You are on page 1of 94

PROJECT

LARSEN & TOUBRO LIMITED QUALITY PLAN


TRANSPORTATION INFRASTRUCTURE IC WORK METHOD
REHABILITATION AND UPGRADATION OF JUNCTION WITH STATEMENT
NH-211 TO MANWATH(TADBORGAON) SECTION OF NH 222
FROM KM 342.00 TO KM 444.000 TO 2-LANES WITH
PAVED SHOULDERS IN MAHARASHTRA
APPENDIX-IV

REHABILITATION AND UPGRADATION OF


JUNCTION WITH NH-211 TO
MANWATH(TADBORGAON) SECTION OF NH
222 FROM KM 342.00 TO KM 444.000 TO 2-
LANES WITH PAVED SHOULDERS IN
MAHARASHTRA

WORK METHOD
STATEMENT

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
1
PROJECT
LARSEN & TOUBRO LIMITED QUALITY PLAN
TRANSPORTATION INFRASTRUCTURE IC WORK METHOD
REHABILITATION AND UPGRADATION OF JUNCTION WITH STATEMENT
NH-211 TO MANWATH(TADBORGAON) SECTION OF NH 222
FROM KM 342.00 TO KM 444.000 TO 2-LANES WITH
PAVED SHOULDERS IN MAHARASHTRA
APPENDIX-IV

VOLUME-II

Summary Sheet for Work Method Statement


SI Reference Page
Detail of method statement
No. No No
1 METHOD STATEMENT FOR SURVEY WORK (FIXING OF
WMS/01 01
ROAD ALIGNMENT, CENTER LINE & TOE LINE)
WMS/02
2 METHOD STATEMENT FOR CLEARING AND GRUBBING 03

METHOD STATEMENT FOR DISMANTALING OF


3 WMS/03 05
CULVERT & BRIDGES.

METHOD STATEMENT FOR DISMANTLING OF EXISING


4 WMS/04 07
ROAD

METHOD STATEMENT FOR EXCAVATION FOR ROAD


5 WMS/05 09
WORK IN SOIL/ROCK
METHOD STATEMENT FOR EARTHWORK IN
6 WMS/06 13
EMBANKMENT(FILLING)
METHOD STATEMENT FOR EARTHWORK IN SUBGRADE
7 WMS/07 15
(FILLING)
METHOD STATEMENT FOR EARTHWORK IN
8 WMS/08 19
MEDIAN/ISLAND
METHOD STATEMENT FOR CONSTRUCTION GRANUAL
9 WMS/09 21
SUB-BASE COURSE
METHOD STATEMENT FOR CONSTRUCTION WET MIX
10 WMS/10 24
MACADAM

11 METHOD STATEMENT FOR PRIME COAT & TACK COAT WMS/11 27

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
2
PROJECT
LARSEN & TOUBRO LIMITED QUALITY PLAN
TRANSPORTATION INFRASTRUCTURE IC WORK METHOD
REHABILITATION AND UPGRADATION OF JUNCTION WITH STATEMENT
NH-211 TO MANWATH(TADBORGAON) SECTION OF NH 222
FROM KM 342.00 TO KM 444.000 TO 2-LANES WITH
PAVED SHOULDERS IN MAHARASHTRA
APPENDIX-IV

METHOD STATEMENT FOR BITUMENIOUS


12 WMS/12 31
CONSTRUCTION (BM, DBM, BC)
METHOD STATEMENT FOR DRY LEAN CONCRETE FOR
13 WMS/13 36
TOLL PLAZA.
14 METHOD STATEMENT FOR PAVEMENT QUALITY
WMS/14 41
CONCRETEFOR TOLL PLAZA
METHOD STATEMENT FOR LAYOUT & BASE
15 PREPRATION FOR STRUCTURES WMS/15 49
(ROB/CULVERRTS/BRIDGES)

16 METHOD STATEMENT FOR PIPE CULVERTS WMS/16 50

METHOD STATEMENT FOR FOUNDATION EXCAVATION


17 WMS/17 52
OF STRUCTURES IN SOIL/ROCK
METHOD STATEMENT FOR FORMWORK,
18 REINFORCEMENT & CONCRETING IN STRUCTRAL WMS/18 54
WORK
METHOD STATEMENT FOR BACK FILLING IN
19 WMS/19 60
STRUCTURES
METHOD STATEMENT FOR INSTALLATION OF
20 WMS/20 63
ELASTOMERIC BEARING

21 METHOD FOR INSTALLATION OF POT / PTFE BEARING WMS/21 65

METHOD STATEMENT FOR ERECTION OF STEEL


22 WMS/22 68
GIRDER IN ROB& CAST IN SIU DECK SLAB
METHOD STATEMENT FOR APPLICATION OF WATER
23 PROFING MEMBERENCE INSTEAD OF MASTIC WMS/23 73
ASPHALT FOR BRIDGES.
METHOD STATEMENT FOR INSTALLATION OF STRIP
24 WMS/24 75
SEAL EXPANSION JOINTS

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
3
PROJECT
LARSEN & TOUBRO LIMITED QUALITY PLAN
TRANSPORTATION INFRASTRUCTURE IC WORK METHOD
REHABILITATION AND UPGRADATION OF JUNCTION WITH STATEMENT
NH-211 TO MANWATH(TADBORGAON) SECTION OF NH 222
FROM KM 342.00 TO KM 444.000 TO 2-LANES WITH
PAVED SHOULDERS IN MAHARASHTRA
APPENDIX-IV

METHOD STATEMENT FOR CONSTRUCTION OF MASTIC


25 WMS/25 77
ASPHALT WORK
METHOD STATEMENT FOR LAYING OF CEMENT
26 WMS/26 79
CONCRETE KERB FOR JUNCTIONS
METHOD STATEMENT FOR KERB PAINT MARKING FOR
27 WMS/27 82
JUNCTIONS.
28 METHOD STATEMENT FOR ROAD MARKING WMS/28 84

29 METHOD STATEMENT FOR TRENCH FILLING WMS/29 86


METHOD STATEMENT FOR TURFING ON EMBANKMENT
30 WMS/30 87
SLOPES
METHOD STATEMENT OF CONSTRUCTION OF PROFILE
31 WMS/31 89
CORRECTIVE COURSE OVER EXISTING CARRIAGE WAY
METHOD STATEMENT FOR STONE PITCHING /
32 WMS/32 93
REVETMENT ON SLOPES

33 METHOD STATEMENT FOR REINFORCEMENT WELDING WMS/33 96


METHOD STATEMENT FOR CONSTRUCTION OF BORED
34 WMS/34 98
CAST IN SITU PILES
METHOD STATEMENT FOR MEASUREMENT OF
35 SURFACE UNEVENNESS BY AUTOMATIC ROAD WMS/35 106
UNEVENNESS RECORDER

METHODOLOGY FOR RECONSTRUCTION& WIDENING &


36 FINISHING OF SUB / SUPERSTRUCTURES FOR BRIDGES WMS/36 109

METHOD STATEMENT FOR WIDENING OF EXISTING


37 WMS/37 111
CARRIAGEWAY

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
4
WMS / 01
METHOD STATEMENT FOR SURVEY WORK
(Fixing of road alignment, Center line & Toe line)
1.1 Scope:
 To provide permanent grid lines and construct bench marks for level control and
road alignment.
1.2 Reference
 MoRT&H Clause No: 109 and technical specifications of the project.
1.3 Equipments:
 Auto level, Levelling staff, total station etc.
1.4 Tools:
 Measuring tape, pegs, Nails, Paint Tins, Safety cones, safety board’s etc.
1.5 Procedure:
 The Project Reference centre line of proposed cross section will be fixed by
surveyor and marked on the ground by nail and changes shall be marked, on
existing roads, with paint. This marking shall be done @ 20m interval on straight
portion &10m interval on curve portion. The offset shall be marked on existing
road wherever applicable.
 2nos DGPS pillar(Size 300x300x600) fixed at a distance of 200m for every 5kms
for traversing purpose,TBM shall be fixed at every 200m on ROW line. The pillar,
shall be150*150*450 mm size with a steel rod embedded in it. The pillar, shallbe
established on hard ground and concreted with M15 Grade.
 Reduced levels shall be established on the marked pillars and closed at
everyGPS and abstract copy of TBM list shall be distributed to Section In charge
at every month.
 Calibration shall be carried out internally at every 1 month for auto levels and
external calibration shall be carried out for every year for auto levels and total
stations .

1.6 Precautions during survey:


 Do not aim the telescope at the sun it will damage the instrument.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
1
 Never place the instrument directly on the ground as it will damage the
instrument bottom.
 Never carry the instruments along with stand from one station to another station.
 Avoid heavy shocks and vibrations.
 Remove the battery before keeping the instrument in the box.
 Never keep wet instrument inside the box, allow it to dry before that.
 Before removing the instrument from the case see the lay out position in order to
keep back the instrument in same position.

1.7 Safety Measures:


 Flagmen and safety cones will be arranged at the time of work.
 All safety measures shall be as per approved EHS Plan.

WMS / 02
METHOD STATEMENT FOR CLEARING AND GRUBBING

2.1 Scope:
 The work consists of cutting, removing, and disposing of all materials such as
bushes, roots, grass, and top organic soil not exceeding 150 mm in thickness. It
shall include necessary excavation,backfilling of pits resulting from the uprooting
of trees and stumps, of girth size less than 300mm, to required compaction,
handling and disposal of cleared material.

2.2 References:
 MoRT&H specification of clause No: 201,

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
2
2.3Equipments:
 Dozer, backhoe, dumpers, etc.

2.4 Tools:
 Measuring Tape, line, rope etc.

 2.5 Procedure:
 Clearing and grubbing process shall be followed by“disposal of material”and shall
be done to the maximum thickness up to 150mm.
 Unwanted material after dozing shall be disposed.

2.6 Safety Measures:


All safety precautionary measures shall be taken as stated below: -
 Flagmen and safety cones will be arranged at the time of work.
 Signboards shall be placed along the right hand side on increasing chainage at
every 500 meters i.e. “KEEP RIGHT WORK IN PROGRESS”, GO SLOW WORK
IN PROGRESS”.
 Moveable signboards shall be place at area where heavy machineries and survey
works being carried out. The movement of machines and lorries at these areas
shall be controlled by flagman’s Signboards such as “CAUTION MAN AT WORK
GO SLOW”, “CAUTION GO SLOW WORK IN PROGRESS”.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
3
WMS / 03
METHOD STATEMENT FOR DISMANTLING OF CULVERTS AND
BRIDGES
3.1 Scope:
 This work shall consist of removing/dismantling the culverts, bridges.
3.2 References:
 MoRT&H specification cl No: 202.2 and technical specification of Contract.
3.3 Equipments:
 Rock breaker, Excavator, Compressor& hand breaker, electrical chipper, DG set,
auto level and levelling staff etc.
3.4 Tools:
 Measuring Tape, Crow bar, spade, etc.
3.5 Procedure:
 Prior to start of dismantling, the dimensions of structure shall be measured.
 Existing culverts, bridges and other structures with in carriage way,identifiedfor
dismantling, shall be removed up to the limits as specified in
Drawings.
 The location of existing piers, abutments falling in the new bridge piers location
shall be removed up to the bottom of raft, if not shall be removed as per drawing.
 The structures shall be dismantled carefully not to cause any damage to the
serviceable materials.
 Where the existing bridges are to be widened, the connecting edges shall be cut,
chipped and trimmed to the required lines and slopes without causing any
Damage to the structure to be retained.
 The Existing reinforcing bars shall be left in place so as to project in to the new
work as dowels or ties.
 Disposal of materials shall be done in accordance with Cl.202.5 of MoRT&H.
 Detailed work method statement shall be submitted separately for specific critical
structures.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
4
3.6 Safety Measures:
All safety precautionary measures shall be taken as stated below: -

 Signboards shall be placed along the right hand side on increasing chainage at
every 500 meters i.e. “KEEP RIGHT WORK IN PROGRESS”, GO SLOW WORK
IN PROGRESS”.
 Moveable signboards shall be place at area where heavy machineries and survey
works being carried out. The movement of machines and lorries at these areas
shall be controlled by flagman’s Signboards such as “CAUTION MAN AT WORK
GO SLOW”, “CAUTION GO SLOW WORK IN PROGRESS”.

WMS / 04
METHOD STAT3EMENT FOR DISMANTLING OF EXISTING PAVEMENT

4.1 Scope:
 The work shall consist of dismantling of existing pavement / removal of all major
cracks area of the existing carriageway by use of excavator / milling machines.

4.2 References:
 MoRT&H specifications Clause no. 202.3, 202.5, 517

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
5
4.3 Equipment’s:
 Excavator, dumper, water tanker, Milling machine, Auto level, levelling staff.

4.4 Tools:
 Lime powder, measuring steel tape, straight board.

4.5 Procedure:
 Joint survey on existing pavement shall be carried out prior to the
Commencement of dismantling / milling and excavation works.
 Dismantling/Milling of the existing asphalt layer shall be carried out to a required
depth based on drawing.
 The material from dismantled pavement shall be partially or fully reused in fresh
constructionbased on guidelines of the codes.
 Disposal of materials shall be done in accordance with Cl.202.5 of MoRT&H.

4.6 Safety Measures:

All safety precautionary measures shall be taken as stated below: -

 Signboards shall be placed along the right hand side on increasing chainage
at every 500 meters i.e. “KEEP RIGHT WORK IN PROGRESS”, GO SLOW
WORK IN PROGRESS”.

 Moveable signboards shall be place at area where heavy machineries and


survey works being carried out. The movement of machines and lorries at
these areas shall be controlled by flagman’s Signboards such as “CAUTION
MAN AT WORK GO SLOW”, “CAUTION GO SLOW WORK IN PROGRESS”.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
6
WMS / 05
METHOD STATEMENT FOR EXCAVATION OF ROAD IN SOIL/ROCK

5.1 Scope:
 This work shall consist of excavation by mechanical means in all types of strata,
in rock by controlled blasting, by wedging / rock splitting or line drilling using
pneumatic equipment and expanding agents, chiselling including dressing to final
line, level, grades, cross section as shown in drawings for roadway, drains,
shoulders, median and foundation for structures, including hauling suitable
excavated materials to site for embankment and sub-grade construction, also
disposal of unsuitable cut materials in specified manner.

