You are on page 1of 92

UDC 665.7.004 : 621.6423-111.

1 :
62t .772.46 : 669.14.018.62 :
623.791-75.053.8

- ..
British Standard Specification for
Manufacture of vertical steel welded
nun-refrigerated storage tanks with
butt-welded shells for the
petroleum industry
......
' a ?

- ' - .-
.+
-. :Si:
!.g.
;
- - ..
.r ?.r.
'..+* <

,.;
"
.>.. .&

. .%,.?*
'.k
::, ?".
'
.. .%I

Fabrication des rkservoirs de stockage verticaux non refrigbrbs en w . :

acier :lenveioppe soudk 'bout 5 bout pour I'industrie de phtrole - Sp6cifications

Herstellung stehender ungekiihlter Lagertanks aus Stahl mit stumpgeschweil3tem


Mantel f k die Erd6findustrie
A

..,.: ...:. -
......i.:
.;.,.. :;' ..
I

' . '

. _.__
:. . .
. .
. ,

1 ' Bfitish Standards Institution


Foreword

This British Standard was prepared under the direction of The method specified i s for determining the notch tough-

I the Pressure Vessel Standards Policy Committee and


replaces BS 2654 :1984 which is naw withdrawn. it is
designed t o provide the petroleum i n d u m y w i t h tanks o f
ness required of a material in any given thickness f o r
design temperatures d o w n t o - 10 *C based a n tests in
which through-thickness defects u p t o 10 mm long, located
adequate safety, reasonable economy and i n a range o f both in locally ernbrittled and postweld heat treated
suitable capacities f o r the storage o f o i t and o i l products. material, are required t o withstand approximately four
The committee recognizes, however, that this standard times yield point strain (see figure 1).
could be adopted w i t h equal safety.andeconomy by other Scale A is derived using these criteria and data f r o m WWP
industries andlor for the storage of other products, tests f o r as-welded joints.
although purchasers and manufacturers may need t o Scale I3 is used f o r determining the requirements for the
formulate and agree additional requirements necessitated hydrostatic test.
by the conditions pertaining t o a particular application.
Appendix A gives recommendations for tank foundations
NOTE. Users of this British Standard are reminded that the BSI
committee responsible is prepared to offer interpretations of the and appendix 6 gives recommendations f o r the design and
texr on request. application of insulation.
The requirements for material selection in this standard This standard is expressed in metric units and a proposed
have been based o n the results o f a number o f notched and range o f standard metric diameters and capacities is given
welded Wells Wide Plate Tests (WWP Tests) o n carbon arid i n appendix C.
carbon/manganese steel plates, carried o u t at the Welding A l l pressure and vacuum values i n this standard are
Institute. I n particular, the proposals are related to the expressed as gauge values.
resutts reportedin 'Mild steel for pressure equipment sub-
The symbols used throughout the t e x t are as listed i n
zero temperatures', British Welding Jaurnal, March 1964,
appendix D.
b u t all other known WWP test data have been taken i n t o
account. They also reflect many subjective assesvnentsof Appendix E gives recommendations f o r internal floating
practice t o date i n this field as permitted by current British.
"American and German codes.
covers, appendix F gives recommendations for the design
of venting systems arid appendix G offers seismic toading
provisions.
1
WWP test data all indicate that resistance t o brittle fracture
is dependent upon the following. it has been assumed i n the drafting of this British Standard
that the execution o f its provisions, is entrusted to appro-
(a) Notch toughness o f the material.
priately qualified and experienced people.
(b) Plate thickness.
This edition introduces technical changes t o bring the
(c) Extent o f crack-like defects present; it is believed
that if such defects are absent, brittle fracture w i l l not
be a problem at normal rates o f loading.
standard up-to-date but it does n o t reflect a full review o f
the standard, which w i l l be undertaken in due course.

Compliance w i t h a British Standard does not of itself


I
(d) Degree o f local embrittfement a t t i p of pre-existing
defects; i n the case o f carbon and carbodmanganese confer immunity from tmal obligations.
steels, postweld heat treatment i n the stress relieving
range temperature is effective i n removing severe
embrittlement arising as a result of welding andfor
flame cutting operations.
Page
55 . ' 10 Shell insert type'rei"forcement
55 :. . 11;~B;ai.rbl 'type nozzle reinforcement . - . .. .
'

12 Graph for the determination of the thickness .


of .barrel type nozzle reinforcement '

13 Flanged roof nozzles


a l details for conmxtion of . - '
14 . ~ ~ p i cweld ,

mountings: set-throughtype (preferred


details): t = 20 mm (rnax.1
15 Typical weld details for connection of
mountings: set-throughtype (preferred
details): 20 m m Q t G 40 rnm .
16 Typical weld details for connection of '
mountings: 'set-throughtype (preferred
details]: t i > 40 mm
17 Typical weld details for the connection of
mountings: set-throughtype (alternative
details)
18 Typical weld details for connection of
mountings: compensated set-through type
(preferred details): t = 12.5 mm (max.)
19 Typical weld details for connection of
mountings: compensated set-through type
(preferred details)
20 Typical weld details for connection of
mountings: Compensated set-through type
(alternative details)
21 Typical weld details for connection of
8 Recommendations for the design and application mountings: set-on type (shell nozzles less
of insulation than 80 mm 0.d.)
C Standard diameters for vertical cylindrical tanks 22 Recognized weld details for connection of
.. D List of symbols mountings
.
. ... E, Recommendations for internal floating covers
'
23 Reinforcement details for low type nozzles
',F Recommendations for the design of venting 24 Detailrof overlay weld for nozzles
;:. + . .
. .: ; . systems 25 Details of an acceptable type of spiral stairway
'
' [ G Seismic provisions for storage tanks 26 Handrailing
27 Typical detail of earthing boss (supplied with
Tables tank) site welded to tank shell plates
28 Flush type clean-out door with insert plate
1 Leg length of fillet weld
reinforcement
' ..2 Minimum specified shell thickness
29 Flush type clean-out door with plate
3 Angle ring dimensions
reinforcement 915 mrn x 1230 mm
' . 4 Minimum sizes of top curb angle
30 Flush type clean-out door with plate
5 Manhole and nozzle body thickness
reinforcement 300 mm x 1230 mm
6 Extent of radiography per tank
31 Davit for 915 rnm x 1230 mm dean-out door
7 Acceptance levels for radiographic examination
32 Combined water draw-off and cleanout sump
8 Standard lengths for shell plates
33 Acceptable water draw-off sumps
9 Nominal capacities of standard vertical
34 Location of Charpy V-notch impact test
cylindrical tanks
specimen
10 Requirements for emergency venting
I 11 Soil profile coefficient
35 Typical tank foundation
36 Pad supports
37 Angle section and plate supports
Figures
38 Typical flanged nozzle or manhole
1 Minimum Charpy V impact requirements 39 Typical arrangement showing termination of
2 Typical bottom layouts for tanks insulation adjacent to.the tank bottom
3 Cross Joints in bottom plates where three 40 Typical arrangement with insulation attached
,' thicknesses occur to the shell only
4 Typical joints in sketch plates under shell 41 Typical flanged nozzle or manhole with
plates: tanks up to and including 12.5 m additional branch insulation
diameter 42 Typical construction of insulation local to
5 Typical annular plate joint under shell plates: wind stiffening ring
tanks over 12.5 rn diameter 43 Effective masses
6 Wind girders 44 Centroids of seismic forces
7 Shell-roof compression areas 45 factor K,
8 Typical tank anchorage detail 46 Compressive force w,
9 Shell manholes
.... .A"?. yz;,: ."/.? ,*
. . . . . '.., .:, . ." .). :'.t
. . ,>c. ..:~;,$,;,::i;.
.. .
Specification'

2.2 Design metal temperature (see 3.l(f))


1 Scope
The design metal temperature shall be specified by the
This British Standard specifies requirements for the purchaser on the basis of the official weather reports over
materials, design, fabrication, erection and testing of at least 30 years. The design metai temperature shall be
vertical cylindrical welded non-refrigerated st& tanks. the lower of t h e lowest daily mean temperaturet plus
10 OC and the minimum temperature of the cbntents.
The standard applies specifically to the needs of the
petroleum industry and the requirements for the design, For a storage tank cunstructed for service in the UK where
construction, inspection and testing of tank shells apply the sheti temperature is controlled by ambient conditions.
when the design relative density of the product stored will the minimum design metal temperature shall not exceed 0 OC,
not be less than 1.0. For a storage tank constructed for use outside the UK and
NOTE 1. This provides the petroleum industry with the necessary where no long term data or weather reports are available,
opera~ionalflexibility in that tanks originally designed to store one .
the design metal temperature shall be the lower of the
particular praduct can subssquently be utilized to stare products
of differing relati* densities when the need arises.
lowest daily mean temperaturet plus 5 O C and the
minimum temperature of the contents.
The standard applies to non-refrigerated storage tanks with
In the interests of operational flexibility, the minimum
the following characteristics:
design temperature for the tank shall not take into account
{a) maximum design pressure of 56 mbar*; the beneficid effect of heated or insulated tanks.
( b )design metal temperature not cooler than - 10 e ~ ;
(c) that are never filled above the level of the top of the
cylindrical shell or the ovetftow, whichever is lower. 3 Informationto be exchanged prior to
NOTE 2. For special cases outside the scope of this specification implementing the requirementsof this
where the design pressure lies between 56 mbar and 140 mbar.
reference may be made to BS 4741 for types of roof design standard and inspections by the purchaser
procedures. during erection
i n addition to the definitive requirements, the standard -
also requires the items detailed in clause 3 to be'hcu- 3.1 lnformstion to be specified by the purchaser*
mented. For compliance with this standard, both'the The following basic information to be specified'bv the
definitive requirementsand the doarmented items have purchaser shall be fully documented. Both the definitive
to be satisfied. requirements specified throughout the standard and the
NOTE 3. The titles of the publicarions referred to in this standard documented items shall be satisfied before a claim of
are listed on the inside back cover. comptiance with the standard can be made and verified.
(a) Geographical location of the tank.
(b) Diameter and height or the capacity of the tank,
2 Design conditions
including ullage. Where only the capacity of the tank i s
specified ground conditions shall be included.
21 Design pressure bee 3.'l(e))
(c) Whether fixed or ftoating roof is to be supplied
2.1.1 General. In the interests of standardization of design and the type of roof if the purchaser has specific
pressures, storage tanks shali be grouped as specified preferences, i.e. for fixed roofs (cone, dome, membrane,
in 21.2 to 2-74. etc.] or for floating roofs (pontoon, double deck, etc.).
2.1.2 #on-pressure tanks. Non-pressure tanks shall be {dl AH relevant properties of the contained fluid,
suitable for working a t ~mosphericpressure, Mdesigned including the relative density and corrosion allowance
.for an internal pressure of 7.5 mbar and a vacuum of (if, how and where required). . . , ..*..
-. 7 : +,;
2.5 mbar. I n ali cases the'tank shall pornply with 8.5. (el The design vapou; pressure and vaciaurn conditions ,;' $<BF'
.,.Fort.anks with columnsupported roofs, an internal inside'thetank (see 2.1).
". : :.-:&?;A
..
.-. .. ' ,. . +.. .L.:2,,rrl ' *.C
?
."
.
;
, .
....%. . . . .presrureof 4 rnbar. shall ..+ <;,-
. be assumed.
a
. . . ..*<<
.. .',7.x;7... . . ..:.:v. . . . . . . . . . . . . . . . . . .. . . .,,
'
_ .. . , . . . (f) me . . . . tem&a-:-$$$;?
minimum and maximum design. metal . .
. .),
tures (see 2.21. . . . . . .- ....:: . .. ~.. . .,- . ;;::2+
.1::-:,.'2.1.3,Lowpressure tanks. ~ ~ ~ , ~ & stanks
: : . : . : : . . ;.... ; i.' ,I ... f.;\:i s u rshall
e be ' 5 * k " )
;
.:,. . . :,,. . :.' . . . .
,.:
,c ,
i..
.......
.; ;,:;::.,I,
. . \"CL' .**
.... "
'.. ..< . . . . . . . ...
desi&edT+ a. internal prawre of 20 mbir a d vacuum .
&.,&&'.' .. ;. . . . . .
(g) he size, nu&bekand type D(sli
m,mti+i~u~i~j;$<;~
$'.. y..,p:::"
? :"

.., * ?._...
<./-p.:.r
<:?*.r-.-.;'
. . .,-: ; ..:.- -. . . . ... .. ... .. . . . . showing locations. Maximum filting arid e+-~yi,cg~ies;,;;.~9
,:........,
,-v,
. . ....
....
:,,,
..i2.
T
.:....;:;.;:z-, 2.1
~.r,..~;~~s::...
..
4 ~&h~rt+r+,tanks. High-pressure tanks,shall be
' . . ,+. :*,.;9;9r?f:
and any special vetiiing arrange+ntsA~see
.: ..-,. .>"!$@.
. . - ,,$Jc
....... -:-. '.-:.. .i:y.":;.".'i?:.
- < . " = - ; . ' ~ ~ , , '. ~ ~
(h)'The mi&&rn dtptti'of &&jb. (see 3s:j . . . &,):?.. .:-:,<?-$&
, ,
.:, z?~..~;,.; !j.r.;-: deiigned for'an internal pressure of 56 mbar and a vacuum
. :.,.. %,". * ,"?.."..
. x .:. .;. . :
>..I ..,.>$'. ,"; ,?- -;<::".:.;<&
. -..?L:.,,A*
. . +..:9, of 6,mbr.,.;. .. . . . ,:" , , ti) Ifthe tank is to &.'i:m~la& (j&'cfa;i'&$f2);. .; .$. . .,.-<;r$$
.
...+ ......,.
,,*,.. ,;. e
a
.. '.
; ..........
: .: : . . : .:' . . . . . . . . ,... . .:. - ; .. +.. ...";,:;:,;7
..."*.:*, ..;<.>::*: "<.*!. +*<. - .:._;< :~,"."~5:
:>:'. : ..: .: . . , , , * .. , , , ;. :.y, %..",,:-.~:~~.::;<#&:
: ,<
.:..7.".-:,.r;'%. . . . . . . . . . . . . . . . . . . . . .*.% . . . . . " '
............. :

..."', :.. ..,...r.$:. . ..... '.-::...


;..:. . . . . . . . .:. . .: . .:.. .<;-+. : : : y&$.$ J,..lr ,-
:.-,:?*:;.<?.? :,,y . . . . > .:$",<.. .. .
;. :.. . .....>:.>>a.l.. >. . . . . . . -.. .. . . .. .. :, . . .I.,:::&'25.;;,5- .y-.: i. . . '2:.-;;..3:.'i:T.s
- -2 7.'-' -'.'-&;?
':, . - ,, .. -- . , *:,-
..-* ," .-.-".."<. 5 .,;. ., .+
'
.. , , ;, . < > -5 :.-&;
.....&I-.. .,C..> ? y"..d:::l . . ..-..:>."?;,..
~<,
: ;."....*.". ;;.,+&' . .:;' .. ... .y
. .. +-:. . $:,

.- . .... . . . . . . . . . . . .-.,;.\.;.>...
..;. "<"<%>w-,
-
....I...

-
. . . ..,-; ? Yh . . , . . . . .'.'. . .. . . . . . . .. . .. . . .>.. .-.,..-...*... ..: ".~;,,~
'
.
. . . i ;\:.......
:&, ::?k;
..;..>.., ~~
@$.-w-:
........
;.y<.,.:-*
. .: ,:.:-,, "::=,';..: ,*f .mi;a&c'tOO ..".. Wl-..r
.'i,
- ;. . ' . . . .. .. .. . . .... : f;;.,:.... ;, >
:. ::::;>.*>- ,':'.
;:--<.- . ;.- ..--.-...
.+,... f;
...z L.c,. , . ':. rn y 100 Pa. . . . . . . . . <I; >;<,*;.
"..:. . .:%::.:,.>:
.
' . -, , .
~

-;:. - f ~%&&r;i~rntekpeiarure minimum temperature);' .+ . . . . . .


, :
;
. .....
. . .
., .
. .
:,
..
,,*:
,2...+ ,
< , &
;:;>;,."
:
., p
$ :?3?;?:,<7
& &%
:.:.
A .

...... :. .
. ...I;;.::
':&-:>, ':,:.;:,. : .., , .; ,,;.
. *w*re tke W O 'purchaser' ~ of the purcbw,&. pu+haser%(n'*~
nrmrs in the text. it is intended to include r e p r e s e n t a t i ~
. . . . ... .>1. ... ....."?'. . .:. .,:;..:1 . .:-....::1.$;,!
. . . . . .< . .; . .. . . . >.: 4;;:
. . I . .<?..,. ........ -, . .. .;y,..:.
,.-,;.' :':',;...1I:..! -
, .Z
3
..+ C
.... ..: .. . . . . . " .. . .':, ..:
. . . - .. ,
. , , '.-: .
. . ,. .\ . . >,-: . <.,:z.:
. '

I,:;. :.
"

(i)~etailsofpairitingrequireme& and k h e t phkling, ~~ . . . '1.


.:. .:.$..
these grit or shot blasting is required (see 13.6.1, 13.6.3 "~
' . . .
. .
. . . . and 14.12). . . . . .
., .' , .' .
,,." .
". . ,.' : ..-: ..- . .
.. .... ..ikl ~ q a l i t 'of
.*.?.. y thewater (particular&. if inhibiters are to (j)~ e t a i k o erection
f marks (&e 13-7.l):. ..... : . .
.. . : .... . .
T . ,. -..
.:?. . be pre&nt) to be used during hnkwater test bee 18.42). (k) Whether welding electrodes and/or key p1aGng. :. . .. .- . . ,
.:I .
-. . . . (I) Expected 'ikxirnum diffekential settlements during equipment are.to be supplied by the tank r&nufatiurkr . .
: j,?.
appendix :.:
. water testing and service lifetime of the tank (see
A)..", . . :'
(see 14.11. ' :. . _ . . .. . _. .<..,...,. ,".
. . !,' . "
.$.A:
.,. ,,.. . . . .
..b.
' ..
\' '
.. (I) Alternative &a&;gements for pib&iion.bf tank ..: :
' rr;.-
. . .(m) ~ t h t z rspecifications which arB to be read in . .
foundation (see 14.3). . .
.: . .. conjunction with this.standard.
' (m) Whether a welder making only fillet is
required to be approved for such welding in accordance
3.2 Optional and/or alternative information to be supplied with BS 4871 : Part 1 (see 16.3.2).
by the purchaser
(n) Whether tack welding of shell, roof and bortom i s
The following optional andlor alternative information to permirted to be carried out by non-approvedoperators
be supplied by the purchaser shalt be fully documented. (see 163.2).
'Both the definitive requirements specified throughout this
standard and the documented items shall be satisfied before (01Whether pneumatic testing of reinforcing plates is
required (see 18.3.1 1.
a claim of compliance with the standard can be made and
verified.
3.3 information to be agreed between the purchaser and
(a) Whether iheck analysis is required (see 4.3.2). t h e manufacturer
(b) Whether the weight of insulation is excluded from The following information to be agreed between the
the minimum superimposed loadings (see 5.3.2). purchaser and manufacturer shall be fully documented.
(c) Whether significant external loading from piping, Both the definitive requirements specified throughout this
etc. is present (see 5.5). standard and the documented items shall be satisf i d
(dl Whether seismic loading is present requiring specialist before a claim of compliance with the standard can be
consideration including methods and criteria to be used made and verified. .
I . in such analysis (see 5.7 arid appendix G). (a) Alternative materials selection (see 4.1). .-
(e) Whether a fixed roof is required and if so: (b) Precautions for avoiding brittle fracture during
(11 i f cone roof slope is other than 1 in 5 (see 81.2); hydrostatic testing (see figure 1).
(2)if radius of curvature of dome roof is other than (c) Alternative bottom plate layouts (see 6.1.2).
1.5 times tank diameter (see 8.2.2); (dl Spacing of the roof-plate-supportingmembers for
(3)whether made as a double-welded lap joint or a dome roof (see 8 3 1).
butt joint (see 8.3.5); (el Any increase in roof joint efficiency for lapped
(4) whether particular venting requirements are and welded roof plates (see 8.3.6),
specified (see 8.6.1 and 8.6.2). (f) Alternative loading conditions for floating roof
or (f) Whether a floating roof i s required and if so: design (see 9.2.1 -4).
(1) whether floating roof is designed to jand as part (g) The operating and cleaning position levels of the
of the normat operating procedure (see 9.1.1); supporting legs (see 9.10.1).
(2)whether floating roof i s designed for wind-excited (h) Proposed method to hold the plates in position
fatigue loading (see 9.3); for welding (but see 14.5.7).
(3) whether top edge of bulkhead is to be provided (i) The tocation and number of checks on shell
with continuous single filiet weld (see 9.5); tolerances during erection (see 14.6.2).
(4) floating roof ladder details (see 9.6.1, 9.6.2 (j) Methods of protecting the shell during erection
and 9+6.4); against wind damage, etc. (see 14.9).
(51type of primary roof drains (see 9.7.1); (k)ff fixed roofs are to be erected in the tank bottom,
and raised into position by an air pressure or suitable
( 6 )requirements for additional roof manholes
means (see 14.10).
(see 9.1 11;
(I)Sequence in which joints are to be welded
(7) whether maximum aromatic content of the
(see 15.2).
product is greater than 40 % h l m ) (see 9.13);
(m) If previously approvedappropriate welding
(8) requirements for the design of gauge hatch
procedures are acceptable (see 16.1.3).
(see 9.14).
In) Test procedures to be used during the tank water
(g) An alternative type of manhole cover (see 11-3).
test (see 18.1.1).
(h) Details of flange drilling i f not in accordance with
BS 1560 .(see 11.7).
3.4 Inspections by the purchaser during erection Bessemer steels nor rimming sted shall be permitted to be
The following inspections by the purchaser during erection used.
shall be fully documented, Both the definitive require- The tank manufacturer shall ascertain from the steelmaker
ments specified throughout this standard and the docu- (at the time of order) the condition of supply of all plates,
mented items shall be satisfied before a claim of compliance e.g. as-rolled, mrrnaliaed, or quenched and tempered,
with this standard can be made and verified. and the nominal composition of the steel.
(a) Rectification'of damage to materials prior to
erection (see 14.4). 4.3 Chemical composition
(b) Repair of all unacceptable defects found in welds 4.3.1 The carbon equivalent calculated from the ladle
(see 15.14.7). analysis using the following formula shall not exceed
(c) Additional radiographic testing of welds 0.43 % (mlm) for plates 20 mm thick up to and including
(see 15.14.2). 25 mm nor 0.42 % ( m / m ) for plates thicker than 25 ,mm.
(dl Records of each welder's approval (see 16-3.5.11.
(el Standard test radiograph (see 17.4.41.
(f) Repair of leaks in bottom and bottom to shell welds 4.3.2 The ladle analysis and check analysis, when required
(see 18.2.4). (see 3.2(a)), shall be reported by the steel maker as
(gl Leaks in pontoon compartments arid decks required by the particular steel specification together
(see f 8.5.3). with values for a l l elements specified i n 43.1 and including
any deliberate additions, e.g. aluminium, niobium, boron
or vanadium. I n a check analysis the carbon equivalent,
4 Materials using the formula C.+ Mn/6 shalt not exceed 0,43 % (rnlrn)
(see 3.2(;t)).The incidence of testing shalt not be less than
that specified in BS 4360.
4.1 Specifications
All materials used i n the manufacture of tanks complying 4.3.3 For steels with specified minimum tensile strength
with this standard shall be in accordance with appropriate greater than 420 Wmm2 the phosphorus plus the sulphur
specifications given in either (a) or [b), and as amended or shall not exceed 0.08 % (mlm).
amplified by the requirements of this st'andard. 4-34 Steels shall be either aluminium treated with a
(a) Plates, in accordance with BS 4x0 minimum ahminium/nitrogen ratio of 2:l or have a
sections and bars: (IS0 630-1980") nitrogencontent of less than 0.01 % (mlm1.
Forgings: in accordance with BS 1503 (carbon
and carbonlmanganese steels only) 4.4 Notch ductility
Bolting material: in accordance with 3s 1506 4.4.1 General. The required impad test temperatures and
Piping: in accordance with BS 3602 levels of impact properties for shell and bottom armutar
and BS 3603. plates shalt comply with the following clauses, as appro-
priate, together with 6.1.4 and figure 1:
(b) Otherwise suitable materials agreed between the
purchaser and the manufacturer {see 3.Na)) provided (a) clause 4.4.2 for materials <430 ~ l m r n 'tensile
that such materials are equivalent in heat treatment and strength;
chemical composition to those listed in (a) and, in other (b) clause 4.4.3 for materials >430 Wmm2 and
respects, comply with aH the requirements of this <490 N/rnmz tensite strength;
standard. (c) clause 4.4.4 for materials > 490 f4/rnrnz tensile
NOTE. Examples are forgings in accordance with ASTM strength.
A105 : 1982t. piping in accordance with ASTM A106 : 1982t or
ASTM A524 : 1980t or Grades A and B of API 5L : 1983*. For thicknesses not exceeding 13 mrn in materials with.
specified minimum tensile strengths up to and including . . ,
4.2 ~t&lrn&ing process 490 N/rnm2, impact tests are not required. ..

Steets shall be made by the open hearth, electric furnace NOTE. Steels may be -lied in conditiwrs@tther'th&nn-afizd:
when it is m be demonstrated to the satisfaction of the purchaser.,.
. . , .
or one Of the basic oxygen processes. Use of semi-killed that the manufacturing pmcedure le.g..contrded mlling, quench..
. . or fully-kilted steels shall'be permitted provided that they in9 and tempering, accelererred cooling, etc,)will provide equivalent
.. .. .
. comply with all the requirementsof this standard. Neither notch ductility. . . . . ., .
. .
. .

""'
. . . .... ., . , . ;. . . . ...1.: .,..
! .,>,.
. , . . <': . - ?..., : :
. ... - ..,.: > ..-...,.:[' .. : A

. .. *When specifying iSO 630-1980. published by the tnternational Organization for Standardization (ISO), i t is morn&nd<d tf;at.referey : :< k:.;
. .-.
..".(+a
. i s made to the appropriate national see1 standard for the purposes of specifying additional r e q o i r e m t s . m included t h g m h ~.. :
' : .....-.<.:. . .I::

, ~
& d ~ilt'6n
tPubli&ed by the American Society of Materials and Testing and available from the-Library. BSI, .Linf~rd , ~ ~ $ hM e s~.j 4,.: d f~.
i.i" (> "
, .
+Pubfishedby the American Petroleum Industw and available from the Library. BSI, tinford Wood, Milton ~ e y r r e s ' ~6~ il 4
~ .,
- >" . .~.
.-
... ' '";
>..,
.2. ,,
.>. . . . - . . . ..-z.r. : . . .. . . . .. . . . .. . . .
" ..., .. - . . . - ..
minimuin specifid y@d& a h for the $hill plates to"::': . , :..?

which they are atiiched,.~ile.bodiesshall also &&ply


with these requirementswhen the nozzle , b d y is used in
the reinforcement calculation. '
4.5.2 Permanent attachrnents,.rsinforcingplates, insert
plates, nozzle bodiesand flangesshall comply with the notch
ductility requirements:of.A.4. The refere&e..thick,r%ss. '
shall be taken &"thb ribminat.ttiidcn& o'f. .the bmponertt
except for the foliowing. .. . .
(a) Welding neck 'f/ang&. T& refeience thickness shall
"NOTE. Provided the design metal tomperaturn i s +10 *C or above,
"~
%iti s not necessary to test materials with a specified minimum yield
be taken as the thickness at the weld or 25 % of. the
strength mt e x d i n g 300 N/rnmz and less than 20 mm thick. flange thickness.. whichever i s greater.
(b)Hubbed or slipon flanges. The reference thickness
4.4.3 Materials with specified minimum tensile strengths
shall be-takenas the n o r n i ~thickness
l of the branch
greater than 430 N/mm2 and up to and including
to which the flange is welded or 25 % of the flange
::490 ~ I m m * thicker
, than 13 mrn. Materials with specified
thickness, whichever is greater.
'-:minimum tensile strengths greater than 430 ~/rnrn' and up
to and'including 490 ~ / r n m ' and thicker than 13 mm shall (c) Reinforcingplates. The reference thickness shall be
" be impact tested and show not Iess than 41 J Charpy V at taken as i t s nominal thickness and if such plates exceed
- 5 OC or at the rest temperature indicated in figure 1 , 40 rnm thick, they shall show not less than 27 J
whichever is the lower. Three specimens shall be tested, Charpy V at -50 OC, irrespective of the minimum design
the value taken being the minimum average of the three metal temperature. Three specimens shall be tested,
results. The minimum individual value shall be not less than the value taken being the minimum average of the three
70 % of the specified minimum average value. results. The minimum individual value shall be not less
than 70 % of the specified minimum average value.
4.4.4 Materials with wecified minimum tensile strengths
greater than 490 ~/mrn*,all thicknessesSMaterials with 4.6 Other requirements
specified minimum tensile strengths greater than 490 N/mm2
and of a l l thicknesses shalEbe impact tested and show not 4.6.1 -The measured thickness a t any point more than
less than 41 J Charpy V at - 35 OC or at the test temperature 15 mm from the edge of any shell (whosethickness shall
. indicated in figure 1, whichever is the lower. Three speci- comply with 7.1.3). bottom, roof or annular plate shall not
mens shall be tested, the value taken being the minimum be'less than the specified thickness less half the total
average of the three results. The minimum individual value tolerance given in table 8 of BS 4360 : 1979.
shall be not less than 70 % of the specified minimum 4.6-2 The measured thickness a t any point more than
average value. 15 mm from the edge of shell plates whose thicknesses have
4.5 Mountings been calculated in accordance with 7.2.2 to be greater than
as specified in 7.1.3, shall not be less than the calculated
4.5.1 Reinforcing plates and insert plates shall have a minimum thickness.
minimum specified yield strength not less than 90 % of the
Scales Scale A

temperature O C [see 2.2

Charpy V t e s t temperature OC

(fntermediate values may be determined by interpolation.)


