Construction Team

Site Construction Matter


Target
No Critical Issues and Action Plan required Status Action By Remark
Required Actual

Bauer manual
1
hacking delay
• T1 manual hacking by Bauer delayed Bauer hacking has done (32ea / 32ea, 100%) Bauer 31st May 30th June Final excavation delayed 1 month

Final soil Bauer requested to excavate until Cut off level of


• Final excavation soil damaged due to
damaged due to board piles and this will impact soil condition due to
2
Bauer manual
Bauer manual pile hacking to use SCT
shifting con’c debris by Bauer
hacking machine
→ Might need to replace soil

Bauer didn’t complete toe grouting for all of board


Bauer shared T1 schedule
Grouting for • Crash work of grouting for board piles piles
3 Bauer ASAP Grouting for T1 will complete by 21st
Board piles for every piles T1-1 will start to toe grouting 23rd June
July
→ more than 1 month delay

Temp stock • Need to stock pile con’c debris at Gate For Bauer pile hacking con’c debris have to dispose
4 piling of con’c #2 area due to EMCO all dumping yard accordingly Bauer
debris for Con’c debris closed → Need to stock piling con’c debris temporary

1
Construction Team
■ Bauer manual pile hacking delay for T1
As of 20/ May/ 2021
- T1 manual hacking was done 32 nos as of 30 th June
- T1 manual hacking should be done by 31 st May due to change of sequence of final excavation

Board pile hacking status by 2nd July


Zone Total pile no Exposed 1st hacking Complete 1st hacking Final HO until COL Complete pile hacking Final HO from Bauer

T1 33 33 33 33 32 32
T2 PIT 8 8 8 0 0 0
T3 33 33 33 33 17 0
T2 27 27 27 27 11 0
T4 31 13 5 4 0 0
T4 PIT 8 5 0 0 0 0

Total 140 119 106 97 60 32

As of 24th May
2
Construction Team
■ Final excavation soil damaged by Bauer
- Bauer requested until COL of board piles
for their manual hacking to excavate
- Bauer used big machine for manual hacking
and remove con’c debris with excavator
→ Final soil level damaged
and have to be replaced with solid soil
※ T1-1 150mm replaced soil ※ T1-2 42 ~ 723mm replaced soil
SCT suggested level for manual hacking 300mm higher than COL

-99m -42m
300mm -628mm -723mm -621mm
-143m
Requested level for manual hacking by Bauer Cut off level -239m
-261mm
Current excavation level 75mm
Lean con 75mm -144mm

Crush run 150mm


Final excavation level
As of 24 Mayth

Board pile
T1-2 over excavation (-42 ~ 723mm) 3
Construction Team
■ Remaining grouting works for all board piles
As of 20/ May/ 2021
- 137 nos of board piles need to do grout not only a few of them
Water proofing work can’t proceed at the same time with grouting due to using much water
for grouting by Bauer

→ RC work will be delay until completion of grouting

Bituthene Liquid membrane

T 104

As of 24th May

CSL report by Bauer


BP T42 Damage soil final level
4
Construction Team
■ Stock piling con’c debris temporary at Gate #2
As of 20/ May/ 2021
- Bauer need to dispose con’c debris accordingly for manual hacking however
due to EMCO all dumping yard for con’c debris closed.

→ Stock pile con’c debris at Gate #2 temporary around 20 ~ 30 lorries until lifting EMCO

