Professional Documents
Culture Documents
Reference DAPPER PDF
Reference DAPPER PDF
for Windows
™
Power*Tools, CAPTOR and DAPPER are registered trademarks and HI_WAVE and I*SIM are trademarks of
SKM Systems Analysis, Inc.
PIXymbols™ Extended Character Set. Copyright ©1995. Page Studio Graphics. All rights reserved.
For information, address Page Studio Graphics, 3175 North Price Road, Suite 150, Chandler, AZ 85224.
Phone/Fax: (602) 839-2763.
ImageStream Graphics & Presentation Filters. Copyright ©1991-1995. ImageMark Software Labs, Inc. All
rights reserved.
Various definitions reprinted from IEEE Std 100-1992, IEEE Standard Dictionary of Electrical and Electronics
Terms, copyright © 1992 by the Institute of Electrical and Electronics Engineers, Inc. The IEEE takes no
responsibility or will assume no liability for the reader's misinterpretation of said information resulting from its
placement and context in this publication. Information is reproduced with the permission of the IEEE.
MathType™ math equation editing fonts are licensed from Design Science, Inc.
©1987-1996 by Design Science, Inc. All rights reserved.
3/26/2006
Contents
1 DEMAND LOAD STUDY 1-1
1.1. What is the Demand Load Study? .......................................................................1-2
1.2. Engineering Methodology.....................................................................................1-3
1.2.1. Definitions of Terms and Concepts..................................................................1-3
1.2.2. Load Characteristics .........................................................................................1-6
1.2.3. Demand Load Library ......................................................................................1-6
1.3. PTW Applied Methodology..................................................................................1-6
1.3.1. Before Running the Demand Load Study ........................................................1-6
1.3.2. Motor and Non-Motor Loads ...........................................................................1-6
Non-Motor Loads...................................................................................................1-7
Demand Load Types ..........................................................................................1-7
Energy Audit Types ...........................................................................................1-7
Motor Loads ...........................................................................................................1-8
Loads Defined in a Schedule..................................................................................1-9
1.3.3. Running the Demand Load Study ....................................................................1-9
1.3.4. Demand Load Study Options .........................................................................1-10
Project Configuration ...........................................................................................1-11
1.3.5. Error Messages...............................................................................................1-11
1.4. Application Examples .........................................................................................1-12
1.4.1. Non-Coincident Demand Calculation ............................................................1-12
1.4.2. Motor Design Load Calculation .....................................................................1-13
1.4.3. Multiple Motors at a Bus................................................................................1-13
1.4.4. Motors Assigned to a Motor Control Center..................................................1-14
1.4.5. Single Phase Non-Motor Loads in a Panel Schedule .....................................1-15
1.4.6. Loads with Different Power Factors ..............................................................1-17
1.4.7. Multiple Motors on a Single Motor Component ............................................1-18
1.4.8. Motor Starting ................................................................................................1-18
1.4.9. Multiple Loops in a System............................................................................1-19
1.4.10. Example from Plant......................................................................................1-20
3/26/2006
Contents DAPPER iii
3/26/2006
1 Demand Load Study
The Demand Load Study calculates the total apparent power and current at each bus and
within each branch in the electrical power system, excluding local generation and power
lost through impedance devices. The purpose of this Study is to calculate the
connected, demand and design load values for each bus, including the effects of load
diversity. The calculated load currents are based on the load bus nominal system
voltage. The results are used as a basis for further studies in PTW.
• Engineering Methodology.
• Examples.
IN THIS CHAPTER
The Demand Load Study requires a radial system with a single power source. If the
power system contains loops, the Study detects the loops, temporarily opens them,
continues calculating, and restores the original system configuration upon completing
the Study. The Demand Load Study can analyze up to ten independent power systems
in a single project.
Beginning at the bus farthest from the source, the Demand Load Study calculates the
vector sum of all load values on the bus, and reports the connected, demand, and design
load values. This process is repeated for each upstream branch in the electrical system.
Demand and design load calculations are based on the principles of the National
Electrical Code (NEC). A basic premise of the NEC is that multiple branch loads
serviced from a single feeder may not necessarily peak concurrently. This concept is
called load diversity. The Demand Load Study considers diversity when calculating
feeder load values (NEC).[1]
[1]
Authored by Committee, 1996 National Electrical Code. Quincy, MA: National
Fire Protection Association, 1996.
3/26/2006
Demand Load Study DAPPER 1-3
Study Setup
Demand Load Library
Run Demand Load Study
Demand Loads
Energy Audit Loads
Study Setup
Saved in Database
For each branch:
Used by Sizing Study Demand and design load and power factor
Total constant I demand load and power factor Used by Load Flow
Total constant Z demand load and power factor Study
Total constant kVA demand load and power factor
Datablocks
Reports
Demand Load Value The largest or peak load value of a single load.
Usually less than the connected load.
Demand Factor The ratio of the demand load value to the connected
load. Usually less than one.
Design Load Value The demand load value multiplied by the long
continuous load factor (LCL).
Long Continuous Load Factor The reciprocal of the cable ampacity derating factor
for a continuous load (design factor).
Coincident Demand The sum of the individual branch demand loads and
loads attached directly to the bus.
Net Branch Diversity The difference between the coincident demand load
and the non-coincident demand load reported at the
bus.
To illustrate these terms, consider a system with three 25 hp motors connected to a bus.
The peak mechanical loads on the three motors are 12, 15 and 25 hp. The total
connected load is 75 hp. The coincident demand load is the sum of the three peak
mechanical loads, which is 52 hp:
Demand Load = 12 hp + 15 hp + 25 hp
= 52 hp
The demand factor is the ratio of the demand load value to the connected load:
52 hp demand load
Demand Factor =
75 hp connected load
= 0.69 or 69%
The NEC defines continuous loads as loads that operate for longer than three hours at a
time. To size branch and feeder circuits with continuous loads, an NEC ampacity rating
(long continuous load or design factor) must be used.
For example, imagine a 30 kVA lighting load that is always on. The connected load is
30 kVA, and the demand factor is 100%. Therefore, the demand load for the lighting is
30 kVA. If the long continuous loading factor is 125%, then the design load value is
37.5 kVA, as shown:
Design Load = 30 kVA demand load × 1.25 long continuous loading factor
= 37.5 kVA
National codes may make reference to multi-level demand factors. For example,
Chapter 2 of the NEC states that a receptacle load demand value is calculated based on
the following rules:
3/26/2006
Demand Load Study DAPPER 1-5
b g b
Demand Load = 10 kVA × 100% + 5 kVA × 50% g
= 12.5 kVA
Next imagine two 15 kVA receptacle branch circuits fed from a single feeder circuit.
The demand load value in each branch circuit is 12.5 kVA. The connected load on the
feeder circuit is as follows:
b g b
Demand Load = 10 kVA × 100% + 20 kVA × 50% g
= 20 kVA
The net diversity or demand load at the feeder circuit is 20 kVA. It is not the sum of the
two coincident branch circuit load values of 25 kVA. The diversity factor now can be
calculated as:
Diversity Factor =
∑ coincident demand load
non coincident demand
12.5 kVA + 12.5 kVA
=
20 kVA
= 1.25 or 125%
The non-coincident demand load (20 kVA) is less than the sum of the individual
coincident or peak demand loads (25 kVA) at the feeder bus.
The Demand Load Study uses NEC methodology to identify each load in an electrical
power system and its specific load factors. The Demand Load Study then vectorially
sums the connected, demand and design load values for each upstream bus and branch.
Each load may be assigned a unique power factor. To account for load diversity, the
Demand Load Study re-calculates the demand and design values from the total
connected load at each bus. If there are motors at the bus, the largest motor is identified
and special multiplying factors are used to calculate the motor circuit design load value.
For an example of multiple motors on a single motor component, see Section 1.4.7 in
this Reference Manual.
The methodology depends upon the assumption that only one source services each load.
When the Demand Load Study detects a loop in the power system, it determines the
number of impedance components in the loop and opens the branch element that is
topologically farthest from the source of supply. The Demand Load Study does not
determine the branch opening point based on total equivalent impedance. If there are
multiple loops, it detects them and opens them as well. With the loop(s) open, it
calculates the demand and design load values at each bus and within each branch
beginning at the farthest point from the source of supply. Multiple independent power
systems may result from either a specific electrical design or the methodology the
Demand Load Study uses to open loops in the system. The Demand Load Study Report
identifies all open branches at the beginning of the Study Report.
Non-motor loads subdivide into Energy Audit types or Demand Load types. The
demand and design load values of an Energy Audit type are the rated load size
(connected load) multiplied by the Load Factor. For Demand Load types, the Demand
Load Study calculates the demand and design load values using demand and design load
factors in the Demand Load Library.
If motor components are assigned to a motor control center (MCC) and the motors are
referenced in the Motor Control Center Library, then the demand and design load values
are based on NEC Table 430-150, as defined in the Motor Control Center Library.
3/26/2006
Demand Load Study DAPPER 1-7
Non-Motor Load
Demand Load type A non-motor load with a uniquely defined set of demand
factors as specified in the Demand Load Library.
Energy Audit Load type A non-motor load with a single unique load factor. Usually
can be directly measured in the field.
Non-Motor Loads
Non-motor loads are modeled as either a Demand Load or an Energy Audit type load.
The Demand Load Study calculates the connected, demand and design load values
based on data from the library. The connected load value is always equal to the rated
size of the load. The demand load value is generally equal to or less than the load rated
size. You can add demand factors greater than one for load growth studies, although
customarily the demand load factor is less than one in most practical design
applications. The design load is generally equal to or greater than the demand load, and
represents the design requirement that derates cables based on continuous loading.
In the Demand Load Library, the General Load category LCL factor (design factor) is
set at 1.0. On the other hand, article 220 of the NEC requires that conductors that are
energized for more than three hours must not carry more than 80% of the calculated
demand load. For these loads, the LCL factor should be set at 1.25. Lighting type
loads, for example, are continuous load types requiring a design factor equal to 1.25 in
accordance with the NEC. For lighting type loads, the design load value will be 125%
of the demand load.
You will receive a warning message if you do not define a demand load category in the
Component Editor. If you ignore the warning, PTW makes the Demand and Design
Load value equal to the Connected Load value, and posts a message telling you so after
running the Study.
The Demand Load characteristic (constant power, constant impedance, constant current)
is defined for each Demand Load category in the Demand Load Library.
New non-motor loads default as Energy Audit loads with a load factor of 1.0 and a
constant kVA load characteristic. This default setting sets the connected, demand and
design load values equal to the load rated size. The demand and design load values are
always identical for Energy Audit type loads.
Motor Loads
Motors are generally modeled as a constant kVA load characteristic when running, and
as a constant impedance load characteristic when starting. When a motor is either
running or starting, the Demand Load Study scales the individual motor rated size by
multiplying the quantity of motors by the motor load factor. When a motor is modeled
as starting, Demand Load Study multiplies the rated size by the number of motors, and
divides the product by the subtransient reactance ( X ′′d ). The default X ′′d is 0.17 pu, and
the default load factor is 1.0. The starting power factor is calculated based on the
motor’s fault duty X/R ratio, which has a default of 10. Thus, the default motor starting
condition is a locked rotor current of 5.9 multiplied by the motor’s full load amperes
(FLA), and a starting power factor of 10%.
The following one-line diagram models a single 100 hp motor at Bus 2. It shows the
motor parameters used to calculate demand and design load values.
UTILITY 1
BUS 1
Connected 91.42 kVA
Demand 91.42 kVA
Design 114.28 kVA C1
BUS 2
Connected 91.42 kVA
Demand 91.42 kVA MOTOR 1
Design 114.28 kVA Size 100.0 hp
PF 0.85 Lag
3/26/2006
Demand Load Study DAPPER 1-9
There are two instances when the motor demand load may be larger than the connected
load when modeled in PTW. First, if a motor service factor (SF) is used in the Demand
Load Study to determine the largest maximum system demand, then you may want to
enter the SF as a load factor. Because the demand load is the motor rated size
multiplied by the load factor, and because the SF might be 1.1, the demand load value
could be 110% of the motor’s connected load.
Second, if a motor is placed in a motor control center and the motor’s control library
data is used, then the NEC Full Load Amperes (FLA) values (Table 430-150) are used
to calculate both the demand and design load values. Because the NEC FLA values
tend to be conservative, the demand and design load values are usually larger than the
connected load. Note that regardless of the NEC FLA values, the motor’s connected
load value is always the motor’s rated size multiplied by the number of motors.
For motor loads, there is no difference between using the shortcut and manually creating
them. While the motor symbols will not initially appear on the One-Line Diagram if
you create them using the shortcut, you can use the Expand command and the symbols
will appear connected at the bus.
For non-motor loads, the shortcut assigns them to the schedule but does not create any
components for them; while the Studies will recognize that the non-motor loads exist,
they will not appear either on the One-Line Diagram or in the Component Editor (which
means that you cannot find them using a query). Typically, if have numerous small
loads which do not need to appear on your One-Line Diagram, the shortcut provides a
quick way to assign them to a schedule. However, if you have larger loads that you
want to show on the One-Line Diagram and retrieve using a query, you should create
them manually and then assign them to the schedule. Note that when you use the
shortcut, and you do not assign a load category, PTW assumes the load’s demand and
design load value equals its connected load value.
Note that motor loads, and non-motor loads created manually, are not automatically
placed out of service when the schedule is placed out of service. Non-motor loads
created using the shortcut, however, are placed out of service automatically when the
schedule is placed out of service.
4. Choose the OK button to return to the Study dialog box, and choose the Run
button.
The Demand Load Study runs, writes the results to the database, and creates a report.
To choose a non-motor load in the Demand Load Study dialog box, refer to the
following table:
Include Only Demand Loads Include non-motor loads entered as Demand Loads.
Include Only Energy Audit Loads Include non-motor loads entered as Energy Audit loads.
The Demand Load Study includes all motors that are in service. Motor Load Design
Factors are used to calculate the design load value of the largest motor and all remaining
motors in a branch and feeder circuit. Enter motor data using the following guidelines:
Remaining Motors A design load multiplying factor for all other motors on
the branch circuit. The Demand Load Study vectorially
3/26/2006
Demand Load Study DAPPER 1-11
The Demand Load Study identifies one motor in each branch as the largest motor. Both
induction and synchronous motors are considered. In a case where the Number of
Motors field in the Component Editor is greater than one, the Demand Load Study
calculates the demand load value as the rated size multiplied by the number of motors.
The design load value requires further steps. First, the Demand Load Study examines
all the motors’ rated sizes on the bus to determine the largest motor on the bus. The
largest motor’s rated size is then multiplied by the largest motor design factor from the
Demand Load Study Setup dialog box.
Project Configuration
You can use the Demand Load Study to examine any number of different project
configurations. For example, during the design process you may want to examine the
power system with selector switches selecting the normal or emergency system in
operation. To do this, simply run the Demand Load Study on the first system
configuration and save the report. Then change the system and run the Demand Load
Study a second time. Prior to running the second Study, change the report name under
Report Files in the Study dialog box to avoid overwriting the first report. Then compare
the two reports.
The purpose of the Demand Load Study is to provide a picture of the total loads in the
project. Therefore, the effects of local generation are not considered in the calculation.
Note: The Load Flow Study can use Demand Load Study information to examine the
load flow in the power system with tie breakers and loops closed. The Demand Load
Study provides feeder and transformer in and out of service switches to simplify opening
and closing the tie breakers and selector switches.
For further information on using the Study Messages dialog box to resolve errors, refer
to Correcting Study Errors in Chapter 9 of the User’s Guide.
• Source Bus Not Identified: No voltage source (swing bus) is defined in the system.
This error is fatal and stops the Study. To correct this problem, define a utility or
swing bus generator.
• Isolated Branch Detected: One or more branches is not connected to a voltage
source. For example, if a single branch is placed out of service, and if downstream
electrical components remain in service, then you effectively have an isolated
branch. This error is fatal. To correct the problem, check the system for
components erroneously out of service.
• Incomplete System Configuration: One or more component connections is missing.
This error is fatal.
• Zero Load Data: The motor load on one or more load buses is zero kVA. This
error is not fatal, and the Study continues.
• Load Demand Category Not Defined, PTW will detect non-motor loads modeled
as demand loads, and where the demand category is not defined. PTW assumes a
100% demand category.
b g b
Demand Load = 100 kVA × 100% + 900 kVA × 50% g
= 550 kVA
At Bus 2, the connected load is 2000 kVA.
The methodology requires that the demand load value be calculated as:
b g b
Demand Load = 100 kVA × 100% + 1900 kVA × 50% g
= 1050 kVA
The connected, demand and design loads are shown on the following one-line diagram:
3/26/2006
Demand Load Study DAPPER 1-13
UTILITY 1
BUS 1
Connected 2000.00 kVA
Demand 1050.00 kVA
Design 1050.00 kVA C1
BUS 2
Connected 2000.00 kVA
Demand 1050.00 kVA
Design 1050.00 kVA C3
C2
BUS 3 BUS 4
Connected 1000.00 kVA Connected 1000.00 kVA
Demand 550.00 kVA Demand 550.00 kVA
LOAD 1 Design 550.00 kVA LOAD 2
Design 550.00 kVA
Size 1000.0 kVA Size 1000.0 kVA
PF 0.85 Lag PF 0.85 Lag
In the diagram, note the coincident demand load is 550 kVA at Buses 3 and 4. The
coincident peak of these values is 1100 kVA. However, the non-coincident demand
load or diversity load at Bus 2 is only 1050 kVA. This is because of the methodology
inherent in the NEC’s multi-level demand factors. For a review of multi-level demand
factors, see the bulleted rules in Section 1.2.1 of this Reference Manual.
