Professional Documents
Culture Documents
Spe 27766 MS
Spe 27766 MS
SPE Member
Commht1994,SOCIW
orPetroleum
Engine-,Inc.
‘mapapa,Wmw.rad farmesenmlm
a lW SPEIDOE
Nln!hSympostum
onImproved
01!Rec
ovw he!dinTulsa,
Omk:, U.S.A.,
,7-’20April?994.
329
.
2’. : A review of IoWEOR opportunities for the Brent Field - SPE 27766
Llepm=.risation, the way forward
considered a mature field, In whmh late life optimisation Walls then began to water out and had to be replaced by
becomes an important objective. mid-row producers.
Resemolr pressure has beih maintahed primarily bywa!er In broad terms there are three $and types which can be
injectors positioned ln the aquifer. To reduce the number of Idendfiedgoodquallty sands, tight Intewals, and l&yrinth
wells, injection has been ~@n91edover_Cyc!es I and 1!, sands (Fg. 7). The remaining ail in the good quafity sands
Cycles Ill and IV, and all Units with the StaQord Reservoir. will be located in attic locations above existing wells and in
Producers, on the other hand, are only completed on one areas close to the onset of slump block faulting which may
Cycle or Unit to maintain control of the oil-rims. compartmentalise the raservoh.
As development progressed oil production steadly By-passing will occur in relatively fight sands which do not
increased until a peak production exceeding 500,000 sfbld compete when producing commingled with better quaky
wasachleved in 1984 (Fig.. 5). Up to that mornentthe Gas- sands, ahhough by selectively producing each sub-cycle In
011 Ratio (GOR) remained constant atZOO08cfbbl with a turn, the volume of by-passed oil can be mlnlmlsed.
Iowwatarcut of 10%. The in%ial row of producing wells on
the Brent Resewoh were placed deep in the oil column to The fhwlal nature of the lower Stattjord sands are examples
produce lowshrinkage oilandto avoid gascusping. These of labyrinth sands whore high permeabla channels can
330
,.
SPE27766 C.I.M.Braithwaile 3
direct the waterflood away from the less permeable facies llw process involves the injection of a slug of su~actant
types. :-..::. with brine as a carrier fluld, and the slug pfus oil bsnk is
displacsd towards the producers by an aqueous polymer
In total, k has been estimated that 360- MMstb would have solution. This may be appfied as a secondary or tetiary
bean by-passed, and the estimated sweep efficiency of the process. The economics of this process are extremely
waterflood for the various sand types Is shown in Fig. 8. unfavourabfe, so a more rscently developsd idea is to
perform a Dilute Suktant Flood as part of the secondary
POTENTIAL IOR/EOR PROCESSES recovery process.
To Improve oil and gas recovery a review of 10RfEOR In this case surfactanl is added continuously to the injection
techniques was undertaken. I.n gener?f, f@ Ca!a90ries of water in extremely low concentrations, and the viscous
IORIEOR processes ‘“can be.. distinguished that may be sweep provided by the water moves the oil bank towards the
applicable:- producers. A much reduced polymer concentration is
therefore raquired, and the basic operating cost$ for the
. Microbial processes . platforms arenotcarried bythe EOR process.
. Thermal processes
. Chemical processes As@ IificaM amount of research has been done on Dilute
. Gravity Dralnage”an”d Miscible pmcasses Surfactant flooding in recent years, directed towards finding
. Depressufisation a suitable swfactant, and overcoming the operational
problems associated with the process.
Some of the processes aim to reduce the residual oil’
saturation in the flushed zones of a resewoir, while others Laboratory research has been focused on basic
are’appfied primarily to recover by-passed oil by enhancing displacement phenomena at ultra-low concentrations.
the sweep efficiency of a watwflood. Unfortunately, ff is thought to be very unfikely that a sukable
process will be developed In time for application in the Brent
In view of the depth of the Brent Fiald, and the light nature Field over the next few years. Moreover, since a large
of the oil, neither micro biologicsf nor thermal techniques are propof60n of the reservoir has already been flooded the
believed to be suitable. Evaluation of IORIEOR. opportunities primary targets for application would be the relatively small
therefore concentrated on chemical,. gravity slump block areas at the crest.
drainagelmiscible processes as well as resewoir
Depressurisation: Csustic Flooding Caustic flooding may be applicable
when the crude contains sufficient saponifiable acids. A
Chemical Pro.$6sses slug is injected Into the reservoir and displaced with water.
