PROJECT : I-TOWER 3

SUBJECT : CONCRETE PHASING PLAN


LOCATION : 1129 DOS CASTILLAS ST., SAMPALOC, MANILA
OWNER : COMMUNITY SUITES REALTY DEVELOPMENT CORP.
AS OF AUGUST 17, 2019

CONCRETE PHASING PLAN


FLOOR LEVEL
Floor Area (sq.m) Vol. (cu.m) Internal Schedule Official Schedule Status
Water Tank
73.80 March 27, 2020
Level 69 February 9, 2020
Upper Roof
364.82 March 19, 2020
Deck 191 February 2, 2020
Lower Roof
365.77 March 11, 2020
Deck 152 January 26, 2020

23F 357.88 March 2, 2020


151 January 19, 2020

22F 349.16 February 22, 2020


151 January 12, 2020

21F 349.16 February 13, 2020


151 January 4, 2020

20F 349.16 February 4, 2020


151 December 26, 2019

19F 349.16 January 26, 2020


151 December 17, 2019

18F 349.16 January 17, 2020


151 December 10, 2019

17F 349.16 January 8, 2020


151 December 3, 2019

16F 349.16 December 30, 2019


151 November 26, 2019

15F 349.16 December 21, 2019


151 November 19, 2019

14F 349.16 December 12, 2019


151 November 12, 2019

13F 349.16 December 3, 2019


151 November 5, 2019

12F 349.16 November 24, 2019


151 October 27, 2019

11F 349.16 November 15, 2019


151 October 20, 2019
GF SLABS @
November 11, 2019
PCP 1 83 October 15, 2019

10F 349.16 November 6, 2019


151 October 13, 2019
2nd LIFT OF
November 3, 2019
TANKS 141 October 8, 2019

9F 349.16 October 28, 2019


151 October 6, 2019

8F 349.16 October 19, 2019


151 September 29, 2019
GF SLABS @
October 10, 2019
PCP 2 141 September 22, 2019

7F 349.16 October 10, 2019


151 September 22, 2019

6F 349.16 October 1, 2019


151 September 15, 2019
1st LIFT OF
September 22, 2019
TANKS 117 September 8, 2019

5F 349.16 September 22, 2019


151 September 8, 2019

4F 349.16 September 13, 2019


151 September 1, 2019

3F 342.58 September 3, 2019


152 August 25, 2019

2F 342.86 August 24, 2019 on going works


141 August 18, 2019
Mezzanine 67 August 17, 2019
103.06 August 14, 2019 DONE
Level 68 August 11, 2019
Ground Floor 63 August 17, 2019
403.95 August 4, 2019 DONE
Beams 67 August 4, 2019
Columns & SW 37 August 8, 2019
July 30, 2019 DONE
@ PCP2 33 August 4, 2019
Columns & SW 57 August 17, 2019
July 21, 2019 DONE
@ PCP1 44 August 4, 2019
448 July 21, 2019
Pile Cap 2 July 21, 2019 DONE
447 July 21, 2019
631 April 28, 2019
Pile Cap 1 April 28, 2019 DONE
594 April 28, 2019
July 15, 2019
Pile Hacking 45 Bored Piles DONE

July 13, 2019


Excavation 3942 cu.m DONE

Legend: INTERNAL SCHEDULE


Delayed Actual Completion Date
Concreted/Done Planned Completion Date
Target for this week
Volume (cu.m)
Tanks & GF Slab Actual Volume
Estimated Volume

Prepared by: Checked by: Noted by: Approved by:

Engr. Junella Kim Bayudan Ar. Armando Doria Engr. Elizardo Tolentino Engr. Maximillian G. Quintos
Office Engineer Project Manager Area Manager SVP - Operations
PROJECT : I-TOWER 3
SUBJECT : CONCRETE PHASING PLAN
LOCATION : 1129 DOS CASTILLAS ST., SAMPALOC, MANILA
OWNER : COMMUNITY SUITES REALTY DEVELOPMENT CORP.
AS OF SEPTEMBER 2, 2019

CONCRETE PHASING PLAN


FLOOR LEVEL
Floor Area (sq.m) Vol. (cu.m) Internal Schedule Official Schedule Status
Water Tank
73.80 March 27, 2020
Level 69 March 7, 2020
Upper Roof
364.82 March 26, 2020
Deck 191 February 29, 2020
Lower Roof
365.77 March 17, 2020
Deck 152 February 22, 2020

