Professional Documents
Culture Documents
CONTENTS
1 INTRODUCTION....................................................................................................................... 3
1.1 Project Description .........................................................................................................3
1.2 Scope..................................................................................................................................3
1.3 Purpose..............................................................................................................................3
2 DEFINITIONS AND ABBREVIATIONS ................................................................................ 4
2.1 Definitions .........................................................................................................................4
2.2 Abbreviations and Other Definitions .........................................................................4
3 REFERENCES .......................................................................................................................... 5
3.1 Standards and Client / Project Specifications.........................................................5
3.2 Project Reference Drawings.........................................................................................6
3.3 Project Method Statements ..........................................................................................7
3.4 Project Inspection and Test Plans..............................................................................8
4 HEALTH, SAFETY & ENVIRONMENT................................................................................. 8
5 RESPONSIBILITIES ................................................................................................................ 9
6 EQUIPMENT............................................................................................................................ 11
6.1 Vessels and Plant..........................................................................................................11
6.2 Installation Aids, Rigging and Tools........................................................................12
7 PERMANENT MATERIALS.................................................................................................. 13
7.1 General Characteristic .................................................................................................13
7.2 Tolerances.......................................................................................................................14
7.3 Weather Limitation........................................................................................................14
8 PROCEDURE .......................................................................................................................... 14
8.1 Work Sequence..............................................................................................................14
8.2 Typical Preparation.......................................................................................................14
8.3 Installation.......................................................................................................................16
9 QUALITY .................................................................................................................................. 17
10 RECORDS AND REPORTS ................................................................................................. 18
11 CONTINGENCIES .................................................................................................................. 18
12 APPENDICES.......................................................................................................................... 18
12.1 Appendix 1 – Risk Assessment.....................................................................................18
12.2 Appendix 2 - Inspection and Test Plan ........................................................................18
12.3 Appendix 3 – Drawings and Sketches .........................................................................19
12.4 Appendix 4 – Data Sheets and Other Supporting Documents.................................20
1 INTRODUCTION
Phase I
Pre Engineering survey of the offshore/onshore fields for obtaining field data for design of
dredging, SPM, PLEM, Pipeline and other accessories etc;
Detailed Engineering of SPM & PLEM system, Offshore/Onshore Pipelines, and accessories
including installation engineering for SPM/PLEM and pipelines;
Procurement of line pipes, SPM /PLEM system, complete with anchors, chains, subsea
hoses, floating hoses and mooring hawser;
Phase II
1.2 Scope
This Method statement details the minimum requirements for performance and procedure of
the PLEM Installation for the Tanzania SPM & Pipelines Replacement EPC Project.
1.3 Purpose
2.1 Definitions
3 REFERENCES
S393-SPM-SBM-ENG-SPEC-
CALM Buoy - General Specification (SZM92003)
2001
S393-SPM-SBM-ENG-SPEC-
PLEM - Piping Material - Specification (SPM84010)
2024
S393-SPM-SBM-ENG-RPT-
PLEM - Piping Stress - Calculation (CPM84012)
2014
S393-SPM-SBM-ENG-RPT-
PLEM - Structure - In place Calculation (CSM84032)
2023
S393-SPM-SBM-ENG-RPT-
PLEM Foundation Calculation (CIU84001)
2028
S393-SPM-CGS-ENG-RPT-
SPM System Transportation Manual
2103
S393-PL-LYE-ENG-DWG-
Overall Pipeline Schematic
1002
S393-SPM-SBM-ENG-DWG-
CALM Buoy - General - Field Layout (DUM86023)
2001
S393-SPM-SBM-ENG-DWG-
PLEM - Structure - Detail Sheet 1 (DSM84002)
2042
S393-SPM-SBM-ENG-DWG-
PLEM - Structure - Detail Sheet 2 (DSM84003)
2043
S393-SPM-SBM-ENG-DWG-
PLEM - Piping - General Arrangement (DPM84007)
2045
S393-SPM-SBM-ENG-DWG-
PLEM - Piping – Isometric (DPM84008)
2046
S393-SPM-SBM-ENG-DWG-
PLEM - Structure – Protection Cage (DSM84005)
2053
S393-SPM-SBM-ENG-DWG-
PLEM - General – Arrangement (DSM84000)
2054
S393-SPM-SBM-ENG-DWG-
PLEM - Lifting - General Arrangement (DSM84006)
2055
S393-SPM-SBM-ENG-DWG-
PLEM - Piping - Support (DPM84009)
2056
S393-SUR-OSS-OPR-MS-
Method Statement for Offshore Survey
3301
S393-SUR-OSS-OPR-MS-
Method Statement for Barge Positioning Survey
3302
S393-SPM-LOPL-OPR-MS-
Method Statement for Subsea Hose Installation
2306
S393-SPM-SBM-ENG-GDL-
CALM System Installation Guidelines
2001
S393-GEN-LOPL-OPR-MS-
Method Statement for Vessel Anchor Handling
6303
S393-GEN-LOPL-OPR-MS-
Method Statement for Diving Operation - Pipeline
6304A
S393-SPM-LOPL-QAM-ITP-
Inspection and Test Plan For PLEM Installation
2301
The activities detailed in this document shall be undertaken in accordance with approved
Leighton safety plan and the specific risk assessments and safety analysis conducted prior
to commencement of the Work.
5 RESPONSIBILITIES
per the approved drawings. Ensure HSE compliance on site and coordinate with site HSE
Manager.
6 EQUIPMENT
NO DESCRIPTION
1 Work Barge - Stealth
Basic Characteristic
Class : ABS – A1 Accomodation Work Barge, Helideck
LOA : 100mtr (330ft)
Breadth : 30mtr (100ft)
Depth : 6mtr (20ft)
Draft : 2.5mtr to 4.5mtr
Deck Loading Capacity : 15MT/m2
9-point Mooring System
FWD Mooring Winches : 5 nos of single drum 45MT with 42mm wire x 1200mtr
AFT Mooring Winches : 4 nos of single drum 35MT with 42mm wire x 1000mtr
A&R Winch : 1 no of single drum 100MT with 64mm wire x 600mtr
Figure 1 - Stealth
4 Support Tug
1no required to support the positioning and handling activities of the 180’ Barge. Minimum
requirements: 2500 BHP
0 NOTE: the above capacity values has been adjusted to suit offshore operation
In the absence of specific manufacturers data Personnel shall not operate a crane in wind
speeds in excess of 10m/sec or swells greater than 2m.
6 Survey Spread
Complete Spread for :
Positioning and Navigation for Work Barge Stealth
Anchor Handling Support System for the AHT and Support Tug
As-Built Survey Equipment
USBL and UNDERWATER GYRO (IXSEA Octans 3000)
7 Diving Spread
Complete Air Diving Spread, comprises of but not limited to:
Dive Control Station
Deco Chamber (1-man or 2-man)
Dive LARS
Other supporting equipment and consumables
NO DESCRIPTION QTY
4-leg Dia.48mm x EL.20mtr Wire Rope, Soft Eye both Ends, Steel Ferrule
1 1 lot
assembled with 80T WLL Master Link
2 35T SWL Crosbly Shackle G-2130 4 nos
3 General Tools and Rigging 1 lot
7 PERMANENT MATERIALS
The permanent materials related to this scope of operation are detailed on this section.
TUGGER LINE
CONNECTION POINT
GYRO PROPOSED
POSITION
Figure 2 – PLEM GA
0 TUGGER LINE
CONNECTION POINT
PLEM
PLEM Type Skirted Gravity PLEM
Dimension (mtr) 8.5m x 12.05m x 2.5m with 1.5m skirt
Weight In Air (T) 54.7 T
Proposed SPM/PLEM Reference
541 526.00 m
0 Coordinate – Easting
Proposed SPM/PLEM Reference
9 246 742.00 m
Coordinate – Northing
Water Depth 25.5m LAT
NOTE:
SPM/PLEM Reference Center Coordinate shall be adjusted based on actual center point
between the spool piece on the PLEM.