5.2 References:
 MoRT&H specification clause No: 301 to 303 and technical specifications of
Contract.

5.3 Equipments:
 Excavators, Dumpers. Rock breaker, blasting arrangement, dewatering
arrangement.

5.4 Tools:
 Line rope, lime powder, pegs etc…

5.5 Procedure:
General:

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
7
 The excavation shall be set out true to lines, curves, grades and sections as per
drawings.
 In works involving the widening of existing carriage way, earthen shoulders,
median shall be excavated to the full width and to the required levels, after
satisfying CBR and density requirement, as shown in drawings without disturbing
the existing pavement that is to be retained. After reaching to the required depth,
it shall be compacted at OMC to achieve min. of 95% of MDD.
 Excavated soil shall be tested for its suitability and shall be reused.
 The cut formation, which serves as sub-grade if found suitable, then the same
shall be checked for its relative compaction as per table:300.2, and if fails, then
the same shall be loosened and compacted in layers in the specified manner .
Any unsuitable material encountered in the sub grade level shall be removed and
replaced with suitable material.
 In case widening beyond existing shoulder, after C&G the bed to be developed
as embankment or Sub Grade in full width with benching in layers

 While executing excavation all adequate precautions of soil erosion, water


pollution and appropriate drainage measures to keep the site free of water shall
be taken.
 The suitable material obtained from excavation shall be used for filling of roadway
embankment, filling of existing pits in the ROW, landscaping etc. All other
unsuitable and surplus materials shall be disposed of.
Rock excavation:
 Rock when encountered shall be removed up to the required slopes, lines,
depths or levels as prescribed in the drawings.
 All loose pieces of rock on excavated slope surfaces that move when pierced by
a crowbar shall be removed. In all cases at no point on cut formation the rock
shall protrude above specified levels.
Rock excavation by blasting:
 In rock excavation wherever blasting is resorted it shall be of controlled blasting
with least disturbance to the adjacent materials and to the required lines as
indicated in drawings and the method of blasting consistent with safety and job
requirements.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
8
 The blasting operations shall be prepared or made by the competent and
experienced personnel and workmen under Licensed Blaster who are thoroughly
acquainted with details of handling explosives and blasting operations.
Site Clearance:
 Blasting shall be carried out in fixed hours as ordered in writing by the Engineer
and kept known to the people, public and authorities in the vicinity sufficiently in
advance.
 Red flags shall be displayed in all directions during blasting operations. People
except those who actually light the fuse shall be prohibited from the area and all
persons, including workmen shall be evacuated from the flagged area at least 10
minutes before firing, a warning alarm or siren sounded for this purpose. The
man-in-charge shall satisfy himself that all charges are exploding before allowing
and workmen or people.
Firing:
 The firing of the charge hole shall be done by electric detonators, by using a
sufficiently long fuse wire (at least 100m) and all charge holes shall be blasted at
one instance.
Explosives:
 The explosives for blasting shall be as per permissible explosives as per
procedure & requirement. The weight of charge depends upon the quantity of
rock to be blasted/excavated, hardness of the rock and site conditions.
Stemming:
 Stemming may be used if required, of free dry-running material, which passes
through a 2.8 mm sieve and retained on 1.2mm sieve by 90%.
Muffling:
 This shall be done to control the fly rock. Since the drill holes loaded with less
charge, sand/earth bags weighing at least 50kg shall be kept on each charge
hole, to control the fly rock.
5.6Safety Measures:
 The cutting material shall not disturb the live traffic
 The cutting crew shall wear PPE, reflective jackets
 The cutting area shall be protected with safety boards and cones
 Take care of nearby passing electrical lines and utilities.
 Flagmen shall be provided on both side of cutting area to regulate live traffic.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
9
WMS / 06
METHOD STATEMENT FOR EARTHWORK IN EMBANKMENT
(FILLING)
6.1 Scope:
 This work shall consist of Embankment construction with approved materials from
roadway excavation or borrow pits.
6.2 References:
 IRC:SP:73-2007, MoRT&H Specifications, Clause no: 305, IRC-36-2010 and
Technical specifications of Contract.
6.3 Equipments:
 Excavator/ Back hoe, Dozer, Motor Grader, Dumpers, Vibratory roller, Water
tanker, Auto Level, measuring tape.
6.4 Tools:
 Hammer, crow bar, spade, strings, pegs, lime powder, etc.
6.5 Materials:
 These materials shall be free from logs, stumps, roots, rubbish or any other
ingredients likely to affect the stability of the embankment. The material that has
LL less than 50%, PI less than 25%, Free Swell Index Less than 50%,shall be
used for Embankment construction. The material which is having Lab MDD 15.2
to 16.0 KN/cum as per IS: 2720(Part8), shall be used in embankment filling. The

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
10
sample from the borrow areas shall be brought to the laboratory and tested for
the above requirements.
6.6 Procedure:
 Before commencing the earth work the Toe limits of Embankment shall be
marked.
 The original ground shall be levelled, scarified, mixed with water and compacted
to achieve 95 % of lab MDD.
 The materials for the Embankment shall be excavated at borrow areas by
excavators and hauled to site by dumpers.
 The dumped material shall be spread in uniform thickness by means of
Graders/mechanical means to achieve specified slopes and grades.
 Clods and hard lumps of earth will be broken to a maximum size of 75 mm for
embankment.
 If the moisture content (NMC) is less than OMC, the water shall be added by
sprinkling considering evaporation losses, so that at the time of compaction it is in
the range of 1%above to 2% below the optimum moisture content.
 If NMC is more than OMC, the material can be allowed to dry by exposure to the
sun.
 The compacted thickness of each layer shall not be more than 250mmthick when
a vibrator roller soil compactor used and not more than 200mm when 80-100KN
static roller used to achieve 95 % of MDD.
 The rolling shall commence from lower edge and proceeded towards upper edge.
 Each pass of roller shall overlap 1/3rd of the preceding pass.
6.7 Acceptance Criteria:
 Field Dry Density Shall be greater than 95% of MDD

 Optimum moisture content shall be +1% to -2% during the time of compaction.
6.8 Safety Measures:
 All tippers, tankers graders etc. shall be provided with reverse horns.
 All exit points of the trucks /tippers shall be marked with safety cones and caution
boards.
 Flagman shall be provided at all exit points of the trucks /tippers.
 The speed of vehicles plying in the work shall be restricted to 40kmph maximum.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
11
 Leveling staff shall be made of wood.
 Any local labour if working in the job shall be screened and trained.
 Adequate area lighting in case of night work shall be ensured.
 Proper PPEs viz. Shoes, Safety Jackets etc. shall be used.

WMS / 07
METHOD STATEMENT FOR EARTHWORK IN SUBGRADE (FILLING)
7.1 Scope:
 This work shall consists of Sub grade construction with approved materials from
roadway excavation or borrow pits.
7.2 References:
 IRC:SP:73-2007, MoRT&H Specifications, Clause no: 305, IRC-36-2010 and
Technical specifications of Contract.
7.3 Equipment:

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
12
 Excavator/ Back hoe, Dozer, Motor Grader, Dumpers, Soil compactor, Water
tanker,
 Auto Level.
7.4 Tools:
 Hammer, crow bar, spade, line rope, pegs, lime powder, measuring tape, etc.
7.5 Materials:
 These materials shall be free from logs, stumps, roots, rubbish or any other
ingredients likely to affect the stability of the Sub grade. The material that have LL
less than 50%,PI less than 25%,Free Swell Index Less than 50% ,shall be used
for Sub grade construction. The material which is having Lab MDD of min.
17.5KN/cum and CBR Value recommended as per designshall be used for filling
in Sub grade. The sample from the barrow areas shall be brought to the
laboratory and tested for the above requirements.
7.6 Procedure:
 Before commencement, Toe width of sub-grade shall be marked.
 The approved Borrow area / Cut section material as per MORT&H clause
305.2.1is brought to the stretch.
 The dumped material shall be spread in uniform thickness by means of
graders/mechanical means to achieve specified slopes and grades.
 Clods and hard lumps of earth will be broken to a maximum size of 50 mm for
sub grade.
 The stretch is to be watered with required quantity of water to bring from natural
moisture content of material to optimum moisture content by sprinkling of water
with water tanker uniformly at control rate of flow.
 If the moisture content (NMC) is less than OMC, the water shall be added
above1% to 2% by sprinkling considering evaporation losses.
 If NMC is more than OMC, the material can be allowed to dry by exposure to the
sun.
 The compacted thickness of each layer shall not be more than 250mmthick when
vibrator roller soil compactor used and not more than 200mm when 80-100KN
static roller used to achieve 97 % of MDD.
 Rolling shall be commenced from the lower edge and proceeded towards the
upper edge. Each pass of roller shall overlap 1/3rd of the preceding pass.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
13
 After rolling & level checking for specific layer, tests shall be carried out to check
its degree of compaction by any suitable method and the results are recorded in
the format.
 Level check for top layer of sub grade shall be recorded in the format.
7.7 Acceptance Criteria:
 Field Dry Density Shall be greater than 97% of MDD
 Layer thickness tolerance shall be +_20mm
 Optimum moisture content shall be +1% to -2% during the time of compaction.
7.8 Safety Measures:
 All tippers, tankers graders etc. shall be provided with reverse horns.
 All exit points of the trucks /tippers shall be marked with safety cones and caution
boards.
 Flagman shall be provided at all exit points of the trucks /tippers.
 The speed of vehicles plying in the work shall be restricted to 40kmph maximum.
 Leveling staff shall be made of wood.
 Any local labour if working in the job shall be screened and trained.
 Adequate area lighting in case of night work shall be ensured.
 Proper PPEs viz. Shoes, Safety Jackets etc. shall be used.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
14
WMS / 08
METHOD STATEMENT FOR ISLAND FILLINGFOR JUNCTIONS

 8.1 Scope:
 This work shall consist constructing of islands in the road dividing the carriage
way in to separate lanes to channelize the traffic in accordance with the lines,
grades and cross sections shown on the drawings for junctions.

 8.2 Reference:
 Section 407 of MoRT&H specification.

 8.3 Equipments:
 Dumpers, Motor Grader/Loader, Roller/Plate Compactor, Wooden Rammer, and
Water Tanker

8.4 Materials:
 The materials used in the island shall be soil, moorum, gravel,only.
 The materials shall satisfy the Physical and chemical requirements as per
MoRT&H Clause No: 305.2.1.1, 305.2.1.2, 305.2.1.3& 407.4.2.

8.5 Procedure:
 Unwanted plants, roots, boulders, concrete and bituminous material shall be
removed prior to start of island filling.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
15
 Care shall be taken to avoid spilling of soil over adjacent pavement while
dumping. Care shall be taken to avoid spilling of soil over adjacent pavement
while dumping. Soil shall be spread in uniform layers of 200mm by manually as
per the site condition. Water shall be added to the material to achieve the
moisture content in the range of +1 % to -2% of OMC before rolling takes place.
 Compaction shall be done whereas in 2.5m median /island compaction shall be
done with 2.5 ton roller or plate compactor for 1.2 m median/ island
 The top most layers shall be compacted lightly in order to facilitate sufficient
growth of roots of grass and plants/shrubs.

8.6 Safety Measures:


 All tippers, tankers graders etc. shall be provided with reverse horns.
 All exit points of the trucks /tippers shall be marked with safety cones and caution
boards.
 Flagman shall be provided at all exit points of the trucks /tippers.
 The speed of vehicles plying in the work shall be restricted to 40kmph maximum.
 Leveling staff shall be made of wood.
 Any local labour if working in the job shall be screened and trained.
 Adequate area lighting in case of night work shall be ensured.
 Proper PPEs viz. Shoes, Safety Jackets etc. shall be used.

WMS / 09
METHOD STATEMENT FOR CONSTRUCTION OFGRANULAR
SUBBASE COURSE

9.1 Scope:
 This work shall consist of Granular sub base construction with approved
materials.
9.2 References:
 MoRT&H Specifications, Clause no: 401, Technical specifications of Contract.
9.3 Equipment’s:

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
16
 Excavator/ Back hoe, Dozer, Motor Grader, Dumpers, Vibratory roller, Water
tanker, Auto Level.
9.4 Tools:
 Hammer, crow bar, spade, line rope, pegs, and lime powder, measuring tape,
etc.
9.5 Materials:
 The material to be used for the work shall be natural sand, crushed gravel, and
crushedstone, crushed slag or combination thereof depending upon the grading
required. If the water absorption of the aggregates determined as per
IS:2386(part:3) is greater than2%,the aggregates shall be tested for wet
aggregate impact value(AIV)IS:5640: 40% maximum
9.6 Procedure:
 Toe width of GSB shall be marked before commencement.
 The material shall satisfy table 400-1 Grading- I requirement of MoRT&H Rev. 5
 GSB layer shall be constructed on the sub grade top layer, which is already
constructed as per MoRT&H clause 305.
 Calculated quantity of GSB material shall be placed on the entire bed. If any
segregation is observed, the same is rectified by processing with the help of
grader blade. GSB material gradation shall be checked at QC lab.
 Material shall be spread uniformly with the help of motor grader.
 Required amount of water will be sprinkled, calculation based on OMC (+1% to
-2% tolerance limits).
 Final grading shall be done carefully as per required slope and level without
segregation.
 The graded material shall be thoroughly compacted to the specified densities by
vibratory roller having a static minimumweight of 8-10 tons.
 Rolling shall be commenced at the lower edge and proceeded towards the upper
edge longitudinally with overlapping of one third of roller drum width for each
passes for areas of unidirectional cross fall (camber) and super elevation.
 The number of heavy vibratory passes shall be established after doing trial
stretch to achieve required density.
 All the depressions, high spots, segregated locations shall be made correct
during initial rolling itself.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
17
 Camber shall be checked and corrected if required before final rolling.
 Finally one plain pass shall be given on the entire length of the stretch.
 Speed of the roller shall be maintained uniformly (not exceeding 5km/hr.) during
rolling.
 After rolling compaction test shall be carried out to check its degree of
compaction by any suitable method.
 Levels shall be checked and recorded in the format no. A/F 03 for the top layer.
9.7 Acceptance criteria:
 The Field Dry density shall be more than 98% of MDD
 The tolerance on the surface level shall be +_10mm
 Surface Regulatory shall not be more than 8 mm

9.8 Safety Measures:


 All tippers /tankers /graders shall be provided with reverse horn.
 Flagman shall be provided at all exit points of the trucks/tippers.
 The speed of the vehicles plying in the work area shall be restricted to 40 kmph
maximum.
 Leveling staff shall be made of wood.
 If night work is to be carried out the area shall be sufficiently provided with
lighting.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
18
WMS / 10
METHODOLOGY FOR CONSTRUCTION OFWET MIX MACADAM
 10.1 Scope:
 Laying and compacting well graded Wet Mix Macadam on prepared granular sub-
base for flexible pavement.
 10.2 References:
 MoRT&H specifications clause No: 406 and technical specifications of contract.
 10.3 Equipments:
 Paver, Motor grader, Dumpers, Vibratory roller, water tanker, Auto level,
 10.4 Tools:
 Measuring Tape, Line rope, lime powder, pegs, String wire etc…
 10.5 Materials:
 The aggregate shall be produced from the multiple stage crushing and screening
plant.
Physical requirements:
 The aggregate blend for WMM for roads shall confirm to grading requirements
mentioned in table 400-13 in MoRT&H specification. The material to be used
shall have Los Angeles abrasion value not more than 40% or aggregate impact
value not more than 30%, combined flakiness and elongation Indices not more
than 35%, PI value not more than 6%.If water absorption is more than
2%soundness test shall be carried out.
 10.6 Procedure:
 Wet Mix Macadam shall be prepared, as per the approved design proportion, in
the Pug mill plant with controlled addition of water.
 Gradation of the mix shall be checked as the production starts for the day at the
site laboratory itself.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
19
 Generally 1.0 to 2% extra moisture shall be maintained in the mix to compensate
the evaporation losses depending upon the lead and ambient temperature.
 Mix shall be transported from the plant to the laying site by dumpers.
 Water shall be sprinkled on the entire GSB surface, before placing the WMM.
 Before laying and spreading of material, the shoulder on both sides shall be
constructed in advance. This will laterally confine the wet mix macadam
while compacting.
 The wet mix shall be spread uniformly and evenly upon the prepared granular
sub-base by a paver finisher / motor grader.
 The required camber, grade, and thickness shall be checked. The high and low
spots are to be rectified by removing or adding new material.
 The number of heavy vibratory passes shall be established after doing trial
stretch to achieve required density.
 Vibratory pass shall overlap 1/3 of preceding pass, and make sure the speed of
the roller shall not exceed 5km/hr. The places not accessible to roller shall be
compacted with mechanical tampers or by a plate compactor
 All the depressions and segregated portions if any will be rectified during initial
rolling itself.
 After the rolling is completed the stretch is to be tested for degree of compaction
with respect to MDD of design mix of WMM.
 Field compaction test shall be conducted as per MoRT&H clause No. 406.3.5.
 Surface levels will be maintained as per table no. 900-1, and recorded in the
specified format.
 All the Field density readings / results will be recorded in the specified format.
 Any rectification in WMM layer will be done after scarifying the layer for proper
bonding.