23F 357.88 March 8, 2020


151 February 15, 2020

22F 349.16 February 28, 2020


151 February 8, 2020

21F 349.16 February 19, 2020


151 February 1, 2020

20F 349.16 February 10, 2020


151 January 25, 2019

19F 349.16 February 1, 2020


151 January 18, 2019

18F 349.16 January 23, 2020


151 January 11, 2019

17F 349.16 January 15, 2020


151 January 4, 2019

16F 349.16 January 7, 2020


151 December 26, 2019

15F 349.16 December 30, 2019


151 December 17, 2019

14F 349.16 December 22, 2019


151 December 10, 2019

13F 349.16 December 14, 2019


151 December 3, 2019

12F 349.16 December 6, 2019


151 November 25, 2019

11F 349.16 November 28, 2019


151 November 18, 2019
GF SLABS @
November 24, 2019
PCP 1 83 November 13, 2019

10F 349.16 November 20, 2019


151 November 11, 2019
2nd LIFT OF
November 16, 2019
TANKS 141 November 6, 2019

9F 349.16 November 11, 2019


151 November 4, 2019

8F 349.16 November 3, 2019


151 October 26, 2019
GF SLABS @
October 26, 2019
PCP 2 141 October 19, 2019

7F 349.16 October 26, 2019


151 October 19, 2019

6F 349.16 October 18, 2019


151 October 12, 2019
1st LIFT OF
October 10, 2019
TANKS 117 October 5, 2019

5F 349.16 October 10, 2019


151 October 5, 2019

4F 349.16 October 2, 2019


151 September 28, 2019

3F 342.58 September 24, 2019


152 September 21, 2019
on going works rebar &
2F 342.86 September 16, 2019
141 September 14, 2019 formworks
Mezzanine waiting for Pump Room
103.06 September 7, 2019
Level 68 September 7, 2019 Area design (structural)
Ground Floor 63 August 17, 2019
403.95 August 4, 2019 DONE
Beams 67 August 4, 2019
Columns & SW 37 August 8, 2019
July 30, 2019 DONE
@ PCP2 33 August 4, 2019
Columns & SW 57 August 17, 2019
July 21, 2019 DONE
@ PCP1 44 August 4, 2019
448 July 21, 2019
Pile Cap 2 July 21, 2019 DONE
447 July 21, 2019
631 April 28, 2019
Pile Cap 1 April 28, 2019 DONE
594 April 28, 2019
July 15, 2019
Pile Hacking 45 Bored Piles DONE

July 13, 2019


Excavation 3942 cu.m DONE

Legend: INTERNAL SCHEDULE


Delayed Actual Completion Date
Concreted/Done Planned Completion Date
Target for this week
Volume (cu.m)
Tanks & GF Slab Actual Volume
Estimated Volume

Prepared by: Checked by: Noted by: Approved by:

Engr. Junella Kim Bayudan Ar. Armando Doria Engr. Elizardo Tolentino Engr. Maximillian G. Quintos
Office Engineer Project Manager Area Manager SVP - Operations
PROJECT : I-TOWER 3
SUBJECT : CONCRETE PHASING PLAN
LOCATION : 1129 DOS CASTILLAS ST., SAMPALOC, MANILA
OWNER : COMMUNITY SUITES REALTY DEVELOPMENT CORP.
AS OF November 5, 2019

CONCRETE PHASING PLAN


FLOOR LEVEL
Floor Area (sq.m) Vol. (cu.m) Internal Schedule Official Schedule Status
Water Tank
73.80 March 27, 2020
Level 69 March 27, 2020
Upper Roof
364.82 March 26, 2020
Deck 191 March 26, 2020
Lower Roof
365.77 March 20, 2020
Deck 152 March 20, 2020