7.2 Tolerances
The installation acceptance criteria and tolerances are presented in the following table:
8 PROCEDURE
NO DESCRIPTION
1 Activity Prior Commencement : ANCHOR POINT AND LEG INSTALLATION
2 Activity Prior Completion : PIPELINE AND SPOOL INSTALLATION
NO DESCRIPTION
PLEM shall be positioned as per S393-SPM-SBM-OPR-DWG-2351 PLEM Installation
1
Methodology and seafastened accordingly to the material barge deck.
Ensure all the hydraulic umbilical actuator valves position on the PLEM are as followed:
Secured a plum bob and a guide on the center protection cage of the PLEM to guide the
14
leveling on seabed.
Prior to any lifting operations or major construction operations, a JSEA will be conducted
15
as required in accordance to RA.
16 Ensure PLEM skirt is marked so diver can be easily identify penetration to seabed.
NOTE:
The above is for PLEM installation based on anchor points installation prior to PLEM
installation.
IF anchor points installation to be done after PLEM installation, then to note the following:
- To ensure clearance of Stealth anchor and anchor wire are clear from the PLEM at all
time
- To ensure the chain lay as per S393-SPM-SBM-ENG-DWG-2061 and chain
tensioning operation, are maintaining safe distance between to the PLEM
8.3 Installation
NO DESCRIPTION
Confirm weather window as referenced in Section 7.3. Once a suitable weather window
1
has been established, bring and secure material barge onto the port side of the Stealth.
2 Personnel and equipment shall be transferred to the material barge.
Confirm PLEM is pre-rigged as per S393-SPM-SBM-ENG-DWG-2055 PLEM - Lifting -
3 General Arrangement.
Note: intermediate 55T shackle is required between the 35T shackle and the slings
Install divers taglines, tugger lines, USBL beacon/Gyro, and other required installation aids
onto the PLEM.
Note: 2nos of 10T tugger lines shall be attached to each end of the PLEM for manoeuvring
Further details refer to Figure 2.
Gyro Stool (sample shown below) will be welded to inner part of the Stabilizer Pipe, the
offset from the target coordinate and centre PLEM will be recorded prior to PLEM
deployment and will be used as a reference.
Cut seafastening and connect the rigging to Stealth stern crane hook to the pre-installed
5 rigging. The seafastenings will be cut progressively, as and when they are required per the
installation sequence.
Lift PLEM off the material barge deck (1-2mtr clearance) and cast the barge away from
6
Stealth port side.
9 QUALITY
The activities detailed in this document shall be undertaken in accordance with the approved
Inspection and Test plan which attached on Appendix 2 of this Method Statement.
The applicable inspection formats as detailed in the Inspection and Test Plan shall be used
to record the inspections carried out. Sample of the Record Sheet is attached on Appendix 2
of this Method Statement.
11 CONTINGENCIES
The PLEM installation can be reversed at all stages of the operation. If recovery is required
the PLEM will be landed onto the material barge/Stealth deck.
12 APPENDICES
Activity: Diving (General) Assessment Purpose: (Preparation/Supplementary to method statement/following incident , etc.)
Activity: Diving (General) Assessment Purpose: (Preparation/Supplementary to method statement/following incident , etc.)
EL -
S -
E - Empowerment of
Seek advise from Barge Master -pertaining to under Barge master to
Personal Injury :- water current prior to start diving operation "stop diving
Strong surface or under water
Divers cuts/bruises/ lost at 2 4 4 Pre-planning Diving operation meeting with Barge 1 4 4 operation" in the -
current A
sea/Fatality master event of strong
Inform medical officer onboard prior to start diving surface/underwater
operation current at site.
EL -
S -
No diving operation in the event of unpermiting
E weather condition -advise seek from the Master of the
Barge
Working/Diving R f t S393 GEN LOPL OPR MS
Activity: Diving (General) Assessment Purpose: (Preparation/Supplementary to method statement/following incident , etc.)
S -
DEEP DIVING
EL -
S
E
Activity: Diving (General) Assessment Purpose: (Preparation/Supplementary to method statement/following incident , etc.)
Activity: Anchor Handling Assessment Purpose: (Preparation/Supplementary to method statement/following incident , etc.)
Preparation / Supplementary to Method Statement
Cause of
People/ Adverse Effect / Type
Ctrl Legal and Other
Job / Task Environment/ Adverse Effect / of Environmental L1 S1 RFN ** Mitigating Controls L2 S2 RRN * Assessment
Type Requirements Reference
Property at Risk Impact
Environmental Aspect
S -
E -
Lifting of Riggers, Skilled Injuries to the All rigging gear used must be tested and should have
Rigging failure, Slings damage. 3 4 12 1 4 4 - -
anchors labors. workers. SWL correctly marked. Experienced riggers shall be
A
deployed for the work. Pre start briefing must be done
before the start of work.
Hard Hat, Safety Shoes, Coveralls, Goggle, Hand
P
gloves, Work Vest.
EL -
S -
Only tested and certified anchor wire must be used,
Tug boat crew Preprty damage, E
Anchor lowering Breaking of anchor cable 3 3 9 load on anchor wire must be monitored all time. 1 3 3 - -
& crew on deck injuries to workers.
Proper regular inspection of anchore wire, pre start
A
meetings, tool box talks to be conducted.
CONTENTS
1 Definitions................................................................................................................................. 3
2 Inspection Test Plan Matrix.................................................................................................. 4
3 Project Standard Forms (PSF)............................................................................................. 6
1 Definitions
Random Witness RW indicates that the party shall choose to witness the
activity randomly when in process, but production need
not stop due to non-attendance
Inspection Requirement/
Op. Description of Operation/ Acceptance Sign Off
Control Procedure Record Generated Frequency
No. Inspection or Test Criteria Employer -
LOPL TPCA
TPA
Related
Documentation, All drawings and Drawing and Document
1. N/A 100 % documents P&H R M
procedures to be IFC and latest Rev register
approved
All materials conform to Specifications and Material certification, DNV inspection
2. S393-QAM-FRM-053 100 % R R M
Approved Client Approvals release note
Approved
Ensure PLEM Dimensions/Visual Approved Drawing S393- Drawing S393-
3. Inspection for welds and compliance, SPM-SBM-ENG-DWG- S393-QAM-FRM-053 100 % SPM-SBM- W W M
damages and any non conformance 2054 ENG-DWG-
2054
Approved Drawing S393-
Check & Ensure PLEM Cathodic SPM-SBM-ENG-DWG-
4. Protection anodes are installed accordingly 2047 & PLEM GA S393- S393-QAM-FRM-053 100 % No Damage P W M
SPM-SBM-ENG-DWG-
2054
Ensure all test records are filled in, fully Hydrotest
5. signed and accepted by Client/TPI PLEM Specifications Acceptance 100 % N/A R R M
Certificate
Carry out seabed debris survey prior to Approved MS S393-SPM- Diver’s Inspection No adverse
6. Installation of PLEM 100 % R R M
OPR-MS-2301 Report conditions
Approved MS S393-SPM-
7. PLEM Lowering N/A 100 % Approved MS RW RW W
OPR-MS-2301
Approved MS S393-SPM- Tolerance of +
8. Survey Set Out / PLEM Coordinates OPR-MS-2301 S393-QAM-FRM-124 100 % R R W
1.5 m
Approved MS S393-SPM- Tolerance of +
9. Check PLEM Heading S393-QAM-FRM-124 100 % W R W
OPR-MS-2301 20
Approved MS S393-SPM- Tolerance of +
10. Check PLEM Tilt S393-QAM-FRM-124 100 % R R W
OPR-MS-2301 30
MAR 2012 Page 4 of 6 S393-PL-LOPL-QAM-ITP-2301 (0)
TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
INSPECTION AND TEST PLAN
PLEM INSTALLATION
Inspection Requirement/
Op. Description of Operation/ Acceptance Sign Off
Control Procedure Record Generated Frequency
No. Inspection or Test Criteria Employer -
LOPL TPCA
TPA
Verification of Diver’s Inspection and As- Approved MS S393-SPM- Diver’s Inspection
11. 100 % N/A R R R
Built Report (including Video) OPR-MS-2301 Report and Video
Document No Description
S393-QAM-FRM-053 PLEM Receipt Inspection Report
S393-QAM-FRM-124 PLEM Installation Report
SHIFT
PLEM RECEIPT INSPECTION REPORT
PAGE NO.
