck Loading Capacity : 15MT/m2
9-point Mooring System
FWD Mooring Winches : 5 nos of single drum 45MT with 42mm wire x 1200mtr
AFT Mooring Winches : 4 nos of single drum 35MT with 42mm wire x 1000mtr
A&R Winch : 1 no of single drum 100MT with 64mm wire x 600mtr

Figure 1 - Stealth

2 Anchor Handling Tug


1no required to support the positioning and anchor handling activities of PLB Stealth.
Minimum requirements: 5000 BHP
Deck Equipment shall comprises, but not limited to: Tugger / Towing Winch, Capstan, Stern
Roller, Shark Jaw, Towing Pin, etc.

3 Flat Top Barge


1no Flat Top barge will be the PLEM storage point.

4 Support Tug
1no required to support the positioning and handling activities of the 180’ Barge. Minimum
requirements: 2500 BHP

Mar 2012 Page 11 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

5 Hydraulic Crawler Cranes


2nos are available on Work Barge Stealth, basic characteristic as followed:
Brand : Hitachi Sumitomo
Type : SCX 2800-2

Table 6.1.5. – Crane Capacity

STERN CRANE - BOW CRANE - Boom


Boom Length 39.6mtr Length 45.7mtr
De-Rated De-Rated
Capacity Capacity
Radius Radius
for for
(mtr) (mtr)
Offshore Offshore
(T) (T)
10 87.7 10 83.3
20 38.9 20 38.5
30 22.2 30 21.8
40 n/a 40 14.4

0 NOTE: the above capacity values has been adjusted to suit offshore operation
In the absence of specific manufacturers data Personnel shall not operate a crane in wind
speeds in excess of 10m/sec or swells greater than 2m.

6 Survey Spread
Complete Spread for :
 Positioning and Navigation for Work Barge Stealth
 Anchor Handling Support System for the AHT and Support Tug
 As-Built Survey Equipment
 USBL and UNDERWATER GYRO (IXSEA Octans 3000)

7 Diving Spread
Complete Air Diving Spread, comprises of but not limited to:
 Dive Control Station
 Deco Chamber (1-man or 2-man)
 Dive LARS
 Other supporting equipment and consumables

8 10T and 5T Air Tugger Winch

6.2 Installation Aids, Rigging and Tools

NO DESCRIPTION QTY
4-leg Dia.48mm x EL.20mtr Wire Rope, Soft Eye both Ends, Steel Ferrule
1 1 lot
assembled with 80T WLL Master Link
2 35T SWL Crosbly Shackle G-2130 4 nos
3 General Tools and Rigging 1 lot

Mar 2012 Page 12 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

7 PERMANENT MATERIALS

The permanent materials related to this scope of operation are detailed on this section.

7.1 General Characteristic

TUGGER LINE
CONNECTION POINT

GYRO PROPOSED
POSITION

Figure 2 – PLEM GA
0 TUGGER LINE
CONNECTION POINT

Mar 2012 Page 13 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

Table 7.1. – PLEM Characteristic

PLEM
PLEM Type Skirted Gravity PLEM
Dimension (mtr) 8.5m x 12.05m x 2.5m with 1.5m skirt
Weight In Air (T) 54.7 T
Proposed SPM/PLEM Reference
541 526.00 m
0 Coordinate – Easting
Proposed SPM/PLEM Reference
9 246 742.00 m
Coordinate – Northing
Water Depth 25.5m LAT
NOTE:
SPM/PLEM Reference Center Coordinate shall be adjusted based on actual center point
between the spool piece on the PLEM.

7.2 Tolerances
The installation acceptance criteria and tolerances are presented in the following table:

Table 7.2. – PLEM Tolerances

PLEM Position Circle 1.5mtr (radius)


PLEM Heading ± 3 deg
PLEM Tilt ± 2 deg

7.3 Weather Limitation


0 The limiting sea state for the PLEM Installation is a 1.5m maximum wave height and 15 knot
maximum wind. Preferable to be done during low tide for minimum current. The minimum
acceptable window to be established prior to PLEM Installation is 12 hours. This limiting sea
state is an indication only and the final decision will be made by the Barge Superintendent.

8 PROCEDURE

8.1 Work Sequence

NO DESCRIPTION
1 Activity Prior Commencement : ANCHOR POINT AND LEG INSTALLATION
2 Activity Prior Completion : PIPELINE AND SPOOL INSTALLATION

8.2 Typical Preparation

NO DESCRIPTION
PLEM shall be positioned as per S393-SPM-SBM-OPR-DWG-2351 PLEM Installation
1
Methodology and seafastened accordingly to the material barge deck.

Mar 2012 Page 14 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

Set up Stealth as shown in S393-SPM-SBM-OPR-DWG-2367 PLEM Installation Anchor


2
Pattern.
While setting up anchors, the seabed at the design location shall be inspected for debris.
3 An area around the design centre of the proposed structure location and spool
approaches shall be inspected.
Divers to identify the size and shape of any debris. Any debris that will effect the
4
installation of the structure shall be reported and removed as directed.
PLEM shall be pre-rigged as per S393-SPM-SBM-ENG-DWG-2055 PLEM - Lifting -
5 General Arrangement.
Note: intermediate 55T shackle is required between the 35T shackle and the slings
0 6 Ensure all the PLEM valves position are as followed:

Table 8.2.6. – PLEM Valve Position

VALVE TAG VALVE SIZE PRODUCT POSITION


U64-BL01-01-0001 20” Crude HALF OPEN
U64-BL03-01-0001 2” Crude HALF OPEN
U64-BL02-01-0001 20” White Line HALF OPEN
U64-BL03-01-0002 2” White Line HALF OPEN

Ensure all the hydraulic umbilical actuator valves position on the PLEM are as followed:

Table 8.2.7. – PLEM Hydraulic Umbilical Valve Actuator Position

VALVE TAG VALVE SIZE PRODUCT POSITION


7 U19-BL01-01-0001 1/2” Crude OPEN
U19-BL01-01-0002 1/2” Crude OPEN
U19-BL01-01-0003 1/2” Crude CLOSE
U19-BL02-01-0001 1/2” White Line OPEN
U19-BL02-01-0002 1/2” White Line OPEN
U19-BL02-01-0003 1/2” White Line CLOSE
Ensure the pipe module of the PLEM are secured in neutral position on the pipe support
8 to allow displacement and securely strapped on the PLEM base (center location, refer to
S393-SPM-SBM-ENG-DWG-2045 PLEM Piping GA)
Ensure all the flanges on the PIPELINE END and SUBMARINE HOSE END connections
are OPEN to allow free flooding.
While the back PLEM END blind flange shall remain installed at all time during
9
installation.
Note: provision to protect to avoid damages on the flange face shall be done and to be
decided on site.
2nos of 10T Air Tuggers shall be pre-set on the port side of the Stealth to support
10
maneuvering of the PLEM.
Ensure all survey system for PLEM positioning all working. Refer to Appendix 4 of this
11 document, S393-SUR-OSS-OPR-MS-3301 Method Statement for Offshore Survey S393-
SUR-OSS-OPR-MS-3302 Method Statement for Barge Positioning Survey.
Ensure all diving system for PLEM positioning all working. Refer to S393-GEN-LOPL-
12
OPR-MS-6304B Method Statement for Diving Operation – SPM System.
Prepare all required rigging for PLEM installation activities and are completed with
13
certificates accordingly.

Mar 2012 Page 15 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

Secured a plum bob and a guide on the center protection cage of the PLEM to guide the
14
leveling on seabed.
Prior to any lifting operations or major construction operations, a JSEA will be conducted
15
as required in accordance to RA.
16 Ensure PLEM skirt is marked so diver can be easily identify penetration to seabed.
NOTE:
The above is for PLEM installation based on anchor points installation prior to PLEM
installation.
IF anchor points installation to be done after PLEM installation, then to note the following:
- To ensure clearance of Stealth anchor and anchor wire are clear from the PLEM at all
time
- To ensure the chain lay as per S393-SPM-SBM-ENG-DWG-2061 and chain
tensioning operation, are maintaining safe distance between to the PLEM

8.3 Installation

NO DESCRIPTION
Confirm weather window as referenced in Section 7.3. Once a suitable weather window
1
has been established, bring and secure material barge onto the port side of the Stealth.
2 Personnel and equipment shall be transferred to the material barge.
Confirm PLEM is pre-rigged as per S393-SPM-SBM-ENG-DWG-2055 PLEM - Lifting -
3 General Arrangement.
Note: intermediate 55T shackle is required between the 35T shackle and the slings
Install divers taglines, tugger lines, USBL beacon/Gyro, and other required installation aids
onto the PLEM.
Note: 2nos of 10T tugger lines shall be attached to each end of the PLEM for manoeuvring
Further details refer to Figure 2.
Gyro Stool (sample shown below) will be welded to inner part of the Stabilizer Pipe, the
offset from the target coordinate and centre PLEM will be recorded prior to PLEM
deployment and will be used as a reference.

Figure 3 – Gyro Stool Sample

Further details on Gyro shall refer to Appendix 4.

Cut seafastening and connect the rigging to Stealth stern crane hook to the pre-installed
5 rigging. The seafastenings will be cut progressively, as and when they are required per the
installation sequence.
Lift PLEM off the material barge deck (1-2mtr clearance) and cast the barge away from
6
Stealth port side.

Mar 2012 Page 16 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

Lower PLEM to position up to 5m above seabed using USBL beacon/Gyro or guidance


from divers. PLEM will be free flooded with un-treated sea water. However the pipeline
which later to be connected to the PLEM will be treated with chemicals.
7
Note:
Prior to diving operations, work system permit must be obtained to cover restriction and
conducted a pre-job meeting to cover the requirements.
Position PLEM as the same bearing as the proposed target (Table 7.1) under guidance
from divers.
NOTE:
Buoy center will be positioned accordingly after PLEM installation, with the following
reference:
- center of the Buoy shall be positioned in the center of the 2 spool
8 piece on the PLEM
- crude bottom piping spool shall be positioned in heading between
A1 and A2
- crude bottom piping spool shall be positioned in heading between
A4 and A5
Further detail refer to S393-SPM-SBM-ENG-DWG-2021 and S393-SPM-SBM-ENG-DWG-
2064.
Survey to check level (pitch, roll and heading) of the PLEM by using Gyro the drop the
PLEM on seabed.
9
NOTE:
Diver can manually verify by using manual spirit level if its necessary.
Take a survey fix on:
- both flanges on Pipeline End
- both flanges on Blind End
10 - each end of the PLEM
- center point of the PLEM
Using Gyro and diver handheld USBL beacon if required.
Further detail shall refer to Figure 2, Table 7.1 and Appendix 4.
11 Disconnect rigging with Diver(s) and recover to surface.
Conduct as-built survey by divers to cover :
- 360deg visual of the PLEM
12
- Visual of the skirt penetration on the seabed
- Level check using spirit level, pitch and tilt
13 Ensure checklists and ITPs are completed.

9 QUALITY

The activities detailed in this document shall be undertaken in accordance with the approved
Inspection and Test plan which attached on Appendix 2 of this Method Statement.

Mar 2012 Page 17 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

10 RECORDS AND REPORTS

The applicable inspection formats as detailed in the Inspection and Test Plan shall be used
to record the inspections carried out. Sample of the Record Sheet is attached on Appendix 2
of this Method Statement.

11 CONTINGENCIES

The PLEM installation can be reversed at all stages of the operation. If recovery is required
the PLEM will be landed onto the material barge/Stealth deck.

The contingencies addressed in this section are as follows:


 Seabed Obstructions
 Equipment Malfunction

11.1 Seabed Obstructions


Seabed obstructions will be removed by either recovery to deck by the crane or by moving
clear of installation target location using divers. The Barge Superintendent and Project
Engineer will evaluate the rigging requirements for each of the items to be moved.

11.2 Equipment Malfunction


The scope of the procedure is dependent on the correct operation of the Work Barge
equipment, namely cranes, survey system and diving system. Spares parts for critical
equipment will be carried onboard the Work Barge for contingency purposes. In the unlikely
event of equipment malfunction, the fault will be rectified by the Work Barge Chief Engineer,
Marine Crew and/or relevant Subcontractor personnel.

12 APPENDICES

12.1 Appendix 1 – Risk Assessment


Doc. No. Title
S393-HSE-RA-015 RA for Diving (General)
S393-HSE-RA-017 RA for PLEM Installation
S393-HSE-RA-023 RA for Anchor Handling

12.2 Appendix 2 - Inspection and Test Plan


Doc. No. Title
Inspection and Test Plan For PLEM
S393-SPM-LOPL-QAM-ITP-2301
Installation

Mar 2012 Page 18 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

12.3 Appendix 3 – Drawings and Sketches


Drawing No. Title
S393-PL-LYE-ENG-DWG-1002 Overall Pipeline Schematic
S393-PL-LYE-ENG-DWG-1003 Overall Pipeline Route Layout
S393-PL-LYE-ENG-DWG-1011 Pipeline Spool Tie In Details at PLEM
S393-SPM-SBM-ENG-DWG-2001 CALM Buoy - General - Field Layout
S393-SPM-SBM-ENG-DWG-2041 PLEM - Structure - General Arrangement

S393-SPM-SBM-ENG-DWG-2042 PLEM - Structure - Detail Sheet 1

S393-SPM-SBM-ENG-DWG-2043 PLEM - Structure - Detail Sheet 2

S393-SPM-SBM-ENG-DWG-2045 PLEM - Piping - General Arrangement

S393-SPM-SBM-ENG-DWG-2046 PLEM - Piping – Isometric

S393-SPM-SBM-ENG-DWG-2047 PLEM - Cathodic Protection Design – Detail

PLEM - Valves Actuation Controls Interface -


S393-SPM-SBM-ENG-DWG-2048
General Arrangement

PLEM - Valves Actuation Controls Interface


S393-SPM-SBM-ENG-DWG-2050
– Detail

S393-SPM-SBM-ENG-DWG-2053 PLEM - Structure – Protection Cage

S393-SPM-SBM-ENG-DWG-2054 PLEM - General – Arrangement

S393-SPM-SBM-ENG-DWG-2055 PLEM - Lifting - General Arrangement

S393-SPM-SBM-ENG-DWG-2056 PLEM - Piping - Support

S393-SPM-SBM-ENG-DWG-2057 PLEM - Spool Piece

CALM Buoy System – Hydraulic System –


S393-SPM-SBM-ENG-DWG-2172
Interface Diagram

S393-SPM-SBM-OPR-DWG-2351 PLEM Installation Methodology

S393-SPM-SBM-OPR-DWG-2367 PLEM Installation Anchor Pattern

S393-SPM-SBM-OPR-DWG-2368 PLEM Set Down Position

Mar 2012 Page 19 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

12.4 Appendix 4 – Data Sheets and Other Supporting Documents


Doc. No. Title
n/a Work Barge Stealth Specification Sheet
n/a Flat Top Barge Specification Sheet
Work Barge Stealth Crawler Crane Load
n/a
Chart
n/a IXSEA Octans 3000

Mar 2012 Page 20 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

Appendix 1 – Risk Assessment


Doc. No. Title
S393-HSE-RA-015 RA for Diving (General)
S393-HSE-RA-017 RA for PLEM Installation
S393-HSE-RA-023 RA for Anchor Handling

Mar 2012 Page 21 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


RISK ASSESSMENT REPORT
Divisional Office / Project: S393 - Tanzania SPM and Pipeline Replacement EPC Project Assessor's) : Nicholas Say
Ref. No.: S393 -HSE -RA-015

Activity: Diving (General) Assessment Purpose: (Preparation/Supplementary to method statement/following incident , etc.)

