MAIN GATE

SR.NO DESCRIPTION NOS L B H

1 EXCAVATION 2 1.8 1.8 1.5


2 P.C.C 2 1.5 1.5 0.1
3 FLAT SOILING 2 1.5 1.5 0.1
4 R.C.C
RAFT 2 1.3 1.3 0.2
COLUMN 2 0.3 0.3 3.6
BEAM 1 1.18 0.23 0.3
5 REINFORCEMENT
RAFT
2 1.44 11 0.62
2 1.44 11 0.62
COULMN
2 4 8 0.89

LINKS 2 1.04 25 0.40


2 0.78 25 0.40

6 GATE
50MM DIA PIPE 1 6 2.4
1 6 2
6MM THK PLATE 2 0.98 0.24 0.78
20MM DIA ROD 1 40 3.14
20MM DIA ROD 1 22 3.14
20MM DIA ROD 1 14 3.14
20MM DIA ROD 1 11 3.14

7 HINGES 4
8 LOCK ARRANGMENT 4

ABSTRACT
MAIN GATE
SR.NO DESCRIPTION QTY UNIT
1 EXCAVATION 9.72 CUM
2 P.C.C 0.45 CUM
3 FLAT BRICKS SOLING 0.45 CUM
4 R.C.C-M-20 1.405 CUM
5 REINFORCEMENT 130.53 KG
6 GATE
50MM DIA MS PIPE 26.4 RMT
20MM SQ.DIA 274.5 KG
6MM THK PLATE 22.2 KG
7 HINGES 4 NOS
8 LOACK ARRANGMENT 4 NOS
DEPTH OF FILLING 0
QTY UNIT BELOW N.G.L 1.5
NOS 2
9.72 CUM L 1.3
0.45 CUM B 1.3
0.45 CUM T 0.3

0.676 CUM
0.648 CUM
0.081 CUM

18.84 KG
18.84 KG

56.89 KG

20.54 KG
15.41 KG

14.4 RMT
12 RMT
22.2 KG
125.6 KG
69.1 KG
44.5 KG
35.3 KG

4 NOS
4 NOS
LENGTH 80
CHAINLINK FENCING WORKING

1 EXCAVATION 1 80
2 COLUMN EXCAVATION 12 0.6
GI CHAIN LINK FENCE 3.15mm∅
3 DIAMOND PATTERN MESH OF SIZE 1 80
75x75mm
4 BARBED WIRE 2 3
5 TENSION WIRE 3 80
6 ANGLE POST
50X50X6 1 12
BASE PLATE 1 12
50X6 MS FLAT 1 80
50X6 MS FLAT 1 12

7 COUMN 33 0.6
8 SOILING-150MM THK 9 1.9
9 BRICK WORK 9 1.9
10 COPING-(1:2:4) 1 80
11 P.C.C-M-7.5 9 1.9

CHAINLINK FENSING
SR.NO DESCRIPTION QTY UNIT
1 EXCAVATION 15.516 CUM
2 SOILING-150MM THK 0.770 CUM
3 P.C.C-M-7.5 0.295 CUM
4 COPING-(1:2:4) 1.38 CUM
5 BRICK WORK(1:5) 2.3598 CUM
6 COLUMN-(1:2:4) 17.82 CUM
GI CHAIN LINK FENCE 3.15mm∅
DIAMOND PATTERN MESH OF SIZE
7 75x75mm 210 SQ.MTR
8 BARBED WIRE 480 RMT
9 TENSION WIRE 240 RMT
10 STRUCTURAL STEEL WORK 590.1 KG
0.3 0.525 12.6 CUM
0.6 0.675 2.916 CUM

2.625 210 SQ.MTR

80 480 RMT
240 RMT

4.71 6.12 345.9 KG


0.471 5.7 KG
2.3622047 189.0 KG
2.3622047 1.75 49.6 KG

0.6 1.5 17.82 CUM


0.3 0.15 0.7695 CUM
0.23 0.6 2.3598 CUM
0.23 0.075 1.38 CUM
0.23 0.075 0.294975 CUM

RATE AMOUNT
L B H
10 0.75 0.9

SR.NO DESCRIPTION NOS L B H

1 EXCAVATION 1 10 1.14 1.15

2 SAND FILLING 1 10 1.14 0.075

2 P.C.C M-7.5 1 10 1.14 0.075

3 RAFT 1 10 1.14 0.1

4 WALL M -20 2 10 0.12 1

5 COVER 21 0.87 0.5 0.09

6 REINFORCEMENT
RAFT
TRANSVERSE 8 MM 1 68 0.39 1.29
TOP BAR 1 68 0.39 1.29
DISTREBUTION
BOTTOM 1 7 0.39 9.92
TOP 1 7 0.39 9.92
WALL DETAILS
INSIDE FACE 2 72 0.39 1.278
OUT SIDE FACE 2 72 0.39 1.3
HZL 4 6 0.39 10
COVER SLAB
7 1 0.39 21
4 0.45 0.39 21