NOTE. Scale A on the ordinate is to be used i n determining minimum Charpy V requirements for the thickness and
minimum design temperature concerned. For the purposes of this note.conversion of the measured impact value to the
27 J (or 41 J for steels with specified minimum tensile strength greater than 430 N/rnmlI value may be made on the basis
of 1.35 J per O C , such extrapolation being limited t o a maximum range of 2 0 ° C For example. ifthe actual value by test
.is 33.75 J at -20 OC for a steel of specified minimum tensite strength greater than 400 Nlrnm2.the equivalent test
temperature for 27 J may be assumed t o be -25 O C .
The requirements derived from scale A take into account an improvement i n safety which may be anticipated as a result ,

of the hydrostatic test. During t h e f i m hydrostatic test the degreo o f sewrity against brittle fracture may be rather less
,
.
than o n subsequent bading. Attention is drawn to the more conservative requirementsof scale 6 when consideratibn is: . .
m be given t o the use of this scale during hydrostatic resting of tank shells constructed o f steels with specified minimum
tensile strength greater than 430 N/mma.The application of scale B. or any alternative procedure regarding the precautions '
',
' '

to b e taken during water testing t o safeguard the tank from brittle fracture, is the subject of agreement between the
purchaser and the manufacturer {see 3.3[bl). ..
Figure 1. Minimum Charpy V impact requirements
.*.7
plates shatl be o r annular plate shall be fillet-welded continuouslyon., , .,; ' . , .
+.~,iapped,They ;hall be welded .onthe t o p side only w i t h a b o t h sides of ft% shell plate... . '1' ' . .. . .._ ..,...
':. " , -. . ..- . . .
'

?$4ult.fil& weld, and,with arninirhum lap o f five times the , *

The leg 'lengthof k c h fillet &eld:h$ll beequal t d t h e t h i c e . ., " .-


' ~ $ ~ : ~ i & of ~ plate['& & t i o n C-C o f f igun 2).
n ethe '~

ness of the sketch plate or annular plate (see sectioris 0-0,' ' ...
.'$:~:Jhi rectan&r
..=?, i.' .: ..pi&
, . . . >.
bnd the
sketch p tates shall be lapped
a d E-E of+.figure.2),except that they sha!l n o t exceed the , .. '. .
:i:+zwer,
.>. .
-+>.,':;
the
-: ,
anrluiac.ring
*
6hegmentaiplates where these are appropriate value given in .table 1 when t h e shell plate . .
.. . .- .
:;%,uset$ They rhali beweld'ed on the t o p side only w i t h a f u l l thickness i s ies'sthan the b o t t o m plate thickness.
..%:$+iilet weld.and the minimum, lap shatl be 60 mm (see
,f '

..%,:*&ction
. .-. E- E of figure 2).
. -. ~ "

1 Table 1. Leg length of fillet weld I


. .
.., .
At the ends of cross joints in rectangular plates and sketch
plates where three thicknesses occur, the upper plate shall
: be hammered d o w n and welded as indicated i n detail A
I Shell plate Log length of
I
n
' '

thicknos fillet weld .


. ,o r B o f figure 3 as a'corrective measure if the upper plate
'overlaps the lower plate. ,

6.2.2 For tanks of 12.5 m diameter and under, the ends o f


.the joints in the sketch plates under the b o t t o m course of
6 and over
shetl plates shafl be welded for a minimum distance of
. .. - 150 mrn as shown i n figure 4.
.. .
in the design o f high-pressure tanks (see 2.1.4), special
6.2.3 For tanks exceeding 12.5 rn diameter, the radial
consideration shatl be given t o the limitation of uplift i n
. seams connecting the ends o f t h e annular segmental plates
the tank bottom (see clause 10).
;'. shall be f u l l penetration butt-welded; a backing strip weld
.' 0.f the form shown i n figure 5 is acceptable. Typical layauts for tank bottom plates are shown in
sections A-A and 6-B o f figure 2.

Section X - X Section Y-Y

Figure 3. Cross joints in bottom plates where three thicknesses occur (see 6.2.1)
. . . .. ..
. . .,.
1

e d iprimary.? .." ..:., . ,


7.3.1;l Op&top tanks shall ' k e ~ p ~ v i d with
stiffening ring to ,mainfair1roundness when the tank js . ..:':.s . .. . . , L
:'
.
.
subjected t o wind load$ The pritnaiy ring'shall'be ldcated .; .1:: : , ''+

at or near the top of the top


. . course'and
. preferably dn the .: - ,

><- outside of the tank,sheli. ' . ' , .


3Wkisht
: . .. -. heisht less the seismic freeboard.
-. or-the
be
,f<i
'

a ~ l on the &ative density of


: ~ :.~ $ : k t c u ~ ; d t i ~ s hb'ased 7.3.1.2 Fixed-roof tanks with r h f struct~ireare considered . ..
to be adequately stiffened a t the top of the shell by tfie ;:
;.rrvi

@!'..st~re$~~du&,and this shall not'be less than 1.0.


. .
.
, ,
. , *, ,.. -.. . . . . .
structure, and a primary ring is not therefqre considered .. , .
27.2.2
Q- .. . ,The &il&kii ' i h i u l a $ih,atl be.iisedin'calculating
necewry. . .
., .. . . . .
,
.
'

.:.,&e k*,ir . .& i l i i m m . i k n t (in,mm} of shell plates {see 4.6.2): . .. ... .._. '
s
. _
:i >.,:, ;..:. '... .
7.3.1.3 The required minimum section modulus of the
' '

. D : f. ;
" ' %

.,
'- -.6.,::. .:2...~i .,-205 ' { .# ,l y i H , 0.3)
-.
.<:;:
>
,;-:

- +c ' primary stiffening ring 2 [in cm31 shall be determined by


~*...
.". . the equation*:
:'where
.. Z = 0.058 D H
H is the distance from the bottom of the caurse under
where
consideration to the height defined in 7.21 (in m);
D 'is the tank diameter (in m);
D is the diameter of the tank (tanks in excess of 60 rn
in diameter shall be considered to be of this dimen-
; w is the maximum density of the contained liquid under sion when determining the section modulus) lin rn);
storage conditions, but shall not be less than 1.0
H is the heightof the tank shell including any 'freeboard'
(in glml);
provided abwe the maximum filling height (see 7.2.1)
S is the allowable design stress (see 7.1) (in ~ / r n m I;* (in m).
p is the design pressure (this can be neglected for
7.3.1.4 The section modulus of the primary stiffening ring
non-pressuretanks) (in mbar);
shall be based upon the properties of the applied members.
c is the corrosion allowance (in mm). NOTE 1. It may include a portion of the tank shell for a distance
of 16 plate thicknesses below and, where applicabte.above the
7.2.3 The tension force in each course shall be computed ring shell attachment.
at 0.3 rn above the centre line of the horizontal joint in
question, except when adjacent upper and lower courses are When curb angles are attached to the top edge of the shell
.made from materials with different mechanical properties ring by butt welding, this distance shall be reduced by the
'and: .- width of the vertical leg of the angle. -,.
NOTE 2. Section moduli values for typical ring members are given
Hu - 0.3 ' HL - 0.3 in figure 6.
3.
Su SL' 7.3.1.5 Stiffening rings shall comprise:
where
(a] structural sections or formed plate sections; or
Hu i s the distance from the bottom of the upper course
(b)sections built up by welding; or
to the height defined in 7.2.1 (in m);
(c) combinations of such types of sections assembled
Su is the atlawable design stress of the upper course
by welding.
(in ~/rnrn');
NOTE. The outer periphery of stiffening rings may be circular
HL is the distance from the bottom of the lower caurse or polygonal.
to the height defined in 7.2.1 (in rn);
7.3.1.6 The minimum size of angle for use alone, or as a
SL i s the allowable design stress of the lower course component in a built-up stiffening ring, shall be
(in ~/mrn*I; 60 mm x 60 mm x 5 mrn. The minimal nominal thickness
then the thickness of the upper course shalt be calculated of plate for use in formed or built-up stiffening rings shall
using the modified formula: be 5 mm when its width does not exceed 600 rnrn and shall
be 6 rnrn if over 600 rnm wide.
t= -
0
(98wH +p) + C.
7.3.1.7 When stiffening rings are I m t e d more than
20s
600 mm below the top of the shell, the tank shall be
Furthermore, no course shall be constructed at a thickness
provided with a 60 rnrn x 60 mm x 5 rnrn top curb angle
less than that of the course above. irrespective of the for 5 rnm top shell course.and 80 mm x 80 mm x 6 mm
materials of mmtruction.
angle for top shell course 6 mrn and thi&er.

r h i r equation is b a d on a wind velocity of 45 mls (100 m.p.h.). If specified by the purchaser, other wind uelocitiez ( V (in mls)) may
be u& by multiplying the equation by tVl46)'.
-. --

Ssctmn through wind # i d ~ Ssction modulus

Member size* 8 mm
shell

cm'
-
-
-
-
&

Detail A top angle

Continuous f i l l e t -
weld
--
-
lnterntttent
weld --
Detail B curb angle

Continuous -
weld -
-
Intermittent. -
veld -
-
-
Detail C single angle

-
-
-
-
-
-
-

Detail D channel

b
t-
Continuous f i l l e t 374.8 1
473.07
577.15
686 89
802.38
922.93
1W9.08
Intermittent weld 1180.59
1317.40
1459.48
T60681
1759.34
1997.07
2079.98
-.- --- 2248.04
2421.24

Detail E formed phte


t4L-

*Mass per unit kngth given in parentheses, where appropriate.


Dimensions are in mitlirnetres, unlessotherwise stated.

Figure 6. Wind girders


. '... . " , .
..... . ' .... : " r , ' :.,.,. . , " .

:.&
. .:?.. ::;..A
i .
.. 1 .
.
. .

(c) 83 rnbar, for other fixed-roof tanks, i.e. 6 mbar V .= 60 rnfs, v, = 5 rnbar, so K = 6.040644
I

I
(design) setting, plus 2.5 mbar to allow accumulation
for the vacuum valve to develop full design throughput.
NOTE. A lower level of total vecuum may be used in the compu-
tation if this can be proven to be justifiable, e.g. with full-bore large
free vents or low pumping rates on non-volatile storage.
Hence

Hp = 6.040644 a = 3.254 rn

Since 2Hp < HE < 3Hp, two secondary rings are required.
7.3.2.7 T h e formulae to be used in the design of secondary These are ideally located at HE/3and 2HE/3, i.e. 2.444 m
wind sirders shall be as follows. and 4.888 m below the primary ring on the'equivalent shell.
The upper ring is on a shetl course of minimum thickness,
so no adjustment of its location is needed.
The lower ring is not on a course of minimum plate thick-
ness, so an adjustment is needed and its position below the
orimarv rins shall be:

The secondary rings are thus 2.444 rn and 5.353 rn below


where the primary ring, and are angles 200 mm x 100 mm x
12 mm.
D i s the tank diameter (in m);
Example 2. A fixed-roof non-pressure tank 48 m diameter
tmi, is the thickness of the top course (in mm);
22.5 rn high having nine 2.5 rn courses of thicknesses 8,
t i s the thickness of each course in turn (corroded 8,10.6, 14.3, 17.9, 21.6.25.3, 29 and 32.6 mm is to be
condition where applicable) (in mm); designed for a wind speed of 55 m/s, How many and what
h i s the height of each course in turn below any i s the location and size of secondary rings?
primary ring (in m); .- Course h f
He
He i s the equivalent stable height of each course m rnm m
at t m i ,(in m); 1 2-5 8.0 2.500
H E i s the equivalent stable full shell height 2 2.5 8.0 2.500
at tmi, [in m); 3 2.5 10.6 1.237
V, i s the design wind speed (in mh); 4 2.5 14.3 0.585
v, i s the vacuum for design of secondary wind girders 5 2.5 17.9 0.334
(in mbar); 6 2.5 21.6 ' 0.209
K is a factor; 7 2.5 25.3 0.141
8
H, is the maximum permitted spacing of'rings on shells
'
9
of minimum thickness (in m).
Example 1. A floating-roof tank 95 m diameter, 20 rn high
having eight 2.5 m courses of thicknesses 12.0, 12.0, 14.2,
19.7.24.7.29.8, 34.9 and 39.9 mm is to be designed for a V, = 55 m/s, v, = 5 mbar, so K = 6,945
wind speed of 60 m/s. The primary ring i s located 1.0 m Hence
from the tank top. How many secondary rings are required
and what are their sizes and tocation?

m mrn rn
<
Since 2 H , < HE 3Hp, two secondary rings are required. .-;. '

These are ideally located H E / 3and 2 n E / 3 ,i.e. 2.561 m . .."


.
and 5.122 m from the tank top. . ..-,:...
. \
, . ".
The upper ring is on a shell course of minimum plate . ..,,,':'..,~'. ,
. a k .

thickness, so no adjustment is needed. . .


. . . . < : .. . '

The lower ring i s not on a c&se of minimum plate thick-r,'::?$


ness, so an adjustment i s needed and i t s position from the.. ..?;:...
. ' .. .

JC)'
tank top will be: ,...
.
j

. " . . 3 .:';
. . .. ,.
(5.1 22 - . O i510- 3 . 2 ~ 0 ~
.
' ' , ?.,.' :.-',: ,
. . . . .
. .... .. ,:

-. -
The secondary rings are therefore 2.561 m and 5.250 m
from the top and are angIes 150 mm x 90 mrn x 10 mm.
. .
(.
. . . ." ...
I " . ,
r. .:
I. j

(b) Additional vertical ring bracing, on trussed roofs For buckling:


only, shall be provided in an approximately vertical
plane between the trusses as follows:
( I t roofs over 15 m up to and including 25 m where
diameter: one ring;
R , is the radius of curvature of roof (in m)
(2) roofs over 25 rn diameter: two rings. {for conical roofs. R , = Rlsin0; see figure 71;

8.4 Roof ptating'witfrout supporting structure P, i s the external Ioading plus self-weight of the
(membrane roofs] .
1; ~
plates (in k ~ / r n
E i s Young's modulus (in ~/mrn'1;
8.4.1 All membrane roofs shall be of either butt-welded or
double-welded lap construction. p i s the internal pressure (in rnbar);
S i s the allowable design stress (in ~ l r n r n *1;
8A.2 Membrane roofs shall be designed to resist buckling
due to external loading and shall be checked for internal tr i s the roof plate thickness (in mml;
oressure. 9 i s the joint efficiency factor as specified in 8.3.6.
For pressure:
8.5 Compression area
tr= -pR1
20sq
(for spherical roofs) 8.5.1 The compression area is the region at the junction of
the shell and the roof which is considered to resist forces
r,= -
pR1
l0Sq
(for conical roofs) imposed by the internal pressure and the maximum widths
of plates making up the compression region shall be as
shown in the shaded areas of figure 7.

R, is the radius of curvature of roof (in ml [for wnicat roofs = RlsinO);


R is the radius of tank shell (in m);
t i s the thickness of shell (in mm);
t, is the thickness of angle stiffener (in mm):
t , is the thickness of roof plate at compression ring (in mml;
Wh is the effective roof length (in mm).

' . Figure 7. Shell-mof compression areas (see 8.5.1)


;:ii,+h&& ;.: . - -.." .- .> .v 1. .... " - .. . .,:, . .. .,.
,. . . :.
'
. < ,,
. ,
. . . .,
:* . . . . . > ,,

?&-('. ;,." prevent the ingress of b&di he &,of,fine-m& &&ins as ',. :..:.;' .: ..< . ,

..+ -
... -...:-, is,thi+~ n t e n i a 1 : ~ r k + ~ ' $ L 2 ~$&;weight
.r;!z;p'f
---
.+$...
.!$:,.
+k-..w,.:.<
>,
7 ... i' &&td '(in:'mbxj;.: ..',.::
....
-
.
.<;.:
..
1
,: , . .
o f roof'
'
. .
anti-flash p r 0 t e t i o n . i ~
of blackage, +pekiafl$.mmd~kilt~
.?...
?f theda,"cJef .:.';.';
&t'r~~?rrim+~Ied:bec+~~
cpn$tians.),::;: I
. 'i,.:;, ~ ..:. .-,.:-:. . ..
..,, ... . ..'. i . .:. . .-"... .: ..
'.-;:i:$:::.,.r.< .
.r;-.:?;'
... G t h i ~ t ~ p e . s @ . r o o f , ~ iadt iroof-rhell
ai; connection ~onsideration'lhouldbe &n to iti;:possibilityo f &rrasbn %en - .,i. ., . :. .
!:z<.2:.
.. 7
:
:..
(see figure'7) (in.de&ees);
'
. .
selecting material for the wire mesh screen.

:,".,'h is the radius o f tank {in m);


hk* . .
.,
8.6.4 Accumolatiun of pressure and vacuum
..
...;.: S, it the alIowa<le compressive stress {which, unless
T.

. .. .. otherwise specified, shaH be taken as 120 ~ l r n r n ') 8.6.4.1 In accordance w i t h 7.3.2.6, the set vacuum plus the
':: . ,. :. (in N/mm2 ). accumulation t o permit the valves t o achieve the required
L: '
throughput shall not exceed v,.
.?&;3 If a horizontal girder is required t o provide additional
-"*:ffoss-sectional
..- area, this girder shall be placed as close t o 8.6.4.2 In accordance w i t h 2.1, the set pressure plus'the
;'.the junction as possible and a t a distance always less than accumulation t o permit the valves t o achieve the required
.".theeffective shelt length'for compression area W, (see throughput f o r normal pressure relief shall n o t exceed the
,...figure 7 1. .. design pressure.

8.5;4 The compression area shall be checked for tension 8.6.4.3 No specific values for emergency pressure a m m u -
. loading due t o external pressure and/or vacuum condition. lation are specified in this standard b u t the following
considerations shall apply.
'8.5.5 When using a structurally-supported roof, care shall
(a) ff it is expected that the design pressure specified
. . taken t o avoid excessive bending in the compression
:be
i n 21 is to be exceeded by the emergency pressure
'region a t the rafter connection t o the shell periphery.
accumulation, then it shall be verified that the strength
:;-8.5.6
.*. For fixed-roof tanks the minimum area defined o f the roof-to-shell junction is adequate and whether
.&
A in 8.5.2 or the mirrikm sizes of t o p curb angle given
:>::.:-by 'tank anchorage is required.
'::.intabfe 4, whichever is the greater, shall be provided. NOTE. This particularly applies to wlumnsupported cone roof
tanks with a low roof slope and to small tanks i n general.
sizes of t o p curb angle
Table 4. ~inimurn (b)f he set pressure of relieving devices for emergency
conditions (if required) shall be consistent w i t h the
Tank diameter D Size of curb angh provisions o f F.5.2.
(c) Account shall be taken of the substantial differences
rn .i rnm between the opening and closing pressures (blowdown)
D <lo 60x 6 0 x 6 that can occur between vents o f different types..
10<D<20 SOX 6 0 x 8 NOTE. This standard does not cater for protection against over:
20<DQ36 8 0 x 8 0 x 10 pressure caused by explosion within the tank, and where such
protection is t o be provided special consideration should be given
36<D<48 100 x 100 x 12 to the design of the tank and the venting devices.
48<d 150 x 150x 10
j
9 Floating-roof design
8.6 Venting requirements
8.6.1 General. The precise requirements for t h e venting of 9.1 General
fixed-roof tanks designed t o this standard shall be either
particularly specified by the purchaser (see 3.2(e)(4)) or 9.1.1 A floating roof, being a structure designed t o float
as specified i n 8.6.2 t o 8.6.4 inclusive. o n the surface o f the liquid i n an open top tank a n d t o be
in complete contactwiththat surface, shall comply w i t h 9.2
8.6.2 Scope of venting provided. The venting system t o 9.15.
provided shall cater f o r the following: NOTE. This clause is not applicable t o the design of floating covers
(a) normal vacuum relief; installed in fixed-roof tanks in accordance with appendix E.

(b)normal pressure relief; The requirements of this clause, unless otherwise qualified,
shall apply only t o the pontoon type and double-deck t Y w
(c) emergency pressure relief.
of floating roofs which shall be differentiated as f o l ~ w s :
In the case of (c), this shall be specified in accordance with
(a) a pontoon type roof has a continuous annular
this standard unless disregarded a t the purchaser's discre-
pontoon divided by bulkheads into liquid-tight pontoon
tion (see 3.2(e)t4)). Where emergency pressure relief is
compartments and has a centcal area covered by a single-
required, it shall be provided by suitable vents or by the
deck diaphragm;
provision o f a frangible roof joint (see F.3).
,-. -
: .. ..(b) adouyedeck 'roof has both an upper and a lower carries a 250 mm rainfall over the entire roof area in
deck extending over the area of the liquid surface, a 24 h period and the primary roof drain is considered
the lower deck iq contact with the liquid surface being to tze inoperative. . G*
'.:
separated from the upfier deck by rim ptates and bulk- NOTE. Such a requirement may be satisfied by designing the
'"

'head plates to form liquid-tight pontoon compartments. roof to carry the entire 250 mm rainfall or alternativeiy a
lower load may be a w r n e d provided adequate emergency . '

In mrrnal operatian, the roof shall remain in the floating drains are fitted which will discharge the excess rainwater .
condition and shall only be landed on to i t s support legs directly into the pmduct.
for maintenance6r inspection purposes. The purchaser When emergency drains are fitted, they shall not permit
shall specify whether the floating roof is to b e designed the product to flow on to the roof.
to land as part of the normat operating procedure
(see 3.2(f)(l)), otherwise this requirement does not apply. 9,2.?.4 Afternative loadingconditions. By agreement
between the purchaser and the manufacturer (see 3.3(f )),
9.1.2 The roof and accessories shalt be so designed and it shall be permitted to design the roof for a fixed specific
constructed as to allow the tank to overflow and then gravity, a fixed product, or a specified amount of rainfall
return to a liquid level which floats the roof well below the deviating from the requirements of 9.2.1.2 and 9.2.1.3.
top of the tank shell without damage to any part of the
roof, tank or appurtenances. This requirement shall apply 9.2.2 Strueturn1 design. The roof shall be designed to be
under both service and hydrostatic testing conditions. structurally mund under the following loading conditions.
If a windskirt or top-shell extension i s used for the purpose (a) Buoyancy conditions as specified in 9.2.1.
of containing the roof seals a t the highest point of travel, {b) When the roof is landed on its support legs and with
overflow drainage openings shall be provided to indicate the a superimposed load of 1.2 k ~ / m (the~superimposed
rise of the liquid level in the tank above the designed toad is not intended to indude any accumulated rain-
capacity height, unless the tank shell has been designed for water). . -
a liquid height to the top of the shell extension. .. .
>',
.-
9.1.3 The specified thickness of all roof plating shall be
9.3 Stability of roof under wind load .._
. . .-...
-,
not less,than5 mm .[see 4.C"l). The purchaser shall advise the manufacturer wheii tanks :.:.
are to be erected in areas where wind conditions could gkk
'

9.2 Design requirements rise to fatigue loading which-couldresult in centre deck .


weld cracks in normal pontoon type roofs, particufarly
9.2.1 Buoyancy for tanks over 50 rn diameter, and the design and type of .
.
9.2.1.1 General. The roof shall comply with 92.1.2, 9.2.1.3 roof to be used shall be as specified by the purchaser
or 9.2.1 A, as appropriate. (see 3.2(f)(2)). Otherwise, no account shall be taken of .
c,. .
wind-excited fatigue loading.
9.2.12 Singledeck pontoon roofs. The design of single- . ,

deck pontoon roofs shall comply with the following. 9.4 Pontoon openings ..
(a) The minimum pontoon volume of a singledeck Each compartment shall be provided with a manway with,
pontoon roof shall be sufficient to keep the roof float- a rain-tight cover. The manway covers shall be so designed.' .:
ing on a liquid with a retative density not exceeding 0.7 that they wilI re-seat if lifted by any gusts and not blow .;I:' c:
' -
'

ifthe single deck and any ~ n r opontoon compartments


\

I
off under the specified wind conditions. . . .:.;:... .
are punctured and the primary roof drain is considered The top edge of manway necks shaA be at an elevation .. . . . . t6''1.::3~
as inoperative. prevent water entering the compartments under the .~ ..-u:.;.
-. fb) The minimum pontoon volume of a singledeck ........
conditions specified in 9.2. . --I..
. . . .,:,
.
. .. . . porkon roof shall be sufficient to keep the roof float-
, ,"'.-< ><'"
+,I '5 '

. .-
.. ' '

. . ing on a liquid with a relative density not exceeding 0.7 9.5 B u i k h d r


-;;,L.".>z~..'.
. ..l.

. . . ~ . .. . g:v;y+:,
. . . . .> ,';,,
.
, " 1 ,;. ,,,,::
,
.: %..
, .: . .: i f it carries a load of 250 mm rainfall over the entire
'
Either a l l internal bulkhead plates shall bs at l!ast singt@--j:G;
. . . . . . . . .'i:. : ...roof area con&ntrated on the centre deck a'nd the
.... .:.:.- :.,; x . . fillet welded along their bottom and vertical edges for ::$$:<:
.- . .. .. . . :: p r i k r y roof drain i s considered as inoperative. No pon-
liquid tightness, or when specified by the pu'rciiaser "'r, ;$$$$$,
, ,
.....
-. . . ). , -: r .
, toon compartri.le&.& centre deck shall be donsidered
. . . b e 32(flM)I, the top edgebf the bu&hdl W l l &I+
$zz$
' " - i Y . ; . , . I . , . ' .
./..I. :-';.:-.-;=C:::b;,,
'
.. . :, . . .r.,.8 4:
.. ... .~. . . . ?.... ...;;.....:...
.' '.
i
.:-:.tbe
. . .
o p u i i m u d ' f o i this condition.
. . provided with a wntinuous single-filfefwefd " . , . for.:liquid
. . .
.
. .. ".......... +

".,?,>!, ..><..:."?
:9:2!.3. dirubh+ck
. roofs. The design ofdouble-deck tightness. . .
. .. ..,,,<:.,. ,.,;* ?", .
.
. . . . . . .
,. . . , ,
. *
;; .L .,;";:"&;
'+.'.6,2dL'
,

.... .-:,&+F'
,
'"L*;:?+:,

. >,>; ...A

.. ,..-. .:.. :. ::: :.:-. roi;fs,?d '&mply with the folfowing. '.':. . . . . Bulkhead plate corners trirhmad fb;r'pai&ge df - - . .. : as~ , k & .
. .-:longitrjd~rigf%
fillet welds shall be .filled by.&hdi@'tp obtain liqdiq .
... . . .. . . .,. . . . - . ..: ... .-;??:?:rn.;:
....
...... . tightness. .
..
. ...,:, . . < ......
, .....
... :... .:
. .... ... .. .....
.:-' . .~::.
.: 1; :;;
'
,,;
.. :.. . :.. ..' .. <. ... .. .. . .. .,,>
.,:
%;. .-3-
a..P'.<
*2&l:i3z
+. ;?. j.:..

I -
. . .".'.'.%..; *?

9.6 M&,able t*.moft t_ .-......(; :_.: <+,: .... ;:.:>.: .:.+:-?+


~. . . . . .-... ".. . ... .? ,
.;....
% ;-.
. ,;;,.,-.,.. ........... ".?3;,::;izz::.:j
-....... :.,
i
f ,-
.,
,:,.,:,2,x,; : . &:'"
.. ,+ .. .;1;j
"{
.4:%?$$
:3$3::
.
9.6.1 Unlesi dthkmik &cifidby i h ~ - p ~ ~ ~ h+ .& a$
;$+?& i,
(see 3.2(f )(4l),the 'fioating r&f. sha1I .be:s&pf&. ~ i r t h , a;i:;ii
1adder.whici-i autoetically . . idjur&-to~~~Y~@rtt<nn&~~@
:. ...-.. * . : ... ..~ b. . .+,. . * .........
. ? . . .s.
........ ,+. ........... :..:.
%<
,.,

;>,: ,:..;\:."
. . . . .. - .. . .. .. . .\. .. ... . .. . .. . . :-..4-3>: .$-..:.
.. .
' . .,V(.

. . .. . ,... .. ; . .,- ,. . . . . ?:<., .:;*..%' . +:~.:;:


> .
. . .. . ,,.,*. :..
. .-. .. . .- . ,::. ,;,*. < ..: ."" ...
' a
.- - ~
- '
' i ' ,
:. . . . - 5

.... ... . . :):':'. ....


. .

. .

, ." the
."roof, The 1a;ider shall be designed for f u l l roof travel,
: wardless of normal setting o f roof-leg supports. If a rolling (a) one 75 mrn drain for roofs up t o and including
.";j
. .@er is fumjshed, it sha#l:havefull-length handrails o n 30 rn in diameter;
"bbth $id&apdshall be'desillrredf o r a 500 kg-vertical (b'l one 100 mm drain for roofs more tdan 30 m i. n. . .
.'%&point toad *tti '?h$!.ladder in.'& 'operating position ' ,
,:. ..
*-.*.~

:~Fdf&'tio*.i,f &
. . I . . . . . . .., . .
,%.,. ....
.'- '.
.,_......
"
;.:kqnbiried w i t h z h e maximumwin$ load pcting in any
!aer;
. ' - '
diameter;

diameter.
:
. .
. . .. .
, ." . '. . . . j .

