Professional Documents
Culture Documents
Abrille-Basketball and Pool
Abrille-Basketball and Pool
I. EARTHWORKS
1.0 Clearing and grubbing 1,763.00
2.0 Sub-grade preparation 1,763.00
B. ARCHITECTURAL WORKS
1.0 Floor finishes
1.1 Plain cement concrete finish 568.26
area 30.80 18.45 568.26 m²
1.2 #10 Pebble washout finish 25.60
area 2.00 8.00 1.60 25.60 m²
1.3 25mm thk Concrete topping 593.86
2.0 Wall finishes
2.1 20mm thk Plaster 30.02
area 2.00 8.30 1.15 19.09
2.00 8.30 0.30 4.98
4.00 1.75 0.85 5.95
30.02 m²
3.0 Painting works
3.1 Paint finish
a. Basketball goal 9.54
area 2.00 1.40 0.25 0.70
2.00 1.20 1.60 3.84
2.00 1.00 1.60 3.20
2.00 0.90 1.00 1.80
9.54 m²
b. 50mm wide Basketball court lines 206.73
c. Logo acrylic paint markings 1.00
area 3.14 1.83 1.83 10.52
2.00 0.60 10.80 12.96
23.48 m²
4.0 Miscellaneous items
4.1 1800 x 1200 x 12mm thk Fiberglass board in paint finish inc. framing 2.00
C. ELECTRICAL WORKS
1.0 Electrical fixtures
1.1 Lamp post 4.00
B. ARCHITECTURAL WORKS
1.0 Floor finishes
1.1 200 x 200mm Ceramic tiles 179.98
1.2 No.5 beige pebble washout with white cement 6.26
1.3 50mm thk Concrete topping 186.24
2.0 Wall finishes
2.1 200 x 200mm Ceramic tiles 68.15
area 56.79 1.20 68.15 m²
2.2 No.5 beige pebble washout with white cement 3.97
area 21.17 0.19 3.97 m²
2.3 50mm thk Plaster 68.15
3.0 Waterproofing works
3.1 Waterproofing membrane 270.02
area 179.98
56.79 1.20 68.15
21.89
270.02 m²
4.0 Miscellaneous items
4.1 38mmØ SS Handrail and ladder steps L=1355mm 2.00
4.2 38mmØ SS Handrail L=1595mm 1.00
C. ELECTRICAL WORKS
1.0 Electrical fixtures
1.1 Uplight 9.00
B. ARCHITECTURAL WORKS
1.0 Floor finishes
1.1 Stamp concrete 258.80
1.2 No.5 beige pebble washout with white cement 74.15
1.3 50mm thk Concrete topping 258.80
1.4 25mm thk Concrete topping 74.15
V. PUMP ROOM
A. STRUCTURAL WORKS
1.0 Structural works
1.1 Footing
a. Excavation 1.87
volume 8.00 0.60 0.60 0.65 1.87 m³
b. Disposal 1.87
c. 50mm thk Gravel bedding 0.14
volume 8.00 0.60 0.60 0.05 0.14 m³
d. Concrete, 3000psi 0.58
volume 8.00 0.60 0.60 0.20 0.58 m³
e. Rebars, grade 40 47.95
weight 6.00 9.00 0.89 47.95 kgs
f. Tiewires 0.96
1.2 Wall footing
a. Excavation 4.97
volume 19.12 0.40 0.65 4.97 m³
b. Disposal 4.97
c. 50mm thk Gravel bedding 0.38
volume 19.12 0.40 0.05 0.38 m³
d. Concrete, 3000psi 1.53
volume 19.12 0.40 0.20 1.53 m³
e. Rebars, grade 40 9.24
weight 2.00 7.50 0.62 9.24
6.00 6.00 0.62 22.18
1.00 12.00 0.62 7.39
7.00 6.00 0.62 25.87
64.68 kgs
f. Tiewires 0.18
1.3 Slab on fill
a. 50mm thk Gravel bedding 0.90
volume 2.50 2.50 0.05 0.31
2.00 1.05 3.22 0.05 0.34
2.00 1.39 1.78 0.05 0.25
0.90 m³
b. Concrete, 3000psi 1.79
volume 2.50 2.50 0.10 0.63
2.00 1.05 3.22 0.10 0.68
2.00 1.39 1.78 0.10 0.49
1.79 m³
c. Rebars, grade 40 42.50