6 STRUCTURAL STEEL
EDGE ANGLE50X50X6 2 10 4.71
BAR 2 0.25 0.39 33

FLAT
75X6 18 0.8 3.54330709
ANGLE
50X50X6 2 18 4.71 0.45
CLEAT
50X50X6 8 18 4.71 0.05

7 PVC WATER STOPPER 2


CABLE TRENCH -1-1

SR.NO DESCRIPTION QTY UNIT


1 EXCAVATION 13.11 CUM
2 SAND FILLING 0.855 CUM
3 P.C.C 0.855 CUM
4 R.C.C-M20 4.362 CUM
5 REINFORCEMENT 426.61 KG
6 STRUCTURAL STEEL 258.95174 KG
7 WATER STOPPER 2 NOS
THK
WALL THK RAFT
0.12 0.1

QTY UNIT RATE AMOUNT

13.11 CUM

0.855 CUM

0.855 CUM

1.14 CUM

2.4 CUM

0.82215 CUM

34.0 KG
34.0 KG

28.8 KG
28.8 KG

72.2 KG
73.4 KG
93.6 KG

45.7 KG
16.0 KG

94.2
6.5

50.0787402 KG

74.889 KG

33.284 KG

NOS

0
Length of Width of Length of
Footing Footing Column
132KV BPI-10T/M2 @ 1.5 MTR A B a
1.5 1.5 0.6
SR.NO Nos Length Bredth
1 Earth work excavation 1 1 1.8 1.8
2 PCC (M7.5) 1 1 1.7 1.7
3 RCC raft - (M25) 1 1 1.5 1.5
4 RCC column (M25) 1 1 0.6 0.6
5 Reinforcement
6 Back filling
7 DISPOSAL
8 Plastering 1 1 0.6 0.6
1 2 0.6 0.6
9 Labour charges for fixing of anchor bolts
10 White wash

11 Shuttering 1 2 1.5
1 2 1.5
1 4 0.6

Reinforcement NOS FACE LENGTH


Raft (BOT) 8 1 1.7
8 1 1.7
top 8 1 1.7
8 1 1.7
Column 8 1 2.15
0 1 2.15
RINGS 10 1 2.16
10 1 1.82
10 0
10 0
10 0
For Chairs
Width of Thikness Depth of
Column of Raft Footing
b d D
0.6 0.25 1.5
Depth qty Total qty Rate Amount
1.5 4.86 4.86
0.1 0.29 0.29
0.25 0.56
1.45 0.52 1.37 1.08
69.59 69.59
3.49 3.49
1.37 1.37
1 0.36
0.3 0.72 1.08
4.00 4.00

1.08 1.08
0.25 0.75 0.00
0.25 0.75
1.45 3.48 4.98

total Dia Dia Spacing


13.6 10.00 0.62 8.40 10 200
13.6 10.00 0.62 8.40 10 200
13.6 10.00 0.62 8.40 10 200
13.6 10.00 0.62 8.40 10 200
17.2 12.00 0.89 15.29 12
0 0.00 0.00 0.00 0
21.6 8.00 0.40 8.53 8 200
18.2 8.00 0.40 7.19 8 200
0 8.00 0.40 0.00 8 200
0 8.00 0.40 0.00 8 200
0 8.00 0.40 0.00 8 200
5.00
69.59
Length of Width of Length of
Footing Footing Column
132KV LA-10T/M2 @ 1.5 MTR A B a
1.5 1.5 0.6
SR.NO Nos Length Bredth
1 Earth work excavation 1 1 1.8 1.8
2 PCC (M7.5) 1 1 1.7 1.7
3 RCC raft - (M25) 1 1 1.5 1.5
4 RCC column (M25) 1 1 0.6 0.6
5 Reinforcement
6 Back filling
7 DISPOSAL
8 Plastering 1 1 0.6 0.6
1 2 0.6 0.6
9 Labour charges for fixing of anchor bolts
10 White wash