, ' ; ~ ~ ~Consideration
TE: &ould&u be tb the&ratian effects
' a f w i n d loadiriq arid torsional rigidity of long ladden which can
..&d to the derailing of the ladder. 9.8 Emergency drains
NOTE I . Pontoon roofs. Open emergency drains should not be
9.61 The fadder shall be equipped w i t h self-levelling treads be installed in pontoon type roofs as the product level in the tank
unless specified by the purchaser (see 3.Z(f) (4)) that fixed is always higher than the rainwater lewl on the centre deck.
rungs are t o be used.
A 100 rnm diameter emergency drain plug shatl be located
NOTE I. When fixed rungs are used, i t is recommended that safety
near the centre of the roof t o permit the drainage of water
wire netting shoutd be provided on the underside of the ladder.
when the roof is landed on its support legs.
--NOTE 2. Attention is drawn to the need for careful selection of ,
NOTE 2. To prevent backflow of the product, measures should be
: heights for smalldiameter tanks to permit the use of movable
-
ladders. taken to avoid this drain plug being opened in m i c e .
NOTE 3. Doublededc roofs. Open type emergency drains may be
9.6.3 The ladder shall run over a track, which shall be a t installed at the centre of double-deck roofs which will discharge
such a height over the deck that snow or ice w i l l not taus rainwater directly into the product [see atso 9.2.f.3(bl).
',. derailment o f the ladder.
.,.-...
, , For long and heavy ladders, special attention shall be given 9.9 Vents
t o the bearing w i d t h o f the rails and the strength of the The purchaser shall specify maximum liquid filting and
:- wheels. withdrawal rates and any special venting requirements
.
(see 3.1 (91I.
,+.

;, 9.6.4 Unless otherwise specified by t h e purchaser


.,j. {see 3.2(f)(4)), flameshields are not required t o be fitted Suitable vents shall be provided t o prevent overstressing o f
:.' to ladders. f f flameshields are fitted, the effect o f the the r o o f deck or seal membrane. These vents*& bleeder
.A-

'increased wind loading shall be considered i n the design o f valves shall be adequate t o evacuate air and gases f r o m
..~ . underneath the roof during initial filling and when the
.'. the ladder and track.
.;/
-i product is being withdrawn w i t h the roof landed o n its
9.7 Primary roof drains support legs. Operating legs for such vents shall be adjust-
able t o suit the various level settings o f the roof-support
.i:.9.7.1 Primary roof drains shall be of the hose or legs.
articulated-pipe type unless otherwise specified by the
-6.
- purchaser (see 32(f)(51). 9.10 Supporting legs
NOTE. lf specified by the purchaser, open type roof drains may
be used on doubldeck roofs.
9.10.1 Design of supporting legs. Floating roofs shall be
provided w i t h supporting legs. Legs fabricated f r o m pipe
Roof drains shall be capable of operating under all shall be provided w i t h a 50 rnm x 25 m m notch at the
specified service conditions o f t h e mof. bottom t o provide drainage. When variable roof levels are
9.7.2 A check valve shail be provided near the roof end required, the legs shall be adjustable f r o m the t o p side o f
of the hose, o r articulated-pipe drains shall be provided on the roof. The operating and cleaning position levels o f the
single-deck pontoon roofs, t o prevent backflow of stored supporting legs shall be agreed between purchaser and
product on t o the roof i n case o f leakage i n the hose or manufacturer (see 3.3(9)).
the jointed pipe. The manufacturer shall make certain that all tank appur-
tenances, such as side-entry mixers, interior'piping and
9.7.3 Provisions shall be included t o prevent kinking o f
filling nozzles. are cleared by the roof in its lowest position.
the hose or pinching under the deck legs.
The design o f the supporting legs shall not allow p r a d u a
Hose drains shall be designed t o permit replacement without
t o flow o n t o the roof deck'when the roof is loaded w i t h
entering the tank.
the maximum specified rainfall.
9 - 1 4 The articulated joints of pipe drains shajl be designed
9.10.2 Loading. Legs and attachments shalt be designed
t o prevent leakage, b o t h o f water i n t o the product and
i n accordance w i t h BS 449 t o support the roof and a live
vice-versa.
load of 1.2 kFJ/m2. Where possible, roof loads shall b e
9.7.5 The installation o f either type o f drain shall include transmitted t o the legs through bulkheads o r diaphragms.
the installation o f the proper shell fittings for i t s operation NOTE. These loadings do not make provision for any oil or water
and, if necessary, its removal. load or the possible effects of frequent landing of the roof (see
also 9.1.T).
9.10.3 Distribution of 1% laads. Measures shall be used, in the lowest part of the roof drain outside the towest shell.
such as steel pads, to distribute the leg loads &I the bottom course.
of the tank. I f used, pads shall be continuously welded to NOTE. The manufacturer should supply the purchaser with an
the bottom plates; shim plates, also continuously welded operating and maintenance marmat which should set out the design
and operational limitations of the floating roof and should include
to the bottom, shall be used when these pads coincide with
at least the following points.
lap joints in bottom plates.
La) Pontoon compartmentsand centre decks should be checked
for lealcs at regular iqtervals; such leaks reduce the water-carrying
9-11 Roof manholes capacity of the roof.
At least one roof manhole shall be provided for access to (b) If the primary roof drain is normally kept closed when the
the tank interior and for ventilation when the tank is empty. roof is floating, rainwater should not be allowed to accumulate
Any additional roof manholes shall be specified by the on the mof but in any case the roof drain should be opened
when water equivalent to about 75 mrn rainfall has collected.
purchaser (see 3.2(f)(6)). These manholes shall be a t least
(c) I f the primary roof drain is normally kept open, frequent,
500 mm inside diameter li.d.1 and shall have tight-gasketed
inspectionsshould be made to ensure that leaking articulated
and bolted covers. joints or punctured hoses are not permitting the product to
escape through the drain.
9.1 2 Centering and anti-rotation device (dl When the product temperature is expected to be less than
Suitable devices shall be provided to maintain the roof in 0 O C, the roof drain should be drained o f entrapped water and
then closed and the precautions outlined in (c) observed.
a centred position and to prevent in rotation. These devices
shall be capable of resisting the lateral forces imposed on [e) The purchaser should ensure that the recommendations set
out in such a manual are carefully observed by his operator.
them by the roof ladder, unequal snow loads, wind loads,etc.

9.13 SeaIs
The space between the outer periphery of the roof and the
tank sheil shall be sealed by a flexible device which shall
10 Tank anchorage
provide a reasonably close fit to the shell surfaces.
If the sealing device ernployssteel shoes in contact with the 10.1 General
shell, such shoes shall be made from either stainless steel or
galvanized sheet with a minimum thickness of 1.5 mm. Tank anchorage shall be provided for fixed roof tanks if,
with one of the following mnditions, there may be a
An adequate number of expansion joints shall be provided tendency for the shell and the bottom plate, close to the
to aid the efficiency of the sealing. shell, to liftoff its foundations.
Adequate means shall be provided to prevent an electrical (a) Uplift on an empty tank due to internal design
charge on the floating roof causing sparking in or above the pressure counteracted by the effective weight of roof
seal, fn the cased seals with jointed mechanisms in the and shel!.
vapour space. a shunt shatl be provided between the roof
and shoe plate at every such mechanism. (b) Uplift due to internal design pressure in combination
with wind loading counteracted by the effective weight
Any fabric or non-metallic material used as a seal or a seal of roof and shell, plus the effective weight of product
component shall be durable in i t s environment and shall considered by the user to be always present in the tank .
not discolour or contaminate the product stored. The pur-
(see 3.14h)).
chaser shall specify the maximum aromatic content of the
product which the fabric is required to resist, if greater Tank weights shall be considered after deducting any
than 40 % (m/m) (see 3.2(f)(7)). corrosion allowance.
The manufacturer shall specify the maximum inward and
10.2 Anchorage attachment
outward movement of which the seal i s capable. .*-.
The anchorage shall not be attached to the bottom plate . . . .:;.'
'

xu

9.14 Gauging device only but principally to the shelf. The design shall a m m - ,;?:;<,,
Each roof shall be provided with a gauge hatch or gauge madate movements of the tank due to thermal changes and :<;,:;:
welt with a tight cap either as specified by the purchaser hydrostatic pressure and reduce any induced stresses in the,+?,f,
(see 3.2(f)I8)) or to the manufacturer's own standard. shell to a minimum. .;, -. ..
.,,$Lp %~

. . . - ..
NOTE. A typical example is shown in figure 8 t;ut other design
. :-.,.;zl::";
9.15 Operatian details are permissible. .. ("." '
< "
.. . .%<,." .....
, ,! ;. .:. .4:
. . . . . .........
. . . ..l..C I
9.15.1 The design conditions specified in 9.2 shall not be 10.3 Allowabte tensile stress . ...
,
. ...,.... %....
% .
considered as normal operating conditions but, as the 7 . . . . ;...;s+;:
.. For the design conditions given.'i& aalioy,mble.teniilestre&,$;:-
ultimate conditions for flotation of the roof.
in the anchorage shall not exceed one-half of the'ipecifikd';:+;;:
9.1 5.2 When primary roofdrains are closed in winter, minimum yield strength or one-third of !he minimum . . . :.:, '?$. -
' . . . :. measures'shatl be taken to prevent the freezing of rainwater tensile strength, whichever'is the lower. . : .: ': . . ?
.:::::,.!;;", :,. '. ..
. . . . . .
. . . . . . . . *
. .-. .$ .
. :. . . ,.. .....
. ..- .'.,. . .I . . '
Min~murn dimension
p o s s ble
~

Lock nut ,._


Nut -, ....--'--

Spreader -
washer

Tank bottom

1
Section A-

Slotted hole in
. anchor bracket
to a l l o w r a d i a l
movement of tank

Figure 8. Typical tank anchorage detail (see 10.2)


10.4 ~oldingdownbolt or strap t is the thickness of the shefl plate (in mm).
Each holdingdown bolt or strap shall have a minimum NOTE. The reinforcement may be provided by any one or any
combination of the following three methods, A corrosion allowance
cross-sectionalarea of 500 mm2 and, if corrosion i s antici- on any surface should be excluded from the computation of rein-
pated, a minimum corrosion allowance of 1 mm, e.g. 2 mm forcement required.
on diameter, shall be added. (a) The addition of a thickened she61 insert plate (see figure 10
NOTE. I t i s recommended that anchorage points are spaced at a and figure 231,or a circular reinforcing plate, the limit o f
minimum of 1 m and at a maximum of 3 rn intervals and should reinforcement being such that:
as far as possible be spaced eventy around the circumference.
where
10.5 Resistance to'uplift do i s the effective diameter of reinforcement (in mm).
The anchorage shall be capable of resisting the uplift A noncircular reinforcing plate may b e used provided the
produced by the test loads applied to the tank. For this minimum requirements are complied with.
condition the stress in the anchorage shall not exceed (b)The provision o f a thickened nozzle or manhole body.
0.85 times t h e specified minimum yield strength of t h e The portion of the body which may be considered as reinforce-
anchorage material, taking into account any initial tension ment is that lying within the shell piate thickness and within
a distance of four times the body thickness from the shell plate
in the anchorage members resulting from bolting loads or surface unless the body thickness i s reduced within this distance,
loads due to transient or long-term thermal movements. when the limit is the point at which the reduction begins.
NOTE. I t is recommended that no initial tension be applied t o the Ic) The provision of a shell plate thicker than that required
anchorage. so that it becomes effecrive only should an uplift force by 7.2 subject t o the limits specified in 7 - 1 3 The limit of
devefap i n the shell of the tank. Steps shatl be taken before the tank reinforcement is that described in (a).
goes into service to ensure that anchorage bolts cannot work loose
or become ineffective over a long period. 11.I .2.3 As an alternative to the area replacement methods
specified in 11.I .2.2, the reinfarcement can be made by
the provision of thickened nozzle body protruding to both
11 Mountings sides of the shell plate as shown in figure 11. The thickness
of the nozzle is to be determined by reference to-figure 12
11.1 Shell manholes and s h k nouter 80 rnm outside such tKat the stress.ooncentration factor j does not exceed 2.
diameter (o.d.1 a n d above
11.1.1 The thickness of the manhole and nozzle bodies
shall be not less than that given in table 5. Table 5. Manhole and nozzle body thickness
NOTE. The typical details of shell manholes for tanks not exceed-
ing 25 m in height are given in figure: 9. Outsids diameter d , Min. manhole and nozzle
body thickness t p

11.1.21 Reinforcementshall be provided as specified rnm


in either 11.1.2.2or 11.1.2.3. 5 -0
11.1-22 The cross-sectionat area of reinforcement 5.5
provided, measured in the vertical plane containing the axis 7.5
of the mounting. shall be not less than:
8.5
0.75d x t
10.5
where
12.5
d is the diameter of the hole cut in the sheH plate
tin mml;
!..<.".'. . . . . : . . ....

Gasket specit ication


C.A.F. or woven asbestos
impregnated and graphited
785 a d . x 6 2 5 i.d. x 3 thick 20 min. projection on horizontal f
with holes for 36 x M 2 O of manhole except for
bolts on 0 7 2 5 pitch
circle

Detail A See 11.5 for detail

2 handles 0 25 steel
Joint faces to be machined
3/' Single - v e e butt weld
in manhole body
Reinforcing plate
curved to suit tank .
$
,::

in reinforcing plate '.,

Weld detail B on horizontal .centre . ,:, . .


lines . . .
16 min. after
machining

. '3.::
. .. ,
. .. ....+' .,,,:, .:.. . . . . . I.',,;..
> .

.. , :
:
_.
. .,. .. . . . " . . . . .. . . .
Alternative construction for neck ring . . . . . . . .. . . . .' . ,. . . ..
, '

All dimensions are in milllrnstrts. ., . . .. -... . ..:.,. .. . . .J ; . : '...


-+

Detail A . . . . ' . . .
Fillet weld dimensions refer to leg length.
.
. . . . . .:..
.
. . . . .. ... .v. . .. . . . .....:,. . .. ,..::,..'. '. ',:
, . .
.
NOTE. Attantion is drawn to the regulations C O V W ~the
~ QUse of asbestos. . . '!.. ... , <., , a ?,t :> '~
.
'

.,. . .
. .. . . .....,( . . . ....,.,
Figure 9. Shell mnnhofes (see 11.I) . . . .
. . . . ................
I _ ,,.. ,2
3'.

... . .,.,'.. .,\


.. Forweldingdetails
see 11.5 she also
11.6:1

weld details

Figure 10. Shell insert type reinforcement .bee 11.1.2.2)


. .
For welding details see 11.5.
See also 11.6.2 and figure 24. Shell plate

{ nozzle.

L> 1 . 1 7 G
where

Figure 11. Barrel type nozzle reinforcement (see 11.I 23)


P 5 Stress c o n c e n t r a t ~ o nfactor j
. -
' : I . "' . . . I . .
. .- '

.. . . . .. . . . . %
.- :,.: . : . . ... .
. .
_
. . .: . " .' . .:

.
.
2
.$
.
.
- .... ..
t h e wall thickness o f the mounting (Ifor examples see
Se>+d m z & $ .sha!l kt b i permined i n sizes of 80 rnm o d . figures 14 t o 20).
an$$+& N o additional reinforcement shall be required When the thickness o f nozzle bodies manufactured from
f,.-.::.._ s than 80 trim o.d.,.provided that the thick-
a r ~ m:. z z l e less rolled plate exceeds 20 mm, either material w i t h specified
rhsiof.tH'e bo& is nor less than that given in table 5. through-thickness properties shall be used o r a minimum
ir'0t~: Set.on naalas Isee figure 21) k& be used. provided.rhat layer o f 3 mrn o f weid metal shatl be applied t o the surface
.%$:ptbths are checked close to the opening to ensure that no of the body, prior to welding the n o u l e t o the shell (see
injelb* ~Pmihationsare h n t . For this pgipose. ultrasonicor figure 24).
,." a g ~ i e r t i c ~crack
;. & e det'ection is recommended.
-:
. . : ... 11.5.4 B u t t joints connecting insert plates t o t h e shell
A

. -;...>
11.3 Roof m n h d t s and nozzles plates shall have full and complete fusion.
The roof manholes shall have a minimum inside diameter 11.5.5 The leg length o f fiilet weids around the periphery
o f 500 mm. They shall be suitable for attachment by o f reinforcing plates shall equal the thickness o f the rein-
welding t o the t a n k . r w f sheets. forcing plate or 20 mm, whichever is less.
The manhole covers shall be either as specified by the
purchaser (see 3.2(g)I o r o f the multiple-bolt fixed o r 11.6 f nspection of shell manholes and nozzles
hinged type.
11.6.1 The b u t t weld connecting insert plates t o the shell
Flanged nozzles for fixed-roof tanks shall be as shown in plate shall be fully radiographed (see 17.3.2)' i n accordance
figure f 3. w i t h 17.4

11.4 Additional loads 11.6.2 Longitudinal and circumferential butt welds in.
nozzles shall be 100 % visually examined t o ensure
Nozzles shall be designed t o withstand the loads specified
complete fusion, i.e. i n single-sided welds, the inside shall
i n 5.5.
be examined t o ensure adequate penetration and in double-
sided welds, the back gouge shall be examined t o ensure
11.5 Nozzle welding details
removal o f the root face.
NOTE 1. Typical weld details for nozzles, manholes and other
openings are shown i n figurn 14 to 21 and recognized weld details O n compktion, dyepenetrant crack detection shalt be
for connection of mountingrare shown in figure 22. carried o u t where accessib14. .-
NOTE 2. Mher fonns of joint preparation are permitted by agree-'
ment between the manufacturer and the purchaser. 11.6.3 A l l other wekis shall be fully magnetic-particle
crack detected before the hydrostatic test or, where
11.5.1 The partial penetration welds, e.g. as shown in applicable, before and after post-weld hear treatment.
figures 18 and 20(e) and (f), shalt only be used when the The weld surface shalt be such as t o ensure that inter-
shell thickness ( t ) i s not more than 12.5 mrn and the pretation o f the crack detection is not impaired.
allowable design stress (SJi s less than 185 bl/rnm2.
11.6.4 When the thickness o f nozzle bodies manufactured
113.2 The toes of fillet welds connecting the nozzle o r f r o m rolled plate exceeds 20 mm, that area o f the body ro
reinforcing plates t o the shell, o r the centre line o f b u t t be wetded to the shell shall be ultrasonically examined t o
welds connecting insert plates t o the shell, shall not be ensure freedom from laminations.
ctoser than 100 mm t o the centre line of any other shetl
b u t t joint, the toe of the shell t o b o t t o m fillet wetd, or the 11.7 Flange drilling
toe o f fillet'welds o f adjacent attachments.
Unless otherwise specified b y the purchaser (see 3.2(h)),
NOTE. The reinforcing ptate or insert plate may be extended to the
the flanges of all mountings except shell and roof manholes
shell to bottom junction provided the plate intersects the bottom
at 90 O (see figure 23). shall be made and drilled i n accordance w i t h class 150 of
BS 1560 : Part 2. The orientation of mating flanges shatl
11.5.3 The dimensions o f the welds connecting set-through be checked for compatibility.
nozzles t o the shell are n o t required t o be larger than twice
:.
. .. . . .IF..rLs.
. .
- . . . . . . . . .'
" :, . .. .. . .. .. . . . . .> .. . . .
" ^

+
. .
. . . .>.: .,. . . ... r..

4 3
'. . , . . . . .
x . .
. . BS 2654 : 1989
' 1

,.,.
;,e;;~~:.;..,-?
.n..i
.. %,.,,::.:..:

Dinlensions of plate ring flanges to comply with dasr 150 of BS t560 :Part 2 in all
respects, except that extended hub at back of flange may be omittcd.Slip-on flanges
complying with class 150 of BS 1560 : Part 2 (forged steet) rnak k substituted for plate
ring f lsnges.

wA~is laiways vertical


7

plate

i
When roof nozzle is used for
venting purposes the neck rnoy
be trimmed flush v i t h the
r e i n f o r c ~ n g p l a f e or roof t ~ n e

W o m i ~diameter
l Outride Diameter Height of Nominet
of nozzle diameta of hole in nodm pips mil
of pipe roof plate thicknra
4 hn 'P

rnm
f 50
150
150

'IM
t 50
150
200
200

, All dimensions are in rnillimetres.


. Fillet weld sizes refer to k g lengths.

Figure 13. Flanged roof nozdes (see 11.3)


F = B = lesser of t and t p , with a minimum of 6
t p = t 2.5 max.
NOTE 1. in cases where the shell thickness. t, is w e d to derive other dimensions, or as a recommended restriction on the
use of a detail. the insert plate thickness, t i . is to be substituted in the warding when inscrt pbtes are being used.
-* -
NOTE 2. ~einforcingfillers are to at least cover the penetration welds beneath.

F, = lesser of t / 2 and tp/2,with a minimum of 6


F, = lesser of t and tp. with a minimum of 6
t p exceeds 125.
All dimensions are in rnillimetres.

Figure 14. Typical weld details for connection of mountings: set-through type (preferred details):
t = 20 mm (max.) (See figure 22 for recognized weld details.)
F = 6 min., 13 rnax.
8 , + F = t p . 6, = to. If 8, or 8, exceeds 16, use J-type weld derail.
+. i f S is less than 3, use details c and d as appropriate.
t p = 12.5 rnax.

F = t14. but not less than 6.


I f t exceeds 30, use J3 weld detail.
tp exceeds 12.5

All dimens'bns are in miflimetres.

Figure 15. Typical weid details for connection of mountings: set-through type {preferred dctailsl:
20 mm G t < 40 mm (See figure 22 for recognized weld details.)
F, ti18 min, but not lscs than 6.
F, = -44 min.. but not less than 13.

All dimensions are in millimetres.

Figure 16. Typical weld details far connection of mountings: set-through type
(preferred details): t i > 40 mrn (See figure 22 for recognized weld details.)
t = 16 max.
\ - - r o o t should be bock
< -
aouped to sound metal
and welded f, = I 6 m a x .
- t = 25 max.

F , = t/8, but not less than 6. ..


F, = t/4, but nor less than 6 and not more than 13.
t exceeds 20, tp exceeds 12.5. If t i exceeds 50. use .I1 weld detail both sides. .. ~. . .
. . .. . ,.
AIl dimensions are in millimtres.
... .>.
, . . ... .
Figure 17. Typical weld details for arnnection'ofmountings: set-through type ..., .
. . . . .
(alt&rtative details) (See figure 22 for recognized weld details.) . :
. . ..
%
.

. . .. . . . "r.
+-I
35 m a x .

. l-4
35 max.

F, = lesser of tp and t,, with a minimum of 6.


F, = t , with a maximum of 10.
See 11.5.1 for restrictions on the use of this detail.

All dimensions are in rnillimetres.

Figure 18. Typical weld details for connection of mountingr: compensated set-through type
(preferred details): t = 12.5 mrn (rnax.1

F , = lesser of t p and t,, with a minimum of 6.


e = 10 rnin. to 20 max. as r e q u i d for access.
F, = t p / 3 rnin. but not I- than 6.

All dimensions are in rnillimetres.


'
Figure 19. Typical weld details for connection of mountings:
compensated set-through type (preferred detaits)
,. .;. ,
' I
1
.
" . ,

6 +F, = lesser of tp and t,.


F , = 6 rnin.
e = 10 min. to 20 rnax. as required for access,
F, = t,/3 rnin. but not less than 6.

F = tpf3 min. but not less than 6.


e = TO min. to 20 max. as required for access.

t = 12.5 ma%.
(8, + F, I = e = lesser of tp and t,, with a minimum of 6.
. . (8, + F, 1 or B, = lesser of t p and t , with a minimum of 6.
. See 11.5.1 for restrictions on the ure of details (el and (f),

All dimensions are in rnillimetres.

Figure 20. Typical weld details for connection of mountings: compensated set-through type
{alternative details) (See figure 22 for recognized weld details-)
la)
t p = I 6 max.

If the welding procedure does not ensure round positive root penetration, these joints should be back
chipped or gouged and back welded. The internal penetration bead of joints welded from one side
only are to be ground smooth and flush with the inside bore.

All dimensions are in millimetres.

Figure 21. Typical weld details for connection of mountings: seton type
(shell nozzles less than 80 mrn o.d.) {See figure 22 for recognized weld details.)
s2 = O m m t o 3 m m

g, = 2.5 mm to 3.2 rnrn

g, = see note 2

a =15°t0350
sl = 1.S rnm to 2.5 mm

g2 = see note 2

g =0mmto3mm

r =8mmto?3mm f,,? u

ic,, . ,

. .
...
.
:.i
..

- .,:>

-
. . . . .
: 1.

. . . . . : -2

.
. .
%
._'
. . . ..<
,. .....
" '
: . .. . .. , . " . ^ . . . . . . . a-
L.
. . . . . . . , .......-
. i ..i.:- . .
. ... . . . . .
. . . NOTE 1. &se recommendations have been included for general guidance. ~ i s c r e t k ~ h g
t o s be'"=ed= ..
. . . . . ~

;.
. .: _- . :. - :in applying the maximum and the minimum dimensions quoted which are subject to nriati0.n. . . ,.'.;. '
.. - '
,;;i:
, . '.
-+.a:

. , . ...
.: . , .. . . . ;a&ording to the welding procedure employed. e.g. size and type of eletitrodes. as Wll
.,.,:.:. ..... .;:. ; in which the welding is carried out apd the welding process adopted. . . . .,.
.. .as
.
.. the,b&'@on
. -, . .
,,,,..
.
,'.:'.L. -..,
.:'.
: _-.. :
. . . . . . . I .
- . '
_
. .. . .> . <. '
. . I

' '
_,:,:"
.
. ../ . . . .. . :. ..
.-..'. _., ., --: . .. =, NOTE 2. i t i;remrnrnend&d that in no case should the gap between nozzle and adjscFntplat<i'_c: : ?:<I: T' ...... ,;!';.,.,
.> ,.,
'j
, , , '.'.
2

. :-exceed 3 mrn.,Wider gaps increase the tendency to spontaneous crpcking during weui*, particitlarty..; ,..:. . , ':.:..' '. '"... .. ...G :.
.
%

. .. . .
. ,:,. ; >.. , . - : . . as the thickness of the parts joined increases. .. . . E . ' . :..-
~:.. , ....:;. ::,.... .: ..... . .
;..
:
..... "
. - . ,: "., 0 " . ... .... .. . . .. . . . . ..... .* .' .- :. ..I..:I -.:.">., ..? . :.. .. . . . . +..
....
:'A"

. . . . . .
.., .7 . _... .*ai"
I
..Z.'.. : . . ,. .- . , " .. . ." . . ........:.... .....,>.,,.~>.> ........... : . .~,>.:
.. , .. .,?->"' . :,.. < .>...,.. . ,.: .
r , , . < . .: -.
. .,.. .. .. . . ,'~,.
. . . . . . ., . . . ,+,
.. .. . . . . . - ' . . "'.
:
I-
".
'.

- ~@k.:q.
"

." : -<.....
.... :;.I Rebagnized weld details for connection o f h n t i n g s . . " . . +..:
. . ....:.'.. *. .. . . .:
:-%,>,

.'-+*"
,,:+:; " .'<."
; : , ; 2 , * :..::.>,Y:Y
,,
. . . . . . .....
-
>.-
. . . ._ . j . . .:, . T.?' .. .: . :. . . -. . .. . ... ... . . . .~.
. . :.*_",. ... :
. . . .
.........
...
-. . ..,.. . . .,.:;
. . . :. -. .,:"?.< . - ;.; .....'.
..:+.-, :." ?..,:;.:. . "'>
<..
: .....:...
.,<:. , :! -' . :. .?id:
.:..... .?! .:?&?
.
.:"&:::<-. ..-.- . . . - . . . . . .. . . . .
, <:;C'd.?-
....
<,+::-:,,: .A,.,
<' ,; ',
i:.. : . " ..."... . . ... . . . ,:.,-_ .. " . . ._ .. . . . . ........ ;. ..,>" <.," :<,; .;?",;/'.+
. :,.. ...<. +,: .<.,<.. ,c.. : : . .. . : ,
.
C . .': 9.
""I"

.
. . . ..,. . .. . I . , .'.. .: . :
;I-

,a ' ~ ~ % .. : . .. . .
. .>'. .:,: , - ' . .
. . . . . . . . . . . ............ :.- . 5.:;. ..... .
. . . .. .. .. . . .
' Y-..'*&~.:
' ' .7;w",

, . -. . . . .. .. .. ..... .. . . .:.."c;.r ...;c~2:>.c':.l:<,:~:,"'..


. . -..:-
,
.'.:.
. .-<-..- : :
%.,.
.
.". ' '
. ., ...
. . .
. ,
. >
, ",
-
. .. .* .. ". .
'
" _
.?..'
. <,
. . I
;..I
See details See detail tg)
1d)le)and (f)
Section A-A Section A-A
(b) External reinforcing plate kl insert reinforcing plate

l : L transition

/shop weld
Site weld
(dl External reinforcing ptm
shop stress-rcliwad nords

L
grind flush i
F = lesser tb/2 and t,12. i
(e) External reinforcing plate ir (f) External reinforcing plate (g) Insert reinforcing plate. S t r e s s r e l i d
h o p rtrass-reliwed nozzle non-ztrtss-relieved nozzlr or non-strarsretid nozzles

Koy to s y m b d s
r is the shell plate thickness
t t i s the in- plate thickness t
t, is the reinforcing plate thickned
tbis the bottom plate thickness i
All dimensions are in millimetres. ;:
. .
.
. .. . . ..
.
.
..
. .
.. . " . . .. . .. . .. ... .... ,...., ..:
~ . .
.- .. ...... .. . :,. . .. .. .. .......
. 6250' ....... ..
. . . .. .. . . . . . . . . . .- .
.+;...: ::
T.",

. . . . . .
(t cir ti] :,:'l . " .. , . .5 .. . . ,.
'
.
.
.
. . .
. .-
. . . . . ." . . . . . .
^.