23F 357.88 March 14, 2020


151 March 14, 2020

22F 349.16 March 08, 2020


151 March 08, 2020

21F 349.16 March 02, 2020


151 March 02, 2020

20F 349.16 February 25, 2020


151 February 25, 2020

19F 349.16 February 19, 2020


151 February 19, 2020

18F 349.16 February 13, 2020


151 February 13, 2020

17F 349.16 February 07, 2020


151 February 07, 2020

16F 349.16 February 01, 2020


151 February 01, 2020

15F 349.16 January 26, 2020


151 January 26, 2020

14F 349.16 January 20, 2020


151 January 20, 2020

13F 349.16 January 14, 2020


151 January 14, 2020

12F 349.16 January 08, 2020


151 January 08, 2020

11F 349.16 January 02, 2020


151 January 02, 2020
GF SLABS @
December 29, 2019
PCP 2 83 December 29, 2019

10F 349.16 December 23, 2019


151 December 23, 2019
2nd LIFT OF
December 21, 2019
TANKS 141 December 21, 2019

9F 349.16 December 17, 2019


151 December 17, 2019

8F 349.16 December 11, 2019


151 December 11, 2019
GF SLABS @
December 05, 2019
PCP 1 141 December 05, 2019

7F 349.16 December 05, 2019


151 December 05, 2019

6F 349.16 November 29, 2019


151 November 29, 2019
1st LIFT OF
November 23, 2019
TANKS 117 November 23, 2019

5F 349.16 November 23, 2019


151 November 23, 2019

4F 349.16 November 17, 2019


151 November 17, 2019
on-going rebar & formworks
3F 342.58 November 11, 2019
152 November 11, 2019 installation
143 90% Concreted, Transformer Room
2F 342.86 October 12, 2019
141 October 12, 2019 pending
Mezzanine 57.18
110.4 September 19, 2019 84% Concreted, Pump Room pending
Level 68 September 19, 2019
Ground Floor 63 August 17, 2019
403.95 August 4, 2019 DONE
Beams 67 August 4, 2019
Columns & SW 37 August 8, 2019
July 30, 2019 DONE
@ PCP2 33 August 4, 2019
Columns & SW 57 August 17, 2019
July 21, 2019 DONE
@ PCP1 44 August 4, 2019
448 July 21, 2019
Pile Cap 2 July 21, 2019 DONE
447 July 21, 2019
631 April 28, 2019
Pile Cap 1 April 28, 2019 DONE
594 April 28, 2019
July 15, 2019
Pile Hacking 45 Bored Piles DONE

July 13, 2019


Excavation 3942 cu.m DONE

Legend: INTERNAL SCHEDULE


Delayed Actual Completion Date
Concreted/Done Planned Completion Date
Target for this week
Volume (cu.m)
Tanks & GF Slab Actual Volume
Estimated Volume

Prepared by: Checked by: Noted by: Approved by:

Engr. Junella Kim Bayudan Ar. Armando Doria Engr. Elizardo Tolentino Engr. Maximillian G. Quintos
Office Engineer Project Manager Area Manager SVP - Operations
PROJECT : I-TOWER 3
SUBJECT : CONCRETE PHASING PLAN
LOCATION : 1129 DOS CASTILLAS ST., SAMPALOC, MANILA
OWNER : COMMUNITY SUITES REALTY DEVELOPMENT CORP.
DATE : SEPTEMBER 19, 2019

INTERNAL EXTERNAL
FLOOR LEVEL PAGARAGAN PAGARAGAN
(7 days) (7-8 days)