IDENTIFICATION
Description Remarks Description Remarks
I/D Nos. Manufacturer’s Marks
Other Certifying Body Stamps
DAMAGE/REPAIRS
1. Description of Damages/Repairs. Attach Repair reports and
2.Sketch of damages (Photograph if required)
approvals as applicable
The material above has been inspected and judged to be (tick one)
Attach the following reports as applicable
Result of Receiving Inspection
Receiving Ins. Report. USOD Report Material Damage NCR
Approved in full for Installation N/A N/A N/A N/A
Approved but requires minor repair
Damaged/Major repair required
Rejected
Signature
Date
S393-QAM-FRM-053 (0)
Report No :
LEIGHTON OFFSHORE PTE LTD
Date :
PLEM INSTALLATION REPORT
Shift :
Page No:
Project :- TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT Contract No. :- S393
Location :-
FINAL POSITION
POSITION (CENTRE)
NORTHING EASTING
PLEM CENTER
TARGET 9 246 742.00 m 541 526.00 m
AS-BUILT
DELTA (Δ)
TOLERANCE ACTUAL
PLEM Position Circle 1.5mtr
(radius)
PLEM Heading ± 3 deg
PLEM Tilt ± 2 deg
Skirt Penetration 1.5mtr
Name :
Signature :
Date :
S393-QAM-FRM-124 (0)
TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation
APPROVED
Approved By : JG
OFFICIAL COPY - SO18021 - DSM84001A1 - S393-SPM-SBM-ENG-DWG-2041 - - PDF Generated on 22-Nov-2011 10:37AM
APPROVED
Approved By : JG
OFFICIAL COPY - SO18021 - DSM84002A1 - S393-SPM-SBM-ENG-DWG-2042 - - PDF Generated on 22-Nov-2011 10:39AM
APPROVED
Approved By : JG
OFFICIAL COPY - SO18021 - DSM84003A1 - S393-SPM-SBM-ENG-DWG-2043 - - PDF Generated on 22-Nov-2011 10:28AM
APPROVED
Approved By : JG
OFFICIAL COPY - SO18021 - DPM84007A1 - S393-SPM-SBM-ENG-DWG-2045 - - PDF Generated on 29-Nov-2011 4:14PM
APPROVED
Approved By : JG
OFFICIAL COPY - SO18021 - DPM84008A1 - S393-SPM-SBM-ENG-DWG-2046 - - PDF Generated on 29-Nov-2011 4:53PM
APPROVED
Approved By : JG
OFFICIAL COPY - SO18021 - DSM06003A1 - S393-SPM-SBM-ENG-DWG-2047 - - PDF Generated on 14-Nov-2011 1:36PM
APPROVED
Approved By : JG
OFFICIAL COPY - SO18021 - DMM19002A1 - S393-SPM-SBM-ENG-DWG-2048 - - PDF Generated on 24-Nov-2011 8:55AM
APPROVED
Approved By : JG
TANZANIA SPM & PIPELINES
REPLACEMENT EPC PROJECT
PROJECT NUMBER: S393
APPROVED
Approved By : JG
OFFICIAL COPY - SO18021 - DSM84005V1 - S393-SPM-SBM-ENG-DWG-2053 - - PDF Generated on 05-Oct-2011 2:10PM
APPROVED
Approved By : JG
OFFICIAL COPY - SO18021 - DSM84000A1 - S393-SPM-SBM-ENG-DWG-2054 - - PDF Generated on 24-Nov-2011 8:46AM
APPROVED
Approved By : JG
OFFICIAL COPY - SO18021 - DSM84006A1 - S393-SPM-SBM-ENG-DWG-2055 - - PDF Generated on 22-Nov-2011 10:35AM
APPROVED
Approved By : JG
OFFICIAL COPY - SO18021 - DPM84009A1 - S393-SPM-SBM-ENG-DWG-2056 - - PDF Generated on 08-Nov-2011 11:42AM
APPROVED
Approved By : JG
OFFICIAL COPY - SO18021 - DPM84010V1 - - - PDF Generated on 21-Dec-2011 5:43PM
APPROVED
Approved By : JG
S393-SPM-SBM-ENG-DWG-2057
OFFICIAL COPY - SO18021 - DMM19004A2 - S393-SPM-SBM-ENG-DWG-2172-00 - - PDF Generated on 08-Feb-2012 11:13AM
APPROVED
Approved By : JG
ANNEXE - PDF Generated on 08-Feb-2012 11:14AM
APPROVED
Approved By : JG
ANNEXE - PDF Generated on 08-Feb-2012 11:16AM
APPROVED
Approved By : JG
STEP 1 STEP 2
1. SET UP STEALTH & PLEM BARGE ON PROPOSED LOCATION. 1. RIG AND CONNECT 2 Nos 10T AIR TUGGER WIRE FROM STEALTH DECK TO EACH END OF THE PLEM.
2. SURVEY PROPOSED PLEM LOCATION BY DIVERS. 2. CUT SEA FASTENING AND LIFT PLEM OF THE BARGE.
3. INSPECT PLEM AND COMMENCE INSTALLING INSTALLATION AIDS I.E. USBL BEACONS, RIGGING, GYRO ETC. 3. LOWER PLEM TO 5m ABOVE SEABED USING USBL BEACON AND / OR GYRO AND DIVER SUPPORT.
P2
PROPOSED
PLEM CENTER
541 526.00 mE
9 246742.00 mN
P1
PICK-UP INSTALLATION MIN. RADIUS =8m
RADIUS = 13 m MAX. LIFT = 93.7 T (80 T Block)
MAX. LIFT = 66 T (80 T Block) MAX. HEAD BOOM = 34.2 m (80 T Block) 49
°
MAX. HEAD BOOM = 32.2 m (80 T Block) (*) OFFSHORE RATED LOAD
(*) OFFSHORE RATED LOAD
18
°
BOOM LGTH. INSTALLATION
39.6 m CRANE
CRANE STEALTH
LCT-KESTREL BLOCK
43°
73°
P3
S1
PLEM WEIGHT IN AIR = 56.7 Te
20 m
1.5 m
LCT-KESTREL
FE
ND
ER
ING S2
E
LIN
72°
PREVAILING WEATHER
IPE
DP
O SE
OP
PR 1m
P4
SW
OM
FROM SOUTH
FR
MAX. RADIUS = 36 m
MAX. LIFT = 17.2 T (80 T Block)
S4 MAX. HEAD BOOM = 14.2 m (80 T Block)
6°
46
°
PLAN VIEW
MAl
S393
NSa
03-03-2012 A3 S393-SPM-LOPL-OPR-DWG-2351 1 OF 2 0
STEP 3
1. ORIENTATE PLEM VIA CRANE MOVEMENT AND 2 Nos 10T AIR TUGGER WIRE.
2. CONFIRM ALIGNMENT AND ORIENTATION OF PLEM OVER TARGET LOCATION USING USBL BEACON GYRO AND DIVERS ASSISTANCE.
3. CONFIRM PLEM LEVELING. SLOWLY LOWER PLEM WITH GUIDANCE FROM DIVERS .
4. LAND PLEM ON SEABED.
5. TAKE A SURVEY FIX ON EACH CORNER USING DIVER HANDHELD USBL BEACON.
6. DISCONNECT RIGGING WITH DIVERS AND RECOVER TO SURFACE.
INSTALLATION
INSTALLATION CRANE
CRANE 39.6m BOOM LGTH.
39.6m BOOM LGTH.