Stock pile area

5
Construction Team PHOTO DATE : 2/ July/ 2021

6
Construction Team
Logistics Plan for L00 as of 3rd July

7
Construction Team
Logistics Plan for LC as of 3rd July

8
Construction Team
Logistics Plan for LP2 as of 3rd July

9
Construction Team
Logistics Plan for LP4 as of 3rd July

10
For Internal Purpose only
Construction Team
■ Overall Status by 1st August
North Elevation View South Elevation View

East Elevation View West Elevation View

* Reference Plan: 210524 - 3 Month schedule May 2021_R1 11


Construction Team For Internal Purpose only

P4 Rebar schedule Updated 2021-06-28

Approved Issued Order 1st Rebar Rebar Casting


shop dwg BBS Rebar Delivery Start Date

T1 2021-05-03 2021-05-09 2021-06-22 2021-07-06 2021-07-20 2021-09-06


T2 Pit 2021-04-16 2021-04-23 2021-04-24 2021-05-20 2021-08-09 2021-08-31
T2 2021-08-29 2021-09-12 2021-09-14 2021-09-28 2021-10-12 2021-11-20
T3 2021-03-31 2021-06-28 2021-07-25 2021-08-08 2021-08-22 2021-10-02
LP4
T4 2021-09-03 2021-09-17 2021-09-24 2021-10-08 2021-10-22 2021-12-05
B6 2021-05-06 2021-05-15 2021-05-22 2021-06-05 2021-06-19 2021-07-08
B5 2021-05-10 2021-05-29 2021-06-05 2021-06-19 2021-07-03 2021-07-18
B4 2021-05-10 2021-06-04 2021-06-11 2021-06-25 2021-07-09 2021-07-25

• Due to FMCO T1 rebar fabrication pending, top bar still didn’t order
• T2 PIT rebar need to modify and reorder some portion
• T3 bottom bar ordered 28th June
• Mega core starter bar shop dwg pending
12
Construction Team For Internal Purpose only

3 WEEK SCHEDULE [2021/06/27 - 2021/07/17] Updated :5th July

Last week This week Next week


Description T Const Plan Actual Diff. Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat
Start Finish Dur Start Finish Dur Prog. 06/27 06/28 06/29 06/30 07/01 07/02 07/03 07/04 07/05 07/06 07/07 07/08 07/09 07/10 07/11 07/12 07/13 07/14 07/15 07/16 07/17
Engineering Schedule 0 0
Rebar Order 0 0
P4 T2 Pit rebar fabrication 2021-04-17 2021-07-15 77 2021-04-24 2021-05-31 32 55%
P4 T1 rebar fabrication 2021-04-24 2021-07-15 71 2021-05-12 0
P4 T3 rebar fabrication 2021-06-28 2021-08-01 30 2021-06-29 0
Level P4 0 0
Excavation 0 0
Excavation T2 pit (1,200 m3) 2021-06-14 2021-06-19 6 2021-06-29 0
Excavation T4 (8,600 m3) 2021-06-19 2021-06-30 10 2021-07-07 2021-07-17 10
Excavation P8 (3,150m3) 2021-06-19 2021-06-27 7 2021-06-19 0 80%
Manual board pile hacking by Bauer 0 0
Manual hacking T1 G 2021-05-23 2021-06-20 24 2021-05-18 2021-06-30 38
Hacking T1-3 2021-05-18 2021-06-20 29 2021-05-18 2021-06-30 38 100%
Manual hacking T2 Pit 2021-06-20 2021-07-01 10 0
Manual hacking T3 G 2021-07-02 2021-07-23 19 2021-06-22 0
Hacking T3-1 2021-07-02 2021-07-11 8 2021-06-22 2021-07-06 13 90%
Hacking T3-2 2021-07-08 2021-07-18 9 0
Hacking T3-3 2021-07-16 2021-07-23 7 0
Compaction and leancon 0 0
compaction and leancon T1 G 2021-06-11 2021-06-28 15 2021-06-13 2021-07-08 22
T1-1 2021-06-11 2021-06-18 7 2021-06-13 2021-06-22 8 100%
T1-2 2021-06-16 2021-06-23 7 2021-06-25 2021-07-01 6 100%
T1-3 2021-06-21 2021-06-28 7 2021-07-01 2021-07-08 7 20%
Board pile grouting 0 0
T1-1 2021-06-26 2021-07-05 8 2021-06-26 0 30%
T1-2 2021-07-02 2021-07-11 8 0
T1-3 2021-07-09 2021-07-18 8 0
Slope of P & T zone leancon 0 0
Formwork and leancon (T1) 2021-06-21 2021-06-28 7 2021-06-23 2021-07-06 12 70%

