Product Launch Checklist

Instructions

1. Data from the "Product Launch Checklist" tab automatically creates a Gantt Chart on the "Gantt Chart" tab.

2. Simply edit the Stage, Department, Task, Description, Owner, Start, Duration, End, and Status fields.

3. We have created drop-down lists to show you how to make this tool very user friendly. If you need help editing drop down lists or color coding, please
visit: http://blog.demandmetric.com/category/excel-help/

4. Once you enter the Start date of a task and the Duration (# days), the End date will automatically be calculated.

5. You can use the filters at the top of each column on the "Product Launch Checklist" tab to drill down on specific items and create a custom report, such as
what are all of our "Overdue" tasks.

6. If you have any difficulties, you can always contact product support at info@demandmetric.com
Product Launch Checklist

Stage Department Task Description Owner Start Duration End Status


(Days)

After Having Demo team have to


Demo Development Team Demo submit the missing funtion, flow, SANTHOSH KUMAR 3-Jan-20 0 3-Jan-20 Not Started
form, bug etc.

Review the Product requirements that Not Started


Draft Product Team Requirements Kalai /Gowtham 3-Jan-20 1 4-Jan-20
resulted in this product's feature set

Make sure that the required form are


Form Development TeamFeature Specs accepting related and correct value, Kalai /Gowtham 5-Jan-20 10 15-Jan-20 Not Started
work flow and form flow

Ensure UI Color and Profesional Not Started


UI Design Product Team Support Ashutosh / Saravanakumar 5-Jan-20 10 15-Jan-20
Screen Layouts

Review the competitive analysis to


understand the differentiation that
2D Features Product Team Feature Specs exists in the new product. Make sure Kalai /Gowtham 5-Jan-20 15 20-Jan-20 Not Started
that the product launch marketing
messages reflect this differentation.

NC Product Team NC Test and Verify NC Generation . Kalai /Gowtham 5-Jan-20 20 25-Jan-20 Not Started

Tool Path Test and Verify Tool Path Verification . Not Started
Stuimulation Product Team Kalai /Gowtham 5-Jan-20 5 10-Jan-20
Verification

Test 3D Not Started


3D Features Product Team Test and Verify 3D Features Kalai /Gowtham 5-Jan-20 15 20-Jan-20
Features

Test All Product Test and Verify All test Case - to Not Started
Test Product Team Kalai /Gowtham 5-Jan-20 26 31-Jan-20
Case Release Beat 1

Manual Product Team Document Manual Readiness NAVEEN KRISHNA 5-Jan-20 15 20-Jan-20 Not Started

Setup Development Team Test Setup Test Setup SANTHOSH KUMAR 5-Jan-20 26 31-Jan-20 Not Started

Verify All Post Processor are Working Not Started


Post Processer Product Team Verify Kalai /Gowtham 5-Jan-20 21 26-Jan-20
Perfect

32 Bit Development Team Setup Setup for 32bit SANTHOSH KUMAR 15-Jan-20 15 30-Jan-20 Not Started
64 Bit Development Team Setup Setup for 64 Bit SANTHOSH KUMAR 16-Jan-20 15 31-Jan-20 Not Started

End User Not Started


EULA Product Team End User Agreement for All Software Saravanakumar 5-Jan-20 20 25-Jan-20
Agreement

Demo and Not Started


Videos Product Team Demo and Tranning Video NAVEEN KRISHNA 18-Jan-20 21 8-Feb-20
Tranning Video

2.5 Migration Development Team Migration Migration SANTHOSH KUMAR 5-Jan-20 21 26-Jan-20 Not Started

Language Option Development TeamLanguage Opti Other Language Options SANTHOSH KUMAR 31-Jan-20 28 28-Feb-20 Not Started
SANJAY SONAR
JOHNSON
NITISH SHUKLA
NAGARAJAN.R
AMIT KUMAR
VENKATESH
GOWTHAMAN
VIVEK M
SHENTHIL KUMAR
BOOMIRAJAN
AMUDHA
PRAVEEN KUMAR
GOWSICK
JERIN JOHN
KALAI SELVAN
KIRUTHIKA
SANTHOSH KUMAR
ASHUTOSH PANDEY
MAHESHWARAN
NAVEEN KRISHNA
SABARI SRIRAM
KATHIRAVAN
SHUBAM BHARAT MISAL
NATARAJAN S
Natarajan
Saravanakumar
Manickam
Ashutosh / Saravanakumar
Kalai /Gowtham

You might also like