Document No.
A8JE-000-50-RQ-0011
Client : Halliburton
Project No. : A8JE
Digitally signed
by ath22960
Date: 2019.10.08
14:09:05 +03'00'
CONFIDENTIAL INFORMATION – PRODUCTION AND USE PROHIBITED EXCEPT IN ACCORDANCE WITH HALLIBURTON MULTI-CHEM BATCH
PLANT COMPANY’S WRITTEN PERMISSION
A8JE-000-50-RQ-0011 Page 1 of 13
HALLIBURTON Multi-Chem Batch Plant Doc No: A8JE-000-50-RQ-0011
MATERIAL REQUISITION FOR CS AND SS PIPES, FITTINGS, Rev. 1
FLANGES, BLINDS, BOLTS AND GASKETS
TABLE OF CONTENTS
A8JE-000-50-RQ-0011 Page 2 of 13
HALLIBURTON Multi-Chem Batch Plant Doc No: A8JE-000-50-RQ-0011
MATERIAL REQUISITION FOR CS AND SS PIPES, FITTINGS, Rev. 1
FLANGES, BLINDS, BOLTS AND GASKETS
1. INTRODUCTION
The Halliburton Multi-Chem Batch Plant (MCBP) will construct a green field batch operated
chemical manufacturing facility at the PlusChem Park near Sadara, Jubail 2 Industrial City,
KSA. The Multi-Chem batch plant will initially manufacture Pour Point Depressant and
Corrosion Inhibitors used within the oil and gas industries. Fluor Arabia Limited (FAL) has
been awarded the project to perform detailed engineering, procurement, and construction
(EPC) services.
This Material Requisition (MR) covers the minimum requirements for the engineering, design,
manufacturing, inspection, testing, preservation, preparation for shipment and packing, and
supply of GOODS as mentioned in this requisition and Bills of Material Doc. No. A8JE-5-
0011-RQ forming part of this requisition.
2. DEFINITIONS
2.1 Definition of the parties involved
OWNER Halliburton
RQ / MR Material Requisition
SDL Supplier Document List
SOW Scope of Work
A8JE-000-50-RQ-0011 Page 3 of 13
HALLIBURTON Multi-Chem Batch Plant Doc No: A8JE-000-50-RQ-0011
MATERIAL REQUISITION FOR CS AND SS PIPES, FITTINGS, Rev. 1
FLANGES, BLINDS, BOLTS AND GASKETS
2.3 Definition
recommended
3.1 General
The Codes, Standards, Specifications and other attachments listed in this section form an
integral part of this Material Requisition.
SUPPLIER shall give a clear statement to confirm his compliance with all applicable
requirements referred in these documents.
Should a conflict exist between documents, it shall be the responsibility of the SUPPLIER to
call attention to the discrepancy and request a written ruling or interpretation from the BUYER
in the attached clarification sheet, Doc No. A8JE-5-0011-RQ-SCS. Failure to do so shall not
result in additional cost or schedule impact to the BUYER for discrepancies discovered during
fabrication or execution.
Review of SUPPLIER’s documents shall in no way relieve SUPPLIER of its responsibility for
compliance to the Purchase Order.
A8JE-000-50-RQ-0011 Page 4 of 13
HALLIBURTON Multi-Chem Batch Plant Doc No: A8JE-000-50-RQ-0011
MATERIAL REQUISITION FOR CS AND SS PIPES, FITTINGS, Rev. 1
FLANGES, BLINDS, BOLTS AND GASKETS
3.3 Deviations
No deviations shall be allowed from any Local Rules, Regulations and Authority requirements.
Deviations from Codes, Standards and Specifications are acceptable only to the extent they
are agreed upon, in writing, by BUYER, prior to award. It shall be SUPPLIER’s responsibility
to request in writing approval from BUYER for any proposed deviation from the inquiry
documents. Following a contract / purchase award, no deviation from the Purchase Order
requirements shall be acceptable.
SUPPLIER shall submit all the deviations on the applicable requirements in the dedicated list
(“Deviation List”) Doc. No. A8JE-5-0011-RQ-DL along with its Proposal, complete with
detailed description and technical justification for BUYER’s review and approval. Any
deviation from the inquiry requirements, not specifically listed / presented in SUPPLIER’s
Deviation List shall not be considered.