The design load value is calculated by multiplying the rated size of the largest motor by
125%, and adding the product to the sum of all other motor rated sizes multiplied by
100%. As shown in the following one-line diagram, Motor 2 is larger than Motor 1;
Motor 2’s rated size of 75 kVA is multiplied by 125%. Motor 1 is the remaining motor;
its rated size of 50 kVA is multiplied by 100%. Therefore, the sum of these two
products is the design load at Bus 2, which is 143.75 kVA as shown:
b
Bus 2 Design Load = 75 kVA × 125% + 50 kVA × 100% g b g
= 143.75 kVA
UTILITY 1
BUS 1
Connected 125.00 kVA
Demand 125.00 kVA
Design 143.75 kVA C1
BUS 2
Connected 125.00 kVA
Demand 125.00 kVA
Design 143.75 kVA C2 C3
BUS 3 BUS 4
Connected 50.00 kVA Connected 75.00 kVA
Demand 50.00 kVA Demand 75.00 kVA
MOTOR 1 MOTOR 2
Design 62.50 kVA Design 93.75 kVA
Size 50.0 kVA Size 75.0 kVA
PF 0.85 Lag PF 0.85 Lag
Since there are no loads directly connected to Buses 1 or 2, the connected, demand, and
design loads are the same at Buses 1 and 2. The Demand Load Study properly
calculates the individual design load values for the two branch circuits as shown on the
drawing.
The Demand Load Study determines that Motors 2 and 3 are both 75 kVA, and then
arbitrarily selects either one as the largest motor to determine the feeder circuit size.
The design load values at Buses 1 and 2 increase as a result of adding Motor 3; but, as
shown, it is immaterial which motor is selected as the largest motor:
b g b
Bus 2 Design Load = Lg Mtr kVA × 125% + sum of remaining mtrs kVA × 100% g
= b75 kVA × 125%g + b75 kVA + 50 kVA g × 100%
= 218.75 kVA
The design load value at Buses 1 and 2 is 218.75 kVA. The data on the following one-
line diagram agrees with the preceding calculations.
3/26/2006
Demand Load Study DAPPER 1-15
UTILITY 1
BUS 1
Connected 200.00 kVA
Demand 200.00 kVA
Design 218.75 kVA C1
BUS 2
Connected 200.00 kVA
Demand 200.00 kVA
Design 218.75 kVA C2 C3
BUS 3 BUS 4
Connected 125.00 kVA Connected 75.00 kVA
Demand 125.00 kVA MOTOR 1 Demand 75.00 kVA
MOTOR 3 Design 93.75 kVA MOTOR 2
Design 143.75 kVA
Size 75.0 kVA Size 50.0 kVA Size 75.0 kVA
PF 0.85 Lag PF 0.85 Lag PF 0.85 Lag
In the following one-line diagram, a motor control center is added to Bus 3. The two
motors at Bus 3 are connected to the schedule, creating a connected load which is the
sum of the two motors’ rated sizes.
UTILITY 1
BUS 1
Connected 125.00 kVA
Demand 133.85 kVA
Design 153.81 kVA
C1
BUS 2
Connected 125.00 kVA
Demand 133.85 kVA
Design 153.81 kVA
C2
MCC
BUS 3
Connected 125.00 kVA
Demand 133.85 kVA
Design 153.81 kVA MOTOR 3 MOTOR 1
The following portion of the Demand Load Study Report shows connected loads of 50
kVA and 75 kVA for the two motors. This is equivalent to 60.1 A and 90.2 A. The
demand load current value is from the Motor Control Center Library, based on Table
430-150 of the NEC. For the 75 hp 460 V motor, the NEC FLA value is 96 A. Because
the 75 hp motor is the largest motor on the bus, the design load value is 125% of the
demand load value (96 A), which is 120 A. The demand and design kVA values are
calculated from the NEC FLA.
LOAD SCHEDULE FOR BUS-0003 480. VOLTS LINE TO LINE
==============================================================================
ITEM DESCRIPTION * CONNECTED LOAD * DEMAND LOAD * DESIGN LOAD * %
KVA AMPS KVA AMPS KVA AMPS P F
==============================================================================
END USE LOADS
KVA TYPE MTR 50.0 60.1 54.0 65.0 54.0 65.0 85.00
LARGEST KVA MTR 75.0 90.2 79.8 96.0 99.8 120.0 85.00
==============================================================================
TOTALS 125.0 150.4 133.9 161.0 153.8 185.0 85.00
With seven single-phase 15 A circuits, the panel is not balanced. Phase A has 45 A of
lighting load, whereas Phases B and C each have 30 A of load. The Phase A power is
3/26/2006
Demand Load Study DAPPER 1-17
5.4 kVA, and Phases B and C each have 3.6 kVA. The sum of the power and current
for each phase is:
45 A + 30 A + 30 A
Average =
3
= 35.0 A
Because the loads all have the same power factor, the arithmetical average current is the
sum of the three-phase currents divided by 3.
Next, the two single-phase, two-pole water heater loads are added to the panel. Again,
the load is not evenly distributed across the three phases. One heater is connected
across Phases A and B, and the other is connected across Phases B and C. Combined
with the seven single-pole lighting loads, the phase currents are 75 A on Phase A, 90 A
on Phase B, and 60 A on Phase C. This phase current is reported at the bottom of the
Schedule dialog box.
Note: In the Load Schedule Report, PTW uses the bus rated voltage to calculate the
fault current, whereas in the Comprehensive Short Circuit Study PTW uses the pre-fault
voltage. You probably won't notice the difference because the bus rated voltage and the
pre-fault voltage are usually the same; the only time they'll be different is when you have
modeled transformer tap values and turn on the "Model Transformer Taps" option in the
Comprehensive Short Circuit Study.
The total heating load per heater is 6.24 kVA. Because there are two heaters modeled,
the total heating load is 12.48 kVA. This load is split across the three phases as shown
in the following chart:
Each heater draws 6.24 kVA split evenly across its two phases, or 3.1 kVA per phase.
Phase B draws current for both heaters. The following demand load report reports the
loads in kVA. Both loads are considered as continuous loads.
LOAD SCHEDULE FOR BUS-0002 208. VOLTS LINE TO LINE
SOURCE OF PWR BUS-0001
==============================================================================
ITEM DESCRIPTION * CONNECTED LOAD * DEMAND LOAD * DESIGN LOAD * %
KVA AMPS KVA AMPS KVA AMPS P F
==============================================================================
END USE LOADS
LIGHTING 12.6 35.0 12.6 35.0 15.8 43.8 95.00
HEATING 12.5 34.6 12.5 34.6 15.6 43.3 95.00
==============================================================================
TOTALS 25.1 69.6 25.1 69.6 31.4 87.1 95.00
25.1 kVA
Demand Load =
e 3jb0.208 kVg
= 69.6 A
This calculation matches the results in the preceding table.
UTILITY 1
BUS 1
Connected 97.95 kVA
Demand 97.95 kVA
Design 110.23 kVA C1
PF 87.89 Lag
BUS 2
Connected 97.95 kVA
Demand 97.95 kVA
Design 110.23 kVA C2
PF 87.89 Lag
BUS 3
Connected 97.95 kVA
Demand 97.95 kVA
Design 110.23 kVA MOTOR 1 MOTOR 2
Size 50.0 kVA Size 50.0 kVA
PF 87.89 Lag No 2 No 1
PF 0.95 Lag PF 0.75 Lag
The results of the apparent power calculation appear as the demand load kVA rounded
up to 98.0 kVA in the Report. The 85.62% power factor for the combined loads is
based on the design load values.
LOAD SCHEDULE FOR BUS-0003 480. VOLTS LINE TO LINE
==============================================================================
ITEM DESCRIPTION * CONNECTED LOAD * DEMAND LOAD * DESIGN LOAD * %
KVA AMPS KVA AMPS KVA AMPS P F
==============================================================================
KVA TYPE MTR 50.0 60.1 50.0 60.1 50.0 60.1 95.00
LARGEST KVA MTR 50.0 60.1 50.0 60.1 62.5 75.2 75.00
==============================================================================
TOTALS 98.0 117.8 98.0 117.8 110.2 132.6 85.62
3/26/2006
Demand Load Study DAPPER 1-19
Before combining the demand loads, the Demand Load Study correctly recognizes the
single 75 kVA motor at Motor 2 as the largest motor on the bus, even though Motor 1
has a total of 100 kVA connected load. The design load is calculated as follows:
b g b
Design Load = 75 kVA × 125% + 2 × 50 kVA × 100% g
= 93.8 kVA + 100 kVA
= 193.8 kVA
The design load value for Bus 3 is 193.8 kVA, as shown in the following one-line
diagram.
UTILITY 1
BUS 1
Connected 175.00 kVA
Demand 175.00 kVA
C1
Design 193.75 kVA
PF 85.00 Lag
BUS 2
Connected 175.00 kVA
Demand 175.00 kVA C2
Design 193.75 kVA
PF 85.00 Lag
BUS 3
Connected 175.00 kVA
Demand 175.00 kVA MOTOR 1 MOTOR 2
Design 193.75 kVA Size 50.0 kVA Size 75.0 kVA
PF 85.00 Lag No. of Mtrs 2 No. of Mtrs 1
PF 0.85 Lag PF 0.85 Lag
The following report show the design load of the largest motor as 93.8 kVA and the
total design load as 198.8 kVA.
LOAD SCHEDULE FOR BUS 3 480. VOLTS LINE TO LINE
SOURCE OF PWR BUS 2
==============================================================================
ITEM DESCRIPTION * CONNECTED LOAD * DEMAND LOAD * DESIGN LOAD * %
KVA AMPS KVA AMPS KVA AMPS P F
==============================================================================
END USE LOADS
KVA TYPE MTR 100.0 120.3 100.0 120.3 100.0 120.3 85.00
LARGEST KVA MTR 75.0 90.2 75.0 90.2 93.8 112.8 85.00
==============================================================================
TOTALS 175.0 210.5 175.0 210.5 193.8 233.0 85.00
thus the lock rotor current ratio is 4 per unit. The starting power factor is related to the
motor’s X/R ratio. The motor’s X/R ratio is defined as 5, thus the starting power factor
is 19.6%. The power factor result is:
d
Power Factor = cos arctan XR i
= cosbarctan5g
= cose78.7 jo
= 19.61% Lag
The following one-line diagram shows this starting power factor. The motor load
characteristic is changed from a constant kVA load to a constant impedance load during
this starting simulation, although it does not effect the outcome of the Demand Load
Study.
UTILITY 1
BUS 1
BUS 2
BUS 3
Note that the report show that 200 kVA of demand load is also at the largest motor:
LOAD SCHEDULE FOR BUS-0003 480. VOLTS LINE TO LINE
SOURCE OF PWR BUS-0002
==============================================================================
ITEM DESCRIPTION * CONNECTED LOAD * DEMAND LOAD * DESIGN LOAD * %
KVA AMPS KVA AMPS KVA AMPS P F
==============================================================================
END USE LOADS
LARGEST Z MTR 50.0 60.1 200.0 240.6 250.0 300.7 19.61
==============================================================================
TOTALS 50.0 60.1 200.0 240.6 250.0 300.7 19.61
3/26/2006
Demand Load Study DAPPER 1-21
Because the branch from Bus 6 to Bus 5 is temporarily out of service, the calculated
connected, demand, and design loads at Bus 4 and Bus 5 are zero. Additionally, the
demand load on the branch between Bus 1 and Bus 2 is 125 kVA. Utility 1 is the
source of supply for all the loads in the system.
If the branch from Bus 2 to Bus 6 were open instead of the branch from Bus 5 to Bus 6,
the two sources of supply would feed the loads more equally. When there are loops in
the power system, pay close attention to where the branches are automatically opened.
Sometimes it is best to manually open the branch to ensure proper load balance between
branches.
UTILITY 1 UTILITY 2
BUS 1 BUS 4
Connected 125.00 kVA Connected 0.00 kVA
Demand 125.00 kVA Demand 0.00 kVA
Design 143.75 kVA C1 Design 0.00 kVA C3
BUS 2 BUS 5
Connected 125.00 kVA Connected 0.00 kVA
Demand 125.00 kVA Demand 0.00 kVA
Design 143.75 kVA C2 C6 Design 0.00 kVA C4
BUS 3 BUS 6
Connected 75.00 kVA Connected 50.00 kVA
Demand 75.00 kVA Demand 50.00 kVA C5
Design 93.75 kVA MOTOR 1 Design 62.50 kVA
Size 75.0 kVA
BUS 7
PF 0.95 Lag
Connected 50.00 kVA
Demand 50.00 kVA MOTOR 2
Design 62.50 kVA Size 50.0 kVA
PF 0.95 Lag
3/26/2006
UTILITY BUS
DAPPER 1-22
R1
CB1
TM -1
R2
CB2
TX A
003-HV SWGR
R8 R9 R10
Reference Manual
R3 R6 R7
CB6
C4
C1 GEN 1 GEN 2 C3
C2 SYN A SYN B 007-TX E PRI
TX B PRI BUS 4
R4 R5 006-TX3 PRI TX E
TX B 005-TXD PRI
CB4 CB5 TX 6
BLDG 115 SERV
DS SWG1 BUS 8 TX D
F1
TX H C10 C11
C6
029-TX D SEC
C5
TX C PRI BUS 9 CMP CTR HVAC BUS CB12 026-TX G PRI 025-MTR 25
C13 C20
LVP1 LVP2 LVP3 C9 L1 M20 L5
M13 L2
C14 C16 C17 LVP4 LVP5
021-TX F PRI TX F
BUS 28 A BUS 28 B
BUS 15 BUS 16 BUS 17
022-DSB 2 MCP#28B-1 MCP#28B-2
MCC 15 - 1A PLN 16 H2A
PLN - 17 H1A
C15 C18
C12
MO/L#28B-1 MO/L#28B-2
MCCB1 MCCB2
023-MTR 23
The following figure shows a portion of the Plant project, including Demand Load
Study results.
TX G
F3
MO/L#25
DSB 3 BUS 27
MO/L#28B-1 MO/L#28B-2
The Demand Load Study reports the connected, demand and design load power and
current at each bus, and the design load value power factor. Some of the data for the
buses in the above one-line diagram are shown in the following report:
LOAD SCHEDULE FOR BLDG 115 SERV 4160. VOLTS LINE TO LINE
SOURCE OF PWR 007-TX E PRI
==============================================================================
ITEM DESCRIPTION * CONNECTED LOAD * DEMAND LOAD * DESIGN LOAD * %
KVA AMPS KVA AMPS KVA AMPS P F
==============================================================================
END USE LOADS
BRANCH LOADS
026-TX G PRI 1081.7 150.1 981.8 136.3 1058.9 147.0 84.05
025-MTR 25 2500.0 347.0 2500.0 347.0 3125.0 433.7 80.00
029-TX D SEC 0.0 0.0 0.0 0.0 WARNING: LOAD IS ZERO
==============================================================================
TOTALS 3580.3 496.9 3480.5 483.0 4125.7 572.6 81.08
The complete load summary from the Demand Load Study Report is shown below. It
lists the connected, demand and design load values and the design load power factor in
each load category.
TOTAL SOURCE LOAD SUMMARY
******************************************************************************
==============================================================================
LOAD DESCRIPTION UNITS CONNECTED DEMAND DESIGN POWER FACTOR
TYPE LOAD LOAD LOAD %
==============================================================================
GENERAL LOADS KW 59.6 59.6 59.6
KVAR 28.9 28.9 28.9
KVA 66.3 66.3 66.3 90.00 LAGGING
LIGHTING KW 216.2 216.2 270.2
KVAR 85.3 85.3 106.6
KVA 232.4 232.4 290.5 93.02 LAGGING
RECEPTACLES KW 80.3 44.4 44.4
KVAR 49.7 27.5 27.5
3/26/2006
Demand Load Study DAPPER 1-25
The demand load factors for the various demand loads are listed in the table below.
Only seven of the twenty demand load categories are used in this example.
LOAD DEMAND TABLE
==============================================================================
LOAD DESCRIPTION LOAD FIRST DEMAND SECOND DEMAND THIRD DEMAND DESIGN
TYPE KVA % KVA % KVA % FACT
==============================================================================
GENERAL LOADS K 100. 100. ALL 50. ALL 50. 1.00
LIGHTING K ALL 100. ALL 100. ALL 100. 1.25
RECEPTACLES Z 10. 100. ALL 50. ALL 50. 1.00
OFFICE EQUIPMENT Z ALL 100. ALL 100. ALL 100. 1.00
HEATING Z ALL 100. ALL 100. ALL 100. 1.25
STANDBY LOADS K ALL 100. ALL 100. ALL 100. 1.25
CAPACITOR BANK Z ALL 100. ALL 100. ALL 100. 1.35
The Sizing Study sizes branch components such as feeders, neutrals, raceways,
transformers, and equipment grounding conductors based on the results of the Demand
Load Study (DLS).
The Sizing Study is the second of two Studies used to quantify the preliminary electrical
design to meet national codes and standards. Combined with the DLS, the preliminary
design ensures that feeders and transformers meet minimum load values. Once the
preliminary design is defined, more detailed Studies (Voltage Drop, Motor Starting, Short
Circuit Studies) are used to verify that electrical apparatus is sized for normal and
abnormal system operation.
• Engineering Methodology.
• Examples.
IN THIS CHAPTER
The Sizing Study follows U.S. National Electrical Code (NEC)[1] procedures; however,
the critical design criteria are user-defined, and can be specified to meet local codes.
The following flow chart shows the procedure for the Sizing Study.
Study Setup
Cable Library
Transformer Library Run Sizing Study
Feeder Voltage Drop Criteria
Transformer Tap Size Criteria
Study Setup
Saved in Database
For each branch:
Feeder size
Used by Short Circuit Study
Quantity of feeders per phase
and Load Flow Study
Transformer nominal kVA
Raceway information
Transformer full-load kVA
Reports
[1]
Authored by Committee, 1996 National Electric Code. Quincy, MA: National Fire
Protection Association, 1996.
3/26/2006
Sizing Study DAPPER 2-3
The Sizing Study bases its calculations on two separate criteria: the minimum conductor
cross-sectional area to meet feeder ampacity values and a user-defined voltage drop value.
