Determine the actual gas migration rate

Post Views: 1,179

You have learned how to estimate the gas migration rate. Today, I would like to show
you how to figure out the actual gas migration rate after you shut the well in due
to well control.

The concept of this topic is to measure the pressure increment in a hour and divided by
gradient of mud weight that you have in the well.

Let’s look at the formula:

Actual gas migration rate = Increase in casing pressure ÷ Pressure gradient of


drilling mud
Where;

Actual gas migration rate in ft/hr


Increase in casing pressure in psi/hr
Pressure gradient of drilling mud in psi/ft
Let’s try to determine the actual gas migration rate with this following
information:
Initial shut in casing pressure = 450 psi

Shut in casing pressure after half an hour shut in = 650 psi

Current mud weight = 12.5 ppg

Solution:
Pressure increase in half an hour = 650 – 450 = 200 psi

It means that pressure increase in an hour is 400 psi. Therefore, you get the increase in
casing pressure = 400 psi/hr.

You need to calculate your mud weight in to ppg with this formula:

Mud gradient = 0.052 x mud weight

Mud gradient = 0.052 x 12.5 = 0.65 psi/ft

Note: you can read more about it via this link: how to convert mud weight to pressure
gradient.
Actual gas migration rate = 400 (psi/hr) ÷ 0.65 (psi/ft) = 616 ft/hr