Professional Documents
Culture Documents
Winter internship
(3rd SEMESTER)
This is to certify that the report entitled is an original piece of work by RAJU SINGHA student of
Bongaigaon Polytechnic 3rd semester and is in with the internship training.
This report is submitted towards the partial fulfillment of the condition laid down for AEGCL and
embodies the work done by under my guidance and supervision.
I would like to express my deep gratitude to Mr. BIJOY BARMAN (AGM, T&C Division), Mr.
RUPJYOTI SARMA (AGM, Dhaligaon GSS), Mr. BIBEK BARUTI(AM), Mr. TAPAN SARKAR(SDO)
for their active support and continuous guidance without which it would not have been done.
They are generous enough to take time from their regular work to lend a helping hand whenever needed
to complete the project.
I would also like to mention the generous guidance of Mr. ANISH BISWAS (AM), Mr. SHUBHO
CHATTERJEE (JM) whose guidance helped e settle down in the organization and complete the project in
relatively short fame of 12 days, from 20th of January to 1st of February 2020.
DECLARATION
I RAJU SINGHA student of Bongaigaon Polytechnic 3rd semester hereby submit the report on internship
training 2020.
This report consists of the original work done by me under the able guidance and supervision of my in
charge Mr. ANISH BISWAS (AM), Mr. SHUBHO CHATTERJEE (JM)
Date
SIGNATURE OF STUDENT
ABSTRACT
During this internship training we have learned about how the transformers actually works, from where
do the supply come from, the generating substation and how it gets distributed among the consumers. The
transformers works on mutual induction. When the current works on mutual induction. When the current
passes through the primary coil, a flux is produced which when passes through the secondary, an emf is
induced due to which we get current through the secondary coil.
The current generated at the generating station has very low value of voltage which is about 11KV-33KV.
So, the voltage is stepped up to high voltage (EHV) i.e. 132KV-220KV and higher for transmission. Then
after the grid substation the voltage is stepped down to 33KV and lower values for distribution system.
CONTENTS
1. INTRODUCTION
2. 132 KV DHALIGAON GRID SUB-STATION, AEGCL
3. SINGLE LINE DIAGRAM OF 132 KV DHALIGAON GRID SUB-STATION,
AEGCL
4. DIFFERENT EQUIPMENTS IN THE SUBSTATION
LIGHTNING ARRESTER
CAPACITIVE VOLTAGE TRANSFORMER
WAVE TRAPS
CURRENT TRANSFORMER
ISOLATOR
BUS ISOLATOR
LINE ISOLATOR
TRANSFER BUS ISOLATOR
EARTH SWITCH
SF6 CIRCUIT BREAKER
POTENTIAL TRANSFORMER
POWER TRANSFROMER
PARTS OF TRANSFORMER
SCADA
RELAY
5. BATTERY BANK
6. MEGGER (TESTING INSTRUMENT)
7. CONCLUSION
Introduction
Assam Electricity Grid Corporation Limited, a vibrant growth oriented public sector Company registered
under “company act, 1956”. It was formed out restructured Assam state electricity board in 2003 and was
notified as the State Transmission Utility (STU). Its core business is to efficiently transport electric power
from electrical power bulk heads to the distribution company networks in Assam.
Assam Grid Electricity Corporation Limited inherited 3862 circuit km of EHV lines above 66 KV voltage
class and 38 numbers of EHV substation having a total transformation capacity of 1636.50 MVA at its
birth in 2003. Since its inception, it has added 1584 circuit km of EHV lines and has added 4125 MVA
transformation capacity by a way of commissioning 17 new EHV substations and augmenting existing
substation. It has also added Reactive power compensation at 33 KV bus to the tune of 285 MVAR.
Assam Electricity Grid Corporation Limited had also added one 400/200 KV grid substation and one
220/33 KV GIS substation during the preceding years.
As on 21-07-18, AEGCL has 65 nos. of EHV grid substations (400KV-1no, 220KV-11nos and 132KV-
10nos.)
Assam Electricity Grid Corporation Limited is playing a strategic role as it is the largest “STU” in the NE
region. It also understands its responsibility towards the entire North East India and is always extending a
helping hand by transporting a fair share of power to the other states of the region.