STEALTH STEALTH
CRANE
BLOCK
DIVER
PROPOSED TIE-IN
SPOOL POSITION
PIPELINE END
SEABED (LAT) -25.5m SEABED (LAT) -25.5m
MAl
S393
NSa
03-03-2012 A3 S393-SPM-LOPL-OPR-DWG-2351 2 OF 2 0
NOTES:
1. ALL DIMENSION ARE IN METERS UNLESS NOTED OTHERWISE.
2. GEODETIC PARAMETERS
N DATUM : WGS 84
ELLIPSOID : WGS 84
9 247 500 mN
PROJECTION : UNIVERSAL TRANSVERSE MERCATOR
P2 CENTRAL MERIDIAN : 39° EAST (UTM ZONE 37)
UNITS : METRES
3. TWIN PIPELINES & TIE-IN SPOOL ARE OMITTED FOR CLARITY
IN DRAWING.
4. CHAIN LENGTH = 330m
5. CD = CHART DATUM
P1
LEGEND:
9 247 250 mN
P3 = EXISTING ANCHOR
PROPOSED
BUOY/PLEM CENTER = PROPOSED BUOY/PLEM CENTRE
541 526.00 mE
9 246742.00 mN
= EXISTING BUOY/PLEM CENTRE
700 m
m
P S = PORT & STBD SIDE ANCHORAGE
0
70
9 247 000 mN A3
70
A2 0
m
49
.0
18
°
KP
.0
3.6 ANCHOR COORDINATES 1st POSITION (START-UP)
°
LCT-KESTREL
ANCHOR COORDINATES HORZ. DIST. WATER DEPTH
EXISTING NO. EASTING (m) NORTHING (m) (m) (m)
SPM
P1 542076.12 9 247282.55 700 25.5
540 751.292 mE
43.0°
9 246698.667 mN P2 541740.85 9 247455.86 700 27.0
A1
9 246 750 mN 72.0° P3 541003.48 9 247203.80 700 26.4
P4 540970.86 9 246628.78 550 23.6
53
73.0°
1 A4 S1 542291.04 9 246578.80 700 22.2
EXISTING ANCHOR
550 m S2 542114.59 9 246258.53 700 23.4
700 m
S3 541349.67 9 246023.52 700 21.4
S4 540954.16 9 246296.08 700 22.0
19.0
PIPELAY BARGE
KP (STBD SIDE)
3.0 P4
°
S1
6.0
°
70
9 246 500 mN 0
0m m
NG 70
TI E
IS LIN A5 46
EX IPE .0
P °
700 m
A6
13
5
ED
OS
OP INE
11
PR IPEL
0
S4
9 246 250 mN
S2
9 246 000 mN
S3
540 500 mE
540 750 mE
541 000 mE
541 250 mE
541 500 mE
541 750 mE
542 000 mE
542 250 mE
542 500 mE
TANZANIA SPM AND PIPELINES REPLACEMENT EPC PROJECT
TANZANIA PORTS AUTHORITY
MAl
S393
NSa
KKa/LMa
PLEM INSTALLATION
ANCHOR PATTERN
N.T.S
03-03-2012 A3 S393-SPM-LOPL-OPR-DWG-2367 1 OF 1 0
NOTES:
1. ALL DIMENSIONS ARE IN METRES UNLESS NOTED OTHERWISE.
541520.899 E 541528.317 E
9246743.407 N 9246747.557 N
X
(X=0.000, Y=0.000)
541525.050 E 541532.468 E
9246735.989 N 9246740.140 N
MAl
S393
NSa
04-03-2012 A3 S393-SPM-LOPL-OPR-DWG-2368 1 OF 1 0
TANZANIA SPM & PIPELINES REPLACEMENT EPC PROJECT
Method Statement – PLEM Installation
GENERAL
ABS + A1 Accommodation/ Work Barge,
Class
Helideck
Flag Singapore
Port of Register Singapore
Year of Built 2006
Special Purpose Ship Safety (SPS)
Additional Compliance CAP 437 Helideck
MODU CODE
DIMENSIONS
LOA 100m (330 ft)
Breadth 30m (100ft)
Depth 6m (20 ft)
Draft (Minimum) 2.8m
Draft (Maximum) 4.5m
Deck Loading Capacity 15MT/m2
MOORING SYSTEM
Mooring Arrangement 9 point mooring system
5 x single drum, 45MT (mid drum) capacity,
Forward Mooring Winches complete with 1200m of 42mm diameter
wire rope.
4 x single drum, 35MT (mid drum) capacity,
Aft Winches complete with 1000m of 42mm diameter
wire rope.
Local and remote control. Electro hydraulic
Winch Control System
system
Fully automatic with payout length and
Tension Monitoring System
tension measurement.
5 off 7MT delta flipper and 4 off 5MT delta
flipper
Anchors 8 x STEVPRIS 8MT
2 x DELTA FLIPPER 11MT
PIPELAY CAPABILITY
Tensioner 2 x 50MT track tensioners
Maximum pipe size 60” OD
Minimum pipe size 8” OD
Fully automatic electro hydraulic with
Control System manual override joystick control, pay in and
pay out.
7 total (1 x fitup plus root and hotpass, 2 x
Work stations fill, 1 x cap, 1 x NDT, 1 x repair and 1 x field
joint coating and strapping).
Fully automatic (manual and semi-auto also
Welding System
possible)
100 MT capacity single drum complete with
Abandonment and Recovery Winch
600m of 64mm diameter wire rope.
1 unit horizontal pipe conveyor, 6 units
longitudinal elevating rollers, 3 units
longitudinal fixed rollers, 1 auxiliary roller
Pipe handling System and 3 stinger rollers. 2 transfer vehicles and
2 line up tables.
Electro hydraulic control system.
Pipe Ramp 2.77 degree inclination.
Stinger Fixed type
MACHINERY
4 x 1000 kW
1 x 400 kW (Harbor)
Generators
1 x 400 kW (Emergency)
System Voltage: 415V, 3 Phase, 50Hz
Air compressors 4 x 290 cfm
Hamworthy Model ST15 suitable for 240
Sewerage Treatment Plant
persons.
LIFTING DEVICES
2 x 280 MT lift capacity Sumitomo model
SCX2800
Deck mounted cranes
Crawler cranes complete with 45m boom,
main hook, and auxiliary hook and whip line.
4 x 50MT DAVITS (Additional davits
Davits
available)
Lifting capacity 500MT (suitable for lifting
A Frame
subsea structures including PLEMS)
SERVICE TANKS
Fresh Water Storage 1100 m3 (approx)
Marine Diesel Storage 1100 m3 (approx)
Certified tank barge with full ballast system
Ballast
comprising 10 ballastable compartments.
SAFETY EQUIPMENT
COLREGS compliant navigation
Navigation
arrangement
Life Rafts 16 x 25 persons
Life Vests For 264 persons
Life Boats 2 x 116 persons
Rescue Boats 2 x Viking 470 GRP
ACCOMODATION
Suitable for 232 persons in 1,2 & 4 man
Accommodation
cabins.
HELICOPTER FACILITIES
CAP437 compliant helideck.