11 Shuttering 1 2 1.5
1 2 1.5
1 4 0.6

Reinforcement NOS FACE LENGTH


Raft (BOT) 8 1 1.7
8 1 1.7
top 8 1 1.7
8 1 1.7
Column 8 1 2.15
0 1 2.15
RINGS 10 1 2.16
10 1 1.82
10 0
10 0
10 0
For Chairs
Width of Thikness Depth of
Column of Raft Footing
b d D
0.6 0.25 1.5
Depth qty Total qty Rate Amount
1.5 4.86 4.86
0.1 0.29 0.29
0.25 0.56
1.45 0.52 1.37 1.08
69.59 69.59
3.49 3.49
1.37 1.37
1 0.36
0.3 0.72 1.08
4.00 4.00

1.08 1.08
0.25 0.75 0.00
0.25 0.75
1.45 3.48 4.98

total Dia Dia Spacing


13.6 10.00 0.62 8.40 10 200
13.6 10.00 0.62 8.40 10 200
13.6 10.00 0.62 8.40 10 200
13.6 10.00 0.62 8.40 10 200
17.2 12.00 0.89 15.29 12
0 0.00 0.00 0.00 0
21.6 8.00 0.40 8.53 8 200
18.2 8.00 0.40 7.19 8 200
0 8.00 0.40 0.00 8 200
0 8.00 0.40 0.00 8 200
0 8.00 0.40 0.00 8 200
5.00
69.59
Length of Width of Length of
0 Footing Footing Column
132KV CT-10T/M2 @ 1.5 MTR A B a
1.7 1.7 0.8
SR.NO Nos Length Bredth
1 Earth work excavation 1 1 2 2
2 PCC (M7.5) 1 1 1.9 1.9
3 RCC raft - (M25) 1 1 1.7 1.7
4 RCC column (M25) 1 1 0.8 0.8
5 Reinforcement
6 Back filling
7 DISPOSAL
8 Plastering 1 1 0.8 0.8
1 2 0.8 0.8
9 Labour charges for fixing of anchor bolts
10 White wash

11 Shuttering 1 2 1.7
1 2 1.7
1 4 0.8

Reinforcement NOS FACE LENGTH


Raft (BOT) 9 1 2
9 1 2
top 9 1 2
9 1 2
Column 8 1 2.1
4 1 2.1
RINGS 10 1 2.96
10 2 2.09
10 0
10 0
10 0
For Chairs
Width of Thikness Depth of
Column of Raft Footing
b d D
0.8 0.3 1.5
Depth qty Total qty Rate Amount
1.5 6.00 6.00
0.1 0.36 0.36
0.3 0.87
1.4 0.90 2.12 1.76
100.05 100.05
3.88 3.88
2.12 2.12
1 0.64
0.3 0.96 1.60
4.00 4.00

1.60 1.60
0.3 1.02 0.00
0.3 1.02
1.4 4.48 6.52

total Dia Dia Spacing


18 10.00 0.62 11.11 10 200
18 10.00 0.62 11.11 10 200
18 10.00 0.62 11.11 10 200
18 10.00 0.62 11.11 10 200
16.8 12.00 0.89 14.93 12
8.4 12.00 0.89 7.47 12
29.6 8.00 0.40 11.69 8 200
41.8 8.00 0.40 16.51 8 200
0 8.00 0.40 0.00 8 200
0 8.00 0.40 0.00 8 200
0 8.00 0.40 0.00 8 200
5.00
100.05
Length of Width of Length of
0 Footing Footing Column
132KV PT-10T/M2 @ 1.5 MTR A B a
1.7 1.7 0.8
SR.NO Nos Length Bredth
1 Earth work excavation 1 1 2 2
2 PCC (M7.5) 1 1 1.9 1.9
3 RCC raft - (M25) 1 1 1.7 1.7
4 RCC column (M25) 1 1 0.8 0.8
5 Reinforcement
6 Back filling
7 DISPOSAL
8 Plastering 1 1 0.8 0.8
1 2 0.8 0.8
9 Labour charges for fixing of anchor bolts
10 White wash