Assam Electricity Grid Corporation Limited has consistency maintained the transmission system
availability bottlenecks get eradicated. It pledges to deliver unrelenting brilliance in performance, deliver
power efficiently but economically show high safety standards and is committed to respect environmental
and heritage issues.
132 KV DHALIGAON GRID SUB-STATION, AEGCL
132 KV dhaligaon grid sub-station, AEGCL gives power supply to almost half part of Assam state. The
Sub-station gets the 132 KV line from BTPS Line#1 and BTPS Line#2. It is distributed in terms of 33 KV
and 132 KV. The 33 KV line is supplied to Birjhora, Kajolgaon, Shyamthibari, Bijni, Bypass FDR, Spare
FDR, Chapaguri, IOCL (BGR), Dolaigaon, Railway. And the 132 KV line is supplied to Barnagar,
Gossaigaon, BGR (IOCL), Nalbari (Rangia), APM (Jhogighopa). Many new advanced technologies have
been installed in this sub-station. Relays, SCADA etc. are some of the equipment installed currently. It
consists of a master control station with one or more PC-based human machine interface (HIMIs). Total
power import is -47.19 MW and total power export is 35.42 MW. It has two transformer of rating 50
MVA and 25 MVA.
SINGLE LINE DIAGRAM OF 132 KV DHALIGAON GRID SUB-STATION, AEGCL
DIFFERENT EQUIPMENTS IN THE SUBSTATION
LIGHTNING ARRESTER
This device is used for the protection of the equipment
at the substation. In other words, Lightning Arrester
diverts the abnormal high voltage to the ground
without affecting the continuity of supply. This
device itself take damage for the protection of the
other equipment. The typical lightning arrester has a
high-voltage terminal and a ground terminal. When a
lightning surge (or switching surge, which is very
similar) travels along the power line to the arrester, the
current from the surge is diverted through the arrester,
in most cases to earth.
In its most basic form, the device consists of three parts: two capacitors across which the transmission line
signal is split, an inductive element to tune the device to the line frequency, and a voltage transformer to
isolate and further step down the voltage for metering devices or protective relay.
The tuning of the divider to the line frequency makes the overall division ratio less sensitive to changes in
the burden of the connected metering or protection devices. The device has at least four terminals: a
terminal for connection to the high voltage signal, a ground terminal, and two secondary terminals which
connect to the instrumentation or protective relay.
Capacitor C1 is often constructed as a stack of smaller capacitors connected in series. This provides a
large voltage drop across C1 and a relatively small voltage drop across C2. As the majority of the voltage
drop is on C1, this reduces the required insulation level of the voltage transformer. This makes CVTs
more economical than the wound voltage transformers under high voltage (over 100 kV), as the latter one
requires more winding and materials
WAVE TRAPS
Wave trap is a parallel tuned inductor - capacitor tank circuit made to be resonant at desired
communication frequency. It reduces corona losses in transmission lines in power system.
Wave trap is installed in the substation for trapping the high frequency communication signal
sent on the line from remote substation and diverting them to the telecom panel in substation
control room. These high frequency signal should not be coming on the buses as these may
damage the equipment.
A wave trap is a device that allow only a particular frequency to pass through it that it filters
the signals coming on to it. So a wave trap is connected between buses and the transmission
line which allow only 50 Hz signal to pass through it.
This is relevant in power carrier communication (PLCC) system for communication among
various substation without dependence on telecom company network. The signals are primarily
teleportation signal and in addition, voice and data communication signal.
CURRENT TRANSFORMER
Current transformers typically consist of a silicon steel ring core wound with many turns of copper wire
as shown in the illustration to the right. The conductor carrying the primary current is passed through the
ring. The CT's primary, therefore, consists of a single 'turn'. The primary 'winding' may be a permanent
part of the current transformer, i.e. a heavy copper bar to carry current through the core. Window-type
current transformers are also common, which can have circuit cables run through the middle of an
opening in the core to provide a single-turn primary winding. To assist accuracy, the primary conductor
should be centered in the aperture.
ISOLATOR
Isolator is a mechanical switch which isolates a part of circuit from the system as when required. Isolator
is operated when a circuit has no load (off load) or else it will cause damage. It is operated manually.
Depending upon the position in power system, the Isolators can further be categorized into following
three types according to their placement in the power system.
