MONITORING PENGECORAN
127 30-Oct-19 Kolom Lt. 1 Zona 1B & 2B FC-45 6-Nov 13-Nov 27-Nov
1 set ABI
Kolom Lt. GWT
128 1-Nov-19 SW 5 Lt 1 FC-45 8-Nov 15-Nov 29-Nov
1 set SCG
Kolom Lt GWT
129 1-Nov-19 Plat Lt. 1 Zona 1A + 1B FC-35 8-Nov 15-Nov 29-Nov
2 set SCG
143 11-Nov-19 Kolom Lt 2 Zona 1A, 1B, 2B FC-45 18-Nov 25-Nov 9-Dec
1 set ABI
144 12-Nov-19 Plat Lantai 4 Zona 2A As S-W/13-17 (MOCK UP) FC-35 19-Nov 26-Nov 10-Dec
1 set ABI
147 13-Nov-19 Plat Lantai 4 Zona 2A As R-S/13-17 FC-35 20-Nov 27-Nov 11-Dec
1 set ABI
148 13-Nov-19 Kolom 1B Lt. 2, Kolom Lt. 4 Zona 2A, dan FC-45 20-Nov 27-Nov 11-Dec
1 set ABI
Kolom Lt. 2 Zona 2B
149 14-Nov-19 Kolom Lt. 4 Zona 2A, Kolom Lt. 2 Zona 2B FC-45 21-Nov 28-Nov 12-Dec
1 set ABI
` SW 2 Lt. 2
150 15-Nov-19 Plat Lt. 3 Zona 1B & 2B FC-35 22-Nov 29-Nov 13-Dec
2 set ABI
151 16-Nov-19 Kolom Lt. 2 Zona 1B, Kolom Lt. 4 Zona 2A FC-45 23-Nov 30-Nov 14-Dec
1 set ABI
Kolom Lt. 2 Zona 2B
152 16-Nov-19 Kolom Lt. 3 Zona 1B FC-45 23-Nov 30-Nov 14-Dec
1 set ABI
Kolom Lt. 3 Zona 2B
153 17-Nov-19 SW 3 Lt. 2 FC-45 24-Nov 1-Dec 15-Dec
1 set ABI
SW 6 Lt .4
154 17-Nov-19 Plat Lt. 3 Zona 1B FC-35 24-Nov 1-Dec 15-Dec 1 set ABI
174 28-Nov-19 BALOK & PLAT LT.4 FC-35 5-Dec 12-Dec 26-Dec 1 SET
MJB
KOLOM FC-45 1 SET
175 28-Nov-19 KOLOM LT.4 FC-35 5-Dec 12-Dec 26-Dec
1 set MJB
30-Nov-19 BALOK & PLAT LT.3 - ZONE 1A FC-35 7-Dec 14-Dec 28-Dec MJB
1 set
183 3-Dec-19 BALOK & PLAT LT.4 FC-45 10-Dec 17-Dec 31-Dec
1 set MJB
186 4-Dec-19 PLAT LANTAI 4 (ZONA 1A) FC-35 11-Dec 18-Dec 1-Jan
1 set MJB
189 5-Dec-19 KOLOM LT.4 (ZONE 1A) FC-45 12-Dec 19-Dec 2-Jan
1 set ABI
MONITORING PENGECORAN
197 8-Dec-19 PLAT & BALOK LT.GROUND FC-35 15-Dec 22-Dec 5-Jan 1 set ABI
204 11-Dec-19 TANGGA (GF to P1) + PARAPET FC-35 18-Dec 25-Dec 8-Jan
1 set ABI
205 12-Dec-19 PLAT LT.5 (ZONE 2B) FC-35 19-Dec 26-Dec 9-Jan
1 set ABI
206 12-Dec-19 SW4 (ZONE 1A) - SCREENING FC-45 19-Dec 26-Dec 9-Jan
1 set ABI
14-Dec-19 PLAT & BALOK LT.5 (ZONA 2B) FC-35 21-Dec 28-Dec 11-Jan
213 1 set MJB
29-Dec-19 BALOK PLAT LT.7 (ZONA 2A) FC-35 5-Jan 12-Jan 26-Jan
249 1 set MJB
31-Dec-19 LT.8 (ZONA 2A) AS U-W / 13-17 FC-35 7-Jan 14-Jan 28-Jan
255 1 set ABI
MONITORING PENGECORAN
3-Jan-19 TANGGA SW1 (LT.P1 - LT1) - ZONA 1A FC-35 10-Jan 17-Jan 31-Jan
261 1 set MJB
21-Jan-19 KOLOM LT.8 ( ZONA 1B & 2B) SCREENING FC-40 28-Jan 4-Feb 18-Feb
320 1 set MJB
28-Jan-20 PLAT LT.9 ( ZONA 1A - 1B) ( ZONA 2B) FC-30 4-Feb 11-Feb 25-Feb
341 1 set MJB
17-Feb-20 SW1 LT.12 KOLOM LT. 11 & SW 6 ( SCREENING ) FC-40 24-Feb 2-Mar 16-Mar
399 1 set ABI
MONITORING PENGECORAN