. . .
'

__ ..
'
.I

. . ,. . .".. . .. . . .. .....'..- .. .. . . ,.
,.
' 7 .
.
. . .. . . .. . . . . .. .
where,t,&d are'!s dcifined'in l'j.9.2 ', ': ' . . .. .. . < ?. , . >. . . . . . .
. .
NOTE., 8&~.400-C,.the assembly rnay,be&led iri &ill air. . . +:,+--q;:: ". .'. . . . .
". . . . < . .
- ,." .. . . ~

..
+

11.97 The t&npe&tur& l.i-ified shsll b & . ~ c t u a l . t e m


. -~ ~ -i.-+e: . :.~..". ~
+ .i... :. ;~
.. ~
. . . .I;
tures uf any part &.the assembly.,andshall be deteririined ';:.-.I..:: :,
. :.' ..:' . ' . - ' .'

;,53yp: :. . by therniocouples attactred to the assembly, unless.it & . . . . .


ad;ats:r$iitfur&mnt '&ail be at least eq"al to the full - be demonstiat& that the type of furnace used wilt always
widfh'&f the course and i t s length shall be not less than comply witg 11.9.1 to 11.9.7.
itd'wiaah.
. . , . '
-
~ .> , A sufficient number of temperatures shall be recorded
134.3. An exteniion pipe or flange welded to either the continuously and automatically to ensure that the whole
in#de.'w outside of the nozzle and not forming part of the assembly being heat-treated is within the range specified.
re&ir@ reinforcement 'shall not be considered part of the
.ad&kblv. 11.10 Stairways and gangways
11-82 Subsequent welds to nozzles shall not be closer to NOTE. For stairways on insulated ranks, see 8.5.2.
anq weld which has been posr-weld heat treated than: 11.10.1 Local regulations shalt be observed and any
2.5 6 conflict with the requirements of this standard resolved.
where 11.10.2 Stairways and gangways shall be of metallic
ri is the inside radius of the pipe (in mm); construction and the minimum clear walking space shall
t, is the wall thickness (in mml. be 600 mm.
NOTE. It is recommended that the angie of stairways to the
11.9 Procedure for post-weld heat treatment
horizontal plane shouM not exceed 45 .
: 1j,$.j The temperature of the furnace at ty
time the
-.
11.10.3 The stairway treads shalt be of the non-slip type,
NOTE. The rise should normally be 200 rnm with a minimum
a&nbly
.-.- i s $aced in it shall not exceed 400 C.
I
width of 200 mm measured at the mid-length of tread. The rise
.& 1+:4.2 The rate of heating above 400 OC (in O C per hour) *
may be adjusted within 5 mm to make treads tevef with landings
or platforms.
. shali not exceed the.following, with a maximum rate of
..- 200 "C per hour: 11.lo.&spiral type stairways incorporating stair treads
1 5000 welded directry to the shell, or by means of local pads,
shall only be permissible where:
(torti)
where
(a) the minimum specified tensile strength of the shell
material does not exceed 460 Nlrnm2;or
t i s the shell plate thickness (in mm);
(b)the minimum specified tensile strength of the shell
ti is the bottom course plate thickness (in mm). material exceeds 460 N/rnm2 and the shell thickness
11.9.3 During - the Heating period there shall not be a
does not exceed 12.5 mm.
greater variation in temperature thoughout the assembly Where the minimum specified tensile strength of the shell
being heated than 150 O C within any 5 rn interval of length material exceeds 460 ~ / r n r n ' and the shell thickness
and when at the holding temperature, the temperature exceeds 12.5 mm, stairways shall be independently
throughout shall be within the range 580 "C to 620 OC. supported or affixed by horizontally oriented continuous
welds (see 11.15).
113.4 During the heating and holding periods the furnace
atmosphere shall be so controlled as to avoid excessive
oxidation of the surface. There shall be no direct impinge- 11.10.5 Stairways and gangways shall he capable of
supporting a superimposed load of 2.4 kWm2 as well as
ment of the flame on the assembly.
the wind loadings specified for the design of the shell.
11.9.5 When the assembly has attained a uniform tempera- NOTE. Ir is recommended;h&t where thevertical rise of stairways
ture as specified in 11.9.3, the temperature shall be held i s more than 6 m, intermediate landing orJandings should be
constant for a period in hours equal to 4 % of the thickness provided.
in miHimetres of the shell plate, with a minimum of one t1.10,6 Tank gangways which exTend from one part of a '

hour. tank to any part of an adjacent tank or to ground or other


11.9.6 The assembly shall be cooled in the furnace structure shall be so supported'as to permit free relative
to 400 O C at a rate in O C per hour not exceeding the movement of the structures joined by the gangway.
11-1I Handrailing 11.15 Permanent attachments
11.1 1.1 Handrailing to tank roofs, stairways and gangways 11 .l!%l Permanent attachments welded to tank shells
shall be of solid steel'sections, and shall be designed to thicker than 12.5 rnm shall be kept to a minimum and
protect personnel and prevent objects from failing (see ' shaH preferably be disposed in a horizontal direction.
figures 25 and 26). NOTE 1, I f vertical fillet welds are necessary, f hese should be made
with special care, having due regard to their stress-intensifying
11.1 1.2 andr rails s b l l be provided on both sides of effect.
gangways and stairways, except on spiral stairways where NOTE 2. Automatic few/ and temperature measurirrg instruments
the distance between the tank shell and the inner stringer is Where it i s required to provide mountings to accommodate auto-
less than or equal to 200 mm when no inner handrail i s matic level and temperature measuring instruments on tanks,
required. At breaks in the handrail, the space, if any, attention is drawn to BS 3792.
between the tank and the platform shall be floored if the 11 -15.2 Vertical attachment welds shall not be located
space exceeds 150 mm in width. within 150 mm of any main vertical seam and horizontal
11.11.3 For tanks over 12.5 rn diameter, where access i s attachment welds shall not be made on top of any main
required to fittings at or near to the centre of the roof, horizontal seam. The soundness of fillet welds shall be
handraifing and treads shall be provided. checked by magnetic-particle crack detection to a suffi-
cient extent to confirm the welding procedure which shall
11.11.4 Particular care shall be taken in the jointing of be agreed previously and designed to avoid any risk of
handrails to ensure that the full strength of the members underbead cracking (see f6.1.3).
is developed. NOTE. The use of multiple cleats or studs is not recommended.
Stud-weldedand similar attachments shall not be permitted
1 1.12 Ladders for plates exceeding 13 mm in thickness.
Fixed steel ladders exceeding 4 m in height shall be 11,16 Temporary attachments
provided with safety cages..
NOTE, These should be generally in accordance with BS 423 1. 11.16.1 The requirements governing the location. . u

'

orientation and procedure for the provision of temporary


.
attachments other than the location of temporary key
1 1.13 Earthing connections plate erection attachments shali be the same as for perma-
All tanks shall be fitted with suitable earthing connections. nent attachments (see 11.15).
NOTE. A typical type of connection is shown in figure 27. 11 .l6.2 When removing temporary attachments from
shell plates, the attachment shall be burned 3 mm to 6 mrn
proud of the plate surface or, alternatively, the securing
11.14 Flush type clean-out doors, D-type sumps and weld shall be weakened by chipping or gouging, taking care
water draw-off sumps not to damage the parent plate, and the attachment shall .
11.14.1 When it is proposed to embody flush type be knocked off.
. .
openings in the bottom course of shell plating, the vertical 11.16.3 The resultant scar shall then be ground to a ..
opening shall not exceed 915 rnrn or half the shell plate smooth profile, ensuring no underflushing of the plate . ..: .:
width, whichever i s the lesser, for steels having a minimum ..
surface occurs. _ ...I.
specified tensile strength less than 460 t4/rnrn2 nor MOTE. After grinding, the surface should b e checked for cracks ' . .<:
300 mm for stronger steels. The assembly shall be prefabri- particularly on plates with specified minimum tensile strengths . i::'- :
cated and stress relieved in accordance with 11.9. greater than 430 N/rnml and 20 rnm thick and over. Should under-' .
flushing b e present, reference should b e made to BS 4360 for ,$:;,:.,
11.14.2 In view of the complicated stress pattern, the use guidance on possible repair.
of flush type openings shall be reduced to a minimum <;:
.".. '?:

and typical details are shown in figures 28 to 31. '

11.14.3 When it is proposed to use a combined water The permanent attachments associated with the requiriz$: :
draw-off and clean-outsump the design shall be as shown ments for the insulation of a storage.tpnk
. . . (see 3.lfi)) shall:.;'
i n figure 32. The fillet weld to the underside of the bottom
.
... ..::.::-:'">:'.;y
comply with 11 . I 5 ... .. '.*...?
.
.,,.il.".

sketch plate or annular plate shall be deposited in the flat


ma,$:Z<.
'-,"<$

NOTE. Tanks designed to cornply ,with 3his'.~r&h ~ t & ? r d


position, the bottom plate being reversed for this purpose require to be insulated for V W ~ O U Sreasons, e q : maintaining prod,i&l:
before final positioning on the tank foundation. temperature. Although thedesign of this insulation is outside the:z<-
N 0 T E . f ypes of acceptable draw-otf sump are shown in figure 33. scope of this standard. the recomrncndatiobsbf appendix B ?~oukfG,
b e taken into consideration in the design. ... . .
a -. * ....
. - .: t..~..;
Elevation of centre landing when = q u i d Typical cross section through stairmy

200 at mid Length

tie-bars to bottom
three treads only

Tank b
ries to suit
hemht of tank
Elevation of bottom staircase iml; rzsl
,Tank shelt
plate

il
600 min.

,
Handrail 0 30
sotid section

All dimensions are in mitlimetres.

Figure 25. Details of an acceptable type of spiral stairway (see 11.10 and 11,11)
Shell plate

@ 45 steel
round bar

..
Copper conductor s t r i p
brazed t o 25 x 3 copper strip

All dimensions are in millirnetres. unless otherwise stated.


Fillet weld dimensions refer to leg length.

Figure 27. Typical detail of earthing boss (supplied with tank)


site welded to tank shell plates (see 11.13)
'
l i
Full f i l l e t veid

L i f t i n g tug S e c t ~ o n0-6

Edge preparation as
for bottom course Edge prcparotton a s SLope 1 in 5 edge
shell verticals for bottom course
\ - -
2700 min.
C shetl horizontal
7p'=ratr0n
f'
i
\

Insert plate
r
tl -.
S e e .lug
32 equal detyl
p~tch:s 100, 38
I

P l a t e wldth
see I 1 1G.Z

Zx@tSround handles
shop welded to cover
+
3 t h i c k C A F full face
joint ring

( machined
f
Sectlon A-A

stape'l in 5 e d g e
preparation to suit
4k 5 m i n
shell piate Section O - D
Section C- C

. . Key to symbds

. ..
t , , i s the battom murse shell thickness < 18.5 mm
.. ' . . ti is the thickness of 2 7 rn insert plate =2t, +3<40rnrn
tf is the thickness of cover and flange =0.78H*11
tb, i s the thicknor of bottom reinforcing plate =7 fi+ 3
rb i s the tank bottom plate thickness
H is the tsnk height tin mi.

All dimens-mrtsare in rnillirnetres, unles otherwise stated.


Fillet weld dimensions refer to leg length.

' : (al915mmx1230mrn
. . . . . . ... . .
.' <. . _=;'_.'...J '
. ' .-+ : . ' F ~ & $ & ' ~ F ~ U
.-</ '-,,r. &'~~
dean-out ~
door with insert plate reinforcement {see 1l.j
, . . . L ...
_ .:..
, .i
u.7.

x.,,.. ,
,..- :
.:..,.
" ,
.
.. .
.. ,
t i f t l n g tug Section 0-6
..L
;";: . : . . . . > .
..,
,*'-. .
,

.* +'
:=.-
Slope 1 in 5 edge

Edge preparation as
far bottom course
PEdge preparation os
shelt verticals for bottom course
2700 min.
\ I- /
shell horizontal

.ration
see 11.5

See lug
Plate width defnil
see 11.14.1

~ a t i n ' gsurfaces
machined
Section A-A
I
34xa28holes
for M 2 4 bolts

5 min.
Section D - D
l 5 edge
~ l o p e 'in
preparation to suit
shell p l a t e
Section C- C
I:",". :. , .

F u l l f ~ l l e tweld

.. i 1
1

Cover p l a t e
Cover Section 8 - 8
L i f t i n g lug
Edge preparation as
f o r bottom course
shell v e r t ~ c a l s A Edge p r e p a r a t i o n
a s for bottom course
_I) s h e l t horizontal
/

See Lug
defait For weld

11 5
Plate widtb
s e e 11.1I.1

3 thick C A F f u l l
face joint ring

Mating surfaces
machined
PF S e c t ~ o nA - A

S e c t ~ o nC - C
4C c - 5 rnirt
Section 0-0

..
Kay to lymboh
t l is the bottom course shell thicknm < 37 mm
, . t, i s the thickness of 2.7 'rnreinforcing plate = tl + 3 < 40 mrn
ff i s the thickness of wvcr and flange = 0 . 7 8 H + 1t
. t k .is the.thicknessof bottom reinforcingplate = 7 @+ 3
. . .. , tb is the rank bottom piate thickness
' , H i s the tank height,(in m)'
.... . . . . . . . ..
. . . . . . .. ..
All dimensions are in millimetres. unless otherwise stated. . " . .. I : .+ ,I .:, . .
Edge 'preparation as
f o r bottom course Edge preparation
shelI verhcals as for bottom course
3300 min. shell horizontal

+
Plate width
see lf.lC.l

For weld
preporahon
.
, 2 ~ 0 2 5round handles
shop veIded to cover
see figure ---.
28(aI
& P
3 2 min.

I machined
36rQ1t1 Section A - A
for M24 b o l t s

Section C - C
-u -
! !

Section 0-0
5 min

Key t o symbols
t l is the bottom course shell thickness < 40 mm
t, is the thickness of 2.7 m reinforcing plate = tl < 40 mrn
tf is the thickness of cover and flange = 0.52H + 6
tbr i s the thickness of bottom reinforcing plate =7 fl
t b is the lank bottom plate rhickness
H is the tank height (in m )

All dimensions are in millimetres, unless otherwise stated.


Fillet weld dimensions refer t o leg length.

Figure 30. Flush type clean-out door with plate reinforcement 300 m m x 1230 mrn (see 13.14.2)
Clea n-out
door body

0 5 7 round
Davit arm

Davit arm swivel

All dim&siom are in millimetres. .


Fillet weld dimensions refer,to leg length.
. . . .
. . . .. -. . . . . .
. ...:I. ... ~ i ~ 31.0avit
u & for 915 mm x 1230 man ckean-out door (see 11.14.2) > - 4 .,. : .
' , '

...
; . _. . . . . . .. .. . ..
.....
. . . . . . . . . . .'.. ,,, .. , :.. . *
' ...
<,
. . :. . . . . . .. . ...
.. . .
I
. . , .
. ,. .<.,
, .
...
- .
1.'
....
. . .
. -
. " , . . .:. . .
..,, . ., 3 -.,
. . .
, .

.. .. . . .

. .

ular or bottom sketch plate


to be reversed to permit
downhand welding at site

18 x @ 2 5 holes
f o r M22 bolts

End elevation
Cover plate not shown

impregnated and graphited and mating


faces machined

for plug Section A - A

Cover plate

Section B-B

NOTE. Sump all shop welded.


Plan

All dimensions are in rnillimetres.


Fillet weld dimensions refer to leg length.

Figure 32.Combined water draw-off and dean-out sump (see 71.14.3)


f
635 hole
in bottom tate 1 ALternotiveIy the
f ~ ~ ~ ~ d : d " Y

I
detail

MI dimensions are in miltimetras.


Falet wld dimensions rsfsr to leg length.
.. ..
. . .
*Figure33.Aceyltrble m t r r drm-off umps (see 11.143) ....
. . '. ., . .'.
'
b .

. .
. . .. :>.,
- 1 .. .-. ,
. + . .'...
.
& "

13.6 Surface preparation and painting


. . . .
13.6.1 Unless otherwise specified by .the purchaser ' . .
(see 32W1, painting shall be as specified in 13.6.2.
.The workmanship ;md finish shaH $e subjected t o close
13.6.2 All r o o f structiiral,inember$, stairways and hand-
,&spection by the manufacturer to ensure t h a t they comply
railings manufactured f r o m mild steel shall b e thoroughly
with all requirements of this standard.
cleaned and freed from rust and scale by pickling, or blast
NOTE. This it required whether or not the purchaser waives any
cteaning, and'painted immediately after cleaning with a'
pprt of his inspection.
primer F a t o f paint.
'.I

13.2 Hard stamping 13.6.3 The method and extent o f surface cleaning and
Hard stamping shall o n l y be permitted f o r the purpose o f painting f o r all other .materials shall be specified b y the
plate identification and in any case shall b e kept t o a purchaser (see 3.2(i) and A.3.4).
minimum. 13.6.4 Special consideration shall be given t o t h e need t o
protect welding margins, machined surfaces, nuts and bolts,
13.3 Plate edge preparation etc. from corrosion during shipment and construction.
. 13.3.1 A l l edges o f all plates except b o t t o m and roof
plates, shall b e prepared by shearing, machining, chipping 13.7 Erection marks (domestic market)
'
or cutting w i t h a machine-operated cutting torch. For butt- 13.7.1 Tanks erected by manufacturer. All plates and
welded joints, shearing shall be limited t o 10 mrn thickness structural members shall be marked in accordance w i t h
of.plates. t h e manufacturer's normal practice, unless specified
'
13.3.2 For b o t t o m and r o o f plates f r o m a steel reversing otherwise by the purchaser (see 3.2lj)).
mill, further edge preparation shall not b e required. 13.7.2 Tanks erected by others. A l l plates and structural
?
T h e edges of t h e products o f a steel strip m i l l shall b e members shall b e marked in accordance with a marking
trimmed in aocordance w i t h 13.3.1 t o achieve a square diagram t o b e supplied by t h e manufacturer which shall
. edge or double-rub fillet welds shall b e adopted t o ensure also bear such other marks as may b e required to facilitate
adequate r o o t penetration. erection. Erection marks shall b e painted clearly o n plates
. . NOTfTThis requirement b necessary since the longitudinal edge and structural members in"Syrnbols a t least 50 m m high,
produced by the mill may not be sufficiently square to ensure a where practicable, and in the case of curved plates, such
wwnd filtet weld with full throat thickness. marks shall be o n the inside surface.
13.3.3 When manual oxygen cutting is used f o r trimming
outside circumferential edges o f roof and b o t t o m sketch 13.8 Erection marks (export market)
- plates, such oxygen-cut edges shall be properly cleaned f o r A l l plates and structural members shall b e marked in
"
welding. free f r o m oxide and cutting scale. accordance with'a marking diagram to be supplied b y the
NOTE. These should be reasonably mooth at the mlding edges, manufacturer which shall also bear such other marks as
.-.- although this would not normally require grinding if a good m a y be required t o facilitate erection overseas.
quality of workmanship i s achieved.
Erection marks shall b e painted clearly o n plates and
13.3.4 Ail shell plates shall be profiled t o a tolerance of structural members- in white paint and shall be a t least
k 2.0 m m in length and width. In addition, t o ensure that 50 mm high. In addition, it m a y b e necessary for them t o
plates are t r u l y rectangular, the diagonals, measured across be hard stamped (see 13.2) in symbols n o t less than 13 m m
the rectangle formed b y scribing lines 50 m m f r o m each high, which in t h e case of plates shall be in the corner
edge, shall not d i f f e r b y more t h a n 3 mm. approximately 150 m m from either edge. For curved plates,
such marks shall be on t h e inside surface.
I For lap welded roof and b o t t o m plates, normal m i l l
tolerances shall be acceptable.
13.9 Packaging
13.4 Rolling and pressing 13.9.1 Structural materials and tank plates. A l I materials
When required, t o comply w i t h t h e dimensional require- t o be erected either b y the manufacturers or by others shall
ments of this standard, shell plates shall have ends preset be bundled and packaged in accordance w i t h t h e usual.
and be rolled t o correct curvature. requirements f o r the m o d e o f transport, taking i n t o account
NOTE. I f plater are not mlled, the manufacturer shovld inform the handling facilities available in transit, and every care
the purchaser. shall be taken to guard against damage or loss.

13.5 Bolt holes


13.9.2 Mountings and fittings. Where flange gaskets are
packed separately, they shall be adequately protected
All b o l t holes shall be punched or drilled to template so against .damage in transit.
t h a t similar parts are interchangeable. Badly matched NOTE. Roof and sfieif manholes, nozzles, bottom sumps, clean-outs,
holes shall n o t be corrected by drifting. etc. may be sent loose with covers bolted on.
electrode%Welding electrodes shall be
13.9.3 . ~ d d i n & out this course, care shall be taken to ensure that due
supplied in cunta iners which give adequate protection allowance i s made for the contraction of the vertical joints
against damage and moisture in transit and in storage on during weiding.
site. The type of packing to,be employed shall be specified
145.3 On all lap joints, the plates shall be held in close
by the electrode manufacturer.
contact during the welding operation. The surfaces where
NOTE. identifbrion. Each case, bundle or package wherever
possible should bo provided with suitable identification marks
the wetd metal i s to be applied shalt be thoroughly cleaned
giving weight or other desired particulars. before assembly.
14.5.4 Lugs attached by welding to the tank, and needed
only for purposes of erection, shall comply with 11.16.

14 Site erection 14.6 Shetl tolerances


14.6.1 The shell shall comply with 14.6.2 to 14.6.6, which
14.1 General
will ensure that the'tank shell is being erected in a satis- '
Unless otherwise specified by the purchaser {see 3.2(kI), factory manner in order that the completed tank will have
the responsibility for supplying welding electrodes andlor an acceptable appearance and assist in maintaining the
key plating equipment lies with the manufacturer. satisfactory function of a floating roof, if fitted.
The responsibilityfor the supply of site erection equipment,
labour, fatse work, e t c lies with the erection contractor. 14.6.2 The tolerances specified in 14.6.3 to 14.6.6 shall
only apply to the tank during erection.
14.2 Workmanship The location and number of tolerance measurementson
The erector shall carry out an inspection of the workrnan- the shell taken during erection and on completion shall be
ship and finish to ensure that they comply with all the by agreement between the purchaser and the manufacturer
requirements of this standard. (see 3.3(ij).
NOTE. This will be completed irrespective of whether th.e purchaser 14.6.3 The internal radius measuwd horizontafly from the'
. .
waives any part of his o w inspection.
centre of the tank at floor level shall not vary from the
nominal internal radius by more than the following:
14.3 Tank foundation aonstructian
Unless he makes alternative arrangements (see 32(1)),
<
(a) tanks 12.5 rn diameter: -t- 13 mm;
the foundation for receiving the tank bottom shall be (b) tanks > 12.5 m <45 m diameter: f 19 mm;
provided by the purchaser. (c) tanks > 45 rn diameter: f 25 mm.
NOTE 1. I t i s recommended that its constru~rtionbe in accordance
with appendix A. At1 reasonable care should be taken to prevent
14.6.4 The overall height 6f the shell shall not be out of
damage to the foundation during erection, vertica1.b~more than 1 in 200.
The top'of the foundation levels shall be checked at a . NOTE. This standard of verticality should apply to each individual
course which should be erected within the same tolerance.
handover'stage to the tank erection contractor and the
difference in'lwel of the surface of the tank foundation 14.6.5 Local departures from the design form shall be
between any two points 10 m apart around the periphery gradual and sharp changes in form shall not be permitted,
+
of the tank shall not be greater than 6 mm and the NOTE. At horizontal and vertical joints the shell profile should
envelope of peripheral surface levels shall Ib within 12 mm not deviate from its design form by more than the following
above to 12 rnrn betow the design levels. measured over a gauge length of 1 m :
NOTE 2. Closer tolerances in the tank foundation peripheral levels la) plates < 12.5 mm thick: 10 mm;
may be necessary in thecase of floating-roof tanks. Uneven founda- (b) plates > 12.5 mrn < 25 mrn thick: 8 mm; 5
tion conditions and settlement can result in the shell assuming an kJplates > 25 mm thick: 6 mm. ,
oval s h g e st the top, causing the floating roof to stick. W-

14.6.6 Plates to be joined by butt welding sha!l be ma&$':,


14.4 Rectification of damage to materiats
Any damage to material shalt be corrected to the satisfac-
accurately and retained in position duri& the.welding. -.?.;:/.
operation. Misalignment of the plates ihall )lot ex&ed
. . . ..
tt$c;;~ .......
following, . . . ... ..:.
tion of the purchaser prior to erection (see 3.4(a)).

14.5 Erection of plates


(a) In mmpletd v e n b l j o i i i i : i o % &:&'+I&
I

thickness, or 1.5 mrn for plates'l9 mm thick and u & - $ ~ .


_
. . -..
.:*
. . ... ;P,p..,
' ,.
..Pi

~c";?;
..
'

. . ..,.<>:>,.
is -$ :;~;:.
a,

and 3 rnm for plates over-19 m . . i. thick>hich&rer


.
14k1.1 he method propobed to hold the plates in position ............ , .. : . .
. . . .:--.
. .- , . .- ....'. for wetding~shall
5' be approved by the purchaser, unless such
the larger. .. -. ...-=..
....... . . . . . .. :. . . . . . . +
. ,
I..:
, :%
........;. :'-.
: .,..
. . ;.....:.. .,appraval.has idready been given in'w;iting by the purchaser (b) In completed hoiizontal'&?ints::$ %kf:&,upwrj&~;~l
: .
, , , . ,.
. . , %. :-..- .'.....-.
..=I; . . ,.. . .tsee,3;3(h)l.
. . . . . ': plate thickness, or 1.5 ,mm far, 8 'mm ttiick a!..!?:,.'.,
;: . -:,,;;
. .. .:...,-. ". . . . .
... ........:... .- under, and 3 mm for plat&'$~e<O~~m~~hi&..vih;ch&~~:;
.. . . .. .
. . . . . . . ..I. . . . . . . . . . <.: ....
:-:,
..,:I
.......
.+.,";
;. .
-14.512 r-~h$; course bf shell plates to be ,erected first shalt be
.:,...>: ;: .' .'held @,p@;on by:yeJalclamps or. bther de,yir;esattached
is the smaller.
>
. . . .. :<,: ....... .,.,,:. .:;., .
. . . . . . -,:. i'
~
.......... sz:<;::~
... ":.:
NOTE. The tank shell s h h d be'dhedked f & r ' c ~ & b i l y , . d m ~ s i d k i * : .,
,;.; *- ...
:ri. . . :..::;-:.!.'.. .to'2he'botto& plates whilst it is piumbed and checked for
:. and level before the roof m m & s arepoakioned o i the'pt~aiy;,'S;~~. .
".
'.<..'%:'I -. .tikulari!p'ind befoteit is tack welded or wetded. j n's&ing
. .." ......... .. .) ... . . . .i.....-.......-.
.... __- . _.....-'- .
....,...
...,-..
. .. :. $1.. : . wind girder iserected . : .. . .....
'

,;;.
-
. . . . . . ,; .;.. . .<,............ *4. :.. .F".
...................... ...... ?
. . .- ... . . .. .. . . . .. .. . = . . . . . : "z.?.:..
- ........
.:..::,-.:a.:

. .
.. -. . . . .
.
. .
. . . .. . . . . .
. . . , .
,.'. 7 , ,

. .. ~
. .
. . . ". . . j.. . ;. .
. . . .. ~." ... . ..
. .. . . ... . . .. . . . . . . . . .
14.12 Find surfatii'fikih . ' . .. . _ ^ ' .- . .
..
. ...
_..> .
.... . i

the peri- The final surface pr'epatationand paintirig &stim'rhall be,


1,'$+y,~f the rckf on completion of erection of the roof specified by the purchaser in accordan& with the environ-
:+aii.not..eideed. "f" '13mm .from.thenominal gap.
,+>-~..,'.
mental and operationaf knditions (see 3Ai)J.. ... ,.
t6 rdof<bthert h l n that at which it war
+
. 5

^. .' : . ~ ' c r l ~ , , ~ fete;'@on'of,


&~ .
. cr*.t!$ thk$ifferaed+4n 9 4 should
~ *
not exceed 50.mm or srch . .
,

S t k valus'as rmy-be.apedm e e n the purchaser and the


::&qGf&urei:firr a particular seal design.
15 Welding .
. ,
:
. .