11 Shuttering 1 2 1.7
1 2 1.7
1 4 0.8

Reinforcement NOS FACE LENGTH


Raft (BOT) 9 1 2
9 1 2
top 9 1 2
9 1 2
Column 8 1 2.1
4 1 2.1
RINGS 10 1 2.96
10 2 2.09
10 0
10 0
10 0
For Chairs
Width of Thikness Depth of
Column of Raft Footing
b d D
0.8 0.3 1.5
Depth qty Total qty Rate Amount
1.5 6.00 6.00
0.1 0.36 0.36
0.3 0.87
1.4 0.90 2.12 1.76
100.05 100.05
3.88 3.88
2.12 2.12
1 0.64
0.3 0.96 1.60
4.00 4.00

1.60 1.60
0.3 1.02 0.00
0.3 1.02
1.4 4.48 6.52

total Dia Dia Spacing


18 10.00 0.62 11.11 10 200
18 10.00 0.62 11.11 10 200
18 10.00 0.62 11.11 10 200
18 10.00 0.62 11.11 10 200
16.8 12.00 0.89 14.93 12
8.4 12.00 0.89 7.47 12
29.6 8.00 0.40 11.69 8 200
41.8 8.00 0.40 16.51 8 200
0 8.00 0.40 0.00 8 200
0 8.00 0.40 0.00 8 200
0 8.00 0.40 0.00 8 200
5.00
100.05
Length of Width of Length of
0 Footing Footing Column
132KV CVT-10T/M2 @ 1.5 MTR A B a
1.7 1.7 0.8
SR.NO Nos Length Bredth
1 Earth work excavation 1 1 2 2
2 PCC (M7.5) 1 1 1.9 1.9
3 RCC raft - (M25) 1 1 1.7 1.7
4 RCC column (M25) 1 1 0.8 0.8
5 Reinforcement
6 Back filling
7 DISPOSAL
8 Plastering 1 1 0.8 0.8
1 2 0.8 0.8
9 Labour charges for fixing of anchor bolts
10 White wash

11 Shuttering 1 2 1.7
1 2 1.7
1 4 0.8

Reinforcement NOS FACE LENGTH


Raft (BOT) 9 1 2
9 1 2
top 9 1 2
9 1 2
Column 8 1 2.1
4 1 2.1
RINGS 10 1 2.96
10 2 2.09
10 0
10 0
10 0
For Chairs
Width of Thikness Depth of
Column of Raft Footing
b d D
0.8 0.3 1.5
Depth qty Total qty Rate Amount
1.5 6.00 6.00
0.1 0.36 0.36
0.3 0.87
1.4 0.90 2.12 1.76
100.05 100.05
3.88 3.88
2.12 2.12
1 0.64
0.3 0.96 1.60
4.00 4.00

1.60 1.60
0.3 1.02 0.00
0.3 1.02
1.4 4.48 6.52

total Dia Dia Spacing


18 10.00 0.62 11.11 10 200
18 10.00 0.62 11.11 10 200
18 10.00 0.62 11.11 10 200
18 10.00 0.62 11.11 10 200
16.8 12.00 0.89 14.93 12
8.4 12.00 0.89 7.47 12
29.6 8.00 0.40 11.69 8 200
41.8 8.00 0.40 16.51 8 200
0 8.00 0.40 0.00 8 200
0 8.00 0.40 0.00 8 200
0 8.00 0.40 0.00 8 200
5.00
100.05
Length of Width of Length of
0 Footing Footing Column
132KV WAVE TRAP-10T/M2 @ 1.5 MTR A B a
2 2 1.3
SR.NO Nos Length Bredth
1 Earth work excavation 1 1 2.3 2.3
2 PCC (M7.5) 1 1 2.2 2.2
3 RCC raft - (M25) 1 1 2 2
4 RCC column (M25) 1 1 1.3 1.3
5 Reinforcement
6 Back filling
7 DISPOSAL
8 Plastering 1 1 1.3 1.3
1 2 1.3 1.3
9 Labour charges for fixing of anchor bolts
10 White wash

11 Shuttering 1 2 2
1 2 2
1 4 1.3

Reinforcement NOS FACE LENGTH


Raft (BOT) 11 1 2.3
11 1 2.3
top 11 1 2.3
11 1 2.3
Column 12 1 2.1
12 1 2.1
RINGS 10 1 4.96
10 2 2.09
10 2 2.09
10 0
10 0
For Chairs
Width of Thikness Depth of
Column of Raft Footing
b d D
1.3 0.3 1.5
Depth qty Total qty Rate Amount
1.5 7.94 7.94
0.1 0.48 0.48
0.3 1.20
1.4 2.37 4.05 3.57
192.38 192.38
3.89 3.89
4.05 4.05
1 1.69
0.3 1.56 3.25
4.00 4.00