If you consider parallel feeder combinations for a specified conductor type, the Sizing
Study can select multiple feeders in parallel for that conductor. Cable sizes must be
specified in the Cable Library in order to be available to the Sizing Study. Derated cable
ampacities are determined based on the temperature derating factor and duct bank design
detail criterion.
The Sizing Study selects the cable that best meets defined ampacity values and has the
smallest cross-sectional area. Once the cable is selected, the voltage drop for the cable or
cable pair is calculated. If the voltage drop criterion is exceeded, the Sizing Study selects
the next larger cable size and begins the comparison of cross-sectional area, rated
ampacity and voltage drop.
The Sizing Study algorithm determines the feeder branch design load value in amperes,
then determines the selected feeder design ampacity. The feeder design ampacity is the
product of the rated ampacity, the temperature derating factor and the number of parallel
cables. The design load value is the rated size of the load multiplied by specified demand
factors and the long continuous load factor (or design factor).
Once the ampacity conditions are met, the Sizing Study then checks the calculated voltage
drop on the cable, based on the branch design load current and power factor, cable
impedance, and length. The voltage drop is calculated using the following formula:
% Voltage Drop =
b g b
3 I × R × cosφ + I × X × sinφ g × 100
VLL
If the voltage drop exceeds the specified level, the Sizing Study selects the next largest
feeder and restarts the Sizing Study in order to select a cable or combination of parallel
cables which meets the ampacity criteria of minimum cross-sectional area and acceptable
voltage drop. The Sizing Study voltage drop calculation follows the methodology cited in
Chapter 3 of the IEEE Red Book.[2] This simple methodology assumes no losses in the
branch.
Feeders attached to the primary or secondary of a transformer are sized differently than
those associated with other branch circuits. These feeders tend to be short in length and
are sized in direct relation to the transformer nominal rated size.
The capacity factor is stored in the Transformer Library. Typical capacity factors are:
[2]
Authored by Committee. IEEE Red Book: IEEE Recommended Practice for Electric
Power and Distribution for Industrial Plants, IEEE Std 141-1993. USA: Institute of
Electrical and Electronics Engineers, Inc., 1994.
3/26/2006
Sizing Study DAPPER 2-5
contains a loop, the DLS will have temporarily opened the loop to run the demand and
design load Studies. Therefore, the Sizing Study is based on the radial system used in the
DLS.
Although user-defined feeders are not sized, if sufficient ampacity data is entered in the
Component Editor, then feeder evaluation is accomplished.
Because the sole purpose of the DLS is to provide the vector sum of the total load at each
bus and in each branch of the electrical system, it ignores local generation. Therefore, the
Sizing Study, which is based on the demand and design load values resulting from the
DLS, tends to oversize feeders and transformers which are upstream from local
generation.
The Cable and Transformer Libraries contain feeder and transformer sizing tables that are
required for the Sizing Study. You can modify the libraries to suit your individual design
requirements.
Tip: You may run the Demand Load Study in the same step that you run the Sizing
Study. All you need to do is select both Studies, and PTW will automatically run the
Demand Load Study first. See “Running the Sizing Study,” following.
The Sizing Study runs, writes the results to the database, and creates a Report.
The Sizing Study is dependent on the system load values. Therefore, the Sizing Study
bases its calculations on the results of the last Demand Load Study run.
You can keep the defaults, or type in new values for the Allowable Feeder Voltage Drop
and Primary/Secondary Feeder percent text boxes:
You can choose one of three options for the Study results:
Size, Report and Change Database Size the existing system, generate a Report of current
feeder and transformer sizes; make changes to the
database based on the findings.
Report Only, Do Not Size Generate a Report of current feeder and transformer sizes;
make no new sizing calculations or changes in the
database.
3/26/2006
Sizing Study DAPPER 2-7
You can select to create a DXF file suitable for import to Computer Aided Design (CAD)
software, and specify an extended print character set:
Use Extended Character Set Provide for vertical lines and boxes around the feeder and
transformer schedules. You must use the
PIXymbolsExtended font which is automatically loaded
as a True Type font when PTW is installed.
The Sizing Study tries to find an appropriate feeder size or parallel combination of feeders
to meet either the cable ampacity or voltage drop limitation, but if none is found, the
Sizing Study will broadcast a warning and leave the cable size unchanged.
Note: Because the Sizing Study may change circuit impedance values, PTW will not
allow you to run the Sizing Study simultaneously with either the Load Flow Study,
Comprehensive Short Circuit Study, A_FAULT Study, or IEC_FAULT Study.
UTILITY
B1 4160 V
Demand Load 200.00 kVA
C1
Size # 6 AWG/kcmil
1 Cables in Parallel
30.10 Amps
Ampacity 75.0 A / Cable
Length 100.0 ft
B2
4160 V
Demand Load 200.00 kVA
T1
225.0 kVA
B3
480 V
Demand Load 200.00 kVA
C3 C4
Size # 2/0 AWG/kcmil Size # 2/0 AWG/kcmil
1 Cables in Parallel 2 Cables in Parallel
128.98 Amps 131.92 Amps
Ampacity 175.0 A / Cable Ampacity 175.0 A / Cable
Length 100.0 ft Length 1000.0 ft
B5 B6
480 V 480 V
Demand Load 100.00 kVA Demand Load 100.00 kVA
L1 L2
Design Load 125.00 kVA Design Load 125.00 kVA
In the one-line diagram, note the branch circuit conductor from Bus B4 to Bus B5. The
#2/0 AWG cable has an ampacity of 175 A and a load current of 129 A. The cable is
loaded to 73% of its ampacity, safely under the NEC’s 80% limit. The branch from Bus
B4 to Bus B6 is ten times longer than the first branch. The voltage drop is significant, and
the Sizing Study selects two #2/0 AWG cables in parallel. Two are required because of
the voltage drop associated with the 1000-foot cable length.
A low voltage feeder circuit is defined between Buses B3 and B4, but this is also defined
as a secondary tap of the transformer. The Sizing Study sizes this feeder based on the
transformer full load size. Transformer T1 was sized as 225 kVA to meet the total
demand load of 200 kVA in this branch.
The Sizing Study always reports when feeder cables are selected based on the transformer
size. In this case, the Report listed the following message regarding the transformer
secondary tap:
PRIMARY/SECONDARY TRANSFORMER FDRS SIZED AT 125. % OF TX FULL LOAD RATING
*** NOTICE *** FEEDER SIZED TO 125. PERCENT OF TRANSFORMER SIZE
BRANCH FROM B3 TO B4
3/26/2006
Sizing Study DAPPER 2-9
From the preceding Report, the secondary feeder will be sized larger than 338.3 A
because the transformer feeder sizing criterion was chosen as 125% of the transformer’s
full load rated amperes. The user-defined Primary/Secondary Feeder sizing criterion is
adjusted in the Feeder and Transformer Sizing Study dialog box. Thus, four parallel sets
of #4/0 AWG cables are selected as the optimal solution, including the effects of the
voltage drop, due to the extremely long cable length. The four #4/0 AWG cables have a
combined cross-sectional area of 846.4 kcmil. Even if 750 kcmil conductors are selected,
parallel circuits are required. If the transfer secondary tap were ten feet long, then two
each #2/0 AWG cables, with a rated ampacity of 175 A per cable, would certainly meet
the ampacity, cross sectional area, and voltage drop sizing criteria.
B4
B5 B6
The derating of Cable C3 is accomplished by adjusting the temperature text box in the
Conductor and Raceway subview. Cable C3 must be sized differently than Cable C4,
based on the 50°C derating factor of 75%. Cable C3 is sized to a single #2/0 AWG cable,
which has a rating of 175 A at 30° C or 131 A at 50° C. The actual demand load value in
this branch is 121.7 A. This result is compared to the identical load and cable length in
the branch from Bus B4 to Bus B5. In this branch only a single #1 AWG cable, rated at
130 A, is required.
U1
B1
C1
Length 6000.0 ft
Ampacity 150.0 A
Size 2
No 1
B2 LF Current 70.48 A
C2 C20
Length 25.0 ft Length 25.0 ft
Ampacity 83.0 A Ampacity 110.0 A
Size 6 Size 4
No 1 No 1
LF Current 28.28 A LF Current 42.86 A
B3 B30
T1
Size 225.0 kVA T2
Load 205.00 kVA Size 500.0 kVA
Load 305.00 kVA
B4 B40
C3
C30
Length 10.0 ft Length 10.0 ft
Ampacity 175.0 A Ampacity 200.0 A
Size 2/0 Size 3/0
No 2 B50 No 4
B5 LF Current 232.86 A LF Current 352.89 A
C40 C50
C4 C5
Length 300.0 ft Length 1000.0 ft Length 300.0 ft Length 1000.0 ft
Ampacity 85.0 A Ampacity 175.0 A Ampacity 150.0 A
Ampacity 175.0 A
Size 4 Size 2/0 Size 2/0 Size 1/0
No 1 No 1 No 3
No 2
LF Current 63.22 A LF Current 175.50 A LF Current 123.43 A LF Current 235.42 A
B6 B7 B60 B70
L1 L2
155.00 kVA L10 L20
55.00 kVA
SPECIAL LOAD SPECIAL LOAD 105.00 kVA 205.00 kVA
SPECIAL LOAD SPECIAL LOAD
The above diagram shows that each branch circuit is sized according to its load and that
the primary and secondary transformer feeders are sized based on the transformer full load
rating.
Tip: To effectively use the Sizing Study where many transformers exist, it is best to
place primary and secondary feeder taps on the transformer, as shown above.
3/26/2006
EDISON
UTILITY BUS
R1
CB1
TM -1
R2
CB2
TX A
003-HV SWGR
R8 R9 R10
R3 R6 R7
CB6
C4
C1 GEN 1 GEN 2 C3
C2 SYN A SYN B 007-TX E PRI
TX B PRI BUS 4
R4 R5 006-TX3 PRI TX E
TX B 005-TXD PRI
CB4 CB5 TX 6
BLDG 115 SERV
DS SWG1 BUS 8 TX D
F1
TX H C10 C11
C6
029-TX D SEC
C5
TX C PRI BUS 9 CMP CTR HVAC BUS CB12 026-TX G PRI 025-MTR 25
C13 C20
LVP1 LVP2 LVP3 C9 L1 M20 L5
M13 L2
C14 C16 C17 LVP4 LVP5
021-TX F PRI TX F
BUS 28 A BUS 28 B
BUS 15 BUS 16 BUS 17
022-DSB 2 MCP#28B-1 MCP#28B-2
MCC 15 - 1A PLN 16 H2A
Sizing Study
PLN - 17 H1A
C15 C18
C12
MO/L#28B-1 MO/L#28B-2
MCCB1 MCCB2
023-MTR 23
C10 C11
F4 SW1
F3
TX G
MO/L#25
L5
C20
C13
LVP5
LVP4
BUS 28 B
MCP#28B-1 MCP#28B-2
BUS 28 A
MO/L#28B-1 MO/L#28B-2
The Sizing Study first lists notices if feeders are identified on either the primary or
secondary side of two winding transformers. If feeders are identified, they are sized in
accordance to the ***Notice*** listed. Some of the data for the buses in the above one-
line diagram are shown in the following Report.
3/26/2006
Sizing Study DAPPER 2-13
The Sizing Study Report also lists all the feeder sizes, as shown below, for a portion of the
Plant project.
FEEDER SIZE REPORT
******************************************************************************
F E E D E R S C H E D U L E
==============================================================================
FEEDER ROUTING FEEDER NO WIRE SIZE TYPE INSUL GROUND RACEWAY
NO NAME VOLTAGE /PH QTY FDR MAT TYPE WIRE SIZE TYPE
==============================================================================
F E E D E R D E S I G N L O A D A N A L Y S I S
==============================================================================
FEEDER ROUTING EXTG % QTY SIZE FEEDER DESCRIPTION DESIGN FEEDER
NO NAME VD /PH FDR MAT INSUL AMBIENT LOAD CAPACITY
==============================================================================
FROM 003-HV SWGR 13800.
*********************
TO TX B PRI BUS 4 0.07 1 4 CU XLP 30. 82. A 110. A
TO 005-TXD PRI EX 0.00 1 2/0 CU XLP 30. 0. A 225. A
*** WARNING *** FEEDER LOAD IS DEFINED AS ZERO
TO 006-TX3 PRI 0.12 2 1/0 CU XLP 30. 368. A 390. A
TO 007-TX E PRI 0.03 2 1/0 CU XLP 30. 173. A 390. A
The Sizing Study Report also includes feeder evaluation, based on the design load value.
FEEDER EVALUATION
******************************************************************************
F E E D E R D E S I G N L O A D A N A L Y S I S
==============================================================================
FEEDER ROUTING EXTG % QTY SIZE FEEDER DESCRIPTION DESIGN FEEDER
NO NAME VD /PH FDR MAT INSUL AMBIENT LOAD CAPACITY
==============================================================================
*********************
TO BUS 28 A 0.75 4 500 CU THWN 30. 609. A 1520. A
T R A N S F O R M E R S C H E D U L E
==============================================================================
LOCATION DESCRIPTION VOLTAGE CONN PCT. TRANSFORMER DESCRIPTION
BUS NO. NAME LEVELS CODE TAP
==============================================================================
3/26/2006
3 Load Flow Study
The Load Flow Study predicts the overall apparent real and reactive power distribution
throughout a power system, including associated losses. Additionally, the Study
calculates the voltage drop through each branch impedance component, and the associated
voltages at each bus or node in the electrical system.
This chapter introduces the steady-state load flow equations used in the Load Flow Study,
demonstrates PTW’s powerful algorithm used to solve these equations, and documents
several case studies that validate the Study and provide you with examples of how to most
effectively use the Load Flow Study.
• Engineering Methodology.
• PTW Applied Methodology.
• Examples.
IN THIS CHAPTER
Saved in Database
For each branch:
Voltage drop
Power flow
Datablocks
Reports
11/22/2006
Load Flow Study DAPPER 3-3
where
I column vector of total positive sequence currents flowing into each node
(bus) in the system;
Y The network admittance matrix (1/Z);
V Column Vector of positive sequence voltage at each bus.
This equation is a linear algebraic equation with complex real and imaginary coefficients.
The matrix may be reduced and the solution for either voltage or current reached using
matrix algebra. The current flowing into any node of the system may be defined:
Ii =
LM bP + jQ g * OP
i i
Eq. 3-2
N V* Q i
where
bP + jQ g *
i i complex conjugate of the apparent power flowing into the ith node;
Vi* complex conjugate of the voltage of the ith node.
Combining Eq. 3-1 and Eq. 3-2 yields:
N [V]* Q
Equation 3-3 is non-linear, and cannot be solved in closed form; thus the numerical
analysis solution technique used must guess at each branch power flow, evaluate the
algebraic equations, and then determine if the power into each bus equals power leaving
the bus, including losses—that is, determine if Kirchoff’s Current Law is met. This
iterative-type numerical analysis solution method continues until convergence is reached.
(Convergence means that the power into the node equals the power out of the node.) A
convergence criteria is established, based on an acceptable level of precision. For
example, the algorithm might identify the largest load in the system and divide that load
value by some constant, such as 20,000, to define a convergence criterion. Convergence
usually occurs in less than ten guesses or numerical iterations.
The steady-state load flow Eq. 3-3 can be reduced to a set of input and output variables;
knowledge about these variables aids in the solution. Three types of buses are defined
when solving for the power flow, as noted below:
The type I bus may be either a motor or non-motor load bus, where power out of the node
is defined as a positive quantity. The dependent variables are voltage magnitude and
voltage angle.
The type II bus is a generation bus where real power is generated. A class A generator
bus is non-regulated; the real and reactive power is fixed in magnitude. As load variations
occur, the voltage magnitude and voltage angle vary. A class B generator type bus is a
regulated bus. Automatic voltage regulation controls the bus voltage within the
generator’s reactive power limits. Since the real power is fixed in magnitude, the system
frequency (the resultant voltage angle) must vary.
The type III bus is called a swing or slack bus, and the voltage magnitude and angle are
held constant, and the real and reactive power then must vary.
At least one bus in the electrical system must be defined as a swing bus in order to solve
the steady-state load flow equation. From the preceding table, two of the four variables
are always unknown, but there is a single equation (Eq. 3-3). This is why the Load Flow
Study solution cannot be solved in closed form. By defining a swing bus voltage and
angle, and recognizing that all type I bus voltages and angles are relative to the swing bus
voltage magnitude and angles, numerical solution techniques may be used. The defining
methodology assumes that the total apparent power into each node must equal the power
out of the node (that is, that Kirchoff’s Current Law is valid).
11/22/2006
Load Flow Study DAPPER 3-5
harmony with solution of the voltage conditions at each load bus, as described in the
previous section.
The type of loads specified and the system losses significantly influence the results of the
load flow and voltage drop calculations. Constant impedance type loads are loads that
vary as the square of the applied voltage. Examples of this type of load include
incandescent lighting and resistance heating elements. Constant kVA loads are loads that
remain (or attempt to remain) constant within boundary limitations regardless of the
applied voltage. Examples of this type of load include motor loads and some types of
lighting which utilize an inductive ballast to establish constant wattage to the lamp.
It is clear that with constant kVA type loads, the actual load currents increase with
decreasing voltage. With constant impedance loads, line currents decrease as the voltage
is lowered. If both kVA loads and constant impedance loads are present, then the
resulting voltage effects may be partially or totally canceled.
Constant current type loads hold their current constant under varying voltage conditions.
Like constant impedance type loads, as the voltage drops at the bus the amount of
apparent power consumed by the constant current type load decreases. Constant current
type loads are affected by the fluctuations in the bus voltage angle.
More simply, adding the receiving end voltage at each load bus and the branch voltage
drop is equal to the sending end voltage, as illustrated in the following figure.
I
R + jX
∅ IR
Load Power Factor Angle
Actual Voltage Drop
Load Current
b
Vs = Vr + I R + jX g Eq. 3-4
where
Vs sending bus voltage;
Vr receiving bus voltage;
I load current;
R feeder resistance;
jX feeder reactance.