Preparation / Supplementary to Method Statement


Cause of
People/
Adverse Effect / Type of Ctrl Legal and Other
Job / Task Environment/ Adverse Effect / L1 S1 RFN ** Mitigating Controls L2 S2 RRN * Assessment
Environmental Impact Type Requirements Reference
Property at Risk
Environmental Aspect

PREPARATION FOR DIVING OPERATION


EL -
S -
Medical Officer onboard to be refer for any medical Medical Doctors /
E Barge Master/
query.
Construction
Diver Medical Fitness-checkup & endorsement by
Diver Fitness to work:- Superintendent Refer to S393-GEN-LOPL-OPR-MS-
Divers Death 2 4 8 recognize diving Medical Doctor, 1 4 4
Intoxicated/Sick.dizziness & etc. empower to remove 6304A/B
A Consequence Management - to an extend of expulsion
Diver's founded
of diver founded in toxicated or working under the
contravening Drugs
influence of Prohibited Drug.
& Alcohol at work
Diving Suit, Diving Mask, Diving Gloves, Diving Boots
P
and Divers Knife
EL
S -
Cease diving operation in the event of any diving gears Diving
E
founded malfunction or damage. Superintendent -
Equipment Fitness:- Verification of all Diving equipment certification by "shall be responsible
Malfunction/damages of diving Supervisor for the diving team, Refer to S393-GEN-LOPL-OPR-MS-
Divers Drowning 2 4 8 1 4 4
gears & Contaminated Air supply Inspection Of Diving equipment by Divers and diving equipment 6304A/B - 8.3.1-Equipment
A
(Diving cylinder) overseeing by Supervisor and consumables
Periodic Maintenance plan emplace for all diving related to diving
equipment operation"
On deck diving Diving Suit, Diving Mask, Diving Gloves, Diving Boots
P
operation and Divers Knife
preparation work EL -
S -
Designated & Dedicated housekeeping session after
E
each operation at site/onboard Diving
Worksite hazard - slippery In place of signage - wet floor/slippery floor Superintendent -
Personal on
surface, wet & tripping hazard on Trips, Slips and Falls 3 2 6 Hazard Observation card to identify, control and 2 2 4 submit any report of -
deck
deck A mitigate the work site condition (unsafe condition & injury or accident on
unsafe act) site/board
Safety Tool Box Talk prior to start operation
Diving Suit, Diving Mask, Diving Gloves, Diving Boots
P
and Divers Knife
EL -
S -
E

Apr 2010 Page 1 of 5 LIL-HSEFM-001A(03)


Divisional Office / Project: S393 - Tanzania SPM and Pipeline Replacement EPC Project Assessor's) : Nicholas Say
Ref. No.: S393 -HSE -RA-015

Activity: Diving (General) Assessment Purpose: (Preparation/Supplementary to method statement/following incident , etc.)

Preparation / Supplementary to Method Statement


Cause of
People/
Adverse Effect / Type of Ctrl Legal and Other
Job / Task Environment/ Adverse Effect / L1 S1 RFN ** Mitigating Controls L2 S2 RRN * Assessment
Environmental Impact Type Requirements Reference
Property at Risk
Environmental Aspect

Ring buoy afloat Hazard identification


Diver ascending/ descending to
Personal Injury :- Standby vessel on standby (rescue purposes) and reporting of
Divers water surface through diver 4 2 8 2 2 4 -
cuts/bruises A Medic / Doctor onboard inform unsafe act or
platform
Master/ Chief officer onboard ready for "man- condition at site
overboard" rescue.

Diving Suit, Diving Mask, Diving Gloves, Diving Boots


P
and Divers Knife

GENERAL DIVING OPERATION

EL -
S -
E - Empowerment of
Seek advise from Barge Master -pertaining to under Barge master to
Personal Injury :- water current prior to start diving operation "stop diving
Strong surface or under water
Divers cuts/bruises/ lost at 2 4 4 Pre-planning Diving operation meeting with Barge 1 4 4 operation" in the -
current A
sea/Fatality master event of strong
Inform medical officer onboard prior to start diving surface/underwater
operation current at site.

Diving Suit, Diving Mask, Diving Gloves, Diving Boots


P
and Divers Knife
EL -
S -
E Wear Shark shield

Ensure dedicated person doing the look out / watch


keeping at all time Ensure
standby vessel and local (onshore ) Ambulance
Shark attack/stingray jellyfish/ service is on 24 hours alert condition
Divers bites/ sting from other marine Personal Injury/Death 2 4 8 Assessing and debriefing of present situation by diving 1 4 4
A
life. superintendent
Testing of local emegergency telephone line prior to
start diving operation. Ensure
medical officer/Doctor onboard are keep update on
diving operation apart from first aider on site.

Diving Suit, Diving Mask, Diving Gloves, Diving Boots


P
and Divers Knife

EL -

S -
No diving operation in the event of unpermiting
E weather condition -advise seek from the Master of the
Barge
Working/Diving R f t S393 GEN LOPL OPR MS

Apr 2010 Page 2 of 5 LIL-HSEFM-001A(03)


Divisional Office / Project: S393 - Tanzania SPM and Pipeline Replacement EPC Project Assessor's) : Nicholas Say
Ref. No.: S393 -HSE -RA-015

Activity: Diving (General) Assessment Purpose: (Preparation/Supplementary to method statement/following incident , etc.)

Preparation / Supplementary to Method Statement


Cause of
People/
Adverse Effect / Type of Ctrl Legal and Other
Job / Task Environment/ Adverse Effect / L1 S1 RFN ** Mitigating Controls L2 S2 RRN * Assessment
Environmental Impact Type Requirements Reference
Property at Risk
Environmental Aspect
Working/Diving Refer to S393-GEN-LOPL-OPR-MS-
operation Injury to personnel /fall Good seamanship & watch keeping at all time 6304A/B - 8.5-Controls in Changing
Divers Adverse weather condition overboard/lost of life 4 1 4 Update weather condition according to latest weather 3 1 3
Meteorological and Ocean Logical
at sea satellite forecast/warning onboard Condition
A Master/Chief officer on board to update Diving
superintendent interval weather condition
Only the Master to handle/manning the barge while
diving operation
Diving Suit, Diving Mask, Diving Gloves, Diving Boots
P
and Divers Knife
EL -

S -

No diving operation in the event of unpermiting


E weather condition -advise seek from the Master of the
Barge
Inclement weather /Unstable Fall overboard/Lost of
Divers 4 1 4 Pull out procedure (Barge) in place in the event of 3 1 3 SOLAS
dive station barge life
weather picking up
A Barge to carry out "Man-overboard drill"as per ISM
requirement (anticipating) any unplanned event
onboard.
Diving Suit, Diving Mask, Diving Gloves, Diving Boots
P
and Divers Knife
EL -
S -
E -
Proper handover note onboard by officer on duty
Asset damage /
Divers Collision /Sinking 3 2 6 (communicate deficiency) 2 2 4 SOLAS- STCW95
Personal Injury
A Carry out ISM (vessel grounding drill on board) in
anticipation of unplanned event
Doctor & ambulance on standby
Diving Suit, Diving Mask, Diving Gloves, Diving Boots
P
and Divers Knife

DEEP DIVING

EL -
S
E

Apr 2010 Page 3 of 5 LIL-HSEFM-001A(03)


Divisional Office / Project: S393 - Tanzania SPM and Pipeline Replacement EPC Project Assessor's) : Nicholas Say
Ref. No.: S393 -HSE -RA-015

Activity: Diving (General) Assessment Purpose: (Preparation/Supplementary to method statement/following incident , etc.)

Preparation / Supplementary to Method Statement


Cause of
People/
Adverse Effect / Type of Ctrl Legal and Other
Job / Task Environment/ Adverse Effect / L1 S1 RFN ** Mitigating Controls L2 S2 RRN * Assessment
Environmental Impact Type Requirements Reference
Property at Risk
Environmental Aspect

Employ only train, competent and experience diving


superintendent to man the recompression chamber.
Ensure the Recompression chamber is available,
Working under inspected and maintain periodically
Decompression Refer to S393-GEN-LOPL-OPR-MS-
water (Deep Exceed duration and deep of The divers and the superintendent to inspected, verify
Divers sickness/Hypothermia/ 2 4 8 1 4 4 6304A/B-8.4-Limits on Dept and
diving & long dive and ensure the Pneumofathometer /dept gauge is
Cold stress A Time Underwater
duration) functioning/working correctly. The
superintendent to verify and assess the water
deepness by consulting with the barge master/chief
officer on board. The diving
superintendent to monitor and keep track of divers
diving log record.

Diving Suit, Diving Mask, Diving Gloves, Diving Boots


P
and Divers Knife
NIGHT DIVING
EL
S
Unless on emergency and live threatening situation,
E only then night diving operation carried out,or Else NO
diving operation at night is permitted.

Diving Bodily Injury, marine


Communicate dive plan thorough Safety Tool Box talk. Refer to S393-GEN-LOPL-OPR-MS-
operations-Night Divers Reduce visibility during diving life attack- 2 4 8 1 4 4
Assessing the weather condition with cross references 6304A/B-8.2.2- Limits
diving operation deadly/drowning
A with forecast weather update.
Seeking advise from Master /Chief officer in pertaining
to sea-state prior to dive at night.

Diving Suit, Diving Mask, Diving Gloves, Diving Boots


P
and Divers Knife

DEPLOYMENT OF SUPPORTING EQUIPMENT/TOOLS/AIRLIFT ettc.


EL
S

Apr 2010 Page 4 of 5 LIL-HSEFM-001A(03)


RISK ASSESSMENT REPORT
Divisional Office / Project: S393 - Tanzania SPM and Pipeline Replacement EPC Project Assessor(s) : Nicholas Say
Ref. No.: S393 -HSE -RA-023

Activity: Anchor Handling Assessment Purpose: (Preparation/Supplementary to method statement/following incident , etc.)
Preparation / Supplementary to Method Statement
Cause of
People/ Adverse Effect / Type
Ctrl Legal and Other
Job / Task Environment/ Adverse Effect / of Environmental L1 S1 RFN ** Mitigating Controls L2 S2 RRN * Assessment
Type Requirements Reference
Property at Risk Impact
Environmental Aspect

Sea Condition / wave & wind speed


EL -
S -
E -
Riggers, Crew Worst sailing condition, Damage or total loss
Sailing Of Accurate weather forecast & 24 hours monitoring for
on Vessel. Exceeded Horizontal and of vessels, Injuries to 2 4 8 1 4 4 - -
Vessels weather warnings, Experienced barge
Others vessels. vertical traverse force. crew
A superintendent and supervisors, to stop operation
and relocate vessels to safe waters ahead of weather
front.
P All required PPE.
Communication
EL -
S -
System of communication between bridge where the
master and winch operator and anchor handling deck
E
and Anchor handling associated vessels must be in
Results in cross place and fully tested prior to start of operation
Internal All crew on Communication System failure / traffic, Assets
3 3 9 2 2 4 - -
Communication board Communication device failure. damage and May The best means of communications VHF and
result in injuries. loudspeakers, both systems should be operational
A and it should be thoroughly tested prior to starting the
operation. Additional accessories like charged
batteries and chargers must be kept in stocks..

Hard Hat, Safety Shoes, Coveralls, Goggle, Hand


P
gloves, Work Vest.
Loading and Unloading of Anchors from barge deck to tug boats.
EL -

S -
E -
Lifting of Riggers, Skilled Injuries to the All rigging gear used must be tested and should have
Rigging failure, Slings damage. 3 4 12 1 4 4 - -
anchors labors. workers. SWL correctly marked. Experienced riggers shall be
A
deployed for the work. Pre start briefing must be done
before the start of work.
Hard Hat, Safety Shoes, Coveralls, Goggle, Hand
P
gloves, Work Vest.

Apr 2010 Page 1 of 3 LIL-HSEFM-001A(03)


EL -
S -
Tag line must be used to avoid abrupt swinging, The
E
tug boat must be placed properly beside the barge.
Damage to tug boat,
Placing of
Riggers, Skilled Sudden drop of anchor, Sudden anchors also to the The lifting must be carried out as per procedure at
anchors on tug 2 4 8 1 4 4 - -
labors. Swing of anchors. crane. Personnel safe / efficient speed. All personnel involved, riggers,
boat
Injury A crane operators, masters must be experienced, fully
trained, and competent. weather conditions prevailing
and forecast must be considered.

Hard Hat, Safety Shoes, Coveralls, Goggle, Hand


P
gloves, Work Vest.
EL -
S -

Work should be carried out in protected work area.


E
Disconnecting Man overboard and Safety harness must be worn where required.
Riggers Slip, trip, fall 3 3 9 1 3 3 - -
the crane line injuries. All personnel involved must be qualified and
A experienced, pre start meetings to be conducted., the
walkways must be kept clear.
Hard Hat, Safety Shoes, Coveralls, Goggle, Hand
P
gloves, Work Vest.
EL -
S -

Proper surveying must be carried out before lowering


E
Assets damage, the anchors to locate existing pipelines.
Anchor lowering Tug boat crew Damage to existing pipeline. water pollution, oil 3 3 9 1 3 3 - -
spillage. The anchors must be lowered slowly, Pre work tool
A box talk to be carried out, proper communication
between surveyor and tug boats must be established.
Hard Hat, Safety Shoes, Coveralls, Goggle, Hand
P
gloves, Work Vest.

EL -

S -
Only tested and certified anchor wire must be used,
Tug boat crew Preprty damage, E
Anchor lowering Breaking of anchor cable 3 3 9 load on anchor wire must be monitored all time. 1 3 3 - -
& crew on deck injuries to workers.
Proper regular inspection of anchore wire, pre start
A
meetings, tool box talks to be conducted.

Hard Hat, Safety Shoes, Coveralls, Goggle, Hand


P
gloves, Work Vest.
EL -
S -
E -
Disconnecting High twisted stress on the line
anchor line (or Workers may cause injury when opening Injuries to workers 3 3 9 Only experienced, qualified worker to be used. 1 3 3 - -
insert line) the link. A Detailed pre work briefing to be conducted.
Remain in protected bulwark area.
Hard Hat, Safety Shoes, Coveralls, Goggle, Hand
P
gloves, Work Vest.

