You are on page 1of 167

Seeh Al-Sarya Engineering LLC.

Line Walk Punch-List


CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1207897


12" OIL PRODUCTION HEADER
SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME NEW REHAM MANIFOLD TO SAQ
MANIFOLD (SAS 1261)

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints A

2 Hydro-test package A

3 The flange ratings are as per the ISO drawing. A

4 Bolt size identification and torquing(After final installtion) B

5 Saddles, shoes, shims, supports are installed / erected N/A

6 Barricade the Locations and restrict any unauthorized entry A


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are A


installed for hydro-test

8 Visual check of pipe Line Routing / Laying A

9 Provision of Launcher and Receiver in the position A

10 Calibration Certicates for the Gauges & Pressure recorder. A

11 Marker plate to be clamp for RDX1,2,3,4,5 and WDX B


1,Reham Manifold and Saqr Manifold.

Pipe is not rest on sleeper near


12 jt143,165,167,176,202,205,188,206,240A,285,286,298,315,3 B
81,420,476,483,522,525,526,610,653,673

13 Line alignment to be done from j130 to 132,212 to 215,291 to B


293,348 to 351,419 to 421,528 to 530,656 to 658

14 Extra pipes,scrap,bends and wooden pieces remove from B


line

15 Guide angle welding to be done for throughout line B

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QC Inspector Position QA/QC Engineer
Signature Signature
Date Date
017460

N HEADER FROM
OLD TO SAQR
1)

OXY QC
Signature
1196883 SWL-CA-2011-24000017460

1203745
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1210707


SAQAR WEST-04, 6 "
SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME WATERINJECTION LINE (SAS127
PART-03
SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints A

2 Hydro-test package A

3 The flange ratings are as per the ISO drawing. A

4 Bolt size identification and torquing(After final installtion) B

5 Saddles, shoes, shims, supports are installed / erected N/A

6 Barricade the Locations and restrict any unauthorized entry A


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are A


installed for hydro-test

8 Visual check of pipe Line Routing / Laying A

9 Provision of Launcher and Receiver in the position A

10 Calibration Certicates for the Gauges & Pressure recorder. A

11 Backfilling to be done for RDX5 B

12 Extra pipes and scrap pipes remove from line B

13 Pipe is not rest on sleeper near jt 388,425,426,427 B

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QC Inspector Position QA/QC Engineer
Signature Signature
Date Date
017460

NE (SAS1276)

OXY QC
Signature
1196883 SWL-CA-2011-24000017460

1203745
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1210707


SAQAR WEST-04, 6 "
SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME WATERINJECTION LINE (SAS127
PART-02
SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints A

2 Hydro-test package A

3 The flange ratings are as per the ISO drawing. A

4 Bolt size identification and torquing(After final installtion) B

5 Saddles, shoes, shims, supports are installed / erected N/A

6 Barricade the Locations and restrict any unauthorized entry A


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are A


installed for hydro-test

8 Visual check of pipe Line Routing / Laying A

9 Provision of Launcher and Receiver in the position A

10 Calibration Certicates for the Gauges & Pressure recorder. A

11 Backfilling to be done for RDX6 B

12 Extra pipes and scrap pipes remove from line B

13 Marker plate to be clamp for RDX6 B

14 Pipe is not rest on sleeper near jt 461,472,473 B

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QC Inspector Position QA/QC Engineer
Signature Signature
Date Date
017460

NE (SAS1276)

OXY QC
Signature
1196883 SWL-CA-2011-24000017460

1203745
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1210707


SAQAR WEST-04, 4 "
SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME WATERINJECTION LINE (SAS127
PART-01
SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints A

2 Hydro-test package A

3 The flange ratings are as per the ISO drawing. A

4 Bolt size identification and torquing(After final installtion) B

5 Saddles, shoes, shims, supports are installed / erected N/A

6 Barricade the Locations and restrict any unauthorized entry A


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are A


installed for hydro-test

8 Visual check of pipe Line Routing / Laying A

9 Provision of Launcher and Receiver in the position A

10 Calibration Certicates for the Gauges & Pressure recorder. A

11 Backfilling to be done for RDX 1 B

12 Extra pipes and scrap pipes remove from line B

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QC Inspector Position QA/QC Engineer
Signature Signature
Date Date
017460