Any requested deviations that are not approved shall be brought into compliance with
requirements of the Purchase Order; costs associated with such compliance shall be for
SUPPLIER’s account.
A8JE-000-50-RQ-0011 Page 5 of 13
HALLIBURTON Multi-Chem Batch Plant Doc No: A8JE-000-50-RQ-0011
MATERIAL REQUISITION FOR CS AND SS PIPES, FITTINGS, Rev. 1
FLANGES, BLINDS, BOLTS AND GASKETS
The above listed Codes and Standards are the principal ones applicable to this MR and are
not intended to be exclusive. For full scope of applicable Codes and Standards refer to the bill
of materials and applicable Project Specifications.
The following listed PIP practices are applicable to this MR and are not intended to be
exclusive. For the full scope of applicable PIP standards refer to all the available PIP
standards (latest as of 07-Nov-2018). The latest editions and addenda at the time of award
shall apply. Unless modified by requirements specified herein, the equipment shall comply
with these publications.
4. EXTENT OF SUPPLY
A8JE-000-50-RQ-0011 Page 6 of 13
HALLIBURTON Multi-Chem Batch Plant Doc No: A8JE-000-50-RQ-0011
MATERIAL REQUISITION FOR CS AND SS PIPES, FITTINGS, Rev. 1
FLANGES, BLINDS, BOLTS AND GASKETS
Quantity and delivery time for the supply of documents is specified in Supplier Drawing and Data
Commitment (SDDC).
5. ENGINEERING NOTES
5.1 General
All materials supplied by the SUPPLIER shall be within the range of SUPPLIER’s proven experience
and shall not involve the use of any prototype design or components. SUPPLIER shall submit its
relevant experience list along with its proposal for BUYER’s review.
1. The design of all GOODS SHALL be furnished by the SUPPLIER for BUYER’s review.
2. General requirements for all GOODS are stated in listed Project Specifications in section 3 of
this requisition.
B. 2” and greater shall supply in Double Random Length (DRL) equal to 12 meters.
C. All galvanized carbon steel shall supply in single random length equal to 6 meters.
Technical requirements for the Material / Components listed in the BOM are included in the Purchase
Description, International Codes and Standards, and Project Specifications referenced in this
requisition.
A8JE-000-50-RQ-0011 Page 7 of 13
HALLIBURTON Multi-Chem Batch Plant Doc No: A8JE-000-50-RQ-0011
MATERIAL REQUISITION FOR CS AND SS PIPES, FITTINGS, Rev. 1
FLANGES, BLINDS, BOLTS AND GASKETS
2. Each length of pipe shall be subjected to a hydrostatic test in accordance with an ASTM
specification referenced for manufacture. Where there is a choice in the specification of
hydrostatic test or other NDE (Nondestructive Examination), the hydrostatic test shall be
performed. If no hydrostatic test is required in the Manufacturer's specification, then the ASTM A
530 hydrostatic test shall be performed.
1. PMI requirements and examination of GOODS SHALL be in accordance with VESPMI01 Positive
Material Identification Specification.
2. All materials rejected by PMI check or with inadequate documentation or marking SHALL be
strictly quarantined pending investigation. Noncompliant materials SHALL be rejected and
returned at SUPPLIER’s cost.
4. Supplier shall perform 5% random PMI for SS304/304L and SS316/316L in with accordance with
VESPMI01 and API RP 578.
5. Color coding shall be in accordance with PFI standard ES-22. PMI procedure shall show a Color
Code Table for Material Identification. Same color code shall be applied for similar grades.
The final acceptance of material is subject to achieving the all requirements. Buyer reserves the right
to perform additional testing upon arrival of the material on construction site.
A8JE-000-50-RQ-0011 Page 8 of 13
HALLIBURTON Multi-Chem Batch Plant Doc No: A8JE-000-50-RQ-0011
MATERIAL REQUISITION FOR CS AND SS PIPES, FITTINGS, Rev. 1
FLANGES, BLINDS, BOLTS AND GASKETS
In case the material fails to meet the requirements, material SHALL be considered as rejected and all
associated cost incurred that resulted from this rejection SHALL be borne by the SUPPLIER.