Apr 2010 Page 2 of 3 LIL-HSEFM-001A(03)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

Appendix 2 – Inspection and Test Plan


Doc. No. Title
Inspection and Test Plan For PLEM
S393-SPM-LOPL-QAM-ITP-2301
Installation

Mar 2012 Page 22 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
INSPECTION TEST PLAN
PLEM INSTALLATION

CONTENTS
1 Definitions................................................................................................................................. 3
2 Inspection Test Plan Matrix.................................................................................................. 4
3 Project Standard Forms (PSF)............................................................................................. 6

MAR 2012 Page 2 of 6 S393-PL-LOPL-QAM-ITP-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
INSPECTION TEST PLAN
PLEM INSTALLATION

1 Definitions

Inspection Legend Remarks


Description
Perform P The party which performs the activity

Witness W indicates that the party shall be invited to inspect an


activity, but production need not stop due to non-
attendance

Random Witness RW indicates that the party shall choose to witness the
activity randomly when in process, but production need
not stop due to non-attendance

Monitor M indicates random attendances or non intrusive


inspection surveillance during normal process activities

Hold H a point where no further production shall take place


until an inspection has been carried out by the parties
nominated in the ITP

Review R indicates review / endorse of records by the nominated


party

MAR 2012 Page 3 of 6 S393-PL-LOPL-QAM-ITP-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
INSPECTION AND TEST PLAN
PLEM INSTALLATION
2 Inspection Test Plan Matrix

Inspection Requirement/
Op. Description of Operation/ Acceptance Sign Off
Control Procedure Record Generated Frequency
No. Inspection or Test Criteria Employer -
LOPL TPCA
TPA
Related
Documentation, All drawings and Drawing and Document
1. N/A 100 % documents P&H R M
procedures to be IFC and latest Rev register
approved
All materials conform to Specifications and Material certification, DNV inspection
2. S393-QAM-FRM-053 100 % R R M
Approved Client Approvals release note
Approved
Ensure PLEM Dimensions/Visual Approved Drawing S393- Drawing S393-
3. Inspection for welds and compliance, SPM-SBM-ENG-DWG- S393-QAM-FRM-053 100 % SPM-SBM- W W M
damages and any non conformance 2054 ENG-DWG-
2054
Approved Drawing S393-
Check & Ensure PLEM Cathodic SPM-SBM-ENG-DWG-
4. Protection anodes are installed accordingly 2047 & PLEM GA S393- S393-QAM-FRM-053 100 % No Damage P W M
SPM-SBM-ENG-DWG-
2054
Ensure all test records are filled in, fully Hydrotest
5. signed and accepted by Client/TPI PLEM Specifications Acceptance 100 % N/A R R M
Certificate
Carry out seabed debris survey prior to Approved MS S393-SPM- Diver’s Inspection No adverse
6. Installation of PLEM 100 % R R M
OPR-MS-2301 Report conditions
Approved MS S393-SPM-
7. PLEM Lowering N/A 100 % Approved MS RW RW W
OPR-MS-2301
Approved MS S393-SPM- Tolerance of +
8. Survey Set Out / PLEM Coordinates OPR-MS-2301 S393-QAM-FRM-124 100 % R R W
1.5 m
Approved MS S393-SPM- Tolerance of +
9. Check PLEM Heading S393-QAM-FRM-124 100 % W R W
OPR-MS-2301 20
Approved MS S393-SPM- Tolerance of +
10. Check PLEM Tilt S393-QAM-FRM-124 100 % R R W
OPR-MS-2301 30
MAR 2012 Page 4 of 6 S393-PL-LOPL-QAM-ITP-2301 (0)
TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
INSPECTION AND TEST PLAN
PLEM INSTALLATION
Inspection Requirement/
Op. Description of Operation/ Acceptance Sign Off
Control Procedure Record Generated Frequency
No. Inspection or Test Criteria Employer -
LOPL TPCA
TPA
Verification of Diver’s Inspection and As- Approved MS S393-SPM- Diver’s Inspection
11. 100 % N/A R R R
Built Report (including Video) OPR-MS-2301 Report and Video

MAR 2012 Page 5 of 6 S393-PL-LOPL-QAM-ITP-2301 (0)


TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
INSPECTION AND TEST PLAN
PLEM INSTALLATION

3 Project Standard Forms (PSF)

Document No Description
S393-QAM-FRM-053 PLEM Receipt Inspection Report
S393-QAM-FRM-124 PLEM Installation Report

MAR 2012 Page 6 of 6 S393-PL-LOPL-QAM-ITP-2301 (0)


REPORT NO

LEIGHTON OFFSHORE PTE LTD DATE

SHIFT
PLEM RECEIPT INSPECTION REPORT
PAGE NO.

PROJECT: TANZANIA SPM & PIPELINES REPLACEMENT


MATERIAL DESCRIPTION:
EPC
CLIENT: TANZANIA PORT AUTHORITY SIZE:
SUPPLIER: QUANTITY:
P.O. NO.: MRR NO.:
DELIVERY DATE: NOTE NO.:

PRE INSTALLATION INSPECTION


Remarks(attach damage reports if
Description Certification Remarks
required)
Visual Certificate of Origin
Paint/Coating Certificate of Conformity
Mechanical Inspection Release Cert.
Electrical Shipping List / Bill Of Landing
Functional Test Certification

IDENTIFICATION
Description Remarks Description Remarks
I/D Nos. Manufacturer’s Marks
Other Certifying Body Stamps

DAMAGE/REPAIRS
1. Description of Damages/Repairs. Attach Repair reports and
2.Sketch of damages (Photograph if required)
approvals as applicable

The material above has been inspected and judged to be (tick one)
Attach the following reports as applicable
Result of Receiving Inspection
Receiving Ins. Report. USOD Report Material Damage NCR
Approved in full for Installation N/A N/A N/A N/A
Approved but requires minor repair
Damaged/Major repair required
Rejected

RECEIVED BY - LOPL STORES VERIFIED BY - LOPL TPCA - DNV EMPLOYER - TPA


Name

Signature

Date

S393-QAM-FRM-053 (0)
Report No :
LEIGHTON OFFSHORE PTE LTD
Date :
PLEM INSTALLATION REPORT
Shift :

Page No:

Project :- TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT Contract No. :- S393

Location :-

MAIN LINE VALVE STATUS (@PLEM)


VALVE TAG VALVE SIZE PRODUCT POSITION ACTUAL
U64-BL01-01-0001 20” Crude HALF OPEN
U64-BL03-01-0001 2” Crude HALF OPEN
U64-BL02-01-0001 20” White Line HALF OPEN
U64-BL03-01-0002 2” White Line HALF OPEN

HYDRAULIC ACTUTAOR VALVE STATUS (@ PLEM)

VALVE TAG VALVE SIZE PRODUCT POSITION ACTUAL


U19-BL01-01-0001 1/2” Crude OPEN
U19-BL01-01-0002 1/2” Crude OPEN
U19-BL01-01-0003 1/2” Crude CLOSE
U19-BL02-01-0001 1/2” White Line OPEN
U19-BL02-01-0002 1/2” White Line OPEN
U19-BL02-01-0003 1/2” White Line CLOSE

FINAL POSITION
POSITION (CENTRE)
NORTHING EASTING
PLEM CENTER
TARGET 9 246 742.00 m 541 526.00 m
AS-BUILT
DELTA (Δ)

SET DOWN REPORT

TOLERANCE ACTUAL
PLEM Position Circle 1.5mtr
(radius)
PLEM Heading ± 3 deg
PLEM Tilt ± 2 deg
Skirt Penetration 1.5mtr

LEIGHTON TPI (DNV / GLM) EMPLOYER - TPA

Name :

Signature :

Date :

S393-QAM-FRM-124 (0)
TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

12.3 Appendix 3 – Drawings and Sketches


Drawing No. Title
S393-PL-LYE-ENG-DWG-1002 Overall Pipeline Schematic
S393-PL-LYE-ENG-DWG-1003 Overall Pipeline Route Layout
S393-PL-LYE-ENG-DWG-1011 Pipeline Spool Tie In Details at PLEM
S393-SPM-SBM-ENG-DWG-2001 CALM Buoy - General - Field Layout
S393-SPM-SBM-ENG-DWG-2041 PLEM - Structure - General Arrangement

S393-SPM-SBM-ENG-DWG-2042 PLEM - Structure - Detail Sheet 1

S393-SPM-SBM-ENG-DWG-2043 PLEM - Structure - Detail Sheet 2

S393-SPM-SBM-ENG-DWG-2045 PLEM - Piping - General Arrangement

S393-SPM-SBM-ENG-DWG-2046 PLEM - Piping – Isometric

S393-SPM-SBM-ENG-DWG-2047 PLEM - Cathodic Protection Design – Detail

PLEM - Valves Actuation Controls Interface -


S393-SPM-SBM-ENG-DWG-2048
General Arrangement

PLEM - Valves Actuation Controls Interface


S393-SPM-SBM-ENG-DWG-2050
– Detail

S393-SPM-SBM-ENG-DWG-2053 PLEM - Structure – Protection Cage

S393-SPM-SBM-ENG-DWG-2054 PLEM - General – Arrangement

S393-SPM-SBM-ENG-DWG-2055 PLEM - Lifting - General Arrangement

S393-SPM-SBM-ENG-DWG-2056 PLEM - Piping - Support

S393-SPM-SBM-ENG-DWG-2057 PLEM - Spool Piece

CALM Buoy System – Hydraulic System –


S393-SPM-SBM-ENG-DWG-2172
Interface Diagram

S393-SPM-LOPL-OPR-DWG-2351 PLEM Installation Methodology

S393-SPM- LOPL-OPR-DWG-2367 PLEM Installation Anchor Pattern

S393-SPM- LOPL-OPR-DWG-2368 PLEM Set Down Position

Mar 2012 Page 19 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


OFFICIAL COPY - SO18021 - DUM86023A2 - S393-SPM-SBM-ENG-DWG-2001 - - PDF Generated on 09-Nov-2011 5:14PM

TANZANIA SPM & PIPELINES


REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393

ISSUED FOR CLIENT REVIEW

ISSUED FOR APPROVAL

APPROVED

FOR INFORMATION ONLY


Checked By : NS

Approved By : JG
OFFICIAL COPY - SO18021 - DSM84001A1 - S393-SPM-SBM-ENG-DWG-2041 - - PDF Generated on 22-Nov-2011 10:37AM

TANZANIA SPM & PIPELINES


REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393

ISSUED FOR CLIENT REVIEW

ISSUED FOR APPROVAL

APPROVED

FOR INFORMATION ONLY


Checked By : NS

Approved By : JG
OFFICIAL COPY - SO18021 - DSM84002A1 - S393-SPM-SBM-ENG-DWG-2042 - - PDF Generated on 22-Nov-2011 10:39AM

TANZANIA SPM & PIPELINES


REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393

ISSUED FOR CLIENT REVIEW

ISSUED FOR APPROVAL

APPROVED

FOR INFORMATION ONLY


Checked By : NS

Approved By : JG
OFFICIAL COPY - SO18021 - DSM84003A1 - S393-SPM-SBM-ENG-DWG-2043 - - PDF Generated on 22-Nov-2011 10:28AM

TANZANIA SPM & PIPELINES


REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393

ISSUED FOR CLIENT REVIEW

ISSUED FOR APPROVAL

APPROVED

FOR INFORMATION ONLY


Checked By : NS

Approved By : JG
OFFICIAL COPY - SO18021 - DPM84007A1 - S393-SPM-SBM-ENG-DWG-2045 - - PDF Generated on 29-Nov-2011 4:14PM

TANZANIA SPM & PIPELINES


REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393

ISSUED FOR CLIENT REVIEW

ISSUED FOR APPROVAL

APPROVED

FOR INFORMATION ONLY


Checked By : NS

Approved By : JG
OFFICIAL COPY - SO18021 - DPM84008A1 - S393-SPM-SBM-ENG-DWG-2046 - - PDF Generated on 29-Nov-2011 4:53PM

TANZANIA SPM & PIPELINES


REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393

ISSUED FOR CLIENT REVIEW

ISSUED FOR APPROVAL

APPROVED

FOR INFORMATION ONLY


Checked By : NS

Approved By : JG
OFFICIAL COPY - SO18021 - DSM06003A1 - S393-SPM-SBM-ENG-DWG-2047 - - PDF Generated on 14-Nov-2011 1:36PM

TANZANIA SPM & PIPELINES


REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393

ISSUED FOR CLIENT REVIEW

ISSUED FOR APPROVAL

APPROVED

FOR INFORMATION ONLY


Checked By : NS

Approved By : JG
OFFICIAL COPY - SO18021 - DMM19002A1 - S393-SPM-SBM-ENG-DWG-2048 - - PDF Generated on 24-Nov-2011 8:55AM

TANZANIA SPM & PIPELINES


REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393

ISSUED FOR CLIENT REVIEW

ISSUED FOR APPROVAL

APPROVED

FOR INFORMATION ONLY


Checked By : NS

Approved By : JG
TANZANIA SPM & PIPELINES
REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393

ISSUED FOR CLIENT REVIEW

ISSUED FOR APPROVAL

APPROVED

FOR INFORMATION ONLY


Checked By : NS

Approved By : JG
OFFICIAL COPY - SO18021 - DSM84005V1 - S393-SPM-SBM-ENG-DWG-2053 - - PDF Generated on 05-Oct-2011 2:10PM

TANZANIA SPM & PIPELINES


REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393

ISSUED FOR CLIENT REVIEW

ISSUED FOR APPROVAL

APPROVED

FOR INFORMATION ONLY


Checked By : NS

Approved By : JG
OFFICIAL COPY - SO18021 - DSM84000A1 - S393-SPM-SBM-ENG-DWG-2054 - - PDF Generated on 24-Nov-2011 8:46AM

TANZANIA SPM & PIPELINES


REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393

ISSUED FOR CLIENT REVIEW

ISSUED FOR APPROVAL

APPROVED

FOR INFORMATION ONLY


Checked By : NS

Approved By : JG
OFFICIAL COPY - SO18021 - DSM84006A1 - S393-SPM-SBM-ENG-DWG-2055 - - PDF Generated on 22-Nov-2011 10:35AM

TANZANIA SPM & PIPELINES


REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393

ISSUED FOR CLIENT REVIEW

ISSUED FOR APPROVAL

APPROVED

FOR INFORMATION ONLY


Checked By : NS

Approved By : JG
OFFICIAL COPY - SO18021 - DPM84009A1 - S393-SPM-SBM-ENG-DWG-2056 - - PDF Generated on 08-Nov-2011 11:42AM

TANZANIA SPM & PIPELINES


REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393

ISSUED FOR CLIENT REVIEW

ISSUED FOR APPROVAL

APPROVED

FOR INFORMATION ONLY


Checked By : NS

Approved By : JG
OFFICIAL COPY - SO18021 - DPM84010V1 - - - PDF Generated on 21-Dec-2011 5:43PM

TANZANIA SPM & PIPELINES


REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393

ISSUED FOR CLIENT REVIEW

ISSUED FOR APPROVAL

APPROVED

FOR INFORMATION ONLY


Checked By : NS

Approved By : JG

S393-SPM-SBM-ENG-DWG-2057
OFFICIAL COPY - SO18021 - DMM19004A2 - S393-SPM-SBM-ENG-DWG-2172-00 - - PDF Generated on 08-Feb-2012 11:13AM

TANZANIA SPM & PIPELINES


REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393

ISSUED FOR CLIENT REVIEW

ISSUED FOR APPROVAL

APPROVED

FOR INFORMATION ONLY


Checked By : NS

Approved By : JG
ANNEXE - PDF Generated on 08-Feb-2012 11:14AM

TANZANIA SPM & PIPELINES


REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393

ISSUED FOR CLIENT REVIEW

ISSUED FOR APPROVAL

APPROVED

FOR INFORMATION ONLY


Checked By : NS

Approved By : JG
ANNEXE - PDF Generated on 08-Feb-2012 11:16AM

TANZANIA SPM & PIPELINES


REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393

ISSUED FOR CLIENT REVIEW

ISSUED FOR APPROVAL

APPROVED

FOR INFORMATION ONLY


Checked By : NS

Approved By : JG
STEP 1 STEP 2
1. SET UP STEALTH & PLEM BARGE ON PROPOSED LOCATION. 1. RIG AND CONNECT 2 Nos 10T AIR TUGGER WIRE FROM STEALTH DECK TO EACH END OF THE PLEM.
2. SURVEY PROPOSED PLEM LOCATION BY DIVERS. 2. CUT SEA FASTENING AND LIFT PLEM OF THE BARGE.
3. INSPECT PLEM AND COMMENCE INSTALLING INSTALLATION AIDS I.E. USBL BEACONS, RIGGING, GYRO ETC. 3. LOWER PLEM TO 5m ABOVE SEABED USING USBL BEACON AND / OR GYRO AND DIVER SUPPORT.