PTW reports the magnitude difference between the receiving and sending end voltages as
the voltage drop, expressed on a three-phase (line-to-line) basis.
VD = Es − E r
11/22/2006
Load Flow Study DAPPER 3-7
Tip: You may run the Demand Load Study in the same step that you run the Load
Flow Study. All you need to do is select both Studies, and PTW will automatically run
the Demand Load Study first. See Section 3.3.2, “Running the Load Flow Study,”
following.
The Load Flow Study runs, writes the results to the database, and creates a report.
You can change any or all of the available Study Options to suit your needs. Following is
a list of all of the controls available in this box, and their functions.
System Modeling
If you select the Utility Impedance check box, PTW uses the three-phase short circuit
capacity to calculate an equivalent positive sequence impedance. The voltage drop at the
swing bus is calculated, given the total power supplied by the swing bus generator and this
positive sequence impedance. It is reported separately in the Load Flow Report. Upon
opening a new Project, the PTW does not model the system equivalent impedance by
default. This means the voltage at the swing bus is equal to the voltage of the swing bus
generator, which is set by default to 1 pu voltage at 0°.
If you uncheck the Transformer Phase Shift checkbox, PTW reports the voltage angles
relative to the swing bus voltage angle. If you check this option, PTW models the voltage
angle phase shift of the transformer connections.
Solution Method
PTW models either an Exact (Iterative) or Approximate Solution. Upon creating a new
Project, PTW selects the Exact (Iterative) Solution method by default. It is recommended
that you run the Study using the Exact (Iterative) Solution method first. This is because
the solution method usually converges on most power systems. In the unlikely event that
the steady-state load flow solution does not converge, you should re-run the Study using
the Approximate Solution method. If it does not converge, a message in the Study
Message dialog box will notify you of the problem.
When the Approximate Solution method is selected, PTW temporarily converts all loads
to constant impedance type characteristics, making these system losses smaller than if
constant kVA type loads were modeled. An output report is then written, and data is sent
to the database. Although it is an approximate solution (since the load characteristic is
approximated), this solution method may help to identify the reasons for the non-
convergence.
If you have a non-convergent solution, examine the output Report’s bus voltage mismatch
values and bus mismatch location, as there may be a data input problem that has caused
the non-convergence. If this does not help, try adjusting the solution criteria; see
“Solution Criteria,” following.
Load Specification
You may select one of five options for load modeling. These options are divided into two
groups: Directly Connected Loads, and loads From the Demand Load Study. The default
upon opening a new Project is to model all loads as Directly Connected loads using the
Connected Load values. For a more detailed discussion of the demand and design load
values, see the “Engineering Methodology” section of the “Demand Load Study” chapter.
When the Connected Load option button is selected, the Load Flow Study calculates the
loads without considering any load or demand factors. If motor loads are identified, and if
multiple motors are modeled in a single motor load object, the total motor connected load
is the number of motors multiplied by the motor’s rated size. Otherwise, the load rated
size is the connected load value. Motors expressed in horsepower are converted to
electrical units by dividing by the efficiency.
11/22/2006
Load Flow Study DAPPER 3-9
When the 1st Level Demand or Energy Factor option button is selected, the Load Flow
Study calculates the loads using the first level demand factors and energy audit load
factors, as appropriate. If a non-motor load is identified with both an energy audit load
factor and a demand load category, then the Study will use both the energy audit load
factor and the first level demand load factor multiplied by the load’s rated size. For motor
loads, the load is calculated as the number of motors multiplied by the motor rated size
multiplied by the motor load factor. Load diversity resulting from identifying multiple
levels of demand load factors is not taken into consideration.
When the Demand Load option button is selected, the Load Flow Study uses the
calculated demand load values from the Demand Load Study. Upon creating a new
Project, the Demand Load Study includes the results from all non-motor loads by default,
unless you selected either the Include Only Demand Loads or Include Only Energy Audit
Loads option button before running the Demand Load Study. Demand loads with multiple
levels of demand factors, such as receptacle loads where the first 10 kVA of load have a
100% demand factor and the remaining receptacle load has a 50% demand factor result in
a non-coincident demand (diversity) load that is unique. This diversity load is calculated
at each branch within the load flow solution. See Example 3.4.4, “Net Branch Diversity
Load” for further discussion.
Remember that when modeling loads using any of the three From Demand Load Study
options, the results are based on the results from the last Demand Load Study. If you
change the system topology you need to first re-run the Demand Load Study. You may
run the Demand Load Study and the Load Flow Study in one step, as described in
“Running the Load Flow Study” on page 3-7
Solution Criteria
The two Acceleration Factor text boxes allow you to control how the Load Flow Study
converges upon the solution. Generally, the Acceleration Factors do not need to be
changed from their default values. However, if a non-convergent solution occurs, even
after an Approximate Solution method has been run, try changing the Generation
Acceleration Factor and/or the Load Acceleration Factor from their default of 1.0 to a
factor between 0.1 and 1.0. This changes the guessing factor used to calculate the next
iteration of the numerical solution. The smaller the factor, the smaller the step change
used in the iteration solution.
The Bus Voltage Drop and Branch Voltage Drop text boxes provide a quick method to
flag excessive voltage drops in the output report. In the report, PTW flags with a dollar
sign ($) any bus or branch voltage drop value that exceeds the limits set in these text
boxes. Upon creating a new Project, the default values are a 5% bus voltage drop, and a
3% branch voltage drop. However, you can change these percentages by typing a percent
value in the appropriate text box.
Loads may be directly connected to the co-generation bus and the utility swing bus. PTW
accurately models the power flow in this situation even when directly connected loads are
installed on Type II or Type III load buses.
On-Site Generation
An on-site generator that operates in parallel with the utility source may be defined as
either a PV- or PQ-type generator in the Component Editor. The generator may have
leading or lagging reactive power. Lagging reactive kVA is plotted as a positive value
and referred to as an over-excited condition of the machine. Leading reactive kVA is
plotted as a negative value and referred to as an under-excited condition of the generator.
Any type of balanced loading within the area bounded by the curve shown following is
considered as safe by the generator manufacturer.
Lagging
1.0
Rated PF
Lagging
Reactive Power-- Per Unit
.50
0.0
-.50
PF Leading
-1.0
Leading 0.25 0.5 .075 1.00
Kilowatts Per Unit
A combined total of up to 10 Swing Bus (SB) and PV-type generators may be modeled in
PTW. A total of up to 60 generators may be modeled, of which no more than 10 may be a
combination of PV- and SB-type generators. When modeling SB generators, they may be
modeled as generator components or as utility components.
The source connection represents the system swing bus or slack bus. It maintains a
constant voltage at a constant bus angle. The kW and kvar of the swing bus vary, or
“swing,” in order to satisfy the following equation:
11/22/2006
Load Flow Study DAPPER 3-11
The swing bus generator or utility source must supply any deficiency in generation, and
all losses. If there is excess generation in the system, the source bus acts to absorb the
excess generation.
Usually, a system requires only a single swing bus. Multiple swing buses may be used to
model large systems having multiple connections to a utility. Therefore, the exact utility
voltages and angles may be specified. Additionally, multiple independent systems require
that you specify a swing bus for each system. Only one swing bus may be specified at a
single bus.
Co-generation modeled as PV-type generators which are not located near the utility or
swing bus generator will serve to regulate the voltage at the generator bus. PTW attempts
to hold the bus voltage at the target level within the reactive power range. It may not be
possible to obtain the target voltage. PTW will maintain the kW output of the generator
and allow the voltage to float to the reactive power limit.
PTW allows for modeling more than one generator at a bus. If the generators are PV-type
generators, then you need to identify how much reactive power is generated by each
machine (pu Var Participation factor). Usually the reactive power is shared equally
between the machines; therefore, if two PV machines are modeled on the same bus, then
the participation factor is 0.5 for each machine. When multiple PV generators are
modeled on individual buses separated by small cables, you may get a non-convergent
solution because the reactive power calculated by PTW depends on very small bus voltage
angles. If this occurs, model the multiple PV machines on a single bus, or lump the
generation into a single generator model.
Diversity Loads
Special attention needs to be paid when running the Load Flow Study when demand loads
are considered. As discussed in the “Non-Coincident Demand Calculation” example of
the “Demand Load Study” chapter, PTW considers the effects of non-coincident or
diversity loads. In the example, even though each of the two branch demand loads are
550 kVA, the total demand load at Bus 2 is only 1050 kVA. The load flow solution must
take this diversity load into consideration. In effect, the feeder servicing these two
branches only needs to supply 1050 kVA, but each branch needs to be supplied 550 kVA.
The load flow solution will report a small net negative diversity load at this upstream bus.
See Example 3.4.4, “Net Branch Diversity Load”at the end of this chapter.
PTW accurately models the loads when loops are present in the power system. As was
discussed in the Demand Load Study chapter, the Demand Load Study methodology must
identify and calculate load diversity only in a radial system. The Demand Load Study
detects loops, opens them temporarily to calculate load diversity, then closes the loops. In
some cases, where extensive (nested) loops exist, the automatic opening of the loops can
result in odd load flow solutions. It is recommended that if multiple loops exist in the
power systems and if load diversity is not a significant issue for the Study, then the load
flow solution be modeled using the Directly Connected Loads Load Specification option.
Remember, this option allows for modeling the Connected Load or 1st Level Demand
Load factor and Energy Factor.
1. Diverging Solution: If the Exact (Iterative) Solution method has been selected, and
under certain extreme loading conditions, it is possible that the Load Flow Study
cannot determine a steady-state load flow condition and no report will be generated.
An error will be reported in the Study Messages dialog box. This can occur in power
systems whenever the system voltages are not sufficient to supply constant kVA
loads.
2. Load Not Defined: PTW will report a warning message if loads are defined with zero
load. This is just a warning message and is provided to give you a listing of the zero
load values. The Study will run, but will ignore the zero load values.
3. Load Category Not Defined: PTW will report a demand load where its demand load
category is not defined. In this case, a 100% Demand Factor will be used as the
default.
4. Incomplete Configuration. PTW will detect components whose nodes (connection
points) are not physically connected. PTW must have all components connected.
11/22/2006
Load Flow Study DAPPER 3-13
GENERATOR
B1
13800 V C1
13800.00 V 1886.52 kW
0.00 % 1467.74 kvar
5.71 kW Losses
57.13 kvar Losses
1.64 % VD
100.00 A
B2
13800 V
13573.55 V
1.64 %
L1
The load draws 100 A at 80% power factor and is assumed to have a constant current-type
load characteristic.
PLoss = I 2 R × 3
= 100b g b0.19044g × 3
2
= 5.71 kW
The magnetization power required by the cable is:
Q Loss = I 2 X × 3
b g b1.9044g × 3
= 100
2
= 57.1 kvar
In a simplified form, the voltage drop through the cable is:
b
VD L− L = IRcosΘ + IXsinΘ × 3 g
= b100gb0.19044gb0.8g + b100gb1.9044gb0.6g × 3
= b80gb0.19044g + b60gb1.9044g × 3
= b129.5g × 3
= 224.3 V
And on a per unit base, this is:
224.3 V
VD pu =
13800 V
= 0.0163 pu V
Vpu = 1 − 0.0163 pu
= 0.984 pu
The datablocks posted on the one-line diagram and the hand calculations are closely
matched. The difference between hand and computer solutions is due to round-off and the
11/22/2006
Load Flow Study DAPPER 3-15
use of the simplified form of the voltage drop formula, as noted in Chapter 3 of the IEEE
Red Book. The Report confirms these hand calculations, as noted below.
BALANCED VOLTAGE DROP AND LOAD FLOW ANALYSIS (SWING GENERATORS)
*****************************************************************************
SOURCE VOLTAGE ANGLE KW KVAR VD% (UTILITY IMPEDANCE)
GEN-0001 1.000 .00 1886.52 1467.74 Gen Z Ignored
BALANCED VOLTAGE DROP AND LOAD FLOW ANALYSIS
==== BUS: BUS-0001 DESIGN VOLTS: 13800 BUS VOLTS: 13800 %VD: .00
========================= PU BUS VOLTAGE: 1.000 ANGLE: .0 DEGREES
*** SWING GENERATOR: GEN-0001 1886.5 KW 1467.7 KVAR
LOAD TO: BUS-0002 FEEDER AMPS: 99.9 VOLTAGE DROP: 226. %VD: 1.64
PROJECTED POWER FLOW: 1886.5 KW 1467.7 KVAR 2390.2 KVA PF: .79 LAGGING
LOSSES THRU FEEDER: 5.7 KW 57.1 KVAR 57.4 KVA
==== BUS: BUS-0002 DESIGN VOLTS: 13800 BUS VOLTS: 13574 %VD: 1.64
========================= PU BUS VOLTAGE: .984 ANGLE: -1.0 DEGREES
NET BRANCH DIVERSITY LOAD: 1880.8 KW 1410.6 KVAR
LOAD FROM: BUS-0001 FEEDER AMPS: 99.9 VOLTAGE DROP: 226. %VD: 1.64
PROJECTED POWER FLOW: 1880.8 KW 1410.6 KVAR 2351.0 KVA PF: .80 LAGGING
LOSSES THRU FEEDER: 5.7 KW 57.1 KVAR 57.4 KVA
*** T O T A L S Y S T E M L O S S E S ***
6. KW 57. KVAR
GENERATOR
B1
13800 V
13800.00 V
0.00 % C1 795.54 kW T1 795.54 kW
605.90 kvar 605.90 kvar
1.00 kW Losses 1.00 kW Losses
10.00 kvar Losses 10.00 kvar Losse
0.68 % 0.68 %
41.84 A 41.84 A
B2 B3
13800 V 13800 V
13705.78 V 13705.78 V
0.68 % 0.68 %
L1 L2
1.0 MVA 1.0 MVA
0.80 Lag PF 0.80 Lag PF
The following input data shows that on a per unit basis, the impedance of the cable equals
the impedance of the transformer.
The Load Flow Report shows the power flow in both the cable and the transformer branch
are identical. Losses in these two components are the same. The transformer was
modeled at a 1:1 voltage ratio.
BALANCED VOLTAGE DROP AND LOAD FLOW ANALYSIS
*****************************************************************************
VOLTAGE EFFECT ON LOADS MODELED
==== BUS: B1 DESIGN VOLTS: 13800 BUS VOLTS: 13800 %VD: .00
========================= PU BUS VOLTAGE: 1.000 ANGLE: .0 DEGREES
*** SWING GENERATOR: GENERATOR 1591.1 KW 1211.8 KVAR
LOAD TO: B2 FEEDER AMPS: 41.8 VOLTAGE DROP: 94. %VD: .68
PROJECTED POWER FLOW: 795.5 KW 605.9 KVAR 1000.0 KVA PF: .80 LAGGING
LOSSES THRU FEEDER: 1.0 KW 10.0 KVAR 10.0 KVA
LOAD TO: B3 TRANSF AMPS: 41.8 VOLTAGE DROP: 94. %VD: .68
PROJECTED POWER FLOW: 795.5 KW 605.9 KVAR 1000.0 KVA PF: .80 LAGGING
LOSSES THRU TRANSF: 1.0 KW 10.0 KVAR 10.0 KVA
==== BUS: B2 DESIGN VOLTS: 13800 BUS VOLTS: 13706 %VD: .68
========================= PU BUS VOLTAGE: .993 ANGLE: -.4 DEGREES
NET BRANCH DIVERSITY LOAD: 794.5 KW 595.9 KVAR
LOAD FROM: B1 FEEDER AMPS: 41.8 VOLTAGE DROP: 94. %VD: .68
PROJECTED POWER FLOW: 794.5 KW 595.9 KVAR 993.2 KVA PF: .80 LAGGING
LOSSES THRU FEEDER: 1.0 KW 10.0 KVAR 10.0 KVA
==== BUS: B3 DESIGN VOLTS: 13800 BUS VOLTS: 13706 %VD: .68
========================= PU BUS VOLTAGE: .993 ANGLE: -.4 DEGREES
NET BRANCH DIVERSITY LOAD: 794.5 KW 595.9 KVAR
LOAD FROM: B1 TRANSF AMPS: 41.8 VOLTAGE DROP: 94. %VD: .68
PROJECTED POWER FLOW: 795.5 KW 605.9 KVAR 1000.0 KVA PF: .80 LAGGING
LOSSES THRU TRANSF: 1.0 KW 10.0 KVAR 10.0 KVA
The losses through the cable and the transformer are equal, as they should be.
You can specify the individual load type in the Load Diversity subview of the Component
Editor by selecting either the Demand Load or Energy Audit option button. The Load
Flow Study results are affected by which load type you select. The Load Flow Study
results also depend on the Load Specification selection in the Load Flow Study setup
dialog box: one of the two Directly Connected Loads, or one of the three From the
Demand Load Study loads. These last three options are more global, as they allow you to
model loads based on results from the Demand Load Study.
In the one-line diagram below, five different branch load types and load factors are
modeled. The results of the Load Flow Study, depending on the individual load type and
Load Specification selected, are shown on the one line diagram.
11/22/2006
Load Flow Study DAPPER 3-17
GENERATOR
3115.26 kW B1
2366.59 kvar 13800.00 V
0.80 PF 0.00 % VD
C1 C2 C3 C4 C5
42.1 A 29.4 A 42.1 A 29.4 A 20.57 A
B2 B3 B4 B5 B6
13705.13 V 13733.81 V 13705.13 V 13733.81 V 13753.77 V
0.69 % VD 0.48 % VD 0.69 % VD 0.48 % VD 0.33 % VD
L1 L2 L3 L4 L5
1000.0 kVA 1000.0 kVA 1000.0 kVA 1000.0 kVA 1000.0 kVA
Energy Audit Energy Audit Demand Load Demand Load Demand Load
1.0 Energy Audit 0.7 Energy Audit General Load Special Load Special Load
Load Factor Load Factor 0.7 Energy Audit
Load Factor
Each of the five loads is rated 1000 kVA; thus each load’s connected load value is 1000
kVA.