 10.7 Acceptance criteria:


 The Field Dry density shall be more than 98% of MDD
 The tolerance on the surface level shall be +-10mm
 Surface Regulatory shall not be more than 8 mm

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
20
10.8 Safety Measures:
 All tippers /tankers /graders shall be provided with reverse horn.
 Flagman shall be provided at all exit points of the trucks/tippers.
 The speed of the vehicles plying in the work area shall be restricted to 40 kmph
maximum.
 Leveling staff shall be made of wood.
 If night work is to be carried out the area shall be sufficiently provided with
lighting.

WMS / 11
CONSTRUCTION METHODOLOGY FORPRIME COAT AND TACK
COAT
 11.1 Scope:
This work consists of
 Preparing base and black topped surfaces in advance
 Application of single coat of bituminous prime coat on WMM,
 Application of tack coat on bituminous layer before laying DBM, SDBC, and BC.
11.2 Reference:
 MoRT&H revision-5, Clause no: 502 &503, IS: 8887-2004/ASTM D 2397, IRC-
16:2008.
11.3 Equipments:
 Bitumen sprayer, Power broom, blower, Electronic balance, compressor etc...
11.4 Tools:

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
21
 Trays, cotton Waste etc.
11.5 Materials:
 Binder: The material shall be cationic bitumen emulsion SS-1 grade or MC30
cutback bitumen as per IS: 8887-2004/ASTM D 2397&IS217 for prime coat and
tack coat.
 11.6 Procedure:
a) Prime coat:
 This work shall consists of application of a single coat low viscosity, low porous
bituminous material over wet mix macadam granular surface at the rate of 0.7-
1.0kg per Sqm(SS-1) whereas rate of spray for MC-30 shall be (0.6 to 0.9)
kg/sqm, to the width and lines as shown in drawing.
 The type and viscosity of primer shall comply with requirements of IS: 8887-
2004/ASTM D 2397&IS:217.
 The bituminous primer shall not be applied on flooded surface, during rain and
dust storm.
 The primer distributor shall be self-propelled, self-heating bitumen pressure
sprayer, spraying the material uniformly at a temperature between 20-60˚C.
 Immediately prior to applying prime coat, the surface shall be freeof dust and
loose particles, and care shall be taken not to disturb the interlocking of
aggregates.
 A primed surface shall be allowed to cure at least by 24hours before any
Subsequent surface treatment or mix is laid.
b) Tack Coat:
 This work shall consist of the application of a single coat of low viscosity liquid
bituminous material/cationic bituminous emulsion (RS1)&MC-70 as per IS: 8887-
2004/ASTM D 2397, IS: 217 on granular surface treated with primer/ hungry bit
surface @2.5 – 3.0 Kg per 10sqm.and normal bituminous surface @ 2.0 – 3.0kg /
10sqm.
 The bituminous tack coat shall not be applied on wet surface or during rain or
dust storm/ wind.
 The tack coat distributor shall be self-propelled, self-heating bitumen pressure
sprayer, spraying the material uniformly at a temperature between 20 – 60˚C.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
22
 Immediately prior to applying tack coat the surface shall be clean of dust and
loose particles.
11.7 Quality control tests and their frequencies :
 Rate of spread of binder at a frequency of 3tests per day will be checked.
 Quality of binder as per IS: 8887/ASTM D 2397, IS: 217.
11.8 Safety Measures:
 All workmen at work area shall wear PPE’s and reflective jackets.
 During night work sufficient lighting shall be provided.
 The work area shall be cleared off any person or workmen before applying
tack /prime coat using bitumen sprayer.
 Wherever required, Flagman shall be provided

WMS / 12

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
23
METHOD STATEMENT FOR CONSTRUCTIONOF BM, DBM AND
BITUMINOUS CONCRETE

12.1 Scope:
 The work shall consist of mixing, laying and compacting Bituminous Macadam,
DenseBituminous Macadam,and Bituminous Concrete.
12.2 References:
 MoRT&H specifications Clause No: 504,505, 507, and Technical specifications of
contract& IRC:111-2009.
12.3 Equipments:
 Sensor paver, Tandem roller, Pneumatic tyre roller, water tanker, dumpers,
Asphalt plant, Wheel loader, Auto level, levelling staff.
12.4 Tools:
 Lime powder, string, sensor pegs, measuring steel tape, straight board,
thermometer, steel scale.
12.5 Materials:
 Binder: The material shall be VG-30 grade bitumen for BM, and DBM and for
BituminousConcrete.
 Aggregate: The coarse and fine aggregate shall consist of crushed stone. These
shall be clean, hard, durable, dry and free from soft or friable, organic or
deleterious matter. These shall satisfy the physical requirement set forth for the
individual relevant materials/mixes. Before approval of the source it shall be
tested for stripping.

12.6 Procedure:
 This work shall consists of construction in a single course or in multiple course of
crushed aggregates premixed in HMP, with VG -30 grade bitumen as per JMF
for DBM, and BC with line, level and slopes as shown in drawings.
 The aggregate blended with coarse and fines shall consist of crushed rock and it
shall satisfy the following physical requirements of grading – as per
MoRT&H/IRC:111-2009.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
24
Aggregate
BM DBM BC
property

Max.5% Max.5% Max.5%


Grain size
passing passing passing
analysis
75mic sieve 75mic sieve 75mic sieve

Combined FI+EI Max. 35% Max. 35% Max. 35%

Los angles
Max.40% Max. 35% Max. 30%
Abrasion Value

AIV Max. 30% Max. 27% Max. 24%

Soundness with
Max. 12% Max. 12% Max. 12%
sodium sulphate
Soundness with
magnesium Max. 18% Max. 18% Max. 18%
sulphate
Water Absorption Max. 2% Max. 2% Max. 2%

Stripping(Retaine
Min 95% Min 95% Min 95%
d coating)
Polished Stone
NA NA Min. 55
Value
Sand Equivalent
Value
NA Min 50 Min 50
 The pre-mixed bituminous material shall be prepared in an electronically
controlledbatch mixed hot mix plant of adequate capacity and capable of yielding
a uniform quality mix.
 At the time of mixing the temperature of aggregate shall be 150-170˚C, bitumen
shall be 150-165˚C and the mix temperature shall not be more than 165˚C.
 The material shall be transported in clean vehicle; a thin coating of lubricating oil
may be applied to the interior of the vehicle to prevent sticking and shall be
covered with tarpaulin.
 The surface on which the bituminous layer to be laid shall be swept clean of all
loose and extraneous material by mechanical or by any other suitable method.
 The material which is to be paid shall be mix designed in accordance with
Marshall Method.
 The material shall be spread by means of self -propelled paver finisher of with
Electronic sensor device, except in inaccessible areas, to the required thickness,
lines and camber as shown in the drawings.
 The thickness of compacted layer shall not exceed 100mm.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
25
 For the inaccessible areas the mix shall be laid with suitable hand tools.
 At the time of laying a minimum temperature of 140˚C shall be maintained.

Requirement of the DBM Mix using VG-Grade Bitumen


Viscosity Grade
Properties Test Method
paving Bitumen
75 blows on each
Compaction level
face of the
(Number of blows)
specimen
Minimum stability (KN
9.0 AASHTO T245
at 60˚C)
Marshall flow (mm) 2-4 AASHTO T245
Marshall Quotient
2-5
(stability/flow)
MS - 2 and ASTM
% Air Voids 3-5
D 2041
% Voids filled with
65 - 75 MS - 2
bitumen (VFB)
Tensile Strength Ratio 80% (Minimum) AASHTO T283
Coating of Aggregate
95% (Minimum) IS:6241
Particles with Bitumen

% Voids in Mineral aggregate VMA

Nominal Min. % VMA related to designed % air voids***


Maximum Particle
size (mm)
3 4 5
9.5 14 15 16
13.2 13 14 15
19.0 12 13 14
26.5 11 12 13
37.5 10 11 12
***For intermediate value of designed percentage air voids VMA shall be interpolate

Mix design requirements DBM BC


Minimum stability at 60˚C 9.0Kn 9.0Kn
Flow 2-4 mm 2-4 mm
Air voids 3-5 % 3-5 %
Voids in mineral
as stated above 11% min
aggregate-VMA

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
26
Voids Filled by bitumen
65-75% 65-75%
-VFB

 As soon as the material is spread, compaction shall commence and completed


within the specified rolling temperatures.
 Minimum temperature of the Mix shall be 90˚C for Rolling. Rolling of longitudinal
joints shall commence behind the paving operations, after this the rolling shall
start from the lower edge towards upper edge parallel to the centre line of road,
and each pass shall overlap 1/3rd preceding pass.
 All deficiencies in the surface shall be made good behind the paver before the
Initial rolling commenced.
 The initial rolling shall be done with static weight smooth wheel roller, followed by
intermediate rolling with a vibratory roller of 80-100KNstatic weight.
 The finishing rolling shall be done by a smooth wheeled tandem roller of 80-
100Knweight. In uni-directional camber and super-elevated portions the rolling
shall progress from lower to the upper edge. Rolling shall be done as per
approved rolling pattern, which is decided in trial stretch.
 All the joints shall have offset of, at least 300mm from parallel joints of the layer
beneath, longitudinal joints shall coincide with either the lane edge or the lane
markings and shall not situated in wheel track zones.

12.7 Acceptance criteria:


 The tolerance in level shall be in between +6 to -6mm.
 The core density shall not be less than the 92% of the average density based on
theoretical maximum specific gravity of the loose mix (Gmm). As per IRC-
111(2009)
 The road unevenness index shall be less than 2000mm/km, over BC surface.
 The mix binder content shall be +/- 0.3% of designed OBC.

12.8 Safety Measures:


 Safety helmet, Safety jacket, Reverse horn, Red Flag, Hand Gloves, Safety
Shoes will be provided wherever required.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
27
 Two signalman with red flag will be deputed at both end to guide the traffic.
Safety jacket will be provided to all the asphalt laying team (Workmen).

WMS / 13
METHODOLOGY FOR CONSTRUCTION OFDRY LEAN CONCRETE
FOR TOLL PLAZA
13.1 Scope:
 This work shall consist of construction of dry lean concrete sub-base with
approved materials and mix, to the lines, grades, camber and thickness as shown
in the drawing.
13.2 References:
 MoRT&H specifications clause No: 601 and technical specifications of contract.
13.3 Equipments:
 Batching plant, Sensor paver/grader, Dumpers, water tanker, and 8-10 ton roller.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
28
13.4 Tools:
 Shovels, broom, wire brush, straight edge, and measuring tape.
13.5 Materials:
 Cement:The cement to be used in the works shall be Ordinary Portland Cement
of 43/53 grade conforming to IS: 8112/ IS: 12269, Fly ash shall be used with
replacement of cement as per mix design.
 Coarse aggregate: These shall be in confirmation with IS 383. The coarse
aggregate shall be dry, clean, hard, and durable of crushed stone. The water
absorption of aggregate shall not be more than 2% and the soundness shall not
be more than 12%with sodium sulphate or 18% with magnesium sulphate.
 Fine aggregate: These shall be in confirmation with IS 383 and shall be free
from clay, loam, shale, mica, etc., and of natural sand or crushed stone sand or
combination. The blended aggregate of coarse and fine aggregate shall confirm
to the following gradations per table 600-1 of MoRT&H.
13.6 Procedure:
a) Mix:
 The mix shall be proportioned with a maximum aggregate cement ratio of 15:1
and with minimum cement content of 150kg/cum.The fly ash shall not be more
than 20% by weight of cement and content of OPC shall not be less than
120kg/cum. However the proportions of aggregate to cement can be increased
based on the mix and machine performance during the trial patch.
 Trial mixes with moisture contents of 5.0,5.5, 6.0, 6.5 and 7.0%shall be made
using the above stated cement and blended aggregates.
 Optimum moisture and density will be determined by casting cubes. These cubes
shall becasted in three layers, each layer being compacted with
electronic/pneumatic vibratory hammer of 300-400N downward force.
 After the determination of moisture, a set of 5 cubes shall be cast for
determination of compressive strength on 7 days shall be achieved 10N/mm2
 If the required compressive strength is not achieved, trials with incremental
cement content will done and the above stated procedure shall be repeated tillthe
required strength is achieved.
 Before production of concrete, natural moisture in the aggregate shall be
determined and adjusted on day-to-day basis.
b) Mixing:

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
29
 The materials shall be mixed in a mechanized batching plant, with weighing
balances calibrated. While mixing, moisture content shall be kept optimum +2, to
avoid the evaporation losses. The capacity of the batching plant shall be at
least25% higher than the proposed capacity of the laying arrangements.
c) Trial length:
 A trial length of 60m shall be paved for the full width of the pavement and rolled,
byincluding at least one transverse construction joint involving hardened concrete
and fresh laid concrete.
 The in-situ density of the freshly laid concrete shall be determined by sand
replacement method with 200mm dia density cone, by making 3 density holes at
equal distances that diagonally bisects the trial length, these shall not be made in
the strip of 500mm from the edges.
 The average of these shall be considered as 100%, and with this the field density
of the regular work shall be compared.

d) Transportation and placing:


 The plant mix concrete shall be transported by sufficient number of tipping trucks
to ensure continuous, uniform supply of concrete to feed the laying equipment.
 The mix shall be protected from weather, by covering the tippers/dumpers with
tarpaulin during the transit.
 The lean concrete shall be laid with the help of sensor paver/grader to the
required widths, grades, camber and thickness.
 The equipment shall be capable of laying the materials in an even manner
without segregation, to the specified thickness after the compaction.
e) Compaction:

 The spreading, compacting and finishing of the lean concrete shall be carried
out as rapidly as possible. The final finishing of the same shall not exceed 90
minutes when the concrete temperature is above 25 and below 30 degree
Celsius and 120 minutes if less than 25 degree Celsius.
 The compaction shall commence as soon as the concrete is laid and levelled to
the full width till there is no further movement under the roller and the surface is
closed.
 Double drum smooth wheeled vibratory rollers of 80-100 KN static weight shall be
used for this purpose. In addition to the number of passes required for

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
30
compaction, there shall be a pass without vibration as preliminary pass and
another at the end as final pass.
 The minimum dry density obtained shall be 98% of that achieved in trial length,
and at a distance of 500mm from edge it shall be 96% of that achieved in the trial
length.
 The final surface shall be inspected immediately, and all loose, segregated or
defective areas shall be corrected by using fresh lean concrete.
 Honeycombed areas, any level/ thickness deficiency and surface irregularities
shall be corrected by concrete with 10mm and down aggregates.
 Special care and attention shall be exercised during compaction near joints, kerb,
channels, side forms, around gullies and manholes.
 Longitudinal and transverse joints are to be provided as shown in drawings. At
these joints unless vertical forms are used, the edge shall be cut back to vertical
face where correct thickness of compacted layer has obtained.
 Covering the surface with gunny bags/ hessian cloth. This shall be kept
continuously moist for 7days by sprinkling water.Or curing shall be done by
spraying curing compound as per requirement.
13.7 Safety Measures:
 All the transit mixers/Dumpers shall be provided with reverse horns.
 All exit points of the transit mixers shall be marked with safety cones and caution
boards.
 Flagman shall be provided at all exit points of the trucks /tippers.
 The speed of vehicles plying in the work shall be restricted to 30kmph maximum.
 Leveling staff shall be made of wood/fiber.
 Any local labour if working in the job shall be screened and trained.
 Adequate area lighting in case of night work shall be ensured.
 Proper PPEs viz. Shoes, Safety Jackets etc. shall be used.