P2
PROPOSED
PLEM CENTER
541 526.00 mE
9 246742.00 mN

P1
PICK-UP INSTALLATION MIN. RADIUS =8m
RADIUS = 13 m MAX. LIFT = 93.7 T (80 T Block)
MAX. LIFT = 66 T (80 T Block) MAX. HEAD BOOM = 34.2 m (80 T Block) 49
°
MAX. HEAD BOOM = 32.2 m (80 T Block) (*) OFFSHORE RATED LOAD
(*) OFFSHORE RATED LOAD

18
°
BOOM LGTH. INSTALLATION
39.6 m CRANE

CRANE STEALTH
LCT-KESTREL BLOCK

43°
73°
P3

S1
PLEM WEIGHT IN AIR = 56.7 Te

20 m
1.5 m
LCT-KESTREL
FE
ND
ER
ING S2

E
LIN
72°

PREVAILING WEATHER
IPE
DP
O SE
OP
PR 1m
P4

SW
OM

FROM SOUTH
FR

PLEM PROPOSED LOCATION


19°

SEABED (LAT) -25.5m

MAX. RADIUS = 36 m
MAX. LIFT = 17.2 T (80 T Block)
S4 MAX. HEAD BOOM = 14.2 m (80 T Block)

(*) OFFSHORE RATED LOAD


S3

46
°

PLAN VIEW

TANZANIA SPM AND PIPELINES REPLACEMENT EPC PROJECT


TANZANIA PORTS AUTHORITY

Worley Parsons Group CDa

MAl
S393
NSa

KKa/LMa PLEM INSTALLATION METHODOLOGY


N.T.S

03-03-2012 A3 S393-SPM-LOPL-OPR-DWG-2351 1 OF 2 0
STEP 3
1. ORIENTATE PLEM VIA CRANE MOVEMENT AND 2 Nos 10T AIR TUGGER WIRE.
2. CONFIRM ALIGNMENT AND ORIENTATION OF PLEM OVER TARGET LOCATION USING USBL BEACON GYRO AND DIVERS ASSISTANCE.
3. CONFIRM PLEM LEVELING. SLOWLY LOWER PLEM WITH GUIDANCE FROM DIVERS .
4. LAND PLEM ON SEABED.
5. TAKE A SURVEY FIX ON EACH CORNER USING DIVER HANDHELD USBL BEACON.
6. DISCONNECT RIGGING WITH DIVERS AND RECOVER TO SURFACE.

INSTALLATION
INSTALLATION CRANE
CRANE 39.6m BOOM LGTH.
39.6m BOOM LGTH.

STEALTH STEALTH

CRANE
BLOCK

DIVER

PLEM PROPOSED LOCATION


PLEM
5m

PROPOSED TIE-IN
SPOOL POSITION
PIPELINE END
SEABED (LAT) -25.5m SEABED (LAT) -25.5m

ELEVATION LOOK'NG FORWARD SIDE ELEVATION

TANZANIA SPM AND PIPELINES REPLACEMENT EPC PROJECT


TANZANIA PORTS AUTHORITY

Worley Parsons Group CDa

MAl
S393
NSa

KKa/LMa PLEM INSTALLATION METHODOLOGY


N.T.S

03-03-2012 A3 S393-SPM-LOPL-OPR-DWG-2351 2 OF 2 0
NOTES:
1. ALL DIMENSION ARE IN METERS UNLESS NOTED OTHERWISE.
2. GEODETIC PARAMETERS

N DATUM : WGS 84
ELLIPSOID : WGS 84
9 247 500 mN
PROJECTION : UNIVERSAL TRANSVERSE MERCATOR
P2 CENTRAL MERIDIAN : 39° EAST (UTM ZONE 37)
UNITS : METRES
3. TWIN PIPELINES & TIE-IN SPOOL ARE OMITTED FOR CLARITY
IN DRAWING.
4. CHAIN LENGTH = 330m
5. CD = CHART DATUM

P1
LEGEND:
9 247 250 mN

P3 = EXISTING ANCHOR

PROPOSED
BUOY/PLEM CENTER = PROPOSED BUOY/PLEM CENTRE
541 526.00 mE
9 246742.00 mN
= EXISTING BUOY/PLEM CENTRE

700 m

m
P S = PORT & STBD SIDE ANCHORAGE

0
70
9 247 000 mN A3
70
A2 0
m

49
.0
18

°
KP

.0
3.6 ANCHOR COORDINATES 1st POSITION (START-UP)

°
LCT-KESTREL
ANCHOR COORDINATES HORZ. DIST. WATER DEPTH
EXISTING NO. EASTING (m) NORTHING (m) (m) (m)
SPM
P1 542076.12 9 247282.55 700 25.5
540 751.292 mE

43.0°
9 246698.667 mN P2 541740.85 9 247455.86 700 27.0
A1
9 246 750 mN 72.0° P3 541003.48 9 247203.80 700 26.4
P4 540970.86 9 246628.78 550 23.6
53

73.0°
1 A4 S1 542291.04 9 246578.80 700 22.2
EXISTING ANCHOR
550 m S2 542114.59 9 246258.53 700 23.4
700 m
S3 541349.67 9 246023.52 700 21.4
S4 540954.16 9 246296.08 700 22.0
19.0

PIPELAY BARGE
KP (STBD SIDE)
3.0 P4
°

S1
6.0
°

70
9 246 500 mN 0
0m m
NG 70
TI E
IS LIN A5 46
EX IPE .0
P °
700 m

A6
13
5

ED
OS
OP INE
11

PR IPEL
0

S4
9 246 250 mN
S2

9 246 000 mN
S3
540 500 mE

540 750 mE

541 000 mE

541 250 mE

541 500 mE

541 750 mE

542 000 mE

542 250 mE

542 500 mE
TANZANIA SPM AND PIPELINES REPLACEMENT EPC PROJECT
TANZANIA PORTS AUTHORITY

Worley Parsons Group CDa

MAl
S393
NSa

KKa/LMa
PLEM INSTALLATION
ANCHOR PATTERN
N.T.S

03-03-2012 A3 S393-SPM-LOPL-OPR-DWG-2367 1 OF 1 0
NOTES:
1. ALL DIMENSIONS ARE IN METRES UNLESS NOTED OTHERWISE.

TRUE PLEM CENTER


TARGET BUOY CENTER

541520.899 E 541528.317 E
9246743.407 N 9246747.557 N

DESCRIPTION EASTING NORTHING

PROPOSED SPM / PLEM CENTER 541 526.000 9246 742.000


TARGET BUOY CENTER 541 526.000 9246 742.000
TRUE PLEM CENTER 541 526.683 9246 741.773
PROPOSED SPM/PLEM CENTER C.O.G OF PLEM 541 526.799 9246 741.792

DESCRIPTION 'X' (m) 'Y' (m)

PROPOSED SPM / PLEM CENTER 3.764 4.782

PLEM C.O.G TARGET BUOY CENTER 3.764 4.782


TRUE PLEM CENTER 4.250 4.250
C.O.G OF PLEM 4.360 4.210

X
(X=0.000, Y=0.000)

541525.050 E 541532.468 E
9246735.989 N 9246740.140 N

TANZANIA SPM AND PIPELINES REPLACEMENT EPC PROJECT


TANZANIA PORTS AUTHORITY

Worley Parsons Group CDa


Tanzania Port Authority

MAl
S393
NSa

LMa PLEM SET DOWN POSITION


N.T.S

04-03-2012 A3 S393-SPM-LOPL-OPR-DWG-2368 1 OF 1 0
TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation

Appendix 4 – Data Sheets and Other Supporting Documents


Doc. No. Title
n/a Work Barge Stealth Specification Sheet
n/a Flat Top Barge Specification Sheet
Work Barge Stealth Crawler Crane Load
n/a
Chart
n/a IXSEA Octans 3000 Manuals and Guidelines

Mar 2012 Page 24 of 24 S393-SPM-LOPL-OPR-MS-2301 (0)


Leighton Stealth – Pipelay Barge

GENERAL
ABS + A1 Accommodation/ Work Barge,
Class
Helideck
Flag Singapore
Port of Register Singapore
Year of Built 2006
Special Purpose Ship Safety (SPS)
Additional Compliance CAP 437 Helideck
MODU CODE
DIMENSIONS
LOA 100m (330 ft)
Breadth 30m (100ft)
Depth 6m (20 ft)
Draft (Minimum) 2.8m
Draft (Maximum) 4.5m
Deck Loading Capacity 15MT/m2

Page 1 of 7 Oct 2011


Leighton Stealth – Pipelay Barge

MOORING SYSTEM
Mooring Arrangement 9 point mooring system
5 x single drum, 45MT (mid drum) capacity,
Forward Mooring Winches complete with 1200m of 42mm diameter
wire rope.
4 x single drum, 35MT (mid drum) capacity,
Aft Winches complete with 1000m of 42mm diameter
wire rope.
Local and remote control. Electro hydraulic
Winch Control System
system
Fully automatic with payout length and
Tension Monitoring System
tension measurement.
5 off 7MT delta flipper and 4 off 5MT delta
flipper
Anchors 8 x STEVPRIS 8MT
2 x DELTA FLIPPER 11MT
PIPELAY CAPABILITY
Tensioner 2 x 50MT track tensioners
Maximum pipe size 60” OD
Minimum pipe size 8” OD
Fully automatic electro hydraulic with
Control System manual override joystick control, pay in and
pay out.
7 total (1 x fitup plus root and hotpass, 2 x
Work stations fill, 1 x cap, 1 x NDT, 1 x repair and 1 x field
joint coating and strapping).
Fully automatic (manual and semi-auto also
Welding System
possible)
100 MT capacity single drum complete with
Abandonment and Recovery Winch
600m of 64mm diameter wire rope.
1 unit horizontal pipe conveyor, 6 units
longitudinal elevating rollers, 3 units
longitudinal fixed rollers, 1 auxiliary roller
Pipe handling System and 3 stinger rollers. 2 transfer vehicles and
2 line up tables.
Electro hydraulic control system.
Pipe Ramp 2.77 degree inclination.
Stinger Fixed type

Page 2 of 7 Oct 2011


Leighton Stealth – Pipelay Barge

MACHINERY
4 x 1000 kW
1 x 400 kW (Harbor)
Generators
1 x 400 kW (Emergency)
System Voltage: 415V, 3 Phase, 50Hz
Air compressors 4 x 290 cfm
Hamworthy Model ST15 suitable for 240
Sewerage Treatment Plant
persons.
LIFTING DEVICES
2 x 280 MT lift capacity Sumitomo model
SCX2800
Deck mounted cranes
Crawler cranes complete with 45m boom,
main hook, and auxiliary hook and whip line.
4 x 50MT DAVITS (Additional davits
Davits
available)
Lifting capacity 500MT (suitable for lifting
A Frame
subsea structures including PLEMS)
SERVICE TANKS
Fresh Water Storage 1100 m3 (approx)
Marine Diesel Storage 1100 m3 (approx)
Certified tank barge with full ballast system
Ballast
comprising 10 ballastable compartments.
SAFETY EQUIPMENT
COLREGS compliant navigation
Navigation
arrangement
Life Rafts 16 x 25 persons
Life Vests For 264 persons
Life Boats 2 x 116 persons
Rescue Boats 2 x Viking 470 GRP
ACCOMODATION
Suitable for 232 persons in 1,2 & 4 man
Accommodation
cabins.
HELICOPTER FACILITIES
CAP437 compliant helideck.
Suitable for S61 and S92 aircraft
CAP 437 & ABS HELIDK

Page 3 of 7 Oct 2011


Leighton Stealth – Pipelay Barge

Page 4 of 7 Oct 2011


Leighton Stealth – Pipelay Barge

Page 5 of 7 Oct 2011


Leighton Stealth – Pipelay Barge

Page 6 of 7 Oct 2011


Leighton Stealth – Pipelay Barge

Page 7 of 7 Oct 2011


Kenya Marine Contractors
Part of the Comarco Group

Comarco Group Companies


Kenya, Madagascar, Seychelles,
Tanzania, Malaysia, Singapore

Landing craft (double bottom)

Year built : 2006


Flag : Zanzibar
Class : BKI
GRT : 499
Length (o.a.) : 54 m
Beam : 11 m
Depth : 3.6 m
Mean Draft : 2.4 m on 700 tonnes d/w
Dead weight : 1,000T
Deck area : 440m3 (44x10)
Ramp width : 7.0 m
Fuel Capacity : 60 m3
Fresh water cap : 35 m3
Cargo tanks : 945 m3 Epoxy coated
Engines : 3x 350HP Mitsubishi
Max speed : 9 knots