NE (SAS1276)

OXY QC
Signature
1196883 SWL-CA-2011-24000017460

1203745
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1211154


DHIYA NORTH-02, 4 " FLOWLIN
SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME (SAS1275)

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints A

2 Hydro-test package A

3 The flange ratings are as per the ISO drawing. A

4 Bolt size identification and torquing(After final installtion) B

5 Saddles, shoes, shims, supports are installed / erected N/A

6 Barricade the Locations and restrict any unauthorized entry A


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are A


installed for hydro-test

8 Visual check of pipe Line Routing / Laying A

9 Provision of Launcher and Receiver in the position A

10 Calibration Certicates for the Gauges & Pressure recorder. A

Marker plate to be provided on one side of RAMP-02,Marker


11 plates on existing line including RDX to be replaced with B
newone.

12 Paint touch up including Field joints to be done through out B


line(JT-50to52,JT-116to119,JT145to150)
General House Keeping including Pipe bundle/loose pipe
13 near JT:8,32,49,97,134,167,sleave pieces near JT:87A,187 B
and wooden skid near 69,83,213 and sleepers to be
removed near Well pad.
Sand dunes near JT:74, Between existing RAMP-02 and
14 EXIST.LOOP-04 & Between existing RDX-01 and A
EXIST.LOOP-02

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Mithun Thilakaraj Name: Mr.Sadiq hussain/Moinul Hassan
Position QC Inspector Position QA/QC Engineer
Signature Signature
Date Date
017460

" FLOWLINE

OXY QC
Signature
1196883 SWL-CA-2011-24000017460

1203745
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1204096

JALAL EAST-29, 4" WATERINJEC


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME LINE (SAS-1063)

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.

11 Joint coating to be done from J10 to BR15,20A TO


22,J73,74

12 Marker plate to be clamp near tie in side

13 Sleeper to be install from jt no BR74C TO BR 88

14 Extra pipes,sleeeper and wooden pieces remove from line

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

ATERINJECTION

OXY QC
Signature
SWL-CA-2011-24000017460
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1204096

JALAL EAST-29, 2" GAS LINE (SA


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME 1063)

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.

11 Sand dune to be remove from J27A to 28

12 Sleeper to be install from jt no 39 to 47

13 Backfilling to be done for RDX1

14 Marker plate to be clamp well pad,tie in and roadcrossing1

15 Extra pipes,sleeeper and wooden pieces remove from line

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

AS LINE (SAS-

OXY QC
Signature
SWL-CA-2011-24000017460
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1203680


REHAM-5, 2" GAS LINE AND TIE
SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME SPOOL AND 4 " TIE IN SPOOL(SA
1050)
SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.

11 Pipe is not rest on sleeper near jt 81,92,143,154

12 Backfilling to be done for wadi crossing and road crossing

13 Marker plate to be clamp well pad,tie in and roadcrossing

14 Extra pipes,sleeeper and wooden pieces remove from line

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

NE AND TIE IN
N SPOOL(SAS-

OXY QC
Signature
SWL-CA-2011-24000017460
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1203680

REHAM-5,4" FLOW LINE (PART


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME 1050

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.

11 Pipe is not rest on sleeper near jt no-1006,1018

12 Extra pipe,sleeper and wooden pieces remove from line

13 Marker plate to be Clamp for Manifoldside

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

LINE (PART6)SAS-

OXY QC
Signature
SWL-CA-2011-24000017460
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1203680

REHAM-5, 4" WATER INJECTION


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME (PART-4)SAS-1050

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.

11 Joint coating to be done for jt 985 to 990F,936 TO 946

12 Backfilling to be done for RDX-02

13 Marker plate to be Clamp for RDX2

14 Pipe is not rest on sleeper near jt 691,693,728,827,977A

15 Extra pipe,sleeper and wooden pieces from line

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

INJECTION LINE

OXY QC
Signature
SWL-CA-2011-24000017460
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1203680

REHAM-5, 4" WATER INJECTION


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME (PART-3)SAS-1050

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.