15.1 Welding process


14.8.1 I f manual oxygen cutting is used for trimming 15.1.1 AH welding, including repair, tack and attachment
outside circumferential edges of roof and bottom sketch welding, shall be carried out according to the welding
plates and for trimming corners of bottom plates where procedure established in 16.2 and by welders approved
two lapped joints intersect, such oxygencut edges shall under 16.3.
be properly cleaned for welding and free from oxide and NOTE. Unless otherwise agreed between the purchaser and the
cutting scale. manufacturer, this standard is confined to manual metat-arc and
multi-mn submerged-arc wdding processes,for all seams. Addition-
. NOTE. These should be reasonably snooth at the welding edges ally, CO, welding using spray t r a d e r is p e r m i t t d for welding
although this would not normalfy requiregrinding if a good quality
girth seams only.
. of workmanship is achieved. i t is particularly 'mpartant for the
, sketch to annular plate connection to be properly prepared and When if is p r ~ p o s t dto utilize welding processes or techniques other
, fitted for welding. than those qrecified in this clause, it may be necessary to modify
or amplify the approval tests and/or inqection t o ensure satisfac-
14.8.2 When openings for fittings fixed on site are tory results. For example, singlepass butt welds may introduce
. manuaHy oxygen cut,then radius arms, srraight edges and special notch ductility problems both in the weld metal and heat-
affected zone and dip transfer welding processescould introduce
nozzle guides shall be used. The cut edge shall be deaned lack of fusian and cold lapping which are.not easy to detect.
and trimmed by chipping or grinding where necessary to Additional tests and/or inspeetion will be the subject of agreement
maintain the correct weld preparation. between the purchaser and the manufacturer.

14.9 Protection of shell during erection 15.1.2 Where manual metal-arc welding is employed in
construction, hydrogen+ntrolled electrodes shall be used
The-erection contractors shall employ suitabfe"methods for for welding steels with specified minimum tensile strengths
the protection of the sheH during erection which have been greater than 430 ~/mrn*in thicknesses exceeding 13 mm.
agreed with the purchaser (see 3.3(j)).When required by
the purchaser, fulkdetails of these methods shall be made 15.2 Welding sequences
available for his approval. The factors to be taken into The sequences in which joints are to be welded shall be
account when determining the suitability of the proposed agreed betweenthe purchaser and manufacturer (see 3.3(l)j,
method of protection shall be: and they shall beadhered to on site. The sequence employed
fa) tank size; for tack welding and welding the bottom, shell and roof
(b) construction method; plates shall be such that the distortion due to welding
shrinkage is minimized.
(c) location and degree of exposure to wind loads;
(dl number and type of key plate equipment; 15.3 Vertical joints
(el availability of reliable meteorological data during I n vertical joints in she[] plates exceeding 13 mm thick,
all periods of erection.
all but the'root runs shall be welded by the 'upwards'
NOTE. The use of steel wire guys or cables may not necessarily be technique. Root runs by either the 'upwards' technique or
adequate and considerationshould be given to the use of temporary
wind girders. by vertical-down welding in such plates over 13 rnm shall
be permitted but, in the latter case, the weld metal shall be
14.10 Erection of fixed roof completely removed by gouging or other suitable means to
Thetemporary support for the erection of roof framing sound clean metal, before welding on the reverse side.
shall remain in position until the completion of the main 15.4 Weather canditions
and secondary framing. Care shall be taken when assembl-
Welding shall not be done when the surfaces of the parts
ing roof sheets on the framing that no excessive
to b e welded are wet, when rain or snow is falling on such
unsymmetrical loading is applied to the roof members due
surfaces, or during periods of high windsuntess the welder
to the stacking of roof sheets. The strength of the temporary
and work are properly shielded. When the parent metal
support shall be calculated using the most unfavourable
temperature i s lower than 0 OC, the surfaces on both sides
loading condition during erection.
of the joint shalt be pretreated to a temperature warm to
When agreed with the purchaser (see 3.3(k)), roofs are the hand, or to the temperature specified in the welding
permitted to be erected on the tank bottom and raised procedure, and to a distance of not less than four times the
into position by an air pressure or other suitable means. plate thickness or 75 rnm, whichever is the greater, in any
direction before welding is begun..During t h e course of the
14.1 1 Erection holes welding operation this preheat temperature shall be main-
Erection holes shall not be permitted in plate work. tained in t h e specified area.
15.5. ~ r e h w t i n g 15.10 Visual inspection
The ~ ~ c . e s s ifor
t y and the extent o f preheat f o r any o f the All welds shall be visuaily inspected.
conditions shall be determined before the procedure tests
are carried out. . . . . . . 15.11 Weld reinforcement
NOTE. Preheat i s not nwmatly necessary on plates less than 25 mrn The weld metal o f both sides ofall b u t t joints shall be
thick if the.thermal input is not less than 1.6 kJlmrn and the built u p so that the finished face i n the area o f fusion
material complies with clause 4.
extends above the surface of the adjoining plates, or the .
For plates t h i d e r than 25 m m and for all thicknesses if thinner plate joined (see 16.2 and 16.3).
the thermal input derived from.the welding process is less
than 1.6 kJ/mm, the necessity f o r preheat shall receive 15.12 Undercutting
special consideration (see BS 5135).
The edges of all welds shall merge smoothly w i t h the
surface o f the plane without a sharp angle. There shall be
15.6 Electrodes
no undercutting o f the parent metal, except that o n
Eledtrodes shall be stored i n their originat packets or horizontal b u t t joints and fillet welds, an undercut n o t
cartons in a dry place adequately protected f r o m weather exceeding 1 m m i n depth shall not be cause for rejection.
effects, Similar precautions shalt be taken i n the storage
o f flux f o r submerged-arc welding. 15.13 Peening
NOTE. lf the electrodes become damp but are not otherwise
damaged. they may be used only after being dried out in a manner Peening o f b u t t welds shalt not be permitted.
approved by the electrode manufacturer. Any ektrodes wbich
have areas of the flux cowring broken away or damaged are t o be 15.14 Repairs
discarded.
Hydrogen-controlled etectrodes shall be stored and 15.74.1 A l l unacceptable defects found i n welds shall be
baked in accordance w i t h the electrode manufacturer's brought to the attention o f the purchaser and his approval
recommendat.ions. shall be obtained as t o the method o f repair (see 3.4b)). . ,.
.-. - 15.14.2 When a section of weld isThown b y radiography :
15.7 Tack welds - . .. not t o comply w i t h this standard, t w o adjacent spots shalt
Tack welds used in the assembly o f the vertical joints o f be examined b y radiography.
tank shells and horizontal joints t o be manually welded If the weld at either of these sections fails t o comply
shall be removed and shall n o t remain in the finished joint. w i t h 77.4.10, then either of the following courses shall be
NOTE. Tack welds in the bottom, shell-to-bottom, roof and followed :
automatically welded horizontal joints of the tank shell and other
joints, need not be removed provided they are sound and the (a) additional nearby spots shall be examined until the
subsequent weld runs are thoroughly fused into the tack welds. limits of such welding are determined; or
(b) all welding performed by the welder i n that joint
15.8 Cleaning o f welds shall be replaced.

C Each run o f weM metat shall be cleaned o f slag and other


deposits before the next r u n is applied. Slag shall also
be removed from finished welds before inspection. Where
I n case (a), i f any additional spot fails t o comply
w i t h 17.4.10 the l i m i t o f such welding shall be determined . '
as specified for the initial section o f the defective weld.
air-arc gouging is used. the surfaces shall be chipped or For case {b),the purchaser shall be permitted t o request
ground back to bright metal before welding. that one radiograph be taken a t any selected location o n
any other joint that the same welder has welded (see 3.4(c))."
15.9 Back gouging and chipping
The reverse side of full penetration butt welds shall be
15.14.3 At1 defects i n excess of the minimum requireme$< ;,:
. . ' . cleaned thoroughly prior t o the application of .the first r u n specified i n 17.4.10 shall be removed by chipping, grinding:;:;,:.
or gouging from one o r bath sides of the joint, as require&:;:;-
:
: . . !.'.:.-.,. . .to this side in a manner that w i l l leave the.expased surface
and rewelded. Onty sufficient cutting-out of the j,oints . . .
: .. ... .. :.,...;
+ '

. . :1,;,:suitable
%
,:' ';.-:

for proper interfusion w i t h the deposited weld . .


. .. . . . .... .. .. .. metal. shaIl be done as is necessary to remove. the defects. . . . ..-
..:".
>
I."