The caustic reacts with the saponfisble acids to form
During a s?condaty or late se?ndaty waterflood, chemicals surface-active compounds which reduce the intetiacis.1
can be added to the injectbn water eiiher to “reduce- the tens fen, giving alowerresidual oil saturation. Inaddition, at
capillary forces which cause oil to be trapped, or to Improve hlghsalinilies, awater-in-oil emulsion is created which has
the sweep efficiency of the waterflood. There are three an spparent viscosity which is higher than that of the crude.
main types of Chemical process; Polymer flooding, This emulsion can act to stabillse the flood front, giving
Su!?actant floo’dhg and Caustic flood[ng. improved $weep.
Polymer Flooding. Polymer flooding is usually apphed to The crude must have an acid number greater than 0.1 mg
reservoirs whsre tha mobility ratio of the waterflood is KOH/gmto besuitable forthistypeof EOR process. Brent
unfavorable. The polymers are dissolved in the injection crude has a Iowacld number (0.03 mg KOH/gm), making
water to increase its viscosily, so improving the mobility ratio thlspmcess unsuitable.
of the flood, which in turn enhances the wate”ti[ood sweep
efficiency. Gravity drainage and miscible procasses
This type of EoR process is not seen to be sutable In”th@ The gravty drainage process involvas the injection of a
Brent field because the mobility ratio of the Brent waterflood hydrocarbon or non-hydrocarbon gas at the crest of the field
1s extra mely favorable (end-paint mobility ratio of 0.25), (sometimes behind a slug of hydrocarbon hqulds), to give a
giving a very high waterflood ultimate recovery. gravity-statillsed displacement of the Ilquids in the re$ewoir
down towards the orlg inal OWC.
Swfacfanf Fhod;ng. Smfactant (or mlcellarlpolymer)
flooding is a process” which increases mcovary by reducing Where the injection gas and oil are immiscible, gas injection
the residual oil saturation In a water fkmdsd reservoir. may allow effactive gravity drainage of the oil in the gas-
When residual oil is contacted by a sUIfaCfarIt, a So-ca!led invaded zone. This process can result in very low residual
micro-emulsion phase is formed. This micro-emulsion oil saturations, but may requhe excessively long times to
phase has an extremely low interracial tension against both achieve. For miscible processes, the microscopic
oil and btine, and so the residual oil is moblfised, forming a displacement efficiency is Ideal, because capillary forces am
bank in front of the surfactant, sbsent.
I 331
.,
I
4 A mVieWof 10i7/EOR opportunities for the Brent Field - SPE 27766
D.pr.sxxlsatkm, the way forward
Bath the Brent and Statflord riservtirs contain light oil, Research into the miscibilly of nitrogm with Statfjord fluid
overlain by a gas cap and the hydrocarbon columns in ths showed thsf the original crestal gas-like fhdds are almost
two reservoirs have compositions which vary with depth directly miscible with nitrogen and-would in time develop full
(Rsf. 6). Howevsr, in the Statfjord Rsservoir a well deflnsd misoibiiiiy. The deeper oil would not develop miscibility, but
gas-oil cDntaQt is not present. Instead the fluids change the properties of the equilibrium flulds .on the forward tie-line
grsdually from oil-like deep in the column to gas-like towards are so favorable that, in a dispersion-free displacement,
the top. The point of inflection of the bubb[e.point ourve residusl oil saturations could be as low as 50A.
defines the interface beween “gas4, and “oIV. With these
properties, the potential for a miscible diSplaC~ME!t was This ValUe was initially confirmed by slim-tube experiments
highest for the Statfjord Rese-Weir. performed in-house and at Winfriih (Ref. 8), but subsequent
experiments at reservoir condkions using reservoir cores dld
Bearing this” In find, whenever gas production has not find such low residual saturations. Component transfer
excaeded sales requirements it is preferentially injected into beween the nitrogen and the oil could be the cause,
tha Staffjord Resewolr. Although principally for storage, resulting in oil shrinksge and an increase in viscosity which
some benefits from a limited miscible gas drive process are would influence the spesd of the gravity drainage process.