WATER TANK LEVEL 27-Mar-20 27-Mar-20


UPPER ROOF DECK LEVEL (SWIMMING POOL) 26-Mar-20 26-Mar-20
LRD - URD FIRST LIFT OF COLUMN 24-Mar-20 24-Mar-20
LOWER ROOF DECK LEVEL 20-Mar-20 20-Mar-20
23F - LRD FIRST LIFT OF COLUMN 18-Mar-20 18-Mar-20
23RD FLOOR LEVEL 14-Mar-20 14-Mar-20
22F - 23F FIRST LIFT OF COLUMN 12-Mar-20 12-Mar-20
22ND FLOOR LEVEL 08-Mar-20 08-Mar-20
21F - 22F FIRST LIFT OF COLUMN 06-Mar-20 06-Mar-20
21ST FLOOR LEVEL 02-Mar-20 02-Mar-20
20F - 21F FIRST LIFT OF COLUMN 29-Feb-20 29-Feb-20
20TH FLOOR LEVEL 25-Feb-20 25-Feb-20
19F - 20F FIRST LIFT OF COLUMN 23-Feb-20 23-Feb-20
19TH FLOOR LEVEL 19-Feb-20 19-Feb-20
18F - 19F FIRST LIFT OF COLUMN 17-Feb-20 17-Feb-20
18TH FLOOR LEVEL 13-Feb-20 13-Feb-20
17F - 18F FIRST LIFT OF COLUMN 11-Feb-20 11-Feb-20
17TH FLOOR LEVEL 07-Feb-20 07-Feb-20
16F - 17F FIRST LIFT OF COLUMN 05-Feb-20 05-Feb-20
16TH FLOOR LEVEL 01-Feb-20 01-Feb-20
15F - 16F FIRST LIFT OF COLUMN 30-Jan-20 30-Jan-20
15TH FLOOR LEVEL 26-Jan-20 26-Jan-20
14F - 15F FIRST LIFT OF COLUMN 24-Jan-20 24-Jan-20
14TH FLOOR LEVEL 20-Jan-20 20-Jan-20
13F - 14F FIRST LIFT OF COLUMN 18-Jan-20 18-Jan-20
13TH FLOOR LEVEL 14-Jan-20 14-Jan-20
12F - 13F FIRST LIFT OF COLUMN 12-Jan-20 12-Jan-20
12TH FLOOR LEVEL 08-Jan-20 08-Jan-20
11F - 12F FIRST LIFT OF COLUMN 06-Jan-20 06-Jan-20
11TH FLOOR LEVEL 02-Jan-20 02-Jan-20
GROUND FLOOR SLAB @ PCP 2 29-Dec-19 29-Dec-19
10F - 11F FIRST LIFT OF COLUMN 29-Dec-19 29-Dec-19
10TH FLOOR LEVEL 23-Dec-19 23-Dec-19
SECOND LIFT OF TANKS 21-Dec-19 21-Dec-19
9F - 10F FIRST LIFT OF COLUMN 21-Dec-19 21-Dec-19
9TH FLOOR LEVEL 17-Dec-19 17-Dec-19
8F - 9F FIRST LIFT OF COLUMN 15-Dec-19 15-Dec-19
8TH FLOOR LEVEL 11-Dec-19 11-Dec-19
7F - 8F FIRST LIFT OF COLUMN 09-Dec-19 09-Dec-19
GROUND FLOOR SLAB @ PCP 1 05-Dec-19 05-Dec-19
7TH FLOOR LEVEL 05-Dec-19 05-Dec-19
6F - 7F FIRST LIFT OF COLUMN 03-Dec-19 03-Dec-19
6TH FLOOR LEVEL 29-Nov-19 29-Nov-19
5F - 6F FIRST LIFT OF COLUMN 27-Nov-19 27-Nov-19
FIRST LIFT OF TANKS 23-Nov-19 23-Nov-19
5TH FLOOR LEVEL 23-Nov-19 23-Nov-19
4F - 5F FIRST LIFT OF COLUMN 21-Nov-19 21-Nov-19
4TH FLOOR LEVEL 17-Nov-19 17-Nov-19
3F - 4F FIRST LIFT OF COLUMN 15-Nov-19 15-Nov-19
3RD FLOOR LEVEL 11-Nov-19 11-Nov-19
2F - 3F FIRST LIFT OF COLUMN 26-Oct-19 26-Oct-19
2ND FLOOR LEVEL 12-Oct-19 12-Oct-19
MEZZ - 2F FIRST LIFT OF COLUMN SEGMENT 1 21-Sep-19 23-Sep-19
MEZZANINE LEVEL FLOOR LEVEL 19-Sep-19 19-Sep-19
GF - MEZZ FIRST LIFT OF COLUMN SEGMENT 1 19-Sep-19 19-Sep-19
MEZZ - 2F FIRST LIFT OF COLUMN SEGMENT 2 12-Sep-19 12-Sep-19
GF - MEZZ FIRST LIFT OF COLUMN SEGMENT 2 21-Aug-19 21-Aug-19
GROUND FLOOR BEAM 08-Aug-19 08-Aug-19
SECOND LIFT OF COLUMN AND SW2 @ PCP 2 08-Aug-19 08-Aug-19
SECOND LIFT OF COLUMN AND SW1 @ PCP 1 01-Aug-19 01-Aug-19
FIRST LIFT OF COLUMN AND SW2 @ PCP 2 30-Jul-19 01-Aug-19
FIRST LIFT OF COLUMN AND SW1 @ PCP 1 21-Jul-19 21-Jul-19
FOUNDATION PCP 2 21-Jul-19 21-Jul-19
FOUNDATION PCP 1 28-Apr-19 28-Apr-19

CONCRETE POURING ON TANKS


CONCRETE POURING ON GROUND FLOOR SLAB