Professional Documents
Culture Documents
Example Coordination Study PDF
Example Coordination Study PDF
Recommended Procedures
The following steps are recommended when 2. Short Circuit Study
conducting a selective coordination study. Perform a short circuit analysis, calculating maximum
1. One-Line Diagram available short circuit currents at critical points in the
Obtain the electrical system one-line diagram that identifies distribution system (such as transformers, main switchgear,
important system components, as given below. panelboards, motor control centers, load centers, and large
a. Transformers motors and generators.) (Reference: Bussmann Bulletin,
Obtain the following data for protection and coordination infor- Engineering Dependable Protection - EDPI.)
mation of transformers:
- KVA rating 3. Helpful Hints
- Inrush points a. Determine the Ampere Scale Selection. It is most
- Primary and secondary connections convenient to place the time current curves in the center of
- Impedance the log-log paper. This is accomplished by multiplying or
- Damage curves dividing the ampere scale by a factor of 10.
- Primary and secondary voltages b. Determine the Reference (Base) Voltage. The best
- Liquid or dry type reference voltage is the voltage level at which most of the
b. Conductors - Check phase, neutral, and equipment devices being studied fall. (On most low voltage industrial
grounding. The one-line diagram should include infor- and commercial studies, the reference voltage will be 208,
mation such as: 240, or 480 volts). Devices at other voltage levels will be
- Conductor size shifted by a multiplier based on the transformer turn ratio.
- Number of conductors per phase The best reference voltage will require the least amount of
- Material (copper or aluminum) manipulation. Modern computer programs will automat-
- Insulation ically make these adjustments when the voltage levels of
- Conduit (magnetic or non-magnetic) devices are identified by the input data.
From this information, short circuit withstand curves can be c. Commencing the Analysis. The starting point can be
developed. This provides information on how overcurrent determined by the designer. Typically, studies begin with
devices will protect conductors from overload and short the main circuit devices and work down through the
circuit damage. feeders and branches. (Right to left on your log-log paper.)
c. Motors d. Multiple Branches. If many branches are taken off one
The system one-line diagram should include motor feeder, and the branch loads are similar, the largest rated
information such as: branch circuit should be checked for coordination with
- Full load currents upstream devices. If the largest branch will coordinate, and
- Horsepower the branch devices are similar, they generally will
- Voltage coordinate as well. (The designer may wish to verify other
- Type of starting characteristic areas of protection on those branches, conductors, etc.)
(across the line, etc.) e. Don't Overcrowd the Study. Many computer generated
- Type of overload relay studies will allow a maximum of ten device characteristics
(Class 10, 20, 30) per page.
Overload protection of the motor and motor circuit can be f. One-Line Diagram. A one-line diagram of the study
determined from this data. should be drawn for future reference.
d. Fuse Characteristics
Fuse Types/Classes should be identified on the one-line
diagram.
e. Circuit Breaker Characteristics
Circuit Breaker Types should be identified on the one-line
diagram.
f. Relay Characteristics
Relay Types should be identified on the one-line diagram.
14
Examples of Selective Coordination Studies
The following pages will analyze in detail the system This simple radial system will involve three separate
shown in Figure 11. It is understood that a short circuit time current curve studies, applicable to the three feeder/
study has been completed, and all devices have adequate branches shown.
interrupting ratings. A Selective Coordination Analysis is the
next step.
13.8KV
Overcurrent Relay
IFLA=42A JCN80E
#6 XLP
1000KVA
∆-Y 5.75% Z
480/277V
#3/0 THW
LOW-PEAK® LOW-PEAK®
LPS-RK-100SP LPN-RK-500SP
LP1
20A Branch 250 kcmil
2/Ø THW
100A Motor Branch
20A CB
#12 THW
20A CB #1 THW
60HP 3Ø
M 77A FLA
Figure 11
15
Example –
16
Example –
400 FLA 3
300 2
XFMR
200 DAMAGE
100
11
80
60
JCN 80E
20A MCCB
40
LPS-RK-200SP 5
30
KRP-C-1600SP
20
MV OLR
TIME IN SECONDS
10
8
4
#6 DAMAGE
3 3/0 DAMAGE
2
#12 DAMAGE 12
13.8KV
14 4
1
.8
Overcurrent .6 13
Relay
.4
JCN80E .3
#6 XLP
.2
1000KVA TX
5.75%Z 1
INRUSH
∆-Y .1
480/277V
.08
.06
KRP-C-1600SP 6
.04
.03
.02
LPS-RK-200SP
200A .01
10,000
1
8
10
20
30
40
60
80
100
200
300
400
600
800
1000
2000
3000
4000
6000
8000
20A CB 20A CB
#12 THW
17
Example –
18
Example –
600 2
400 FLA 3
300 2
100 24
80 23
13.8KV 60
JCN80E
MTR START
40 5
30 LPS-RK-100SP
Overcurrent
Relay MV OLR
20
KRP-C-1600SP
JCN 80E
TIME IN SECONDS
10
#6 XLP 8
6
1000KVA
5.75%Z 4
∆-Y #6 DAMAGE
480/277V 3
2
22
25
KRP-C-1600SP #1 DAMAGE 4
1
.8
.6
.4
LPS-RK-400SP 21
.3
400A Feeder
.2
TX
INRUSH
.1
LPS-RK-100SP 1
.08
#1 THW .06
.04 6
.03
.02
.01
60HP M
10,000
1
8
10
20
30
40
60
80
100
200
300
400
600
800
1000
2000
3000
4000
6000
8000
19
Example –
20
Example –
600 2
3
400 FLA FLA
300 2
XFMR DAMAGE
200
100
80
60
JCN80E
13.8KV 40
LPS-RK-225SP 5
30
LPN-RK-500SP
MV OLR
20
Overcurrent KRP-C1600SP
Relay 31
TIME IN SECONDS
10 34
8
2-250 DAMAGE
JCN 80E 6
35
4
#6 DAMAGE
3
#6 XLP XFMR DAMAGE 33
2
1000KVA
5.75%Z
∆-Y 4
1
480/277V
.8
.6
.4
KRP-C-1600SP
.3
.2
TX TX
INRUSH INRUSH
LPS-RK-225SP .1 32 1
.08
150KVA .06
2.0%Z
∆-Y .04
208/120V 6
.03
.02
LPN-RK-500SP
250 kcmil
2/Ø THW .01
10,000
1
8
10
20
30
40
60
80
100
200
300
400
600
800
1000
2000
3000
4000
6000
8000
21
Conclusions
Unnecessar y power OUTAGES, such as the
BLACKOUTS we so often experience, can be stopped by
isolating a faulted circuit from the remainder of the system
through the proper selection of MODERN CURRENT-
LIMITING FUSES.
Time-Delay type current-limiting fuses can be sized
close to the load current and still hold motor-starting
currents or other har mless transients, thereby
ELIMINATING nuisance OUTAGES.
The SELECTIVITY GUIDE on page 10 may be used for
an easy check on fuse selectivity regardless of the short-
circuit current levels involved. Where medium and high
voltage primary fuses are involved, the time-current
characteristic curves of the fuses in question should be
plotted on standard NEMA log-log graph paper for proper
study.
The time saved by using the SELECTIVITY GUIDE will
allow the electrical systems designer to pursue other areas
for improved systems design.
22