11 Joint coating to be done for jt BR349 to BR355

12 Backfilling to be done for RDX-01

13 Marker plate to be Clamp for RDX1

14 Pipe is not rest on sleeper near jt


581,628,669,414,423,417,360,674,667,615,579

15 Extra pipe,sleeper and wooden pieces from line

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

INJECTION LINE

OXY QC
Signature
SWL-CA-2011-24000017460
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1203680

REHAM-5, 4" FLOW LINE (PART


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME 1)SAS-1050

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

LINE (PART-

OXY QC
Signature
SWL-CA-2011-24000017460
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1202332

DHIYYA WEST -13, 6"WATER


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME INJECTION LINE (PART-5)SAS-1

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

"WATER
RT-5)SAS-1024

OXY QC
Signature
SWL-CA-2011-24000017460
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1202332

DHIYYA WEST -13, 6"WATER


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME INJECTION LINE (PART-4)SAS-1

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

"WATER
RT-4)SAS-1024

OXY QC
Signature
SWL-CA-2011-24000017460
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1202332

DHIYYA WEST -13, 6"WATER


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME INJECTION LINE (PART-1)SAS-1

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

"WATER
RT-1)SAS-1024

OXY QC
Signature
SWL-CA-2011-24000017460
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1202332

DHIYYA WEST -13, 6"WATER


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME INJECTION LINE (PART-3)SAS-1

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

"WATER
RT-3)SAS-1024

OXY QC
Signature
SWL-CA-2011-24000017460
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1202332

DHIYYA WEST -13,4 " WATER


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME INJECTION LINE FROM WELL PA
(SAS-1024)
SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

" WATER
M WELL PAD

OXY QC
Signature
SWL-CA-2011-24000017460
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1201710

NASIYAH FAR EAST 2(SAS 1017)


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME 4

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.


Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

(SAS 1017) PART

OXY QC
Signature
SWL-CA-2011-24000017460
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1201710

NASIYAH FAR EAST 2(SAS 1017)


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME 3

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

(SAS 1017) PART

OXY QC
Signature
SWL-CA-2011-24000017460
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1201710

NASIYAH FAR EAST 2(SAS 1017)


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME 2

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

(SAS 1017) PART

OXY QC
Signature
SWL-CA-2011-24000017460
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1201710

NASIYAH FAR EAST 2(SAS 1017) PA


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME 1

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized


entry at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure


recorder.

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Moinul Hassan/Sadiq hussain
Position QA/QC Engineer PositionQA/QC Engineer
Signature Signatur
Date Date
017460

SWL-CA-2011-24000017460

(SAS 1017) PART

OXY QC
Signature
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1204096

JALAL EAST-29, 4" WATERINJEC


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME LINE (SAS-1063)

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.

11 Joint coating to be done from J10 to BR15,20A TO


22,J73,74

12 Marker plate to be clamp near tie in side

13 Sleeper to be install from jt no BR74C TO BR 88

14 Extra pipes,sleeeper and wooden pieces remove from line

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain/Moinul Hassan
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

ATERINJECTION

OXY QC
Signature
SWL-CA-2011-24000017460
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1201658

TIE IN FROM EXISTING WADIASWA


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME NORTH-8 TO WADIASWAD
NORTHMANIFOLD(SAS 1013)
SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized


entry at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure


recorder.

11 Marker plate to clamp near RAMP-1,Tie in side and


Manifold side

12 Extra pipe and wooden pieces to be remove

13 Pipe is not rest sleeper near jt 393

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Moinul Hassan/Sadiq hussain
Position QA/QC Engineer PositionQA/QC Engineer
Signature Signatur
Date Date
017460

SWL-CA-2011-24000017460

G WADIASWAD
WAD
AS 1013)
OXY QC JADWAL 006 FLOWLINE ROAD CROSSING REPLACEMENT
Signature
TIE IN FROM EXISTING WADIASWAD NORTH-8 TO
WADIASWAD NORTH MANIFOLD
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1200326

SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME JADWAL 32,4 " FLOW LINE (PART -2

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized


entry at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure


recorder.