BUS ISOLATOR
A bus isolator is an off-load switch that connects the line breaker and
the bus. It sits between circuit breaker and bus.
LINE ISOLATOR
A line isolator is an off-load switch that connects the line breaker and the
line. It sits between circuit breaker and current transformer.
TRANSFER BUS ISOLATOR
The main conception of Main and Transfer
Bus System is, here every feeder line is directly
connected through an isolator to a
second bus called transfer bus. The said isolator in
between transfer bus and feeder line is generally
called bypass isolator.
EARTH SWITCH
What I described above is for type of maintenance earth switch but now-a-days high speed earth switch
are also being used in GIS. This high speed earth switch come with high speed motors and whenever any
fault occurs it will ground the faulted part immediately to protect the equipment.
SF6 CIRCUIT BREAKER
The primary winding consists of a large number of turns which is connected across the high voltage side
or the line in which measurements have to be taken or to be protected. The secondary winding has lesser
number of turns which is connected to the voltmeters, or potential coils of wattmeter and energy meters,
relays and other control devices. These can be single phase or three phase potential transformers.
Irrespective of the primary voltage rating, these are designed to have the secondary output voltage of 110
V.
Since the voltmeters and potential coils of other meters have high impedance, a small current flows
through the secondary of PT. Therefore, PT behaves as an ordinary two winding transformer operating on
no load. Due to this low load (or burden) on the PT, the VA ratings of PTs are low and in the range of 50
to 200 VA. On the secondary side, one end is connected to the ground for safety reasons as shown in
figure.
POWER TRANSFORMER
CONSERVATOR
Conservator serves two important functions:
In an explosion vent, the diaphragm is fitted at the exposed end of the vent, which should
be inspected at frequent intervals and replaced if found deteriorated / damaged. Failure to
replace the defective diaphragm quickly may allow the ingress of moisture, which will
contaminate should be made to determine the nature and cause of the fault before re-
energising the transformer.
COOLING TUBES
In this method, heat is transferred to the oil surrounding the core and windings
and it is conducted to the walls of the transformer tank. Finally, the heat is
transferred to the surrounding air by radiation and convection.
BUCHHOLZ RELAY
BREATHER
Substation Control
Feeder Control
End User Load Control
RELAY
Relay Design
The diagram shows an inner section diagram of a relay. An iron core is surrounded by a control coil. As
shown, the power source is given to the electromagnet through a control switch and through contacts to the
load. When current starts flowing through the control coil, the electromagnet starts energizing and thus
intensifies the magnetic field. Thus the upper contact arm starts to be attracted to the lower fixed arm and
thus closes the contacts causing a short circuit for the power to the load. On the other hand, if the relay was
already de-energized when the contacts were closed, then the contact move oppositely and make an open
circuit.
As soon as the coil current is off, the movable armature will be returned by a force back to its initial position.
This force will be almost equal to half the strength of the magnetic force. This force is mainly provided by
two factors. They are the spring and also gravity.
Relays are mainly made for two basic operations. One is low voltage application and the other is high
voltage. For low voltage applications, more preference will be given to reduce the noise of the whole circuit.
For high voltage applications, they are mainly designed to reduce a phenomenon called arcing.
BATTERY BANK
Most high voltage substations house either a sealed or flooded cell battery bank. In a
normal functioning system, the batteries provide very little current. A continuous load
current maintains a constant charge on the battery. The battery charger provides a current
if the charge exceeds the output capability. A failing substation battery charger or if the
charger trips is a good indication of whether the system is working effe ctively.
An average battery load profile can last for up to 8 hours with the options to adjust the
duration to suit the requirements of the installation or application. Installing the correct
charging system is vital as it increases the service and the l ongevity of the battery system.
Selecting the correct substation battery charger system requires consideration of key
factors, such as environment, duty cycle and battery type.
MEGGER
The electronic type megger, also known as electrical megger, is compact of all types and uses a battery
for operation.
The handheld type megger is still used on the ship as it provides service without the need of battery and
external power source.
CONCLUSION
Throughout the training I have learned many new things about a substation like its power distribution
system in rural and other parts of the places. New advanced technology had been introduced to us like
SCADA, Relay, etc. which are intelligent devices that play a significant role in power system operation.
I would like to thank the trainers for their valuable time towards us in teaching new things.