being realised. ., , ..- At field displacement rates, however, a higher microscopic
displacement efficiency might be expeoted [eading to a
For any EOR procsss involving a gas flood, the Injected gas better recovery than seen in the resewoh condition
is more mobile and less dense than the watwloil that it is axperimenfs.
displacing, so over-running or viscous fingering Is a danger,
leading to low sweep efficiency. Thus the application of The Unit technical cost for a 15 year project staiiing after the
these processes IS normally Nmitsd to steeply dpplng, high- waterflood and requiring approximately 4 Tscf of nitrogen
permeability resewoirs. Nevertheless, even for this type of was estimated to fm in exoass of $40rbbL Taking into
reservoir, there is a a limit to how fast the displacement can account the uncertainties in oil recovery, nitrogen injection
be done before becoming unsfsble. was therefore not an Immediately attractive EOR option for
Brent
For Brent, the process should be inherently stable, except in
those sands where the horizonta[ permeability is less than Hydrocsrhon Gas Although Iesn hydrocarbon gas would
500 mD (Ref. 7), Tsking into account the inevitable bY- be dheotly miscible with the top Staffjord gas, the feasibMty
passing of oil reserves In the less permeable layers reduces of performing a full tertiary hydrocarbon gas flood of the
the EOR target by 210 MMsib. ,. Smnt Field wss not investigated in any detail. It wss
considered unlikely that an existing or undiscovered field
However, a practical consideration for thu implementation of could supply the volumes of gas required at low enough
a graviiy drainage process is tha large amount of well price to bring unit technical costs below $40hbl.
activity that would be required. By the and of the waterflood
phase, most wells will have bean completed at the crest of C.w’bon Diox;ds. C02 flooding Is normally conducted as a
the reservoir. Assuming that it would be desirable to stat slug process, and the displacement is done using water.
produofion at an esrly stage, three to four rows of wells When the C02 contacts the oil, hydrocarbons are vaporised
would be required thst follow the downward progress of the into the gss. This extrati[on may be very ‘deep’, involving
20 or more separate 6il.rims (Fig. 9). In total, approximately components up to C30. The hydrocarbon-rich C02 Is then
140 side-tracks would be nsoessary with a similar number of recovered and the hydrocarbons extraoted. In addtiion, ss
Well interventions to shut-off gassed-out zmes 1“ order to in any miscible drive, an oil bsnk will form, supplementing
msxlmlse recovery from each well bore. the vaporisation recovery process.
In addiion, there remainss significant degrae of uncertainty The C02 used for most small EORproji?cts In the USAIS
concerning the final thickness of the oil-rim once it has been usually the unwsnted by-product of a manufacturing or
displaced down to the original oil-water contact. Simulation extraction process. Large scale C02f[oods are carried out
studies indicated that, because of cusping and coning using gas produced from natural C02 reservoirs. There are
effects around a producer, oil-rim thicknesses could not be no known C02-rich resewoirs in the Brent area which would
reduced below an average of 40ft. be sb[e to provide the required volumes.
The attractiveness of pwforming a misclblelnear miscible The feasibility of extrscfing C02 from the flue gss of power
gas flood of the Brent field, at or close to the end of the sfsfions Iocsted in the north-east of England wss looked
waterflood phase, using @fiber nitrogen, carbon dioxide or a into. However, the delivery cost alone equated to $18 to
hydrocarbon gas was evaluated. At an early stage options $36 for evefy Incremental bbl,
involving air, flue gas and Wblne exhaust gsses were ruled
out for both practicsl and safety reasons. Before a C02 flood could begin, significant addtional
expenditure would be Incurred to Install downhole and
Nitrogen The Introduofion of technology to produce large topsides equipment suitable for C02 service, and to insfsll
volumes of the nitrogen from ah using cryogenic techniques the plant required to separate the produced fluids. [n view
has raised interest In this option. of the costs, there was no scope for appliisflon of thks
I process.