WMS / 14
METHODOLOGY OF CONSTRUCTIONPAVEMENT QUALITY
CONCRETE FOR TOLL PLAZA
14.1 Scope:

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
31
 This work shall consist of construction of reinforced or dowel jointed or Plain
CementConcrete Pavement.
 PQC in accordance with the lines, grades, camber and thickness as shown in the
drawings.
14.2 References:
 MoRT&H specifications clause No: 602, IRC 15 – 2011 and technical
specification of contract.
14.3 Equipments:
 Batching plant, Wheel loader, transit mixers, needle vibrator and screed vibrator,
concrete - power saw, and levelling floats.
14.4 Tools:
 Floor Form, Jacks, Steel pegs, and measuring tape.
14.5 Materials:
 Cement:The cement to be used in the works shall be Ordinary Portland Cement
of 43/53 grade conforming to IS: 8112/ IS: 12269, Portland Pozzolana Cement
conforming to IS: 1489.
 Admixtures: The admixtures shall confirm to IS 6925 and IS 9103 shall improve
the workability of concrete or extension of setting time and they will not have any
effect on the properties of concrete. The performance of these admixtures will be
proved both on laboratory trials and in trial paving works. The admixtures
containing calcium chloride shall not be used
 Fly ash:When ordinary Portland cement is used the quantity of cement shall not
be less than 360kgs.In the case of fly ash grade-1(asperIS 3812) is blended at
site as part replacement of cement the quantity of fly ash shall be up to 20% by
weight of cementious material and the quantity of OPC in such a blend shall not
be less than 310kg/cum..
 Aggregates: The aggregates shall be of crushed stone or naturally available
confirming to IS 383. The coarse aggregate shall be clean, hard, strong, dense
and durable of crushed stone, for pavements the size and gradation and physical
properties of mix will be as per the technical specifications of pavements quality
concrete. The fine aggregate shall be of clean natural sand or crushed stone
sand or combination of both. These shall be free from clay, shale, loam, mica and
other organic matter

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
32
 Water: Water used for mixing and curing of concrete shall be free from oil, salt,
acid and other substances, which are harmful to concrete.
 Mild steel bars for dowel and tie bars: Dowel bars shall confirm to S 240 grade
and tie bars to Fe 500 of IS:1786-2008.
 Joint sealing compound: This shall be hot poured Elastomeric type as per
AASHTOM-282 or cold poured Polysulphide type as per BS 5212part2 having
flexibility, resistance to age hardening and durability.
 Separation membrane: A separation membrane of impermeable plastic
sheeting 125microns thick shallbe provided between the concrete slab and sub-
base by nailing with concrete nails to the lower layer. Where overlap is necessary
the same shall be at least300mm.
14.6 Procedure:
a) Mix:
 The mix shall be designed as per IS 10262 . The design shall be based on the
flexural strength of concrete.
 The water content shall be minimum required to provide workability for full
compaction of the concrete to the required density. The maximum free water
cement ratio shall be 0.5.
 The mix shall be proportioned to give an average strength at 28 days exceeding
the specified strength (4.5Mpa) by 1.65 times the standard deviation calculated
from the flexural strength of the first 30 beams casted during the trial length and
the job control test beams (during the actual execution).
 The workability requirements at the batching plant and at site shall be established
by slump tests while doing trial length. The ratio of 7 days strength to 28 days
strength shall be maintained, by testing pairs of beams and cubes batch wise for
at least six batches of trial mix.
b) Mixing:
 The materials shall be mixed in a mechanized batching plant consisting air-
conditioned decentralized control cabin, minimum 4bins, weigh hoppers, separate
scales for cement, fine and coarse aggregate with weighing balances calibrated,
aggregates being proportioned by automatic weighing devices using load cells.
 The concrete ingredients shall be mixed thoroughly by a mixer with automatic
timing/alarm device to mix and discharge (in case of failure of timing/alarm device

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
33
concrete shall be mixed as per Manufacturer’s recommendations) capable of
mixing to get a homogenous mix without being segregated while discharge.

c) Joints:
 The location and type of joint shall be as shown in the drawings:
i) Contraction Joints
 Transverse joints shall be contraction and expansion joints, cut with mechanical
saw and could start as early as 6-8 hours, i.e. initial hardening of concrete, after
laying. The contraction joints shall consist of mechanical sawn joint groove, 3 to
5mm wide and 1/4to 1/3 depth of the slab. The expansion joints shall consist of a
joint filler board positioned vertically with the prefabricated assemblies along the
line of joint.
ii) Dowel bars:
 The dowel bars shall be mild steel with details and dimensions as indicated in the
drawings. Unless otherwise shown in the drawings the dowel bars shall be
positioned at the mid depths of the slab with suitable tools/means within +/-20mm
tolerances. The dowel bars shall be covered with plastic sheath for at least 2/3rd
from one end for contraction joint, and ½ length +50mm for expansion joint. For
expansion joints, a closely fitting cap of 100mm long shall be provided at the
sheath end. To block the entry of cement slurry between dowels and cap a
compressible sponge may be used.
 The dowel bars shall be supported on cradles / chairs in pre-fabricated joint
assemblies positioned prior to the construction of slab or mechanically inserted
with vibration into the plastic concrete by a method which ensures correct
placement of the bars besides full re-compaction of the concrete around the
dowel bars.
iii) Longitudinal Joints
 The longitudinal joints shall be saw cut as shown in the drawings. A groove of
1/3rd the depth of the slab may be cut after the final set of the concrete. The tie
bars shall be deformed steel bars of 415 Mpa complying to IS 1786-2008. Tie
bars shall be painted with bituminous paint for 75mm at the both ends and
positioned with suitable tools/means.
 Tie bars shall be placed within the middle third of the slab depth.
 Tie bars in the longitudinal joints shall be made up into rigid assemblies with
adequate supports to remain firmly in position during the construction of slab.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
34
iv) Construction Joints:
 Transverse construction joints shall be placed whenever concreting is completed
for the day’s work or is suspended for more than 30 minutes. These shall be
provided at regular location of contraction joints using dowel bars as stated
above. All transverse and longitudinal joints of slab shall be sealed using
sealants, after 14days of construction, but prior to allowing the traffic ply on the
new construction.

d) Separation membrane:
 A separation membrane of impermeable plastic sheeting 125 microns thick shall
lay between the concrete slab and the sub base by nailing with concrete nails to
the lower layer. Wherever overlap is necessary, the same shall be laid by at least
300mm. Before placing the separation membrane the sub-base shall be swept
clean of all extraneous materials using high pressure water jetting or compressed
air.
e) Construction by fixed form:
 This shall consist of straight side forms made of steel of thickness not less than
5mmand of minimum 3000mm length. These shall have a depth equal to the
prescribed thickness of the pavement. These forms shall be straight and free
from bends and warps. Side forms shall be of sufficient rigidity in the form and in
the interlocking connection with adjoining form such that springing will not occur
under the weight of the sub grade and paving equipment or from pressure of
concrete.
 The vibrators for concreting shall be either surface pan type or internal type with
immersed tube or multiple spuds. The surface vibrators shall have a frequency
not less than3500 impulse per minute and the internal type vibrators shall have
frequency more than5000 impulse per minute.
f) Trial length:
 A trial length of 50m shall be made for the full width of the pavement, by involving
at least one transverse construction joint involving hardened concrete and freshly
lay concrete.
 After the side forms are removed, edges of slabs shall be corrected wherever
irregularities have occurred by using fine concrete consisting 1:3 ratio of cement
to fine chips and aggregate.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
35
 After the final regulation of the slab and before the application of curing
membrane, the surface of the concrete shall be brush-textured at right angles to
the longitudinal axis.
 The wire brush used for this purpose shall be made of 32 gauge type wired
grouped together in tufts at 10mm centres and of width not less than 450mm.
 The total time taken from addition of water to the mix, until the completion of
surface finishing and texturing shall not exceed 120minutes when the concrete
temperature is less than 25˚C and 90minutes when the temperature of concrete
is between 25˚C-30˚C.
 Immediately after the surface texturing, the surface and sides shall be cured by
application of curing compound, which hardens in to impervious film with the help
of mechanical sprayer. The curing compound shall have a water retention
efficiency of90%. After 3hours, the pavement shall be covered with moist Hessian
cloth or pond with Water for at least a period of 14 days.

g) Joints sealing:
 When saw cuts joints are adopted in construction, they are providedas per width
specified in the drawings, and is widened subsequently by sawing before sealing,
and the width and depth are controlled by gauges. When sealants are applied, an
appropriate primer is used, as recommended by the manufacturer and is applied
in accordance with their requirements. The sealant shall be applied within the
minimum and maximum drying time of the primer recommended byte
manufacturer. Before sealing, the temporary seal provided for blocking the
ingressive dirt, soil, etc. should be removed. A highly compressible heat resistant
paper backedde-bonding strip as shown in drawing shall be inserted in the
groove to serve the purpose of breaking the bond between sealant and the
bottom of the groove and to plug the joint groove, so that the sealant may not
leak through the cracks.
 The road may be opened for regular traffic after completion of curing period and
after sealing of joints.

h) Sand Patch Test (for measuring the texture depth):


 The surface to be tested shall be dried; any extraneous mortar and loose material
shall be removed and swept clean, using a wire brush at right angles and parallel

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
36
to the carriageway. A cylindrical container of 25ml capacity shall be filled with
sand passing
 300microns sieve and retained on 150microns sieve, compacted by tapping the
base and excess sand stroked off to level with the top of cylinder. Then the sand
shall be poured on the surface to be tested into a heap and spread with the help
of flat wooden disc of 64mm diameter of 1.5mm thick, with its face kept flat, in a
circular motion, so that the sand is spread into a circular patch, with the surface
depressions filled with sand to the level of peaks.
 The diameter of the patch shall be measured to the nearest 5mm. The texture
depth of concrete shall be calculated as follows:
 Texture depth in mm = 31000/ D2
 Where, ‘D’ is the diameter of the patch.
 Five such texture depth tests shall be taken along the diagonal line across the
lane width at least 2m apart, between 50m points along the road. No
measurement shall be taken within the 300mm of longitudinal edges of the slab
constructed in one pass.
14.7 SafetyMeasures:
 All the transit mixers shall be provided with reverse horns.
 All exit points of the transit mixers shall be marked with safety cones and caution
boards.
 Flagman shall be provided at all exit points of the trucks /tippers.
 The speed of vehicles plying in the work shall be restricted to 30kmph maximum.
 Leveling staff shall be made of wood/fiber.
 Any local labour if working in the job shall be screened and trained.
 Adequate area lighting in case of night work shall be ensured.
 Proper PPEs viz. Shoes, Safety Jackets etc. shall be used.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
37
WMS / 15
METHOD STATEMENT FOR LAYOUT & BASE PREPARATION OF
STRUCTURES(ROB/CULVERTS/ BRIDGES)
15.1 Scope:
 This work shall consist of Layout and base preparation of ROB/ Culverts/ Bridges
in line with the approved GFC drawings.

15.2 Reference:
 MoRT&H specifications.

15.3 Equipments:
 Total station, Auto level, levelling staff, Excavator.

15.4 Tools:
 Measuring tape, crow bar, spade, Line rope, Lime powder, Pegs, nails, paint etc.

15.5 Procedure:
 The Layout coordinates are noted from the GFC and marked on the ground, after
cleaning the site.
 Excavation is done up to required level as mentioned in the GFC.
 After attaining the level are checked with respect to the drawing dimensions.
 Avoid side cutting in case of side falling. Loose materials are removed
completely; layout is done for laying PCC.
 Before laying PCC the surface can be sprinkled with water to prevent water flow
between concrete to earth.

15.6 Safety Measures:


 All safety measures shall be as per approved EHS Plan.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
38
WMS / 16
METHOD STATEMENT FOR PIPE CULVERTS
16.1 Scope:
 To construct a pipe culvert .
16.2 References:
 MoRT&H specification of Clause 2900, 1006, 1700, IS: 383, IRC: SP13 and
technical specification of Contract.
16.3 Equipments:
 Batching plant & Transit mixture, Excavator, Hand rammer, vibrator, Trailer/Open
body truck, Water tanker, Hydra crane/Tripod/JCB, plate compactor, chipping
machine.
16.4 Tools:
 Measuring Tape, Crow bar, spade, chisel, line rope, lime powder, packing
material etc.
16.5 Materials:
 Np-4 Hume pipes of required diameter as in GFC, granular material, concrete,
cement mortar.

16.6 Procedure:
 Layout is done as per method statement “Layout & Base preparation for
Structures”.
 Excavation is done for pipe bed and Head wall.
 PCC done for head wall fixing the flow for 1st lift for head wall is completed.
 After deshuttering the gap between headwall and pipe bed is filled with selected
material and compacted.
 Bed shall be preparedand done as per level and slope mentioned in GFC.
 In case of widening groove is cut around the existing pipe in the existing headwall
to joint the new pipe with a cast in situ collar.
 Pipes are laid with the help of crane and are aligned as per line & level. Packing
blocks shall be used for alignment.
 The pipe joints are prepared as mentioned in the drawing. It is to be cured with
moist hessian cloth.
 For head wall shuttering to be fixed and concreted to the required height of wall.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
39
 Back filling to be done with selected material with compaction with suitable
compactor. back filling to be done with approved material.
 Protection work to be taken after completion of the filling work.