3.25 3.25
0.3 1.20 0.00
0.3 1.20
1.4 7.28 9.68

total Dia Dia Spacing


25.3 12.00 0.89 22.49 12 200
25.3 12.00 0.89 22.49 12 200
25.3 12.00 0.89 22.49 12 200
25.3 12.00 0.89 22.49 12 200
25.2 12.00 0.89 22.40 12
25.2 12.00 0.89 22.40 12
49.6 8.00 0.40 19.60 8 200
41.8 8.00 0.40 16.51 8 200
41.8 8.00 0.40 16.51 8 200
0 8.00 0.40 0.00 8 200
0 8.00 0.40 0.00 8 200
5.00
192.38
Length of Width of Length of
Footing Footing Column
132KV CB-10T/M2 @ 1.5 MTR A B a
FOR 1(ONE) SET 1.75 1.75 0.8
SR.NO Nos Length Bredth
1 Earth work excavation 1 2 2.05 2.05
2 PCC (M7.5) 1 2 1.95 1.95
3 RCC raft - (M25) 1 2 1.75 1.75
4 RCC column (M25) 1 2 0.8 0.8
5 Reinforcement 1 1
6 Back filling
7 DISPOSAL
8 Plastering 1 2 0.8 0.8
1 4 0.8 0.8
9 Labour charges for fixing of anchor bolts 1 2
10 White wash

11 Shuttering 1 2 1.75
1 2 1.75
1 4 0.8

Reinforcement NOS FACE LENGTH


Raft (BOT) 9 2 2.05
9 2 2.05
top 9 2 2.05
9 2 2.05
Column 8 2 2.3
4 2 2.3
RINGS 10 4 2.96
10 4 2.09
10 0
10 0
10 0
For Chairs
Width of Thikness Depth of
Column of Raft Footing
b d D
0.8 0.3 1.5
Depth qty Total qty Rate Amount
1.5 12.61 12.61
0.1 0.76 0.76
0.3 1.84
1.4 1.79 4.39 3.63
303.23 303.23
8.22 8.22
4.39 4.39
1 1.28
0.3 1.92 3.20
8.00 8.00

3.20 3.20
0.3 1.05 0.00
0.3 1.05
1.4 4.48 6.58

total Dia Dia Spacing


36.9 12.00 0.89 32.80 12 200
36.9 12.00 0.89 32.80 12 200
36.9 12.00 0.89 32.80 12 200
36.9 12.00 0.89 32.80 12 200
36.8 16.00 1.58 58.15 16
18.4 16.00 1.58 29.08 16
118.4 8.00 0.40 46.78 8 200
83.6 8.00 0.40 33.03 8 200
0 8.00 0.40 0.00 8 200
0 8.00 0.40 0.00 8 200
0 8.00 0.40 0.00 8 200
5.00
303.23
Length of Width of Length of
Footing Footing Column
132KV ISOLATER ES-10T/M2 @ 1.5 MTR A B a
FOR 1(ONE) SET 2.5 1.4 0.4
SR.NO Nos Length Bredth
1 Earth work excavation 1 2 2.8 1.7
2 PCC (M7.5) 1 2 2.7 1.6
3 RCC raft - (M25) 1 2 2.5 1.4
4 RCC column (M25) 2 2 0.4 0.4
5 Reinforcement
6 Back filling
7 DISPOSAL
8 Plastering 1 4 0.4 0.4
1 8 0.4 0.4
9 Labour charges for fixing of anchor bolts
10 White wash

11 Shuttering 2 2 1.4
2 2 2.5
2 4 0.4

Reinforcement NOS FACE LENGTH


Raft (BOT) 13 2 1.7
8 2 2.8
top 13 2 1.7
8 2 2.8
Column 8 4 2.1
0 1 2.1
RINGS 12 4 1.36
12 4 1.3
12 0
12 0
12 0
For Chairs
Width of Thikness Depth of
Column of Raft Footing
b d D
0.4 0.3 1.5
Depth qty Total qty Rate Amount
1.5 14.28 14.28
0.1 0.86 0.86
0.3 2.10
1.4 0.90 3.86 3.00
230.05 230.05
10.42 10.42
3.86 3.86
1 0.64
0.3 1.92 2.56
8.00 8.00