:
. . ..:. . .:.;.',.
15.14.4 All repairs carried o u t bec&e o f nori-complianq@~~::~i
w i t h 17.4.10 shall be 1Od % radiographed unkss the . ' ..'.
complete seam is removed and reive1ded;'in which casethe, &.
. , ".<
~~~~~
original weld inspection procedure shall be fouowed.' ,,,.:<,?,?:!
. -
." , . ' .; .;.-";,,
.. . .-.,.
. . .:,. . J..""

* . . . + . ..:.. *.
. ,..-
;,>'7X,
....
~

_ . . . . . . .,.*.
, .,'f
.*
'.*>.-;
. .. ::_
.*.*
>
'
.
.?:;:."!:'$:>.:
:,i.,I.&.i*.;.:.:$:;
&$.qs@?~989;.
...,% .,l/.* :.
.

. ; ,.: .
.I-;
, .
........
- .,;,' . '.
, ,
~ .
,:':
'

. .
, ~ , .,

...
'

>*-;pc;'. .
:*.r/:&
.;yv -*.*-:. ..
":!>.+,!J - <
- ,., .s. .' . .
< . " ..r ....--
o'. d
"... :
(, a hi.? . ."'. . . . . . .
....:........ ....
<psi<
-.g.3.c
><.;:-
; ;? ., -:
,,,; . . . . .. . .. . .. . *. . . .
,:
"" ,., ," .?'.
:
' '
@&: .: ,:5.",: . . .,..
:.r ,+:* :?,!K, ;::;,'z :. , ., ; .: : 2 . :
-.;.:.
:' . ,;.. .... .............. . ..< .
,

.. . .
;&a :.?'4*
. . , . . .
. -..,.?'. /.. 7.. .- ,-;., . . ., . . . .
,. .?.. . . . . . . . . . .
.....,.-.:
d
?.
. *% <" I '

. . .. .':~- . . . .
,
.+r':.
:.e~-.-" .:' . . .. .. ..
... . .,+:
.+r..- > .:., ... .. . . . ;.-. .. . . . . .
.-?,= -'........ . . . .
+
, .. . . . . . . . .
"..-;z'if...::':
\+

..b .,. " '


1
< ..,... :: . .. ...__:,
' ,
. . . ,'
5 .

I.

... r

$$6 ding
... <,,. . . pr&edure. . . and welder provided the process and conrumabler have been a p p r o v e
:
,ipprwal ,*
. . , l :
o n a weld tert plate in accordance w i t h BS 4870 : Part 1.
.-. y .
.. ,
. < ~ . . .
' . 16.2.3 Examination of test prate. Each butt-welded test
.....< :. ...
, . , ..
. ._:.: '

... : . . . . . . . . .
plate shall be prepared and radiographed in accordance
-.
-46.1
... .
mir rat... ' . . . . . ' .
, --
w i t h BS 4870 :Part 1.
. . .
The.welding processes to be wed for the construc-
.'$&l.l' 16.2.4 Destmcrive testing
*.'ii&of the ta3k shall be usied in.the procedure and welder 16.2.4.1 General, Destructive tiding shall be i n accordance
'a'pproval,tests. ,,
w i t h BS 4870 :Part 1.
':"* ,

i6.t.2 A l l welding procedures shall be approved i n Where impact testing o f the plate material is specified
accordance w i t h 16.2 and all welders shall be approved i n (see 4.41, then impact testing o f the weld metal shall be
accordance w i t h 16.3. carried out.
16.1.3 Previously approved procedures shall be acceptable 16.2.4.2 Impact tests. Charpy V-notch impact test
.
asagreed between purchaser and manufacturer (see 3.3(m)). specimens shall be selected, machined and tested as shown
i n figure 34 and in accordance w i t h BS 131 :Part 2.
The weid metal of vertical shell butt welds and o f manual
*16.2 Welding procedure approval metal arc welded shell b u t t welds, induding the connections
between nozzles and mountings and the shell, hat1 meet
16.21 Procedure derails. The welding procedure specifica-
27 J minimum average Charpy V impact energy a t the same
tion shall give all details o f the welding processes t o be used
test temperature as required by 4.4 f o r the plate material.
by the contractor, including those for repair, tack and
When connections are made between materials o f different
attachment welds and shall also include the results o f such
thickness, the reference thickness for figure 1 shall be that
approval tests as required b y this standard.
of the thicker part joined.
'16.2.2 Number and types of rest plates. The number and When girth seams are welded b y an automafic process.
types o f test plates shall be i n accordance w i t h BS 4870 : t h e Charpy V impact energy shall not be less than 27 J
Part 1 a n d this standard. When steels w i t h specified minimum average a t -10 OC o r a t a temperature indicated
minimum tensite strengths greater than 490 N i m m Z are b y figure 1 using scale A, whichever is the least onerous.
kd'in construction, the highest tensile grade'of steel t o Three specimens shall be tested, the value taken being the
be used in C O ~ R ~ U C shall
~ ~ Obe~ used in approval testing. minimum average o f the three results. The minimum
Procedure tests for nozzle (stress relieved or as welded) individual value shall be not less than 70 % o f the specified
repair, tack and attachment weldsare n o t normally required minimum average value.

$weld and notch


I

I I r

I . !

.55-- I
__C1

All dimensions are in millimetres.

figure 34. Location of Charpy V-notch impact test specimen {see 16.2.4.2)
16.2.4.3 Retests. If one o r more Charpy specimen fails t o purchaser (see 3.2(n)). Otherwise, approved welders
comply w i t h 16.2.4.2, three further specimens shall be shatl carry out these operations.
prepared and tested. 16.3.3 Examination of welders' tesr plates. Each butt-
I f any of the retests fail t o comply w i t h 16.2.4.2, the pro- welded test-plate shall be radiographed in accordance
cedure shalf be deemed n o t t o w m p f y w i t h this standard w i t h BS 4871 : Part 1.
and a new procedure shall be tested. 16.3.4 Extent o f approval. A welder who has success-
NOTE. Nardnesr tt is.remmmended that it is demonstrated in the f u l l y welded the specified tests shall be approved t o the
procedure tests that the hardness af the heat-affected zone at the
shell to bottom plate and of the weld metal, heat-affected zone extent specified in BS 4871 : Part 1 except that:
and parent plate at other lacations in the shell, shauld not exceed (a) a welder who has successfully welded the tests
300 H V (using 30 kg load). using a basic coated electrode shall be approved t o use
Where wet H,S conditions are to be encountered and an appro- rutile, celfulosic or iron powder coated electrodes;
priate low level of hardness cannot be obtained, the most'sultable
way ta avoid stress carrosion cracking will be to protect the shell (b) a welder w h o has successfully welded the tests using
to annular weld area and ihe adjacent vertical shell and annular a rutile coated electrode shatl be approved to use ceflu-
plate weids using an ppropriate paint. losic or iron powder coated electrodes;
16.2.5 Changesaffecting approval. A welding procedure (c) a change f r o m single arc to multipie arc o r vice versa
test shall be required when any o f the changes specified for welders operating automatic or semi-automatic
in BS 4870 :Part 1 and/or the following are made t o an machines requires re-testing.
approved welding procedure.
16.3.5 Records
(a) A change o f brand o f hydrogen-controlted welding
electrode o r i n automatic welding consumables, except 16.3.5.1 Copies of the records o f each welder's approval
for the wire i n submerged-arc welds. shall be available f o r examination o n site by the purchaser
(see 3.4(d)).
(b} For a specified weld preparation in plates 12.5 m m
thick and thicker, a change of more than 2 25 % in the 16.3.5.2 A welder who has been approved shall not be
number o f ~ u n s . I f the cross-sectional area o f the grdove prevented f r o m undertaking p r o d u k i o n work pending
is increased, it is permissible t o increase the number o f examination o f these records, or certified copies o f these
runs i n proportion t o the increase in area. records, provided 16.3.5.1 has been complied with.
I d For automatic girthseam welding, a change f r o m
multiple runs per side t o single r u n per side.
(d) For automatic girthseam welding, a change from
17 Radiography
single arc t o multiple arc o r vice-versa.
17.3 Application
16.3 Approval process for welders The procedure specified i n this clause shall apply to the
inspection of the joints listed i n 17.3. Radiographic
16.3.1 Approval of weldem Each welder shall be approved examination of fillet welds shall not be required.
before welding on the tank. A welder w h o has successfully
welded the procedure test plate shaIl be considered t o have 17.2 Preparation for exami~tion
been approved.
Surface dressing o f butt-welded seams is not normally
16.3.2 Approval tests. Each welder shall be approved in required except that surface irregularities which may
accordance w i t h BS 4871 :Part 1 and this standard, except confuse o r mask any objectionable defect shall be care- .:;
.,
for the following applications. fully removed.
..
(a) Unless specifically required b y the purchaser - _ .. . .
17.3 Extent of radiography per tank .......
(see 3.2(m)), a welder w h o is only required t o make
I.I. j

<~
'; ,:.
fillet welds o n the tank bottom, roof o r shell plates n o t 17.3.1 The extent o f radiography shall be n o t less than . ;:,. .:_.
exceeding 12.5 rnm thickness, except f o r the shell-to- that listed in tabte 6 for each plate thi.&ness, but shall :$-j:. :
b o o m weld, is n o t m u i r e d to pass an approval test, inctude one radiograph taken f r o m the 'first w m p f e t e d :$$?:;
.,
but his standard o f workmanship shall be such that the vertical joint f o r each welding process and thickness, >,;:<;'
requirements o f this standard are maintained. +
,

if differing by more than 3 mm, welded by each welder.%:,:..:.


(b)Tack welding o f shell, roof o r bottom, where the Thereafter, without regard t o the number of welders '1. ;, +.!,;
. .;<...q:+- .. ,?

.f
working thereon, the same incident+ o f radiogiaphy shaH.',".+,..~..
.-r...
tack weld shall be removed by gouging o r shall be
. . ,, ,.' % . +->f.:,< .
~

1 .' completely fused, can be carried out by nonapproved be maintained. . . -. . . . . .. . .


...
,

...
.t,C
"

. . .. A:'&.;..

. . operators w h o are suitably instructed and supervised t o NOTE. The location of the radiographs.ii'.ti
. . be &@mined in,;
.. . . .,. . :-:,$4j:;,.,.< . : .
the purchasei.'~satisfaction when permitted by the ' agreement with the purchaser. . . :.* . - . I,.
"

. . . '. . .. . . .,>.I.:;."
. .
.L .
. :. . .

Vsrtimt welds and f joints . Horizontal -ma Annular battoxi butt wddr;: ..
. .

10 % of total seam length 2 % of seam length


plus alt T-junctionst
10 % of total seam length, 2 % of seam length -
a t least half of the
radiographs to include

I T-junctions
'

Up to and including 13 mm 1 56 of total vertical 1 % of seam length -


seam length
Annular plates over 10 mm - All joints
Annular plates over 8 mrn Half the number of joints 1
-'up to and including 10 mm
. .
Annutar plates up to and A quarter of the number
including 8 mm of joints, with a minimum
of 4 radiographs

'The length to be radiographed shall consist of that length from the outside of the annular plate to a p d n t 250 mm inside the tank.
t50 % of radiographs with film horizontal and 50 % of radiographs with film vertical.

17.3.2 Butt welds around the periphery of an insert plate subjected to mechanical or chemical damage and it is
shall be radiographed over the whole of their length. particularly important to guard against inadvertent expo-
ww ..,
NOTE.When two or more tanks are erected in the.same location sure to sunlight, radiat5n or excessive heat.
for the =me purchaser, either concurrently or consecutively, 17.4.4 Standard test radiograph. The exposing, film pro-
the initial radiographsof the work of each welder need only be
taken on one tank. In addition. the total number of radiographs
cessing and handiing procedures shall be demonstrated to
taken may be based on theaggngate length of welds for the same the purchaser and shall be subject to his approval
type and thickness i n such a group of tanks rather than on the (see 3,4(e)). A standard t e s t radiograph shall be prepared
length in each tank,'ht with a minimum of 50 % of the coverage and shall be made available for inspection.
requirementsgiven in table 6 on each tank.
17.4.5 t m g e quality indicators. To check the degree of
11.4 Radiography procedure definition and contrast achieved and to determine whether
the minimum radiographic standard is being attained,
17.4.1 Techniques. Radiography shall be carried out in an image quality indicator complying with BS 3971 shall
accordance with BS 2600 :Part 1 using techniques 1.2,3, be used with dimensions appropriate to the thickness of
6 or 7 for plate thicknesses up to and including 19 mm and the weld. The method of assessing the radiographic sensi-
techniques 1 or 2 for plates thicker than 19 mm. tivity shail be that described in BS 3971.
NOTE. X-radiography i s preferred to gamma-radiography because
of the inherent low contrast of the latter. I f , because of local 17.4.6 Film Iucation. The film during exposure shall be
conditions or special cimmdances, gamma-radiography i s used as close to the adjacent weld surface as i s practicable,
the isotope employed will be iridium 192.
17.4.7 ' identification markers. ldentification markers,
17.4.2 Intensifying screens. Lead screens shall be used in the images of which will appear on the film, shall be placed
all the techniques and their thicknesses shall be in accor- adjacent to the weld a t each spot examifred and their
dance with table 3 of BS 2600 : Part 1 : 1983. locations accurately marked near the weld on the outside
17.4.3 Radiographic film. Each film shall show clearly a surface, so that a defect appearing on the radiograph may
minimum of 300 mm of wetd length; it shall be centred on be accurately located.
the weld and shall be sufficiently wide to permit adequate 17.4.8 Referem marker. There shall also be a suitable
space for the location of identification markers and image reference marker on each film.
quality indicator (1QI). Care shall be taken to ensure that
films are carefully handled and stored; they should not be 17.4.9 Submission of radiography. All radiographs shall
be submitted to the purchaser.
t 7.4.10 Radiographicstandards. The defect acceptance 18 Testing
levels given in table 7 shall be imposed during fabrication
as a means of quality control. Areas found to be outside 18.1 General
these limits shalt be repaired in accordance with 15.f.4,
18.1.1 A comprehensive test procedure shall be s p c i f i d
17.4.1 1 Record of radiog&h;c examinarion and agreed between ?he purchaser and manufacturer
17.4.11.3 The erention'&ntia~torshall make a record of (see 3.3(n)). The water test procedure shall specify .

a l l films, with their identification marks, preferably on a maximum filling rates, hold periods, emergency and normal
developed shell plate di&iam. emptying procedures, method of settlement measurement,
NOTE. Other agreed methods comparable with this diagram may
limits for differential and maximum settlement of the
be acceptable. foundations, minimum water temperatures. etc. (see AS).
On completion of the test, the manufacturer in conjunc-
17.4.11.2 After completion of the tank, the films shall
tion with the purchaser shall review the settlement data
be retained for a minimum of 5 years.
and determine that the tank is fit for service. Consideration
shatl also be given to the effect of future settlements.
18.1.2 No connections shall be made between a tank and
Table 7. Acceptance Ievels for radiographic examination
any product fine until the tank and i t s appropriate mount-
ings have been satisfactorily tested in accordance with 18.2
Defect type Permined maximum
to 18.6.

Crack Not permitted


18.2 Bottom testing
Lack of fusion Nut permitted
Incomplete penetration Not permitted except as 18.2.1 The bottom of the tank shall be tested for leaks .
4.
. specified in 7.5.2 using either of the methods in 18.2.2 or 18.2.3.
, - . -
. . . ., .'.

Isolated pores -. .,.


.-~
# t/4
- ." 18.2.2 The bottom seams shalf Wested by thevacuum ' :::"
.
- box method using a pressure of 650 mbar absolute

Unifwmly distributed or
locaiized porosity I 2 % by area* (as seen in
a radiograph)
(is. 350 mbar of vacuum).
18.2.3 Alternatively, after the tank bottom and at least the
bottom course of shell plates have been welded, air shall be
pumped beneath the tank bottom at a pressure sufficient
Linear porosity ( Linear porosity in vertical
to lift the bottom plates off the foundation. The pressure,
I welds paraltel to the axis
of the weld may indicate
lack of fusion or lack of
which shaH be 7 rnbar maximum, shall be held by the
construction of a temporary dam of clay or other suitable
penetration and therefore material around the tank periphery. Soap solution or other
is not permitted suitable material shall be applied to the ioints for the
detection of leaks.
Wormholes, isoiated 1 Length* 6 rnm 18.24 The bottom and bottom-to-shellweMs shall be :.
made free of leaks as required by the purchaser (see 3.4(f)):
Wormholes, aligned I As hear porosity

Individual slag inclusions


parallel to major weld axis
NOTE 1. inel~rionsto be
I Length >t
18.3.1 Pneumatic testing of the reinforcing ptates is not .
required unless specifiedby the purchaser bee 3.2(6)),. 'm:??:.
:?,::. ...
repar,atedon the majw axis. when it shall be done at a pressure of I'.bar prior.to the'';?;?- .....d; ;: ' ,-..
by a distance equal to or . . , shell water test. For this purpose. tapped of 12 nim;: +.;:
greater than the length of - . :
the l o y e r inclu$on and The
'
diameter,muimum shall-beipedand . . . .. . . . .. .&&"tip!$
....
. . .. . . . . .
s.blf.,F
_. ,-:. .$.
::$:$j:)
the.;. left open aftertesdw-
.. ., , , ,
,
$rim of the lengthrof ...,. .:. .: . . . . . .::;, .;+&:;,;:: .'
<'

'inclusions.sh~l,+t ex*'.. , 18.12 The ioofdrain shall in&li&.wihf t&'ih$<.:i:i.5;>:$ix>:


/~

the totat weld,l&gth being . . .". + :. .. .,


hydraulic t e a m the tank a d d j h g this t& ths d&.y?~$$7
:4 b

exwined '! .
:, .... ..-., . .. .
... . . . . . shalt be examined to &&re that jt 6s not .!&king
"
dlre:toI:-$>.;:
.. .. - . I . .... . .. .. .. - . -. . ,,,:.**',
external pressure. . . . . . . . . : . .- ' .*. .. .. . . . . . . ;':..s.
"

'Area to be mnsid&ed should be the length of the weld . ,. . ..,, ...:...


- . % " . :.
. --....n..' .
affected by porosity,muItiplied by the maximum width of the
wdd locallyl ",. .
NO~E 2. In this table rhe tollawing symbols are used:
.$is a defect diameter (in mm); '

:t,i s t h e thieness of thinner plate be& joined (in I&).

:.
. .......
^._.
I

: , .
--
._
. .
.. . . .
I . . . .

<..- .
. > . .
'..
. . . . . ." . .. . - . . .
. . . : " . ; ...
. .

. ,

, ..

caused by the deeper immersion in the stored product . .


than in the water (see 3A(gI). .
............ water to the . . . . . . . . . . . . . .
~i~'ciel~&pe@j&
. . , L ~. . .
t in 7.21. The rate of.. ,filling shall not exceed 18.5.4 pin-holesand/& defective &eldingin&iirk i m &. d .
.
,;,that:s&cifiiNd'$t,
::j;.. .... .;. . . . . . . . . procedure.
. to be in contact with the product shall be corre~ted't;~ . .: ~

. . . . . . ,. . , . . .
.~€J?&bttei+~~<diiim tM notes of figtire 1relating to the welding. ,. .. - ' . .. ". .. . . . %
. ..
. .
jnnnihm test rvatet'tmerature and i o the m m e n d a t i o n s NOTE. Isolated pin-holes in -r not in &act with the product' - '' ''

a$!~.~eFati~$~t& the rateof teit h e r fillin#. . may be caulked mechanically. .


.. +. ..... . . . . . . . . .
. ie2,'c.. .
: %..'
,,.r...,.:,
',' . ,- .'".*.
,.-: ........ -? .. .i.bt.'. > .....
', ~
. . . . . . . . . . . .
<J18.d.X
...F~... .. fie ma'ik$a$&r shill be infoi-medby the 18.5.5 The sealing mechanh shafi be checked to ensure
- .w. . h & r ' o f ihk&iatity,,of the water to be used and if proper functioning ov& the full height of the shell.
'&ci,sary. any yleciat cleaning or corrosion protection,
e.g. inhibitor or cathodic protection (see 3.1 (k)). 18.6 Fixed-roof testing
38.4.3 '&ntirmous i n m i o n shall be maintained for the 18.6.1 When the tank shell i s tested with water the roof
whore filling period. Ait leaks found shall be repaired with joints shall be tested by applying an internal air pressure
the water level at feast 300 mm below t h e point being equal to 7.5 mbar for non-pressuretanks and 3 mbar above
repaired.
. -
the design pressure of the tank for pressure tanks.
..
. -, ._
.:: 18.4.4
I

During emptying of test water, precautions shall In the case of oolumn-supported roof tanks, the air test
, .
:;. betaken to ensure that the design vacuum i s not exceeded. pressure shall be limited to that pressure equivalent to the
.....
weight of the roof plates unless the compression area has
been determined in accordance with 8.5, using a design
3-'
.' pressure of 7.5 mbar {see 2.1.2).
.,-=;
: 18.5.1 The centre dedc plate, pontoon bottom plate a n d Soap solution or other suitable material shall be used for
g rim ptate welded joints shall be tested by spraying with a
the detection of leaks.
.-.I. . penetrating oil, such as light gas oil, on the bottom side
NOTE. Attention is drawn to the need for careful control and
, . and inspecting visually on the top side and inside of rim
monitoring of pressures during this testing. Climatic chawes can
: plates. cause sharp fluctuations i n test pressures and pmvision rhouid be

,
...
made for the safe relief of pressure or vacuum i n the m n t of such
,.
1.
fluctuations. .. =
.

'. .. '18.5.21
. € i t h i of the methods of test specified in 18.6.2 Pressure a n d vacuum or free vents shall normally
..: or 18.5.2.3 shall be applicable. be installed after completion of the tank water test or
3'

'.:
:- 185.2.2 The filler welds connecting the bulkheads alt&natively shall be blanked-off during the testing of the
<. between wntoons to the inner and outer rim plates
..*,
roof. After installation or immediately following the roof
.,'i the pontoon bottom shall be examined for leaks using pressure test all vents shall be carefully examined to ensure
',v. penetrating oil prior to the installation of the pontoon top that all packing and blanks have been removed and that
:
.*; plates. When continuously welded. the welds connecting all moving parts function normally.
' :' the pontoon top plates shall be inspected visually for NOTE 1. AnchoragesJ I f tank anchorages are provided. these should
pinholes or defective welding. be checked and readjusted, if necessary, with the tank full of water
and prior to the air pressure test.
18.5.2.3 Alternatively, when the compartments are NOTE 2. Foundations. Attention is drawn to the recommendations
completely welded, each completed compartment of of A.5, When foundations are not constructed i n accordance with
pontoon roof shall be individuaHy tested with an air appendix A i t i s still advisable that the rceornmendations i n A.5
are adhered to.
pressure of 7 mbar gauge, a soapy .water solution being
Water filling should be stopped immediately there is evidence of
applied to ail welded joints under pressure which have not
excessive abnormal or unexpected soil movement or the differen-
been previously tested with penetrating oil. tial or maximum settlements are tending to exceed those specified
i n the testing procedure. I f there is a risk o f continuing excessive
18.5.3 The roof shall be given a flotation test while the settlements or m i l movement, the tank should be off-loaded.
tank i s being fifled with water and emptied. During this
Any tank showing evidence of ledrage from the bottom during
test. the upper side of the lower deck and all pontoon water tat should be emptied immediately. The source of such leaks
compartments shall be examined for leaks. Rainwater shall should be determined and rectified. Where there is a risk that the
be prevented from entering the pontoon compartments leakage may have caused washout of the foundation material,
during this test. the foundations are to be inspected. The repair of the foundation
should b e the subject of spsial consideration and approval by the
During the initial filling with product the purchaser shall purchaser.
check pontoon compartments and decks for any leaks
Appendices

of significant bottom plate settlements (see 8.2.1 1.


Appendix A. ~ecomrnenda&ons
for ...
. . ( c ) Ewnamic considerations, e.g. savings of foundations
' : : tank foundations costs versus the risk of excessive settlements and .the
possibility of future maintenance costs.
A1 General (dl The allowabfe relative movement of adjoining or
related foundations or pipework.
A.1.1 The recommendationsgiven in this appendix are (e) The difference in settlement between the periphery
intended to establish general principles for'the design and and the centre.
construction of foundations under vertical oil storage tanks. Settlement calculations are of limited accuracy even with
They are offered as an outline of good practice and point detailed investigationand sophisticated analysis. f anks
out some precautions which should be observed in should not therefore be designed to depend for their
constructing such foundations. integrity on precise settlement predictions.
~ 1 1 . 2~ecauseof the wide variety of surface, sub-surface A.2.3 Maximum tank settlements can vary from a few
and climatic conditions, it obviously i s not practicableto millimetres to a metre or more. The initial settlement
establish design data to cover all situations and the allow- measured a t water test can be greatly exceeded during the
able soil loading should be decided for each individual case life of the tank particularly on weak slow draining sub-soils
having regard to the type and size of tank. The design ,
and the amount of settlement may also be affected by the
should be generally in accordance with CP 2004 and take cyclic nature of the load. The extent of the differential
account of the special nature of the soiljstructure inter- settlement will depend on the uniformity or otherwise of
act ions and the definition of the load.
the sub-soil, the stiffness of the tank and any interactive
A.1.3 If tank anchorages are required according to effects from adjacent tanks. The use of foundations with
clause 10, suitable foundations are required. The design large permissible settlements should only be considered ..
of these foundations should be based on the loadings after a thorough site investigation and in consultation with
soil mechanics specialists.
-
specified by the tank designer.
'.
The following are some of the many variations in condi-
tions which should, i f a t all possible, be avoided for the
A 2 Site design considerations construction of tank foundations. Where, from ecanomic
considerations or lack of alternative areas, they are unavoid-
A.2.1 At any tank site, the nature of the sub-surface able, then they require special considerations.
conditions should be known in order to determine the
variation of soil properties over the site and to estimate the (a) Sites where part of a tank may be on rock,
amount of settlement that will be experienced. A site undisturbed ground or other construction and part on
investigation should be carried out in accordance with fill: where the depth of required fill is variable; or where
BS 5930 to identify the ground conditions under the ground under part of the tank area has been precon-
complete area of kach tank to a depth over which signifi- solidated.
cant settlements may occur. Where the founding material (b) Sites on swampy or filled ground. or where layers of .'
i s sound or weathered rod, the site investigation shall be highly compressible material are below the surface.
supplemented by geophysical mapping of the tank pad fc) Sites where stability of t h e ground is questionable;
formation. such as adjacent to water courses, deep excavations or ;' ,

Additional useful information can be obtained from a heavy loads, or an hillsides.


review of sub-surface conditions and the history of similar (dl Sites where tanks may be exposed to flood waters, ';'.1:
structures in the vicinity. resulting in possibie uplift, displace&ent or scour. . .;.I ...
:--
The allowable soil loading can then be decided in relation Special consideration should also be given to the effect on\:;::; .
, to the reliability of predictions of ultimate bearing capacity the foundation of heated tanks. .; .?:#.;
...
and the permissible settlements by a soil mechanics ,'*r.T;
specialist A 2 4 I f the wb-soil supporting t h foundation&
~ k ;.k -:,;:,.
. . .- . . . and inadequate to carry the load of the fiiled tank witho~$$,:
.. '
2 permissible'settlementi s the maxirnhn atlow-
. 7 : .~
. i The excessive settlement, the;following methcid$should . b&.:,5$5?
. . ..
. . r . able design limits for the settlement of the foundation.
-.. ' . . ,..- .'.&.: r
considered. .. .. . . .. . ... . ' ? .,.. .;,.,F;,:
. .,-.-
:. ; : :.: - I .These limits are to. be ggreed between the purchaser and
the manufacturer for the maximum and differential settle-
ment across the bottom and around the periphery of the
tank. The considerations affecting the limits of permissible
. .
. .. ' -. .. . . : :.? ~. '
..settlementare as foltows.
. . ... .. . . .
." . ,. '. .:'... .'... . . (a) The dimensions and ratio of the tank.
.. ., . < " . . .
..... ;... . , . . .(b) he type of tank, eg. open-top tanks with pontoon
. .. . ., ..
I ,,,~pe-floaging roofs will ge.nerally tolerate a much
. - ,+.
.,
. .. .:. , . . .. .. .:;i: . - :'smaller differehal settlement around the circurnfer&ce
>,. . . .. . .. . .
. . .. . .. . .. . ..than fixed-roof tanks. Tanks with column-supported
'
L
.
. . . ....
. . .
. . .. * . . .. .:. . . . . ioofs require special design considerations in the event
, .
.GJZi.:- -
..:,IS !jhstrated iiifigure 35; is described i n A.3.2 to A.3.6.
,. !. -.,'.. .' . . .
...!.Y< . . , . .. . .
'+@ -
- -$. ),, ,): ~ ~ ? . ~ . : ~ i h i f = i iaatqpicaI
-.-'.. t:k fobndation and to
repiace
:.:anyumatisfactoiy
3..~"" , -..- ,- *derlyiri&dt spots, should be sound, :.c . .. . . _ . .. .
. :.. .:... "".+.'.
'

bottom, ~eA.4.2); ... . ... .,_ .,?,,. .*,,-


..... , .,. I- . .
.' . .; .&; -,
,:~~,ei$i$:w@:c&rable. I t should bind to form a dense surface . ., . .',.,";.'? : .
, ' , "

.. . -. ,, " ,
. ... .".*," ~..-.;. .' .
iTwtieh laid'in'l56:mm layers'and rolled with a 6 tonnes A.3.4 When the profile of the &f&e i; cornpi& it Vhould ' . . . ;." ..
' '
. '
.%'.40 tor&s roller. het to^
surface of the pad should be covered with a smooth bitumen-sand mix that (5 50 rhin
!&&poiate a stable perqweable granular drainage layer, thick.to weatherproof the foundation and provide a layer.
. .:
..ftiebore of the pad can be &nstructed from any highly sufficiently firm to carry the necessary traffic and facilitate
"compactable, chemically inert, locally available material welding of the bottom plates. This layer will also retard
:that is not susceptible to frost heave, is noncorrosive and corrosion of t h e tank bottom. Mill scale should have been
i s of low compressibility and sufficient strength. An annular removed from the underside of the bottom plates to
ring of coarse gtanular material may be required to provide minimize corrosion (see 3.2(i)). This bitumen-sand surfac-
'...high edge load resistance when the locally avaiiabte material ing should extend outside the tank periphery to protect
. . the external surface of the foundation and may need
L h as tow strength except when confined, e.g. most sands.
re-trimmingafter the water test and from time to time
. ;. The annular ring may also be required to prevent wash-out
during operation to maintain suitable water drainage away
4.

<,; of fine soits in thqevent of a bottom leak and provide from the tank. Bitumen-sandsurfacing should be omitted
A ..
,.,: protection against.erosion around the tank perimeter.
where cathodic protection of the tank bottom is adapted.
C-il~ A 3 3 It is suggested that the surface upon which the tank
'-2 bottom will rest be constructed to a height of a minimum

Stable permeable cornpocted


100 min. SO thick bitumen- granutar drainage layer
sand mix approximately 150 thick

@ 7 5 mrn PVC pipes or ThoroughIy ~ o m p a c f e d


equal at not more than chemicaLLy inert f i l l o f
5 m between centres granular or o t h e r stable,
around periphery, ptastic heave free, low compressibility
mesh screen over inside mater~al
open end

AH dimsnrions are in millimetres, unless otherwise stated.

Figure 35. Typical tank foundatiin


A.3.5 A suitable bitumen-sand can be produced by hot- Where the foundation design incorporates a ring beam,
:
mixing i n the following proportions b y mass: care shoutd be taken t o ensure that the relative settlement
(a) 9 k 0.5 % (rnlm) non-toxic c u t back bitumen characteristics o f the ring wall and the infill are n o t such
I (is. fluxed w i t h kerosine and n o t creosote'); as t o result i n excessive differential settlement local t o
the inner wall o f the ring beam. Consideration may need
(b) 10 ir 1.0 Sg ( d m ) filler: either limestone dust passing
t o be given to the provision o f a hinged transition slab in
a sieve o f nominal aperture size 75 pm complying w i t h
this area. A minimum thickness of 50 m m o f bitumen-sand
BS 410, or Portland cement;
should be maintained over the concrete.
'(c)81 + 1 3 % (rnlm) clean dry washed sand w i t h the
properties given i n table 2 o f BS 882, 1201 :Part 2 :
1973.
A.5 Water testing
As an alternative t o the sand, crushed rock types 1 t o 7,
slag o r limestone i n accordance w i t h table 53 o f BS 4987 :
While it is normal practice t o test all tanks b y filling w i t h
1973 may be used,
water before commissioning, this filling should be done
Some variation o f these proportions may be necessary t o under controlled conditions t o ensure that foundation
suit ambient temperature conditions, locally available failure does not occur during filling. The water test pressure
materials, etc., and it is recommended that trial mixes be is an integral part of the foundation design and should be
made i n order t o achieve the correct proportions t o suit agreed w i t h a soil mechanics specialist.
the partiarlar case.
All tank tests wilk be carried o u t t o provide adequate
A.3.6 A series of 75 mm diameter PVC pipes should be measured load/settlernent records.
ptaced around the perimeter o f the drainage layer and The first tank i n a new area w i l l be the most critical and
protrude through the bitsand facing t o the berm t o give subsequent testing arrangements o n other tanks should be
warning of any b o t t o m plate leakage. The pipes should be adjusted in the light o f the first test results where the tanks
at not more than 5 m intervals and the inlet should be are o n similar sub-soil conditions.
cpvered w i t h a mesh screen t o prevent clogging by material
A minimum o f four points o n tanks under 25 rn diameter
from the drainage layer. I n special cases it may be
and eight points o n tanks.over.25 m diameter should be
necessary t o introduce an impermeable layer below the
marked around the base o f the tank for subsequent levelling
base o f the foundation pad (see figure 35).
reference. A greaternumber o f points may b e required for
large tanks andlor where a complex settlement pattern is
expected. Before water is added t o the tank, the levels a t
A.4 Modifications and alternatives to each reference point should be recorded. Permanent refe-
typical foundation pads rence levels have t o be established in locations unaffected
by tank loading.
A.4.1 Where poor subsoil conditions necessitate the use As a guide, when ground conditions are good and settle-
o f a reinforced concrete raft and piled foundations, the raft ment is expected t o be negligible, the tank may be half-
should be designed i n accordance w i t h normal reinforced filled w i t h water as quickly as practicable, having regard to
concrete practice (see CP 114 or CP 1101 and surfaced its size, the pumping facilities and water suppry avaifable.
w i t h a reduced thickness o f bitumen-sand m i x as described N o further filling shoutd proceed untit levels have been
i n A.3. taken and checked against the readings when empty t o
ensure that no uneven settlement is occurring in which case
A.4.2- Where a tank w i t h a central internal b o t t o m drainage filling can proceed u n t i l the tank is three-quarters full, when
sump is required: level readings should be taken again. Provided the tank
(a) o n hard ground where little settlement is expected, remains level w i t h only slight settlement due t o load, filling
the tank foundation may be given a slight fat1 t o the can then proceed until the tank is full, when level readings
centre; are again repeated. The full water load should be main-
(b) on poor ground where considerable settlement is taind for 48 h and provided levels remain sensibly consis-. . .,
expected, special consideration should be given t o the tent, t h e tank can be offloaded prior to calibration for .:' ,

possibility o f unacceptable tensile stresses developing service. Provided this tank is satisfactory and subsequent ,.:
in the b o t t o m plates and in such cases a foundation tanks are founded similarly. the level readings a t one-half .'. .
'

constructed as recommended in A.4.1 should be used. and threequarters capacity may be omitted for small tanks. . ".
o f less than 25 m diameter. O n weak:'grbund where signifi-
A,4.3 F o r high-pressure tanks, it may be necessary t o cant settlements may be.expected or where the initial
prevent upfift o f the shell due t o the combined effects o f
, .
factor o f safety against slip failure is low, the rate o f fitling
vapour pressure and wind movement by means o f an should be greatly reduced. Some guidance o n the safe
anchorage around the shelf built into a suitable concrete heights for initial filling and where pause's in fitting are
ring o r raft.
. .

*creosote fluxed bitumen i s not considered t o be acceptable in view of i t s acid content.


. .... ,
., .
sprayed-on'insulatmn, m q
b
in
f$
g
.i in situ oi by i @ c h a ~ i a l' . .. . .. ,....
. ..
-

attachmentsto the tank.'While wetding of stud; &St& . .: . . . : * '


. .. ..

shouldbe added to the tank in decreasing increments of members to small t k k s may be satisfactory, welding on
head when the settlement graph shows that the rate of large tanks can materially affect the design and integrity
settlement under each new increment of load is reducing. of the construction but it is permissible when considered
As the water toad nears the full capacity of the tank, water as part of the tank design. The use of adhesives isa possible
should preferably be added after an early morning check alternative method of fastening attachments where welding
of-referencefevels so that further readings can be taken cannot be permitted but is subject to temperature limita-
_duringthe day and the tank offloaded should the rate of tions and should only be carried out by specialists in this
-:-<settlement increase unduly. On very weak soils, these tests field.
'may extend aver considerable periods and where such The basis of all weldedun attachments should be to provide
'- conditions apply, the tank builder should be advised so that a series of points disposed cirarmferentially on the tank at
adequate provisions can be made in his programme for the a number of vertical intervals, on to which vertical andlor
I
necessary resting and acceptance procedure, horizontal members may be fastened. The support structure
:&,~omeguidance on-safeheights for initial filling and where and welded-on attachments should be designed so as to
::
i. pauses are desirable may be deduced from the shear transmit back to the tank all the dead loads and super-
-?;strength data and strata thicknesses of the underlying sail. imposed wind loads expected to be experienced a t the
+ .
.. location concerned.
:..In carrying out such test procedures adequate arrangements
.*:.
'
:::should.bemade for the emergency disposal of water i f off-
;":>" . . .
~.:@ading
.. ..,
'

became necessary. Dischargeshouid be to a safe


Design aspects which are nqt dealt with in this appendix
should wrnply with tbe requirements in the main body of
the text,
-
-:i.
. ..
area, ckar of all foundations and structures and such that
+ ::no danger of erosion can occur; On existing tanks, careful consideration needs to be given
in such cases to the safety aspects in providing the attach-
ments in order to take account, where corrosion has taken
. IJ

"-.+? Appendix B. Recommendationsfor the place, of the corroded shell thickness and to provide an
adequate safety margin in the design of the system as a
,.,.,designand application of insulation whole.
.. ..
The basic consideration necessary on methods to be
B.1. General employed to achieve acceptable insulation systems are set
out below. These insdation systems suitable for large tanks
This appendix i s intended for new tanks but may also be include:
used for existing tanks. While not attempting to specify
(a) man-made mineral fibre or preformed foam block
in detail the insulation systems themselves, it is intended
with cladding;
to provide a sound basis on which these systems can be
specified and particularly to facil-Me the provision of (b) in situ foam behind cladding;
suitable mechanical supports for the insulation materia!. (c)foamlcladding laminate sheets;
these wppdrts to form an integral part of the tank fabrica- (d) sprayed foam.
tion. The recommendationscover storage tanks operating
a t temperatures above ambient and of a size where banding This standard recognizes that for a particular installation
is unreliable and direct fixing to the tank is necessary. a proprietary system of insviation including fixing and
weather protection maybe suitable. I f a proprietary system
In order that a correct choice may be made of type and is offered, specific acceptance should be obtained,
method of providing the insulation attachments, it i s the element of the system that constitutes the mechanical
emphasized that, where new tanks are concerned, early support which forms part of the tank fabrication being
consideration of the need for insulation is essential so that clearly identified.
the necessary provisions for it can be integrated with the
tank design and erection programme. This consideration In this appendix, separate references are made to the tank
designer, i.e. the organization responsible for carrying out
should also include the possible need for insulation of the
the design of the tank, and the tank fabri&tor, i.e. the
tank roof.
.
organization responsible for the ereqi?~of the tank, but it
On small tanks the problem of attaching the insulation is recognized that this distinction is only necessary in the
securely is not serious but on tanks above 10 rn to 15 m event that the two parties are not the same.
diameter problems due to wind loading, associated
B.2 Design considerations B.2.4 Thermal expansion
The possibility of relative thermal movement between the
8.2.1 General tank and the insulation system should be taken into
The design of an insulation system, which incorporates the account in the design. The purchaser wiH state the range
insulating material, i t s means of attachment to the tank and of operating temperatures.
. ,.
i t s means of weather protection, should take into account
.the following: B.2.5 Movements due to hydrostatic pressure
(a) the product in the storage tank under i t s operating The pressure of the tank contents causes slight bulging
conditions; which may account for an increase in tank diameter of the
order 0.1 %;this may need to be taken into account in
(bl the storage tank itself; designing the insulation system and the actual value is to
(c) the insulation materials; be provided by the tank designer.
(d) the mechanical support system associated with the
insulation system;
(el the means whereby the insuiation and i t s support
8.3 Mechanical support arrangement
system is enabled to withstand environmental conditions.
B.%t General
The insulation system is to be agreed between tank designer,
The mechanical supports may be divided into the following.
insulation contractor and the purchaser.
(a) Primary mechanical supports, where the members
The system including its mechanical supports and fastenings
form part of the mechanical support system and are
should bedesigned to withstand the mechanical and therrnab
directly attached to the tank surface.
stresses to which it will be subjected resulting from all
known factors including those4isted in 8.2.2 to B.2.5. (b) Secondary mechanical supports, where the members
These factors should be assumed to occur simultaneously. form part of the mechanicalLsupportsystem and are not
directly attached t o the tank but are fixed to the
Because relatively large forces are involved.in providing a
primary support members or to other secondary support
secure system for the attachment of insulation to the
members.
outside of storage tanks, the mechanical support arrange-
ments can be extensive and will frequently be attached Suitable mechanical supports for the insulation system
to the outer face of the tank itself. The design of the should be provided by one of the following means or a
attachment of the support system should be subject to care- combination thereof.
ful scrutiny by the tank designer and he should ensure that (1) Primary supports, welded to the tank, to which the
a minimum of attachments are used, insulation system is attached either directly or by
Preliminary discussions with insulation contractors are secondary supports.
.often helpful in identifying suitable systems and the type (2)A structural frame that is substantially self-supporting.
of supporting arrangements likely to be necessary. (3) Primary supports fixed to the tank by adhesive,
to which the insulation system is attached.
B.2.2 Dead toad
Welding is the preferred method of attachment but may
Dead laads result from the weight of all parts of the not always be possible especially where existing tanks are
insulation system. to be insulated. While in each case the system chosen is
to be with the agreement of all parties concerned, the direct
B.2.3 Wind loading responsibilitieswill be as follows unless otherwise agreed.
In the design of the insulation system accarnt is to be (il In cases ( I ) and (31, the insulation contractor should
taken of t h e effect of wind loading using CP 3 : Chapter 5 : agree with the tank designer the locations of the supports
Part 2 as a basis for estimating wind pressures. The para- to which the insulation system i s to be attached and the
meters required for using CP 3, including the basic wind loads t h a t will be transmitted to the tank and the basis
speed appropriate to the site and the factors S1, 52 and S3, on which his calculations have been made or other
should be agreed between the tank designer and the referencedata he hasused. I f required, h e should provide
gurchdser and this information given to the insulation .
details oft h e calculations to be approved by the tank
contractor. Unless otherwise specified, the parameter 53 is designer.
to be'based on a life of 25 years. At present CP 3 does not
give pressure coefficients for the full range of shape factors
(ii)In case (2)where an external structure or frame is
that are of interest in large tank insulation and further data intended, this wit1 be regarded as part of the insulation
are required to.include smaller heightldiameter ratios, system to be provided by the insulation contractor.
appropriate roof profiles and the effect of proximity where The design and erection procedure should be agreed
more than one tank i s invohred. with the tank designer but will be the responsibility
of the insulation contractor unless otherwise agreed.
The tank designer should agree with the purchaser the basis
on which the wind loading calculations are to be made. The dimensions of the mechanical supports normal to the
surface to which the insuiation is to be attached should be
an agreed size to suit the insulation thickness.
.:. : z -
the adhesive manufacturer, account being tak=,npf+the.1. -:- :.::'.' ' , -
..
&&qvi,ng & rhaterial and the welding procedures.
./:

suitabiliti of the adhesive formulation for th'ambientr.', : .:.+


'-:rf&r
..... .. . . '-

..;:m.:. e;
.,t
ank fabricator ,will'be responsible for fixing the . conditions, particularly temperature, a"t the time o f . . . .. . . ... .'..
application. Procedure, qualification and acceptan&.te8ts ,' . .:.
.. 'primary sqpparts to the tank surface. Welding of primary "

.. 3 b p ' ~ ' q s ~*?:ta;lk


.,,+!* s.
to
. ...n.,&rr.ied will be completed before hydraulic are to be carried out to the satisfaction of the purchaser;.
..... . . . . :. . .
;*.,xetestrng
:. 5- wt. .The number of rflultiple&elded ' 8.3.4.2 ~ro&dur& ksrs, Tests killb e cairied kt &ingt$e,' . ' '

;:i~o~si@&&pport attachrn&ti'ra high,tensile steel proposed procedure to demonstrate to the satisfaction of .'
~~~inimurn ip&fied tensile strength 460 ~ / m r }nshells
~ the purchaser that it is capable of providing 12 times the
should beminimized. I n any case the centre-tocentre strength required as calculated from the wind loading and
.distance between them should not be less than 3 m. any other loading if applicable (see 8.2.2). Such tests
All welds should be ground smooth and magnetic particle should include exposure for not less than 2 months at the
crack detected (see 11.15). These supports should take temperature at which the surface of the tank will reach in
'one of the foliowing forms. service and temperature cycling if appropriate.
' ' (a) Pads (not smaller than 100 mm square) with corners
:rounded to a radius not less than 12 mm, spaced not B.3.4.3 Qualification tests. Only trained personnel are to
%loserthan150 mm to any other weld and welded along be used in making the adhesive joints and each individual
horizontal edges only (see figure 36). to be empfciyed on this work should carry out the qualifi-
cation test within one month of commencement of
Ibl Angles or plates welded on-edge to the tank having a adhesive joint preparation. Six joints will be prepared in
..circumferential
.". length of not less than 100 mm at a the manner proposed for the contract and in the presence
spacing not closer than-150rnm to any other weld, of such persons as may be agreed between the purchaser
-.-weldedalong horizontal edges only (see figure 37). and the tank designer. When tested according to the agreed
Materials for the primary supports are to be selected procedure the strength of these joints should exceed
according to the requirements of this specification. In cases 12 times the minimum required strength.
(a) and (b), secondary supports may be welded or attached
B.3.4.4 Acceptance tests. Records are to be kept to permit
to-the pads, plates or cleats. I n the case of circumferential
'%hgles,the welds should not be closer than"I50 mm to identifications of supports attached with adhesive from -
each separate batch. A proof load will be applied equal to
other horizontal welds. The welding will be carried out by
three times the calculated load. If more than 5 96 of the
approved welders and the welding and nondestructive
batch has failed, the whore batch i s to be removed and
testing proceduresshould be agreed between the tank
replaced.
designer and the purchaser.
Plates welded on-edge or pads will be placed in horizontal 6-35Secondary support members
rows a t a suitable vertical pitch which wilt be, typically,
The design of secondary support members and their attach-
2 m to 3 m. Horizontal support angles, whether primary or
ments to the primary support will be the responsibility of
secondary, should be of a minimum sire 40 mm x 40 mm
the insulation contractor who will obtain the agreement
x 5 mm and of radiai dimension compatible with the
of the tank designer to the design and means of attachment.
insulation system (see 6.8.1.31. The spacing between
It should be made clear in enquiries to the insulation
adjacent members will not be more than + 15 mm from the
contractor whether or not he is to provide the material
specified dimensions with the spacing between the highest
forming the secondary supports for which he is taking the
and lowest members being not more than 2 25 mm from
responsibility. Holes made in any support member welded
the specified dimensions. The outer leg of the member
to the tank should be drilled, not punched, and if self-
should be pointing downwards in order to shed water
tapping screws are used. they should be not larger than
during construction.
6 mm diameter.
6.3.3 External strulural frame
B.3.6 Roof insulation
A structural frame suitably attached to the tank structure
Early consideration of the possible need for roof insulation
at the top and bottom may be used in certain circum-
is important. A roof construction of adequate stiffness i s
stances. This may be in contact with the tank or external
to the insulation. required with the slope everywhere adequate to permit
satisfactory weather protection of the insulation.
8.3.4 Supports attached by adhesive In the case of tanks with an insulated shell, where the tank
roofs are not insulated, catcutations should be carried out
8.3.4.1 General. If an adhesive system is used. the materials
to check the stresses in the roof supporting structure
and procedure are to be such as to withstand the working caused by the difference in temperature of the roof plates
conditions including both mechanical and thermal condi-
and the supporting structure, e.g. when cold rain falls on
tions. The surface of the tank in the vicinity of the fixing
roof plates.
a i ~ dthe corkact surface of the member to be fixed should
Conf inuous
velds. (
WeIded
seam

All dimensions are in millimetres.

Figure 36. Pad supports {see B.3.2ta))


-.
;. ,
<;:5.,,. a
. ' ,,. ,.. ,. . HorizonQl supports should be f i t t e d n o t further than
. '.@:41
..-.,;
. ~ o a l n ' a n'manholes
d '
300 rnm below and 150 mm abow wind girders.
::2
Intermediate stiffeners should also be included in the
. ~ h h f ~ & ~ l a a n d m a n ~arel eflanged,
s they w i l l project
insulation of the shell unless t h e stiffening angles are
,a.ydistance"from t h e tank shell n o t less t h a n the insutation
welded o n the inside o f t h e tank shell.
.th.ickneiiplus 7.5 jimes the bolt length unless otherwise
%gr.&d (see figire 38].<lfa nozzle projects a greater distance
8.4.4 Roof projection
.:,k$& the tank; i t &'to be insulated. (ice-B.6.1). Where
%dja&nt nozzles are close together, f i e y shoukl be offset I f the tank roof is designed t o project beyond the tank
'$9ensure 50 mm minimum clearance between the insulated shell, the projection should b e n o t less than the thickness
.flanges. AH nozzle and manhole connections requiring of the insulation system plus 50 mm. I f the roof weather
insulation are t o be clearly indicated. protection is provided as part of the insulation system,
the overlap shoufd similarly be n o t less then 50 mm beyond
B.4.2 Stairway connections the thickness of the insulation on the tank shell. The over-
hanging part of t h e roof should be cqrnpletely included in
The inner stringer o f double-stringer staircases should be
the insulation. Details o f this are t o be agreed between the
spaced away f r o m the tank a distance sufficient t o ensure
manufacturer and the insulation contractor.
n o t less than 75 m m between it and the outer face of the
insulation system. Stairways w i t h treads wetded directly
8.4.5 Wind stiffening rings
to the shell should n o t be used o n insulated new tanks.
With such stairways on existing tanks, a weather shiefd I n certain circumstances it may be desirable t o locate
should be provided beneath the treads o f dimensions to the wind stiffening rings o n the inside of t h e tank shell
ensure adequate weather protection o f the insulation. (see 6.6.3).