Particulars are believed to be correct but are not guaranteed


NAVAL AFRICA DESIGN CC +27 31 2053747

13 APPLICABLE DRAWINGS
13.1 GENERAL ARRANGEMENT

SUBTECH IMVUBU Pg 15 of 49
SCX2800-2 CRAWLER CRANE RATED LOAD FOR MAIN BOOM - PICK & CARRY EC410033
Unit: ton P.1 / 3
Boom length (m) 18.3 21.3 24.4 27.4 30.5 33.5 36.6 39.6 42.7 45.7 48.8 51.8 Boom length (m)
Reeved lines 18 16 16 14 12 11 10 9 9 8 7 7 Reeved lines
Wind (m/sec) 17 17 14 14 14 14 14 14 11 11 11 11 Wind (m/sec)
Radius (m) Radius (m)
4.8 188.6 5.2m x 4.8
5.0 188.1 167.7t 5.7m x 5.0
5.5 173.3 167.0 167.0t 6.1m x 6.6m x 5.5
6.0 159.6 159.3 159.0 146.7t 125.7t 7.5m x 6.0
7.0 137.6 137.4 137.1 136.8 125.7 115.2 104.8t 8.4m x 8.9m x 7.0
8.0 120.8 120.6 120.4 120.1 120.0 114.7 104.6 93.7 94.3t 83.8t 9.3m x 9.8m x 8.0
9.0 107.6 107.3 107.1 106.8 106.2 103.1 101.3 93.0 94.3 83.8 73.3t 72.3t 9.0
10.0 96.8 96.6 96.3 96.1 93.9 91.3 90.0 87.7 85.4 83.3 73.3 72.2 10.0
12.0 79.3 79.2 79.1 77.7 75.9 74.0 73.4 71.8 70.1 68.6 67.1 65.6 12.0
14.0 63.6 63.5 63.4 63.2 63.2 62.0 61.8 60.4 59.0 57.9 56.8 55.5 14.0
16.0 52.7 52.7 52.6 52.4 52.4 52.2 53.1 52.0 50.9 50.0 49.0 48.0 16.0
18.0 17.6m x 44.7 44.7 44.5 44.4 44.2 45.1 45.0 44.5 43.8 43.0 42.0 18.0
20.0 46.4t 38.8 38.7 38.5 38.4 38.2 39.1 38.9 38.7 38.5 38.1 37.3 20.0
22.0 20.2m x 34.0 33.8 33.7 33.5 34.3 34.1 33.9 33.8 33.6 33.3 22.0
24.0 38.4t 22.8m x 30.0 29.8 29.6 30.5 30.2 30.0 30.0 29.8 29.5 24.0
26.0 32.4t 25.5m x 26.7 26.5 27.3 27.1 26.9 26.7 26.6 26.3 26.0
28.0 27.7t 24.2 23.9 24.6 24.5 24.2 24.2 23.9 23.7 28.0
30.0 28.1m x 21.7 22.5 22.2 21.9 21.8 21.7 21.5 30.0
32.0 24.0t 30.8m x 20.5 20.3 20.0 19.9 19.7 19.5 32.0
34.0 20.9t 33.4m x 18.7 18.4 18.3 18.0 17.8 34.0
36.0 19.4t 17.2 16.9 16.8 16.6 16.3 36.0
38.0 15.6 15.5 15.2 14.9 38.0
40.0 38.7m x 14.4 14.1 13.8 40.0
42.0 15.2t 41.3m x 13.1 12.8 42.0
44.0 13.7t 12.2 11.8 44.0
46.0 11.1 46.0
46.6 10.9 46.6

1.The rated loads are determined according to EN13000 rating on the condition that the machine is stationed on firm, level ground.
2.Be sure to remove the hanger sheaves block from the top boom when boom length is 36.6m or more.
3.To calculate the maximum load that can actually be lifted, deduct weight of all lifting accessories, such as boom hook and jib hook, from figures shown above.
4.Working radius is the horizontal distance from the slewing center to the center of gravity of a lifted load.
5.The counterweight is 120.8 ton. (Superstructure 102.8ton + Undercarriage 18.0 ton )
6.Be sure to fully extend the side frames before operating the machine.
7.Correlation between the number of reeved lines, maximum rated loads, hook weights are shown in the table below.
8.Capacities shown are in metric tons, and are based on 66% of minimum tipping loads with machine standing level on firm supporting surface under ideal job conditions.
9.Travel speed must be less than 0.4km/h and cautiously in order to avoid shock loading.
10.Position the load lower than 500mm (or as lower as possible) above the ground.
11.Position the lifted load in front of the crawler while traveling forward.
12.Engage the slewing lock and apply the slewing brake.

Hook Capacity Hook Weight Maximum rated loads (t)


(t) (t) 18 falls 17 falls 16 falls 15 falls 14 falls 13 falls 12 falls 11 falls 10 falls 9 falls 8 falls 7 falls 6 falls 5 falls 4 falls 3 falls 2 falls 1 falls
275 4.3 243.0 229.5 216.0 202.5 189.0 175.5 162.0 148.5 ― ― ― ― ― ― ― ― ― ―
250 3.7 243.0 229.5 216.0 202.5 189.0 175.5 162.0 148.5 ― ― ― ― ― ― ― ― ― ―
145 3.3 / 2.7 ― ― ― ― ― ― ― ― 145.0 121.5 108.0 94.5 81.0 67.5 54.0 40.5 27.0 ―
80 1.4 ― ― ― ― ― ― ― ― ― ― ― ― 80.0 67.5 54.0 40.5 27.0 ―
35 0.9 ― ― ― ― ― ― ― ― ― ― ― ― ― ― ― 35.0 27.0 ―
13.5 0.6 ― ― ― ― ― ― ― ― ― ― ― ― ― ― ― ― ― 13.5
SCX2800-2 CRAWLER CRANE RATED LOAD FOR MAIN BOOM WITH SHORT JIB - PICK & CARRY EC410033
Unit: ton P.2 / 3
Boom length (m) 18.3 21.3 24.4 27.4 30.5 33.5 36.6 39.6 42.7 45.7 48.8 51.8 Boom length (m)
Reeved lines 18 16 16 14 12 11 10 9 9 8 7 7 Reeved lines
Wind (m/sec) 17 17 14 14 14 14 14 14 11 11 11 11 Wind (m/sec)
Radius (m) Radius (m)
4.8 188.1 5.2m x 4.8
5.0 187.7 167.2t 5.7m x 5.0
5.5 172.9 166.5 166.6t 6.1m x 6.6m x 5.5
6.0 159.1 158.9 158.6 146.2t 125.3t 7.5m x 6.0
7.0 137.1 136.9 136.6 136.4 125.3 114.8 104.3t 8.4m x 8.9m x 7.0
8.0 120.4 120.1 119.9 119.7 119.5 114.2 104.1 93.3 93.8t 83.3t 9.3m x 9.8m x 8.0
9.0 107.1 106.9 106.6 106.3 105.7 102.6 100.8 92.5 93.8 83.3 72.9t 71.8t 9.0
10.0 96.4 96.1 95.8 95.7 93.4 90.8 89.5 87.2 84.9 82.9 72.9 71.7 10.0
12.0 78.8 78.8 78.7 77.2 75.4 73.6 72.9 71.3 69.6 68.1 66.6 65.1 12.0
14.0 63.1 63.1 62.9 62.8 62.8 61.5 61.3 60.0 58.6 57.5 56.3 55.1 14.0
16.0 52.3 52.2 52.1 52.0 51.9 51.7 52.6 51.5 50.4 49.6 48.6 47.5 16.0
18.0 17.6m x 44.3 44.2 44.0 44.0 43.7 44.7 44.5 44.0 43.4 42.5 41.6 18.0
20.0 45.9t 38.3 38.2 38.1 37.9 37.8 38.6 38.5 38.2 38.1 37.6 36.8 20.0
22.0 20.2m x 33.6 33.3 33.3 33.0 33.8 33.6 33.4 33.3 33.2 32.9 22.0
24.0 37.9t 22.8m x 29.5 29.4 29.1 30.0 29.8 29.5 29.5 29.3 29.1 24.0
26.0 31.9t 25.5m x 26.3 26.0 26.8 26.7 26.4 26.3 26.1 25.9 26.0
28.0 27.2t 23.7 23.4 24.2 24.0 23.7 23.7 23.5 23.2 28.0
30.0 28.1m x 21.2 22.0 21.8 21.5 21.4 21.2 21.0 30.0
32.0 23.6t 30.8m x 20.1 19.8 19.5 19.4 19.3 19.0 32.0
34.0 20.4t 33.4m x 18.2 17.9 17.8 17.6 17.3 34.0
36.0 18.9t 16.7 16.4 16.3 16.1 15.9 36.0
38.0 15.2 15.0 14.8 14.5 38.0
40.0 38.7m x 13.9 13.6 13.3 40.0
42.0 14.8t 41.3m x 12.6 12.4 42.0
44.0 13.2t 11.8 11.4 44.0
46.0 10.6 46.0
46.6 10.4 46.6

1.The rated loads are determined according to EN13000 rating on the condition that the machine is stationed on firm, level ground.
2.Be sure to remove the hanger sheaves block from the top boom when boom length is 36.6m or more.
3.To calculate the maximum load that can actually be lifted, deduct weight of all lifting accessories, such as boom hook and jib hook, from figures shown above.
4.Working radius is the horizontal distance from the slewing center to the center of gravity of a lifted load.
5.The counterweight is 120.8 ton. (Superstructure 102.8ton + Undercarriage 18.0 ton )
6.Be sure to fully extend the side frames before operating the machine.
7.Correlation between the number of reeved lines, maximum rated loads, hook weights are shown in the table below.
8.Capacities shown are in metric tons, and are based on 66% of minimum tipping loads with machine standing level on firm supporting surface under ideal job conditions.
9.Travel speed must be less than 0.4km/h and cautiously in order to avoid shock loading.
10.Position the load lower than 500mm (or as lower as possible) above the ground.
11.Position the lifted load in front of the crawler while traveling forward.
12.Engage the slewing lock and apply the slewing brake.

Hook Capacity Hook Weight Maximum rated loads (t)


(t) (t) 18 falls 17 falls 16 falls 15 falls 14 falls 13 falls 12 falls 11 falls 10 falls 9 falls 8 falls 7 falls 6 falls 5 falls 4 falls 3 falls 2 falls 1 falls
275 4.3 243.0 229.5 216.0 202.5 189.0 175.5 162.0 148.5 ― ― ― ― ― ― ― ― ― ―
250 3.7 243.0 229.5 216.0 202.5 189.0 175.5 162.0 148.5 ― ― ― ― ― ― ― ― ― ―
145 3.3 / 2.7 ― ― ― ― ― ― ― ― 145.0 121.5 108.0 94.5 81.0 67.5 54.0 40.5 27.0 ―
80 1.4 ― ― ― ― ― ― ― ― ― ― ― ― 80.0 67.5 54.0 40.5 27.0 ―
35 0.9 ― ― ― ― ― ― ― ― ― ― ― ― ― ― ― 35.0 27.0 ―
13.5 0.6 ― ― ― ― ― ― ― ― ― ― ― ― ― ― ― ― ― 13.5
SCX2800-2 CRAWLER CRANE RATED LOAD FOR SHORT JIB - PICK & CARRY EC410033
Unit: ton P.3 / 3
Boom length (m) 18.3 21.3 24.4 27.4 30.5 33.5 36.6 39.6 42.7 45.7 48.8 51.8 Boom length (m)
Reeved lines 1 1 1 1 1 1 1 1 1 1 1 1 Reeved lines
Wind (m/sec) 17 17 14 14 14 14 14 14 11 11 11 11 Wind (m/sec)
Radius (m) Radius (m)
5.6 10.4 6.1m x 6.5m x 5.6
6.0 10.4 10.4t 10.4t 7.4m x 7.9m x 6.0
7.0 10.4 10.4 10.4 10.4 10.4t 10.4t 8.3m x 8.8m x 7.0
8.0 10.4 10.4 10.4 10.4 10.4 10.4 10.4t 10.4t 9.2m x 9.7m x 8.0
9.0 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4t 10.4t 10.1m x 10.6m x 9.0
10.0 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4t 10.4t 10.0
12.0 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 12.0
14.0 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 14.0
16.0 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 16.0
18.0 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 18.0
20.0 18.8m x 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 20.0
22.0 10.4t 21.5m x 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 22.0
24.0 10.4t 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 24.0
26.0 24.1m x 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 26.0
28.0 10.4t 26.8m x 10.4 10.4 10.4 10.4 10.4 10.4 10.4 10.4 28.0
30.0 10.4t 29.4m x 10.4 10.4 10.4 10.4 10.4 10.4 10.4 30.0
32.0 10.4t 10.4 10.4 10.4 10.4 10.4 10.4 10.4 32.0
34.0 10.4 10.4 10.4 10.4 10.4 10.4 34.0
36.0 34.7m x 10.4 10.4 10.4 10.4 10.4 36.0
38.0 10.4t 37.3m x 10.4 10.4 10.4 10.4 38.0
40.0 10.4t 10.4 10.4 10.4 10.4 40.0
42.0 10.4 10.4 10.4 42.0
44.0 42.6m x 10.4 10.4 44.0
46.0 10.4t 45.2m x 10.4 46.0
47.9 10.4t 10.1 47.9

1.The rated loads are determined according to EN13000 rating on the condition that the machine is stationed on firm, level ground.
2.Be sure to remove the hanger sheaves block from the top boom when boom length is 36.6m or more.
3.To calculate the maximum load that can actually be lifted, deduct weight of all lifting accessories, such as boom hook and jib hook, from figures shown above.
4.Working radius is the horizontal distance from the slewing center to the center of gravity of a lifted load.
5.The counterweight is 120.8 ton. (Superstructure 102.8ton + Undercarriage 18.0 ton )
6.Be sure to fully extend the side frames before operating the machine.
7.Capacities shown are in metric tons, and are based on 66% of minimum tipping loads with machine standing level on firm supporting surface under ideal job conditions.
8.Travel speed must be less than 0.4km/h and cautiously in order to avoid shock loading.
9.Position the load lower than 500mm (or as lower as possible) above the ground.
10.Position the lifted load in front of the crawler while traveling forward.
11.Engage the slewing lock and apply the slewing brake.