2.56 2.56
0.3 1.68 0.00
0.3 3.00
1.4 4.48 9.16

total Dia Dia Spacing


44.2 10.00 0.62 27.28 10 200
44.8 10.00 0.62 27.65 10 200
44.2 10.00 0.62 27.28 10 200
44.8 10.00 0.62 27.65 10 200
67.2 12.00 0.89 59.73 12
0 0.00 0.00 0.00 0
65.28 8.00 0.40 25.79 8 150
62.4 8.00 0.40 24.65 8 150
0 8.00 0.40 0.00 8 150
0 8.00 0.40 0.00 8 150
0 8.00 0.40 0.00 8 150
10.00
230.05
H A B a E
132KV TOWER -1 NOS 3 4.75 4.00 0.50 0.4

ITEM Nos Length Breadth Depth qty


Earth work excavation 1 1 5.00 4.25 3.1 65.88
PCC (M7.5) 1 1 4.850 4.10 0.1 1.99
RCC raft - (M25) 1 1 4.75 4 0.4 7.6
RCC column (M25) 1 4 0.5 0.5 2.9 2.9 10.5
Reinforcement 1025.225
Back filling 55.375
DISPOSAL 10.5
Plastering 1 4 0.5 0.5 0 1
4 4 0.5 0.3 0 0.6
Labour charges for fixing of
anchor bolts
Cement Paint 1 4 0.5 0.5 0 1
4 4 0.5 0.3 0 0.6
Grouting 1 4 0.50 0.50 0.04 0.04
Shuttering 1 2 4.75 0.4 3.8
1 2 4.00 0.4 3.2
Column 4 4 0.50 2.9 23.2

Reinforcement NOS FACE LENGTH total Dia DIA


Raft (BOT) 33 1 4.85 160.05 12 12
28 1 4.1 114.8 12 12
TOP 49 1 4.95 242.55 12 12
41 1 4.1 168.1 12 12
Column 8 4 2.9 92.8 20 20
0 4 0 0 25 25
RINGS 18 4 1.76 126.72 8 8
18 4 1.29 92.88 8 8
Sepratar ( Chairs)
Total qty Rate Unit Amount
65.88 cum 0.00
1.99 cum 0.00

10.50 cum 0.00


1025.22 kg 0.00
55.38 cum 0.00
10.50 cum 0.00 `
1.00 sq.m 0.00
0.60 sq.m 0.00
16.00 0.00
l.s
1.00 sq.m 0.00
0.60 sq.m 0.00
0.04 cum 0.00

30.20 Sq.mtr

Total 0.00

0.89 142.27 0.15


0.89 102.04 0.15
0.89 215.60 0.1
0.89 149.42 0.1
2.47 229.14
3.86 0.00
0.40 50.06 0.19
0.40 36.69
100.00
1025.22
H A B a E
LCLM -1 NOS-25MTR 3 3.50 3.50 0.55 0.4

ITEM Nos Length Breadth Depth qty


Earth work excavation 1 1 3.75 3.75 3.1 43.59
PCC (M7.5) 1 1 3.600 3.60 0.1 1.30
RCC raft - (M25) 1 1 3.5 3.5 0.4 4.9
RCC column (M25) 1 4 0.55 0.55 2.9 3.509 8.409
Reinforcement 631.8568
Back filling 35.18475
DISPOSAL 8.409
Plastering 1 4 0.55 0.55 0 1.21
4 4 0.55 0.3 0 0.66
Labour charges for fixing of
anchor bolts
Cement Paint 1 4 0.55 0.55 0 1.21
4 4 0.55 0.3 0 0.66
Grouting 1 4 0.55 0.55 0.04 0.0484
Shuttering 1 2 3.50 0.4 2.8
1 2 3.50 0.4 2.8
Column 4 4 0.55 2.9 25.52

Reinforcement NOS FACE LENGTH total Dia DIA


Raft (BOT) 25 1 3.6 90 12 12
25 1 3.6 90 12 12
TOP 25 1 3.7 92.5 12 12
25 1 3.6 90 12 12
Column 8 4 2.9 92.8 16 16
0 4 0 0 25 25
RINGS 22 4 1.96 172.48 8 8
22 4 1.29 113.52 8 8
Sepratar ( Chairs)
Total qty Rate Unit Amount
43.59 cum 0.00
1.30 cum 0.00

