You are on page 1of 4

Form No.

INSPECTION AND TEST PLAN 017-F023-2667

Procurement and Construction of New LNG Jetty (Berth 4)


Project Name:
at Bintulu Port, Sarawak Project No.: 2667
Owner / Owner’s Rep.: Petronas LNG 9 Sdn Bhd / Konsultant SHC Sdn Bhd MLNG Doc. No.: N/A
Contractor: SYS – MCD Joint Venture PLNG9 Doc. No.: TRAIN9-P18B-SYMCD-QAC-ITP-0006
Construction Process: Statnamic Load Test Date: 24 June 2015 SMJV ITP No: 017 - W004 - 2667

LEGEND REFERENCE DOCUMENTS


1. Project Specifications Section 3 “Pile Installations”
Verification Activity
2. CEP 017-V004-2667 Statnamic Load Test
H – Hold Point - work shall not proceed past the Hold Point until
released by the organisation imposing the Hold Point. 3. 017-M003-2667 Quality Management Plan

W – Witness Point - an inspection point that may be witnessed by the


organisation imposing the Witness Point.

X – Inspection - formal inspection activity to be undertaken and


recorded.

S – Surveillance - an activity that is subject to ongoing monitoring.

R – Review - review of text reports/records or other evidence of APPROVAL / REVISION


compliance. Prepared Approved
Rev Date Details
Responsible Inspectorate (RI) (may be modified to meet site specific requirements) By By
MCD – McConnell Dowell C0 15/06/24 Issued for Approval ROC BMC
PM – Project Manager
CM – Construction Manager
DEM – Design / Engineering Manager
PE – Project Engineer
SE – Site Engineer
SUR - Surveyor
SQN – Subcontractor Quality Nominee
PQMR – Project Quality Management Representative
CLIENT– Owner / Owner’s Representative

017-F023-2667 Rev0 24 June 2015 Page 1 of 4


Form No.
INSPECTION AND TEST PLAN 017-F023-2667

Construction Proj. No.: TRAIN9-P18B-SYMCD-QAC-ITP-0006


Statnamic Load Test
Process: ITP No.: 017 – W004 - 2667 Rev C0
Inspection / Test Verification By
Respon- Applicable
Item Basic Job Step Acceptance Criteria Standard Sub- Verifying Records
sibility Method Frequency SMJV Client
Con

1.0 Site Testing Personnel

As
Section 3 – Pile 017-F009-2667Vendor
1.1 Testing Operator Agency Lab. Tech. Approved Testing Agency Approval determined R R
Installation S3.8.5 Approval Request
by Owner

2.0 Statnamic Testing of Test Piles

Identified by the owner


Pile
All the necessary cables is selected
Preparation of pile for statnamic Method Statement 017-F002-2667 Request for
2.1 in place and secured Inspect for X X
testing ASTM D1143 Inspection Notice
statnamic
As per approved method testing
statement

Gravel structure base frame


Pile
position is in place and
selected
Setting up the gravel structure levelled Method Statement 017-F002-2667 Request for
2.2 Inspect for X X
base frame ASTM D1143 Inspection Notice
statnamic
Laser window is clearly
testing
visible from side window

017-F023-2667 Rev0 24 June 2015 Page 2 of 4


Form No.
INSPECTION AND TEST PLAN 017-F023-2667

Construction Proj. No.: TRAIN9-P18B-SYMCD-QAC-ITP-0006


Statnamic Load Test
Process: ITP No.: 017 – W004 - 2667 Rev C0
Inspection / Test Verification By
Respon- Applicable
Item Basic Job Step Acceptance Criteria Standard Sub- Verifying Records
sibility Method Frequency SMJV Client
Con

Fuel charge is properly


installed

Cylinder is clean, greased


and seal

Reaction masses is properly


placed onto the cylinder

Gravel structure bolts is Pile


secured, level selected
Final check prior to proceed to Method Statement 017-F002-2667 Request for
2.3 PE Inspect for X X
statnamic test ASTM D1143 Inspection Notice
Aggregates is level and statnamic
even testing

Data acquisition cable


connected and secured

Check input data, trigger


level is check, laser position
is ok, load cell reading is ok,
earth wire is connected

Tested to 200% of pile


design compression load as
PE / Third Section 3 – Pile As 017-F002-2667 Request for
follows:
2.4 Statnamic test Party Lab. Installation S3.8.2; Test determined X R Inspection Notice , Test
- 1100mm Dia. - 5000 KN
Tech. ASTM D1143 by Owner Report
- 800mm Dia. - 2500 KN
- 600mm Dia. - 1500 KN

017-F023-2667 Rev0 24 June 2015 Page 3 of 4


Form No.
INSPECTION AND TEST PLAN 017-F023-2667

Construction Proj. No.: TRAIN9-P18B-SYMCD-QAC-ITP-0006


Statnamic Load Test
Process: ITP No.: 017 – W004 - 2667 Rev C0
Inspection / Test Verification By
Respon- Applicable
Item Basic Job Step Acceptance Criteria Standard Sub- Verifying Records
sibility Method Frequency SMJV Client
Con

3.0 Quality Records

Statnamic tested pile driving Complete, properly signed Section 3 – Pile Statnamic
3.1 PE/ PQMR Visual R R Pile driving record forms
records are submitted off and submitted Installation S3.4.3 tested pile

Valid Calibration Certificate Calibration Prior to


3.2 Gauges Calibration PE Visual R R Calibration Certificate
is available Procedure proceed

Drawings showing actual


positions, inclination and
eccentricity at pile cut off
level

Off Center Deviation


Horizontal: ± 100mm all
Section 3 – Pile Statnamic As built drawing duly
3.3 Tested Pile As built drawings PE direction Visual R
Installation S3.7.4 tested pile endorsed by Surveyor
Verticality Tolerances ≤1:50

Rake Tolerances ≤ 1:25

Pile Head Elevation : Equal


or above Cut of Level

017-F023-2667 Rev0 24 June 2015 Page 4 of 4

You might also like