332
. .
Depressurisation itself would be achlevqd by wthdrawal Of Wtih these oil-rim management policy in place full field
large volumes of liquids and free gas from the reservoir. The simulations indicste that oillcondensate production will be
proposed scheme envisages using gas-lift i“ cresta[ oil wells sustained during the early stages of depressurisation and
to maximise fluid offtake from existing producers, and, by total recovery will exceed that expected from a pure
maintaining flow through the reservoir, ensures continued waterflood.
production of any remaining waterflood movable oil during
the early stage of depressurisation. Criticsl gas
As gas-lift performance decfines, back production of water Before Iberated gas csn migrate towards the crest acrkics[
through the farmer water injectors using i3ectric gas saturation has to be built-up. Knowledge of this
Submersible Pumps (ESPS) would be required to maintain parameter [s Important in order to establish when gas will be
the required pressure dBplefiOn rate (Fig. 11). DWicated released from by-passed and residual oil, which is essential
facilities, installed as and when necessary, would handle the for estimating future gas ssles potential.
Iwe volumes of aquifer water produced in this way.
Core experiments have confirmed that Sgc in the waterflood
oil zone is dependent upon the pressure decllma rate.
UNCERTAINTIES AND RISKS Extrapolating measurements to field conditions using a
semi-log relationship between pressure decline rate and Sgc
Depressuikation of an oil field of the magnitude of Brent has indicstes a value of 107. (Ref. 10 and Fig. 13).
never been attempted. Quantifying the risks, uncsrtalnties
and possible consequences has therefore been an impmtant Theoretical work has suggested that, at pressure decline
aspect of determining whether the process Is both rates seen in laboratory experiments, gas saturations are
technically and economically viable (Ref. 9). dominated by nucleation effects, but at field decline rates,
gravity effects are dominant. This Mnearextrapolatlon from
Oil-rim managemem one regime to the other is therefore open to Ulscussion.
One of the major concerns with Depressurisation was the Using the 10% value etirapolated from core experiments,
possibi[fty that oil production would be compromised. As simulation studies of the depressurisat[on process
reservoir pressures fall not only would well productivity suggested that an additiona13°A should be included toalfow
decline but the creation of a small gas cap in each of the forvetical transport effecfs within individual flow unifs, and
many layer could result In existing oil producers turning a fwthar 2% to account for possible geological trapping (e.g.
333
i
. .
under small shale layers). Wflh this in min”d, a value of 15°% measurements under both drained and pore pressure
has been used for planning purposes. depletion conditions have been carri6d out The results
indicate that formation compressibility Is almost linear over
Since tio$t of the original gas cap will have bwn flooded, the stress range expected during depressurisation, with
first by oil and then by water prior to depressurisation, the vafues for the Statfjord roughly tvdce that of the Brent.
critical gti saturation In the flooded gas cap is ?m important
value to know, When the reservoir pressure declhres the Predictions indicate that compaction is Ikkely to be in the
trapped gas saturation will increase as gas comes out of order of 1% of the gross reservoir thickness. Under extreme
solution and””the residual gas expands. This increased gas worst case assumptions, compaction will never exceed more
saturation may immediately” be mobile, but timited than 2.5%. From a well integrity viewpoint, field exparlence
experiments to date suggest that it may reach a 507. higher indicates that up to 5-674 compaction on gross reservoir
saturation than the tiapped gas saturation before mobifiry Is thickness can be accommodated, provided th@re are no
achieved. Further theoretical analysis needs to be caviti%s behind the casing. With cavities, this hit reduces to
conducted to understand the physical processes involved. 1-2%. The magnitude of expected compaofion is therefore
not likely to present any threat to sub-surface well integrity,
Aquifer influx
Finite element techniques have. been used to estimate
The size and strength of the aqufier is one .Of the most subsidence. This has taken into account the location of the
important factors that will influence the success of the platform in relation to the shoulder of the subsidence bowl,
depressurisation project. During” the history match of From reoent ah gap measurements on each of the platforms
resewoh pressures, the Brent full field simulation model fi appears that Brent Alpha is the only platform where
indicated’ that the aquifer connected to the Statfjord subddence could reduce the air gap below Ifs current safety
Reservoir is hmited and of low permeabiiiiy. The Brent bmit of 2 m, Predictions indicate that between 1.6 and 2.4 m
Groop aqiiifer, iii” cbntrast, appears to be stronger, with a of subsidence could develop during depressurisation,
pore volume some 15 times larger than the volume of the oil although, even in the high case this would not accur until the
column. year 2004 (Fig, 14). since Brent Alpha would not form pad
of the main refurbishment program fis role at that time
A review of regional geology. and .ps!OrMaOCE .o!. nW.rbY would, at the most, be fimite.d to being a riser jacket for the
fields has helped to define the timifs of the Brem Reservoir FLAGS line. Subsidence, therefore, is unfikely to
aquifer. To the north, a fault zone separating the Brent and compromise the operabilFdyof any of the four platforms.