Loads L1 and L2 are Energy Audit type loads, whereas Loads L3, L4, and L5 are Demand
Load types. Load L1 has an Energy Audit load factor of 1.0, while Loads L2 and L5 have
an Energy Audit load factor of 0.7. Note that while Load L5 is a Demand Load type, it
still has an Energy Audit load factor specified. Load L3 is selected as a General Load,
while Loads L4 and L5 are selected as Special Loads; these selections were made from the
Demand Load Category drop-down list box found in the Load Diversity subview of the
Component Editor.
The demand load factors (which are referenced from the Demand Load Library) used in
this example are:
See the “Engineering Methodology” section of the “Demand Load Study” chapter for
additional discussion on design and demand loads and long continuous loading (LCL)
factors.
It is important also to note that the Load Flow Study takes into account the effects of
voltage on loads. All of the loads in this example are modeled as constant kVA type
loads; thus, as the voltage at the load bus decreases, the current in the branch servicing the
load increases. Calculating the load current is not easily accomplished by hand methods
because the solution cannot be solved in closed form.
Remember that all five loads in this example have a rated size of 1000 kVA, or 42.13 A.
The calculated current in each branch is different , based on the Individual Load Type and
the Individual Load Factor.
The calculated load flow branch current using the 1st Level Demand or Energy Factor for
Load L1 is equal to the connected load because the load factor is 1.0, whereas the current
in the branch servicing Load L2 is 0.7 of the connected load. Note that the only
difference in load characteristics between Loads L4 and L5 is that, although both are
modeled as demand loads, Load L4 has a default energy audit load factor of 1.0 while
Load L5 has a energy audit load factor of 0.7. Therefore, the calculated load flow branch
current using the 1st Level Demand or Energy Factor is 29.4 A for Load L4 but only
20.57 A for Load L5.
The calculated load flow branch current using the results From Demand Load Study
should be further discussed. For example, the load flow current using the Demand Loads
for both Loads L4 and L5 is equal to 40.85 A, the Energy Audit load factor of 0.7 is not
used.
The data shown in the above one-line matches the load specification 1st Level Demand or
Energy Factor Study setup.
This example is the load flow solution for the “Non-Coicident Demand Calculation”
example presented in the “Demand Load Study” chapter. Two identical demand loads of
1000 kVA (General Load Category) are connected in a system shown in the one-line
following:
11/22/2006
Load Flow Study DAPPER 3-19
GENERATOR
840.03 kW
630.04 kvar
0.80 PF
B1
13800.00 V
C1
0.00 % VD
840.03 kW
630.04 kvar
B2
13799.57 V
C2 C3
0.00 % VD
440.00 kW 440.01 kW
330.01 kvar 330.01 kvar
B4
B3
13799.38 V 13799.28 V
0.00 % VD 0.01 % VD
L1 L2
1000.0 kVA 1000.0 kVA
Demand Load Type Demand Load Type
From the “Non-Coicident Demand Calculation” example, note that the connected load at
Bus B2 is 2000 kVA, but the demand load value is 1050 kVA. This is a diversity load
value, as the sum of the two branch (coincident) demand loads is 1100 kVA (550 kVA
each). It can then be concluded that only 1050 kVA of apparent power must service Bus
B2, but 550 kVA must flow to each of the two loads.
Inspection of the real component of apparent power at Bus B2 is instructive. From the
one-line diagram, 840 kW flows into the bus, but 440 kW flows out. A net branch
diversity of -40 kW exists.
This is most clearly displayed in the Load Flow Study report, as shown following:
BALANCED VOLTAGE DROP AND LOAD FLOW ANALYSIS
*****************************************************************************
VOLTAGE EFFECT ON LOADS MODELED
==== BUS: B2 DESIGN VOLTS: 13800 BUS VOLTS: 13800 %VD: 0.00
========================= PU BUS VOLTAGE: 1.000 ANGLE: 0.0 DEGREES
NET BRANCH DIVERSITY LOAD: -40.0 KW -30.0 KVAR
At Bus B2, PTW reports the net difference in power flowing into the node (1050 kVA)
and the power flowing out of the node (1100 kVA). This net difference acts to raise the
system voltages, compared to the case where diversity is not considered. For example, in
the above problem, change the load type by selecting the Energy Audit option button
instead of Demand Load, and change the load factor to 0.55. The demand load at Bus 2
will now be 1100 kVA.
11/22/2006
EDISON
UTILITY BUS
R1
CB1
TM -1
R2
CB2
TX A
003-HV SWGR
R8 R9 R10
R3 R6 R7
CB6
C4
C1 GEN 1 GEN 2 C3
C2 SYN A SYN B 007-TX E PRI
TX B PRI BUS 4
R4 R5 006-TX3 PRI TX E
TX B 005-TXD PRI
CB4 CB5 TX 6
BLDG 115 SERV
DS SWG1 BUS 8 TX D
F1
TX H C10 C11
C6
029-TX D SEC
C5
TX C PRI BUS 9 CMP CTR HVAC BUS CB12 026-TX G PRI 025-MTR 25
C13 C20
LVP1 LVP2 LVP3 C9 L1 M20 L5
M13 L2
C14 C16 C17 LVP4 LVP5
021-TX F PRI TX F
BUS 28 A BUS 28 B
BUS 15 BUS 16 BUS 17
022-DSB 2 MCP#28B-1 MCP#28B-2
MCC 15 - 1A PLN 16 H2A
PLN - 17 H1A
C15 C18
C12
MO/L#28B-1 MO/L#28B-2
Load Flow Study
MCCB1 MCCB2
023-MTR 23
The following figure shows a portion of the Plant project, including Load Flow results.
The Load Flow and Voltage Drop Report first lists the Study setup conditions and
constraints. Also included is a listing of the convergence criterion and the number of
iterations required for the load flow solution to converge upon an acceptable solution.
*** SOLUTION COMMENTS ***
=========================
SOLUTION PARAMETERS
BRANCH VOLTAGE CRITERIA : 3.00 %
BUS VOLTAGE CRITERIA : 5.00 %
ACCELERATION FACTOR FOR 'PV' GENERATORS : 1.00
ACCELERATION FACTOR FOR CONSTANT KVA LOADS: 1.00
EXACT(ITERATIVE) SOLUTION : YES
UTILITY IMPEDANCE : YES
TRANSFORMER PHASE SHIFT : NO
ALL PU VALUES ARE EXPRESSED ON A 100 MVA BASE
LOAD FLOW IS BASED ON CALCULATED DEMAND LOAD RESULTS
FROM THE DEMAND LOAD ANALYSIS STUDY.
LOAD ANALYSIS INCLUDES ALL LOADS.
<<PERCENT VOLTAGE DROPS ARE BASED ON NOMINAL DESIGN VOLTAGES>>
SWING GENERATORS
SOURCE NAME VOLTAGE ANGLE
11/22/2006
Load Flow Study DAPPER 3-23
================================
EDISON 1.000 0.00
PV GENERATORS
SOURCE NAME VOLTAGE kW kVARMIN kVARMAX PARTICIPATION
==================================================================
GEN 2 1.000 350. 0. 300. 0.25
GEN 1 1.000 600. -600. 500. 0.75
GEN 3 1.000 2400. -900. 1600. 1.00
Next the report lists the system swing bus generation and equivalent voltage drop of the
swing bus generator(s) based on the the system utility fault duty contribution as you
defined it.
BALANCED VOLTAGE DROP AND LOAD FLOW ANALYSIS (SWING GENERATORS)
*****************************************************************************
SOURCE VOLTAGE ANGLE KW KVAR VD% (UTILITY IMPEDANCE)
EDISON 1.000 0.00 10190.11 4696.85 0.55 0.00370+J 0.11105
Once the swing bus generation is known, the generation of the various PV machines can
be listed:
BALANCED VOLTAGE DROP AND LOAD FLOW ANALYSIS (PV GENERATOR SCHEDULE REPORT)
*****************************************************************************
---VOLTAGE--- -KVAR LIMITS- ---ACTUAL----
PV SOURCE NAME SCHED. ACTUAL MIN MAX KW KVAR
GEN 2 1.000 1.000 0. 300. 350. 98.
GEN 1 1.000 1.000 -600. 500. 600. 295.
GEN 3 1.000 0.996 -900. 1600. 2400. 1600.
The basic data presented in the Load Flow and Voltage Drop Report is listed below for
key buses and branches associated with the Building 115 Service:
BALANCED VOLTAGE DROP AND LOAD FLOW ANALYSIS
*****************************************************************************
VOLTAGE EFFECT ON LOADS MODELED
VOLTAGE DROP CRITERIA: BRANCH = 3.00 % BUS = 5.00
==== BUS: UTILITY BUS DESIGN VOLTS: 69000 BUS VOLTS: 68618 %VD: 0.55
========================= PU BUS VOLTAGE: 0.994 ANGLE: -0.6 DEGREES
*** SWING GENERATOR: EDISON 10190.1 KW 4696.9 KVAR
LOAD TO: TX A PRI FEEDER AMPS: 93.8 VOLTAGE DROP: 1414. %VD: 2.05
PROJECTED POWER FLOW: 10185.5 KW 4557.0 KVAR 11158.4 KVA PF: 0.91 LAGGING
LOSSES THRU FEEDER: 7.9 KW -2.9 KVAR 8.4 KVA
LOAD FROM: EDISON FEEDER AMPS: 93.8 VOLTAGE DROP: 382. %VD: 0.55
PROJECTED POWER FLOW: 10185.5 KW 4557.0 KVAR 11158.4 KVA PF: 0.91 LAGGING
LOSSES THRU FEEDER: 4.7 KW 139.8 KVAR 139.9 KVA
==== BUS: BLDG 115 SERV DESIGN VOLTS: 4160 BUS VOLTS: 4071 %VD: 2.13
========================= PU BUS VOLTAGE: 0.979 ANGLE: -6.1 DEGREES
LOAD FROM: 007-TX E PRI TRANSF AMPS: 502.1 VOLTAGE DROP: 46. %VD: 1.10
PROJECTED POWER FLOW: 2866.5 KW 2296.5 KVAR 3673.0 KVA PF: 0.78 LAGGING
LOSSES THRU TRANSF: 26.2 KW 181.4 KVAR 183.3 KVA
LOAD TO: 026-TX G PRI FEEDER AMPS: 146.3 VOLTAGE DROP: 12. %VD: 0.28
PROJECTED POWER FLOW: 834.9 KW 607.1 KVAR 1032.3 KVA PF: 0.81 LAGGING
LOSSES THRU FEEDER: 2.9 KW 1.1 KVAR 3.1 KVA
LOAD TO: 025-MTR 25 FEEDER AMPS: 355.8 VOLTAGE DROP: 15. %VD: 0.36
PROJECTED POWER FLOW: 2005.4 KW 1508.0 KVAR 2509.1 KVA PF: 0.80 LAGGING
LOSSES THRU FEEDER: 5.4 KW 8.0 KVAR 9.6 KVA
LOAD FROM: 029-TX D SEC FEEDER AMPS: VOLTAGE DROP: 0. %VD: 0.00
PROJECTED POWER FLOW: 0.0 KW 0.0 KVAR 0.0 KVA PF: 0.00 LAGGING
LOSSES THRU FEEDER: 0.0 KW 0.0 KVAR 0.0 KVA
==== BUS: DSB 3 BUS 27 DESIGN VOLTS: 480 BUS VOLTS: 460 %VD: 4.09
LOAD TO: BUS 28 A FEEDER AMPS: 568.4 VOLTAGE DROP: 3. %VD: 0.70
PROJECTED POWER FLOW: 362.0 KW 272.9 KVAR 453.3 KVA PF: 0.80 LAGGING
LOSSES THRU FEEDER: 2.0 KW 2.9 KVAR 3.5 KVA
LOAD TO: BUS 28 B FEEDER AMPS: 574.2 VOLTAGE DROP: 8. %VD: 1.65
PROJECTED POWER FLOW: 367.5 KW 273.2 KVAR 457.9 KVA PF: 0.80 LAGGING
LOSSES THRU FEEDER: 7.5 KW 3.2 KVAR 8.1 KVA
==== BUS: BUS 28 A DESIGN VOLTS: 480 BUS VOLTS: 457 %VD: 4.79
========================= PU BUS VOLTAGE: 0.952 ANGLE: -8.6 DEGREES
NET BRANCH DIVERSITY LOAD: 360.0 KW 270.0 KVAR
LOAD FROM: DSB 3 BUS 27 FEEDER AMPS: 568.4 VOLTAGE DROP: 3. %VD: 0.70
PROJECTED POWER FLOW: 360.0 KW 270.0 KVAR 450.0 KVA PF: 0.80 LAGGING
LOSSES THRU FEEDER: 2.0 KW 2.9 KVAR 3.5 KVA
==== BUS: BUS 28 B DESIGN VOLTS: 480 BUS VOLTS: 452 %VD: 5.74$
========================= PU BUS VOLTAGE: 0.943 ANGLE: -8.3 DEGREES
NET BRANCH DIVERSITY LOAD: 360.0 KW 270.0 KVAR
LOAD FROM: DSB 3 BUS 27 FEEDER AMPS: 574.2 VOLTAGE DROP: 8. %VD: 1.65
PROJECTED POWER FLOW: 360.0 KW 270.0 KVAR 450.0 KVA PF: 0.80 LAGGING
LOSSES THRU FEEDER: 7.5 KW 3.2 KVAR 8.1 KVA
A summary listing of all bus voltages and branch currents is listed at the end of the report.
BALANCED VOLTAGE DROP AND LOAD FLOW BUS DATA SUMMARY
*****************************************************************************
BUS NAME BASE VOLT PU VOLT BUS NAME BASE VOLT PU VOLT
UTILITY BUS 69000.00 0.9945 TX A PRI 69000.00 0.9740
003-HV SWGR 13800.00 0.9899 TX B PRI BUS 4 13800.00 0.9897
005-TXD PRI 13800.00 0.9899 006-TX3 PRI 13800.00 0.9892
007-TX E PRI 13800.00 0.9897 DS SWG1 BUS 8 4160.00 1.0000
TX C PRI BUS 9 4160.00 0.9997 HVAC BUS 4160.00 0.9977
TX3 SEC BUS 11 4160.00 0.9898 DSB 1 BUS 14 480.00 1.0029
DS SWG2 BUS 13 4160.00 0.9898 TX3 TER BUS 12 4160.00 0.9958
DS SWG3 BUS 20 4160.00 0.9957 021-TX F PRI 4160.00 0.9938
BLDG 115 SERV 4160.00 0.9787 026-TX G PRI 4160.00 0.9758
025-MTR 25 4160.00 0.9751 022-DSB 2 480.00 0.9949
BUS 15 480.00 1.0018 018-RA 480.00 0.9971
BUS 16 480.00 0.9925 BUS 17 480.00 0.9894
H3A BUS 19 480.00 0.9870 023-MTR 23 480.00 0.9914
DSB 3 BUS 27 480.00 0.9591 BUS 28 A 480.00 0.9521
029-TX D SEC 4160.00 0.9787 BUS 28 B 480.00 0.9426
CMP CTR 208.00 0.9763
11/22/2006
Load Flow Study DAPPER 3-25
*** T O T A L S Y S T E M L O S S E S ***
201. KW 949. KVAR
***WARNING*** STUDY CONTAINS 1 VOLTAGE CRITERIA VIOLATIONS
VIOLATIONS DENOTED BY ($) AT BUS AND BRANCH %VD LOCATIONS
The voltage drop data reported is based on the criteria in the text boxes in the Load Flow
Study Setup dialog box.
This chapter examines the theoretical basis of the Comprehensive Short Circuit Study
(referred to hereafter as “Short Circuit Study”). It includes a systematic methodology and
applies the methodology to numerous practical examples. You can also purchase
separately the A_FAULT and IEC_FAULT Short Circuit Study modules. The chapters
provided with A_FAULT and IEC_FAULT discuss the Short Circuit Methodology as
defined by the American National Standards Institute (ANSI) and the International
Electrotechnical Commission (IEC), respectively.
The basis of all short circuit studies is Ohm’s Law and is referred to in this Reference
Manual as the comprehensive methodology. This comprehensive methodology is
exclusively examined in this chapter.
• Engineering Methodology.
• Examples.
IN THIS CHAPTER
Study Setup
Cable Library Run Short Circuit Study
Transformer Libray
Study Setup
Used by Load
Saved in Database Schedules
Datablocks
Reports
3/26/2006
Short Circuit Study DAPPER 4-3
inverted admittance (impedance) matrix, the bus fault currents are calculated using Ohm’s
Law.
[E] = [Z][I]
where
E bus voltage matrix;
Z bus impedance matrix; referred to as the Z Bus matrix;
I bus nodal current matrix.
The impedance Z in complex notation is:
Z = R + jX
where
R resistance;
jX reactance.
The following one-line diagram shows the process used to calculate the fault current at
Bus 2. For a fault at Bus 2, the fault current contributions flow from the Utility and from
Motors 1 and 2 into Bus 2.
UTILITY
B1
T1
B2
C1
M1
B3
M2
Z Transformer Z Cable
Next, the systematic procedure calls for converting all impedances to per unit values on a
common power base, such as 100 MVA. Converting impedances from units of ohms to
per unit is more critical when transformers are included in the power system. This is
because the transformer’s impedance in ohms depends upon whether the impedance is
viewed through the primary or secondary connection. When the transformer’s impedance
is in per unit, its value is the same as when viewed through either the primary or the
secondary connection. From the Thevenin equivalent impedance diagram, you can create
a Norton equivalent diagram by short circuiting the voltage sources and injecting a Norton
equivalent current (If) into the faulted bus.
Bus 2
Bus 1 Bus 3
Z Cable
If
In the above circuit diagram, the Norton equivalent current If splits at Bus 2 and flows
through the three branches. The current in each branch is dependent on its impedance. The
current at Bus 2 is actually the negative of the Norton equivalent current If. The sum of
the three branch currents is also equal to If.