16.7 Safety Measures:


 All safety precautionary measures shall be taken as stated below:
 Signboards shall be placed along the right hand side on increasing chainage at
every 500 meters i.e. “KEEP RIGHT WORK IN PROGRESS”, GO SLOW WORK
IN PROGRESS”.
 Moveable signboards shall be place at area where heavy machineries and survey
works being carried out. The movement of machines and lorries at these areas
shall be controlled by flagman’s Signboards such as “CAUTION MAN AT WORK
GO SLOW”, “CAUTION GO SLOW WORK IN PROGRESS”.

WMS / 17
METHOD STATEMENT FOR FOUNDATION EXCAVATION
FORSTRUCTURES IN SOIL/ROCK
17.1 Scope:
 Excavation of foundation pit for any structure to accommodate the foundation
below ground level as mentioned in GFC drawings.
17.2 Reference:
 Section 304 of MoRT&H specification & Technical specification of contract.

17.3 Equipments:
 Excavators, Dumpers, Drilling machine, Total station, Auto level, staff, rock
breaker, and electric chipper, Dewatering pump etc.
17.4 Setting out:
 This is to be done as described in Method statement for setting out.
17.5 Procedure:

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
40
 Layout for excavation is decided basically on the type of soil and depth of
excavation area of marking should include the scope for width for side slope,
 Adequate space for fixing and removing of formwork, berm & sump for drainage
is to be provided.
 As per ground water table dewatering pumps is to be assessed and mobilized
before start of excavation.
 Excavation is done to required depth as indicated in the GFCdrawing.
 Adequate side slope is to be provided against collapse.Depending on the site
conditions, berm, shoring and strutting shall be carried out.
 Ramp is to be provided if depth of excavation is more. If seepage water is
encountered, drains around the PCC to be provided and should be continuously
pumped out. Beyond PCC areas a sump is to be made for collecting seepage
water.
 During PCC laying water level should not rise above the bottom of PCC till
concrete sets. In case of sand layers strutting arrangement to be done.
 The excavated earth should be removed from the edges of the pit.
 If rock is to be excavated, rock breaker is to be used, and the layout of
foundation to be checked time and again.
 Backfilling of excavated pit is to be done as mentioned in the drawing &
MoRT&H.
17.6 Safety Measures:
 The area shall be restricted from public entrance
 All trucks shall be provided with reverse horns/lights
 Wherever required, Flagman shall be provided.
 Blasting shall be done at pre-fixed hours.
 All persons including the workmen shall be excluded from the blasting area at
least
 10minutes before blasting.
 Only licensed blaster shall be allowed to take out the blasting operations.
 During night work sufficient lighting shall be provided.
 The excavated pits shall be properly barricaded.
 Proper access shall be provided to go down to pit excavated for structures.
 Road working area shall be demarcated using Sand bags.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
41
 All workmen at work area shall wear PPE’s and reflective jackets.

WMS / 18
METHOD STATEMENT FOR FORMWORK, REINFORCEMENT &
CONCRETING IN STRUCTURAL WORK
18.1 Scope:
 Form work: This work shall consists of furnishing and fixing of form
work(shuttering) of approved quality for cast- in- situ / pre-cast/ pre-stressed plain
or reinforced concrete with necessary props, staging, centring, scaffolding and
any temporary construction required for their support.
 Reinforcement: This work shall consist of furnishing and placing of high yield
strength deformed bars of the shape and dimensions as shown in approved
drawings.
 Concrete: This work shall consist of furnishing and placing of plain or reinforced
concrete of all grades with 40 or 20mm downgraded aggregates as defined in
technical specifications of contract, machine mixed and mechanically vibrated to
the required level, slope, etc. as per approved drawings.
18.2 References:
 MoRT&H specifications clause No: 1000, 1500, 1600, 1700 and technical
Specification of Contract.
18.3 Materials:
 The source of materials (for cement,flyash, coarse aggregate, fine aggregate,
water, admixture, reinforcement steel) shall be identified as per specification.
 Cement: The cement to be used in the works shall be Ordinary Portland Cement
of43/53 grade confirming to IS 8112/ IS 12269, Ordinary Portland Cement with
Fly Ash or PPC Cement. The manufacturer test certificate shall be furnished, and
cement shall be stored as per IS 4082.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
42
 Flyash: Flyash shall confirm to IS: 3812(Part-1)-2003, and shall be stored as per
IS 4082.
 Water: The water to be used shall be as per clause 1010 of MoRT&H
specification and as per Clause 302.4 of IRC: 21.
 Coarse aggregate: Coarse aggregate shall confirm to IS 383, when tested in
accordance to IS 2386 parts 1 to 8. The grading of coarse aggregate shall
confirm to table 1000-1 of Mo RT&H specification.
 Fine aggregate: Fine aggregate shall consist of clean, hard, strong, dense, and
durable pieces of crushed stone or natural sand or a combination of both. All fine
aggregates shall confirm to IS 383, when tested in accordance to IS 2386 parts 1
to 8. The grading shall confirm to table 1000-2 of MOST specification.
 Admixtures: Admixtures shall be high water reducing agents, retarders, super-
plasticizers, airentrainers or a combination confirming to the requirements of
IS9103. The manufacturer test certificate shall be obtained and submitted to
Concessionaire. The appropriate dosage of admixture shall be determined at the
mix design stage. The admixture-cement compatibility shall be tested for every
type, grade or source of cement.
 Reinforcement: For plain or reinforced cement concrete the reinforcement shall
be grade 500 confirming to IS: 1786- 2008, HYSD bars. The steel supplied with
test certificate shall be assembled in accordance with approved drawings and
shall ensure storing to avoid deterioration and corrosion.
18.4 Equipment:
 Batching plant, Wheel loader, Boom placer, Static concrete pump, Crane, crane
bucket, transit mixers, trailers, Bar bending and shearing machine,Auto level with
staff etc.
18.5 Tools:
 Measuring tape, plumb bob, Line rope etc.

18.6 Procedure:

a) Formwork:
 The formwork shall provide a smooth finish of uniform texture and appearance.
 Ensuring necessary care will be taken, the formwork in true to line, levels,
plumbed, rigid, adequately braced both horizontally and vertically. Form joints

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
43
shall be minimized as much shall be tight and shall not permit any leakage of
slurry from concrete.
 Required formwork shall be made out of plywood/ steel shutters to suit the site
 Conditions. Formwork materials shall be rigid, even surface, and sufficiently
strong to prevent deformation during concrete. Releasing agents such as diesel
mixed with grease, shuttering oil, etc. shall be applied before fixing formwork, and
shall not allowed to come into contact with any reinforcement or prestressing
tendons and anchorages. The formwork shall be cleaned carefully, dried and
releasing agents shall be applied before re-use.
 The formwork shall be so removed as not to cause any damage to the concrete.
 Formwork shall be gradually and uniformly lowered so as the concrete to take
stresses due to its own weight uniformly and gradually to avoid any shock or
vibration.
 Before re-use all components of formwork shall be examined for damage and
damage pieces shall be rectified. Before re-use all components shall be cleaned
of deposits of soils, concrete or other unwanted materials. Threaded parts shall
be oiled after cleaning.
b) Reinforcement Steel:
 Bar bending schedule shall be prepared strictly as per approved drawings, and
reinforcement steel shall be cut and bent as per approved bar bending schedule.
Bars shall be bent cold to the specified shape and dimensions, using a proper bar
bender, operated by hand or power to obtain correct radius of bends and shape.
 Reinforcement bars shall be placed accurately in position as shown in the
drawings.
 The bars, crossing one another shall be tied together at every intersection with
binding wire (Dia of binding wire shall not be less than 1mm) where the spacing is
more than150mm and at alternate intersection where the spacing of bars is less
than 150mm,to make the skeleton of reinforcement rigid such that it does not get
displaced during placing.
 Spacer bars at approx. 2m intervals shall separate layers of reinforcement. Cover
blocks of thickness equal to the specified cover shall be placed between
formwork and bars made of concrete/ cement mortar of specified grade of
concrete/ strength as those of the member.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
44
 Necessary stays, blocks, chairs, spacers, hangers, etc. or other subsidiary
reinforcement shall be provided to fix the reinforcement firmly in its correct
position.
 Laps shall be staggered.
c) Concrete:
 The grades of concrete shall be as specified in the drawings/ contract. Necessary
mix designs shall be submitted to Concessionaire. The mix design of concrete
shall be as per clause 1700 of MoRT&H specifications / IS456:2000 / IS10262 /
IS SP23. The workability of concrete when determined by slump cone test shall
be 75-125mm.
d) Mixing:
 The mixing of concrete shall be done in batch type concrete mixer or by concrete
batching and mixing plant. All measuring devices shall be maintained in a clean
and serviceable condition. Its accuracy shall be checked periodically.
 Mixing of concrete shall be continued till the individual particle of coarse
aggregate shows complete coating of mortar containing its proportionate amount
of cement.
 Corrections in water and aggregate with respect to moisture present in the
Aggregates shall be done on day-to-day basis.
 The mixing shall also be done in 10/7 mixers at site and weigh batchers shall be
used for the weighment of CA and FA. The aggregate shall be stored on
prepared surface. Different sizes of aggregates shall be segregated properly by
partitions.
e) Transportation and placing:
 Concrete shall be transported and placed as near as practicable to its final
position, so that no contamination, segregation or loss of its constituent materials
takes place.
 Concrete from batching plants shall be transported by scoop tippers or transit
mixers.
 Concrete shall be placed in horizontal layers to a compacted layer not
exceeding450mm. Concrete when deposited shall have a temperature neither
less than 5*C nor more than 40*C.
f) Compaction:

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
45
 The concrete shall be compacted within 30minutes of its discharge from the
mixer.
 To maintain required slump, it is necessary to add retarding/plasticising
admixtures.
 This shall be controlled by taking slump at batching plant and site.
 Concrete shall be thoroughly compacted with vibrators or by other means
 Where immersion vibrators are used contact with reinforcement and all inserts
shall be avoided. Standby vibrators in serviceable conditions shall be kept at site
so that they can be used in the event of breakdowns.

g) Construction joints:
 Construction joints shall be minimised as far as possible. The old surface shall be
thoroughly cleaned and soaked with water. Standing water shall be removed and
surface shall be wetted with neat cement slurry shortly before placing of fresh
concrete and shall be thoroughly compacted.
 For a vertical construction joint, a supporting board shall be fixed at
predetermined position and shall be properly stayed to prevent displacement or
bulging when concrete is compacted against it. Concreting shall be continued
right up to the board.
h) Curing:
 Exposed surfaces of concrete shall be kept continuously in a damp or wet
condition by ponding or by covering with a layer of sacks, canvas, Hessian or by
similar materials and shall be kept constantly wet at least for a period of 7-14
days. Curing compounds may also be used.

i) Finishing:
 Immediately after removal of forms, exposed tie rods or bolts, if any, as far as
possible shall be removed, or if necessary, shall be cut inside the concrete
member to a depth at least 50mm below surface of concrete and the resulting
hole shall be filled by fresh cement mortar.
18.7 Safety Measures:
 All safety measures shall be as per approved EHS Plan.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
46
WMS / 19
METHODSTATEMENT FOR BACK FILLING IN STRUCTURES

19.1 Scope:
 This work shall consist of back filling of trenches behind the abutment, wing wall,
return wall, Box culvert & pipe culvert once completed. The filter media shall be
provided where weep holes are provided.
19.2 References:
 MoRT&H specifications clause 305.2&No: 2900, 2504.2.2 and technical
specification of contract.

19.3 Equipments:
 Dumpers, wheel Loader, roller, plate compactors & water tanker.

19.4 Tools:
 Measuring Tape, Crowbar, spade & line rope etc.

19.5 Procedure:
a) Back filling of Pipe culverts:

 After the pipe installation has been completed and approved,


 The backfill material shall be approved material free from boulders, large roots,
other vegetable matters.
 The back fill material shall be placed in layers and thoroughly consolidated or
compacted.
 The thickness of the layer shall not exceed 250mm.
 The minimum thickness of the material for cushion above the top of pipe shall be
300mm and shall be thoroughly consolidated.
 Filling of trench shall be carried out simultaneously on both sides of the pipe in
such a manner that the unequal pressure do not occur.
 Particular care being taken to thoroughly consolidate the materials under the
haunches of the pipe.
 Pneumatic or light mechanical tamping equipment can be used.
 Above the cushion layer, approved Borrow Area material shall be placed and
compacted with 8-10tone rollers to the required density of 95% for embankment
& 97% for sub grade. The thickness of layer shall be 250mm.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
47
b) Back filling of Box culverts:
 The additional excavated area for work space up to raft level shall be filled with
approved backfill material and thoroughly consolidated.
 The Backfill material shall be approved backfill material as per MORT&H
.
 The backfill material shall be filled in layers & the thickness of the compacted
layer shall be 200 mm.
 The rolling shall be carried out to achieve the required density.

c) Back filling of Box Minor bridges, MNB, MJB, ROB & Return walls:
 The filter media shall be provided behind the abutment, wing wall, return wall and
where weep holes are provided.
 The width of the filter media(600mm) shall be as per drawing.
 The material for the filter shall consist of sand, gravel, stone or crusher sand to
prevent escape of the embankment material through the voids of weep holes in
abutments as well as to allow free movement of water without creating any uplift
head.
 The gradation of the filter material shall satisfy the requirements of clause
2504.2.2 of MoRT&H. The filter shall be compacted to a firm condition.
 The filter media shall be provided 300mm below the bottom weep hole of the
abutment and up to the top of Sub grade.
 The back fill soil shall be approved Embankment & sub grade material as per
clause 305.2 of MoRT&H.
 The backfill soil shall be clean, free from boulders, large roots, excessive
amounts of sods or other vegetable matter and lumps.
 The backfilling shall be done in layers and thoroughly compacted to the required
density.

19.6 Safety Measures:


 All trucks and tankers etc. Shall be provided with reverse horns.
 All exit points of the trucks/ tippers shall be marked with safety cones and caution
boards.
 Flagman shall be provided at all exit of trucks/tippers.
 The speed of vehicles in the work shall be restricted to 30 Kmph. Maximum.
 Proper PPEs viz, shoes, safety Jackets etc. Shall be used.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
48
 Where it is necessary to close the traffic on the existing highway for construction
and divert the traffic on to an alternative route. The diversion road shall have
fluent geometry and maintained in traffic worthy condition such that traffic can
safely negotiate.

WMS / 20
METHODOLOGY FOR INSTALLATION OF ELASTOMERIC BEARING

20.1 Scope:
 The work shall consist of fixing of elastomeric bridge bearings in position as per
details shown in drawings.