13
Construction Team
Updated : 5th July
3 WEEK SCHEDULE [2021/06/27 - 2021/07/17]
Last week This week Next week
Trade Description T Plan Actual Diff. Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat
Start Finish Dur Start Finish Dur Prog. 06/27 06/28 06/29 06/30 07/01 07/02 07/03 07/04 07/05 07/06 07/07 07/08 07/09 07/10 07/11 07/12 07/13 07/14 07/15 07/16 07/17
Earth work 0 0 0

Excavation LP4 T2 pit (1,200 m3) 2021-06-14 2021-06-19 6 2021-06-29 0

Excavation T3 (9,200 m3) 2021-06-10 2021-06-18 8 2021-06-10 2021-06-23 12 100%

Excavation T4 (8,600 m3) 2021-06-19 2021-06-30 10 2021-07-07 2021-07-17 10

Excavation B8 (3,150m3) 2021-06-19 2021-06-27 7 2021-06-19 0 80%

Manual board pile hacking by Bauer 0 0

Manual hacking T1 G 2021-05-23 2021-06-20 24 2021-05-18 2021-06-30 38

Hacking T1-3 2021-05-18 2021-06-20 29 2021-05-18 2021-06-30 38 100%

Manual hacking T2 Pit 2021-06-20 2021-07-01 10 0

Manual hacking T3 2021-07-02 2021-07-23 19 2021-06-22 0

Hacking T3-1 2021-07-02 2021-07-11 8 2021-06-22 2021-07-06 13 90%


Excavation
Hacking T3-2 2021-07-08 2021-07-18 9 0

Hacking T3-3 2021-07-16 2021-07-23 7 0

Compaction and leancon 0 0

compaction and leancon T1 G 2021-06-11 2021-06-28 15 2021-06-13 2021-07-07 21

T1-1 2021-06-11 2021-06-18 7 2021-06-13 2021-06-22 8 100%

T1-2 2021-06-16 2021-06-23 7 2021-06-25 2021-07-01 6 100%

T1-3 2021-06-21 2021-06-28 7 2021-07-01 2021-07-08 7 20%

Board pile grouting 0 0

T1-1 2021-06-26 2021-07-05 8 2021-06-26 0 30%

T1-2 2021-07-02 2021-07-11 8 0

T1-3 2021-07-09 2021-07-18 8 0

Slope of B & T zone leancon 0 0


RC work
Formwork and leancon (T1) 2021-06-21 2021-06-28 7 2021-06-23 2021-07-06 12 70%

