PUNCH POINT OF U#3 DRY ASH SYTEM

1. All pass vacuum isolation valve feedback not showing in PLC


2. All pass dry isolation valve feedback not showing in PLC
3. Pass C&E LDG valve feedback not showing
4. Cross over valve BC line feedback not showing in PLC
5. Tower A inlet valve feedback not showing PLC
6. Buffer hopper all pass high level not working
7. All pass DP transmitter not working
8. Conveying line bend used not properly (such as 1 nos. MS bend used 22.5 degree & 2 nos. bend
used 45* in place of 1 nos. bend)
9. Clamping not available some places in conveying line
10. Conveying line is not properly straight some places
11. Conveying discharge line first bend rise there is required support and clamp
12. Silo blower foundation grouting not done properly
13. Silo blower discharge pressure blow down as per required parameter
14. Silo blower heater temperature blow down as per required temperature
15. Silo blower discharge operating valve missing (4 nos.)
16. Rotary feeder chain cover required in some place
17. Silo-1 level transmitter not showing accurate reading in PLC
18. Silo bag chamber ladder required
19. Operating for knife gate valve chain required
20. Silo discharge conveying vertical line platform required
21. Telescopic chute rotary feeder & KGV platform required to maintenance work.
22. Silo fluidizing blower-1 current not showing in PLC
23. Silo top discharge vlv platform required to maintenance work
24. Conveying line bend support & bend required in front of vacuum pump house
25. All dry tower inlet vlv platform,vent & equalizing vlv platform
26. Discharge line of dry system near main road platform not available to maintenance work
required platform
27. Conveying discharge line bend some places required platform & support.
28. Telescope chute required platform to maintenance work.
29. Vent fan grouting not properly and pulley cover not available