20.2 References:
 MoRT&H specifications clause no 2005 and Technical specifications of contract.

20.3 Equipments:
 Total station, Auto level, leveling staff, spirit level, Air compressor, etc.

20.4 Tools:
 Measuring steel tape, line rope, wire brush, and plumb bob.

20.5 Materials:
 Elastomeric bearings, Non shrink grout, adhesive material.

20.6 Procedure:

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
49
 Water accumulated in the groove meant for bearing to be removed and the
surface made dry.
 Level of the surface to be checked. The derbies to be removed, if there is any
undulation form that should be chipped off. The surface is to be cleaned with wire
brush and blown away using compressed air.
 The c/c marked on both the groove and the bearing, a layer of adhesive of 20
mm thick is applied on the surface. After 20 minutes of application of adhesive
bearing is placed on the centerline exactly, and after checking the position it is
pressed a little and made it level perfectly.
 Level to be checked with the use of spirit level. After it being horizontal non shrink
grout to be applied around the bearing to arrest the displacement.
 Grout can be cured for 7 days using wet hessian cloth.

20.7 Safety Measures:


 Proper PPEs viz, shoes, safety Jackets etc. Shall be used.
 Special precautions for working at heights shall be taken.
 Special precautions for lifting shall be taken.
 Proper barricading of work area.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
50
WMS / 21
METHODOLOGY FOR INSTALLATION OF POT / PTFE BEARING
21.1 Scope:
 The work shall consist of fixing the POT / PTFE bearings in position as per the
details shown in Drawings.

21.2 References:
 MoRT&H specifications clause no 2006 and Technical specifications of contract.

21.3 Equipment:
 Total station, Auto level, leveling staff, spirit level, Air compressor, etc….

21.4 Tools:
 Measuring steel tape, line rope, wire brush, and plumb bob.

21.5 Materials:
 Elastomeric bearings, Non shrink grout, adhesive material.

21.6 Procedure:
 Pedestals are cast with the sleeves left for accommodation of the legs of bearing.
 Diameter & depth of pockets to be checked. Depth should be as mentioned in the
drawing.
 The pockets are to be cleaned using compressed air, it is to be filled with water &
left for 24 hours.
 Center lines are to be marked on the pedestal also center line to be punched on
the bearing also removing the packing, central lines, bolts to be checked all the
bolts to be tightened if loose.
 Before placing the bearing packing steel plates to be kept for leveling and make
the bearing move since it is heavy tools to be used (wedge & stick)to be used to
lifting & moving the bearing.
 Water from the pocket to be removed by using a siphon pipe after pocket being
dried, the bearing is placed on the position.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
51
 The lugs inside the pocket should not touch any wall. Using wedge & stick the
bearing should be positioned in the center line as mentioned in the drawing.
 Directions are mentioned on the bearing.it should be aligned along the traffic line.
 Using packing it should be leveled. After thorough checking alignment & level
forms to be fixed for grouting.
 The pockets are grouted using non-shrink grout up to top of the bottom plate of
bearing.it is to be cured using wet hessian cloth.
 Lugs of the top plate to be kept as it is.it has to be embedded in the concrete
while pouring in the diaphragm in case of cast in situ.
Pre cast girders./Steel girder
 In case of pre-cast girders (continuous slab), the girders are placed on the
pedestal and supported on wooden sleepers temporarily.
 Then the bearing placed on the location and grouted as described. The top lugs
to be embedded in the diaphragm Concrete.
 After the concrete being set, packing (wooden sleepers) to be removed by raising
the slab by 2-5 mm using hydraulic jacks. On releasing the jacks the diaphragm
rests on the bearing. Now the bearing is loaded fully.
21.7 Safety Measures:
 Proper PPEs viz, shoes, safety Jackets etc. Shall be used.
 Special precautions for working at heights shall be taken.
 Special precautions for lifting shall be taken.
 Proper barricading of work area.
 All safety measures shall be as per approved EHS Plan.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
52
WMS / 22
METHOD STATEMENT FOR ERECTION OF STEEL GIRDER IN ROB

22.1 Scope:
The object of this Method Statement is to lay down a procedure for transportation
erection of I-Girders as per IRC code &MoRT& H Specifications for Road and
Bridge works (fifth Revision).
This scope of method statement is as follows:
 Transporting the Steel Girders from stock Yard to the ROB location.
 Erection of Steel Girders in position with bearing fixing and grouting.
 Preparation for Deck slab Construction.

22.2 Reference documents:


 MoRT&H Specifications for Road and Bridge works published by Indian Roads
Congress, New Delhi, (Fifth Revision).
 IS: 2502-1963: Code of practice for bending and fixing of bars for concrete
reinforcement.

22.3 Machinery& Equipment:


 Total Station/Auto level, Crane, Trailer, Welding Machine, Lifting Tackles,

22.4 Tools:
 Measuring steel tape, Line dory, Plumb bob, and Sprit level.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
53
22.5 Procedure:
The following sequences of activities are narrated as under.
a) Transportation of steel Girders form stock Yard to Bridge
b) Installation of Bearing (Already Covered in separate method statement)
c) Erection of steel Girders
d) Deck Slab Casting

a) Transporting The Steel Girders To Bridge


 The ground shall be compacted all around the stacking yard to facilitate the
movement of crane and trailer, so that they are not stuck while movement after
the girder is loaded.
 The shifting of girder shall be primarily done in the day time. However based on
the site requirement it shall be transported in the night hours too.
 Before the girder is loaded on to the trailer for transportation the following checks
shall be done for the safe and uninterrupted movement of the girder till it reaches
the major bridge location.
a. The designated driver for the trailer is available.
b. The condition of the trailer to be checked before the girder is loaded.
c. The road at any point till the major bridge is not congested because of
traffic.
d. The safety personnel along with all safety measures are available.
 During transportation of girders, sudden jerks by trailer shall be avoided.
 Steel girder will be received in pieces at site from fabrication yard and will be
unloaded at prepared compacted base nearby to the site for further assembly
activity.
 If required the girder segments shall be stacked at bridge site on wooden
Sleepers for any subjected condition or unavoidable condition of site.
 The steel girders, which are to be shifted to the bridge are either stacked within
the reach of the travelling of crane or nearby suitable place.
 The steel girder will be aligned before tightening of bolts/riveting for final
assembling as per approved drawings.
 Site & QA team will check the all dimension/alignment and other design
parameter as per approved drawing before lifting for erection on span.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
54
 Permission for train traffic block period from Railway department for erection of
girder on track’s span will be obtained. This is for safe working in track area.
 After the confirmation of train traffic block period by railway department the steel
girders will be shifted to the location.
 The ground shall be compacted all around the track span, nearby the abutment
area to facilitate the movement of crane and trailer, so that they are not stuck
while movement after the receiving the girder at erection location.
 The slings/D shackles shall be inspected in line with load applications.
 The ‘D’ Shackle shall be tied with wire rope sling with the lifting hook properly.
 Necessary supports shall be used to support the girders for lateral stability
against overturning.
 The guide rope shall be tied to the I-Girder to avoid oscillation.
 The erection foreman shall co-ordinate with crane operators by means of hand
signals or other established methods.
 The girder shall be lifted slowly by using crane of suitablecapacities and placed
on the trailer.
 The sling and ‘D’ shackle shall be removed.

b) Installation of Bearing(Refer Separate Method Statement)

 Once the bearings are received from the approved supplier, it shall be ensured
that they are accompanied by all relevant test certificates.
 The bearings shall be stored in such a place that they remain free from dust.
 The bearing installation shall be done when the arrangement for girder erection is
being organized.
 The grout underneath the bearing shall be allowed to gain strength equal to
strength of the girder, before erections of the girder over them are taken up.

c) Erection of Steel Girders


 The ground shall be compacted all around the structure to facilitate the crane
movement.
 The slings & D shackles of suitable capacity shall be used for handling the girders
during erection.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
55
 Adequate clearance for crane movement shall be maintained. Normally two
cranes shall be engaged. If possible single crane of higher capacity may also be
used.
 The sequence of girder erection shall be followed as indicated in the drawings.
 After erection of the Steel girders, the girders shall be braced as per the approved
drawings.
 The level of the ground shall be maintained in such a way that no crane at the
time of combined handling has to travel in an undulated ground profile during its
forward/backward travel.
 The exact location on the bearing shall be marked so that the girder is placed
perfectly over it.
 Once the girder is placed at its designated location over the bearing, the gap
between the girder and the bearing is grouted with non-shrinkage cement grout.
 Proper access to the top of the pier-cap shall be made available.
 The working space for the workmen, when they align & place the girder over the
bearing shall be protected, so that a sense of security against the working at
height is ensured for the workers working at the pier cap level.
 Once the girder is erected over the bearing, as a precautionary measure, lateral
support shall be provided from the pier-cap against any lateral tilt.
 After the erection is completed of girder the same girder and fixed bearing will be
fitted and tightened/bolted properly for further deck slab construction activity.

d) Deck Slab Casting


 The safety net shall be fixed.
 The temporary brackets on outer girder for shutter supporting shall be erected.
 The temporary support in between the girders for deck shall be erected.
 Conventional slab shuttering shall be provided for deck slab concreting.
 Reinforcement steel shall be fixed.
 In-situ concrete shall be done.
 Brackets in cantilever area and conventional slab shuttering shall be removed
after 7 days.

22.6 Safety Measures:

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
56
 Proper PPEs viz, shoes, safety Jackets, safety belt etc. Shall be used.
 Special precautions for working at heights shall be taken.
 Special precautions for lifting shall be taken.
 Proper barricading of work area.

WMS / 23
METHODOLOGY FOR APPLICATION OF WATER PROOFING
MEMBRANE INSTEAD OF MASTIC ASPHALT ON CONCRETE BRIDGE
DECKS

23.1 Scope:
 This work shall consist of furnishing and laying of 4mm thick water proofing
membrane on concrete bridge decks for water proofing.
23.2 Reference:
 Latest Specification and Product Technical Brochure.
23.3 Equipment’s:
 Gas Cylinder, trowel, wire brushes, Gas cutter, measuring tape, knife,
compressor, and wooden flat/PVC Pipe.
23.4 Materials:
 Water proofing membrane: Water proofing membrane consists of high strength
reinforcement in layers of heat resistant rubberized asphalt. The reinforcement
and rubberized asphalt interact to form a tough membrane that remains flexible
through a wide range of temperature and movements. The tacky rubberized
asphalt assures quick adhesion to the deck.
 Primer: It is a special primer which affords a good adhesion of the membrane to
the concrete deck. It provides a tight water seal and the same time allows gases
in the concrete to escape.
23.5 Procedure:

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
57
 The surface of the concrete bridge deck shall be water proofed and cleaned
completely.
 Make sure the bridge deck shall be free from dust, oil, protrusions, ribs, hooks,
and nails, rebar’s etc.
 Heat the surface to release the moisture if any from the bridge deck.
 If any protrusions visible on the bridge deck, shall be cut completely to avoid
puncture to the asphalt seal membrane.
 Apply a coat of primer on the bridge deck surface at required rate.
 The water proofing membrane rolls shall be lined up and spread open over the
deck area with proper side laps and end laps without any wrinkles.
 The membrane shall be rolled back without changing its orientation.
 The roll shall be unrolled once again and torch the underside with the help of
LPG Gas cylinder evenly and sufficiently to cause surface melting.
 The membrane shall be pressed with the help of wooden flat/PVC Pipe from top
of the membrane from inside to outside ensuring that there is no entrapped air
and proper adhesion to the deck.
 The overlap joints shall be heated from the top to produce a thin bead of molten
bitumen as the seam, should be smoothened out with a hot travel, ensuring a
proper joint.
 Make sure that the overlapping of the subsequent rolls shall as per the
specification.
 Repeat the same procedure for further layers and make a firm, water proof
surface.
 Prior to allowing the traffic over water proofing membrane, required layer of BC
shall be laid.
23.6 Safety Measures:
 All exit points shall be marked with safety cones and caution boards.
 Flagman shall be provided at all exits.
 Use of protective cloths, rubber gloves a bearing cream is recommended.
 Proper PPEs viz, shoes, safety Jackets etc. Shall be used.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
58
WMS / 24
METHODOLOGY FOR INSTALLATION OF STRIP SEAL EXPANSION
JOINTS
24.1 Scope:
 To embed the fabricated mould in the concrete and fix the strip seal in the mould
for expansion joint location for structures as mentioned in the GFC.

24.2 References:
 MoRT&H specifications clause no 2607 and Technical specifications of contract.
 Installation manual / Procedure specified by the manufacturer.

24.3 Equipments:
 Pneumatic breaker, Auto level with staff, welding aids, compressor, bitumen
cutting machine, electric chipper, wire brush, Needle vibrators, spirit level.

24.4 Tools:
 Measuring steel tape, line rope.

24.5 Materials:
 Concrete, thermo cool, fabricated mould, strip seal, formwork, ISMB 100.

24.6 Procedure:
 Measuring to be done as per drawing from both sides of the c/c of joint on the
BC earlier laid. The BC is cut above the cutout area on the deck slab. Debris are
cleaned and removed.
 The cut out to be made as per drawing on each face of the deck slab. Thegap
below cutout between 2 slabs edges to be cleaned and kept free.
 The cut out surfaces to be cleaned with wire brush.
 The mould is jointed to required length as per drawing. The gap shall be
maintained as per drawing between the two pieces of mould by welding a
channel on the top of mould at an interval of 2.5 metre. The channel should
project minimum 600 mm each side of the joint.
 The lugs of the mould welded with channels to be placed in the prepared cut out
in position and level the assemble ranges from the channel. So that the top of
mould matches with the BC top exactly.
 The length of the mould is welded to the projected steel from the slab and
bridges to be provided along the mould in the cut out.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
59
 After perfect welding to the protected steel and newly provided bindered steel,
Thermo col is to be provided in the gap 40 mm or as mentioned in the drawing.
 The cut out is cleaned with compressed air. Concrete is poured carefully on both
sides of the thermo col so that the itis in position without any displacement.
 It is finished by matching to the top level of BC. It is cured with wet hessian
cloth .The strip seal is to be inserted in the groove of mould.

24.7 Safety Measures:

 All safety precautionary measures shall be taken as stated below:


 Moveable signboards shall be place at area where heavy machineries and
survey works being carried out.
 The movement of machines and lorries at these areas shall be controlled by
flagman’s Signboards such as “CAUTION MAN AT WORK GO SLOW”,
“CAUTION GO SLOW WORK IN PROGRESS”

WMS / 25
WORK METHOD STATEMENT FOR CONSTRUCTION OF MASTIC
ASPHALT WORK
25.1 Scope:
 This work shall consist of laying of 25mm thick Mastic Asphalt over bridge deck.