Hook Capacity Hook Weight


(t) (t)
275 4.3
250 3.7
145 3.3 / 2.7
80 1.4
35 0.9
13.5 0.6
Document N° : MU/3464/EGF/001

OCTANS

Subsea Unit
Models 3000 TI

User’s guide

February 2002
iXSEA Document n° : MU/3453/EGF/001

TABLE OF CONTENTS

RIGHTS......................................................................................................5
WARRANTY .............................................................................................6
CUSTOMER SUPPORT............................................................................7
EXPORTS ..................................................................................................8
SHIPPING PACK CONTENTS.................................................................9
I- INTRODUCTION ............................................................................................................10
II- TECHNICAL DESCRIPTION.....................................................................................11
Figure 1 : Subsea Octans unit opened.......................................................................11
II-1 Fiberoptic gyrometer description..............................................................................12
Random walk: 0.0025 deg/ hour............................................................................12
II-2 Accelerometer description ........................................................................................12
II-3 Computer description ...............................................................................................13
III- MECHANICAL INTERFACE.................................................................................14
Figure 2 : Subsea Octans bottom plate mounting diagram.......................................14
IV- ELECTRICAL INTERFACE .......................................................................................15
IV-1 Description of the top panel......................................................................................15
Figure 3 : Subsea Octans top panel...........................................................................15
IV-2 Listing of interfaces ..................................................................................................16
IV-3 Description of the 13-pin connector .........................................................................16
IV-4 Power supply (pins 1, 2) ...........................................................................................17
IV-5 IXSEA configuration and display output (pins 9, 11, 12, 13) ..................................18
IV-6 Analog Ouputs (pins 7, 8).........................................................................................19
IV-7 Digital Input/Output (pins 3, 4, 5, 6 and 10) ............................................................20
IV-7.1 RS 232 Input / Ouput ............................................................................................21
IV-7.2 RS 422 Input/ Output ............................................................................................22
V. POSSIBLE SOURCES OF ERRORS ..............................................................................23
V-1 Heading error due to the speed log ...........................................................................23
V-2 Error due to unreliable latitude data .........................................................................24
VI- COMPUTATION OF HEAVE, SURGE, AND SWAY ..............................................25
VI-1 Definition of heave, surge, and sway........................................................................25
VI-2 Axis directions for heave, surge and sway measurements........................................25
VI-2.1 General ..................................................................................................................25
VI-2.2 Sign conventions ...................................................................................................26
VI-3 Choice of the high-pass filter....................................................................................26
VI-3.1 General behaviour of an heave, surge and sway filter...........................................26
VI-3.2 Guidance for tuning the filter ................................................................................27
VI-4 Use of lever arms for heave computation .................................................................28
VI-4.1 Multiple lever arms...........................................................................................28
Figure 6: Multiple lever arms monitoring ................................................................28
VI-4.2 Effect of a lever arm on the computation of heave ...............................................29
Figure 7 : Effect of lever arms ..................................................................................29
VII- TRUE HEADING, ROLL AND PITCH ......................................................................31
Figure 9 : Definition of true heading ........................................................................31
VII-2 Roll .......................................................................................................................31
Commercial in Confidence
2/44
iXSEA Document n° : MU/3453/EGF/001

Figure 10 : Definition of roll ....................................................................................31


VII-3 Pitch ......................................................................................................................32
Figure 11 : Definition of pitch ..................................................................................32
APPENDIX A-SPECIFICATION ............................................................................................33
1. TECHNICAL DESCRIPTION............................................................................................34
1.1. Performances .................................................................................................................34
Gyrocompass Technical Performances.............................................................................34
Motion Sensor Technical Performances...........................................................................34
Sensor (IMU) Intrinsic Performances...............................................................................34
1.2. Environment ..................................................................................................................35
Environmental specifications ..........................................................................................35
1.3. Interface .........................................................................................................................35
1.3.1 Power Requirement .................................................................................................35
1.3.2 Outputs.....................................................................................................................35
1.3.3 Inputs .......................................................................................................................35
1.3.4 Installation Software................................................................................................36
1.4. Housings ........................................................................................................................36
1.4.1. Surface unit.............................................................................................................36
1.4.2. Sub-sea units...........................................................................................................36
1.4.3 Useable configuration..............................................................................................37
2. CERTIFICATION ................................................................................................................38
APPENDIX B - PHYSICAL PRINCIPLES OF OCTANS......................................................39
1. THE TECHNOLOGY OF FIBER OPTIC GYROSCOPES (FOGs) ...................................40
1.1. The Sagnac Effect..........................................................................................................40
1.2. FOG description and performance.................................................................................40
Figure 1 : The “heart” of a FOG / the optical fiber coil with its integrated optical
circuit ........................................................................................................................41
1.3. Inertial Measurement Unit (IMU)..................................................................................42
2. THE FIBER OPTIC GYROCOMPASS – UNDERLYING PRINCIPLES .........................42
2.1. North finders..................................................................................................................43
2.2. Gyrocompasses ..............................................................................................................44

Commercial in Confidence
3/44
iXSEA Document n° : MU/3453/EGF/001

FOREWORD
This document serves as the user’s guide for the subsea versions, model 1000 and 3000, of the
Gyrocompass and Motion Sensor Octans developed and manufactured by IXSEA. For any
question, contact your nearest IXSEA’s representative or directly IXSEA at:

Our Main Office:


IXSEA S.A.S
55, Avenue Auguste Renoir Phone : + 33 (0)1 30 08 98 88
78160 MARLY LE ROI Fax : + 33 (0)1 30 08 88 01
FRANCE Email: info@ixsea.com
Our Benelux Office:
Phone : +31 (0) 23 750 5110
IXSEA b.v.
A Hofmanweg 5A Fax : +31 (0) 23 750 5111
2031 BH HAARLEM Email : info@ixsea.nl
THE NETHERLANDS

Version Date Commentary


/ January 2002 First diffusion

Commercial in Confidence
4/44
iXSEA Document n° : MU/3453/EGF/001

RIGHTS

All IXSEA products, and notably FOG technology, are protected by patents that have either
already been issued or which have been formally applied for. The information contained in
this manual supersedes all previously published information. IXSEA reserves the right to
change prices and technical specifications.

IXSEA is a trademarks registered by IXSEA S.A.S.

Printed in France by IXSEA S.A.S., 55, Avenue Auguste Renoir, F-78160 Marly-le-Roi.

Commercial in Confidence
5/44
iXSEA Document n° : MU/3453/EGF/001

WARRANTY

IXSEA provides a warranty covering this product against any defect in materials or
manufacture for a period of one (1) year from the date of shipment. In the event that such a
defect becomes manifest during the stipulated warranty period, IXSEA undertakes, at its sole
discretion, either to repair the defective product, bearing the cost of all parts and labor, or to
replace it with an identical product.
In order to avail itself of the present warranty, Customer must notify IXSEA of the defect
before expiry of the warranty period and take all steps necessary to enable IXSEA to take the
required action. Customer shall be responsible for the packaging and shipment of the defective
product for delivery to the repair center notified by IXSEA, the cost of such shipment being
borne by Customer. IXSEA agrees to bear the cost of return shipment of product to Customer,
who undertakes to pay all taxes, dues and expenses arising from such shipment.
This warranty shall not be construed as covering defects, malfunctions or damage caused by
improper use or inadequate maintenance of the product. Under no circumstances shall IXSEA
be obligated to provide repair or replacement under this warranty in order a) to repair
damage caused by work done by any person not representing IXSEA for the installation,
repair or maintenance of the product ; b) to repair damage caused by improper use or
connection to incompatible equipment, and specifically, the opening of the housing of the
equipment under warranty shall cause the warranty to be automatically cancelled ; c) to
maintain any product that has been modified or integrated into a larger configuration, if such
modification or integration increases the duration or difficulty of the maintenance of said
product.
This warranty covers the product hereunder and is provided by IXSEA in place of all
and any other warranty whether explicit or implicit. IXSEA does not guarantee the
suitability of the product under warranty for sale or any specific use. IXSEA’s liability
is limited to the repair or replacement of defective products, this being the sole remedy
open to Customer in the event the warranty becomes applicable. IXSEA cannot be held
liable for indirect, special, subsequent or consequential damage, irrespective of whether
IXSEA has or has not received prior notification of the risk of occurrence of such
damage.

Commercial in Confidence
6/44
iXSEA Document n° : MU/3453/EGF/001

CUSTOMER SUPPORT

To obtain support or information on any of our products, please contact IXSEA directly, or
one of its local representatives.
• IXSEA S.A.S.
55, Avenue Auguste Renoir,
78160 Marly-le-Roi,
France
Tel.: + 33 (0)1 30 08 98 88
Fax: + 33 (0)1 30 08 88 01
E-mail: info@ixsea.com

For Benelux, please contact directly the Dutch site of


• IXSEA b.v
A. Hofmanweg 5A
2031 BH Haarlem
Netherlands
Tel.: + 31 (0) 23 750 5110
Fax: + 31 (0) 23 750 5111
E-mail: info@ixsea.nl

• A detailed description of our products and a list of our representatives is available on


our website: www.ixsea.com

Commercial in Confidence
7/44
iXSEA Document n° : MU/3453/EGF/001

EXPORTS

OCTANS is free of exportand use worlwide, excpet in the following countries (list dated
december 2001):
OCTANS cannot be export or re-export in the territory of :
Afganistan, Angola, Myanar, Cuba, Iran, Iraq, Lybia, North Korea, Sudan, Syria,
Serbia Montenegro.

Commercial in Confidence
8/44
iXSEA Document n° : MU/3453/EGF/001

SHIPPING PACK CONTENTS


You have just received your equipment in a protective carton. This contains the following
items:
1. A blue shipping case (see photo 1) containing the items listed below. This enables the
OCTANS unit to be protected for shipment by air.
2. The OCTANS navigation unit (photo 2).
3. This User Guide.
4. A mains supply module directly connectable to the OCTANS unit (photo 3), enabling
conversion of 100/240V AC to 24V DC.
5. A Souriau 851-06J 14-19 S 50 connector (photo 4), enabling connection of analog I/O
interfaces.
6. A Souriau 851-06J 20-41 S 50 connector (photo 5), enabling connection of digital I/O
interfaces.
7. A cable enabling connection of the OCTANS unit to a local mains supply (photo 6).
8. A cable enabling connection of the OCTANS unit to a PC-compatible computer, to
allow the unit to be configured (photo 7).
9. A CD-Rom to be downloaded onto a PC to enable the unit to be configured (photo 8).
10. A half-cable enabling the OCTANS unit to be powered at 24V (photo 9).
11. A calibration certificate signed by the IXSEA Quality Department.
12. The IMO certificate for surface units.

Verification of pack contents

You will find in the shipping case a Packing List detailing all the items referred to above. This
Packing List was completed and checked by IXSEA shortly before shipment, and should
logically match the contents of the pack you have received.
However, we recommend that you check the contents of the pack and the equipment
immediately on receipt of your OCTANS unit. Specifically, you should check that all the
items referred to above are present on delivery and that none has sustained damage.
If you observe any non-conformity or damage, please inform the carrier and IXSEA without
delay by certified mail, describing in detail the nature of the problem.

Commercial in Confidence
9/44
iXSEA Document n° : MU/3453/EGF/001

I- INTRODUCTION
Octans 3000 TI are the members of the Octans family dedicated to underwater applications
(down to 3000 m), featuring a specific waterproof housing in Titanium (13 kg total weight in
air).
Octans is both a fiber-optic survey-grade IMO-certified gyrocompass and a Motion Reference
Unit for marine applications that provides true-heading, roll, pitch, yaw, heave, surge, sway,
rates of turn and accelerations even in highly volatile environments. Octans is also certified to
meet to the requirements of the International Maritime Organisation (IMO) for
gyrocompasses. Its heart consists of a small strapdown Inertial Measurement Unit (IMU),
which contains three accelerometers, three fiberoptic gyrometers, and a real-time computer.

The fiberoptic gyrometer is a recent technology generated to meet the requirements of the
aeronautical industry. It is totally inert, has no moving parts, and requires neither maintenance
nor recalibration. It is capable of a very wide dynamic range and can tolerate extremely
demanding mechanical environments without compromise to its performances.

Octans features the benefits of fiberoptic gyrometer technology and therefore shares the
advantages of not requiring maintenance or recalibration. Its strapdown IMU structure enables
straightforward, effective use with which no traditional mechanical gyrocompass can
compete. Octans is insensitive to physical shock, can be carried in a case, and is easy to
install. Strapdown equation processing enables the system to find North in less than 5 minutes
whatever the sea conditions may be. Notably, it can be powered up at sea, which is impossible
with a conventional gyrocompass.

In addition, Octans consumes only a small amount of power and directly outputs binary data
to NMEA 0183 standard, which can be reconfigured if desired, in addition to analog data
allowing easy interfacing with most available repeaters.

This document briefly describes how a subsea Octans works, and provides in more detail all
the possible interfaces which can be configured.

Commercial in Confidence
10/44
iXSEA Document n° : MU/3453/EGF/001

II- TECHNICAL DESCRIPTION


Octans is a strapdown IMU that contains three fiberoptic gyrometers in the 0.05°/hour class,
three milli-g accelerometers, and a real-time DSP computer. Figure 1 shows the Octans unit
“open”.

Figure 1 : Subsea Octans unit opened

Dimensions and physical characteristics are given in appendix [A].

Commercial in Confidence
11/44
iXSEA Document n° : MU/3453/EGF/001

II-1 Fiberoptic gyrometer description

The fiberoptic gyrometers contain fiberoptic coils with a length of nearly 800 m and an
average diameter of 90 mm.

Typical performance specifications include:


Temperature bias stability: ± 0.05 deg/hour (-40°C to +80°C)
In room bias stability: 0.002 deg/hour
Random walk: 0.0025 deg/ hour
Dynamic range: ± 500 deg/sec
Angular resolution: ≈ 0.2 arc second
Temperature scale factor: 30 ppm (-40°C to +80°C)
Bandwidth: 5 kHz

These fiberoptic gyrometers are manufactured by iXSEA and are used for other applications,
notably for military and aerospace applications.

II-2 Accelerometer description

The accelerometers are of pendulum type, particularly suited for attitude detection.

Typical performance specifications include:


Bias stability over one year: < 500 µg
In room bias stability : 10 µg
Dynamic range: ± 30 g
Scale factor over one year: < 500 ppm
Noise : 15 µg/√Hz
Resolution: ≈ 10 µg
Bandwidth: > 300 Hz

The accelerometers can withstand a severe environment in mechanical and thermal terms:
Physical shock: 250 g
Vibration: 25 g peak, 20 Hz to 2000 Hz
Temperature: -55°C to +95°C

Commercial in Confidence
12/44
iXSEA Document n° : MU/3453/EGF/001

II-3 Computer description

The unit’s computer is a Digital Signal Processor (DSP) chip enabling rapid and complex
real-time computation. This computation relates particularly to angle integration using
quaternion algebra, a heading search algorithm and Coriolis force correction for vessel speed.

The heading search algorithm is specific to IXSEA and is suited to use with a strapdown IMU.
It enables the heading to be sought whether the system is in movement or not and without an
external reference point. It is based on (filtered) measurement of shifts in local gravity as the
Earth rotates. This is possible because, in relation to an inertial reference frame, local gravity
moves within a cone whose axis is related to the direction of the Earth’s rotational vector (its
North-South axis). Monitoring the movements in local gravity enables the axis of the cone to
be determined and therefore the direction of geographical North. More detail on the algorithm
used are given in appendix B.

Commercial in Confidence
13/44
iXSEA Document n° : MU/3453/EGF/001

III- MECHANICAL INTERFACE


The Octans 3000 TI is installed using six M6 screws on the base plate of the unit (see figure
2). Alignment is carried out by means of two centering pins located on the bottom plate of the
system, enabling precise “point/line” positioning. These pins are located on the Octans 3000
TI centerline as shown by grooves on the base plate of the unit. The mechanical tolerance in
the manufacture of Octans bottom plate allows to have 0,01° of accuracy on the centreline of
the unit.

NOTE: Useable configuration

All our subsea units are designed as a standard for use on a vertical configuration.
For a subsea use in an horizontal configuration, please consult IXSEA.

Figure 2 : Subsea Octans bottom plate mounting diagram


Commercial in Confidence
14/44
iXSEA Document n° : MU/3453/EGF/001

IV- ELECTRICAL INTERFACE

IV-1 Description of the top panel


Octans 3000 TI inputs/outputs are arranged via a 13-pin Burton connector. The reference of
the connector is 5506 20-13.

Figure 3 : Subsea Octans top panel

Commercial in Confidence
15/44
iXSEA Document n° : MU/3453/EGF/001

IV-2 Listing of interfaces

The 16-pin connector fitted on subsea octans is used to provide the following:

1. Power supply, described in IV-4,


2. Configuration port, described in IV-5,
3. 1 Analog Outputs described in IV-6,
4. 1 Serial Input/Output RS232/422 user-configurable, described in IV-7,

IV-3 Description of the 13-pin connector


The structure of the Octans 3000 TI connector is shown below:

Pin Signal Pin Signal


1 VDC (19 V to 35 V) 9 ConfigOutGnd
2 GROUND 10 SerGnd
3 SerOutV+/232 11 ConfigOutV+
4 SerOutV- 12 ConfigIn-
5 SerInV+ 13 ConfigIn+
6 SerInV-
7 AnaOutASig
8 AnaOutGnd

Commercial in Confidence
16/44
iXSEA Document n° : MU/3453/EGF/001

IV-4 Power supply (pins 1, 2)

24 V DC

Electrical Ground

Octans is powered with a standard 24 V DC supply. It is possible however to supply power at


any voltage between 19 V and 35 V. Maximal power consumption is 12 W in all cases.
Octans does not possess an on/off switch. As soon as it is powered, it begins to seek
geographical North.