14
Construction Team
■ Detail schedule of excavation and pile hacking
- Input Bauer schedule base on T1 progress
- T1 manual hacking completion date delayed 30 days (31 st May → 30th June)
Detail schedule of excavation and pile hacking
1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week
ID Description T Plan Actual Diff. S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Start Finish Dur Start Finish Dur Prog. 05/16 ~ 05/22 05/23 ~ 05/29 05/30 ~ 06/05 06/06 ~ 06/12 06/13 ~ 06/19 06/20 ~ 06/26 06/27 ~ 07/03 07/04 ~ 07/10 07/11 ~ 07/17 07/18 ~ 07/24 07/25 ~ 07/31 08/01 ~ 08/07 08/08 ~ 08/14 08/15 ~ 08/21 08/22 ~ 08/28
LP4 - T1 0 0
Excavation to Expose Pile to COL (10ea) 2021-05-20 2021-05-22 3 2021-05-22 2021-05-23 1 100%
Manual Hacking to Pile COL by Bauer (33ea) 2021-05-23 2021-06-20 24 2021-05-23 2021-06-30 32 100%
LP4 - T2 0 0 T4 Part 1
T2 Part 1 0 0
Piles 1st Hacking by Bauer (missing 1) 2021-05-15 2021-05-17 2 2021-05-17 2021-05-17 1 100%
Excavation to Expose Pile to COL (8ea) 2021-05-18 2021-05-21 4 2021-05-18 2021-05-21 4 100% T4 PIT
Handover to Bauer until COL (8ea) 2021-05-22 2021-05-22 1 2021-05-22 2021-05-23 1 100%
Manual Hacking to Pile COL by Bauer (8ea) 0 0
T2 Part 2 0 0 T2 PIT T2 Part 1
Piles 1st Hacking by Bauer (10ea) 2021-05-18 2021-05-20 3 2021-05-22 2021-05-24 2 100%
MRT Dwall Hacking 2021-05-14 2021-05-21 7 2021-05-14 2021-05-25 10 100%
Excavation to Expose Pile to COL (14ea) 2021-05-21 2021-05-25 4 2021-05-26 2021-06-16 19 100%
Handover to Bauer until COL (14ea) 2021-05-26 2021-05-26 1 2021-06-16 2021-06-16 1 100%
T3
Manual Hacking to Pile COL by Bauer (14ea) 2021-07-24 2021-08-05 11 0
T2 Part 2
T2 Pit 0 0
Piles 1st Hacking by Bauer (12ea) 2021-05-23 2021-05-24 1 2021-06-18 2021-06-24 6 100%
Excavation to Expose Pile to COL (12ea) 2021-05-25 2021-06-01 7 7
Handover to Bauer 2nd Hacking to Pile COL (12ea) 2021-06-02 2021-06-02 1 1
Manual Hacking to Pile COL by Bauer (12ea) 2021-06-21 2021-07-01 10 9
0 0
LP4 - T3
Excavation to expose pile for 1st Hacking (33ea) 2021-05-07 2021-05-10 3 2021-05-07 2021-05-10 3 100%
FMCO
Piles 1st Hacking by Bauer (33ea) 2021-05-22 2021-05-27 5 2021-05-22 2021-05-27 5 100%
Excavation to Expose Pile to COL (33ea) 2021-06-10 2021-06-18 8 2021-06-10 2021-06-23 12 100%
Handover to Bauer 2nd Hacking to Pile COL (33ea) 2021-06-19 2021-06-19 1 2021-06-24 2021-06-24 1 100%
Manual Hacking to Pile COL by Bauer (33ea) 2021-07-02 2021-07-23 19 2021-06-25 2021-07-19 19 30%
LP4 - T4 0 0
T4 Part 1 0 0
Excavation to expose pile for 1st Hacking (29ea) 2021-06-19 2021-06-24 5 2021-07-07 2021-07-12 5
Piles 1st Hacking by Bauer (29ea) 2021-06-25 2021-06-30 5 0
Excavation to Expose Pile to COL (29ea)' 2021-06-25 2021-06-30 5 2021-07-13 2021-07-17 0
Handover to Bauer 2nd Hacking to Pile COL (29ea) 2021-06-30 2021-06-30 1 0
Manual Hacking to Pile COL by Bauer (29ea) 2021-08-06 2021-08-18 11 0
T4 Pit 0 0
Excavation to expose pile for 1st Hacking (10ea) 2021-07-01 2021-07-03 3 0
Piles 1st Hacking by Bauer (10ea) 2021-07-04 2021-07-09 5 0
Excavation to Expose Pile to COL (10ea) 2021-07-10 2021-07-15 5 0
Handover to Bauer 2nd Hacking to Pile COL (10ea) 2021-07-15 2021-07-15 1 0
Manual Hacking to Pile COL by Bauer (10ea) 2021-08-19 2021-08-26 7 0

