Prepared By Name :
Designation : Testing & Commissioning Engineer
Reviewed By Name :
Designation : Project Manager
INDEX
SI.NO DESCRIPTION
1 SCOPE
2 PURPOSE
HSE REQUIREMENTS
3.1 Permit to Work
3 3.2 Personal Protective Equipments
3.3 Tool Box Talk
3.4 Safe Work Practice
5 RESPONSIBILITY
1.0 SCOPE
The scope of work cover the activities related to Method of Statement for Installation of Access
ladder, Cable Rack, Painting and its necessary works in (AL HASSA AREA) AMI/AMR
INSTALLTION PROJECT, NG Contract No – 4400011486. This also includes the Inspection,
Safety Measures & Material handling.
2.0 PURPOSE
The purpose of this document is to outline the sequences and methods of works of the electrical
equipments and associated activities to satisfy with all the relevant specifications and
requirements.
5.0 RESPONSIBILITY
Site Engineer/ Site Supervisor shall be responsible person in supervising the above activities on
site.
Safety Officer must be available full time to monitor the safety aspects during the activity at site.
Arrange for atmospheric testing using an appropriate gas tester. Test at each entry/exit and
ventilation point and at remote parts of the space.
Determine if any specific monitoring plan is needed to track changes in atmosphere and other
possible changes (i.e rising water)
Establish a suitable emergency response plan and appoint a competent rescuer/standby person (to
be located outside the space) & emergency vehicle.
Ensure there is a process for communication between workers in the space, the standby person,
network control and emergency services.
Ensure the communication devices are appropriate for the space and in working order.
Maintain log-sheet separately and monitor continuously by concerned person.