25.2 Reference:
 Clause no. 516 of MORT&H Specification
25.3 Equipments:
 Mastic cooker or any other suitable means for heating, Bitumen/ Emulsion
Sprayer, Tractor with compressor, Wheel Barrow, Water Tanker, Hand tools
Shovels, Wooden float, Wire brush, Steel scraper, Steel strip of 25mm thick,
thermometers, concrete nails, measuring tape, steel scale.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
60
 Materials :Bitumen shall be used for mastic asphalt as per 500-39 table
MORT&H& aggregate nominal size 13mm table500-40 of MORT&H
25.4 Procedure:

 The surface shall be thoroughly swept clean free from dust and foreign matter
using wire brush / steel scraper / tractor compressor. Laying shall be suspended
in case of moist surface, dust storm or when the shade temperature falls below
10º C.
 Tack coat of medium Setting Emulsion shall be applied to the prepared concrete
surface at the rate of 0.30-0.35 kg/sqm before laying Mastic Asphalt.
 Mastic mix shall be prepared in the mastic cooker or in any suitable means, for
lesser quantity of work, to the temperature not more than 210º C. Proportion of
aggregate, filler and bitumen shall be as per the approved mix design.
 Hot mastic mix shall be transported to the laying site by wheel borrow and spread
to the tacked surface using wooden floats. Laying shall be done in one coat at
temperature 170 to 210º C. 25mm thick steel strips will be used to get the uniform
thickness throughout. Any blow holes appeared to the surface shall be punctured
while the mix is hot and the surface is smoothened by further floating.
 All construction joints shall be made by warming existing mastic asphalt by the
application of an excess quantity of hot mastic mix which afterwards shall be
trimmed to get the smooth surface.
25.5 Safety Measures:
 All tippers/ tankers shall be provided with reverse horns
 Flagman shall be provided at all exit points of the trucks/tippers
 The speed of the vehicle playing in the work area shall be restricted to 40kmph
maximum
 Leveling staff shall be made of wood/fiber.
 If night work is to be carried out the area shall be sufficiently provided with
lighting.
 The tippers when being positioned in front of the paver shall be move very slowly
as per the directions given by the unloading supervisor.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
61
WMS / 26
METHOD STATEMENT FOR LAYING OFCEMENT CONCRETE KERB
FOR JUNCTIONS
26.1 Scope:
 This work shall consist of constructing cement concrete kerbs in the central
median and/or along the foot paths or separators in conformity with lines, levels
and dimensions as specified in the drawings.

26.2 References:
 MoRT&H specification of clause No: 408, Sec 1700 and Technical specification
of contract.

26.3 Equipments:
 Mechanized Kerb casting machine
 Batching plant
 Transit Mixer, Auto level with staff etc.

26.4 Tools:
 Measuring Tape, spade, string wire, winch, pegs, Aluminum square bar, Trowels
etc.

26.5 Procedure:

 The area, where kerb is laid shall be identified with respect to the drawing.
 Pegs & piano wire/string shall be fixed in line and level as shown in drawing, at
10 m interval.
 In curved portion the pegs shall be fixed at smaller intervals, say 5 m.
 The mechanized, sensor controlled Kerb Casting Machine shall be set properly
over the reference marks for the casting of the kerb.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
62
 The M20 grade concrete shall be used. The slump of concrete at site shall be
maintained between10-30mm.
 Required quantity of Concrete shall be brought from the batching plant in transit-
mixer to the site & shall be fed to the machine.
 The mechanized Kerb Casting Machine shall be operated and casted the kerb to
be checked for line and level along with casting.
 Laying of PCC foundation on the existing road only, (if found necessary).
 Finishing / touch up on surface shall be done manually (if required) to get the final
kerb within tolerance limit.
 Joint of end & middle portion of kerb shall be finished manually after completion
of concreting.
 Casting of cubes frequency shall be done as per clause 1716.2.4 of MoRT&H.
 The kerb thus cast shall be allowed to set & shall be cured with water or curing
compound accordingly.
 The kerb shall be cut at 5m intervals to introduce expansion joints. The cutting
process shall start once the concrete attains sufficient strength, which can able to
with stand during cutting operation with cutting machine. The Blade thickness
shall be 3 to 5mm.
 Manual casting of kerb shall be restored to where machine casting is not
possible. Shuttering and forms of proper size & shape shall be used for such
manual castings.
 All necessary Survey checks shall be conducted before and after kerb casting.
 Vertical and Horizontal tolerances with respect to true line and level shall be +/-
6mm.

26.6 Safety Measures:

 All the transit mixers shall be provided with reverse horns.


 All exit points of the transit mixers shall be marked with safety cones and caution
boards.
 Flagman shall be provided at all exit points of the trucks /tippers.
 The speed of vehicles plying in the work shall be restricted to 30kmph maximum.
 Leveling staff shall be made of wood/fiber.
 Any local labour if working in the job shall be screened and trained.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
63
 Adequate area lighting in case of night work shall be ensured.
 Proper PPEs viz. Shoes, Safety Jackets etc. shall be used.

WMS / 27
METHODOLOGY FOR KERB PAINT MARKINGFOR JUNCTIONS

27.1 Scope:
 The work shall consist of marking on kerb using the solvent based paint
meeting the requirements as shown in Drawings.

27.2 References:
 MoRT&H specifications clause no 803.3 and Technical specifications of
contract.

27.3 Tools:
 Measuring steel tape, wire/coir Brush, tins, other tools

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
64
27.4 Materials:
 Kerb marking paint shall be as per grade 1 of IS: 164 or as per approved
drawing.

27.5 Procedure:
 The traffic will be regulated by placing proper safety barricades/safety
cones/flag man in the area where the work has to be carried out.
 Ensure the Kerb surface shall be free from dust, grease, oil and all other
foreign matter.
 The Kerb surface shall be cleaned with wire brush and cotton waste prior
to application of primer.
 Apply a coat of approved primer on cleaned kerb surface and allow for
drying for min 4 hours.
 The paint shall be properly mixed prior to use.
 The surface should be thoroughly dry and free from moisture before
painting.
 After drying of primer apply a coat of solvent thinnable paint and allow for a
drying period of min 2 hours.
 The colour of the paint shall be yellow & black in median openings and
White & black in remaining portions as per the drawings. The width of strip
shall be 500 MM.
 Then apply the second coat of paint.
 The paint shall be applied at the rate of 30 microns /coat.
 The paint shall not be applied, if the temperature less than 10 degree C
and relative humidity more than 85%.

27.6 Safety Measures:


 All the transit mixers shall be provided with reverse horns.
 All exit points of the transit mixers shall be marked with safety cones and
caution boards.
 Flagman shall be provided at all exit points of the trucks /tippers.
 The speed of vehicles plying in the work shall be restricted to 30kmph
maximum.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
65
 Leveling staff shall be made of wood/fiber.
 Any local labour if working in the job shall be screened and trained.
 Adequate area lighting in case of night work shall be ensured.
 Proper PPEs viz. Shoes, Safety Jackets etc. shall be used.

WMS / 28
METHODOLOGY FOR ROAD MARKING

28.1 Scope:
 The work shall consist of marking traffic stripes using a thermoplastic
compound meeting the requirements as shown in Drawings.

28.2 References:
 MoRT&H specifications clause no 803, IRC:35-1997 and Technical
specifications of contract.

28.3 Equipments:
 Thermo plastic material heating Equipment, Road marking machine, Total
station.

28.4 Tools:
 Measuring steel tape, line rope.

28.5 Materials:
 Thermo plastic material as per clause No: 803.4.2, Glass reflectorizing beads
Type 2 as per Clause No: 803.4.3.

29.6 Procedure:
 The traffic will be regulated by placing proper safety barricades/safety
cones/flag man prior to the work zone.
 Median and shoulder work shall be completed prior to Road marking.
 The BC surface shall be thoroughly cleaned of all dust, dirt, grease, oil and all
other foreign matter before application of paint.
 The thermoplastic powder is put in to the container of machine and it is to be
heated. The material is mixed uniformly by operating the mechanical agitator

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
66
in the container. The thermostat is adjusted to a temp of 180-200 0C.The
material is added to the container to its full capacity and melted till it achieves
smooth consistency.
 Thermoplastic materials shall be applied in hot condition either by screeding
or extrusion process.
 After transferring the thermoplastic paint to the laying apparatus, the material
shall be laid at a temperature within the range of 180 to 200 degree
centigrade.
 The application properties of the thermoplastic material shall be such that it
shall readily get screeded or extruded at applied temperature.
 The paint shall be applied with a thickness of 2.5 mm exclusive of surface
glass beads. The width shall be as per drawing.
 The Glass beads shall be applied at the rate as specified in the ref code.
 The finished lines shall be free from ruggedness on sides and ends. The
upper surface of the lines shall be level, uniform and free from streaks.
 Traffic shall be allowed after 60 minutes of application at specified
temperature.

28.7Safety Measures:
 Safety cones & PPE’S will be provided during the time of painting.
 Diversion boards, work in progress boards will be arranged.

WMS / 29
METHOD STATEMENT FOR TRENCH FILLING

29.1 Scope:
 This work shall consist of filling of Trenches encountered in the alignment.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
67
29.2 References:
 MoRT&H specifications and technical specification of Contract.

29.3 Equipments:
 Dumpers, Grader, Water tanker, Wheel loader, Dozer, Excavator/JCB, Roller and
Auto level etc.
29.4 Tools:
 Measuring Tape, Crow bar, spade, etc.

29.5 Procedure:
 Prior to start of back-filling, the dimensions of trenches shall be measured.
 The trench sides shall be cut to enable the roller to enter, shall be filled in layers
with cut / suitable Embankment / sub grade material and compacted with roller to
the required density as per MORT&H table No: 300-2.

29.6 Safety Measures:


 The barricading tape and temporary barricades painted with alternate black and
white strips shall be provided around the well.
 Helmets, Safety Jackets will be provided to the workers.
 To control dust pollution both at borrow area and work site, water sill be
sprinkled.

WMS / 30
METHODOLOGY FOR TURFING ON EMBANKMENT SLOPES

30.1 Scope:
 This work shall consist of furnishing and laying of grass seeding or sowing of
grass sapling on embankment slopes location as specified in the drawing.
30.2 Reference:
 IRC:SP:21-2009
 30.3 Equipments:

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
68
 Template with 1:2 slopes, Spirit level, JCB, Water Tanker, Spade, Lime powder,
Line rope, measuring tape etc.
30.4 Materials:
 Grass seeding shall be used for turfing materials.
30.5 Procedure:
 The area to be turfed will first be constructed to the required slope and cross
section with the help of JCB.
 Trimmed surface shall be loosened and stones of size more than 50mm, stumps
or any undesirable foreign materials shall be removed.
 Prepared embankment slopes shall be moistened to the loosened depth and
seeding or sowing of grass sapling shall be done immediately thereafter. Sowing
of grass sapling will be done at the rate 15 to 20 sapling per square meter.
 The first watering shall start immediately after sowing the grass. This shall be
continued for the first seven days at least 1-2 times of watering per day. Further,
the watering shall be done depending on rain/moisture levels.
 The entire area of grassing shall be protected.

30.6 Safety Precautions:


 All safety precautionary measures shall be taken as stated below:
 Moveable signboards shall be place at area where heavy machineries and survey
works being carried out. The movement of machines and lorries at these areas
shall be controlled by flagman’s Signboards such as “CAUTION MAN AT WORK
GO SLOW”, “CAUTION GO SLOW WORK IN PROGRESS”

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
69
WMS / 31
METHODOLOGY OF CONSTRUCTIONOF PROFILE CORRECTIVE
COURSE OVER EXISTING CARRIAGE WAY

31.1 Scope:
 The work shall consists of mixing, laying and compacting of bituminous macadam
for profile corrective course on existing carriage way.
31.2 References:
 MoRT&H specifications Clause no. 504, IRC:16-2008 and Technical
specifications of contract.
31.3 Equipments:
 Sensor paver, tandem roller, water tanker, dumpers, hot mix plant, wheel loader,
auto level and leveling staff.
31.4 Tools:
 Lime powder, string, sensor pegs, measuring steel tape, straight board,
thermometer, steel scale.
31.5 Materials:
 Binder: The material shall be VG-30 grade bitumen as per IS:73-2013for profile
corrective course.
 Aggregate: The coarse and fine aggregate shall consist of crushed stone. These
shall be clean, hard, durable, dry and free from soft or friable, organic or
deleterious matter. These shall satisfy the physical requirement set forth for the
individual relevant materials/mixes. Before approval of the source it shall be
tested for stripping.
31.6 Procedure:

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
70
 This work shall consist of in single course or in multiple courses of crushed
aggregates premixed in HMP with VG-30 grade bitumen at the rate of as per BM
mix design to the line, level and slopes as shown in drawings.
 The aggregate blended with coarse and fines shall consist of crushed rock and it
shall satisfy the requirements as per MoRT&H clause no.504.
Specification
Aggregate property
BM
Grain size Max.5% passing in 75micron sieve

Combined FI+EIIndex Max 35 %

Los anglesAbrasion Value Max 40 %

AIV Max 30 %

Soundness withsodium sulphate Max 12 %

Soundness withMagnesium sulphate Max 18 %

Water Absorption Max 2 %

Stripping(retainedcoating) Min 95 %

 The pre-mixed bituminous material shall be prepared in an electronically


controlled batch mix hot mix plant of adequate capacity and capable of yielding a
uniform quality mix
 At the time of mixing the temperature of aggregate shall be 150-170C, bitumen
shall be 150-165*C and the mix temperature shall not be more than 165*C.
 The material shall be transported in clean vehicles; a thin coating of lubricating oil
may be applied to the interior of the vehicle to prevent sticking.
 The surface on which the bituminous layer to be laid shall be swept clean of all
loose and extraneous materials by mechanical or by any other suitable method.
 Profile corrective course for correcting the existing pavement profile shall be laid
to varying thickness as shown on the drawings or as indicated in the contract
documents
 The material which is to be laid shall be mix designed in accordance with
Marshall Method.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
71
 The material shall be spread by means of self-propelled paver finisher except in
inaccessible areas, to the required thickness, lines and camber as shown in the
drawings.
 The thickness of compacted layer shall not exceed 100mm.
 In the inaccessible areas the mix shall be laid with suitable hand tools.
 At the time of laying a minimum temperature of 140 degree C shall be
maintained.
 As soon as the material was spread, compaction shall commence and completed
within the rolling temperatures.
 Rolling shall be completed at min. 90deg.C of Mix. Rolling of longitudinal joints
shall commence behind the paving operations, after this the rolling shall start
from the lower edge towards upper edge parallel to the centre line of road, and
each pass shall overlap 1/3rd preceding pass.
 All deficiencies in the surface shall be made good behind the paver before the
initial rolling commenced.
 The initial rolling shall be done with a smooth wheeled roller of 80-100KN static
weight, followed by intermediate rolling with a vibratory roller of 80-100KN static
weight.
 The finishing rolling shall be done a smooth wheeled tandem roller of 80-100KN
weight.
 In uni-directional camber and super-elevated portions the rolling shall
progress from lower to the upper edge. Rolling shall be done as per
approved rolling pattern, which shall be decided in trial stretch.
 All the joints shall have offset of , at least, 300mm from parallel joints in the layer
beneath, longitudinal joints shall coincide with either the lane edge or the lane
markings and shall not situated in wheel track zones.
31.7 Acceptance criteria:
 The tolerance in level shall be in between +6 to -6mm.
 The mix binder content shall be +/- 0.3% of designed OBC.
31.8 Safety Measures:
 . All safety measures shall be as per approved EHS Plan.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
72
WMS / 32
METHODOLOGY FOR STONE PITCHING / REVETMENT ON SLOPES
32.1 Scope:
 The work shall consist of covering the slopes of road embankments with stone,
boulders over a layer of granular material called filter.
32.2 Reference:
 Section 2500 of MoRT&H specification & Technical specification of contract.
32.3 Equipments:
 Tractors, Excavators, water tanker etc…
32.4 Materials:
 Pitching: The stone shall be sound, hard, durable and fairly regular in shape.
Quarry stone shall be used. The stones subject to marked deterioration by water
or weather shall not be accepted. The weight of stone shall be minimum 40Kg.
The size of spalls shall be minimum 25mm and suitable to fill the voids in the
pitching.
 Filter media: The material for filter shall consist of sand, gravel, stone, coarse
sand or approved material. To prevent escape of Embankment material through
the voids of stone pitching as well as to allow free movement of water without
creating any uplift head on pitching, one layer of filter material shall be provided
underneath the pitching. The gradation of the filter media shall satisfy the
requirements of clause No; 2504.2.2 of MoRT&H.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
73
32.5 Procedure:
Stone pitching:
 The banks, side slopes of Embankment shall be trimmed to the required depth as
shown in Drawing.
 To maintain uniform slope and profile put up by means of line and pegs at the
interval of 3 meter.
 Depressions shall be filled and thoroughly compacted.
 The approved filter granular material shall be laid over prepared base and
suitably compacted to the thickness as shown in Drawing.
 The lowest course of pitching shall be started from the toe wall and built up in
courses upwards.
 The toe wall shall be constructed as per drawing.
 The stone pitching shall commence in a trench below the toe of the slope.
 Stone shall be place by hand to the required length and depth confirming to the
drawing.
 Stones shall be set normal to the slope, and placed so that the largest dimension
is perpendicular to the face of the slope.
 The pattern of laying shall be such that the joints are broken and voids are
minimum by packing the spalls wherever is necessary and top surface is as
smooth as possible.