8.41 cum 0.00


631.86 kg 0.00
35.18 cum 0.00
8.41 cum 0.00 `
1.21 sq.m 0.00
0.66 sq.m 0.00
16.00 0.00
l.s
1.21 sq.m 0.00
0.66 sq.m 0.00
0.05 cum 0.00

31.12 Sq.mtr

Total 0.00

0.89 80.00 0.15


0.89 80.00 0.15
0.89 82.22 0.15
0.89 80.00 0.15
1.58 146.65
3.86 0.00
0.40 68.14 0.15
0.40 44.85
50.00
631.86
ESTIMATE 16 MVA TRANSFORMER
Sr.No Description Nos L B D

1 Below Raft 1 4.7 5.7 1.5


BELOW OIL TANK 1 9.2 7.2 0.5
RADIATOR 1 4.5 1.3 1.5
FAN 2 1.7 1.2 1.5

2 PCC-M-7.5 1 3.9 4.9 0.1


1 8.5 6.5 0.1
1 4.2 1.2 0.1
2 1.2 1.7 0.1

3 Raft 1 3.7 4.7 0.4


Wall 2 4.7 0.35 1.7
JACKING PAD 4 0.5 0.5 1.7
OIL PIT 1 8.2 6.2 0.15
2 8.2 0.95 0.15
2 6.2 0.95 0.15
RADIATOR FOUNDATION 1 4 1 0.3
COLUMN 4 0.25 0.45 1.7
FAN 2 1 1.5 0.3
FAN COLUMN 2 0.35 0.45 1.7

4 REINFORCEMENT
5 STRUCTURAL STEEL
RAIL 2 4.7 42
PLATE 17 8.478
CLEAT ANGLE
90MM-65X65X6 17 0.1 6.1
65X65X6 9.4 1 6.1
FLAT-8MM THK 16 0.2 3.14

5 METAL FILLING 1 8.2 6.2 0.2

ABSTRACT-16MVA TRAFO-FOUNDATION

SR.NO DESCRIPTION QTY UNIT RATE AMOUNT

1 EXCAVATION 88.2 CUM


2 P.C.C-M-7.5 8.348 CUM
3 R.C.C-M25 29.3795 CUM
4 REINFORCEMENT 3672.4375 KG
5 STRUCTURAL STEEL 616.684 KG
6 METALING 10.168 CUM
NSFORMER
Qty Unit Rate Amount

40.185 Cum
33.12 Cum
8.775 Cum
6.12 Cum

1.911 Cum
5.525 Cum
0.504 Cum
0.408 Cum

6.956 Cum
5.593 Cum
1.7 Cum
7.626 Cum
2.337 Cum
1.767 Cum
1.2 Cum
0.765 Cum
0.9 Cum
0.5355 Cum
29.3795

3672.4375 KG

394.8 KG
144.126 KG

10.37 KG
57.34 KG
10.048 KG

10.168 CUM
OIL SUMP PIT
SR.NO DESCRIPTION NOS L B D

1 EXCAVATION 1 4.4 4.4 3.5


PIPE LAYING 1 15 1 0.75
2 P.C.C 1 4.2 4.2 0.15

3 R.C.C-M-25
RAFT 1 4 4 0.25
WALL 4 4 0.25 4.1
TOP SLAB 1 4 4 0.15

4 REINFORCEMENT 1

5 VERTICAL STEEL STAIR


6 VENT PIPE-100 MM DIA 1
8 1 HP PUMP FOR DEWATERING
150 MM DIA HUME
8 2 15
PIPELAYINGINCLUDING FIXING

ABSTRACT-OIL SUMP PIT PIPE LAYING

SR.NO DESCRIPTION QTY UNIT RATE AMOUNT

1 EXCAVATION 79.01 CUM


2 P.C.C-M-7.5 2.646 CUM
3 R.C.C-M25 22.8 CUM
4 REINFORCEMENT 2850 KG
5 STRUCTURAL STEEL 500 KG
6 1 HP PUMP FOR DEWATERING 1 NOS
150 MM DIA HUME
7 PIPELAYINGINCLUDING FIXING 30 RMT
QTY UNIT

67.76 CUM
11.25 CUM
2.646 CUM

4 CUM
16.4 CUM
2.4 CUM

2850 KG

500 KG
3 MTR
1 NOS

30 RMT