Suitable for S61 and S92 aircraft
CAP 437 & ABS HELIDK
13 APPLICABLE DRAWINGS
13.1 GENERAL ARRANGEMENT
SUBTECH IMVUBU Pg 15 of 49
SCX2800-2 CRAWLER CRANE RATED LOAD FOR MAIN BOOM - PICK & CARRY EC410033
Unit: ton P.1 / 3
Boom length (m) 18.3 21.3 24.4 27.4 30.5 33.5 36.6 39.6 42.7 45.7 48.8 51.8 Boom length (m)
Reeved lines 18 16 16 14 12 11 10 9 9 8 7 7 Reeved lines
Wind (m/sec) 17 17 14 14 14 14 14 14 11 11 11 11 Wind (m/sec)
Radius (m) Radius (m)
4.8 188.6 5.2m x 4.8
5.0 188.1 167.7t 5.7m x 5.0
5.5 173.3 167.0 167.0t 6.1m x 6.6m x 5.5
6.0 159.6 159.3 159.0 146.7t 125.7t 7.5m x 6.0
7.0 137.6 137.4 137.1 136.8 125.7 115.2 104.8t 8.4m x 8.9m x 7.0
8.0 120.8 120.6 120.4 120.1 120.0 114.7 104.6 93.7 94.3t 83.8t 9.3m x 9.8m x 8.0
9.0 107.6 107.3 107.1 106.8 106.2 103.1 101.3 93.0 94.3 83.8 73.3t 72.3t 9.0
10.0 96.8 96.6 96.3 96.1 93.9 91.3 90.0 87.7 85.4 83.3 73.3 72.2 10.0
12.0 79.3 79.2 79.1 77.7 75.9 74.0 73.4 71.8 70.1 68.6 67.1 65.6 12.0
14.0 63.6 63.5 63.4 63.2 63.2 62.0 61.8 60.4 59.0 57.9 56.8 55.5 14.0
16.0 52.7 52.7 52.6 52.4 52.4 52.2 53.1 52.0 50.9 50.0 49.0 48.0 16.0
18.0 17.6m x 44.7 44.7 44.5 44.4 44.2 45.1 45.0 44.5 43.8 43.0 42.0 18.0
20.0 46.4t 38.8 38.7 38.5 38.4 38.2 39.1 38.9 38.7 38.5 38.1 37.3 20.0
22.0 20.2m x 34.0 33.8 33.7 33.5 34.3 34.1 33.9 33.8 33.6 33.3 22.0
24.0 38.4t 22.8m x 30.0 29.8 29.6 30.5 30.2 30.0 30.0 29.8 29.5 24.0
26.0 32.4t 25.5m x 26.7 26.5 27.3 27.1 26.9 26.7 26.6 26.3 26.0
28.0 27.7t 24.2 23.9 24.6 24.5 24.2 24.2 23.9 23.7 28.0
30.0 28.1m x 21.7 22.5 22.2 21.9 21.8 21.7 21.5 30.0
32.0 24.0t 30.8m x 20.5 20.3 20.0 19.9 19.7 19.5 32.0
34.0 20.9t 33.4m x 18.7 18.4 18.3 18.0 17.8 34.0
36.0 19.4t 17.2 16.9 16.8 16.6 16.3 36.0
38.0 15.6 15.5 15.2 14.9 38.0
40.0 38.7m x 14.4 14.1 13.8 40.0
42.0 15.2t 41.3m x 13.1 12.8 42.0
44.0 13.7t 12.2 11.8 44.0
46.0 11.1 46.0
46.6 10.9 46.6
1.The rated loads are determined according to EN13000 rating on the condition that the machine is stationed on firm, level ground.
2.Be sure to remove the hanger sheaves block from the top boom when boom length is 36.6m or more.
3.To calculate the maximum load that can actually be lifted, deduct weight of all lifting accessories, such as boom hook and jib hook, from figures shown above.
4.Working radius is the horizontal distance from the slewing center to the center of gravity of a lifted load.
5.The counterweight is 120.8 ton. (Superstructure 102.8ton + Undercarriage 18.0 ton )
6.Be sure to fully extend the side frames before operating the machine.
7.Correlation between the number of reeved lines, maximum rated loads, hook weights are shown in the table below.
8.Capacities shown are in metric tons, and are based on 66% of minimum tipping loads with machine standing level on firm supporting surface under ideal job conditions.
9.Travel speed must be less than 0.4km/h and cautiously in order to avoid shock loading.
10.Position the load lower than 500mm (or as lower as possible) above the ground.
11.Position the lifted load in front of the crawler while traveling forward.
12.Engage the slewing lock and apply the slewing brake.
1.The rated loads are determined according to EN13000 rating on the condition that the machine is stationed on firm, level ground.
2.Be sure to remove the hanger sheaves block from the top boom when boom length is 36.6m or more.
3.To calculate the maximum load that can actually be lifted, deduct weight of all lifting accessories, such as boom hook and jib hook, from figures shown above.
4.Working radius is the horizontal distance from the slewing center to the center of gravity of a lifted load.
5.The counterweight is 120.8 ton. (Superstructure 102.8ton + Undercarriage 18.0 ton )
6.Be sure to fully extend the side frames before operating the machine.
7.Correlation between the number of reeved lines, maximum rated loads, hook weights are shown in the table below.
8.Capacities shown are in metric tons, and are based on 66% of minimum tipping loads with machine standing level on firm supporting surface under ideal job conditions.
9.Travel speed must be less than 0.4km/h and cautiously in order to avoid shock loading.
10.Position the load lower than 500mm (or as lower as possible) above the ground.
11.Position the lifted load in front of the crawler while traveling forward.
12.Engage the slewing lock and apply the slewing brake.
1.The rated loads are determined according to EN13000 rating on the condition that the machine is stationed on firm, level ground.
2.Be sure to remove the hanger sheaves block from the top boom when boom length is 36.6m or more.
3.To calculate the maximum load that can actually be lifted, deduct weight of all lifting accessories, such as boom hook and jib hook, from figures shown above.
4.Working radius is the horizontal distance from the slewing center to the center of gravity of a lifted load.
5.The counterweight is 120.8 ton. (Superstructure 102.8ton + Undercarriage 18.0 ton )
6.Be sure to fully extend the side frames before operating the machine.
7.Capacities shown are in metric tons, and are based on 66% of minimum tipping loads with machine standing level on firm supporting surface under ideal job conditions.
8.Travel speed must be less than 0.4km/h and cautiously in order to avoid shock loading.
9.Position the load lower than 500mm (or as lower as possible) above the ground.
10.Position the lifted load in front of the crawler while traveling forward.
11.Engage the slewing lock and apply the slewing brake.
OCTANS
Subsea Unit
Models 3000 TI
User’s guide
February 2002
iXSEA Document n° : MU/3453/EGF/001
TABLE OF CONTENTS
RIGHTS......................................................................................................5
WARRANTY .............................................................................................6
CUSTOMER SUPPORT............................................................................7
EXPORTS ..................................................................................................8
SHIPPING PACK CONTENTS.................................................................9
I- INTRODUCTION ............................................................................................................10
II- TECHNICAL DESCRIPTION.....................................................................................11
Figure 1 : Subsea Octans unit opened.......................................................................11
II-1 Fiberoptic gyrometer description..............................................................................12
Random walk: 0.0025 deg/ hour............................................................................12
II-2 Accelerometer description ........................................................................................12
II-3 Computer description ...............................................................................................13
III- MECHANICAL INTERFACE.................................................................................14
Figure 2 : Subsea Octans bottom plate mounting diagram.......................................14
IV- ELECTRICAL INTERFACE .......................................................................................15
IV-1 Description of the top panel......................................................................................15
Figure 3 : Subsea Octans top panel...........................................................................15
IV-2 Listing of interfaces ..................................................................................................16
IV-3 Description of the 13-pin connector .........................................................................16
IV-4 Power supply (pins 1, 2) ...........................................................................................17
IV-5 IXSEA configuration and display output (pins 9, 11, 12, 13) ..................................18
IV-6 Analog Ouputs (pins 7, 8).........................................................................................19
IV-7 Digital Input/Output (pins 3, 4, 5, 6 and 10) ............................................................20
IV-7.1 RS 232 Input / Ouput ............................................................................................21
IV-7.2 RS 422 Input/ Output ............................................................................................22
V. POSSIBLE SOURCES OF ERRORS ..............................................................................23
V-1 Heading error due to the speed log ...........................................................................23
V-2 Error due to unreliable latitude data .........................................................................24
VI- COMPUTATION OF HEAVE, SURGE, AND SWAY ..............................................25
VI-1 Definition of heave, surge, and sway........................................................................25
VI-2 Axis directions for heave, surge and sway measurements........................................25
VI-2.1 General ..................................................................................................................25
VI-2.2 Sign conventions ...................................................................................................26
VI-3 Choice of the high-pass filter....................................................................................26
VI-3.1 General behaviour of an heave, surge and sway filter...........................................26
VI-3.2 Guidance for tuning the filter ................................................................................27
VI-4 Use of lever arms for heave computation .................................................................28
VI-4.1 Multiple lever arms...........................................................................................28
Figure 6: Multiple lever arms monitoring ................................................................28
VI-4.2 Effect of a lever arm on the computation of heave ...............................................29
Figure 7 : Effect of lever arms ..................................................................................29
VII- TRUE HEADING, ROLL AND PITCH ......................................................................31
Figure 9 : Definition of true heading ........................................................................31
VII-2 Roll .......................................................................................................................31
Commercial in Confidence
2/44
iXSEA Document n° : MU/3453/EGF/001
Commercial in Confidence
3/44
iXSEA Document n° : MU/3453/EGF/001
FOREWORD
This document serves as the user’s guide for the subsea versions, model 1000 and 3000, of the
Gyrocompass and Motion Sensor Octans developed and manufactured by IXSEA. For any
question, contact your nearest IXSEA’s representative or directly IXSEA at:
Commercial in Confidence
4/44
iXSEA Document n° : MU/3453/EGF/001
RIGHTS
All IXSEA products, and notably FOG technology, are protected by patents that have either
already been issued or which have been formally applied for. The information contained in
this manual supersedes all previously published information. IXSEA reserves the right to
change prices and technical specifications.