NOTE: IMPORTANT
Please remember that any interruption of the power supply, even brief, will return the system
to its initial condition and it will begin to seek North again.

Commercial in Confidence
17/44
iXSEA Document n° : MU/3453/EGF/001

IV-5 IXSEA configuration and display output (pins 9, 11, 12, 13)

ConfigOutGnd

ConfigIn+

ConfigOutV+
ConfigIn-

The pins 9, 11, 12, 13 are used to link the subsea Octans directly to the IXSEA Octans
Installation and configuration Software.

In order to install, configure Octans or to use the Display Data, please connect your subsea
Octans to a PC using a standard SUB D9 connector.

The cable between Octans and the PC has to be as follows :

Burton connector ConfigIn- pin (12) 5 SUB D9 connector

ConfigIn+ (pin 13) 3

ConfigOutV+ (pin 11) 2

ConfigOutGnd (pin 9)

Commercial in Confidence
18/44
iXSEA Document n° : MU/3453/EGF/001

IV-6 Analog Ouputs (pins 7, 8)


One analog ±10 V outputs are available and can be entirely configured (signal, sampling
frequency, and scale factor). For more details, please refer to the Octans Installation and
configuration Software user’s guide.
This output offers 14-bit resolution at 300 Hz and is identified by the signals AnaOutGnd (pin
8) and AnaOutASig (pin 7).

AnaOutASig
AnaOutGnd

Commercial in Confidence
19/44
iXSEA Document n° : MU/3453/EGF/001

IV-7 Digital Input/Output (pins 3, 4, 5, 6 and 10)


One serial input and one serial output are available on the subsea Octans. These serial I/O can
be entirely configured. For more details, please refer to the Octans Installation and
configuration Software user’s guide. Please note that only the port A is to be used.

For each I/O, configuration parameters include:

• Electrical levels : RS 232 or 422 (see detailed pinout hereafter),


• Pair, parity: No parity, Even parity or Odd Parity,
• Number of bits: 0.5, 1, 1.5, or 2 stop bits,
• Data transmission rate: from 600 Bauds to 115.2k or from two definable values
• Protocol: 30 protocols based on NMEA 0183, ASCII or Binary,
Output frequency: 0.1 Hz to 100 Hz.

Commercial in Confidence
20/44
iXSEA Document n° : MU/3453/EGF/001

IV-7.1 RS 232 Input / Ouput


In RS 232, the following pinout is used:

RS232

RS232

RS232

RS232

OutGnd Out /+232 InGnd In /+232

A SerOutGnd (10) SerOutV+/232 (3) SerInV- (6) SerInV+ (5)

Note 1 : It is possible to connect the OutGnd to the InGnd pins to allow the use of
1 single Sub D9 connector for I/O,

Note 2 : SerOutGnd is internally connected to ConfigOutGnd and AnaOutGnd

Commercial in Confidence
21/44
iXSEA Document n° : MU/3453/EGF/001

IV-7.2 RS 422 Input/ Output


In RS 422, the following pinout is used:

RS422

RS422
RS422

RS422

RS422

OutGnd / InGnd Out /+422 Out /-422 In /+422 In /-422

A SerOutGnd (10) SerOutV+/232 (3) SerOutV- (4) SerInV+ (5) SerInV- (6)

Note 1 : SerOutGnd is internally connected to ConfigOutGnd and AnaOutGnd

Commercial in Confidence
22/44
iXSEA Document n° : MU/3453/EGF/001

V. POSSIBLE SOURCES OF ERRORS


All gyrocompasses, Octans included, are sensitive to the speed of travel of the vessel and
current latitude. However these errors are small and as described below, latitude needs to be
entered in Octans only if the ship changes latitude very substantially, and very precise speed
measurement is not imperative.

V-1 Heading error due to the speed log


The heading output of all gyrocompasses is sensitive to the speed of travel of the vessel
towards North. The international standard (ISO 8728) defines that:

“Course error in degrees for a gyrocompass aligned north-south is determined by the


formula V/5 x the secant of the latitude, where V is the North component of the speed in
knots”.

This speed correction applies whatever the technology used in the gyroscopes: Indeed, the
linear speed of a boat travelling on the terrestrial “sphere” produces, with respect to the Earth
and therefore with respect to the inertial frame of reference, a rotational speed V/R, where R is
the radius of the Earth. This disturbs the measurement of the speed of rotation of the Earth and
therefore the detection of North.

Using the above formula, it is easy to compute the speed level at which the heading will begin
to demonstrate an error, if the accuracy of the heading measurement is known: Octans has an
dynamic accuracy of 0.2 degree x secant of latitude and therefore the speed in knots at which
an error greater than this appears is V Northmax = 0.2 x 5 3,2 knots.

Given that this is a relatively low value, it is generally recommended to enter the speed in
Octans to allow the unit to compensate automatically and indicate the correct heading. It can
be seen from the above formula however that the speed needs to be known only to a few
knots. In practice, a log which gives the speed of the vessel in relation to the water without
intrinsically taking into account the surface currents is more than satisfactory for such
compensation. Since all ships are equipped with GPS, the GPS speed can also be entered.

Commercial in Confidence
23/44
iXSEA Document n° : MU/3453/EGF/001

V-2 Error due to unreliable latitude data


Gyrocompasses are intrinsically sensitive to latitude. Heading error is itself dependent in
general terms on the secant of the latitude, which is fairly logical: the error tends theoretically
toward infinity when the gyrocompass approaches one of the geographical Poles. However, it
is not this error which is considered here, but rather intrinsic system inaccuracy when it has
unreliable data for the latitude of the current location.

Octans needs to know the latitude of its location in order to find geographical North rapidly. If
the latitude information input is incorrect, Octans will produce an error. This error is
nevertheless very small: The curve in the figure 4 shows the heading error in degrees
multiplied by the secant of the latitude versus the latitude of the current location, assuming
that the latitude entered in the Octans unit is incorrect by one degree. In practice, Octans needs
to know the latitude only to an accuracy of a 5 degrees or so. Please note that this dependency
is slightly more important at low latitudes and it is recommended below 30° to enter the
current latitude in the system with at worst a 3° accuracy.

In practice, it is possible to enter the latitude directly to Octans by using a GPS NMEA
sentence. You can also manually enter the latitude, please refer to the Octans Installation
Software.

0,05
0,04
0,03
Error in degrees

0,02
0,01
0
0 10 20 30 40 50 60 70 80 90
-0,01
-0,02
-0,03
Latitude in degrees

Fig. 4 : Heading error in degrees by secant of latitude for a 1 degree latitude error

Example:
At 40° latitude, an error of 3° in the latitude will cause 3x0,02 = 0,06° sec. Lat error.

Commercial in Confidence
24/44
iXSEA Document n° : MU/3453/EGF/001

VI- COMPUTATION OF HEAVE, SURGE, AND SWAY

VI-1 Definition of heave, surge, and sway


The heave, or vertical motion of the vessel, is determined by the double integration of the
vertical acceleration. Unfortunately, the vertical acceleration is measured with small bias due
to the physical limitations of the sensors. Because of this bias component, the double
integration, which represents vertical position, can diverge to infinity very quickly. The best
solution, used in every motion sensor, is to use an high-pass filter, which nulls out the bias
component effect. By definition, the vertical amplitude of a movement which is filtered to cut-
off the frequency around zero, is called "Heave". Respectively, the two horizontal positions
filtered to cut-off the frequency around zero, the surge and the sway.

VI-2 Axis directions for heave, surge and sway measurements

VI-2.1 General

Base Plate

Sway (horizontal) Heave (vertical)

Surge (horizontal)

Heave (vertical)

Sway (horizontal) Surge (horizontal)

Base Plate

Figure 5 : Axis directions for the heave, surge, and sway measurements

Commercial in Confidence
25/44
iXSEA Document n° : MU/3453/EGF/001

VI-2.2 Sign conventions

The axis directions are defined as follows :

• The heave is default defined positive up on a vertical axis pointing to the


direction of the connector.
• The surge is default defined positive on a horizontal axis parallel to the
centerline pointing to the direction of the circle located on the base plate.
• The sway is default defined positive on a horizontal axis pointing to the left of
the subsea Octans (on the port side of the vehicule, if the unit is “correctly”
mounted).

VI-3 Choice of the high-pass filter

VI-3.1 General behaviour of an heave, surge and sway filter


Since the heave (surge and sway) output is high-pass filtered, the output will always
return to zero when Octans is static. If Octans is moved over a given vertical distance,
the heave output will show a step change in position. If Octans remains static in the
new position, the output will gradually return to zero with a certain time constant
(which depends upon the adjustment parameter of the filter). If Octans is moved
following a sine or a combination of sinus, as usually observed with swell movements,
the heave (surge and sway) output will follow this movement, provided that the high-
pass filter is adapted to the swell frequency.

The heave, surge, and sway are computed by the double integration of the three
accelerations. The frequency response of Octans for the heave measurement, which is
the ratio between the measured heave and the exact vertical position, is :

3
é f ù
ê j f c úú
H( f ) = ê
ê
j úú
f where fc is the cut-off frequency of the high-pass filter.
ê1 + fc û
ë

Commercial in Confidence
26/44
iXSEA Document n° : MU/3453/EGF/001

VI-3.2 Guidance for tuning the filter


For practical and operational reasons, the heave (surge and sway) formula is
implemented inside octans as follows:

æ jT f ö
3
ç o ÷
H( f ) = ç ÷
ç 1 + jT f ÷
è o ø

Where "To" is the adjustment parameter that the operator can modify in order to adjust
the heave behaviour to the sea state. For more detail, please refer to the "Octans
Installation Software" or the "Repeater Software".

• How to choose To, the adjustment parameter ?


To correctly measure the swell movement using the heave output, it is important to
adjust To to a value quite larger than the longest period of the swell expected
during the operations.
The longer the swell period is, the higher To must be. However, if To is high, the
time to come back to zero in case of a sudden change in altitude increases. There
is therefore a conflict between the need to reduce the effects of errors, and the need for
an extended bandwith in order to maximize the operational ability of Octans.
A compromise is found when To is higher that 5.4 times the longest period of the
swell (in that case the amplitude response is 95 %).

Please refer the application note ‘’HEAVE TOOL’’ file included in the installation
and configuration software CD if you wish to assess the effect of different To settings.

Commercial in Confidence
27/44
iXSEA Document n° : MU/3453/EGF/001

VI-4 Use of lever arms for heave computation

VI-4.1 Multiple lever arms


Octans is able to calculate the heave of an external monitoring point. Effective from
firmware 4.1, three “secondary” monitoring points have been added. For each one of
those secondary monitoring points, data can be outputted with a completely different
setting including serial or analog I/O. In particular, at each location, a different
protocol can be set. This allows, for instance, to drive a multibeam on one side of a
vessel, to drive a single beam echosounder at an other location, to send analog heave
info to a sub-bottom profiler.

Lever Arm 1,
Protocol 1

Octans

Lever Arm 3,
Protocol 3
Lever Arm 2,
Protocol 2
Figure 6: Multiple lever arms monitoring

Commercial in Confidence
28/44
iXSEA Document n° : MU/3453/EGF/001

VI-4.2 Effect of a lever arm on the computation of heave


Octans can be located some distance away from the desired monitoring point. In this
case, the heave of the monitoring point can be very different from the one of the subsea
Octans, due to the lever arms.
Let us assume for example that the heave of the subsea Octans is null, but there is just
a pitch angle. If there is a lever arm between Octans and the desired monitoring point
in the direction of the subsea Octans, it is easy to see that the heave of the monitoring
point is not null, but equal to the tangent of the pitch angle times the lever arm distance
(see figure 7).

Monitoring
point

Axis 1 Heave ≠ 0
Octans
Heave = 0
Pitch angle

Horizontal plane

Figure 7 : Effect of lever arms

To avoid this effect, it is recommended to place the subsea Octans as close as possible
to the monitoring point.
Otherwise, it is possible to compensate the effects of lever arms by computation. To
perform this computation, it is necessary to know the exact place of the monitoring
point in the frame of the subsea Octans . It is possible to give the vector ( X1 , X2 , X3 )
to Octans using the Octans Installation Software. The definition of this vector follows
(see figure 8, next page).

Commercial in Confidence
29/44
iXSEA Document n° : MU/3453/EGF/001

Axis 1

Monitoring point

X1

Top Panel
Axis 2

X2

Axis 3

X3

Axis 1

X1

Figure 8 : Definition of the vector ( X1 , X2 , X3 ) for lever arms


compensation for heave computation

Commercial in Confidence
30/44
iXSEA Document n° : MU/3453/EGF/001

VII- TRUE HEADING, ROLL AND PITCH


The true heading is the angle between the vertical plane oriented in the North direction and the
vertical plane passing through the subsea Octans. The vertical plane passing through Octans is
visualized by the centreline, oriented positive from the oval-shaped hole towards the
circular-shape hole located on the bottom plate.
The orientation of this angle is given in figure 9.

True North
Heading Axis 1

Figure 9 : Definition of true heading

VII-2 Roll
The roll is the angle between the horizontal plane and the axis 2 of the subsea Octans. This
angle is default defined positive in the direction of axis 1, i.e. when the vehicle’s port side is
up.

Axis 1

Roll angle

Figure 10 : Definition of roll

Commercial in Confidence
31/44
iXSEA Document n° : MU/3453/EGF/001

VII-3 Pitch
The pitch is the angle between the horizontal plane and the axis 1 of the subsea Octans. This
angle is default defined positive in the direction of axis 2, i.e. when the vehicle’s bow is
down.

Axis 2

Pitch angle

Figure 11 : Definition of pitch

Commercial in Confidence
32/44
iXSEA Document n° : MU/3453/EGF/001

APPENDIX A-SPECIFICATION

Commercial in Confidence
33/44
iXSEA Document n° : MU/3453/EGF/001

1. TECHNICAL DESCRIPTION
Octans in an IMO-compliant survey-grade gyrocompass and an integral motion sensor at
the same time.