weight 2.00 10.50 0.62 12.94
5.00 6.00 0.62 18.48
3.00 6.00 0.62 11.09
42.50 kgs
d. Tiewires 0.85
1.4 Column
a. Concrete, 3000psi 1.06
volume 4.00 0.30 0.15 3.35 0.60
4.00 0.30 0.15 2.55 0.46
1.06 m³
b. Formworks 21.24
area 4.00 0.90 3.35 12.06
4.00 0.90 2.55 9.18
21.24 m²
c. Rebars, grade 40 155.04
weight 8.00 7.50 0.89 53.28
8.00 12.00 0.62 59.14
8.00 6.00 0.89 42.62
155.04 kgs
d. Tiewires 3.10
1.5 Beam
a. Concrete, 3000psi 0.72
volume 19.12 0.15 0.25 0.72 m³
b. Formworks 9.56
area 2.00 19.12 0.25 9.56 m²
c. Rebars, grade 40 138.11
weight 7.00 7.50 0.89 46.62
5.00 6.00 0.89 26.64
2.00 10.50 0.89 18.65
10.00 7.50 0.62 46.20
138.11 kgs
d. Tiewires 2.76
2.0 Structural steel
2.1 100 x 50 x 15 x 2mm R-1 Rafter 10.08 43.33
weight 2.00 6.00 3.61 43.33 kgs
2.2 40 x 3mm Flat bar 10.08 11.30
weight 2.00 6.00 0.94 11.30 kgs
2.3 LC 75 x 50 x 15 x 1.5mm 40.50 101.38
weight 7.00 6.00 2.41 101.38 kgs
2.4 Miscellaneous items 1.00
3.0 Masonry
3.1 150mm thk CHB
a. 150mm thk CHB 52.58
area 10.00 3.35 33.50
9.12 2.55 23.26
2.50 1.05 2.63
D-1 -1.00 1.60 2.10 -3.36
opening -2.00 0.80 2.15 -3.44
52.58 m²
b. Rebars, grade 40 157.74
c. Tiewires 3.15
B. ARCHITECTURAL WORKS
1.0 Floor finishes
1.1 Plain cement finish 13.00
area 2.50 2.50 6.25
2.00 1.05 3.22 6.75
13.00 m²
1.2 200 x 200mm Ceramic tiles 4.95
area 2.00 1.39 1.78 4.95 m²
1.3 25mm thk Concrete topping 17.95
2.0 Exterior wall finishes
2.1 20mm thk Plaster 52.58
area 10.00 3.35 33.50
9.12 2.55 23.26
2.50 1.05 2.63
D-1 -1.00 1.60 2.10 -3.36
opening -2.00 0.80 2.15 -3.44
52.58 m²
2.2 Stone cladding 8.32
area 9.24 0.90 8.32 m²
2.3 200 x 50mm Concrete moulding 9.12
2.4 100 x 50mm Concrete moulding 12.36
3.0 Interior wall finishes
3.1 20mm thk Plaster 52.58
area 10.00 3.35 33.50
9.12 2.55 23.26
2.50 1.05 2.63
D-1 -1.00 1.60 2.10 -3.36
opening -2.00 0.80 2.15 -3.44
52.58 m²
3.2 10mm Grooves 11.08
3.3 200 x 200mm Ceramic tiles 11.08
area 11.08 1.00 11.08 m²
4.0 Doors
4.1 Double leaf steel louver door (1600 x 2100mm) 1.00
4.2 Steel door jamb 1.00
4.3 Ball bearing hinges 6.00
4.4 Lockset 1.00
4.5 Dummy trim 1.00
4.6 Flush bolt 2.00
5.0 Roof finishes
5.1 Concrete roof tiles with Ga.26 GI undersheeting 24.95
area 2.00 4.50 2.52 22.68 m²
5.2 12mm thk Ficem board fascia 19.08
6.0 Paint finishes
6.1 Textured paint finish
a. Exterior masonry wall 44.27
6.2 Paint finish
a. Interior masonry wall 41.50
b. 200 x 50mm Concrete moulding 9.12
c. 100 x 50mm Concrete moulding 12.36
d. 12mm thk Ficem board fascia 19.08
6.3 Epoxy paint finish
a. Steel door 6.72
area 2.00 1.60 2.10 6.72 m²
b. Steel jamb 5.80
C. ELECTRICAL WORKS
1.0 Electrical fixtures
1.1 Flourescent light 2.00
D. PLUMBING WORKS
1.0 Plumbing fixtures and accessories
1.1 Shower 2.00
1.2 Faucet 2.00
1.3 Floor drain 2.00
2.0 Drainage system
