Project Hotel Benzz Park, Chennai

Owner Sree Raja Rajeshwari Hotels (Chennai) Pvt. Ltd.


Subject Design of Pile (17 length)

STRUCTURAL DETAILS:
Pile Diameter, D = 450 mm
Cross-sectional area , Ag = 1590.43 cm2
Vertical capacity of pile = 97.3 MT
Lateral capacity of pile = 1.5 MT
Pullout capacity of pile = 28.5 MT
Grade of Concrete, fck = 30 N/mm2
Grade of Steel, fy = 500 N/mm2
Cover to main rebar, d' = 75 mm
Partial safety factor on load = 1.5
SPT N value at top layer, N = 16 blows
Unconfined compressive strength, qc = 96 kN/m2

Depth of Fixity (IS:2911 (Part-1/Sec-2)-2010)

Soil type = Clayey Soil


Stiffness factor R in m = (E*I/K*B)0.25
Where
Young's modulus of pile material, E = 2.74E+07 kN/m2
Moment of inertia of the pile cross section, I = 2.01E-03 m4
Width of the pile shaft,B = 0.45 m
K= (k1*0.3)/(1.5*B)
Modulus of subgrade reaction for cohesive soil,
k = 17.28 MN/m3
K = 7680 kN/m2
Stiffness factor R 2.00 m
Cantilever length above ground to the point of
load application, L1 = 0m
For L1/R = 0, LF = 5.5 R
Depth of fixity, LF = 10.99 m
Reduction factor, m = 0.7 for Fixed head pile
Deflection for Fixed head pile
Pile head deflection for fixed head pile, y = (H(L1+Lf)3/12EI) × 103
Youngs modulus of pile material (concrete) = 27386128 kPa
Moment of inertia of pile = 2.01E-03 m4
Deflection of pile, y = 30.1 mm

Design for compression with bending


Factored Vertical load, Pu = 1459.5 kN
Factored Lateral load, Hu = 22.5 kN
Maximum moment of the pile is given by M = mH(L1+LF)/2
Maximum moment, M = 5.77 T-m
Pu/(fck*D^2) = 0.24 =>
Mu/(fck*D^3) = 0.03
p = 0.4 %
Required Ast = 6.36 cm2

Design for tension with Bending


Factored Lateral load, Hu = 22.5 kN
Maximum moment, M = 57.71 kNm
Effective Cover = 85 mm

Factored Uplift load (Tension),Tu = 427.5 kN


Equivalent side of a square, b = 0.40 m
Mu/(fck*b^3) = 0.045
Tu/(fck*b^2) = 0.090
p= 1.5 %
Required Ast = 23.86 cm2
Provide 8 bars of 20
Ast provided = 25.13 .

Lateral Ties

HELICALS
Provide 10 mm @150 C/C
(Bored Cast-in-situ Piles)

As per KBM soil report

(IS 2911 Part1/Sec2:2010, Table4)

(IS 2911 Part1/Sec2:2010, Fig 5)

d'/D = 0.19
(Taking into account min. eccentricity)
p/fck = 0 (Chart 60, SP-16)

d'/D = 0.21

p/fck= 0.05 (Chart 85, SP-16)

mm dia tor steel


OK
Project Hotel Benzz Park, Chennai
Owner Sree Raja Rajeshwari Hotels (Chennai) Pvt. Ltd.
Subject Design of Pile (22m length)

STRUCTURAL DETAILS:
Pile Diameter, D = 450 mm
Cross-sectional area , Ag = 1590.43 cm2
Vertical capacity of pile = 112.3 MT
Lateral capacity of pile = 1.5 MT
Pullout capacity of pile = 41.7 MT
Grade of Concrete, fck = 30 N/mm2
Grade of Steel, fy = 500 N/mm2
Cover to main rebar, d' = 75 mm
Partial safety factor on load = 1.5
SPT N value at top layer, N = 16 blows
Unconfined compressive strength, qc = 96 kN/m2

Depth of Fixity (IS:2911 (Part-1/Sec-2)-2010)

Soil type = Clayey Soil


Stiffness factor R in m = (E*I/K*B)0.25
Where
Young's modulus of pile material, E = 2.74E+07 kN/m2
Moment of inertia of the pile cross section, I = 2.01E-03 m4
Width of the pile shaft,B = 0.45 m
K= (k1*0.3)/(1.5*B)
Modulus of subgrade reaction for cohesive soil,
k = 17.28 MN/m3
K = 7680 kN/m2
Stiffness factor R 2.00 m
Cantilever length above ground to the point of
load application, L1 = 0m
For L1/R = 0, LF = 5.5 R
Depth of fixity, LF = 10.99 m
Reduction factor, m = 0.7 for fixed head pile
Deflection for Fixed head pile
Pile head deflection for fixed head pile, y = (H(L1+Lf)3/12EI) × 103
Youngs modulus of pile material (concrete) = 27386128 kPa
Moment of inertia of pile = 2.01E-03 m4
Deflection of pile, y = 30.1 mm

Design for compression with bending


Factored Vertical load, Pu = 1684.5 kN
Factored Lateral load, Hu = 22.5 kN
Maximum moment of the pile is given by M = mH(L1+LF)/2
Maximum moment, M = 5.77 T-m
Pu/(fck*D^2) = 0.28 =>
Mu/(fck*D^3) = 0.03
p = 0.4 %
Required Ast = 6.36 cm2

Design for tension with Bending


Factored Lateral load, Hu = 22.5 kN
Maximum moment, M = 57.71 kNm
Effective Cover = 85 mm

Factored Uplift load (Tension),Tu = 625.5 kN


Equivalent side of a square, b = 0.40 m
Mu/(fck*b^3) = 0.045
Tu/(fck*b^2) = 0.131
p= 1.5 %
Required Ast = 23.86 cm2
Provide 8 bars of 20
Ast provided = 25.13 .

Lateral Ties

HELICALS
Provide 10 mm @150 C/C
(Bored Cast-in-situ Piles)

As per KBM soil report

(IS 2911 Part1/Sec2:2010, Table4)

(IS 2911 Part1/Sec2:2010, Fig 5)

d'/D = 0.19
(Taking into account min. eccentricity)
p/fck = 0 (Chart 60, SP-16)

d'/D = 0.21

p/fck= 0.05 (Chart 85, SP-16)

mm dia tor steel


OK