Sttijord Fields Is currently exposed to a 1000 PSI pressure
differential with no indications of communication. Sand failure
To the west, a major regional fault and deteriorating Predictions based on Iabcmtory measurements and
reservoir properties are separating the Erent Field.!r!m the theoretical work indicate that the initial rock failure of sands
Dunlin/Hutton area. These fields “have historically exhibited of average strength can be expected at a reservoir pressure
very different pressure behavlour to that of BrenL Further of around 3000 psi.
south, the Brent South accumulation and the Strathspey
Field are both in communication with the Brent Field at the A field test, designad to calibrate and supporf this e.st[mate,
Brent Reservoh level. Pressure measurements in the Brent showed a burst of sand production at simulated reservoir
Ninth accumulation of Alwyn North Field prior to production, pressures of 4000, 3100 and 27OO psi. Once a stable
indicates a small degree of communication with Brent. drawdown was established, sand production stabilised and
dropped to trace levels which would be manageable from a
The largest impact of low Brent reservoir pressures would well and facility point of view, Even at a simulated reservoir
be seen In Brent South, aithough the bulk of the ultimate pressure of tOOO psi, no massive sand failure was
recovery from this accumulation will have been produced by observed.
the time full depressurisation of the Brent reservoir is
initiated in the year 2000. The Stratfwpey Field would also Although further research Is in progress on this subject, t is
be influenced to a fimited extent, bm only at the very end of currently assumed that small but manageable amounts of
its production life. sand production will occur once Initial failur~ has been
experienced. On the bask of this test, sand exclusion will
For design purposes, a range of possible aquifer volumes not be incorporated In any of the wells, although contingency
have been considered (up to twice that contained within the measures will be in place to gravel-pack gas and back-
Brent fault block) to evaluate how much water would need to produced water wells it found to be necessary.
be pumped from back-produced water wells with ESPS.
Reservoir souring
Reservoir compaction and well Integrity
H2S is formed when bacteria, introduced with the injected
Reservoir compaction aid reddng sub.sidenc.e could have sea water, come into contact with nutrients in the form of
an impact on wellbore integrity and platform wave height fatty acids within formation water. The bacteria reduce the
safety margins. To provide data upon which compaction and available sulphate in sea water to form hydrogen sulphide
subsidence estimates can be made, uniaxlal compaction which can pa!tition Into the oil.
334
. .
Since production began in 1977; no noticeable increase in Although an attractive possibllky, the topside weight required
H2S levels has been obsewad, amd it is expected that only to procsss d[ Brent’s oil and gas exporl far exceeded the
towsrds the end of the pressure maintenance phase will a load carrying capacky of any of the platforms.
rise above Indigenous Ievsl.s occur. This favorable situation
is thought tobe a result of a c0rpk3!natiOnOf an actk water New centrsl platform - four satellites
shut-off policy, which reduces sea water breakthrough in the
producers, and scavenging by the abundance of iron To overcome the weight limitations of the csntral platform
containing minerals In the Brent Reservoir rock. concepts, the construction of a new central processing
platform, bridge-linksd to Bravo, was evaluated.