2.1 100mmØ x 3m uPVC Pipe 4.00 2.00
2.2 100mmØ uPVC Tee 2.00
2.3 Miscellaneous items 1.00
3.0 Water system
3.1 20mmØ x 3m uPVC Pipe 14.00 3.60 6.00
3.2 20mmØ uPVC Elbow 5.00
3.3 20mmØ uPVC Tee 4.00
3.4 Miscellaneous items 1.00
VI. PATHWAY
A. STRUCTURAL WORKS
1.0 Structural works
1.1 Slab on fill
a. 75mm thk Gravel bedding 5.48
volume 73.00 0.08 5.48 m³
b. Concrete, 3000psi 5.48
volume 73.00 0.08 5.48 m³
B. ARCHITECTURAL WORKS
1.0 Floor finishes
1.1 Stamp concrete 73.00
1.2 50mm thk Concrete topping 73.00
m²
m²
m³
m³
m³
m³
m²
kgs
kgs
m³
m²
m³
m²
kgs
46.00 30.80
77.00 18.45
kgs
m³
m³
m³
m³
m³
m²
kgs
30.00 8.30
12.00 1.75
160.00 0.60
56.00 3.00
kgs
m²
kgs
kgs
m²
m²
m²
m²
m²
lm
lot
nos
nos
m³
m³
m²
m³
m³
m²
kgs
620.00 1.50
620.00 0.75
20.00 12.00
kgs
lm
m³
kgs
66.00 12.00
340.00 1.20
kgs
m³
m³
m³
m³
m²
kgs
21.00 1.70
10.00 4.50
80.00 1.00
kgs
m²
kgs
kgs
m²
m²
m²
m²
m²
m²
m²
nos
nos
nos
m³
m³
m²
m²
m²
m²
m²
m³
m³
m³
m³
kgs
64.00 0.80
kgs
m³
m³
m³
m³
kgs
6.00 2.50
6.00 6.00
6.00 2.00
64.00 0.60
kgs
m³
m³
kgs
8.00 2.50
5.00 6.00
8.00 1.78
kgs
m³
m²
kgs
16.00 3.50
116.00 0.80
16.00 3.00
kgs
m³
m²
kgs
20.00 2.50
20.00 1.39
10.00 1.78
96.00 0.70
kgs
kgs
kgs
kgs
lot
m²
kgs
kgs
m²
m²
m²
m²
m²
lm
lm
m²
lm
m²
set
set
nos
set
set
nos
m² 10% waste
lm
m²
m²
lm
lm
lm
m²
lm
nos
nos
nos
nos
nos
nos
lot
nos
nos
nos
lot
m³
m³
m²
m²
nos wp
nos
lot
nos
lot
nos
nos
nos
lot
lot
Project : FUENTE DE VILLA ABRILLE (Phase 2)
Location : Fuente de Villa Abrille, Brgy. Matina, Davao City
Subject : BUDGETARY COST ESTIMATE
Date : December 11, 2006
I. EARTHWORKS
1.0 Clearing and grubbing 1,763.00 m² 3.75 6,611.25
2.0 Sub-grade preparation 1,763.00 m² 12.50 22,037.50
B. ARCHITECTURAL WORKS
1.0 Floor finishes
1.1 Plain cement finish 568.26 m² 100.00 56,826.00
1.2 #10 Pebble washout finish 25.60 m² 288.75 7,392.00
1.3 25mm thk Concrete topping 593.86 m² 221.25 131,391.53
2.0 Wall finishes
2.1 20mm thk Plaster 30.02 m² 196.25 5,891.43
3.0 Painting works
3.1 Paint finish
a. Basketball goal 9.54 m² 162.50 1,550.25
b. 50mm wide Basketball court lines 206.73 lm 31.26 6,462.50
c. Logo acrylic paint markings 1.00 lot 6,250.00 6,250.00
4.0 Miscellaneous items
Page 15 of 22
item description quantity unit unit cost total amount
4.1 1800 x 1200 x 12mm thk Fiberglass board in paint 2.00 nos 52,291.38 104,582.75
finish inc. framing
C. ELECTRICAL WORKS
1.0 Electrical fixtures
1.1 Lamp post 4.00 nos 29,167.23 116,668.90
B. ARCHITECTURAL WORKS
1.0 Floor finishes
1.1 200 x 200mm Ceramic tiles 179.98 m² 653.58 117,630.99
1.2 No.5 beige pebble washout with white cement 6.26 m² 288.75 1,807.58
1.3 50mm thk Concrete topping 186.24 m² 415.00 77,289.60
2.0 Wall finishes
2.1 200 x 200mm Ceramic tiles 68.15 m² 653.58 44,541.35
2.2 No.5 beige pebble washout with white cement 3.97 m² 288.75 1,146.34