' ~ o t e r ~ r o o f seal

Figure 38. Typical flanged nozzle o r manhole (see BA.1 and B.6.2)
8.4.6 External shell wind girders and bottom-to-shell B.6 lnsutation
insulation
External shell wind girders and bottom-to-shellinsulation B.6.1 General
represent a discontinuity in the envelope of the tank and Insulation practice should be in accordance with RS 5970.
require detailed consideration by the insulation system insulation thickness should be specified by the purchaser or
designer in conjunction with the tank designer to avoid designed to meet the purchaser's heat loss requirements.
the following. Unless the stresses produced are unacceptable, the insula-
(a) Unacceptable thermal gradients in the tank plate tion should terminate approximately 150 mm from the
material due to part exposure. tank base to avoid corrosion and to allow inspection at the
lb) Considerationof potential corrosion due to such areas bottom of the tank (see figure 39). Where the stresses are
forming a lodgement for corrosive fluids. Consideration unacceptable, foamed glass slabs set in bitumen or other
should be given to enveloping all such structural suitable adhesive may be used for insulation of the tank
elements with the insulation, particularly if the storage shell bebw the lowest horizontal support.
temperature is high, but each case is to be taken on its The shell insulation should fit closely under the roof over-
merits. lap and be sealed against ingress of water (see figure 40).
Special care should be taken where roof insulation is to be
carried out to avoid corrosion (see 3.4.4, B.7.3 and 6.8.4).
When the roof is not insulated, a check should be made as
6.5 Corrosion protection to whether the thermal stresses in the roof supporting
structure, caused by the difference in temperature between
T h e presence of insulation prevents inspection of the tank roof plates and supporting structure, are acceptable (see
surface and priming is therefore required before the figure 40).
insulation is applied. The tank shell and welded attach-
ments should be dry, free from grease and loosely adhering 8.6.2 Nozzle connections and manholes
Qarticlesand coated with a suitable primer.3ll to a Where these project u p t o a distance equal to the sum of
specification agreed by the purchaser. I f the roof is to be the insulation thicknesl ptus depth of cladding profile plus
insulated, two coats of primer are recommended. I f shop 1.5 times the bolted length, they are to be insulated with
priming is employed, care should be taken to make good the main shell/roof insulation (see figure 38). Where the
any defects in the priming caused during site fabrication. projection is in excess of the above, they will be insulated
The responsibility for this work is to be clearly determined and finished prior to the application of insulation to the
at the time the tankage contract is let. shell/roof (see figure 41 ).
In the case of in situ spraying or foaming, the paint system
should be such that it is compatible with the foam system Wind stiffening
and unaffected by any foaming reaction or in-service The wind stiffening rings and'their associated supports
condition. Where foam insulation is used with fire retardant should be enclosed by the shell insulation to minimize
formulations, protection against the possibility of halogen- the temperature difference; figure 42 shows a typical
induced accelerated corrosion should be considered. construction local to a wind stiffening ring.
All dimensions ere in millimetrcr

F b r e 40. Typical &rrangsmsntwith.insulation


attached to the rhdl only (see B.61

Dimension is in millimetres.

Figure 39.Typical arrangement showing


termination of insulation adjacent to the
tank bottom (see.8.6)
Tank

Insulation -

Not less than

All dimensions are in rniltirnetres.

Figure 41. Typial fla* nozzle or manhole with additional b r r M insulation (see 8.62)
Wind girder

# 6 mm mild steel pins

welded to wind girder. I


I
Insulation to be retained I
by p l a t e or expanded metal I
I
washer and speedfix I
fastener 1
1
I
I
I
I
I
I

All dimensions are in millimffres.

Figure 42. Typical construction of insulation l a d to wind stiffening ring (see 8.6.31
B.7 Cladding All overlaps in the cladding are to be not less than 100 mm
and be so arranged as to shed water. All joints should
contain a continuous strip of a sealant approved by the
B.7.t General
purchaser and be secured by bulb-typeblind pop-rivetsof a
Cladding i s a feature common to most insulation systems. material compatible with the cladding. The pop-rivets
The effectiveness of the insutation depends particularly on should be a t a maximum pitch of 75 mrn.
the care applied in the design and installation of the
Consideration should be given to properly draining rain-
cladding. The type and quality of cladding should be
water over the edge of the roof so that it does not affect
selected bearing in mind environmental w d i t i o n s on either
the integrity of the insulation system. (See figure 40.)
side.
It i s essential that all cladding be kept dean, free from
grease, free from corrosion and dry on the inner surface B.8 Securing insutation materials
prior to erection and until the installation i s complete and
a l l joints are well sealed. 6.8.1 Slab or block insulation with metal cladding
B.7.2 Side-wail cladding B.8.1 .I Bondedman-made mineral fibre with metal
Care should be taken to prevent direct contact between cladding. The insulation should consist of bonded mineral
stairway supports and cladding. Cut-outs in cladding for wool complying with BS 3958 : Part 5, the bulk density
stairway supports should be sealed with mastic to prevent being not less than 48 kg/m3.
ingress of water. Sealant i s not normally considered The insulation materiai should be supported on the
necessary for vertical or horizontal joints in the cladding. horizontal support members and held in place with t mm
The tank side-wall cladding should be troughed aluminium (minimum) galvanized tie wires for use with galvanized
or galvanized steel sheet attached To the support members. steel cladding and 0.5 mrn (minimum) stainless steel wire
The minimum depth of trough i s to be 25 rn. Corrugated for use with aluminium cladding or plastics-coated steel
sheet having sinusoidal profiles should receive special cladding. The insulation slabs should be fitted tightly
between the horizontabsupport members with all edges
attention in view of the need to avoid the iniress of water
closely butted and verticat joints offset from those in
and to ensure adequate fixing. The minimum thickness of
adjacent courses. The tie wires should be a t a pitch not
sheet should be:
greater than 450 mm with a minimum of two t i e wires
(a) 0.9 mm for aluminium; per insulation slab.
Ib) 0.7 rnm for galvanized or plastics-coatedsteel.
B.8.1.2 Other slab or block insularion with metal cladding.
Galvanized steel sheet will be gade 22, coating type H I Preformed slabs of polyurethaneor palyisocyanurate may
complying with BS 2989. be used on the tank sides as an alternative to mineral wool,
Aluminium sheet should be to BS 1470 - 3103, the method of fixing being similar to that described for
BS 4300/6 - 3105 or BS 1470 - 5251 of grade H4 or mineral wool slabs (see 8.8.1.1) or by adhesives suitable
harder or be of the grades specified in 65 4868. for the operating temperature.
In any horizontal ring, adjacent sheets should have a For certain circumstances foamed glass blocks may be
minimum overlap of one trough profile and be secured required. Where this material is used, the blocks should be
with bulb-type blind pop-rivets a t not greater than 100 mm held in place with 20 rnm x 0.8 mm bands of approved
pitch. The rivets should be of material compatible with the material a t centres not exceeding 450 mm. The bands
cladding and such as to secure the overlap to accommodate should be secured to vertical tie bars fitted to the harizon-
the maximum design windsuction. tal support members at centres not exceeding 12 m.
Each horizontal ring of cladding should overlap the lower Alternatively, adhesives suitable for the operating tern-
horizontal ring by a minirnum of 75 mm and be secured perature may be used,
with bulb-type blind poprivets a t a distance not less than
B.8.13 Horizontal supports. The horizontal supports will .. '..,
. .
25 mm from the edges of the sheets. .
have a radial width adequate for support of the insulation '

Sheets should be secured to support members using fasten- and agreed with the insulation contractor. . ..
ings designed to accommodate the agreed wind loading and
'
tank movements due to thermal expansion and hydro- B.8.2 I n situ faam behind'rnetal dadding . .
"

static pressure. t h e type of foam and its physical and thermal properties ::?:
B.7.3 R w f cladding
are to be agreed between the insulation contractor, the tank F.
designer and the purcharer. The ctadding should comply ; "

Metal cladding for the tank roof should be plain or with 8.7.2 or 8.7.3. The cladding may be supported as :.:!:
embossed and the minirnum thickness should be: recommended in 8.7.2 or may be spaced from'the tank .
{a) 1.2 mrn for aluminium; using foamed blocks. stuck to the sidq-wall, of agreed type :'..'.:*-::
(b) 0.9 mm'for galvanized or plastics-coated steel.
and size and of thickness equal to the minimum insulatioh
. .
. .,. '.
. .
.:%I..,
.. . e,
,

. A _ _ '

. .,
.. .
. . '. ..

. . .
.. > :.-"
...
-.
.. '
-.'- : ..
. . .:. :.
. ..$'..
. .. .
...
-':to efisursa~kquate.'resisk& towind loads. Approved
~Pfi&hirw.pr
*. ".I... &tWpeqns of,weather protection should be
-!.'pro&d.wf\ere
..If' . metar connections for. wa tkways, etc.
;'.*:*n&rate the'imulation. All pipe connections should be when tested to BS 476 :Pah 7. tie 'insulation conkactor
,insulated prior to fitting the cladding. The insulation at is to agree suitable means for weather protecting the foam
'the roof edge is to terminate as shown in figure 40. at the top edge of the tank.
The sequence of the cladding and foaming procedure, The tank should be left uninwlated for a distance of
the method of injecting the foam and the foaming pattern approximately 150 mm from the base.
are to be approved by the tank designer and the purchaser.
8.8.4 Roo&
The insulation contractor wilt define the weather and
substrate temperature limits necessary for satisfactory Where mineral wool and metal cladding form the insulation.
foaming. the mechanical support system should comply with 8-35
and 6.3.6 and be of upstand not less than the thickness of
Means should be agreed between the insulation contractor,
the insulation and not greater than this thickness plus
the tank designer and t h e purchaser for establishing and
5 mm. Metal cladding is to be as described in 8.8.2 and be
checking the satisfactory quality of the foam.
.b..
fixed to the support system to withstand wind loading and
wind induced vibrations, The fastening will be compatible
8.8.3 Sprayed foam with the cladding.
The type of foam and its physical and thermal properties Additional reinforcement of the i n ~ f a t i o n
system may be
should be agreed between the insulation contractor, necessary where access may be required.
'
the tank designer and the purchaser. It may be convenient to apply foam insulation to the roof,
-.The insulation contractor will define theweather and
substrate temperature limits necessary for satisfactory
either sprayed or fo,amed in sku, even ifa mineral wool or
other system is specified for the tank sides.
-
:' spraying.
The thickness of the sprayed foam is not to be less than
the nominai design thickness. The standard of finish of the 6.9 Fire hazard
.sprayed foam wi!l be agreed with the purchaser and the
insulation contractor and samples of foam of the agreed Possible fire hazards exist during construction and
appearance prepared and retained for reference. Means operation when organic plastics foam insulation is used.
should b e agreed between the insulation contractor, Although some materials and formulations are more
. . resistant to fire than others. they are nevertheless still
:the tank designer and the purchaser for establishing and
'checking the satisfactory quality of the foam. combustible and may not necessarily alleviate a fire
hazard.
Appendix C. Standard diameters for
vertical cylindrical tanks
The standard range of diameters is based on the applica- Table 9 gives the capacities for the standard range o f
t i o n of the standard lengths for shell plates given in diameters.
table 8. These standard piate lengths are selected i n accordance
with plate lengths generally used i n Europe.
Table 8. Standard lengths for shetl plates
The heights have not been standardized and table 9 shows
capacities for every metre of tank height.
Tank diamrtar Shell plats length
For a given tank height the manufacturer may choose the
m number of courses and the plate widths t o obtain the most
3 economical solution.
1.5 a
4 t o 10 2.0 n It is strongly recommended that the standard diameter
12.5 t o 30 2.5 r given i n table 9 should be used. The standardization w i l l
reduce the possibility of errors in design, fabrication and
33 t o 114 3.0 r
erection as well as the time required for approval of design
drawings b y purchasers and authorities.

Tnnk diameter (ml -,

3 4 6 8 10 12.5 15 17.5 20 22.5 25 27.5 30 33 36 :39 42

Nominal capacities

m3 m' m3 m3 rn9 m3 m3 m' rn3 m 3 . m' m3 m3 . ma m3 ' rn3


Appendix D. List of symbols
Units Units

A Roof compression area rnm2 Section modulus em3


6, BI ,B2,B3 Weld details - dimensions rnm Wind girder dimension mm
D Tank shell diameter (nominal) m Corrosion allowance mrn
E Young's modulus N/mm2 Diameter o f hole in shell plate mm
Outside diameter of nozzle body mm
F, F I , F2 Weld detaits - dimensions rnm
Outside diameter o f reinforcing
Fa Maximum allowable longitudinal plate o r insert plate mm
compressive stress i n the shell N/mrn2
Diameter o f hole in r o o f plate mm
G I , Gz Lateral force coefficients given
Weld detail - dimensions mm
as a ratio o f the acceleration
of gravity Weld details -dimensions mm
C H Tank shelf height
A

m Height o f each shell course


Height o f roof nozzle
m
rnm
H,, H E ,Hp Shell heights f o r stabiiiry
calculations m Stress concentration factor -
Total height o f tank shell m Design pressure mbar
Maximum filling height o f tank rn Weld dimension rnm
Outside, inside, and mean radii rnm
Site amplification factor -
respectiveiy for branch bodies
K Factor for stability calculations - Weld detaiis - dimensions mm
I Ks- Factor for seismic calculations - Shell plafe thickness mm
L Shell branch length mm
Top course shell p b t e thickness mm
I Overturning moment kN-m Angle stiffener thickness mm
pe ExternaI roof l o a dng k~/m' Tank bottom plate thickness rnm
R Tank shell radius rn
R1 Radius o f curvature of roof m
Thickness of b o t t o m plate under
the shell mm I
1 Re,,R,, Minimum specified yield Bottom reinforcing plate
thickness mn:
strength ~/mm'
Bottom course shelf plate
S
SC
Allowable design stress
Allowable compressive stress
~lrnm'
NfmmZ
thickness
Reinforcing plate thickness
rnm
mm
I
T Total weight o f shell
(F.4.l (c) refers) kg Flange and cover plate thickness m m
Insert plate thickness mm
TI Weight o f effective mass of
tank contents kg Nozzle body thickness rnrn
Roof plate thickness rnm
Tz Weight o f effective mass o f first
mode slashing contents kg Design vacuum mbar .. - .'.,,
'%

Tr Total weight of tank roof kg


Design liquid density drnf _.
, . ..

Maximum longitudinal shell ,


~
.,. .
rs Naturat period o f first mode
sloshing s compression force k ~ / m . . .j'..
. ... ..>.
. .
Tt .. . ~ o t aweight
l o f tank shelf Maximum force o f tank . .'. . . . . :-.. .
. .. .. . . . kg contents . ' . kfq/,,,,,
TT '' ' Totat weight of rank contents . .**..
"
,
. . .
~

. . ... . .
., '

- V , . , Design w i n d speed
kg
m/s
The maximum density
.. . . ..
dm1 . .:.*
,,. - -
' ".
.%

, .. . . Maximum f o r e . : . . . . . . ..
. ... kN/rn .:+..': .:ti.
. + ..
. - . . . . .. . . , . :.,,L,::+
'

..;. . . ..:;
W , . . . . . Effective shell length for -..
- . . . . . Replacement factor " - . . ....... .*..
.,........... . . !.>. ,,
' I

,
..- , :..::,
.I,/
. :. .,'>., : ' cornpressionarea rnrn . ,. :.~., .
." '
: , . ' I
.; +

.
.., .. . .. ." .s .:,'. 'i...Wh Weld detail &mensiun .- . '.- degreei; .- !r :; .:.
. .
': :: -
~ "

Effective m o f length f o r :,,. ~\..;.7 ,


. .. . r ::." .. .. . .:. --. Joint efficieilck factor :. :.ir7'
... .. . . . . . . ._ .. .:-r :' . compression area mm
Slope o f roof
. .
',
,
.: . "
.
'.. . . . dew-.
; . ,. <:.:.
. . . . .:
.;,, :..
..
:.
:.; ',

... Height t o centroid m ...: ,....I"


to centre of gravity
A weld imperfect& d&&br :I, &&'' ,jj:: !,$: :. :i
.. .. . ..,-~,.:-..y.."
',

m . . . ..
. , . .. . . . .. . . . .... 5
' . . .
... . . "::..-
'
. -.-.:. .-is
, . .'..,
'
....
"

<..... . . .
. . .,.... .. . .. . . . -:;.-:; .. .:.:>..
- , .......
"/

.
.
..
. .
. .
. . . ._.__ .
.-.. . ..:. . . . . ,<!;A:>, ..
^ '

,:," 'L . ... . . : . .>, .


.I.. <
;:
,
;<>
.~
.
:.
... ;I ?." .
. .. . * . . . . . .. . .. .',' . . .. " .
<...
. : . . ,;.
. . . .. , . . :. & '

. . . .. . . . . . . . " . .
'"

.. . . .. . . ..,.:.-..! , :, p' . . .& .. ... . .. .


2 7

. . ,,. .. . .. .. -
% . . +. 9".

. , ,
2 ,

:..;;:..:, . .. .. .. .. .. .. . . r , . : . .... _,
. . <. . . '.:. - . . . . . . ., ..-..
. . . . ..... . . . . .._.....
'.>
. -.,
. . . ..\. . '
' X
E.3 Materials -
...
.
c*.,:
: <., .,->,...,. .- ,,.,:, - J -< : ' E.3.1 The purchaser ,should specify the liquid to be . '

:,!'~.(&$,
+ . -+- !ntknd~d'f6r.iimfiiti.n . . . in prarbre tanks (see 2.1 11 contained, indicating any special properties which may .....
.z . . . . -. . ........ .. .
+,.; j;, :;:,.*,. ..:*,
n ,:.:,<.
.*x.
: . ,. , . . . .
.. . . - .. . . . . . . . .
. affec?materiais. . . . .
. . .
>
. . .
. . -. .. . . . . . . . . .
-:-'

..-* . . . . .
Gm&ral . .
. .
.. .. . . E.3.2 Materials should be compatible w i t i t h e pkduct
''

;$?-.%,;
:,\w >;:, ,
.>.:, . .:... ..':.;-:.; .,. . -!,
. :
L,h
.<
. . .: -.;.: ,.?..,:.
. -. ' . ....:
-;
. . . . .
. .
contained. If dissimilar rnater.ials are used, the possibility
. ,<*u ..
, + ~ * j . 1ha ft&in~;&en ditailed'inihis appendix consist of accelerated iorrosion due to inter-reaction should be .

'
"iif
.'.>
'an internatf laating.deck p r d t e ~ e by
d a fixed-type roof considered.
t h ~ever to operate up and down,
..Which, w h i ~ e ' ~ e r m i tthe E.3.3 Sealing materials used to make joints in panels or
;ir,wents the ingress of rainwater, sand or snow. sections should be compatible with the pioduct contained.
'.hating covers are also known as floating screens, floating
- .I..blankets qr.floatim decks, E.3.4 Edge seal material should be highly resistant to
abrasion and tmany aromatic content specified by the
E,1.2 Floating covers in fixed-roof tanks are normally purchaser. It should also be sufficiently flexible to take
used for the following applications; the order i s not an up irregularities in the tank shell.
indicationof their relative importance.
' (a) Reduction of breathing and filling losses.
E.4 Mountings
(b) Reduction of air pollution.
(c) Reductionof ingress of rainwater and sand into E.4.1 Ladders
the product.
Access Ladders from the fixed roof to the floating cover
(dl As an alternative to floating roofs in open-top tanks, are not recommended. Access should be by way of the
in localities where excessive snow may be experienced. shell and cover manholes after the tank has been emptied
(e) To reduce the hazards of static ignition associated and gas-freed (see E.4.4.1 and E.4.51.
-
with highly charged liquid surfaces.
E.4.2 Cover draim
- Primary or ernergEicy drains will not normally be required
-
E.2 Types of cover since the floating cover is not exposed to the elements.
However, condensation can occur in the air space between
E.2.1 The more common'ty~es of cover fall into one of the cover and the fixed roof and this may collect on the
four categories briefly described as follows, cover. Spillage of product on to the cover may also occur,
(a) Rigid preformed polyurethane foam sections and consideration should be given to the provision of a
sandwiched between aluminium foil and fitted together drain where such problems are anticipated. Simple drains
.;. withja simple connecting device. which allow drainage directly into the product may be
..,. . . .+

:(. (b) Glass reinforced plastics panels superimposed on a


possible for some cover designs, but for singledeck
pan-type covers only steel pipe or hose drains, having
flotation structure. The panels are bolted together to
outlets through the shelt, can be considered.
form a continuous covering over the entire tiquid
surface.
E.4.3 Vents
(c) Aluminium sheeting, superimposed an a flotation
structure or aluminium floats for buoyancy. The sheet- E.4.3.1 Floating cover. The purchaser should specify the
ing sections are joined together to form a continuous maximum liquid filling and withdrawal rates. Suitable
covering over the entire tiquid surface. vents or bleeder valves should be provided to prevent
overstressing of the cover deck and seal membrane and
(d) A shallow steel pan designed to float over the entire
should be adequate t o evacuate air and gases from under-
liquid surface of the tank.
neath the cover during initial filling and should also be
E.2.2 The design shoutd not allow the contents to flow adequate to allow air and gas to pass the cover, when the
on to the cover. liquid i s being withdrawn with the cover resting on i t s
support legs.
.E.2.3The cover should be designed to support at least
3 men (300 kg over 3 m2) anywhere over the surface of E.4,3.2 Tank shell, Circulation vents should be provided
the cover in the floating (water testing only j and supported in the tank shell, located clear of the seat when the cover
condition. This recommendation is included for inspection is at i t s highest position. The maximum spacing should
and maintenance purposes. be 10 m, but in no case should there be less than four
equally spaced vents. The total open area.of these vents E.4.7.2 Cover penetrations. Where f ixed-roof support
should beiiot less than 0.06 m2 per metre of tank diamete'r. cotumns, antisotation devices or other appurtenances pass
through the rover. seals should be provided to ensure a,.
E.4.33 Fixed roof. An open vent should be provided at reasonably dose fit, taking into account horizontal and
the highest point of the fixed roof. It should have a vertical movements of the cover.
weather cover and a minimum open area of 0-03m2.
E.4.3.4 Protection. Unless otherwise specified by the E.4.8 Gauging and sampling devices
purchaser, vents should be provided with coarse mesh The fixed roof and the floating cover should each be
tminimum openings 6 mrn x 6 mrn square) to prevent provided with gauging and sampting devices designed to
the ingress of birds or animats: comply with the requirements of the purchaser.

E.4.4 Low level supparts E.4.9 Antistatic cables


E.4.4.7 The cover should be supported a t a low level to be E.4.9.1 All covers should be efectrically conductive.
specified by the purchaser. The manufacturer should ensure For non-metaltic covers, antistatic materials should be used
that all internal appurtenances such as side entry mixers, or, when agreed between the purchaser and the manufac-
piping. inlet and outlet connections, etc. are clear of the turer, metallic strips bonded to the cover may he used as
cover in the low position. Supports fixed to the cover or an alternative.
the tank bottom may be used. The supports, attachments
and tank bottom should be designed to support a live E.4.9.2 When peripheral seals with a high electrical
load of 0.4 kfV/rn2. resistance are'used, e.g. non-metallic seals, flexible multi-
strand antistatic cables should be fitted between the cover
If the load on a support exceeds 2.5 kN, steel pads or and the tank shell to provide an electrical bond.
other means should be used to distribute the load on the
tank bottom. Pads should be continuously welded to the A minimum of two cables should be provided on tanks up
tank battorn to prevent corrosion under the pads. Supports to 20 rn diameter and a minimum of four for larger
fabricated from pipe should be provided with a notch at diameter tanks.
the bottom for drainage.
E.4.10 High-tiquid lwel alarms
E.4.4.2 On the underside of t h e deck ptates of mild steel It is recommended that a high-level alarm be fitted which
covers, where flexure i s anticipated adjacent to cover
will automatically warn the operator of the tank overfilling
supports or other relatively rigid members, full fillet wefds
or the cover fouling an obstruction, e.g. fixed-roof structure.
not less than 50 mm long a t 250 mm centres should be
used on !ap welds within 3W mm of such rigid supports
or members. E.5 Fabrication
E.45 Manhales E.5.1 General L
At l e s t ane manhole, not less than 600 mm i.d., should Good workmanship and finish should be obtained through-
be provided i n the cover for access and ventilation purposes out and all work subjected to the closest inspection by the
when the cover is on i t s supports and the tank is empty. manufacturer, even ifthe purchaser waives any part of
The manhole should be designed to be opened from the his inspection.
underside of the cover. Loose covers may be used but
the height of the manhole neck should be such as to E.5.2 Mild steel wverr
prevent the contents flowing on to the cover.
The fabrication of mild steel covers should comply with the...
. .
.
minimum applicable requirements specified in clauses 13 :'.. :+ .
E.4.6 Centralixing and anti-rotation devices ,*+' ,? .
and 14. .....
Suitable arrangements should be made to maintain the ... ...'
. ..,-.-
'~

: cover in a central position and to prevent its rotation. E.5.3 Non-metalliccomponents ,. I


"
..-- . _. .
d .
,> ,.. The peripheral seal may be considered ta act as a , . .. . . . . . . . .
',.'.C

.s.,.;

. . . . . . . . . . . centralizing device and the rdof support columnsccanbe Components of covers, fabricated from non-metallic :.,.:+ .L
7.
..,
. . . ..
. .
. . . .. . . . . . . . .
used as an anti-rotation device except where only a single materials, should be provided wi.th,edgqwithin toierahies $:-;
,,\?<, .
:
. . . . .. . . . . which will ensure accurate and tight'erection. ' ,I'.'
.
.. . : central column is used. . . . . . . . . . : . . ':. ,...... >*.;:. .,.
. .. . :.:
'
.. . .
.... . ..,:;;..+
I . . . . '. ...'. . .. ". . . . . . . ,. . .. .. . . .
. . . . . . . . . : . . r . , *..:<;,
. . .<. .:. ... . . . .. E.5.4 ~ork;ho~,&einbl~, . : :. . -.:, . . . .. . . .-..<...y;..
.....
., h.,.:&t;,'
E.4.7 Seals . . . . . . .
.
. . ,.',<...
.,.I

. ,
.....
'. .
""';

. 2 .... ::
. . . .
E.4,7.f &riphemi seals, The ctearance between the .perk
!f specified by the purchas* in
t h i order*fhe + s e & $ y , ~ & ~ ~ ? ~
part thereof should be'laidout in'tee works f. o j i~spection:;: ::. .
. . . . . . . . . . ,...I
.. .
"
phqy of the cover .and the tank shell should be fitted with . . . . :. . .."* 5; . ..
- . z i -.:.
. ... ,.a.
'
....a*'. <.. -.:,
~:
. . +. ". , . _ . . ,. -a flexible seal and provide a reasonably close fit to the shefl
~'
*,
....'. .
. . . E . 5 5 Erection marks, i p, i::,,c2,-..~- . ...;;:~..:":..-
padcaging~ . . ~ . h ~ i ..... . .-~.L:.,-
~+ ? ~ +
. '. 3 ,. -. -surface.'Th& inanufacturer shui$d specify.?he .m%'xikum
and a h a * movement Erection marks, packaging @ . ., . .
. shipping.s$$ld ..", m. .*..
p" l -l~
.'.x.~
. $ ..'..:<. :
.... t :in&ird . of which the seal is capable.
, ,
. . . . . .
+

,. -.
. . - .
.....
."+I.' '

. . . ".." . . . . . . _ ,.__.
./*....'.... . .. . .<:;;,.<; " . . . .. , :. . ..<.
, ..'
with this,standard., . . . _ .:... . ... . :-"+.
. ... ..>.&-. $
. . .. :...::,.
..;." ...' .'.::>'
.<. ;

. . :.. .
A
>"
. . ~ ~
. L . ~

. . .: .-.
, , I
*
.
.,.I_
.
. . . . '.. Y:' :,; >.:
. . ... . . ., ,.- .'
. . . . ... ... .. . .. . .. . .. .. . .. . .. . . . .. .. .
i
. ....<>?. -.. . ,-.
..:... . :. .. . . < . . .
:. .,. . .. . .
... , . .. . . . .::
". .. . .
. . . . . . ...\.. .
. . . .
. . .
E.8.3 Use 2 ride. d h t i . . . .s. :':;,
.>..
.:' . . . . . :- .
;.,. : ,
. . . . . . . . . . .. . ... . .. .
: +. .,-
%
.
. ..:
.>. :. ..
. -
Side entry mixers s h w l d be alltiwed to dperitk &ly inh& ' , . . '.

the floating cover is a t a level where the normal function-'


ing of the cover wit1 not be affected.
3' been given i n writing b y the purchaser.

. ,i'
-,.lh .the construction o f the floating wver, every care should Appendix F. Recommendationsfor the
;.be
-. taken to minimize distortion or ladc o f circularity due design of venting systems
:' ' '.tb,,welding or other reasons. The clearance between the
.' ".~puipkry o f the cover and the tank shelt should be uniform
' .:.andcomply w i t h the dimensional requirements specified F.1 General
: :fortheseaI(see'E.4.7.1).
This appendix gives recommendations for the normal
vacuum, normal pressure and emergency venting of fixed-
roof tanks w i t h or without internal floating roofs
constructed t o comply with this British Standard.
. . Ei7.1 Where applicable, before a floating cover is put into Provision is made t o enable evaluation o f venting require
'

operation, it should be carefully tested for liquid tightness. ments arising from the following sources.
'
., . Lap-welded joints i n mitd steel covers may be tested b y the (a) Normal vacuum venting requirements resulting from
- :?&aal#m
-.
. ...'."~.
-, .
box method or by the use o f high penetrating oil. the maximum tate of export of product from the tank. .--
,
:;:;.., ,-
.E.7.2 On completion, the tank should be filled w i t h water,
(b) Normal vacuum venting requirements resulting from
:'. to check that ttie.cover and seals travel freely t o the full the maximum anticipated decrease i n tank surface
:,
. operating height and that the cover is free from leaks. temperature.
9E.7.3 ~ a n h o l e s ' i nthe fixed roof should be kept closed (c) Normal pressure venting requirements resulting from
'during testing in wet weather, since any ingress o f rain- the maximum anticipated rate of import of product t o
:Miter might lead to misleading conclusions o n water- the tank.
xightness. (d) Normal pressure venting requirements resulting from
the maximum anticipated inaease in tank surface
'E.7.4 ;Any damp spot o n the cover should be taken as an temperature.
indication of a possibfe leak.
(e) Emergency pressure venting requirements resulting
Time may be necessary for leaks t o become evident and from the exposure of the tank to an external fire.
checks should therefore be made at frequent intervals,
particularly during the first metre o f fitling. Any additional causes o f normal venting arising from
process considerations should be quantified and added t o
E.7.5 A l l leaks detected during testing should be rectified the venting requirements listed i n (a) to (el.
t o the satisfaction o f the purchaser or his representative.