During depressuris.atlon, however, H2S formed In the
reservoir, but not produced during the waterflood phase, This option gainsd the benefit in terms of low OPEX but was
may be absgrbad by the llberateU gas as it .~grstes towards reJecfed because of the increased vulnerability with respect
the crest, resuiting in Increased levels of H2s. to meeting gas sales commitments from a single
installation.
Sulphate and chloride concentrations in water samples from
high watercut wells have been used to determine sea Water Two producing pfsfforms, two satellites
fractions, and the loss of sulphate Indicates how much H2S
may have been. generated in the reservoir. The results Maintaining full processing on two central platforms and
provide a range and an upper limit fo the amount of H2S converting the two outboard platforms to satellites should, in
that may have been generated. theory, spread the weight of processing facilities over two
platforms. However, to maintain gas sales while one
Souring data from nearby fields producing from the same processing platform is undergoing routine maintenance
geological formations have shown errat(c variations in during the summer pwiod would require each platform to
behaviour. However, using the Ostribufion of such H2S have 80% of the total processing capacity. Tip-side weight
producing wells, simulation results of a model that describes [Imitations would onca qain be exceeded.
the Br.snl souring mechanism have been scaled to create a
range of probabilistic souring forecasts (Ref. 11). These Refurbishment of existing fscififies
predict a greater than 50% chaiice” of average H2s levels
exceeding th@3.3 ppm contract liriiit for dry gas, but only a Inthisoption each installation woufc produce, process and
25% probabihty of ever exceeding the 25 ppm FL4GS fine expartoil and gas in the same manner ascurrentlyt aking
timit, which would require OffShOrB treatment. However, plac+ although a number of existing modules would be
individual wells may produce up to 150 ppm H2S. replaced by new modules with changed functlonalitiy. The
aim would be to minimise captal costs by limiting the
As a contingency, weight and space would be resewed on amount of new equipment required.
the platforms to allow offshore sweetening facilities to be
installed in the unfikely event thai.they.ar9 needed.. RepIa~ all topside fscifities
PLATFORM CONFIGURATION A “green field approach was considered In which the existing
topsides (except the wellhead module anu the drilling rig)
Proving that depressurisation was a viable project depended would be removed and replaced with two new modules on
to a large extent on a. systemauc evaluation of the each platform. The scheme would incur lowar long term
engineering options and the associated. costs..These options operating costs but this had to be weighed against higher
had to considec ‘ capital costs.
. Safety standards following the Cullen enquiry A analysis of the costs and rewards of the six options
. LQWpressure facilities for depressurisation lndlcatad that only two (the refurbishment and replacement
. Reliability throughout the fields extended Me options) were approaching the economic crtierla. However,
. Environmental aspects fuflher rationalisation was required in ordw to make tha
project attractive.
At the outset it was clear that certain assets, such as the
substructure of all platforms, welfs and pipehnes were in Subsequent studies indicated that depressurisation could be
good ccmdtion and the cost benefit of re-usin9 them was carried out with three out of the four platforms wlh
substantlaf. Therefore sub-sea options wwe not considered, significant cost ssvlngs and only a marginal loss of recovery.
Early scouting studes identified six possitiliiles: The foufth platform, Brent Alpha would funcfion as a riser
platform for the FLAGS Iineonce its production rate falls
One centrsl platform - three satellites below the economic threshold.
In this option, all main production facilities would be located In addition, by combining the cost savings of the
on Brent Charlie, and the other threm platforms would refurbishment option with the OPEX benefits of the
become satellites with minimum mannln.g levels. replacement option, aflnal redevelopment engineering plan
was defined (Fig. 15).
335
1
,,
The new facilities will be designed to opersts at 36 bar first indicates that the project would extend the hfe of ths Brent
stage separator pressure snd handle a total ofhake of Field to at least the year 2010 (Fig. 17).