2.3 50mm thk Plaster 68.15 m² 438.75 29,900.81
3.0 Waterproofing works
3.1 Waterproofing membrane 270.02 m² 625.00 168,762.50
4.0 Miscellaneous items
4.1 38mmØ SS Handrail and ladder steps L=1355mm 2.00 nos 15,000.00 30,000.00
4.2 38mmØ SS Handrail L=1595mm 1.00 nos 6,250.00 6,250.00
C. ELECTRICAL WORKS
1.0 Electrical fixtures
1.1 Uplight 9.00 nos 18,750.00 168,750.00
Page 16 of 22
item description quantity unit unit cost total amount
D. PLUMBING WORKS
1.0 Pipes and fittings 1.00 lot 150,000.00 150,000.00
2.0 Motor pump 1.00 lot 150,000.00 150,000.00
3.0 Filter tank 1.00 lot 37,500.00 37,500.00
B. ARCHITECTURAL WORKS
1.0 Floor finishes
1.1 Stamp concrete 258.80 m² 1,500.00 388,200.00
1.2 No.5 beige pebble washout with white cement 74.15 m² 288.75 21,410.81
1.3 50mm thk Concrete topping 258.80 m² 415.00 107,402.00
1.4 25mm thk Concrete topping 74.15 m² 221.25 16,405.69
V. PUMP ROOM
A. STRUCTURAL WORKS
1.0 Structural works
1.1 Footing
a. Excavation 1.87 m³ 225.00 420.75
b. Disposal 1.87 m³ 187.50 350.63
c. 50mm thk Gravel bedding 0.14 m³ 750.00 105.00
d. Concrete, 3000psi 0.58 m³ 3,750.00 2,175.00
e. Rebars, grade 40 47.95 kgs 42.50 2,037.88
f. Tiewires 0.96 kgs 50.00 48.00
1.2 Wall footing
a. Excavation 4.97 m³ 225.00 1,118.25
b. Disposal 4.97 m³ 187.50 931.88
c. 50mm thk Gravel bedding 0.38 m³ 750.00 285.00
d. Concrete, 3000psi 1.53 m³ 3,750.00 5,737.50
e. Rebars, grade 40 9.24 kgs 42.50 392.70
f. Tiewires 0.18 kgs 50.00 9.00
1.3 Slab on fill
a. 50mm thk Gravel bedding 0.90 m³ 750.00 675.00
b. Concrete, 3000psi 1.79 m³ 3,750.00 6,712.50
c. Rebars, grade 40 42.50 kgs 42.50 1,806.25
d. Tiewires 0.85 kgs 50.00 42.50
1.4 Column
a. Concrete, 3000psi 1.06 m³ 3,750.00 3,975.00
b. Formworks 21.24 m² 312.50 6,637.50
c. Rebars, grade 40 155.04 kgs 42.50 6,589.20
d. Tiewires 3.10 kgs 50.00 155.00
1.5 Beam
a. Concrete, 3000psi 0.72 m³ 3,750.00 2,700.00
Page 17 of 22
item description quantity unit unit cost total amount
B. ARCHITECTURAL WORKS
1.0 Floor finishes
1.1 Plain cement finish 6.25 m² 100.00 625.00
1.2 200 x 200mm Ceramic tiles 4.95 m² 653.58 3,235.21
1.3 Stamp concrete 6.75 m² 1,500.00 10,125.00
1.4 50mm thk Concrete topping 6.75 m² 415.00 2,801.25
1.5 25mm thk Concrete topping 11.20 m² 221.25 2,478.00
2.0 Exterior wall finishes
2.1 20mm thk Plaster 52.58 m² 196.25 10,318.83
2.2 Stone cladding 8.32 m² 2,625.00 21,840.00
2.3 200 x 50mm Concrete moulding 9.12 lm 343.75 3,135.00
2.4 100 x 50mm Concrete moulding 12.36 lm 221.25 2,734.65
3.0 Interior wall finishes
3.1 20mm thk Plaster 52.58 m² 196.25 10,318.83
3.2 10mm Grooves 11.08 lm 62.50 692.50
3.3 200 x 200mm Ceramic tiles 11.08 m² 653.58 7,241.65
4.0 Doors
4.1 Double leaf steel louver door (1600 x 2100mm) 1.00 set 15,000.00 15,000.00