15
Construction Team
■ LP4 T1 handover status with Bauer

□ Excavation and Leancon plan


Excavation Manual hacking Compaction and leancon
Zone Remark
Plan Actual Plan Actual Plan Actual

T1 - 1
T1-1 20-May 22-May 10-Jun 19-Jun 16-Jun 22-Jun

T1-2 18-May 19-May 21-Jun 24-Jun 27-Jun 2-Jul

T1-3 17-May 17-May 25-Jun 30-Jun 1-Jul

T1 - 2

□ Pile hacking progress As of 2th July

T1 - 3
Zone Total pile no Exposed 1st hacking Complete 1st hacking Final HO until COL Complete pile hacking Final HO from Bauer

T1 33 33 33 33 32 32
T2 PIT 8 8 8 0 0 0
T3 33 33 33 33 17 0
T2 27 27 27 27 11 0
T4 31 13 5 4 0 0
T4 PIT 8 5 0 0 0 0

Total 140 119 106 97 60 32

<T1 Zone>
16
Construction Team
■ LP4 T2 handover status with Bauer

□ Excavation and Leancon plan

Excavation Manual hacking Compaction and leancon


Zone Remark
Plan Actual Plan Actual Plan Actual

T2-PIT 1-Jul 11-Jul 18-Jul

T2 Done Done 29-Jul 5-Aug

※ Bauer started 1st hacking from 18th June

※ Excavation and hacking for PIT have stopped since 9 th July

T2 PIT 17
Construction Team
■ LP4 T3 handover status with Bauer

□ Excavation and Leancon plan


Excavation Manual hacking Compaction and leancon
Zone Remark
Plan Actual Plan Actual Plan Actual

T3-1 15-Jun 15-Jun 4-Jul 11-Jul

T3-2 21-Jun 21-Jun 13-Jul 20-Jul

T3-3 23-Jun 23-Jun 19-Jul 26-Jul


T3 - 3
Excavation : Done

T3 - 2
Excavation : Done

T3 - 1
SCT : Done

T3 Zone
18
Construction Team For Internal Purpose only

■ 3 month ahead schedule for excavation Target to complete excavation - Delay


+ Ahead

Level Panel Excavation Diff.

By June By Aug By Sep


T2 20 Mar
th
* Legend By July

By Oct T3 16th Mar


P2
P3 8h Apr
P4 8th Apr
T1 22nd May
T 2 PIT 6th July -5 ● Pit stopped
T2 21st June
T3 23th June
● MRT handover delay (28th Feb → 31st Mar)
T4 17th July -5
T4 PIT 25th July -5
● P zone excavation after
P8 5th July -8 T zone finish
P4 P6 6th July
P5 24th July
P4 5th Aug
P3 14th Aug
P2 24th Aug
P1 30th Aug
P9 5th Sep
P7 11th Sep

19
Construction Team For Internal Purpose only

■ Manual pile hacking schedule Requested manual Pile hacking - Delay


+ Ahead

Level Panel Hacking done Diff.

* Legend By June By July By Aug By Sep T1 30th June -1 ● FMCO

By OCT By Nov
T2 - Pit 17th July -5

T2 5th Aug

T3 25th July -2

T4 26th Aug

P 10 30th June -10

P6 4th Sep

P4 P5 13th Sep

P4 22th Sep

P3 1st Oct
※ P zone hacking start after completion T zone
P2 10th Oct
※ Still didn’t receive any updated schedule by Bauer
P1 19th Oct

P9 28th Oct

P7 6nd Nov

P8 15th Nov

20
Construction Team For Internal Purpose only

■ Compaction and leancon Compaction and leancon schedule - Delay


+ Ahead
Compaction &
Level Panel Diff.
Lean con
By June By July By Aug
* Legend By Sep T1 9th July -5
By OCT By Nov
T2 - Pit 25th July