Using simple series and/or parallel impedance combinations, you can determine the single
Thevenin equivalent impedance at Bus 2. If you know the Thevenin equivalent
impedance, you can determine the fault current in per unit amperes.
V
If =
Z Thevenin
3/26/2006
Short Circuit Study DAPPER 4-5
Single-Line-to-Ground Faults
The following diagram shows a bolted single-line-to-ground fault in Phase A.
Phase a
Phase b
Phase c
Ic I V=0
b Ia
Fault
Va = 0, I b = 0, I c = 0
where
Va line-to-ground voltage in Phase A;
Ib currents in Phase B;
Ic currents in Phase C.
From symmetrical components the following solution matrix is written:
MMI PP = 3 MM1 a 2
P
a Q MNI PQ
a1 b
NI a2 Q N1 a 2
c
where
I b = Ic = 0
and
a = e j120
a 2 = e j240
Substituting the above and solving yields the single-line-to-ground fault case:
I a0 =
1
3
Ia b g
1
I a1 = I a
3
b g
1
I a2 = I a
3
b g
Therefore:
I a1 = I a2 = I a0
Because the three symmetrical components are equal in magnitude and in phase, they may
be viewed as connected in series, as shown:
Z1 Ia1
Z2 Ia2
Ea
Z0 Ia0
Ea
I a1 =
Z1 + Z 2 + Z 0
where
Z1 positive-sequence impedance;
Z2 negative-sequence impedance;
Z0 zero-sequence impedance.
From the preceding equations we know that the positive sequence current in Phase A is
one-third of the phase current.
Therefore:
3/26/2006
Short Circuit Study DAPPER 4-7
I a = 3I a1
Substituting yields:
3E a
Ia =
Z1 + Z 2 + Z 0
It is entirely possible that the return current (ground current) for a line-to-line-to-ground
fault could be larger than the fault current in the two faulted phase-conductors.
Grounding Impedance
The zero-sequence impedance of delta-wye-grounded transformers is modeled as an
infinite impedance (open connection) when viewed from the delta side, and modeled as a
shunt to the reference through the transformer’s zero-sequence impedance when viewed
from the wye-grounded side. The wye-grounded wye-grounded transformer, if provided
with a grounding impedance, is modeled with grounding impedance on either or both
sides of the transformer connection. In this configuration there is no connection to
reference. Although not specifically discussed in the above formulation of the unbalanced
fault networks, any grounding impedance must be modeled at three times its ohmic value
in the zero-sequence network. If a grounding impedance is established on the wye-
grounded side of the transformer, its impedance is added in series to the shunt path (that
is, in series with the transformer’s zero-sequence impedance).
where
F kV IJ FG kVA IJ pu Ω
= X ′′ G motor
2
base
Z pu d
H kV K H kVA K
base motor
where
X ′′d motor subtransient reactance on its motor rated line-to-line voltage (kVmotor)
and three-phase power (kVAmotor) base;
kVmotor line-to-line motor rated voltage;
kVAmotor three-phase power base;
kVbase line-to-line bus nominal system voltage at the point of the motor;
kVAbase three-phase power base.
For feeders:
Z cable Z cable
Z pu = = pu Ω
kv base × 1000
2 2
kVbase
kVA base MVA base
where
For transformers:
Z pu =
FG Z transformer % IJ FG kV IJ FG kVA
2
IJ
H K H kV
transformer base
100 base K H kVA
transformer K
where
Ishort circuit =
FG V IJ pu A
HZ Thevenin K
Expressed in amperes:
kVA base
I base =
3 × kVbase
Sometimes the aforementioned per unit notation equations cannot be used directly. For
example, if your utility fault data is not in power or current units, convert it to acceptable
units. Suppose the utility equivalent impedance at the source is expressed as:
3/26/2006
Short Circuit Study DAPPER 4-9
Z utility = eR 2
+ X2 j
V
I=
3 × Z utility
4160 V
Ishort circuit =
e 3jb0.4272 Ωg
= 5622 A
The utility X/R ratio is:
X 0.425 Ω
=
R 0.0425 Ω
= 10
The interrupting fault current is defined as the short circuit current that flows through a
protective device at the time of its contact separation. The interrupting duty of a circuit
breaker may be lower than its associated closing and latching (momentary) rating. The
interrupting current tends to be more symmetrical with the time axis than the momentary
fault current. Medium and high voltage circuit breakers in particular may have
interrupting ratings based on contact parting times of 3 or 5 cycles after the onset of the
fault.
The asymmetrical nature of the momentary fault current is a result of the instantaneous
change in system X/R at the point of the fault prior to and immediately after the fault.
Prior to the fault, the system generally operates at a very small X/R ratio (that is, a high
power factor). However, after the fault when all the high power factor loads are ignored,
the system X/R ratio can be quite large. This instantaneous change in system X/R ratio at
the instant the fault occurs is exacerbated when, during the voltage sine wave, the fault
occurs. If the fault occurs at a positive-increasing voltage peak, then the current wave is
said to have maximum asymmetry. This asymmetric condition is known as the dc
component or dc decay because the asymmetric nature of the wave shape decays
exponentially over time. Also, the momentary fault current and, to a lesser degree, the
interrupting fault current are dependent upon the time varying collapse in machine
voltages. This time varying collapse is known as the ac decrement and is most often
modeled as a time varying machine reactance.
Current limiting fuses which operate within one-half cycle are subject to momentary
currents and may open to clear the fault before the maximum prospective fault current
occurs. Devices such as circuit breakers require the fault current to pass through a current
zero before the arcing current is extinguished. Breakers may experience significant
interrupting fault current for many cycles during operation.
To calculate the momentary and interrupting fault currents, you must evaluate both the
transient and steady state conditions.
Consider a fault that occurs in a simple RL series circuit driven by an ideal sinusoidal
voltage source. You can write Kirchoff’s Loop Equation as:
b g
Vpeak × sin ω t + Θ = Ri +
Ldi
dt
This differential equation can be solved for the instantaneous current, i:
LM V -t OP
i=
Vpeak
b g MZ
sin ω t + α - Θ −
peak
e
L
R
b
sin α - Θ gP
Z
N Q
where
Z b g
R 2 + ωL
2
3/26/2006
Short Circuit Study DAPPER 4-11
Current
Theoretical maximum
Peak at 1/2 cycle
Top envelope
Decaying (aperiodic) component idc Asymmetrical values
(DC decay) including motor contributions
2 I"k
ip
2
2 2I k
i dc
Time
The first one-half cycle asymmetrical peak current is the sum of the de decay and ac
decrement components. This can be expressed in equation form as:
−2π
FG R IJ c
i asymmetrical peak = 2 I ′′k + 2 I ′′k e H XK
where
F R I 2
R
−4π c
= I ′′k 1 + 2e X
R
−2π
= I ′′k 1 + 2e X
Do not guess at the effects of transformer taps on short circuit calculations. Taps may
increase or decrease fault current, even to a degree that protective device fault duties or
time/current coordination is affected.
Tap
X d" Z Transformer
Faulted Bus
Transformer
Voltage Generator
The relationship between the short circuit current and primary tap setting is:
V
If =
LMF 1 I 2 OP
MNGH 1 + Tap JK × X ′′d generator + Z transformer
PQ
where
If fault current;
V fault point pre-fault no loads pre-fault voltage;
Tap ideal voltage shifter in per unit;
X ′′d machine reactance;
Ztransformer transformer impedance.
The fault point no load voltage is:
FG 1 IJ
V = Vgenerator
H 1+ Tap K
3/26/2006
Short Circuit Study DAPPER 4-13
Tap
X d" Z Transformer
Faulted Bus
Transformer
Voltage Generator
The relationship between the short circuit current and transformer secondary tap setting is:
V
If =
(1 + Tap ) ( X2 "
d generator + Z transformer )
b
V = Vgenerator 1+ Tap g
You can model transformer off-nominal voltages similar to transformer taps. In both
cases, the modeling uses an ideal voltage shifter either on the primary, secondary, or both
sides of the transformer.
In order to model off-nominal voltages, you must have the Model Transformer Taps
checkbox selected in the Study Setup dialog box.
When the transformer phase shift is modeled for a single-line-to-ground fault, the branch
sequence current might be:
1388 -120°
1388 -120°
Positive-Sequence
1388 -120°
1388 -120°
Negative-Sequence
418 -120°
0 -0°
1388 -120°
418 -120°
0 -0°
Zero-Sequence
In this example, the transformer is rated 13.8 kV - 4.16 kV, and if 1388 A in the positive-
sequence network flow in the secondary winding, the primary winding positive-sequence
current is 418 A.
3/26/2006
Short Circuit Study DAPPER 4-15
The Short Circuit Study runs, writes the results to the database, and creates a report.
Fault Type
By default, PTW includes Three Phase Fault and Single Line to Ground fault calculations;
the Line to Line Fault and Line to Line to Ground fault calculations can also be selected.
Generally, the three-phase and single-line-to-ground current model the worst case fault
currents in the system. You can select any combination of the four check boxes.
Faulted Bus
By default, PTW faults All Buses. If you want to fault a single bus, select the One Bus
option button and select the appropriate bus from the box. If All Buses is selected, limited
data is written to the database; however, the Report can be extensive.
If you are running a Study on a 100 bus facility and choose to report fault duties on all
buses and branches, the total report could be 300 or more pages.
Calculation Models
Select the checkbox(es) for the calculations you want to include in the Study: Motor
Contribution, Transformer Tap, and Transformer Phase Shift. You can select any
combination of the three.
Motor Contribution
By default, PTW includes motor contributions. Unchecking the check box eliminates
motor contributions from the Study results.
Transformer Tap
By default, PTW does not include tap effects in the transformer model. If this box is
unchecked, all transformers appear without the effect on any taps, and the pre-fault
voltage is relative to the swing bus voltage. By selecting Transformer Tap, PTW
calculates the system pre-fault no load voltage profile based on the swing bus voltage and
transformer tap settings. You must check this box to analyze transformer off nominal
voltages properly.
Report Specifications
Make Report specification selections based on the following criteria.
Bus Voltages
By default, PTW calculates and reports voltages for the First Bus From Fault. You can
also select from three other options: Second Bus From Fault, All Buses, and None. Keep
in mind that if you select All Buses, the Study will take significantly longer to run.
Bus voltages are reported but not written to the database. Bus voltages are not reported
when sequence branch current values are selected.
Branch Currents
You can also select from three other options: First Branch From Fault, Second Branch
From Fault, and All Branches. Upon opening a new project, the default is to report branch
currents one branch away from the fault point.
As shown in Figure 4-1, if you wish to display branch fault currents through 3-winding
transformers, you must select the option to report 2 branches away (not just one branch
away).
3/26/2006
Short Circuit Study DAPPER 4-17
Figure 4-1. To report branch fault currents for 3-winding transformers, select to
report 2 branches away, not one.
The speed of the Study is significantly impacted by the amount of Study results written to
the database and to the output report.
Branch currents are only written to the database if a fault at a single bus is selected. If a
bus is faulted, then branch currents may flow from any location to the faulted bus. If a
different bus is faulted, then different branch fault currents flow. Only one complete set
of branch fault data is saved to the database for retrieval onto a datablock. Only initial
symmetrical phase currents in the branch are reported.
Phase or Sequence
By default, PTW reports phase A, B, and C quantities. Phase current will always be
written to the Report, but branch current flow will not be written to the database unless a
single bus is faulted. You can also select to report the positive-, negative-, and zero-
sequence quantities. Sequence currents are not reported in the database, and therefore
they will not appear in datablocks. Also, the sequence currents are not reported when
asymmetrical fault currents are calculated.
The Initial Symmetrical RMS Only option calculates bus voltages and branch flows as
complex values. All values arise from the symmetrical. The Asymmetrical Peak option
calculates the total asymmetrical peak or crest (dc offset and decay) fault current at a
specified time. You must enter the time in cycles. The Asymmetrical RMS option
calculates the total asymmetrical symmetrical (dc offset) rms current at a specified time.
You must enter the time in cycles.
If you selected initial symmetrical fault current calculations, the Study ignores the
Asymmetrical Fault Current at Time value.
The following sections describe the minimum data required for the Short Circuit Study to
run.
Feeder Data
You must specify a cable’s positive-sequence impedance and one-way circuit length.
PTW models the negative-sequence impedance as equal to the positive-sequence
impedance. If a cable’s zero-sequence impedance is zero, the Short Circuit Study uses the
positive-sequence value. Cable positive and zero sequence impedances may be selected
from the Cable Library, or you can define them in the Component Editor.
If you make the cable User Defined, you can enter specific cable impedance in ohms per
1000 feet or ohms per 1000 meters. Cable lengths must be entered in the same units as the
cable impedance data (feet or meters). If you switch the Program Options from English to
Metric units, PTW converts entered cable lengths and impedances to the appropriate units.
Cable impedances are unaffected by the wire circuit description characteristics.
Transformer Data
You can select predefined two-winding transformers from the Transformer Library or you
can define them yourself in the Component Editor. PTW defines two-winding
transformers by their percentage leakage positive- and zero-sequence impedance value,
cooling capacity type, and the nominal kVA rating. If a transformer's zero-sequence
impedance is zero, PTW uses the positive-sequence value. Transformers' rated voltages
may differ from the bus nominal voltages. PTW models those off-nominal voltages as
ideal voltage shifters separate from any primary or secondary tap that is modeled. A
warning message appears in the Study Messages dialog box when PTW detects a
mismatch between the bus nominal voltage and the transformer rated voltage. You can
also define the transformer impedance in the Component Editor using the transformer's
resistance and reactance values in percent on the nominal or self-cooled kVA rating.
When you set the PTW Project for the IEC Standards, user-defined transformers can be
defined in per unit on any kVA base, the Rated Short Circuit Voltage percent or on Rated
Ohmic voltage percent.
Three-Winding Transformers
Three-winding transformers may be modeled. Off-nominal voltage and transformer taps
may be modeled in a manner similar to two-winding transformers. All three-winding
3/26/2006
Short Circuit Study DAPPER 4-19
transformer data must be user defined in the Component Editor. PTW models the three-
winding transformer using conventional network reduction, and establishes a fictitious
center point bus. Also, PTW establishes a secondary to tertiary branch. This fictitious bus
and associated branch count against the total bus and branch limit in PTW.
There are two networks in the following one-line diagram. Transformer T1 is a three-
winding transformer with a primary, secondary and tertiary power rating of 15 MVA, 15
MVA and 5.25 MVA, respectively.
GEN 1 GEN 2
BUS 1 BUS 7
27856.53 A 27856.53 A
C1 C4
BUS 2 BUS 8
22405.02 A 22405.02 A
T2 6.0214%
T1 BUS 9
BUS 3 BUS 4 CENTER POINT
7199.51 A
21706.12 A 11150.80 A
T3 0.8790% T4
9.9790%
C2 C3 BUS 10 BUS 12
21705.22 A 11150.56 A
BUS 5 BUS 6 C5 C6
BUS 11 BUS 13
20520.80 A 10860.47 A 20520.00 A 10860.25 A
It is important to note that the preceding measurements are relative to different power
bases. In Test 1 when the tertiary circuit is open, short circuit current flows only in
primary and secondary windings. Both of these windings have 15 MVA ratings. In the
test, the voltage across the primary winding is increased until 6.9 % rated voltage causes
the rated full current to flow in the secondary winding. By opening the tertiary circuit, no
current flows in this winding.
In Test 2, the tertiary winding is fully loaded based on its 5.25 MVA rating, even though
the primary carries only about one-third rated current on its 15.0 MVA rating. The test
stopped when the 5.6 % rated voltage was applied to the primary winding and full load
current was reached on the tertiary winding (corresponding to 5.25 MVA). It is critical to
know on what base the short circuit voltage takes place.
Z PT
ZST
P
Z PS
S
You can convert this into an equivalent wye diagram using standard network reduction
techniques:
Z3
T
Z1
P
S
Z2
Z PS = Z1 + Z 2
Z PT = Z1 + Z3
ZST = Z 2 + Z3
Z1 = 1
2 (Z PS + Z PT - ZST )
Z2 = 1
2 (Z PS + ZST - Z PT )
Z3 = 1
2 (Z PT + ZST - Z PS )
3/26/2006
Short Circuit Study DAPPER 4-21
You can solve the equations by substituting the manufacturer’s data expressed on a
common 15 MVA base:
= j6.0214 %
LM j6.9 + FG j3.8 × 15 IJ - j5.6 × 15 OP
N H 5.25K
1
5.25 Q
Z2 = 2
= j0.879 %
LMFG j5.6 × 15 IJ + FG j38. × 15 IJ − j6.9OP
NH 5.25K H 5.25K Q
Z3 = 1
2
= j9.978 %
The above values represent the two-winding transformer equivalent impedances that must
be used in the one-line diagram on page DAPPER 4-18.
As of DAPPER Version 2.0, you cannot enter negative impedance values for the two-
winding transformer component, even though these sometimes occur with network
reduction of a three-winding transformer into an equivalent two-winding transformer case.
Contribution Data
Fault duty contributions to the power system originate from the motor generator and utility
source components. PTW provides default subtransient and X/R ratio values. You can
calculate the machine kVA and voltage base using the rated size and connected bus
nominal voltage. For example, if you enter a 50 hp motor with an 80% power factor and
92% efficiency, PTW calculates the rated kVA base as:
50 hp × 746 W hp
kVA base =
1000 W
× 0.8 pf × 0.92 efficiency
kW
= 50.7 kVA
This is close to the rule-of-thumb that 1 hp is equal to 1 kVA. Of course, if you have a
1000 hp synchronous motor with a unity power factor, PTW calculates the motor’s kVA
base value as 746 kVA for short circuit current purposes. The fault contribution
calculation remains unaffected by the motor load factor.
Fault contributions can be at any bus and there may be multiple contributions located at
any bus.