The SUPPLIER / MANUFACTURER shall submit a Quality Assurance and Quality control (QA/QC)
program. This submittal shall be after release of the purchase order, but before starting
manufacturing.
Buyer will review SUPPLIER’s quality program. The SUPPLIER shall have in effect at all times a
QA/QC program, which clearly establishes the authority and responsibility of those responsible for the
quality system. Persons performing quality functions shall have sufficient and well-defined authority to
enforce quality requirements, initiate, identify, recommend and provide solutions to quality problems
and verify the effectiveness of the corrective action.
The SUPPLIER’s proposed quality system shall fully satisfy all applicable elements of ISO 9001, 2000
or other internationally recognized standard. The quality system shall provide for the planned and
systematic control of all quality-related activities performed.
All materials are subject to inspection by Buyer or its authorized agent, third party, and/or OWNER as
per the instructions included in the Requisition package. Supplier shall prepare and submit for Buyer’s
approval, no later than indicated on the SDDC, a detailed Inspection & Testing Plan (ITP - Quality
Control Plan) developed from the Seller’s Quality Assurance System. The Inspection and Test Plan
shall be prepared based on the actual production facilities of the SUPPLIER or SUB-SUPPLIER(s)
performing the work.
7.2 Inspection, Certification and Traceability.
SUPPLIER shall retain details of the components, material inspection and examination certifications
for at least 10 (ten) years from the date of delivery.
All certificates shall be original or certified copies. The certificates shall be in English language or an
endorsed and dated English translation.
7.2.1 Traceability
SUPPLIER shall implement a material traceability system to ensure that the certificates are fully
traceable to their base materials, the manufacture details and the quality control results.
A component QC sheet shall be maintained for each pipe, fitting and flange, and shall include the raw
material details, the manufacture and construction details, the GOODS dimensions and the QC
results.
A8JE-000-50-RQ-0011 Page 9 of 13
HALLIBURTON Multi-Chem Batch Plant Doc No: A8JE-000-50-RQ-0011
MATERIAL REQUISITION FOR CS AND SS PIPES, FITTINGS, Rev. 1
FLANGES, BLINDS, BOLTS AND GASKETS
2. Material Test Certificates shall comply with BS EN 10204, Type 3.1 and SHALL include the
Purchase Order number, PO item number, item codes, and quantity delivered. These SHALL be
signed by the Manufacturers Quality Assurance Department and SUPPLIER’s Authorized
Inspector.
3. The Certified Test Reports SHALL be originated by the primary Manufacturer and SHALL be
traceable.
4. Each certificate SHALL be either the original or a full-size, complete and totally legible photocopy.
A partly complete duplicate of the original will not be accepted.
5. Material certificates SHALL be submitted prior to SQS inspection. A hard copy of the certificates
SHALL also be available at the SUPPLIER’s facility during the scheduled SQS inspection.
6. Where material is supplied by a SUB-SUPPLIER prior to any form of working and treating, the two
certificates will be required:
7. A retest of materials will not be accepted as an alternative to a missing certificate, since a series
of tests cannot exhaustively indicate all aspects of product quality.
A8JE-000-50-RQ-0011 Page 10 of 13
HALLIBURTON Multi-Chem Batch Plant Doc No: A8JE-000-50-RQ-0011
MATERIAL REQUISITION FOR CS AND SS PIPES, FITTINGS, Rev. 1
FLANGES, BLINDS, BOLTS AND GASKETS
Buyer shall be allowed unrestricted entry to all SUPPLIER and SUP-SUPPLIER shops that
are in the process of manufacturing, testing or inspecting the equipment, after giving advance
notice to the SUPPLIER.
Manufacturing hold points for inspection and testing shall be identified by joint agreement of
buyer, the authorised inspector and the SUPPLIER after receipt of the purchase order and as
indicated on the relevant Quality and Inspection Test Plan.
SUPPLIER shall provide records of test instrument calibration to the inspector when
requested.
The final inspection shall be done before shipment by BUYER’s representative.
All non-destructive examinations performed as required by this material requisition shall be
done to a written procedure as per SUPPLIER standard procedure. All NDE procedures shall
be submitted for Buyer review and acceptance.
