KAJIMA CORPORATION

CEBU SOUTH COASTAL ROAD PROJECT


SEGMENT 3B-2SUBWAY (TUNNEL) SECTION

October 20, 2007

TO: MR. HIKONARI MAEDA


Project Manager

MR. MASATO KOBAYASHI


Deputy Project Manager

THRU: MR. MOTOHIDE TAKANO


Chief Construction Manager

Subject: EXPLAINATION TO KC-3B-2-RE-07-10-92 dated OCTOBER 17, 2007

Gentlemen:

This has reference to the memorandum dated October 17, 2007.

Regarding the aforementioned memo KC-3B-2-RE-07-10-92, I received yesterday


October 19, 2007, I submitted already a report addressed to the Project Manager thru Mr.
Levi Las Marias, the Safety/Security Officer, on October 18, 2007. (See attached copy)

I hope you consider this reply acceptable and satisfactory.

Respectfully Yours,

MARLITO L. PANIS
Assist. Site Engineer

Cc: Ma. Ellen R. Alcomendras


Personnel Manager