240,000 .stbld of oil. Suff[clent gas processing capacity will
be available on any two of the three refurbist,ed platforms to CONCLUSIONS
meet gss commitments while the third is shutdown for
routine maintenance, and also cope with possible increases A review of the 10RiEOR options for the Brent Fie[d
in gas export. levels. The spare compression during normal indicatsd that surfactsrd flooding, Immiscible (or near
operations will be used to satisfy gas-fift demands. mkclble) gss injection and depressurisation are technically
viable. However, based on an estimate of the costs
Water injection facihies till be rstained to allow normal Involved it was established that only ressrvoir
wsferflood development of the nearby prospects and any depressurisation was economically attractive under the
non-commun[catlng slump blocks. Sufficient capacity is also current and projected oil pries trend.
planned to permit an intermediate pressure waterflood to
start if depressurisation psrformancs is better than To initiate this new development phase, a 21.3 million
expected. For late Depressurisation, when gas -fift refurbishment programme of three of the four existing
performance declines, Electrical Submersible Pumps (ESPS) platforms will be undertaken. It is expscted that the gas
will be installed in the water Injsctors. In addtion, space and plateau oould be exfendsd to ths year 2003 with incremental
weight provision is being maintained for offshore sweetening gasrecov8ry ofl.5TWfcomparedtoano rmalwaterflood.
facilities to reduce H2S COntent to at least 25 ppm FLAGS
line fimit Mrequlrsd. The risks associated with depressurisation have been
assessed sod where possible, engineering solutions have
Taksn together, the installation of new processing .f@ClliieS, been Identiied in order to minimise their impact on the
refurbishment of Wing quarters, completion of required
Project. From a “Wb-sutiace viewpoint, reservoir
safety upgrades, as well as improvements to the drilling and man2gBment procedures have been Outlindto ensure that
utility modules, will result in an exlentive engineering oil recovery Is msximised while maintaining gas sales Into
programme costing 21.3 Billion that will fske approximately the 21st Century.
SIXyears to wmplete (Ref. 14).
ACKNOWLEDGEMENTS
ADDITIONALRECOVERY
The author would ~keto thank Shell U.K. Exploration and
By lowering reservoir pressures to 1000 psi, up to 2.3 Tscf Production and Esso Exploration and Production U.K.
of wet gas is expecrsd to. be mobilised (Ffa. 16), and a large Limned for their permission to publhh this paper, and
fraction will be csptured by crestal producers. The results of acknowledge the contribution of C. Joly (now with Dansk
the full field simulation model have been used to provide an Shell) who carried out a significant proportion of the EOR
initial estimate of the additional recovery. Following a evaluation work outlined in this paper.
stochastic analysis of the risks and their possible
Consequenos, a discount was. applied to reflect the REFERENCES
uncertainty associated w[th the project. Taking everything
t. Johnson, H.D.and Krol, D.E?<’..Geologicz[ ModeUingofa
into account, depressurlsatimr is likely to yield over 1.5 Tscf
Heterogeneous Sandstone Reservoic Lower Jurassic
additloim wet gas.
Statfjord Formation, Brent Field,” pzpar SPE 13050
presented at the 59th Annual Technical Conference,
COntraly to initial expectations, depressurisation will not lead Houston, Sept. 1984.
to a loss of oillcondensate recovery. In the westf lank,
condensate that would have been trapped in by-passed and 2. Struijk, A, P., and Grean, R.T., 1991, The Brent field,
residual gss at the end of a waterflood will drop out during Block 211/29, UK North Sea. In: Abotts,l.L. (cd.), The
depressurisation.” Of this condensate, a proportion will Geo[ogica! Society Msmoir No.14, United Kingdom Oil and
aooumulate at the oil-rims to be produced via the oil-rim Gss Fields, 25 Years Commemorative volume,
wells with the assistance of gas-lfi.
3. Bath, P.G., Fowler, W.N. and Russel M. P.: “The Brent
In addtion, the combined effect of gravty drainage of Field, A Resarvoir Engineering Review,” paper EUR 164
presented at the European Offshore Petroleum Conference,
watetilood residual oil in the expanding gascaps and the
London, Oct. 1980.
extended waterf looding of the oil-rims using aquifer influx,
could help to incresse of recovery. As gas saturations bulld- 4. Kingston, P.E. and Niko, H.: ‘“Development Planning of
uP, oil exPu!siOn from IOWPefmeabilky areas, and from by- the Brent field,’ JPT (Oct. 1975) 1190-1198.
passed oil in small geological traps will also. occur.
