PLANT HOT START-UP

A.PLANT HOT START-UP READY


- MCWS A On and MCWS B On
- CCWS Normal
- Air Compressor Sys Normal
- Gen Stator Cooling Water Sys Normal
- Auxiliary Steam Sys Normal
- HP Bypass Hydraulic Sys Normal
- LP Bypass Hydraulic Sys Normal
- Water Level In Storage Condenser Normal
- Water Level In Feedwater Storage TNK is Normal
- MECH CLNG is In Service
- U1 Chlo Sys On
- LDO Forwarding Sys In Service
- Condenser Water Box Vacuum Sys In Service
- Condenser Sys In Service
- Circulating Water Sys In Service
- CPP In Service
- Scanner Cooling Air Fan In Service
- BFPT A Lube Oil & Turning Gear In Service
- BFPT B Lube Oil & Turning Gear In Service
- TBN LUBE Oil Sys Normal
- Generator Seal Oil Sys Normal
- H2 Gas Fill Up Complete In Gen
- Steam Turbine Turning Gear In Service
- ACW Sys In Service
- DM Water Storage & Transfer Sys In Service
- Service Water & F/F Sys In Service
- CEMS Normal
- TBN Steam Seal Sys Normal
- Operation Verification
- Unit In Hot Start Mode
Node: The Operator shall verify the following Condition before Plant Start-up Sequence
- Water Treatment System Normal
- Condensate Storage & Trabsfer Sys Normal
- Condenser Hot Well FW Storage TNK Filled
- CTCS In Service
- Debris Filter In Service
- All Manual Valves In all System Properly Positioned
- All Equipment (Train Group, Pumps) Preselected
- BLR Fill Up Complete
- Clean Up of Condensate Sys Complete
- BLR Flushing Complete
- Flow Path FW 1,2,3,4 Available
- ESP Heating Complete
- Sampling System Normal
B. STEP BY STEP HOT START-UP

Step Conditions Step by Step


No

01 - PB Start - Common Sys Group Auto


- Plant Hot Start Ready

02 - Auxiliary PRDS Group Auto Mode - Main Steam & Reheat Drain Sys Auto
- DM Water SPLY PP Group
Control Auto Mode
- COND XFP Group Control Auto
Mode
- PW PP Group Control Auto Mode
- Service WTR PP GRP CTL Auto
Mode
- DO FWD PP GRP CTL Auto
Mode
- CCW GRP CTL Master Auto
Mode
- FGD CCWP GRP CTL Master
Auto Mode
- ACW GRP CTL Master Auto
Mode
- CVP GRP CTL Master Auto Mode

03 - Main Steam & Reheat Drain Sys In - FW HTR Vent Sys To Start-up Position
Auto

04 - FW HTR Vent Sys In Start-up - Delay 10s to Next Step


Position

05 - - Reset STG

06 - STG Reset Complete - Start S-U BFP

07 - S-U BFP Running - Start Automatic Boiler Sequence

08 - Automatic Boiler Sequence In - Set FW HTR EXT STM DRN SYS To


Process Start Position

09 - FW HTR EXT STM DRN SYS In - Start ESP Sys


Start Position
- ESP A RDY to Start-up
- ESP B RDY to Start-up
- Remode Mode Selected

10 - ESP A Running - HP/LP Bypass to Start Mode


- ESP B Running

11 - HP BP Auto Mode - Start FGD Sys


- HP BP A M/A Auto Mode
- HP BP B M/A Auto Mode
- LP BP Auto Mode
- LP BP A M/A Auto Mode
- LP BP B M/A Auto Mode
- FGD Sys Ready
- FGD Sys Remote

12 - FGD Sys Running - BFPT A Reset CMD


- All TBN DRN VLV Open - BFPT B Reset CMD
- TBN Ready to Start - STG Auto Start

13 - TBN Rolling In Reverse Flow - Verify TBN Speed 2600 rpm


Mode

14 - TBN Speed > 2600 rpm - Verify TBN Speed 3000 rpm

15 - TBN Speed > 3000 rpm - Start Fly ASH Handling Sys

16 - Fly ASH Handling Sys Running - Start SDCC for BAHS


- SDCC for BAHS Start Permissive

17 - SDCC for BAHS Running - LP FW HTR #2, 3, 4 Start Vent MOV


Closed At HTR LVL Normal

18 - FW HTR 4 Vent MOV Closed - Release to STG Synchronization


- FW HTR 3 Vent MOV Closed
- FW HTR 2 Vent MOV Closed

19 - STG Synchronized - Delay 10s to Next Step

20 - - Enable UMC Command

21 - TBN In UMC Mode - Set TBN Master Control Auto

22 - TMC Auto Mode - Set BLR Master CTL Auto


- Both HP Bypass VLV Closed

23 - BMC Auto Mode - Set UMC Target 50% Load

24 - TBN Actual MW > 150 MW (25%) - Start 1ST TBN Driven BFP
- BFPT A Duty Selection
- BFPT A RDY to Start
- Or BFPT B Duty Selection
- BFPT B RDY to Start
25 - BFPT A Duty Selection - Verify Motor Driven Stop
- And BFPT A Running
- Or BFPT B Duty Selection
- And BFPT B Running
- BFP Discharge Pres Equlized

26 - S-U BFP Stopped - Verify FW 100% MOV Open

27 - FW HTR to Economizer Inl MOV - Set UMC Target 100% Load


Opened

28 - TBN Actual MW > 240%(40%) - Start 2nd TBN Driven BFP


- BFPT A Duty Selection
- BFPT A RDY to Start
- Or BFPT B Duty Selection
- BFPT B RDY to Start

29 - BFP B Running - Start 2nd CEP


- BFP A Running

30 - More Than Two CEP Running - Verify 50% Load (300MW) Reach

31 - TBN Actual MW > 300MW(50%) - Verify 70% Load (420MW) Reach

32 - TBN Actual MW > 420MW(70%) - Verify 90% Load (540MW) Reach

33 - TBN Actual MW > 540MW(70%) - Verify 100% Load (600MW) Reach


- Plant Cold Start-up Complete