AUDIT GROUP ________ AUDIT TEAM__________
___________________________________
(Official Station of the ATL)
AUDITORIAL CONTRACT REVIEW ANALYSIS SHEET (ACRAS) FOR GOODS AND SERVICES
Public Bidding
(Updated as of November, 2016)
Date Prepared:
I. GENERAL REQUIREMENTS:
Name/Position Date
Purchase Request requested by/date:
B. AUDIT ANALYSIS:
Yes No Date Remarks
B.1. Procurement project included in the Project
Procurement Management Plan (PPMP)
B.2. Procurement project included in the Annual
Procurement Plan (APP):
B.2. Indicative APP
B.2. Final APP
B.3. Final APP match the budget per GAA,
corporate budget, appropriation ordinance,
as the case may be.
B.4. Final APP submitted in the GPPB on or before the
end of January of the budget year and posted in
the GPPB Website
III. PREPARATORY REQUIREMENTS:
A. DOCUMENTS NEEDED: Present Absent Date Remarks
A.1. Approved Technical Specifications
(Section 17.2 and 18 of 2016 Revised IRR)
A.2. Approved Budget for Contract (ABC) with Detailed
Quantity and Cost Estimates
A.3. Complete Bidding Documents, in accordance with
Philippine Bidding Documents (PBD), 5th Edition dated
August, 2016 (Section 6.2. of 2016 Revised IRR)
B. AUDIT ANALYSIS:
Yes No Date Remarks
B.1. Approved Technical Specifications complete and reflect
the necessary specifications required to meet the needs
of the End-user in clear and unambiguous terms.
B.2. Approved Technical Specifications contained the relevant
characteristics, functionality and/or performance
requirements and no reference to brand name except for items
or parts that are compatible with the existing goods
B.3. Approved Budget for Contract (ABC) match with Detailed
Quantity and Cost Estimates
B.4. Procurement use the Standard Philippine Bidding Documents,
5th Edition dated August, 2016, containing the following:
Section I. Invitation to Bid
Section II. Instruction to Bidders (ITB)
Section III. Bid Data Sheet (BDS)
Section IV. General Conditions of Contract (GCC)
Section V. Special Conditions of Contract (SCC)
Section VI. Schedule of Requirements
Section VII. Technical Specifications
Section VIII. Bidding Forms
Section IX. Foreign-Assisted Projects
3. Statement of SLCC;
4. NFCC Computation;
5. JVA, if applicable;
6. Bid security in the prescribed form, amount and
validity period;
6.1. Form of Bid Security Amount
1) Cash or cashier’s/manager’s
check issued by a Universal
or Commercial Bank 2.00% of ABC
OR 2) Bank draft/guarantee or
irrevocable letter of credit
issued by a Universal or
Commercial Bank 2.00% of ABC
OR 3) Surety bond 5.00% of ABC
OR 4) Bid Securing Declaration
7. Technical Specifications
7a. Production/delivery Schedule
7b. Manpower Requirements
7c. After-sales service/parts, if applicable
A. DOCUMENTS NEEDED:
A.1. Invitation of three(3) obsevers in writing, at least Present Absent Date Remarks
5 calendar days before procurement activity.
B. AUDITORIAL ANALYSIS:
B.1 LCB submitted the additional document within the
required time
B.2. BAC completed the Post Qualification within required time
B.3. TWG Post Qualification Evaluation Report contained the
verification, validation and ascertaining all the statements
made and documents submitted by the bidder with the LCB
on the following:
1. Authenticity of the document submitted
8. Award of Contract: within a period not exceeding fifteen (15) cd from the
determination by the BAC of the bidder with the LCRB and the
recommendation to award the contract (Section 37.1.2. of the 2016 Revised IRR)
9. Contract Preparation and Signing : within ten (10) calendar days from
receipt by the winning bidder of the NOA. (Section 37.2. of 2016 Revised IRR)
Findings/Observations:
Date : Date :