Contents
Performance Qualification
Recalibration ..................................................................................................................... 2
Functional Tests................................................................................................................ 3
Unstirred Water Bath SUB Aqua Plus SAMPLE COPY 29571 Version 1 – March 2010
Performance Qualification 1
Performance Qualification
Triggering Factor for Performance Qualification
Recalibration
Suggested Not
Recalibration Step Refer to OK Not OK
Frequency Done
Comments:
Unstirred Water Bath SUB Aqua Plus SAMPLE COPY 29571 Version 1 – March 2010
Performance Qualification 2
Performance Qualification
Functional Tests
Not
Functional Test Refer to Acceptance Criteria Pass Fail
Done
1. Display illuminates
Powers up - and shows fluid
temperature
Heats fluid to reach 1. Display shows fluid
set-point
temperature
OM5.3.2 temperature increase
and rising bar
1. Display shows fluid
Controls fluid
temperature at set-point
temperature when
set-point reached
OM5.3.2
and rising bar
disappears
Controls fluid
temperature when
sample protection
thermostat level 1. Display alternates
reached (Test by between fluid
setting sample temperature and ‘’
protection and audible alarm
thermostat slightly
lower than set-point
OM5.3.3 sounds.
2. Fluid held just above
temperature. sample protection
Remember to reset temperature with greater
sample protection fluctuation
thermostat back
above set-point
afterwards)
1. Display shows
'then preset
Water heats to the OM5.3.4 temperature when
preset tempearture OM5.3.5 Preset Key 1 is pressed
2. Water reaches
preset temp
1. Dot will flash on the
display.
2. Alarm sounds at the
Countdown timer OM5.3.6
end of countdown period
3. Alarm stops when
enter is pressed
Comments:
Unstirred Water Bath SUB Aqua Plus SAMPLE COPY 29571 Version 1 – March 2010
Performance Qualification 3
Performance Qualification
Routine Maintenance
This instrument has been designed to require minimal servicing. If a fault occurs, it is
advised that Grant Instruments (or local distributor if outside the UK) should be contacted.
The frequency with which routine maintenance tasks are being completed should be
recorded below. Details of each specific occurrence should be maintained elsewhere. The
Performance Qualification checks that this schedule is being adhered to.
Schedule Adherence
Scheduled
Routine Maintenance Refer to
Frequency
OK Discrepancy
Unstirred Water Bath SUB Aqua Plus SAMPLE COPY 29571 Version 1 – March 2010
Performance Qualification 4
Performance Qualification
Safety Tests
This instrument conforms to the following standards and is supplied fully tested by the
manufacturer:
BS EN 61326:2006 – Electrical equipment for measurement, control and laboratory
use – EMC requirements.
BS EN 61010 Part 2-010:2003 – Safety requirements for electrical equipment for
measurement, control and laboratory use – particular requirements for laboratory
equipment for the heating of material.
Not
Safety Test Refer to Pass Fail Date Signed
Done
Earth
Bonding
OM9.2.3
Insulation
Resistance
OM9.2.3
Comments:
Unstirred Water Bath SUB Aqua Plus SAMPLE COPY 29571 Version 1 – March 2010
Performance Qualification 5
Performance Qualification
Yes No
If yes: Description of fault: _______________________________________________
________________________________________________________________
________________________________________________________________
Rectification: ____________________________________________________
________________________________________________________________
________________________________________________________________
Specialised Return to
User Engineer Manufacturer
________________________________________________________________
________________________________________________________________
________________________________________________________________
Unstirred Water Bath SUB Aqua Plus SAMPLE COPY 29571 Version 1 – March 2010
Performance Qualification 6
Performance Qualification Serial Number:
Summary Report
Successful completion of the preceding activities and tests indicates that this instrument is
operating satisfactorily following recalibration, maintenance or functional checks. The
instrument has passed the Performance Qualification procedure and may now be returned
to use.