Main Activity

1 Water Treatment System


+ The process was stopped
+ Pump load test started on 05/12/2019, now is ongoing
+ Regular tank of WWTP not ready to receive water. Maybe
this tank handover on 7/12/2019

2 Waste Water Treatment System


+ Until now some of civil work not 100% complete.
+ Commissioning procees will start after civil complete.
+ All scope I&C; Elec ready to start.

3 Air compressor
TA ongoing setup system (PLC; interface PLC-DCS)
Piping flushing not start.
When Temp.CCW running this system will be start also
Some minor electrical work not completed yet such as:
+ Lighting work not start
+ HVAC fan: wiring not connected.

4 Temp. CCW
+ Temp. cooling tower erection complete
+ Motor solo test finished (23/11).
+ The target to put this system in service in the end of Nov (28/12)
+ Piping flushing started on 4/12/2019, now is ongoing
+ The boundary piping flushing refer to PID attached file.

5 Condensate tranfer system


+ Pump load test finished. Tank A+B, water fully filled and
using Demi.water from that tank to flushing for CCW system.
Photo
Nov (28/12)