Important: You may change the ANSI contribution calculated kVA base, for example
to model the 50 hp motor as 50.0 kVA. However in PTW, once the machine ANSI
contribution kVA base is selected (or automatically calculated by PTW if the base kVA
value is 0), it will not change. Therefore, if you enter the motor load as 50 hp, run a
Study, and then change the motor’s rating to 75 hp, the motor’s ANSI contribution base
kVA will remain 50 kVA. You must change the base kVA to 75 kVA manually.
It involves the entry of single-line-to-ground short circuit contribution data. PTW uses the
three-phase fault data and the single-line-to-ground fault data to calculate the positive,
negative- and zero-sequence impedances from the following per unit equations:
Z1 = Z 2
1.0
Z1 =
I f3Φ
I fslg =
b g
3 × 1.0
b Z1 + Z 2 + Z 0 g
3
Z0 = − Z1 − Z 2
I fslg
kVA = 3 × I fslg × kV
kV
kVA = I fslg ×
3
where
kV line-to-line voltage.
You cannot use the three-phase equivalent rating of a single-line-to-ground short circuit
contribution. If you do, PTW may attempt to calculate the zero-sequence impedance as a
negative value. The actual apparent power to be entered into PTW is the utility equivalent
single-line-to-ground duty divided by 3. Enter the single-line-to-ground fault current X/R
ratio, not the zero sequence impedance X/R ratio.
3/26/2006
Short Circuit Study DAPPER 4-23
The following one-line diagram in Figure 4-1 shows the positive- and zero-sequence
reactances of each component, and the three-phase and single-line-to-ground fault current
at Bus 3 (the faulted bus) as calculated by PTW. The negative-sequence impedance is
assumed to be equal to the positive-sequence impedance.
UTILITY
X1 1.0000 pu
Xo 1.3333 pu
B1
X1 1.0000 pu C1
Xo 1.0000 pu
B2
X1 1.0000 pu
Xo 1.0000 pu T1
B3 40,094.23 A 3 Ph
51,549.68 A SLG
Figure 4-1
The short circuit capability of the Utility is given as 100 MVA at an X/R ratio of 99. This
equates to an impedance of 0.010101 + j 0.999948 pu Ω on a 100 MVA base at the
nominal system voltage at Bus 1 of 13.8 kV. The Utility equivalent positive-sequence
impedance, X positive, is shown in Figure 4-1 as 1.0000 pu Ω, which is 0.999948 pu Ω
rounded to four significant digits. Although the computer displays impedance values to
four significant digits, the calculations are accomplished to 16 significant digits.
C1 is a high voltage cable between Bus 1 and Bus 2; its impedance is given as 0.0 + j1.0
pu on the 100 MVA 13.8 kV system base.
The transformer (T1) impedance is also given as 0.0 + j1.0 pu Ω, on its own base, which
is the system base. The Thevenin equivalent impedance at Bus 3 is the sum of the utility,
cable and transformer impedances, all expressed on the same 100 MVA base, or as:
b g b g b
Z Thevenin = 0.010101+ j0.999948 + 0 + j1.0 + 0 + j1.0 pu Ω g
= 0.010101+ j2.999948 pu Ω
Combining the real and imaginary components of the Thevenin equivalent impedance into
a single complex impedance yields:
Z Thevenin = j2.999965 pu Ω
The short circuit current is equal to the driving point voltage divided by the Thevenin
equivalent impedance. The driving point voltage is 480 V or 1 pu V on the 480 V system
base. Therefore, the three-phase fault current is:
1
Isc = pu A
j2.999965
= - j0.333337 pu A
The base current on the 480 V side of the transformer on a 100 MVA base is:
100,000 kVA
I base =
3 × 0.48 kV
= 120,281.3 A
Thus the fault current in amperes is:
Likewise the single-line-to-ground fault current at Bus 3 is calculated from the following
equation:
3V
Islg =
Z1 + Z 2 + Z 0 + 3Z ground
Z 0transformer = 0 + j1.0 pu Ω
3 × 1 pu V
pu Ω
Islg =
b g b g b g
0.010101+ j2.999948 + 0.010101+ j2.999948 + 0 + j1.0
3V
=
0.020202 + j6.999896 pu Ω
3 pu V
=
j6.999925 pu Ω
= - j0.428576 pu A
Recalling that the base current for the 480 V system is 120,281.3 A, the single-line-ground
fault current at Bus 3 is:
3/26/2006
Short Circuit Study DAPPER 4-25
3V
Islg =
Z1 + Z 2 + Z 0
3V
Z0 = - Z1 - Z 2
Islg
The goal is to limit Islg to no more than 200 A or 0.00166 pu A on the 120,281.3 A current
base. The positive- and negative-sequence impedances at Bus 3 are 0.010101 + j2.999948
pu Ω, respectively. The positive- and negative-sequence impedances are not affected by
adding impedance in the ground path.
Zo = j1803.97 pu Ω - 2( j2.999948) pu Ω
= j1797.99 pu Ω
Z 0 = Z tranformer0 + 3Z ground
3Z ground = Z 0 - Z tranformer0
j1797.99 - j1.00
Z ground =
3
j1796.99
= pu Ω
3
= 598.99 pu Ω
0.48 kV 2
Z base = = 0.002304 Ω
100 MVA
Z generator = Z base × Z pu
= 0.002304 Ω × 598.99 pu Ω
= j1.38 Ω
PTW allows you to enter grounding reactors to one decimal; therefore PTW rounds 1.38
Ω to 1.4 Ω. Thus, the resulting single-line-to-ground fault current at Bus 3 is slightly less
than 200 A (197.71 A), as shown in Figure 4-2.
X1 1.0000 pu UTILITY
Xo 1.3333 pu
B1
X1 1.0000 pu C1
Xo 1.0000 pu
B2
X1 1.0000 pu
Xo 1.0000 pu T1
1.4 Ω
40094.23 A 3 Ph
B3 197.19 A SLG
Figure 4-2
The three-phase and single-line-to-ground hand calculations match PTW’s results. PTW
automatically takes into account the multiplying of grounding reactance by 3.
The grounding impedance is entered in ohms: PTW automatically places it on a per unit
base impedance on the nominal system voltage on the transformer’s grounded side, in this
case 480 V. Likewise, if the transformer is connected wye-grounded-delta, the grounding
impedance is entered in ohms; however, all per unit calculations would be based on the
13.8 kV nominal system voltage. PTW warns you in the Study Messages dialog box if a
grounding impedance is entered on an unacceptable connection (a grounding reactor
placed on a delta-transformer connection). Also, PTW allows two grounding reactors for
the wye-grounded wye-grounded transformer connection. Each grounding impedance is
converted to its respective per unit impedance value based on the bus nominal system
voltage on each side of the transformer.
3/26/2006
Short Circuit Study DAPPER 4-27
UTILITY
X1 0.4183 pu B1
Xo 0.1673 pu
C1
X1 1.000 pu B2
Xo 1.000 pu
X1 1.000 pu
Xo 1.000 pu T1
Thevenin X1 2.4184 pu
Thevenin Xo 2.1673 pu
B3 51519.40 A SLG
Figure 4-3
On a 100 MVA base, the three-phase short circuit capability expressed in per unit ohms is:
100,000 kVA
Z utility =
239,023 kVA
= j0.4184 pu Ω
3
Z0 = − Z1 − Z 2
Islg
In order to determine the single-line impedance, you must first express the current as a per
unit value.
Z0 =
3
- j2.9878
b
− j0.4184 + j0.4184 g
= j0.1673 pu Ω
If the fault occurs at Bus 3 and the transformer connection is wye-grounded wye-
grounded, then the zero-sequence impedance is the series of the transformer, cable and
utility zero-sequence impedances:
If the driving point voltage is 1 pu, the single-line-to-ground fault current at Bus 3 is:
3 × 1 pu V
Zslg =
Z1 + Z 2 + Z 0
3 × 1 pu V
=
j2.418 + j2.418 + j2.1673 per Ω
= - j0.4284 pu A
In amperes:
Islg = I pu × I base
Islg = - j0.4284 × 120,281.3 A
= j51,524.9 A
This 51,524.9 A is close to the 51,519.40 A predicted by PTW in Figure 4-3. The slight
difference between solutions is because the hand calculations ignored resistance.
3/26/2006
Short Circuit Study DAPPER 4-29
GENERATOR
X pos 1.0000 pu
X neg 0.8000 pu
B1 X zero 0.5000 pu
X1 1.0000 pu
Xo 1.0000 pu C1
B2
X1 1.0000 pu T1
Xo 1.0000 pu 40093.79 A 3 Ph
53065.31 A SLG
Thevenin X1 3.0000 pu
Thevenin X2 2.8000 pu
B3 Thevenin Xo 1.000 pu
Figure 4-4
1
Ik = pu A
3.0000
= - j0.3333 pu
I base = 120,281.3 A
I3Φ = 0.3333 pu A × 120,281.3 A
= - j40,093.77 A
Once again the difference between the hand calculated 40,093.77 A and the PTW
calculated 40,093.79 A is that the hand calculation ignored resistance.
==============================================================================
The positive-, negative-, and zero-sequence impedance values are reported, and the total
of the three impedances is 0.002 + j6.8 pu Ω. The fault point X/R ratio is 3400, or as
reported in PTW, an infinite X/R ratio. Clearly, the generator negative-sequence
impedance is used to calculate the Thevenin equivalent impedance at the fault point. The
Thevenin equivalent zero-sequence impedance at Bus 3 is defined as only the impedance
of the wye-grounded side of the transformer, as was the case in Section 4.4.1.
GENERATOR
X" X1 1.0000 pu
X" X2 0.8000 pu
B1 X" Xo 0.5000 pu
X1 1.0000 pu
Xo 1.0000 pu C1
B2
X1 1.0000 pu
Xo 1.0000 pu T1
B3
X1 1.0000 pu C2
Xo 1.0000 pu 150,351.94 A 3 Ph
B4 181,177.31 A SLG
Thevenin X1 0.8000 pu
Thevenin X2 0.7917 pu
Thevenin Xo 0.4000 pu
MOTOR
Figure 4-5
Z1 =
b j1.0 + j1.0 + j1.0 + j1.0g × j1.0
j1.0 + j1.0 + j1.0 + j1.0 + j1.0
-4.0
= pu Ω
j5.0
= j0.8 pu Ω
The zero-sequence impedance at Bus 4 is the sum of the transformer T1 and cable C2
impedances in parallel with the motor’s zero-sequence impedance:
3/26/2006
Short Circuit Study DAPPER 4-31
Z0 =
b j1.0 + j1.0g × j0.5
j1.0 + j1.0 + j0.5
- j1.0
= pu Ω
j2.5
= j0.4 pu Ω
The Thevenin equivalent positive- and zero-sequence impedances predicted by PTW
match the above hand calculations.
Note that the base current in this part of the system is 120,281.3 A; therefore the
calculated three-phase and single-line-to-ground fault current at Bus 4 is 150,352 A and
181,177 A, respectively.
The Study is conducted with the Study Setup defined to fault a single bus (Bus 4), and all
the Bus Voltages and Branch Currents for a fault at Bus 4 are selected.
Using the datablock formats, the branch current flows can be displayed on the one-line
diagram in Figure 4-6.
GENERATOR
1045.94 A
B1
1045.94 A
C1
B2
1045.94 A
T1
B3
30,070.63 A C2
B4
150,351.94 A 3 Ph
MOTOR
Figure 4-6
The single-line-to-ground Short Circuit Study report, for a fault at Bus 4 is shown:
FAULT TYPE: SLG
MODEL INDUCTION MOTOR CONTRIBUTION: YES
MODEL TRANSFORMER TAPS: YES
MODEL TRANSFORMER PHASE SHIFT: YES
==============================================================================
The single-line-to-ground report shows that the voltage on Phase A of the faulted bus is 0
pu V, but the voltage on Phases B and C are 0.9 pu V. The phase current on phase A from
the Utility is 3,6739 A and the motor contribution is 144,438 A. The total fault current
into Bus 4 is therefore the sum of these two currents into the bus, or 181,177 A. Because
the synchronous motor stator windings are connected wye-grounded configuration at Bus
4, there are currents flowing in all three phases.
You can run the same Study with a short circuit at Bus 4 again; however this time the
Study Setup has been modified to ignore motor contributions.
3/26/2006
Short Circuit Study DAPPER 4-33
***************** F A U L T A N A L Y S I S R E P O R T ****************
*****************************************************************************
*****************************************************************************
On the branch from Bus 3 to Bus 4 the positive-, negative-, and zero-sequence currents are
equal in magnitude and angle. The Phase A current is the sum of these three sequence
values, or 36,821 A. Because the transformer is delta connected to the primary
connection, there is no zero-sequence current flow on the 13.8 kV side of the system.
In each of the motor branches, the total motor load is 100 kVA. In the branch from Bus 2
to Bus 3, motor M1 is rated 100 kVA, and its associated X ′′d is 0.17 pu Ω on its own base
of 100 kVA and 480 V. In the second branch, motor M2 is modeled as four individual 25
kVA motors, with each of the four motors’ X ′′d equal to 0.17 pu Ω on its base of 25 kVA
and 480 V. Motor M3 is also modeled as four 25 kVA motors, but its ANSI contribution
is entered as 0.68 pu Ω (4 × 0.17 pu Ω) on a 100 kVA base at 480 V. Finally, the fourth
branch is nearly identical to the first branch; it is a single 100 kVA motor on the bus.
However, note that motor M4 is rated as 0.17 pu Ω at 440 V, operating on a system at 480
V.
UTILITY
22,768.38 A
B1
FEEDER
22,768.35 A
B2
C1 C2 C3 C4
24,686.32 A 698.55 A 698.55 A 698.55 A 835.20 A
B3 B4 B5 B6
M1 M2 M3 M4
Size 100.0 kVA Size 25.0 kVA Size 25.0 kVA Size 100.0 kVA
Xd" 0.1700 pu Xd" 0.1700 pu Xd" 0.6800 pu Xd" 0.1700 pu
No. Mtrs 1 No. Mtrs 4 No. Mtrs 4 No. Mtrs 1
100 Mtr kVA Base 25 Mtr kVA Base 100 Mtr kVA Base 100 Mtr kVA Base
Figure 4-7
It is important to note that the fault current contributions from the first three branches into
the faulted bus are identical. Because each of these cases has 100 kVA of connected
motor load in the branch, the motor fault duty contribution is identical. (Be aware that
when you enter the data for motors M1 and M2, you need to enter only the Number of
Motors and the motor Rated Size in the first subview of the Component Editor.) For both
motors, the motor base kVA is the same value as the rated size. PTW correctly models the
total Thevenin equivalent subtransient reactance for both cases; for M1 it models the one
motor as a single motor load object and for M2 it models the four motors as a single motor
load object.
Modeling motor M3 requires further explanation. The motor rated size is 25 kVA and
there are four motors modeled in the single motor load object. However, when the data
was entered in the ANSI Contribution subview, the motor contribution was lumped as 100
kVA. For PTW to correctly calculate the lumped impedance of these four 25 kVA
motors, the motor X ′′d must be multiplied by four and the product entered in the X ′′d field.
This is noted on the datablock below motor M3. If the motor data for M3 is entered
correctly, then the results for motors M1, M2 and M3 will be identical.
In the last branch from Bus 2 to Bus 4, a single 100 kVA motor is modeled but the rated
voltage of the motor is 440 V. If the motor is rated 0.17 pu Ω on its own base of 100 kVA
and 440 V, then its impedance on the system base 480 V is:
X ′′d = X d motor
FG kV IJ FG kVA IJ
motor
2
base
H kV K H kVA K
base motor
Substituting:
This fault duty contribution is limited by the impedance of the 50 ft of cable from Bus 2 to
Bus 6. The cable is #2 AWG THHN with a copper conductor in non-metallic conduct
3/26/2006
Short Circuit Study DAPPER 4-35
and has a published impedance of 0.202 + j0.0467 Ω per 1000 ft. Therefore, on a 100
kVA base (machine base) the cable impedance is:
FG 0.202 + j0.0467 Ω IJ 50 ft
Z cable =
H 1000 ft K
= 0.0101+ j0.002335 Ω
kV base2
Z base =
MVA base
0.482
=
0.100
= 2.304 Ω
Therefore, the cable impedance on the system base of 100 kVA is:
b g b
Z branch = 0.00438 + j0.000998 + 0.0 + j0143
. gpu Ω
= 0.00438 + j0.14385
= 0.1439 pu Ω
V
Isc =
Z
FG 1 IJ pu Ω
=
H 0.1439 K
= 6.949 pu Ω
100 kVA
I base =
1.732 × 0.48 kV
= 120.28 A
Therefore the fault current contribution for Motor 4 is:
Case 1
The one-line diagram in Figure 4-8 has three-phase transformer rated voltages that match
the bus nominal system voltages, and there are no taps. The transformer reactance is rated
6% on a base of 13.8 kV and 10,000 kVA. PTW places all per unit values on a 100 MVA
system base.
GENERATOR
X1 0.2000 pu
Bus System Nominal 13,800.0 V
B1 Pre Fault Driving Point Voltage 1.00 pu V
Bus Fault Current 20,918.49 A
Pri Rated Voltage 13,800.0 V T1
Sec Rated Voltage 4160.0 V
Leakage Impedance 0.6000 pu
Pri Tap 0.00 %
Sec Tap 0.00 %
Bus System Nominal 4160.0 V
B2 Pre Fault Driving Point Voltage 1.00 pu V
Bus Fault Current 17,348.27 A
Figure 4-8
The Generator equivalent impedance is j0.2 pu and the transformer per unit impedance is
j0.6 pu. The total Thevenin equivalent impedance at Bus 2 is the sum for the generator
and transformer impedances, or j0.8 pu. Therefore the three-phase fault current is:
1
Isc = pu A
j0.8
= - j1.25 pu A
However the base current at 4.16 kV is:
3/26/2006
Short Circuit Study DAPPER 4-37
100,000 kVA
I base =
3 × 4.16 kV
= 13,878.6 A
Isc = I base × I pu A
= 13,878.6 A × 1.25 pu A
= - j17,348.27 A
Case 2
You can substitute a transformer rated 13.2 kV - 3.979 kV, as shown in Figure 4-9. If the
generator exciter is set to produce 13.8 kV at the transformer rated 13.2 kV bus, then the
transformer on its low voltage side will produce 4.16 kV, which is greater than 3.979 kV.