1.1. Performances

Gyrocompass Technical Performances


Dynamic accuracy ± 0.2° Secant Latitude (*)
(whatever sea-state) or 0.1° Rms
Settle point error ± 0.1° Secant Latitude
or 0.05° Rms
Settling time (static conditions) 1 Minute
Settling time at sea : 3 Minutes
Repeatability ± 0.025° Secant Latitude
Resolution 0.01°

No Latitude limitation
No speed limitation
(*) Secant Latitude = 1/cosine Latitude

Motion Sensor Technical Performances


Heave, Surge & Sway :
Accuracy 5 cm or 5% (whichever is highest)
Resolution 1 cm
Heave motion periods 0.003 to 100 s (tunable)

Roll, Pitch & Yaw :


Accuracy 0.01°
Range No limitation
Follow-up speed Up to 500°/s

Sensor (IMU) Intrinsic Performances


Accelerometers Gyroscopes
In-room bias stability (rms) 20 µg 0.005 °/h
Bias stability over temperature ± 500 µg ± 0.05 °/h
range (-40°C to +80°C)
Resolution 10 µg 0.2Arc
second

Commercial in Confidence
34/44
iXSEA Document n° : MU/3453/EGF/001

1.2. Environment

Environmental specifications
Operating temperature : -40°C to +60°C
Storage temperature : -40°C to +80°C
Shocks : 30 g in 6 ms (operating)
50 g in 11 ms (survival)
Vibrations : 1 g sine (5 to 50 Hz)
MTBF 30 000 Hours

1.3. Interface

1.3.1 Power Requirement


Input voltage : 19 to 35 V d.c. (24 V nominal)
Power consumption : 12 W (max.)

1.3.2 Outputs
• Serial: 3 independent and configurable digital outputs (Surface Octans)
Or 1 configurable digital output (Sub-sea Octans)
To be chosen among a complete set of existing protocols (NMEA
0183, TSS, Seatex, Simrad, Robertson, Tokimec, Anschutz
Compatible) or any custom protocol, with RS 232 or RS 422 levels
• Analogue: 4 independent and configurable analogue outputs, 14 bits / ± 10
V, (Surface Octans)
Or 1 configurable analogue output,14 bits / ± 10 V, (Sub-sea Octans),
• Pulses
• Update rate: up to 300 Hz

1.3.3 Inputs
• Serial: 3 independent and configurable digital inputs (Surface Octans),
Or 1 configurable digital output (Sub-sea Octans)
• Analogue: 2 independent and configurable analogue inputs, 16 bits / ±15
V,
• Pulses
• Update rate : up to 300 Hz

Commercial in Confidence
35/44
iXSEA Document n° : MU/3453/EGF/001

1.3.4 Installation Software


Octans is delivered with a powerful and easy-to-use installation software, which
allows a complete configuration (choice of baud-rates and frequencies, data frame
protocols, scale factors for analogue I/O, multiple lever arms, filtering
parameters….).

1.4. Housings

1.4.1. Surface unit


OCTANS
Shape : Rectangular box, splash proof(IP 66)
Dimensions (L x W x H, in mm) : 280 x 136 x 152
Weight in air : 4.5 kg
Material : Aluminium

1.4.2. Sub-sea units


OCTANS 1000, built in an underwater housing (1000-meter depth rated)
Shape : Cylinder
Dimensions (Ø x H, in mm) : 209 x 318 (body = 179 x 318)
Weight in air : 10 kg
Weight in water : 2 kg
Material : Aluminium (hard anodising)

OCTANS 3000, built in an underwater housing (3000-meter depth rated)


Shape : Cylinder
Dimensions (Ø x H, in mm) : 209 x 318 (body = 179 x 318)
Weight in air : 25 kg
Weight in water : 17 kg
Material : Stainless steel (duplex)

OCTANS 3000 TI, built in an underwater housing (3000-meter depth rated)


Shape : Cylinder
Dimensions (Ø x H, in mm) : 209 x 322 (body = 173 x 322)
Weight in air : 13 kg
Weight in water : 5 kg
Material : Titanium

OCTANS 6000, built in an underwater housing (6000-meter depth rated)


Shape : Cylinder
Dimensions (Ø x H, in mm) : 209 x 318
Weight in air : 15 kg
Weight in water : 7 kg
Material : Titanium

Commercial in Confidence
36/44
iXSEA Document n° : MU/3453/EGF/001

1.4.3 Useable configuration


All the Sub-sea units are designed as a standard for use on a vertical
configuration. For a sub-sea use in an horizontal configuration, please consult
IXSEA.

Commercial in Confidence
37/44
iXSEA Document n° : MU/3453/EGF/001

2. CERTIFICATION
Octans complies with the regulations of the International Maritime Organisation
resolutions A.424 (XI), A. 694 (17), A.183 (19) for gyrocompasses, with SOLAS 74 as
amended (regulations V/12 (d), (i)) and IEC 60945, IEC 61162-1 and ISO 8728.

Octans has been awarded certificate N° 09807/A0 EC from certifying authority N°


0062. A copy of all relevant documentation is available upon request to iXSEA.

Commercial in Confidence
38/44
iXSEA Document n° : MU/3453/EGF/001

APPENDIX B - PHYSICAL PRINCIPLES OF OCTANS

Commercial in Confidence
39/44
iXSEA Document n° : MU/3453/EGF/001

APPENDIX B:
PHYSICAL PRINCIPLES OF OCTANS
Extract from
‘’highly compact fiber optic gyrocompass for applications at depths up to 3,000 meters,
presented at the Underwater Intervention 2000 show, January 2000’’

1. THE TECHNOLOGY OF FIBER OPTIC GYROSCOPES (FOGs)


FOGs do not use the rapidly spinning top employed in mechanical gyroscopes – in fact, they
have no moving parts at all. They do not use the gyroscope effect to measure the rotational
speeds of mobiles, but a radically different phenomenon – the so-called “Sagnac Effect”.

1.1. The Sagnac Effect


The Sagnac Effect is a physical phenomenon of relativistic type; understanding it requires a
good grasp of Special Relativity [1]. However, it is possible to provide a simplified (although
inaccurate) physical interpretation of the effect. Imagine a coil of optical fiber. Optical fiber,
as is well known, is a good vector for the propagation of light. This coil will in principle have
two exits at the two ends of the fiber. If we inject a light pulse into one end, it will come out at
the other after a duration equal to the time the light takes to cover the entire length of the
coiled fiber. If we now inject two pulses simultaneously into the two ends of the coil, they will
travel in opposite directions, pass each other in the middle and come out at opposite ends of
the coil. The time the light takes to travel through the coil will be the same irrespective of its
direction of travel, and the two pulses will therefore exit the fiber at the same time. If we now
imagine that the coil is rotating around its central axis, this movement will “help” one pulse
but “hold back” the other. It can be seen therefore that the two pulses will leave the coil at
different times. If we measure this temporal difference, we can deduce from it the speed of
rotation.

1.2. FOG description and performance


In practice, this difference is determined in optics using interferometry, which provides a
measurement of the phase difference between the two light waves travelling in opposite
directions within the coil. The interferometer is created by “closing” the coil on itself using an
optoelectronic component called an “Integrated Optical Circuit” (see figure 1).

Commercial in Confidence
40/44
iXSEA Document n° : MU/3453/EGF/001

Figure 1 : The “heart” of a FOG


the optical fiber coil with its integrated optical circuit

Commercial in Confidence
41/44
iXSEA Document n° : MU/3453/EGF/001

The ingenious signal processing which follows requires a large number of optoelectronic
components if the information on optical phase, carrying information on rotation, is to be
converted into a digital signal useable by a calculator.

In practice, FOG performance gets better as it gets bigger, a fact which can be easily
understood in terms of the length of the coiled optical fiber: at any given rotational speed,
increased length will make it easier to separate the two light pulses temporally in the way
described above.

FOG performance can be measured in terms of many parameters, of which the most important
is known as bias stability, which means the stability of the zero point, or the intrinsic accuracy
of the measurement of rotational movement. It is usual to express bias stability in degrees per
hour (deg/hour), to make comparison easier with the Earth’s rotation rate, which is 15
deg/hour (1 revolution in 1 day, 360 degrees in 24 hours, giving 15 degrees per hour). In
practice, in order to measure the bias stability of a FOG, we measure the Earth’s rotation rate.
As an example, at the latitude of Paris, France (48,57°N), a FOG must measure 11.33
deg/hour (i.e. the projection of the rotation of the Earth onto the apparent vertical).

1.3. Inertial Measurement Unit (IMU)


In fact, a single FOG measures the projection of the instantaneous rotation along the main axis
of its coil, and three FOGs are necessary to measure the rotation rate vector.

This triad of gyrometers is usually combined with a set of three accelerometers. An


accelerometer enables measurement firstly of the instantaneous acceleration along a given axis
(and thereby, through successive integrations, speed and position), and secondly, knowledge
of apparent local gravity, and thereby the local vertical axis.

The compact assembly formed by the three gyrometers and the three accelerometers is called
an “Inertial Measurement Unit” (IMU) and forms the heart of any inertial reference system.
When an IMU is coupled to a calculator and an interface, the result is an “inertial reference
system”.

Octans is an inertial reference system capable of providing complete information on the


physical attitude of the mobile. The IMU comprises three FOGs (0.05 deg/hour bias stability)
and three accelerometers (± 500µg).

2. THE FIBER OPTIC GYROCOMPASS – UNDERLYING PRINCIPLES

By definition, a gyrocompass is a gyroscope-based system for the measurement of true


heading, that is to say, angular measurement of a position in relation to geographical North,
whatever the movements made by the object on which the gyrocompass is placed. This means
for example, that the gyrocompass must remain relatively insensitive to pitch and roll
movements, which may be at high levels on certain ships. In this way, the gyrocompass is to
be distinguished from North finders, which need to remain totally immobile in relation to the
Earth when the measurement is done.

Commercial in Confidence
42/44
iXSEA Document n° : MU/3453/EGF/001

Gyrocompass types currently in use comprise a gyroscope which aligns its angular moment
with that of the Earth and therefore exploit at a basic level the intrinsic properties of rotating
solids, and notably the principle of gyroscopic spins. A gyrocompass using FOGs must
therefore be based on a radically different concept. It is this concept that we explain below.

2.1. North finders


We can begin by assuming that our initial objective is to produce a “static” indicator of North,
that is to say, an indicator without any mechanical system (which means that we cannot rotate
a single horizontal-axis gyro in order to find the position which cancels out the signal, which
will correspond to the East). In order to measure the rotation vector of the Earth Ω, the first
thing we need is three gyros for the three spatial axes. However, that is not enough yet to
indicate a heading, because we lack information about the horizontality of the assembly. This
information can be obtained from a plumb line, electrolytic levels or accelerometers, by
making a measurement of the local gravity vector g. It then remains to project the Earth
rotation vector Ω onto the horizontal plane orthogonal to g to obtain the direction of
geographical North (figure 2). It can be seen that the intrinsic accuracy of this measurement
depends on the accuracy of the sensors (the bias of the gyros bgyro and the accelerometers bacc
for example) and the latitude L. It can be expressed in radians as:

bgyro bacc
∆Φ = Sec L + tan L
Ω g

Equatorial plane
North
ΩEarth

South

Figure 2: North Finder / basic concept

To achieve a North finder capable of rivalling commercially available conventional


gyrocompasses, accurate to a few tenths of a degree of the secant of the latitude, it is necessary
to select gyros offering accuracy to at least one-hundredth of terrestrial rotation rate (0.1 °/h),
such as the FOG 90 (0.05°/h) produced at IXSEA, and accelerometers precise to one-
hundredth of apparent gravity. In practice, the accelerometers used in octans provide better
performance than this in order to improve dynamic stability.

Commercial in Confidence
43/44
iXSEA Document n° : MU/3453/EGF/001

2.2. Gyrocompasses

The gyrocompass represents a step up from the above in terms of complexity. At this level,
the system has to withstand random movements – which may be violent, such as a ship’s pitch
and roll. The difficulty is twofold compared with the previous design: firstly, measurement of
terrestrial rotation is disturbed by enormously high rotational values (several orders of
magnitude greater than the Earth’s rotation rate), and secondly, measurement of gravity is
disturbed by centrifugal accelerations which may also prove to be relatively high.

The basic idea is therefore to abandon the direct use of the measurement of the Earth’s
rotation rate related to the gyroscopic frame, in favour of a “fixed” reference frame, which is
called the Inertial Space.

Described briefly, the system comprises three gyros and three accelerometers: the three gyros
enable the rotation rate of the moving object to be measured at any given instant (including
the Earth’s rotation rate), and the three accelerometers give the sum of the acceleration and
apparent gravity; these measurements are both related to a reference bound to the moving
object itself. The angular attitude of the moving object compared to the Inertial space is then
computed by integration of the rotation rate. The accelerometer data, which is the sum of the
acceleration and gravity, is then expressed within the Inertial Space. After filtering out the
acceleration values, it is possible to “observe” the slow drift of apparent gravity due to the
rotation of the Earth. In fact, it is easy to show that the apparent gravity expressed within the
Inertial Space defines a cone whose main axis is the rotational axis of the Earth (see figure 3).
Examination of the movement of g can therefore tells us where geographical North is without
need of an external reference.

Rotation of Earth

Figure 3: Conical movement of the local


gravity g in relation to the Inertial Space

Commercial in Confidence
44/44
STEP 2. ONBOARD INSTALLATION

Mechanical Installation

OCTANS 100 and 3000 are installed using three M6 screws (Duplex or Titanium) accessible on the base plate of
the unit (see Figure 2 for OCTANS 100 and Figure 3 for OCTANS 3000).

Figure 2 - Definition of OCTANS 100 Reference Frame (X1,X2, X3) and P centre of measurement

Figure 3 - Definition of OCTANS 3000 Reference Frame (X1, X2, X3) and P centre of measurement

Recommendations
• Temperature in operation must be in the range -40 °C to 60 °C
• The dimensions of the OCTANS housing are 276 mm x 136 mm x 148.5 mm.
There must be enough place for the wire way on the connector side of OCTANS
2006 -07 / MU / OCTIII / 012 ed.A 15
OCTANS 6000 is mounted by IXSEA on a bracket that will share a chassis for RDI Doppler Velocity Log. OCTANS
6000 is designed as a standard for use in its bracket on an horizontal configuration. Removing OCTANS from its
bracket will void the factory calibration of the unit.
X3

X2 X1

X2

X3 X1

X1
X3

X2
X2

Figure 4 - Definition of OCTANS 6000 Reference Frame (X1, X2, X3) and P centre of measurement

Recommendations
• Temperature in operation must be in the range -40 °C to 60 °C
• The dimensions of the OCTANS housing are 276 mm x 136 mm x 148.5 mm.
There must be enough place for the wire way on the connector side of OCTANS

16 2006 -07 / MU / OCTIII / 012 ed.A


Electrical Connections

All OCTANS inputs/outputs are made via one sealed connector located on the OCTANS front panel. A 16-pin
SUBCONN connector, reference MCBH16M is delivered as a standard (see Figure 5 for diagram of this standard
connector).

Figure 5 - Diagram of the SUBCONN 16-pin connector

• Power Supply: pin 1 and pin 2 (ground) are assigned for the power supply for direct connection to a 24 V power
supply.

IMPORTANT: any outage of the power supply, even brief, will return the system to its initial condition and it will
begin to seek North again. The alignment phase will start over.

• Connection to PC: pins 12, 14, 15 and 16.The pin assignments are described hereafter.

OCTANS Subconn connector PC SUB D9 connector


Pin Signal Pin Signal
16 ConfigOUT GND 5 PC GND
15 ConfigOUT + 2 PC Rx
12 ConfigIN - 5 PC GND
14 ConfigIN + 3 PC Tx

Pins 16 and 12 need to be connected to pin 5 of DB9 for the communication to work properly

2006 -07 / MU / OCTIII / 012 ed.A 17

You might also like