E.8 Operation F.2 Normal venting


t o the cover
E.8.1 A-
During operation, no access t o the tank and floating cover
The total normal venting has t o cater for at least the sum
should be permitted, and the tank and cover should be
of product movement and rherrnai effects,
'
cleaned and gas-freed before access is permitted for
maintenance purposes. It is recommended that this is
indicated near the tank manholes. F.22 Normal vacuum venting
F.2.2.1 The normal vacuum venting requirement associated
E.8.2 Periodic inspettion
The cover should be inspected for teaks, when i n the t o p
position, from a suitable manhole i n the fixed roof. it is
with the maximum rate of product export should be .
1.O m3 of free air per hour far each 1.0 rn3 /h o f product
export rate for products o f any flash point.
a
. ,.,.., - . ' I ' . . ;i

F.2.2.2 The normal vacuum venting requirement associated F.4 Frangible roof-to-shelljoint
with the maximum anticipated rate of tank surface tem-
perature decrease should be: F.4.1 Tanks without anchorages
(a) d 4000 rn3 capacity: 0.18 m3 of free air per hour For the roof-toshell joint of tanks without anchorages to
for each 1 rn3 of capacity; be considered frangible (see F.3.l) the following should
>
(b) 4000 m3 capacity: 0.61 m3 of free air per hour apply.
for each 1 rn2 of shell and roof area. (a) The mntinuous fillet weld between the roof plates
and the top curb angle should not exceed 5.0 mm.
~2.3
Normal pressure venting (b) The slope of the roof sheeting adjacent to the top
F.23.1 For products with a flash point of 38 O C or above, curb should not exceed 1 in 5.
the normal pressure venting requirernents associated with (c) The effective cross-sectional area of the curb A
the maximum a t e of product import should be 1.07 m3 of (in mm2) as shown in figure 7 shouid not exceed:
free air per hour for ea& 1.0 m3/h of product import rate.
7.07 x lod3T
A =
F.2.32 For products with a flash point below 38 OC, tan 0
the normal pressure venting requirements associated with
where
the maximum rate of product import should be 2.14 rn3 of
free air per hour for each 1.0 m3/h of product import rate. 7 i s the total weight of shell, shell stiffening and
roof framework supported by the shell but
F.2.3.3 For products with a flash point of 38 O C or above, excluding the roof sheeting (in kg);
the normal pressure venting requirements associated with
6 is the slope of roof meridian a t roof-to-shell
the anticipated rate of tank surface temperature increase
connection (in degrees).
should be 60 9S of the values specified in F.2.2.2.
This may result in a curb area less than that required
F.2.3.4 For products with a flash point below 38 "c, by 8.5.6.
the normal pressure venting requirements assocjated with -
the anticipated maximum rate of tank sur.face temperature F A 2 f anks with anchorage
increase should be as recommended in F.2.2.2.
In addition to the recommendationsof F.4.l(a) and {b),
the curb area provided should be checked to ensure failure
at a pressure which will not exceed the permitted design
F.3 Emergency venting stresses in the holding down anchors, tank shell and the
roof alatinp. Curb failure is assumed to occur at a
F.3.1 Tanks with a frangible roof joint compressive stress of 220 PJ/mrnz (i.e. use S, = 220 ~ / r n r n ~
in curb area equation in 8.5.2 to calculate failure pressurel.
No p;ovision need b e made for emergency venting for
fixed-roof tanks which have a shell to roof joint which
is considered frangible according to the provisions of F.4.

F.3.2 Tanks without a frangible roof joint


F.5 Means 05 venting
F.3.2.1 Without additional protection. For tanks not F.5.1 Normal venting
pravided with additional protection as indicated in F.3.2.2,
the total rate of emergency venting should be as given in F-5-1.1 Normalventing should be by a
table 10. Full credit should be taken for the venting pressure relief valve, a vacuum relief valve. a pressure
capacity provided for normal venting since thermal effects vacuum (PV) valve or an open vent with or without a . .
flame-arresting device complying with F.5.1.2 to F.5.1.7. .
can be disregardedduring a fire as it can be asumed that '

no product movement will take place at that time. F.5.f .2 Relief valves equipped with a weight and lever are .. . :

:. F.3.2.2 Tanks with additiomlprotection. The total rate of remrnrnended- .. .

- . .
,, . emergency venting shouId be multiplied the appropriate F.5.13 PV valves are recommended for use on atmos- . .. . , , .'
. .
.'. factor when the following forms of protection are provided. merit storage tanks in a pro&ct'with a flash point ,.
..
. ..*.,
..
. .
>
. .(a) A factor of 0.5 when drainage away from the tank
is provided.
below 38 O C is stored and for use on tanks containing a .
product that i s heated above i t s flash p0int.A fiame ... ' I
.,. ':,:,1.

..-..I
... . .....
. ... '. . .. [ b ) 'factor
~ of 7.5/tl, but limited toa value arrester is not generalty considered nwessary for use in :<: .;.; .. I , '

.. . .., _.

conjunction with a PV valve because, even at low settings, .' j l . .~


.. ... . ..1._. .<.I"... . 'of 0.075 (where t l is the thickness of the insulation
i:
. .
. insulation
(in mm)) when e x t e r ~shell
l is provided mat the Ws efflux velocil~exceeds the'fiame &eds of most . . - I ' ' :
' .
.. ...*. ::.. : . is considered noneornbustible, does not decompose at gases. . . . ..
. .. .
. . . ,..: .: . .
. .
. . . ., ' _ , iamperaturr.below SO0 OC and is resistant to damage F-5.1.4 Opsn vens with s flaw-arrening d e v h h a y be . .::.
.. .-.
. .
. ..
. . .
':,
;. ,; from fire water impingement. used in place of PV valves on tanks in which a'product with .I.:..
&.
:
' :
. " ' -.. : .
: .fpe,:p&vision of any water cooling system will not result a flash point below 38 OC is stored and on tanksmktaining . '.':
... .....
... .in a reduction in the venting requirements. a product that is heated above i t s f&h +ciint. 1': :-I .. . . . * ,.-..
' ,
. . . . . . .
. . :I._ . . . .
. . .. ..... . . .. . . . .
.... . ..
. % . . I . I

81
. :. "
tc>provide. venting F.5.3 Vent discharge
, :capacity
. for tanks iq which the product w i t h a fiash point . For tanks Located inside a building, a discharge f r o m t h e
.:-..of
. 38 *Cor'above is stared, for heated tanks i n which the vents should be to the outside o f the building. A weak
,' Orodqct's storaq! temperature is below the product's flash roof-to-shell connection should not be used as a means
..'point,
-. for ianks'with,a cahcity o f Iess than 10 m3 used of emergency venting tanks inside a building.
. ,.for storing any product, and for tanks w i t h a -pacity of For valves w i t h connected pipework o n the inlet o r
::.lgss
:. . than 500.r$. us.e,for
. ,storing crude oil.
<.' . > ... 1 discharge side, suitable allowance should be made in the
'1. .F6.t.6 lij the',&& af v i k o u s &xlucts, such as cutback vent sizing for pressure drops occurring in this pipework.
and penetration grade asphalts, where the danger o f tank Flame arresters w i l l similarly reduce the capacity o f the
collapse resulting from sticking pallets and frame arrester valves o r openings.
elements fs greater than the possibility of flame transrnis-
sion i n t o the tank, open vents may be used as an exception
. t o the recommendations o f F.5.12 to F.5.1.4.
.:.Where flame arresters are used, it i s good practice t o stock ( Tabk 10. ~e&rements for emergency venting I
':.spare element assemblies so that they can be removed and
Wettsd arm Venting requirements
'replaced o n a regular basis depending o n local conditions ' (standid m3 of free air per hour?
.:and in'this way clean elements would always be available
land maintenance time on the tank roof kept to:a minimum. m2 m3/h . '

.<Where regular maintenance cannot be guaranteed, the use


o f flame arresters should be avoided.

.: F.52 Emergency venting


.: Emergency venting may be accomplished by the use of
,' the following.
. (a) Larger or additional valves or open vents as limited
, b y F.5.1.4and F.5.1.5.
(b) A gauge hatch that permits the cover t o lift under 1-',173W , ,

. abnormal internal pressure. '


I$
19 000
(c)
,

-A minhdle cover that lifts when exposed t o 250 20 400


300 21 600
atjnormal internal pressure.
'. 2, {d) A connection between the roof and the shell that NOTE 1. No increase in venting requirement i s

-
required for tank with wetted area > 300 m a .
; is considered frangible i n accordance w i t h F.4. . . I
(e)LQther forms of construction demonstrably
comparable for the purpose of pressure relief.
NOTE 2.The wetted area is the toral surface area
of the shell within 9 m above local grade level.
1
Appendix G. Seismic provisions for storage T2 is the weight of effective mass of the tank contents
.tanks which move in the first sloshing mode and which is
determined in accordance with G.1.2.t (in kg);
NOTE. This appendix gives techmendations for the se$mic design T, is the totat weight of tank roof (fixed or floating)
of storage tanks and is bawd on the reauirements of appendix E of ptus portiqn of snW load, if any, as specified by
APt 656 The zone coefficients used i n - ~650 ~ lhave been modified the purchaser (in kg);
t o lateral force coefficients expressed as a ratio o f the acixleration
due t o gravity. This allows application of these calculations t o T, is the total weight of tank shell (in kg);
geog@*cal locations outside the USA. XI i s the height from bottom of tank shell to centroid
It is recognized that other pFMedures or additional requirements of lateral seisrhic force applied to TI and which is
may be called for by the purdfiaser or the local authorities i n
highly active seismic areas. In this case, specialized local knowledge
determined in accordance with 6.1.2.2 (in m);
should be used in agreement between the purchaser, the local Xz is the height from bottom of tank shell to centroid
authority and the manufacturer which takes into account local of lateral seismic force applied to T, and which i s
requirements, the necessary integrity, soil conditions, etc.
determined in accordance with 6.1.2.2 (in m);
Consideration s h w l d be given t o design for an operating basis
earthmake (OBE) condition and a safe shutdown earthauake ' (SSE) X, is the height from bottom of tank shefl to centre
comli;ion. when establishing site safety requirements. of gravity of shell (in ml.
The following definitions apply.
Operating Basis Earthquake IOBE). The structure should resist 6.1.2 Effective mass of tank contents
this earthquake without any damage. It is suggested t o consider
t h e seismic loads with a 10 % probability of being exceeded
6.1.2.1 The effective mass TI and the effective mass T2
during the structure's lifetime. Allowable stresses should not (as defined in G.1.1). may be determined by multiplying
beexceeded. TT by the ratios TiITr and T2/TT respectively, obtained
Safe Shutdown Earthquake (SSEI. The structure may be from figure 43 for the ratio D/&, where:
damaged by this earthquake, but it s h w l d not collapse nor
should it impose serious consequential hazards. It is suggested
TT is the total weight'of tank contents (based on a
toy.= the seismic loads with a I% probability of being exceeded specific gravity notl-s than 1.0) (in kg);
during the lifetime of the structures. Under this load the D is the diameter of tank (in m);
ultimate strength should not be exceeded.
HT is the maximum filling height of tank from bottom
of shell to top of curb angle or overftow which
limits filling height (in m).
G.? Design loading
6.1.2.2 The heights from the bottom of the tank shell to
0.1.1 Overturning moment the centroids of the laterat seismic forces applied to T I ,
The overturning moment due to seismic forces applied to T z ,X1 and X2 may be determined by multiplying HT by
the bottom of the tank shell should be calculated as the ratios X 1/HT and X2/HT,respectively, obtained from
follows: figure 44 for the ratio of D/HT.

GI( r t X s + T ~ H +
L TIXI)+'G~ TZx2 6.723 The curves in figures 43 and 44 are based on a
M= modificationof the equations presented in ERDA Technical
102 Information Document 7024.
where
G1 is the lateral force coefficient given as a ratio of the 6-13 Lateral force coefficients
acceleration due to gravity (see G.1.3.1);
6.1.3.1 The lateral force coefficient GI is to be specified
G2 is the lateral f o r e coefficient given as a ratio of the by the purch&r on the b&is of seismology records . .;,
.
acceleration due t o gravity and determined in available for the proposed tank site and should be given as ::.
accordance witb G.1.3.2; a ratio of the acceleration due to gravity.
. . . . HL 'is the total height of tank shell (in m); For a storage tank constructed for service in the UK it is ,'

-- .M is the overturiing moment applied to bottom of recommended that the lateral force " coefficient
. GIbe taken .'
:
. . . . iank shell {in kN-in); . 1 . : . . as no greater than Q.045. :......;
.- ..
. >.... . . .. , ",.
..., ,
. - 3

.. :Tx' is the weight of effective mass of tank contents . ,- ." .


.
. .. .
. l.-
.I.

moves in'unisonwith tank shell and which . . . . . .. .*


. .: . ..which
. .. -K. . . .. :: :. . =. .
. " .. .:
: .' . is deterrnined in accordance with G.l.2.1 (in kg); .......... ....
,."
. .. .... .... . : ., .
"
. . . . . .
. . . . .. ":,'. +.' . '.." -'
. .. . . . . . . . . .......... . * .. . . .. . . . ", ,.
.
'"

. . ^ . : , .:.... ? ;:. ;., .... ,, , .:;


. . . . . . . . . . .I..,- .... ' . + d -
" . . , .... *. . .: ,,;.'a .>.,'*
. .
. . ... ... ... . . . . . .. . . -
' '

. . , . .
. . . . . ., ..:.$, .,,*..... .
. .-'. . -:,., :.2:
<: :-.
,.:'
i.

T'.'",'
.'.
I.:

. .
,

. .
. .
. ,... -- . .",;,.. .< ,..,*. ..-a*.:.:. .-.-1
. .." .
:b,?.
'

. . . .... . "
.. .. ." . >.; " ?.<:
>
L 7;>: ; : '; ,:.. .:is: . >
+............. >'+
.. :-A.... ,(,<<&, ;,;:. :.q.:q<
..4&..
....-".. .., .$.-...'. ............
. . . . .. ;&.$= :; *
.
.%- ........ .:.-:
i.'. * -
... .. . .. :,. - . >.">,.
' " ' . I "

,<... ,
.,..
. :.:::::.; ,. ; -..,. <. ..;.+
"
.. . ..
. . .
". - . .
.
L....
.....
-J7 .... "
.=., ....... '..,. . ..
. . .. , . , . . . : , : ; :
..Ic.,

. , _ ,. . . , . , .".. . _- .
.,. .-, . ,. * ." . .-, . ~ - ' . > - :'
+_ " I,'

.-.,. .. . . .,
'I
'.
. . .. .. .. . , , ..., ..,;:.:' : .:. 'l:i:,.:,: . . .-,
>
... ~ . . . . . . . . .
I
. Figure 43. Effective masses

D/HT
Figure 44. Centroids of seismic forcer
6.132 The laterai force coefficient G2 is to be determined
as a function of G1of the natural period of the first mode Table I Soil profile coeffiiiertt
I.
sloshing T, and the soil conditions at the tank site (unless
otherwise determind by the method given in 6.1.3.3) as Site amplification faaor Soil W Itypr
~
follows. l L F - F L 7
(a) When T, is less than 4.5
125G1 J
G2 =
Ts *Soil profile type A i s either of two profiles as follows.
( 6 )When T, is greater than 4.5 (al Rock of any characteristic, either shale-like or
5.625GJ crystalline in nature. Such material may be characterized
G2 = by a shear wave velocity greater than 760 m per second,
T
,
' or
where (61 Stiff soil conditions where the soil depth is less than
J is the site amplification factor from table 11; 60 rn and the sail types overlying rock are stable deposits
of sands. gravels, or stiff clays.
Ts is the natural period in seconds of first mode stoshing. %oil profile rype B is a profile with deep cohesionless w
T, may be determined from the following expression: stiff clay conditions, including sites where the soil depth
exceeds 60 m and the soil types overlying rock are stable
f-, = 1.8 K, D''' deposits of sands, gravels, or stiff clays.
Ks is a factor obtained from f$ure 45 for the ratio D/HT. f Soil profile type C is a profile with saft-to-medium-stiff
clays and sands, characterized by 10 m or more of soft-to-
6.1.3.3 As an alternative to the method described medium-stiff clay with or without intervening layers of
in 6.1.3.1 and 6.1.3.2 and by agreement between purchaser sand or o t h h cohesionless soils.
and manufacturer, G Iand G2 may be determined from NOTE. I n locations where the sail profile type is not known
response spectra established for the specific site of the i n sufficient detail to determine the soil profile type. soil
tank aad which may atso take into account the dynamic profile C should be assumed._
characteristics of the tank. The spectrum for GIshould be
established for a damping coefficient of 2 % of critical.
T h e spectrum for G2 should correspond to the spectrum
for GIexcept modified for a damping coefficient of
0.5 X of critical.
NOTE. I n no case should the values of GI and G2 be less than
those obtained from 0.13.1 and 0.13.2.

.... .
, ..
.. . . . . .
.. , . . . -
, ,... _
, . .. .
..I.
a
:
"
....
. . . . . .: :.'.....
._.. _.. .., - . .IFigure 45. Factor K,
' , ?,.. "'
..a,..' I) ,
...? + .,. ,

$%+pendent
+<A .' o h i h e w i d t h of t h e b a t t o m plate under t h e
:+*ti
,.. which lifts o f f the foundation arid may be determined
.:has'
..,. foliws:,
- .<
i.:;;;'..wL.'=&I rba/,, &b Ws HT M
(b' when is greater than 0.785 b u t
..,except.
. .. -
". .
t h a t wl should n o t exceed 0 2 w,ffTD; and where D' (wL +- w,)
;P
.--;.'
&x.. wig. is the maximum force of tank wntents which less than or equal t o 1.5, wb may be computed from
+
,?
w :.
- 5 may be Mitixed to resist the shell overturning the value o f the parameter
Wb * WL
obtained from
y*
..
I:" ..
... . ." moment (in kN per metre o f shell circumference); wt ' WL
.$'. .. .. tba ii the ttjicknek of b o t t o m plate under the shall figure 46
. . ..
. ". -.. (in mm,; where
.:.'. . . R;lb is the minimum specified yield strength o f b o t t o m
' wb is the maximum tongitudinat shell compression
) . . piate under the shell (in ~ / m m '1; force ( i n kN per metre of shell circumference);
.a .
.I . , w, is the maximum density o f the contained liquid w, is the maximum force exerted by tank shell and
.
:. . . under storage conditions, to be n o t less than 1.0 portion o f roof supported by shell (in kN per metre
".", -
7s A

?.+
<* :
.. . (in g/ml). of shelt circumferenoe).
M
% .

+*~..'
G.3.12 When is great& than l .$-or when
D, (lv. wLl
'$)m,fhi&ness of the b o t t o m plate under the shell, tba,
+

w,/t,,exceeds Fa (,when calculated using the method


?'should n o t exceed the thickness of the b o t t o m shell course.
described i n E3.3). . . the tank is structurally unstable.
Where the bottom plate under t h e shell is thicker than the
In such cases, it is necessary t o make the tank stable by
remainder of the bottom, the width o f the thicker plate
one o f t h e following methods:
.under the shell in metres, measured radially inward from
the shell. should be equal t o or greater than: (a) increase the thickness o f the bottom plate under the
shell, t b , to increase wL, providing that t h e limitations
o f G.2.1 and 6.2.2 are n o t exceeded;
(b) increase shell thickness, t,,;
NOTE. A narrower width of annular plate than that required by
'
the a k v e expresrion is acceptable provided the resultant reduced
(c) change the proportions o f the tank t o increase the
w, mistance loading is adopted in the shell compression compu- diameter and reduce the height;
I ta&s of 0.3. (d) anchor t h e tank in accordance with 6.4.

G.32 Anchored tanks


The maximum longitudinal compression force at the
bottom of the shelt, wb (in kN/m), may be determined
as follows:
1373M
w#.,= w* + -
D'
Figure 46.Compressive force wb

0.3.3 Maximum allowable shell wmpression Fa is the maximum allowable longitudinal wrnpressive :
The maximum longitudinal compressive stress in the shell, stress in the shell (in N/mmZ1. The formulae in
wbltb, (in N/mrn2 I, should not exceed t h e maximum items (a) and (b)for F, take into acmunt t h e effect
allowable stress, Fa ( i n N/rnm2 1, determined as foltows: of internal presswe due to the liquid contents;
wr HT D' R,, is t h e minimum specified yield strength of t h e . .:... .
(a) when the value of is greater than 44 bottom shell course (in Nlmtn2 I. . ... . ....
.. ~ .
tbr
. ,.I
.
....
In no case is the value of Fa to exceed 0,5R,,. ._ ....
. I .

., ~

6.3.4 Upper h t i cwrrer


... :.
If the thickness of the lo- shell course calculated'to ' . .' ,;.+
,.I "'

wsHTD
' resist the seismic overturning mo
(b) when the value of - is less than 44
thickness required for hydrostatic
corrosion allowance, then unless a special analysis is rhade...
to determine the seismic ow
ponding stresses at the bottom
where the calculated thickness of each
hydrostatic p r k s u r e should be in
tb, is the thickness, excluding corrosion allowance, proportion.
'of the trottom sheH course (in mm); , , . .
,.
should be designed for a load equal @ the mi$dd , .
specified yield strength of the anchorage.mate'rial'multi-',
plied by the as-built minimum cross-sectional area of .
the an&or. For the attachment of the anchorage to the
tank shell and the embedment of the anchor into the .
foundation the design stress should not exceed 1-33times
6.4.2 ~ e r ' i ; ranchorags
f that given in 7.3.1.
v

'0.4.2.1 If an anchored tank is not properly designed i t s


.shell can be susceptible to tearing. Care should be taken
to emure that the strength of anchorage attachments to 6.5 Piping
the tank shell is greater than the specified minimum yield
strength of the anchors so that the anchors yield before
Suitable flexibility should be provided in the vertical
. the attachments fail. Experience has shown that properly direction for all piping anached to the shell or bottom of
designed anchored tanks retain greater reserves of strength the tank. On unanchored tanks subject to bottom uplift,
with respect to seismic overload than do unanchored piping connected to the bottom should be free to lift with
tanks. the bottom or be located so that the distance measured
In addition to the requirements of 10.1 to 10.5, from the shell to the edge of the cdnnecting reinforcement
- the recommen&ions given in G.4.2.2 to 6.4.2.4 should is the width of the bottom plate (as #culated by 6 2 2 ) -
. . .
t be followed plus 0.3 m. ..
Publications referred to
Methods for notched bar tests
Part 2 The Charpy V-notch impact test
Specification for test sieves
The use of structural steel i n building
Fire tests on building materials and structures
Part 7 Surface spread o f flame teas for materials
Aggregates for natural sources for concrete (including granolithid
Part 2 Metric units
-
Wrought aluminium and aluminium alloys for general engineering purposes plate, sheet and strip
Specification for steel forgings (including semi-finirhed' forged products) for pressure purposes
Carbon and altoy Reel bars for batting material
Steel pipe flanges and flangkl fittings (normal sizes X i n to 24 in1
Part 2 Metric dimensions
Radiographic examination of fusion welded butt joints i n steel
Part IMethods for steel 2 mm up to and including 50 mm thick
Specification for continuously hot-dip zin: coated and imn-zinc alloy coated steel: wide strip, sheetlplate and
slit wide strip
Specification for steel pipes and tubes for pressure purposes: carbon and carbon manganese steel with specified elevated
temperature properties
Specification for sttel pipes and tubes for pressure purposes: carbon and carban alloy steel with specified low
temperature pmpert ies
Recommendations for the installation o f automatic liquid level and temperature measuring instruments o n storage tanks
Thermal insulating materials
Pam 5 Banded mineral waol slabs (for use a t temperatures above 50°C1
Specification far image quality indicators for industrial radiography (induding guidance on their use)
Steel tadders f o r permanent access
3105 Sheet and strip
Specificatian for weldable structural steels
Vertical cylindrical welded steel storage tanks for low-temperature service. Singkcwall tanks for temperatures
down t o -50 "C
Profiled aluminium sheet for building
Approved testing of welding procedures
Part t Fusion welding of steels
Approval testing of welders working t o approved welding procedures
Part 1 Fusion welding of steel
Coated macadurn for roads and other paved areas
Specification far arc welding of carbon manganese Reels
Specification for vertical cylindrical welded storage tanks for Iow-temperatures down t o -196 O C
Code o f practice for site investigatians
Code of practice for thennd insulation o f p i p e w r k and equipment (in the temperature range - 1 0 0 ' ~t o +87 O C )
Code of basic data for the design o f buildings
Chgwr V Loading
Part 2 Wind loads
The structural use of concrete
Stmctural use of reinforced concrete in buildings
Foundations
Structural steels
ASTM A 1 S Forgings, carbon steet, for piping components
ASTM A106 Seamless carbon steel pipe for high temperature service
ASTM A524 Seamless c a r b n steet pips for atmospheric and low temperatures
API Standard 5L Specification for line pipe
Mild steel for pressure equipment sub-zem temperatures. Britisb Welding Journal, March t964*
Rose R.T. Rim reinforcement of manholes. British WeIding Journal. October 1961.
Nudear reactors and earthquakes, Ttxhn~WJnfomxetimDowment 7024 prepared by Lockhead Aircraft Corporation and Holmes
I and Narver Inc. for the US Atomic Energy Commission, August 1963.

*Referred to i n foreword only.

. ...
. -

BS 2654 : 1989; -..?%

-~<,
A' 3
+-
This British Standard, having been prepared under the direction Copyright. Users of British Standards are reminded that copyright
of the Pmsure Vessels Standards Policy Committee. was published subsists in all BSI publications. No part of this publication may be
under the authority of the Board of BSI and comes into effect on reproduced i n any form without the prior permission in writing of
29 September 1989 BSI. This does not preclude the free use, in the course of
O British Standards Institution, 1989 implementing the standard, of necessary details such as syrnboIs and
size, type or grade designations. Enquiries should be addressed t o
Part 1 First published February 1956 the Pubfications Manager, BSI. Linford Wood. Miltor: Keynes
First revision September 1965 MU14 6LE. The number for telephone enquiries is 0908 220022
Part 2 First published December 1961 and for telex 825777.
Part 3 First published September 1968
Contract requirements. A British Standard does not purport to
First revision, combined as BS 2654, February 1973 include all the necessary provisions of a contract. Users of British
Second revision December 1984 Standards are responsible for their correct application.
New edition September 1989
ISBN 0 580 17661 4 Revision of British Standards. British Standards are revised. when
The following BSI references relate t o the w w k on this standard: necessary, by the issue either of amendments or of revised editions.
Committee reference PVEIIS Draft for comment 87177053 DC It is important that ufsm of British Standards should ascertain t h a t
they are in p-ion of the latest amendments or d i t i o n r
Automatic updating ssrvice. BSI provides an economic, indiv~dual
British Standards Institution. Incorporated by Royal Charter. BSI i s and automatic standards updating service called PLUS. Detalls are
the independent nationai body for the preparation of British available from BSI Enquiry Section at Milton Keynes, telephone
Standards. It is the UK member of the International Organization 0908 221 166. telex 825777.
for Standardization and U K sponsor of the British National
Committee of the International Etectrotechnical Commission. Information on all BSI publications is in the BSI Catalogu~.
I n addition t o the preparation and promulgation of standards, BSI supplemented each month by BSI News whlch i s available t o
offers specialist services including the provision of information subscribing members of BSI and gives details of new publrcafions,
through the BSI Library and Standardline Database; Technical Help revtsions, amendments and withdrawn standards. Any person who.
t o Exporrers; and other services. Advice can be obtained fromthe when making use of a British Standard, encounters an inaccuracy or
Enquiry Section. BSI. Milton Keynes MK14 6LE. telephone ambiguity. is requested t o notify BSI without detay i n order that
0908 221166, telex 825777. the matter may b e investigated and appropriare action taken.

Cgmmit.tea responsible for this British Standard


The preparation of this British Standad was entrusted by the British Steel Industry
Pressure Vessels Standards Policy Committee (PVCI-) t o Technical Energy lndusries Council
Committee PVEIIS, upon which the following bodies were Engineering Equipment and Materials Users' Association
represented: Institution of Gas Engineers
Associated Offices Technical Committee Institution of Mmhanical Engineers
British Chemiml Engineering Contractors' Association Process Plant Association
British Compressed Gases Association Welding fnstitute
British Gas pic

Amendments issued since publication

Amd. No. I Date of issue I Text affected

British Standards Institution - 2 Park Street London W I A 28s . Telephone 01-629 9000 Telex 266933 .@:

You might also like