Professional Documents
Culture Documents
Introduction
1.CP4 vs EC7 in design of bored pile
2.Development of bored pile design from 1970’s to 2010
Design of bored pile
Development of boring rig
Geotechnical Design
Load test
3.Impact in piling contractor due to changes from CP4 to EC7
Pile become smaller
Length increase
Rock socket length increase
Load settlement become higher
4.Suggession and conclusion
2
Presentation note from Dr.T.G.Ng, Date 24/4/2015
3
Presentation note from Dr.T.G.Ng ,Date 24/4/2015
4
Before 1983
5
Boring rig in the 1970’s torque about 10 ton-m
Total weight 35 ton
6
• In 1978 I was told for bored pile
7
By 1983,torque of mechanical boring rig increase to 21 ton-m
9
Ultimate Load Test
The test load of a working load test shall be two times the
designed working load of the pile
10
Failure of Pile
• Maximum settlement under full test load is maximum of 25mm
• The permanent or residual settlement after removal of the test load
exceeds 5mm for piles with nominal working load less than equal to
100 tonnes or 0.05mm per tonne of nominal working load for piles
with nominal working load greater than 100 tonnes subject to a
maximum of 13 mm.
• Failure of pile materials.
• Failure of concrete to reach the design compressive strength
11
Permissible Stress
The minimum and maximum grade of concrete used shall be
Grade 25 and Grade 35 respectively. The minimum and maximum
permissible stress under working load condition shall not exceed
0.2 times the characteristic cube strength of concrete.
Slump of Concrete
The concrete used shall have a slump of not less than 100mm but
not more than 175mm . Slump for tremie concrete may be
increased to not more than 225mm.
12
In 1983 PWD allow bored pile with maximum
permissible stress up to 7 N/mm2 (Grade 35 concrete)
Many engineer still limit the permissible stress to 5.17
N/mm2
13
SUBMISSION TO BUILDING CONTROL UNIT
In compliance to Building Control Act(1989),the contractor shall
submit pile layout plans and design calculation to the Building
Control Unit in HDB’s Civil Engineering Department for approval
before the commencement of the piling works.
1) Certificate of supervision of piling work
2) Certificate of completion of piling work
3)Tow sets of As-Built drawing showing pile penetration and
eccentricity duly endorsed by licensed surveyor and contractor’s
professional engineer
14
NOMINAL WORKING LOAD OF BORED PILE
16
From 1990 to 2017 torque of hydraulic rig increase from 12 to 55 ton-m
17
Quality of rock tools improving
18
• Quality of rock bucket improving
19
• Quality of rock tools keep improving
• Can core into Rock with UCS> 200Mpa
(Note: Slow and high cost)
20
• From 1980 unit now torque increase from 12 tons-m to 55 ton-m
• Kelly bar length get longer from 4x12m to 4x22m
21
Construction of Bored Pile in CP4
22
23
From 1983 to 2003 allowable stress increase from
5.17 to 7.5 N/ mm2 ,45% in 20 years
24
Pile with working
load of 834 tons
CP4(1200mm) and
EC7(1000mm) but
soil and rock
parameter remain
un change so pile
get deeper.
25
Impact in increase in pile length
1) On pile bore into soil only
2) On pile bore into soil and rock
26
The longer is the kelly bar,the rig get bigger
Kelly Bar Length Max Penetration
4x12m 42m
4x15m 54m
4x17m 62m
4x20m 74m
4x22m 82m
27
• When pile go deeper, say
go to 90m must use 5
elements kelly bar with
reduce torque by 50%
because thickness of
kelly bar getting thinner.
28
Standard Bill of quantity pay piling contractor on
meter run regarding of pile depth
To contractor bored from 50 to 60 m is different
from bore from 40 to 50 m
29
Reason
1)Bored to deeper depth kelly bar take longer
time to move up and down
2)As kelly bar get longer torque reduce
30
Standard bill of quantity pay piling contractor
extra over for socketing into rock regardless
of rock grade(either GI,GII or GIII)
31
Rock weathering classification
GIII GIII
32
• When rock socket
length increase, rock
get harder chances to
bored into G1 rock is
getting harder
33
• More and more fresh
granite bored out
from pile hole
34
➢ CP4 , 1000mm pile test to 589 tons x 2 = 1178 tons
35`
Working stress of the total 9 project carried out by KH FOGES
Site No Working Stress (MPa) Remarks
36
➢ CP4
1) Limit the working stress to 7.50 Mpa
2) Allowable settlement at 2x WL=25mm
3) Present equipment can handle very well
4) Cost effective
37
➢ From 1982 to 2003
38
➢ From CP4 to EC7
Allowable stress of bored pile increase from 7.5N/mm² to
10.26N/mm²(37%) boring tools and boring rigs need more
time to improve
39
40
➢ EC7
1) Working stress can be as high as 10.60 MPa
2) Allowable settlement at 2x WL=25mm
3) Over load the present boring rigs in particular big pile
4) Increase cost and time for boring
5) Higher risk in load test failure
➢ While waiting for boring tools and boring rigs to improve
41
42