Printed in France by IXSEA S.A.S., 55, Avenue Auguste Renoir, F-78160 Marly-le-Roi.
Commercial in Confidence
5/44
iXSEA Document n° : MU/3453/EGF/001
WARRANTY
IXSEA provides a warranty covering this product against any defect in materials or
manufacture for a period of one (1) year from the date of shipment. In the event that such a
defect becomes manifest during the stipulated warranty period, IXSEA undertakes, at its sole
discretion, either to repair the defective product, bearing the cost of all parts and labor, or to
replace it with an identical product.
In order to avail itself of the present warranty, Customer must notify IXSEA of the defect
before expiry of the warranty period and take all steps necessary to enable IXSEA to take the
required action. Customer shall be responsible for the packaging and shipment of the defective
product for delivery to the repair center notified by IXSEA, the cost of such shipment being
borne by Customer. IXSEA agrees to bear the cost of return shipment of product to Customer,
who undertakes to pay all taxes, dues and expenses arising from such shipment.
This warranty shall not be construed as covering defects, malfunctions or damage caused by
improper use or inadequate maintenance of the product. Under no circumstances shall IXSEA
be obligated to provide repair or replacement under this warranty in order a) to repair
damage caused by work done by any person not representing IXSEA for the installation,
repair or maintenance of the product ; b) to repair damage caused by improper use or
connection to incompatible equipment, and specifically, the opening of the housing of the
equipment under warranty shall cause the warranty to be automatically cancelled ; c) to
maintain any product that has been modified or integrated into a larger configuration, if such
modification or integration increases the duration or difficulty of the maintenance of said
product.
This warranty covers the product hereunder and is provided by IXSEA in place of all
and any other warranty whether explicit or implicit. IXSEA does not guarantee the
suitability of the product under warranty for sale or any specific use. IXSEA’s liability
is limited to the repair or replacement of defective products, this being the sole remedy
open to Customer in the event the warranty becomes applicable. IXSEA cannot be held
liable for indirect, special, subsequent or consequential damage, irrespective of whether
IXSEA has or has not received prior notification of the risk of occurrence of such
damage.
Commercial in Confidence
6/44
iXSEA Document n° : MU/3453/EGF/001
CUSTOMER SUPPORT
To obtain support or information on any of our products, please contact IXSEA directly, or
one of its local representatives.
• IXSEA S.A.S.
55, Avenue Auguste Renoir,
78160 Marly-le-Roi,
France
Tel.: + 33 (0)1 30 08 98 88
Fax: + 33 (0)1 30 08 88 01
E-mail: info@ixsea.com
Commercial in Confidence
7/44
iXSEA Document n° : MU/3453/EGF/001
EXPORTS
OCTANS is free of exportand use worlwide, excpet in the following countries (list dated
december 2001):
OCTANS cannot be export or re-export in the territory of :
Afganistan, Angola, Myanar, Cuba, Iran, Iraq, Lybia, North Korea, Sudan, Syria,
Serbia Montenegro.
Commercial in Confidence
8/44
iXSEA Document n° : MU/3453/EGF/001
You will find in the shipping case a Packing List detailing all the items referred to above. This
Packing List was completed and checked by IXSEA shortly before shipment, and should
logically match the contents of the pack you have received.
However, we recommend that you check the contents of the pack and the equipment
immediately on receipt of your OCTANS unit. Specifically, you should check that all the
items referred to above are present on delivery and that none has sustained damage.
If you observe any non-conformity or damage, please inform the carrier and IXSEA without
delay by certified mail, describing in detail the nature of the problem.
Commercial in Confidence
9/44
iXSEA Document n° : MU/3453/EGF/001
I- INTRODUCTION
Octans 3000 TI are the members of the Octans family dedicated to underwater applications
(down to 3000 m), featuring a specific waterproof housing in Titanium (13 kg total weight in
air).
Octans is both a fiber-optic survey-grade IMO-certified gyrocompass and a Motion Reference
Unit for marine applications that provides true-heading, roll, pitch, yaw, heave, surge, sway,
rates of turn and accelerations even in highly volatile environments. Octans is also certified to
meet to the requirements of the International Maritime Organisation (IMO) for
gyrocompasses. Its heart consists of a small strapdown Inertial Measurement Unit (IMU),
which contains three accelerometers, three fiberoptic gyrometers, and a real-time computer.
The fiberoptic gyrometer is a recent technology generated to meet the requirements of the
aeronautical industry. It is totally inert, has no moving parts, and requires neither maintenance
nor recalibration. It is capable of a very wide dynamic range and can tolerate extremely
demanding mechanical environments without compromise to its performances.
Octans features the benefits of fiberoptic gyrometer technology and therefore shares the
advantages of not requiring maintenance or recalibration. Its strapdown IMU structure enables
straightforward, effective use with which no traditional mechanical gyrocompass can
compete. Octans is insensitive to physical shock, can be carried in a case, and is easy to
install. Strapdown equation processing enables the system to find North in less than 5 minutes
whatever the sea conditions may be. Notably, it can be powered up at sea, which is impossible
with a conventional gyrocompass.
In addition, Octans consumes only a small amount of power and directly outputs binary data
to NMEA 0183 standard, which can be reconfigured if desired, in addition to analog data
allowing easy interfacing with most available repeaters.
This document briefly describes how a subsea Octans works, and provides in more detail all
the possible interfaces which can be configured.
Commercial in Confidence
10/44
iXSEA Document n° : MU/3453/EGF/001
Commercial in Confidence
11/44
iXSEA Document n° : MU/3453/EGF/001
The fiberoptic gyrometers contain fiberoptic coils with a length of nearly 800 m and an
average diameter of 90 mm.
These fiberoptic gyrometers are manufactured by iXSEA and are used for other applications,
notably for military and aerospace applications.
The accelerometers are of pendulum type, particularly suited for attitude detection.
The accelerometers can withstand a severe environment in mechanical and thermal terms:
Physical shock: 250 g
Vibration: 25 g peak, 20 Hz to 2000 Hz
Temperature: -55°C to +95°C
Commercial in Confidence
12/44
iXSEA Document n° : MU/3453/EGF/001
The unit’s computer is a Digital Signal Processor (DSP) chip enabling rapid and complex
real-time computation. This computation relates particularly to angle integration using
quaternion algebra, a heading search algorithm and Coriolis force correction for vessel speed.
The heading search algorithm is specific to IXSEA and is suited to use with a strapdown IMU.