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Moinul Hassan/Sadiq hussain
Position QA/QC Engineer PositionQA/QC Engineer
Signature Signatur
Date Date
017460

SWL-CA-2011-24000017460

LINE (PART -2)

OXY QC JADWAL 006 FLOWLINE ROAD CROSSING REPLACEMENT


Signature
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1196355

SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME JALAL 51,4" FLOW LINE

Date SAS
Sl no# Description Category Status Closed CONSTRUCTIONSI
GNATURE

1 1/2" plug to be install in therdolet after hydrotest near man B

2 Sand duneto be remove from jt 99 to 105,jt 119 to 121,jt 135 to150, A

J222 TO 230,J233 TO J235

3 Marker plate to be provided near well pad area and B


Manifold

4 Pipe is not rest on sleeper near jt no 70A,91C,92 B

5 Jt 75 in sleeper to be move B

6 Near jt 37 pipe touch with existing line to be move B

7 Backfilling to be done near road croosing B

8 House keeping to be done B


Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By:
Name: Selva kumar
Position QA/QC Engineer
Signature
Date
00017460

SWL-CA-2011-24000017460

W LINE

SAS QC
Signature

Sand duneto be remove from jt 99 to 105,jt 119 to 121,jt 135 to150,j222 to j230,j233 to j235
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1196355

SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME JALAL 51,4" FLOW LINE

Date SAS
Sl no# Description Category Status Closed CONSTRUCTIONSI
GNATURE

1 1/2" plug to be install in therdolet after hydrotest B

2 Line to be straight from J12 to J15 B

3 Field joint paint touch up to be completed after hydrotest B

4 House keeping to be done B

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By:
Name: Selva kumar
Position QA/QC Engineer
Signature
Date
00017460

SWL-CA-2011-24000017460

W LINE

SAS QC
Signature
Seeh Al-Sarya Engineering LLC.
CHECK LIST FOR WATER INJECTION HOOK UP
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-240000174

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO.

SYSTEM WATER INJECTION HOOK UP PROJECT NAME

SAS SAS QC
Sl no# Description Checked ok CONSTRUCTION Signature
Signature

1 Valve installation and direction of flow as per


drawing(check valve)

2 Strainer installation and direction of flow as per


drawing

3 Flow meter installation and direction of flow

4 Flange rating & Gasket installation and position


as per drawing

5 Elbow &Choke valve position as per


drawing(Yes/No)
Choke valve insulation washer installation and
6
Lock nut

7 DBB valve handle sleeve is installed

8 Pipe support installation

9 Bolt torquing as per procedure

Prepared By:
Name: Selva kumar
Position QA/QC Engineer
Signature
Date
-2011-24000017460

REMARK
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1197835

SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME JALAL 36,HOOK UP

SAS QC
Sl no# Description Category Status Date Closed Signature

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.SADIQ HUSSAIN
Position QA/QC Engineer PositionQA/QC Engineer
Signature Signatur
Date Date
017460

SWL-CA-2011-24000017460

OXY QC
Signature
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1196355

SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME JALAL 51,2" GAS LINE

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized


entry at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure


recorder.

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Sadiq hussain
Position QA/QC Engineer PositionQA/QC Engineer
Signature Signatur
Date Date
017460

SWL-CA-2011-24000017460

OXY QC
Signature
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1140896

8",4",3",2" WATER DISPOSAL


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME LINE(DISCHARGE ) AREA 800,A
BARAKAH(OM-55060865)

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Mr.Selva kumar Name: Mr.MOINUL SYED
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

SPOSAL
REA 800,AL
0865)

OXY QC
Signature
SWL-CA-2011-24000017460

8" ,4",3",2" WATER DISPOSAL LINE(DISCHARGE) AREA 800,AL


BARAKAH

SALMA#10 WATER INJECTION EXTENSION LINE


Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1197531

SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME JALAL EAST-24,4" FLOW LINE

SAS QC
Sl no# Description Category Status Date Closed Signature

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Mr.Selva kumar Name: Mr.MOINUL SYED
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

OW LINE

OXY QC
Signature
SWL-CA-2011-24000017460

SALMA#10 WATER INJECTION EXTENSION LINE


Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1198481

BADAR 16 WATER INJECTION FL


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME LINE

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized entry


at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure recorder.