5. Diehl, A.L. :“The Development of The” Brent Ffeld . A
Taking the above factors into account t has bee” estimated Complex Of Projects,’’EUR 108presented atthe European
that depressurisation would. yield approximately 30 MMstb Pstroleum Conference, London, Oct. 1978.
addiional oil compared to a normal waterflood. Predictions
336
. .
9. Eraithwafte, C.L M. and Schulte, W. M.: “Transforming the 13. Tollss, J.M. and Sayers, J.R.: “Brent Field 3-D Reservoir
future of thB Brent Field: Depressurisation - the next Simulation,” Paper presented at 56th Annual Technical
development phsse,” SPE 25026. presented at EUROPEC, Conference, San Francisco, Oct. 1983.
Nov. I 992. “’.
14. Schulte, W. M., wan Rossum, P.A. H., van de Vljver, W.:
10. Kortekaas, T. FM. and van PoelgeeS, F.: ‘“Liberation of
Solution Gas Durlna Pressure Deoletion of Virgin and
Watered-out Oil R&ervolrs,” pap6’r presented ;! 64th
I ,,Current Challenges in the .Brent Field; SPE 2678a,
Offshore Europe, Aberdeen, Sep. 1993.
337
lb A reviewof IOR/EOR.Pp.rtu. itiesf., the Brent Rdd.
SPE 27766
Depressmi,dbII theway forward
!,* - .,
,,ms”KL).3$o\ I A
‘:~”“EE!zl. . ---J:
L BRENT WESTFMNK .,8,)0
1-
CSESTAL SLUMPS
H=l s~,rmaro~n
SLUMPS
GXPILMJ* *..:..:.:..:.:.:..
.:.:..: ,..
..m
A% ~gm
,.7WWS
,----
G ..0,, W03
339
.
ResidualOil in
Bypassed oil Presence of Gas
-.
loooo — ——
*
Ight Sand, ●
g
~
.—
3
● Good
m“:””-”””..”
+ Labytinth
%rds
Sad.
~~
““-”
E. 1Coo- ——————————————-—————-———-
●
:.
-8—— $:
●
*
*
‘
a
. ●
● ‘***
~
● *
5 . ..
+
% .
$
100- —-———-— ——— —-— ——— ——— ———-— ———-— —
*
*
102030. ZO 5060 .70..8C 90100
Waltilmxl Valumelrk Sweep Effide”cy (%)
CJ.h4. BwJthwaite 13
SPE 277G
Cmluvllti c.ff.taue
ANDMIQBATION
y.a,wm
~~ EXVULS!ON
OF
7RAPPEOMYPASSED
OIL
— Exm.tatim of U.R.
-- Highcaaa
I
W%%d + I D.pr,murkatim
““d”a’ +
x ,000
&
2
,
: 4000
:
&
-.
:
.
0
.... YEAR
I (3AS
PLATEAU . . . . .
I n==+-
341
.,.
, D.,
Modal fluid SY.t,lll
; ~77:,,7
/“
lo~ F I // ,~
!—l-d.<.— %y..
-—-—-—-— 5 Yam% R.sav.,,
-—- —-—-— 10 Ymr$ \ C“ndM”m
i% —--—-—--zoy..=
J
01’oz’oia 40s0
G.. S.t.rati.n [%)
Brent
---- —----
Allowable Subsidence
1.00
929496982GQ3G2 04080810
Year
342
-,-
80 A
3 1, +
6000 5000 4000 3000 2000 1000
AVERAGE ABANDONMENT PRESSURE (psi)
mxeswisatbn
athspey & ~.mt
her fields ~ ---
WET GAS
d OIL
:..%
oil
I Eq”Wdmt :
---- t..:
1
-l %_, ~-~
‘1 :..*
%... ..__.%...
-1, L
>..; L.,
,..q--- -.
HISTORY FORECAST ‘-=.-t-. ,..“q..... LI”..% ‘“
%
\
,,%4 ,,98 ,938 2W$ 2W2 20M 20C6 2000 S
YEAR