It enables the heading to be sought whether the system is in movement or not and without an
external reference point. It is based on (filtered) measurement of shifts in local gravity as the
Earth rotates. This is possible because, in relation to an inertial reference frame, local gravity
moves within a cone whose axis is related to the direction of the Earth’s rotational vector (its
North-South axis). Monitoring the movements in local gravity enables the axis of the cone to
be determined and therefore the direction of geographical North. More detail on the algorithm
used are given in appendix B.
Commercial in Confidence
13/44
iXSEA Document n° : MU/3453/EGF/001
All our subsea units are designed as a standard for use on a vertical configuration.
For a subsea use in an horizontal configuration, please consult IXSEA.
Commercial in Confidence
15/44
iXSEA Document n° : MU/3453/EGF/001
The 16-pin connector fitted on subsea octans is used to provide the following:
Commercial in Confidence
16/44
iXSEA Document n° : MU/3453/EGF/001
24 V DC
Electrical Ground
NOTE: IMPORTANT
Please remember that any interruption of the power supply, even brief, will return the system
to its initial condition and it will begin to seek North again.
Commercial in Confidence
17/44
iXSEA Document n° : MU/3453/EGF/001
IV-5 IXSEA configuration and display output (pins 9, 11, 12, 13)
ConfigOutGnd
ConfigIn+
ConfigOutV+
ConfigIn-
The pins 9, 11, 12, 13 are used to link the subsea Octans directly to the IXSEA Octans
Installation and configuration Software.
In order to install, configure Octans or to use the Display Data, please connect your subsea
Octans to a PC using a standard SUB D9 connector.
ConfigOutGnd (pin 9)
Commercial in Confidence
18/44
iXSEA Document n° : MU/3453/EGF/001
AnaOutASig
AnaOutGnd
Commercial in Confidence
19/44
iXSEA Document n° : MU/3453/EGF/001
Commercial in Confidence
20/44
iXSEA Document n° : MU/3453/EGF/001
RS232
RS232
RS232
RS232
Note 1 : It is possible to connect the OutGnd to the InGnd pins to allow the use of
1 single Sub D9 connector for I/O,
Commercial in Confidence
21/44
iXSEA Document n° : MU/3453/EGF/001
RS422
RS422
RS422
RS422
RS422
A SerOutGnd (10) SerOutV+/232 (3) SerOutV- (4) SerInV+ (5) SerInV- (6)
Commercial in Confidence
22/44
iXSEA Document n° : MU/3453/EGF/001
This speed correction applies whatever the technology used in the gyroscopes: Indeed, the
linear speed of a boat travelling on the terrestrial “sphere” produces, with respect to the Earth
and therefore with respect to the inertial frame of reference, a rotational speed V/R, where R is
the radius of the Earth. This disturbs the measurement of the speed of rotation of the Earth and
therefore the detection of North.
Using the above formula, it is easy to compute the speed level at which the heading will begin
to demonstrate an error, if the accuracy of the heading measurement is known: Octans has an
dynamic accuracy of 0.2 degree x secant of latitude and therefore the speed in knots at which
an error greater than this appears is V Northmax = 0.2 x 5 3,2 knots.
Given that this is a relatively low value, it is generally recommended to enter the speed in
Octans to allow the unit to compensate automatically and indicate the correct heading. It can
be seen from the above formula however that the speed needs to be known only to a few
knots. In practice, a log which gives the speed of the vessel in relation to the water without
intrinsically taking into account the surface currents is more than satisfactory for such
compensation. Since all ships are equipped with GPS, the GPS speed can also be entered.
Commercial in Confidence
23/44
iXSEA Document n° : MU/3453/EGF/001
Octans needs to know the latitude of its location in order to find geographical North rapidly. If
the latitude information input is incorrect, Octans will produce an error. This error is
nevertheless very small: The curve in the figure 4 shows the heading error in degrees
multiplied by the secant of the latitude versus the latitude of the current location, assuming
that the latitude entered in the Octans unit is incorrect by one degree. In practice, Octans needs
to know the latitude only to an accuracy of a 5 degrees or so. Please note that this dependency
is slightly more important at low latitudes and it is recommended below 30° to enter the
current latitude in the system with at worst a 3° accuracy.
In practice, it is possible to enter the latitude directly to Octans by using a GPS NMEA
sentence. You can also manually enter the latitude, please refer to the Octans Installation
Software.
0,05
0,04
0,03
Error in degrees
0,02
0,01
0
0 10 20 30 40 50 60 70 80 90
-0,01
-0,02
-0,03
Latitude in degrees
Fig. 4 : Heading error in degrees by secant of latitude for a 1 degree latitude error
Example:
At 40° latitude, an error of 3° in the latitude will cause 3x0,02 = 0,06° sec. Lat error.
Commercial in Confidence
24/44
iXSEA Document n° : MU/3453/EGF/001
VI-2.1 General
Base Plate
Surge (horizontal)
Heave (vertical)
Base Plate
Figure 5 : Axis directions for the heave, surge, and sway measurements
Commercial in Confidence
25/44
iXSEA Document n° : MU/3453/EGF/001
The heave, surge, and sway are computed by the double integration of the three
accelerations. The frequency response of Octans for the heave measurement, which is
the ratio between the measured heave and the exact vertical position, is :
3
é f ù
ê j f c úú
H( f ) = ê
ê
j úú
f where fc is the cut-off frequency of the high-pass filter.
ê1 + fc û
ë
Commercial in Confidence
26/44
iXSEA Document n° : MU/3453/EGF/001
æ jT f ö
3
ç o ÷
H( f ) = ç ÷
ç 1 + jT f ÷
è o ø
Where "To" is the adjustment parameter that the operator can modify in order to adjust
the heave behaviour to the sea state. For more detail, please refer to the "Octans
Installation Software" or the "Repeater Software".
Please refer the application note ‘’HEAVE TOOL’’ file included in the installation
and configuration software CD if you wish to assess the effect of different To settings.
Commercial in Confidence
27/44
iXSEA Document n° : MU/3453/EGF/001
Lever Arm 1,
Protocol 1
Octans
Lever Arm 3,
Protocol 3
Lever Arm 2,
Protocol 2
Figure 6: Multiple lever arms monitoring
Commercial in Confidence
28/44
iXSEA Document n° : MU/3453/EGF/001
Monitoring
point
Axis 1 Heave ≠ 0
Octans
Heave = 0
Pitch angle
Horizontal plane
To avoid this effect, it is recommended to place the subsea Octans as close as possible
to the monitoring point.
Otherwise, it is possible to compensate the effects of lever arms by computation. To
perform this computation, it is necessary to know the exact place of the monitoring
point in the frame of the subsea Octans . It is possible to give the vector ( X1 , X2 , X3 )
to Octans using the Octans Installation Software. The definition of this vector follows
(see figure 8, next page).
Commercial in Confidence
29/44
iXSEA Document n° : MU/3453/EGF/001
Axis 1
Monitoring point
X1
Top Panel
Axis 2
X2
Axis 3
X3
Axis 1
X1
Commercial in Confidence
30/44
iXSEA Document n° : MU/3453/EGF/001
True North
Heading Axis 1
VII-2 Roll
The roll is the angle between the horizontal plane and the axis 2 of the subsea Octans. This
angle is default defined positive in the direction of axis 1, i.e. when the vehicle’s port side is
up.
Axis 1
Roll angle
Commercial in Confidence
31/44
iXSEA Document n° : MU/3453/EGF/001
VII-3 Pitch
The pitch is the angle between the horizontal plane and the axis 1 of the subsea Octans. This
angle is default defined positive in the direction of axis 2, i.e. when the vehicle’s bow is
down.
Axis 2
Pitch angle
Commercial in Confidence
32/44
iXSEA Document n° : MU/3453/EGF/001
APPENDIX A-SPECIFICATION
Commercial in Confidence
33/44
iXSEA Document n° : MU/3453/EGF/001
1. TECHNICAL DESCRIPTION
Octans in an IMO-compliant survey-grade gyrocompass and an integral motion sensor at
the same time.