The transformer turns ratio is 3.317 and the ratio of nominal system voltages from buses
B1 to B2 is also 3.317.
GENERATOR
X1 0.2000 pu Bus System Nominal 13,800.0 V
B1 Pre Fault Driving Point Voltage 1.00 pu V
Bus Fault Current 20,918.49 A
Pri Rated Voltage 13,200.0 V T1
Sec Rated Voltage 3979.0 V
Leakage Impedance 0.6000 pu
Pri Tap 0.00 %
Sec Tap 0.00 %
Bus System Nominal 4160.0 V
B2 Pre Fault Driving Point Voltage 1.00 pu V
Bus Fault Current 18,531.12 A
Figure 4-9
The transformer is 6% on its own base; however this value must be modified by the
transformer voltage to nominal system voltage ratio squared. The system base is 100
MVA. Substituting:
FG kV IJ F kV I2
H kV K GH kV JK
given
Z new = Z given × new
new given
= j0.06 pu × G
F 13.2 kV IJ FG 100,000 kVA IJ
2
The Thevenin equivalent impedance at Bus 2 is the sum of the generator and transformer
impedance as shown:
Z = j0.2 + j0.54896 pu Ω
= j0.74896 pu Ω
1.0 pu V
Isc =
j0.74896 pu Ω
= - j1.335 pu A
Remembering that Ibase is 13,878.6 A for a system base of 4160 V, the fault current at Bus
2 is:
Case 3
You can also substitute a transformer rated 13.2 kV - 4.16 kV, as shown in Figure 4-10.
Since the generator produces 13.8 kV without a primary tap on the transformer, the
secondary voltage is 4.35 kV. To limit the secondary side voltage, the transformer is
tapped at 13.8 kV. This is applied in PTW as a +4.54% primary tap. A positive primary
transformer tap reduces the secondary voltage.
GENERATOR
X1 0.2000 pu
Bus System Nominal 13,800.0 V
B1 Pre Fault Driving Point Voltage 1.00 pu
Bus Fault Current 20,918.49 A
Pri Rated Voltage 13,200.0 V
T1
Sec Rated Voltage 4160.0 V
Leakage Impedance 0.6000 pu
Pri Tap 4.54 %
Sec Tap 0.00 %
Bus System Nominal 4160.0 V
B2 Pre Fault Driving Point Voltage 1.00 pu
Bus Fault Current 17,348.73 A
Figure 4-10
It should be noted that the combination of the lower transformer primary voltage rating
and the positive tap setting work together to maintain the system voltage at Bus 2 at 4.16
kV. While the lower voltage transformer increases the fault current (Figure 4-9), adding
the positive tap value reduces the fault current. The total fault current at Bus 2 is
identical to that in Figure 4-8, or 17,348 A.
3/26/2006
Short Circuit Study DAPPER 4-39
Case 4
A 13.8 kV-4.16 kV transformer is placed in a system with bus nominal voltages of 13.8 -
4.16 kV, as shown in Figure 4-11. However because of heavy loading, the transformer is
placed in service with a -2.5% primary tap. Under loaded conditions, the nominal system
voltage with the -2.5% primary tap is 4.16 kV; however under no-load conditions, the pre-
fault driving point voltage at Bus 2 is 1.0256 pu higher than the nominal system voltage.
GENERATOR
X1 0.2000 pu
Bus System Nominal 13,800.0 V
B1 Pre Fault Driving Point Voltage 1.00 pu
Bus Fault Current 20,918.49 A
Figure 4-11
F 1 IJ + j0.6 pu Ω
Z = j0.2 × G
2
H 1+ Tap K
F 1 IJ + j 0.6 pu Ω
= j0.2 × G
2
H 1- 0.025K
= j(0.2 × 1.0519) + j0.6 pu Ω
= j0.81034 pu Ω
1.0256 pu V
Isc = pu Ω
j0.81034
= - j1.26558 pu A
Remembering that the base current at 4160 V is 13878.6 A, then the fault current is:
Case 5
In this final case, the nominal system voltage at Bus 2 is set to 4.266 kV or 1.0256 higher
voltage than in Case 4, as shown in Figure 4-12.
GENERATOR
X1 0.2000 pu
Bus System Nominal 13,800.0 V
B1 Pre Fault Driving Point Voltage 1.00 pu V
Bus Fault Current 20,918.49 A
Pri Rated Voltage 13,800.0 V T1
Sec Rated Voltage 4160.0 V
Leakage Impedance 0.6000 pu
Pri Tap -2.50 %
Sec Tap 0.00 %
Bus System Nominal 4266.5 V
B2 Pre Fault Driving Point Voltage 1.00 pu V
Bus Fault Current 17,565.02 A
Figure 4-12
The fault current at Bus 2 remains 17,565 A. The pre-fault voltage is now 1.0 pu V. The
6% transformer reactance must be placed on the system base, which is 13.8 kV. With the
-2.5% primary tap, the Thevenin equivalent impedance at Bus 2 is:
Z = j0.2 + j0.06 ×
FG 13.455 kV IJ FG 100,000 kVA IJ
2
1.0 pu V
Isc =
j0.7704 pu A
= - j1.2980 pu A
The base current at this voltage is:
100,000 kVA
I base =
3 × 4.2665 kV
= 13532.2 A
Isc = I base × I pu A
= 13532.2 A × 1.2980 pu A
= - j17,565 A
Carefully study the differences between Cases 4 and 5. The same transformer with the
same ratings and taps is analyzed in the each case. The only difference is the system
voltage selected at the faulted bus. In both cases, the fault current is the same. The
impedances were calculated differently because the base voltages were different. The
fault current in both cases is the same.
3/26/2006
Short Circuit Study DAPPER 4-41
UTILITY
100.0 MVA 3 Ph
30.0 MVA SLG
B1 B4
4183.70 A 3 Ph 6609.78 A 3 Ph
3765.33 A SLG 8007.95 A SLG
C1
T2
B2
3803.54 A 3 Ph
3454.58 A SLG
T1
B3
6609.78 A 3 Ph
8007.95 A SLG
Figure 4-13
If the utility and cable impedance each are 1 pu, then the total Thevenin equivalent
positive-sequence impedance at Bus 3 and at Bus 4 is 3 pu.
Figure 4-14
The Transformer 2 is connected between Bus 2 and Bus 4, as shown in Figure 4-13.
Unlike Transformer 1, the Transformer 2 connections were changed in the Component
Editor, as shown following in Figure 4-15.
Figure 4-15
Thus, in Figure 4-13 the Node 2 (bottom) connection for Transformer 1 is Bus 3, and in
the Component Editor view shown in Figure 4-14, the Node 2 connection is wye-
grounded.
We know that the proper transformer connection for Transformer 2’s connection at Bus 4
is wye-grounded. Knowing that the Node 1 connection is always on the top of the symbol
when viewed on the one-line diagram, or as the primary connection when viewed in the
Component Editor, the connection must be set as wye-grounded. Likewise, the Node 2
(bottom) connection for Transformer 2 must be delta. Compare the connections and
transformer voltages in the two Component Editor screens shown in Figure 4-14 and
Figure 4-15.
3/26/2006
EDISON
UTILITY BUS
R1
CB1
TM -1
R2
CB2
TX A
003-HV SWGR
R8 R9 R10
R3 R6 R7
CB6
C4
C1 GEN 1 GEN 2 C3
C2 SYN A SYN B 007-TX E PRI
TX B PRI BUS 4
R4 R5 006-TX3 PRI TX E
TX B 005-TXD PRI
CB4 CB5 TX 6
BLDG 115 SERV
DS SWG1 BUS 8 TX D
F1
TX H C10 C11
C6
029-TX D SEC
C5
TX C PRI BUS 9 CMP CTR HVAC BUS CB12 026-TX G PRI 025-MTR 25
C13 C20
LVP1 LVP2 LVP3 C9 L1 M20 L5
M13 L2
C14 C16 C17 LVP4 LVP5
021-TX F PRI TX F
BUS 28 A BUS 28 B
BUS 15 BUS 16 BUS 17
022-DSB 2 MCP#28B-1 MCP#28B-2
MCC 15 - 1A PLN 16 H2A
PLN - 17 H1A
C15 C18
C12
MO/L#28B-1 MO/L#28B-2
MCCB1 MCCB2
023-MTR 23
The following figure shows a portion of the Plant project including Short Circuit Study
results.
C10 C11
F3
TX G
MO/L#25
LVP5
LVP4
BUS 28 B
18508.62 A 3 PH
15548.13 A SLG
MCP#28B-1 MCP#28B-2
BUS 28 A
20786.14 A 3 PH MO/L#28B-1 MO/L#28B-2
17923.31 A SLG
The Short Circuit Report includes all the pre-fault voltages and associated voltage angles,
given that some transformers within the system have voltage taps set. Some of the data
for the buses in the above one-line diagram are shown in the following report.
************* P R E - F A U L T V O L T A G E P R O F I L E **************
3/26/2006
Short Circuit Study DAPPER 4-45
The comprehensive Short Circuit Study (three-phase) Report for a short circuit at DSB 3
or Bus 27 is listed below.
***************** F A U L T A N A L Y S I S R E P O R T ****************
FAULT TYPE: 3PH
MODEL INDUCTION MOTOR CONTRIBUTION: YES
MODEL TRANSFORMER TAPS: YES
MODEL TRANSFORMER PHASE SHIFT: YES
==============================================================================
DSB 3 BUS 27 VOLTAGE BASE LL: 480.0 (VOLTS)
INI. SYM. RMS FAULT CURRENT: 24713.1 / -170. ( AMPS/DEG )
THEVENIN EQUIVALENT IMPEDANCE: 0.883 +j 5.176 (PU)
THEVENIN IMPEDANCE X/R RATIO: 5.865
The comprehensive Short Circuit Study (single-line-to-ground) Report for a short circuit
at DSB 3 or Bus 27 is listed below.
***************** F A U L T A N A L Y S I S R E P O R T ****************
FAULT TYPE: SLG
MODEL INDUCTION MOTOR CONTRIBUTION: YES
MODEL TRANSFORMER TAPS: YES
MODEL TRANSFORMER PHASE SHIFT: YES
==============================================================================
DSB 3 BUS 27 VOLTAGE BASE LL: 480.0 (VOLTS)
INI. SYM. RMS FAULT CURRENT: 23955.3 / -170. ( AMPS/DEG )
THEVENIN EQUIVALENT IMPEDANCE: 2.765 +j 16.015 (PU)
THEVENIN IMPEDANCE X/R RATIO: 5.791
SEQUENCE EQUIVALENT IMPEDANCE Z1: 0.883 +j 5.176 (PU)
Z2: 0.883 +j 5.176 (PU)
Z0: 1.000 +j 5.662 (PU)
3/26/2006
Bib A-1
A Bibliography
Anthony, Michael A. Electric Power System Protection and Coordination. New York:
McGraw-Hill, 1995.
Beeman, Donald, ed. Industrial Powers Systems Handbook. New York: McGraw-Hill,
1955.
Earley, Mark W., ed. National Electric Code Handbook. 7th ed.
Elgard, Olle I. Electric Energy Systems Theory: An Introduction. New York: McGraw-
Hill, 1971.
Fitzgerald, A.E., Charles Kingsley, Jr., and Alexander Kusko. Electric Machinery. 3rd ed.
New York: McGraw-Hill, 1971.
IEEE Brown Book: IEEE Std 399-1990. New York: IEEE, 1990.
IEEE Red Book: IEEE Std 141-1993. New York: IEEE, 1993.
National Electric Code, 1996 ed. Authored by Committee. Quincy, MA: National Fire
Protection Association, 1996.
Skilling, Hugh Hildreth. Electrical Engineering Circuits. 2nd ed. New York: John
Wiley & Sons, Inc., 1967.
Stagg, Glenn W., and Ahmed H. El-Abiad. Computer Methods in Power System Analysis.
New York: McGraw-Hill, 1968.
Stevenson, William D. Elements of Power System Analysis. 3rd ed. New York:
McGraw-Hill, 1975.
Stigant, S. Austin, and A.C. Franklin. The J & P Transformer Book. 10th ed. London:
Newnes-Butterworths, 1973.
Wagner, C. F., and R.D. Evans. Symmetrical Components. New York: McGraw-Hill,
1961.
3/26/2006
Index DAPPER i
Index
non-coincident demand, 1-12
Plant project, 1-20
A single phase non-motor loads in a panel schedule, 1-
15
load categories, 1-6
Admittance Matrix loads. See Loads
definition of, 4-2 looped systems, 1-2, 1-5
Ampacity, 2-3 methodology, 1-3
ANSI, 4-1 radial systems, 1-2
Asymmetrical Peak Fault Current. See Faults running the Study, 1-9
Asymmetrical rms Fault Current. See Faults service factor (SF), 1-9
special considerations, 1-11
B
Study options, 1-10
terms and concepts, 1-3
Demand Load Type. See Loads
Balanced Faults. See Faults Demand Load Value, 1-3
Design Load Value, 1-3
Diversity Factor, 1-4
D
Demand Factor, 1-3
F
Demand Load Categories, 1-6
Demand Load Library Fault Current. See Faults
and the Demand Load Study, 1-6 Faults
Demand Load Study balanced, 4-3
and the Demand Load Library, 1-6 definition of, 4-3
before running the Study, 1-6 Thevenin Equivalent Circuit, 4-3
error messages, 1-11 fault current
examples, 1-12 asymmetrical peak, 4-10
loads with different power factors, 1-17 asymmetrical rms, 4-11
motor design load, 1-13 interrupting, 4-9
motor starting, 1-18 momentary, 4-9
motors assigned to a motor control center, 1-14 steady state, 4-11
multiple loops in a system, 1-19 unbalanced, 4-5
multiple motors at a bus, 1-13 definition of, 4-3
multiple motors on a single motor component, 1-18 double line-to-ground, 4-7
I
Energy Audit types, 1-7
remaining motors design factor, 1-8, 1-10
Long Continuous Load Factor (LCL). See Loads
IEC, 4-1 Looped Systems, 1-2, 1-5, 1-19, 3-11
Impedance
equivalent, 3-4
grounding, 4-7
Interrupting Fault Current. See Faults
M
Methodology
K
Demand Load Study, 1-3, 1-6
Load Flow Study, 3-2
Short Circuit Study, 4-2
Kirchoff's Current Law, 3-3, 3-4, 4-3 Sizing Study, 2-3, 2-4
Momentary Fault Current. See Faults
Motor Loads. See Loads
Lead/Lag, 3-10
Line-to-Line Fault. See Faults
N
Load Categories, 1-7
Load Flow Study NEC, 1-2, 1-4, 1-5, 1-7, 1-9, 2-2, 2-3, 3-5
bus types, 3-3 Negative-Sequence Modeling. See Sequence Modeling
co-generation, 3-10 Net Branch Diversity, 1-4
definition of, 3-2 Non-Coincident Demand, 1-4
error messages, 3-12 Non-Motor Loads. See Loads
examples, 3-12 Norton Equivalent Circuit, 4-4
load specifications, 3-15 Norton Equivalent Diagram, 4-4
modeling transformer losses, 3-14
net branch diversity load, 3-17
Plant project, 3-19
voltage drop and power losses, 3-12
O
load types, 3-4 Off-Nominal Voltage Modeling. See Transformers
methodology, 3-2 Ohm's Law, 3-2, 4-3
running the Study, 3-7 Oil/Air Cooled Transformer, 2-4
solution process, 3-4 Oil/Air/Forced Air Transformer, 2-4
3/26/2006
Index DAPPER iii
R
cooling characteristics, 2-4
Slack Bus, 3-4
Steady State Fault Current. See Faults
Radial Systems, 1-2 Steady State Load Flow Equation. See Load Flow Study
Reactive Power, 3-10 Swing Bus, 3-4, 3-10
S T
Sequence Modeling Taps. See Transformer Taps
positive-, negative-, and zero-, 4-7 Thevenin Equivalent Circuit, 4-3
Service Factor (SF). See Demand Load Study Thevenin Equivalent Impedance, 4-3
Short Circuit Study. see also Faults Transformer Sizing. See Sizing Study
before running the Study, 4-15 Transformer Taps
definition of, 4-2 modeling in Load Flow Study, 3-4
error messages, 4-22 modeling in Short Circuit Study, 4-12
examples, 4-22 Transformers
fault currents on a radial unloaded feeder, 4-23 modeling in Load Flow Study, 3-4
fault duty contribution to a faulted bus, 4-33 off-nominal voltage modeling in Short Circuit Study, 4-
fault with a generator source with unequal positive-, 13
negative-, and zero-sequence reactances, 4-28 phase shift, 4-13
modeling transformer connections, 4-40
Plant project, 4-42
short circuit currents with a motor load at bus 4, 4-30
single-line-to-ground fault currents at the secondary
U
of a transformer with a grounding reactor, 4-25 Unbalanced Faults. See Faults
source sequence impedance, 4-26 Utility, 3-4
transformer off-nominal voltages and transformer
taps, 4-36
methodology, 4-2
running the Study, 4-15 V
Study options, 4-15
transformer taps Voltage
primary modeling, 4-12 voltage angle, 3-4
secondary modeling, 4-13 voltage magnitude, 3-4
transformers Voltage Angle, 3-6
off-nominal voltage modeling, 4-13 Voltage Drop, 3-5, 3-6
phase shift, 4-13
Single-Line-to-Ground Faults. See Faults
Sizing Study
before running the Study, 2-5
Z
3/26/2006