Extent of Visual Examination shall be 100%.
Preparation for shipment, transport and storage of the GOODS shall be in accordance with the
packing, marking and shipping instructions in purchase specifications, codes and standards, and
purchase order requirements. On completion of inspection and tests, materials shall be thoroughly
cleaned and dried internally and externally and prepared for shipment.
The package shall be adequately protected against corrosion and mechanical damage for shipment to
plant site and outdoor storage for periods up to 6 month unless otherwise instructed in the
procurement documents.
The materials shall not be shipped unless buyer's inspector has issued a "Release Note" for
shipment.
The SUPPLIER SHALL ensure that the packing list to be submitted prior to shipment SHALL
accurately document the contents of each package. Each item SHALL be properly tagged so it can
easily be tracked and located.
Special tools and handling equipment SHALL be packed separately and identified as included in the
shipment.
Flange facings and butt-welding ends shall be protected for shipment as follows:
a. The entire gasket seating surface or butt-welding end shall be covered with wood, plastic, or
metal covers.
b. The protection covers shall prevent dirt and other foreign matter from entering the interior of
the GOODS and damaging the flange facings or butt-welding bevels.
c. If flange facings or butt-welding bevels are protected with metal covers, a layer of nonmetallic
material shall be provided between the GOODS and the cover.
A8JE-000-50-RQ-0011 Page 11 of 13
HALLIBURTON Multi-Chem Batch Plant Doc No: A8JE-000-50-RQ-0011
MATERIAL REQUISITION FOR CS AND SS PIPES, FITTINGS, Rev. 1
FLANGES, BLINDS, BOLTS AND GASKETS
9. SUPPLIER DOCUMENTS
9.1 General
9.1.1 The SUPPLIER shall, upon receipt of an order, comply with the drawing submittal
requirements of the SUPPLIER Drawing & Data Commitment Doc No. A8JE-5-
0011-RQ-SDDC
9.1.2 The SUPPLIER SHALL submit all required documents in electronic format, and as
specified in form 000.206.F0520, PDDM SUPPLIER Drawing and Data
Commitment Form Attachment (SDDCFA).
9.1.3 The BUYER will review the SUPPLIER’s documents and will comment (if required)
accordingly prior to any work commencing. BUYER review and comment shall in
no way relieve the SUPPLIER of responsibility for design, materials, or
workmanship as defined in this Specification, BOM descriptions and other
referenced documents.
9.1.4 SUPPLIER shall make sure that prior to resubmission of the documents all
BUYER’s comments are addressed and agreed to avoid unnecessary revisions of
the documents. SUPPLIER and BUYER shall agree a procedure regarding the
comment resolution during the Kick-Off Meeting
9.1.5 Documents may not be released for purchase or fabrication until BUYER have
been returned the documents to the SUPPLIER at either “A1” (Data Complete –
No Comments – Do Not Resubmit) or “B1” (Data Complete – With Comments -
Proceed - Resubmit) review status, unless otherwise specifically permitted in
writing by the BUYER.
9.1.7 SUPPLIER shall submit three (3) bound hard copies of Quality Control Dossier
including drawings, material test certificates, inspection & test reports, repair
procedures etc. Index of IOM and QC Dossier shall be issued prior to formal
issuance of these documents for BUYER’s review and approval.
9.1.8 SUPPLIER shall also submit one (1) electronic copy of all deliverables.
9.1.9 The SUPPLIER’s performance of its obligations under this Purchase Order SHALL
not be deemed complete until the BUYER is in receipt, in proper form, of all
technical documents and other data that are required to be submitted to BUYER
as part of SUPPLIER’s Scope of Supply.
A8JE-000-50-RQ-0011 Page 12 of 13
HALLIBURTON Multi-Chem Batch Plant Doc No: A8JE-000-50-RQ-0011
MATERIAL REQUISITION FOR CS AND SS PIPES, FITTINGS, Rev. 1
FLANGES, BLINDS, BOLTS AND GASKETS
Number Description
A8JE-5-0011-D-RQ-BOM Gaskets
A8JE-000-50-RQ-0011 Page 13 of 13