Bauer manual
1
hacking delay
• T1 manual hacking by Bauer delayed Bauer hacking has done (32ea / 32ea, 100%) Bauer 31st May 30th June Final excavation delayed 1 month
Temp stock • Need to stock pile con’c debris at Gate For Bauer pile hacking con’c debris have to dispose
4 piling of con’c #2 area due to EMCO all dumping yard accordingly Bauer
debris for Con’c debris closed → Need to stock piling con’c debris temporary
1
Construction Team
■ Bauer manual pile hacking delay for T1
As of 20/ May/ 2021
- T1 manual hacking was done 32 nos as of 30 th June
- T1 manual hacking should be done by 31 st May due to change of sequence of final excavation
T1 33 33 33 33 32 32
T2 PIT 8 8 8 0 0 0
T3 33 33 33 33 17 0
T2 27 27 27 27 11 0
T4 31 13 5 4 0 0
T4 PIT 8 5 0 0 0 0
As of 24th May
2
Construction Team
■ Final excavation soil damaged by Bauer
- Bauer requested until COL of board piles
for their manual hacking to excavate
- Bauer used big machine for manual hacking
and remove con’c debris with excavator
→ Final soil level damaged
and have to be replaced with solid soil
※ T1-1 150mm replaced soil ※ T1-2 42 ~ 723mm replaced soil
SCT suggested level for manual hacking 300mm higher than COL
-99m -42m
300mm -628mm -723mm -621mm
-143m
Requested level for manual hacking by Bauer Cut off level -239m
-261mm
Current excavation level 75mm
Lean con 75mm -144mm
Board pile
T1-2 over excavation (-42 ~ 723mm) 3
Construction Team
■ Remaining grouting works for all board piles
As of 20/ May/ 2021
- 137 nos of board piles need to do grout not only a few of them
Water proofing work can’t proceed at the same time with grouting due to using much water
for grouting by Bauer
T 104
As of 24th May
→ Stock pile con’c debris at Gate #2 temporary around 20 ~ 30 lorries until lifting EMCO
5
Construction Team PHOTO DATE : 2/ July/ 2021
6
Construction Team
Logistics Plan for L00 as of 3rd July
7
Construction Team
Logistics Plan for LC as of 3rd July
8
Construction Team
Logistics Plan for LP2 as of 3rd July
9
Construction Team
Logistics Plan for LP4 as of 3rd July
10
For Internal Purpose only
Construction Team
■ Overall Status by 1st August
North Elevation View South Elevation View
• Due to FMCO T1 rebar fabrication pending, top bar still didn’t order
• T2 PIT rebar need to modify and reorder some portion
• T3 bottom bar ordered 28th June
• Mega core starter bar shop dwg pending
12
Construction Team For Internal Purpose only
13
Construction Team
Updated : 5th July
3 WEEK SCHEDULE [2021/06/27 - 2021/07/17]
Last week This week Next week
Trade Description T Plan Actual Diff. Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat
Start Finish Dur Start Finish Dur Prog. 06/27 06/28 06/29 06/30 07/01 07/02 07/03 07/04 07/05 07/06 07/07 07/08 07/09 07/10 07/11 07/12 07/13 07/14 07/15 07/16 07/17
Earth work 0 0 0
14
Construction Team
■ Detail schedule of excavation and pile hacking
- Input Bauer schedule base on T1 progress
- T1 manual hacking completion date delayed 30 days (31 st May → 30th June)
Detail schedule of excavation and pile hacking
1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week
ID Description T Plan Actual Diff. S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Start Finish Dur Start Finish Dur Prog. 05/16 ~ 05/22 05/23 ~ 05/29 05/30 ~ 06/05 06/06 ~ 06/12 06/13 ~ 06/19 06/20 ~ 06/26 06/27 ~ 07/03 07/04 ~ 07/10 07/11 ~ 07/17 07/18 ~ 07/24 07/25 ~ 07/31 08/01 ~ 08/07 08/08 ~ 08/14 08/15 ~ 08/21 08/22 ~ 08/28
LP4 - T1 0 0
Excavation to Expose Pile to COL (10ea) 2021-05-20 2021-05-22 3 2021-05-22 2021-05-23 1 100%
Manual Hacking to Pile COL by Bauer (33ea) 2021-05-23 2021-06-20 24 2021-05-23 2021-06-30 32 100%
LP4 - T2 0 0 T4 Part 1
T2 Part 1 0 0
Piles 1st Hacking by Bauer (missing 1) 2021-05-15 2021-05-17 2 2021-05-17 2021-05-17 1 100%
Excavation to Expose Pile to COL (8ea) 2021-05-18 2021-05-21 4 2021-05-18 2021-05-21 4 100% T4 PIT
Handover to Bauer until COL (8ea) 2021-05-22 2021-05-22 1 2021-05-22 2021-05-23 1 100%
Manual Hacking to Pile COL by Bauer (8ea) 0 0
T2 Part 2 0 0 T2 PIT T2 Part 1
Piles 1st Hacking by Bauer (10ea) 2021-05-18 2021-05-20 3 2021-05-22 2021-05-24 2 100%
MRT Dwall Hacking 2021-05-14 2021-05-21 7 2021-05-14 2021-05-25 10 100%