T2 13th Aug

T3 2th Aug

T4 3th Sep

T4 - Pit 11th Sep

P6 8th Sep

P4 P5 17th Sep

P4 26nd Sep

P3 5th Oct

※ Manual hacking sequence changed to do P2 14th Oct


before final compaction and lean con
P1 23th Oct
※ P zone compaction start after completion T zone
P9 1th Nov

P7 7th Nov

P8 20th Nov

21
Construction Team For Internal Purpose only

■ Grouting work by Bauer Grouting work schedule - Delay


+ Ahead
Compaction &
Level Panel Diff.
Lean con
By June By July By Aug
* Legend By Sep T1 16th July -5
By OCT By Nov
T2 - Pit 30th July

T2 20th Aug

T3 10th Aug

T4 10th Sep

T4 - Pit 18th Sep

P6 15th Sep

P4 P5 22th Sep

P4 30th Sep

P3 12th Oct
※ Grouting work schedule
P2 21th Oct

P1 30th Oct

P9 8th Nov

P7 14th Nov

P8 27th Nov

22
Construction Team For Internal Purpose only

■ 4 month ahead schedule for water proofing Target to complete water proofing - Delay
+ Ahead

Level Panel Water proofing Diff.

* Legend By June By July By Aug By Sep T1 24th July -5


By OCT By Nov
T2 - Pit 8th Aug

T2 18th Aug

T3 21th Aug

T4 - Pit 19th Sep

T4 26th Sep

P 10 22st Nov

P6 16th Sep
P4
P5 6th Oct

P4 10th Oct

※ P zone water proofing start after completion T zone P3 13th Oct

P2 22th Oct

P1 11st Nov

P9 6st Nov

P7 15th Nov

P8 24th Nov

23
Construction Team For Internal Purpose only

■ Top down RC work schedule Target to cast con’c date - Delay


+ Ahead
* Baseline program Rev 1
Baseline Diff.
Level Panel Casting Difference
Casting* last week
By July By Aug
* Legend T1 20th Feb 23th Feb -3
By Sep By Oct By Nov By Dec T4 22th Mar 27h Feb 23
T5 12th Mar 9th Mar 3
T6 2 Mar
nd
4th Mar -2
P2 T 3-2 18th Mar 27th Mar -9
●: MRT handover 28th Feb →1th Apr
T 3-1 6th Apr 7nd Apr -1
●: MRT handover 28th Feb →10th Mar
T2 29th Mar 7th Apr -9
P3 1 Apr
st
22 Apr
th -21
P4 9th Apr 26th Apr -17
T1 9th Aug 9th Sep -31 -3
Level P2 T2 - Pit 21th July 31th Aug -41
T2 21th Oct 21th Nov -31
T3 2th Sep 4th Oct -32
T4 - Pit 9th Sep 13th Oct -34
T4 16th Nov 5th Dec -19
P 10 23th Nov 4th Dec -11
P6 13th Sep 6th Oct -23
P4
P5 16 Nov
th
19th Oct 28
P4 6th Dec 23th Oct 44
P3 23th Dec 2th Nov 51
P2 11th Jan 11th Nov 61
P1 29th Jan 1th Dec 59
P9 18th Feb 29th Dec 51
P7 8th Mar 1st Jan 66
P8 26th Mar 20th Jan 65 24
Internal purpose only
Construction Team Requested by CRE

■ Top down RC work schedule Target to cast con’c date


* Baseline program Rev 1

Level Panel Casting Remark

* Legend By July By Aug T1 23 Feb


th

By Sep By Oct By Nov By Dec T4 27h Feb


T5 9th Mar
T6 4th Mar
P2 T 3-2 27th Mar
●: MRT handover 28th Feb →1th Apr
T 3-1 7nd Apr
●: MRT handover 28th Feb →10th Mar
T2 7th Apr
P3 22th Apr
P4 26th Apr
T1 9th Sep
Level P2 T2 - Pit 31th Aug
T2 21th Nov
T3 4th Oct
T4 - Pit 13th Oct
T4 5th Dec
P 10 4th Dec
P6 6th Oct
P4
P5 19th Oct
P4 23th Oct
P3 2th Nov
P2 11th Nov
P1 1th Dec
P9 29th Dec
P7 1st Jan
P8 20th Jan 25
Construction Team For Internal Purpose only