4.2 Steel door jamb 1.00 set 2,125.00 2,125.00
4.3 Ball bearing hinges 6.00 nos 225.00 1,350.00
4.4 Lockset 1.00 set 2,650.00 2,650.00
4.5 Dummy trim 1.00 set 1,625.00 1,625.00
4.6 Flush bolt 2.00 nos 118.75 237.50
5.0 Roof finishes
5.1 Concrete roof tiles with Ga.26 GI undersheeting 24.95 m² 1,500.00 37,425.00
5.2 12mm thk Ficem board fascia 19.08 lm 218.75 4,173.75
6.0 Paint finishes
6.1 Textured paint finish
a. Exterior masonry wall 44.27 m² 375.00 16,601.25
6.2 Paint finish
a. Interior masonry wall 41.50 m² 162.50 6,743.75
b. 200 x 50mm Concrete moulding 9.12 lm 48.82 445.25
c. 100 x 50mm Concrete moulding 12.36 lm 32.47 401.38
d. 12mm thk Ficem board fascia 19.08 lm 40.63 775.13
6.3 Epoxy paint finish
a. Steel door 6.72 m² 287.50 1,932.00
b. Steel jamb 5.80 lm 71.88 416.88
C. ELECTRICAL WORKS
1.0 Electrical fixtures
1.1 Panelboard 1.00 nos 9,375.00 9,375.00
1.2 Incandescent lamp 2.00 nos 1,687.50 3,375.00
D. PLUMBING WORKS
Page 18 of 22
item description quantity unit unit cost total amount
VI. PATHWAY
A. STRUCTURAL WORKS
1.0 Structural works
1.1 Slab on fill
a. 75mm thk Gravel bedding 5.48 m³ 750.00 4,110.00
b. Concrete, 3000psi 5.48 m³ 3,750.00 20,550.00
B. ARCHITECTURAL WORKS
1.0 Floor finishes
1.1 Stamp concrete 73.00 m² 1,500.00 109,500.00
1.2 50mm thk Concrete topping 73.00 m² 415.00 30,295.00
Page 19 of 22
item description quantity unit unit cost total amount
Page 20 of 22
Project : FUENTE DE VILLA ABRILLE - OPEN SPACE DEVELOPMENT of PHASE 1 and 2
Location : Davao City
Subject : BUDGETARY COST ESTIMATE
Date : December 11, 2006
I. PHASE 1
1.0 Earthworks 1.00 lot 44,442.78 44,442.78
2.0 Rotunda (20000mmØ) 1.00 lot 387,923.50 387,923.50
3.0 Parking area (11000 x 6000mm) 2.00 nos 57,681.22 115,362.44
4.0 Sidewalk W=1000mm 1.00 lot 20,455.63 20,455.63
5.0 Playground 1.00 lot 402,395.80 402,395.80
6.0 Simulated playground 1.00 lot 27,395.80 27,395.80
7.0 Pathway 1.00 lot 344,187.41 344,187.41
8.0 Gazebo (5010 x 5010mm) 2.00 nos 414,672.80 829,345.59
9.0 Multi-purpose hall 1.00 lot 5,221,067.47 5,221,067.47
10.0 Landscaping 1.00 lot 1,061,748.44 1,061,748.44
11.0 Utilities 1.00 lot 649,847.27 649,847.27
12.0 General requirements 1.00 lot 275,000.00 275,000.00
II. PHASE 2
1.0 Earthworks 1.00 lot 28,648.75 28,648.75
2.0 Basketball court 1.00 lot 1,005,232.06 1,005,232.06
3.0 Swimming pool 1.00 lot 1,625,681.02 1,625,681.02
4.0 Swimming pool deck 1.00 lot 647,914.75 647,914.75
5.0 Pump room 1.00 lot 282,653.84 282,653.84
6.0 Pathway 1.00 lot 164,455.00 164,455.00
7.0 Plumbing works 1.00 lot 90,471.04 90,471.04
8.0 General requirements 1.00 lot 62,500.00 62,500.00
35,554.22
310,338.80
46,144.98
16,364.50
321,916.64
21,916.64
275,349.93
331,738.24
4,176,853.97
849,398.75
519,877.82
220,000.00