Excavation to Expose Pile to COL (14ea) 2021-05-21 2021-05-25 4 2021-05-26 2021-06-16 19 100%
Handover to Bauer until COL (14ea) 2021-05-26 2021-05-26 1 2021-06-16 2021-06-16 1 100%
T3
Manual Hacking to Pile COL by Bauer (14ea) 2021-07-24 2021-08-05 11 0
T2 Part 2
T2 Pit 0 0
Piles 1st Hacking by Bauer (12ea) 2021-05-23 2021-05-24 1 2021-06-18 2021-06-24 6 100%
Excavation to Expose Pile to COL (12ea) 2021-05-25 2021-06-01 7 7
Handover to Bauer 2nd Hacking to Pile COL (12ea) 2021-06-02 2021-06-02 1 1
Manual Hacking to Pile COL by Bauer (12ea) 2021-06-21 2021-07-01 10 9
0 0
LP4 - T3
Excavation to expose pile for 1st Hacking (33ea) 2021-05-07 2021-05-10 3 2021-05-07 2021-05-10 3 100%
FMCO
Piles 1st Hacking by Bauer (33ea) 2021-05-22 2021-05-27 5 2021-05-22 2021-05-27 5 100%
Excavation to Expose Pile to COL (33ea) 2021-06-10 2021-06-18 8 2021-06-10 2021-06-23 12 100%
Handover to Bauer 2nd Hacking to Pile COL (33ea) 2021-06-19 2021-06-19 1 2021-06-24 2021-06-24 1 100%
Manual Hacking to Pile COL by Bauer (33ea) 2021-07-02 2021-07-23 19 2021-06-25 2021-07-19 19 30%
LP4 - T4 0 0
T4 Part 1 0 0
Excavation to expose pile for 1st Hacking (29ea) 2021-06-19 2021-06-24 5 2021-07-07 2021-07-12 5
Piles 1st Hacking by Bauer (29ea) 2021-06-25 2021-06-30 5 0
Excavation to Expose Pile to COL (29ea)' 2021-06-25 2021-06-30 5 2021-07-13 2021-07-17 0
Handover to Bauer 2nd Hacking to Pile COL (29ea) 2021-06-30 2021-06-30 1 0
Manual Hacking to Pile COL by Bauer (29ea) 2021-08-06 2021-08-18 11 0
T4 Pit 0 0
Excavation to expose pile for 1st Hacking (10ea) 2021-07-01 2021-07-03 3 0
Piles 1st Hacking by Bauer (10ea) 2021-07-04 2021-07-09 5 0
Excavation to Expose Pile to COL (10ea) 2021-07-10 2021-07-15 5 0
Handover to Bauer 2nd Hacking to Pile COL (10ea) 2021-07-15 2021-07-15 1 0
Manual Hacking to Pile COL by Bauer (10ea) 2021-08-19 2021-08-26 7 0
15
Construction Team
■ LP4 T1 handover status with Bauer
T1 - 1
T1-1 20-May 22-May 10-Jun 19-Jun 16-Jun 22-Jun
T1 - 2
T1 - 3
Zone Total pile no Exposed 1st hacking Complete 1st hacking Final HO until COL Complete pile hacking Final HO from Bauer
T1 33 33 33 33 32 32
T2 PIT 8 8 8 0 0 0
T3 33 33 33 33 17 0
T2 27 27 27 27 11 0
T4 31 13 5 4 0 0
T4 PIT 8 5 0 0 0 0
<T1 Zone>
16
Construction Team
■ LP4 T2 handover status with Bauer
T2 PIT 17
Construction Team
■ LP4 T3 handover status with Bauer
T3 - 2
Excavation : Done
T3 - 1
SCT : Done
T3 Zone
18
Construction Team For Internal Purpose only
19
Construction Team For Internal Purpose only
By OCT By Nov
T2 - Pit 17th July -5
T2 5th Aug
T3 25th July -2
T4 26th Aug
P6 4th Sep
P4 P5 13th Sep
P4 22th Sep
P3 1st Oct
※ P zone hacking start after completion T zone
P2 10th Oct
※ Still didn’t receive any updated schedule by Bauer
P1 19th Oct
P9 28th Oct
P7 6nd Nov
P8 15th Nov
20
Construction Team For Internal Purpose only
T2 13th Aug
T3 2th Aug
T4 3th Sep
P6 8th Sep
P4 P5 17th Sep
P4 26nd Sep
P3 5th Oct
P7 7th Nov
P8 20th Nov
21
Construction Team For Internal Purpose only
T2 20th Aug
T3 10th Aug
T4 10th Sep
P6 15th Sep
P4 P5 22th Sep
P4 30th Sep
P3 12th Oct
※ Grouting work schedule
P2 21th Oct
P1 30th Oct
P9 8th Nov
P7 14th Nov
P8 27th Nov
22
Construction Team For Internal Purpose only
■ 4 month ahead schedule for water proofing Target to complete water proofing - Delay
+ Ahead
T2 18th Aug
T3 21th Aug
T4 26th Sep
P 10 22st Nov
P6 16th Sep
P4
P5 6th Oct
P4 10th Oct
P2 22th Oct
P1 11st Nov
P9 6st Nov
P7 15th Nov
P8 24th Nov
23
Construction Team For Internal Purpose only
Total Manpower 0 0 140 140 140 140 140 140 140 140 140 140 140 140 140 220 220 190 190 190 190 190 190 190 190 190 190 190 190 190 190 190 190 330 330 330 330 250 250 250 250 250 250
26
Construction Team
LC Column schedule As of 5th July
■ LC column schedule ※ Work done : 50/52 (96%)
- 1st cast done (H 3.9m) : 52/52 (100%)
- 2nd cast done (full height) : 50/52 (96%) Panel Start Finish Remain
* Form work plan Done This week Nest week
(H 6m) B6 7
B5 6
B4 14
B3 8
28
Construction Team
■ D wall rectification status by Bauer LC to L00
NOTE :
Level C to Level 00 :
D-wall rectification work ( Hacking and
Grouting ) done by Bauer
LC to L00
29
Construction Team
■ D wall rectification status by Bauer LP2 to LC
30