Manpower plan from July for Raft work


1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week
ID Description T Plan S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Start Finish Dur 06/27 ~ 07/03 07/04 ~ 07/10 07/11 ~ 07/17 07/18 ~ 07/24 07/25 ~ 07/31 08/01 ~ 08/07 08/08 ~ 08/14 08/15 ~ 08/21

T1 Raft rebar work 2021-07-12 2021-08-26 40


110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110

T1 raft formwork 2021-07-12 2021-07-26 13


30 30 30 30 30 30 30 30 30 30 30 30 30 30 30

T2 Pit raft rebar work 2021-07-25 2021-08-15 18


80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80 80

T2 Raft rebar work 2021-10-04 2021-11-11 34

T2 Raft fromwork 2021-10-05 2021-10-11 6

T3 Raft rebar work 2021-08-12 2021-09-23 37


110 110 110 110 110 110 110 110 110 110

T3 Raft formwork 2021-08-12 2021-08-25 12


30 30 30 30 30 30 30 30 30 30

T4 Raft pit rebar work 2021-09-20 2021-10-11 19

T4 Raft rebar work 2021-10-22 2021-12-02 36

T4 Raft formwork 2021-10-22 2021-10-27 5

Maga core Zone A 2021-09-05 2021-10-13 33

Mega column Zone A 2021-09-05 2021-09-30 22

Total Manpower 0 0 140 140 140 140 140 140 140 140 140 140 140 140 140 220 220 190 190 190 190 190 190 190 190 190 190 190 190 190 190 190 190 330 330 330 330 250 250 250 250 250 250

26
Construction Team
LC Column schedule As of 5th July
■ LC column schedule ※ Work done : 50/52 (96%)
- 1st cast done (H 3.9m) : 52/52 (100%)
- 2nd cast done (full height) : 50/52 (96%) Panel Start Finish Remain
* Form work plan Done This week Nest week

* 1st casting 2nd casting P1 2nd Feb 11th Feb Done

P2 15th Feb 24th Feb Done

P8 25th Feb 3rd Mar Done


RR
P7 5th Mar 8th Mar Done
Rebar
QQ P6 9th Mar 12th Mar Done

void P5 12th Apr 15th Apr Done


PP
P4 17th Mar 25th Mar Done
OO
P3 26th Mar 19th Apr Done

NN P1 18th June 21st June Done

P2 22nd June 30th June Done


MM
P8 25th Apr 3rd May Done

LL Form P7 19th June 21st June Done


void +
Casting P6 26th June 29th June Done
KK
2nd casting done P5 30th June 2nd July Done
JJ P4 5th July 10th July
1st casting done
P3 5th July 17th July

27
② ③ ④ ⑤ ⑥ ⑦ ⑧ ⑨ ⑩
Construction Team For Internal Purpose only

■ LP2 column schedule


* Rebar work plan Done This week Nest week

On hold due to Bauer deviation


LP2 Column schedule
Panel Start Finish Remain

B1 14th May 26th June 11

B2 6th May 30th June 14

B8 21st May 3st July 6

Rebar B7 19th May 25th May 6

(H 6m) B6 7

B5 6

B4 14

B3 8

※ P3, P4, P5, P6 don’t have for con Dwg

28
Construction Team
■ D wall rectification status by Bauer LC to L00

NOTE :

Level C to Level 00 :
D-wall rectification work ( Hacking and
Grouting ) done by Bauer

LC to L00
29
Construction Team
■ D wall rectification status by Bauer LP2 to LC

30