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Mr.Selva kumar Name: Mr.MOINUL SYED
Position QA/QC Engineer Position QA/QC Engineer
Signature Signature
Date Date
017460

JECTION FLOW

OXY QC
Signature
SWL-CA-2011-24000017460

1198481

SALMA#10 WATER INJECTION EXTENSION LINE


Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1164190

SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME MASROUQ FOREAST -01

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized


entry at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure


recorder.

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Saddiq hussain
Position QA/QC Engineer PositionQA/QC Engineer
Signature Signatur
Date Date
017460

SWL-CA-2011-24000017460

01

OXY QC
Signature
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1205403

JADWAL 35,4 " FLOWLINE AND 2" G


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME LINE (SAS 1101)

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized


entry at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure


recorder.

11 Marker plate to clamped near well padside and tie in side

12 Extra pipe and sleeper to be to be remove from line

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Mithun thilakraj Name: Mr.Moinul Hassan/Sadiq hussain
Position QC inspector PositionQA/QC Engineer
Signature Signatur
Date Date
017460

SWL-CA-2011-24000017460

LINE AND 2" GAS

OXY QC JADWAL 006 FLOWLINE ROAD CROSSING REPLACEMENT


Signature
TIE IN FROM EXISTING WADIASWAD NORTH-8 TO
WADIASWAD NORTH MANIFOLD
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1201212

10 SLOT SOUTH MANIFOLD(SAS


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME 1053A)

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized


entry at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure


recorder.

11 Slot 2,spl 2&slot 8,spl2&slot9 ,spl2 alignment to be done

12 After hydrotest 10 Nos ,4"600 # check valve to reinstalled


to valve direction

13 Test header -1,outside skid,PS-18,PS 19 to be install

14 Transportation coating damage Paint touch up to be done


for all manifold spools

15 15 Nos 2" 600" DBB to be install after hydrotest

16 Guide angle to be welded and shim plate to be provided


for slot2,spl1

17 Manifold number stencil to be displayed both side of


manifold

18 Manifold grating to clamped

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Moinul Hassan/Sadiq hussain
Position QA/QC Engineer PositionQA/QC Engineer
Signature Signatur
Date Date
017460

SWL-CA-2011-24000017460

IFOLD(SAS

OXY QC JADWAL 006 FLOWLINE ROAD CROSSING REPLACEMENT


Signature
TIE IN FROM EXISTING WADIASWAD NORTH-8 TO
WADIASWAD NORTH MANIFOLD
Seeh Al-Sarya Engineering LLC.
Line Walk Punch-List
CLIENT OCCIDENTAL OF OMAN INC. CONTRACT NO. SWL-CA-2011-24000017460

CONTRACTOR SEEH AL-SARYA ENGINEERING L.L.C PROJECT NO. 1202014

JABIAH SOUTH-3,4 " FLOW LINE (S


SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME 1073)

SAS QC
Sl no# Description Category Status Date Closed Signature

1 NDT completion of weld joints

2 Hydro-test package

3 The flange ratings are as per the ISO drawing.

4 Bolt size identification and torquing(After final installtion)

5 Saddles, shoes, shims, supports are installed / erected

6 Barricade the Locations and restrict any unauthorized


entry at the time of hydro-testing.

7 All temporary Supports, blind/caps/plugs/gaskets are


installed for hydro-test

8 Visual check of pipe Line Routing / Laying

9 Provision of Launcher and Receiver in the position

10 Calibration Certicates for the Gauges & Pressure


recorder.

11 All Coated pipe field joints painting to be done

12 Extra sleeeper to be to be remove from line

13 Pipe is not rest sleeper near jt 1167 to 1169

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: Selva kumar Name: Mr.Moinul Hassan/Sadiq hussain
Position QA/QC Engineer PositionQA/QC Engineer
Signature Signatur
Date Date
017460

SWL-CA-2011-24000017460

FLOW LINE (SAS

OXY QC JADWAL 006 FLOWLINE ROAD CROSSING REPLACEMENT


Signature
TIE IN FROM EXISTING WADIASWAD NORTH-8 TO
WADIASWAD NORTH MANIFOLD