1.1. Performances
No Latitude limitation
No speed limitation
(*) Secant Latitude = 1/cosine Latitude
Commercial in Confidence
34/44
iXSEA Document n° : MU/3453/EGF/001
1.2. Environment
Environmental specifications
Operating temperature : -40°C to +60°C
Storage temperature : -40°C to +80°C
Shocks : 30 g in 6 ms (operating)
50 g in 11 ms (survival)
Vibrations : 1 g sine (5 to 50 Hz)
MTBF 30 000 Hours
1.3. Interface
1.3.2 Outputs
• Serial: 3 independent and configurable digital outputs (Surface Octans)
Or 1 configurable digital output (Sub-sea Octans)
To be chosen among a complete set of existing protocols (NMEA
0183, TSS, Seatex, Simrad, Robertson, Tokimec, Anschutz
Compatible) or any custom protocol, with RS 232 or RS 422 levels
• Analogue: 4 independent and configurable analogue outputs, 14 bits / ± 10
V, (Surface Octans)
Or 1 configurable analogue output,14 bits / ± 10 V, (Sub-sea Octans),
• Pulses
• Update rate: up to 300 Hz
1.3.3 Inputs
• Serial: 3 independent and configurable digital inputs (Surface Octans),
Or 1 configurable digital output (Sub-sea Octans)
• Analogue: 2 independent and configurable analogue inputs, 16 bits / ±15
V,
• Pulses
• Update rate : up to 300 Hz
Commercial in Confidence
35/44
iXSEA Document n° : MU/3453/EGF/001
1.4. Housings
Commercial in Confidence
36/44
iXSEA Document n° : MU/3453/EGF/001
Commercial in Confidence
37/44
iXSEA Document n° : MU/3453/EGF/001
2. CERTIFICATION
Octans complies with the regulations of the International Maritime Organisation
resolutions A.424 (XI), A. 694 (17), A.183 (19) for gyrocompasses, with SOLAS 74 as
amended (regulations V/12 (d), (i)) and IEC 60945, IEC 61162-1 and ISO 8728.
Commercial in Confidence
38/44
iXSEA Document n° : MU/3453/EGF/001
Commercial in Confidence
39/44
iXSEA Document n° : MU/3453/EGF/001
APPENDIX B:
PHYSICAL PRINCIPLES OF OCTANS
Extract from
‘’highly compact fiber optic gyrocompass for applications at depths up to 3,000 meters,
presented at the Underwater Intervention 2000 show, January 2000’’
Commercial in Confidence
40/44
iXSEA Document n° : MU/3453/EGF/001
Commercial in Confidence
41/44
iXSEA Document n° : MU/3453/EGF/001
The ingenious signal processing which follows requires a large number of optoelectronic
components if the information on optical phase, carrying information on rotation, is to be
converted into a digital signal useable by a calculator.
In practice, FOG performance gets better as it gets bigger, a fact which can be easily
understood in terms of the length of the coiled optical fiber: at any given rotational speed,
increased length will make it easier to separate the two light pulses temporally in the way
described above.
FOG performance can be measured in terms of many parameters, of which the most important
is known as bias stability, which means the stability of the zero point, or the intrinsic accuracy
of the measurement of rotational movement. It is usual to express bias stability in degrees per
hour (deg/hour), to make comparison easier with the Earth’s rotation rate, which is 15
deg/hour (1 revolution in 1 day, 360 degrees in 24 hours, giving 15 degrees per hour). In
practice, in order to measure the bias stability of a FOG, we measure the Earth’s rotation rate.
As an example, at the latitude of Paris, France (48,57°N), a FOG must measure 11.33
deg/hour (i.e. the projection of the rotation of the Earth onto the apparent vertical).
The compact assembly formed by the three gyrometers and the three accelerometers is called
an “Inertial Measurement Unit” (IMU) and forms the heart of any inertial reference system.
When an IMU is coupled to a calculator and an interface, the result is an “inertial reference
system”.
Commercial in Confidence
42/44
iXSEA Document n° : MU/3453/EGF/001
Gyrocompass types currently in use comprise a gyroscope which aligns its angular moment
with that of the Earth and therefore exploit at a basic level the intrinsic properties of rotating
solids, and notably the principle of gyroscopic spins. A gyrocompass using FOGs must
therefore be based on a radically different concept. It is this concept that we explain below.
bgyro bacc
∆Φ = Sec L + tan L
Ω g
Equatorial plane
North
ΩEarth
South
Commercial in Confidence
43/44
iXSEA Document n° : MU/3453/EGF/001
2.2. Gyrocompasses
The gyrocompass represents a step up from the above in terms of complexity. At this level,
the system has to withstand random movements – which may be violent, such as a ship’s pitch
and roll. The difficulty is twofold compared with the previous design: firstly, measurement of
terrestrial rotation is disturbed by enormously high rotational values (several orders of
magnitude greater than the Earth’s rotation rate), and secondly, measurement of gravity is
disturbed by centrifugal accelerations which may also prove to be relatively high.
The basic idea is therefore to abandon the direct use of the measurement of the Earth’s
rotation rate related to the gyroscopic frame, in favour of a “fixed” reference frame, which is
called the Inertial Space.
Described briefly, the system comprises three gyros and three accelerometers: the three gyros
enable the rotation rate of the moving object to be measured at any given instant (including
the Earth’s rotation rate), and the three accelerometers give the sum of the acceleration and
apparent gravity; these measurements are both related to a reference bound to the moving
object itself. The angular attitude of the moving object compared to the Inertial space is then
computed by integration of the rotation rate. The accelerometer data, which is the sum of the
acceleration and gravity, is then expressed within the Inertial Space. After filtering out the
acceleration values, it is possible to “observe” the slow drift of apparent gravity due to the
rotation of the Earth. In fact, it is easy to show that the apparent gravity expressed within the
Inertial Space defines a cone whose main axis is the rotational axis of the Earth (see figure 3).
Examination of the movement of g can therefore tells us where geographical North is without
need of an external reference.
Rotation of Earth
Commercial in Confidence
44/44
STEP 2. ONBOARD INSTALLATION
Mechanical Installation
OCTANS 100 and 3000 are installed using three M6 screws (Duplex or Titanium) accessible on the base plate of
the unit (see Figure 2 for OCTANS 100 and Figure 3 for OCTANS 3000).
Figure 2 - Definition of OCTANS 100 Reference Frame (X1,X2, X3) and P centre of measurement
Figure 3 - Definition of OCTANS 3000 Reference Frame (X1, X2, X3) and P centre of measurement
Recommendations
• Temperature in operation must be in the range -40 °C to 60 °C
• The dimensions of the OCTANS housing are 276 mm x 136 mm x 148.5 mm.
There must be enough place for the wire way on the connector side of OCTANS
2006 -07 / MU / OCTIII / 012 ed.A 15
OCTANS 6000 is mounted by IXSEA on a bracket that will share a chassis for RDI Doppler Velocity Log. OCTANS
6000 is designed as a standard for use in its bracket on an horizontal configuration. Removing OCTANS from its
bracket will void the factory calibration of the unit.
X3
X2 X1
X2
X3 X1
X1
X3
X2
X2
Figure 4 - Definition of OCTANS 6000 Reference Frame (X1, X2, X3) and P centre of measurement
Recommendations
• Temperature in operation must be in the range -40 °C to 60 °C
• The dimensions of the OCTANS housing are 276 mm x 136 mm x 148.5 mm.
There must be enough place for the wire way on the connector side of OCTANS
All OCTANS inputs/outputs are made via one sealed connector located on the OCTANS front panel. A 16-pin
SUBCONN connector, reference MCBH16M is delivered as a standard (see Figure 5 for diagram of this standard
connector).
• Power Supply: pin 1 and pin 2 (ground) are assigned for the power supply for direct connection to a 24 V power
supply.
IMPORTANT: any outage of the power supply, even brief, will return the system to its initial condition and it will
begin to seek North again. The alignment phase will start over.
• Connection to PC: pins 12, 14, 15 and 16.The pin assignments are described hereafter.
Pins 16 and 12 need to be connected to pin 5 of DB9 for the communication to work properly