Aircon Installation Works

Project Timeline: October 21, 2019 to October 30, 2019 (from 7:00pm to 2:00am)

Resume of work: November 4, 2019 to November 6, 2019 (from 7:00pm to 2:00am)

Completion Date: Turnover will defend on the availability of permanent supply.

Activity: Installation of Chilled Water Aircon

ACTIVITY HAZARDS/IMPACT of the CONTROL MEASURES to


PROCEDURE/STEP PROCEDURE implement for the
HAZARD
Using of ladder. Slip hazards. Make sure that the ladder
is not broken.
Select proper ladder.
Lifting of Unit Trip or fall of the unit. Make sure that they have
the right number of
helper.
Use proper lifting
techniques.
Use of electric like welding Burns and other injuries Keep a fire extinguisher at
machine. from welding. welding site.
Use of hand tools. Bodily injury. Follow safety standard for
operating power hand
tools.

Ellan E. Aguilar
IG-9 Head Poweraire Installer Group