Procedure for Dry rubble flooring:


The work shall consist of constructing dry rubble flooring at cross drainage works.

 The base of the flooring shall be prepared to the specified levels and slopes and
compacted suitably with hand rammers or other means to have even bedding.
 The thickness of flooring shall be made with one stone only.
 The stones shall then be laid closely on prepared base in one layer.

Procedure for Flexible Apron:


 The flexible apron comprising loose stone boulders shall be provided beyond
curtain walls.
 The weight of stone shall not be less than 40 kg.
 The dimensions of apron shall be provided as shown in the drawing.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
74
32.6 Safety Measures:
 All safety measures shall be as per approved EHS Plan.

WMS / 33
METHODOLOGY FOR REINFORCEMENT WELDING

 33.1 Scope:
 The work shall consist of Welding of Fe 500 Reinforcement bars as per
specification.

 33.2 Reference:
 As per IS: 9417 and MoRT&H specification.

 33.3 Equipments:

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
75
 Welding machine with electrodes.

 33.4 Procedure:
 E -7018 grade electrode only be used for welding.
 The size of electrode shall be used based on the diameter of Rebar.
a) If the dia of bar up to and including 10mm – size of electrode 2.5mm.
b) Over 10mm and Up to and including18mm – 3.15 mm
c) Over 18mm and up to and including 28mm - 4.0mm
d) Over 28mm – 5.0mm
 The arc shall start in the Groove /joint, which will be subsequently welded over.
 The movement of electrode for welding lap joints in horizontal and vertical
position shall be as per IS: 9417.
 The Lap welding for same diameters of rebar shall be greater than or equal to 5d
at both ends.
 The min gap between the end welding shall be minimum 5d.
 Welding directions for horizontal or near-horizontal lap joints, In case of Vertical
lap joints, the welding shall be performed from bottom to top (rising).
 The visual Inspection shall be carried out.

 33.5 Safety Measures:


 All safety measures shall be as per approved EHS Plan.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
76
WMS / 34

METHODOLOGY FOR CONSTRUCTION OF BORED CAST IN SITU


PILES
 34.1 Scope:
 The work shall consist of construction of bored cast in situ piles for structures in
accordance with the details shown on the drawings and confirming to the
requirements of these specifications.
 34.2 References:
 MoRT&H specifications clause no 1115.2 and Technical specifications of contract
cl: 7.10.3.

 IS: 2911 (Part –IV): IS 2911: Part 1: Sec 2: 1979 Code of practice for design and
construction of pile foundations: (Part-1: Section-2:Bored cast-in-situ piles )

 IS2911: Part-4: 1985 Code of practice for design and construction of pile
foundations ( Part 4: Load test on piles)

 34.3 Equipments:
 Excavator, Batching plant, Transit mixers, Hydra crane, casing, tripod, tremie
pipes, barrel, chisel, winch, Auto level, levelling staff. Welding machine.
 34.4 Tools:
 Cube moulds, slump cones, trays, Steel pins/wooden pegs, Hammer, chisel,
measuring steel tape, line rope.

 34.5 Materials:
 Bentonite, Aggregate, river sand, cement, Reinforcement etc.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
77
 34.6 Procedure for Casting of Piles:
a) Setting Out:
 Prior to the start of piling operations, setting out stations and bench marks will be
established at site. Pile point will be established using total station and marked
with a steel pin/wooden peg. After casing installation the casing will again be
surveyed to determine that it is within tolerance.
b) Boring of Piles:
 The excavation of clay-based material down to the top of first sand layer will be
excavated by auger. At the sand layer, bentonite will be added to the pile bore
and boring will continue by drilling bucket. Constant level of bentonite will be
maintained to stabilize the shaft and level of bentonite will be kept at a minimum
of 1.5 m above the water table. Continuous supply of bentonite solution will be
maintained to avoid any collapse of adjacent soil. This process will continue until
pile toe level has been reached. The drilling tools are designed to allow adequate
free flow of bentonite during tool extraction. Operation of boring, lowering of cage,
flushing of bore and concreting of pile for full length will be accomplished in one
continuous operation as far as possible.
c) Reinforcement Cage:
 The reinforcement cages will be fabricated at site as far as possible near the pile
location. To prevent damage and distortion the cages will be lifted at two points
and carried vertically to the pile. Reinforcement cage will be made either in one
piece of entire length of pile or in two / three pieces and splicing of bars will be
done with sufficient lap length or couplers. Cage will be lowered with the service
crane.

d) Bentonite Replacement:
 During excavation specific gravity of bentonite becomes high. Prior to concreting,
this heavy bentonite must be replaced by light one. To achieve this, 250 mm dia
tremie pipe will be lowered to the pile base with flushing head on top. Fresh
bentonite will be pumped through the tremie to replace the existing solution till the
specific gravity of bentonite becomes less than 1.05 g/cc. However this

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
78
procedure must be limited to prevent over excavation and loosening of the pile
base material. Bentonite suspension shall have the following properties:
 The density of bentonite suspension to 1.05 g/cc
 The marsh cone viscosity between 30 and 40
 The pH value between 9.5 and 12
 The silt content less than 1 per cent
 The liquid limit of bentonite not less than 400 per cent

e) Concreting:
 As soon as possible, after the pile and bentonite have been cleaned, high
workability retarded concrete (slump – 150 to 180 mm) will be delivered to the
pile location in transit mixer. A concrete hopper with plug will replace the flushing
head. The first charge of concrete will be placed with a plug when pulled will push
down the concrete. The concrete will be poured rapidly into the hopper and
continue until flow ceases in the pipe. The tremie pipe will be raised slightly until
flow recommences and concrete discharge will continue. Tremie pipe should
always be kept full of concrete. To ensure compaction by hydraulic static heads,
rate of placing concrete in the pile shaft shall be maintained at minimum 6m per
hour. After each truckload of concrete, the depth of concrete will be measured &
recorded. The tremie will be split as the concrete proceeds to ensure a free flow
and a minimum embedment depth of tremie. The concreting operation will
continue until its level is at least 1.0m above pile cut-off level. In case of
interruption during concreting, guidelines mentioned in clause 7.5 and
subsequent sub clause 7.5.1, 7.5.2 & 7.5.2.1 of IS: 2911 (Part I/ sec 2) 1979 will
be followed. The casing will be extracted by heavy-duty crane.
 34.7 Records:
 Rebar casing dimensions
 Pile depth measuring format (shall be checked by chain method).
 Compressive strength & Slump record
 Liquid limit of bentonite.

 34.8 Safety Measures:


 All safety measures shall be as per approved EHS Plan.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
79
WMS / 35
METHODOLOGY FOR MEASUREMENT OF SURFACEUNEVENNESS
BY AUTOMATIC ROAD UNEVENNESS RECORDER
 36.1 Objective:
 Towed fifth wheel bump integrator test is to be conducted on bituminous surface
to evaluate surface regularity.
 36.2 Scope:
 This work shall consist of measurement and determination of surface
unevenness by “Automatic Road Unevenness Recorder” also known as
“Bump Integrator” on finished Bitumen layer (BC) before allowing the
traffic.
 36.3 Reference:
 IRC: SP:16-2004
 36.4 Equipment:
 It comprises of a trailer of Single wheel with a pneumatic tyre mounted on a
chassis over which an integrated device is fitted. The machine has a panel board
fitted with two sets of electromagnetic counters for counting the unevenness
index value

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
80
 Four Wheeler/Utility vehicle for attaching the bump integrator, pilot vehicle and
broomer for cleaning the bituminous surface.
 36.5 Testing Procedure:
 Operation of the Bump integrator:
a) Calibrated fifth wheel bump integrator shall be used for checking the unevenness
of bituminous surface.
b) The Bump integrator should be towed by a vehicle at a speed of 32 +1 km/hr. A
jeep or Utility vehicle with a canvass body is eminently suitable because it affords
opportunities for the driver to keep a watch on the unit. The jeep or utility should
have sound suspension system. The tyre pressure of 2.1 kg/cm 2 in the rear
wheels of the jeep or utility should be same.
c) Before carrying out tests it is advisable to check the following items:
1) Tyre pressure is 2.1 kg/cm2 (30 PSI).
2) All the bolts of the towing hitch and the bracket fixed with the towing vehicle
are tight.
3) The caster-wheel adjustable jacks are removed from the Bump integrator.
4) Tyre pressure gauge and foot pump kept in towing vehicle.
5) Spare like integrator cords, tool-kit, dipstick and fluid for the dashpots kept in
the Towing vehicle.
6) The relevant result-recording forms are also kept with the counter-board.
Comprehensive notes should be taken giving particulars of test length, width of
road, type of surfacing and any other relevant details needed. The machine
drives over the test section of road at a speed of 32 +/- 1 kmph. Normally in the
nearside wheel track of the nearside lane (position of machine on road is
dependent on purpose of measurements). At the beginning of the section, the
observer having set the counters to zero operates the on/off switch to on-position
on the instrument board. At the end of the section the observer changes over to
the second set of counters, which are then set to zeros thus allowing continuous
measurements. The readings of the integrating and wheel-revolution counters are
entered. The test section should not be less than 1000m.

Processing of results obtained with Bump integrator


i) Integrator value of irregularities in cm (BI counter reading).

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
81
ii) The Distance travelled in Km.
 Each set of readings (BI reading and corresponding distance travelled)
arerequired to be converted to the unevenness index value (UI value) in terms of
cm/km.
 Readings of bump integrator has to be noted down from the display for each
1000m.
 The unevenness index value for the test section is arrived for each 1000m stretch
using the equation from calibration.
 The unevenness index value is calculated by dividing the BI counters values (in
cm) by the distance traveled in km.

The Unevenness Index = Integrator Counter value


Distance travelled (km)
As per IRC SP-73-2007 the unevenness value should not be more than 2000/km
 36.6Safety Measures:
 All safety measures shall be as per approved EHS Plan.

WMS / 36
METHODOLOGY FOR RECONSTRUCTION& WIDENING & FINISHING
OF SUB / SUPER STRUCTURESFOR BRIDGES
 37.1 Scope:
 This work shall consist of reconstruction& widening & finishing of sub structures
like Pier, abutments, pier cap, abutment cap, Dirt wall, Return wall, and wing wall
etc to the lines, grades and cross sections shown on the drawings.
 37.2 Reference:

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
82
 Section 1714 of MoRT&H specification.
 37.3 Equipment’s:
 Trowel, Sponge, wooden flat, and plumb bob.
 37.4 Materials:
 Cement: The cement to be used in the works shall be Ordinary Portland Cement
of 43/53 grade confirming to IS 8112/ IS 12269, OPC with Fly Ash, PPC Cement.
The manufacturer test certificate shall be furnished, and cement shall be stored
as per IS 4082.
 Fine aggregate: Fine aggregate shall consist of clean, hard, strong, dense, and
durable pieces of crushed stone or natural sand or a combination of both. All fine
aggregates shall confirm to IS 383, when tested in accordance to IS 2386 parts 1
to 8. The grading shall confirm to table 1000-2 of MoRT&H specification.
 Water: The water to be used shall be as per clause 1010 of MoRT&H
specification.
 37.5 Procedure:
 As per CA the list of reconstruction of bridges, the existing bridges shall be
dismantling with suitable excavator and removed the existing old concrete and
stacking at suitable place as per instruction of authority engineer. SBC of
thefoundation of the bridge to be tested before construction, after conformation of
safe bearing capacity, bridge shall be constructed as per approved drawing. ,
Before widening the bridge, safe bearing capacity of soil shall be confirmed by
carried out SPT test randomly at widening area of the bridge. Existing wing wallto
be dismantled and new wing wall to be constructed. The bridge shall be widened
as per approved drawing.
 Immediately after removal of the forms, exposed bars or bolts, if any, shall be cut
inside the concrete member to a depth of at least 25 mm below the surface of the
concrete and the resulting holes filled with cement mortar.
 All fins caused by form joints, all cavities produced by the removal of form ties
other holes and depressions, honeycomb spots, broken edges or corners, and
other defects, shall be thoroughly cleaned, saturated with water, and carefully
pointed and rendered true with mortar of cement and fine aggregate mixed in the
proportions used in the grade of concrete that is being finished and of as dry a
consistency as is possible to use.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
83
 Considerable pressure shall be applied in filling and pointing to ensure thorough
filling in all voids.
 Surfaces which have been pointed shall be kept moist for a period of twenty four
hours.
 Special pre-packaged proprietary mortars shall be used where appropriate.

 37.6 Safety Measures:


 All safety measures shall be as per approved EHS Plan.

WMS / 37
METHODOLOGY FOR WIDENING OF EXISTING CARRIAGEWAY

38.1 Purpose:
The purpose of this methodology for Widening and Strengthening of Existing
Carriageway is to provide details of construction procedures to be adopted,
Quality Assurance & Control System/Procedures to be adopted, details of Plants,
Equipment to be deployed, and Safety and Environmental measures to be taken
in execution of Existing Carriageway at various locations/stretches as shown in
the construction drawings.

38.2 Scope:
The scope of this methodology covers the Widening and Strengthening of
Existing Carriageway with as per the drawings & specifications. In general, this
methodology will be the same as that for new carriageway except some change
in work sequences as indicated in respective layer construction.

38.3 Cross References:

This methodology shall be read in conjunction with the following documents:


MoRT&H – Specifications for Road and Bridge Works
IRC: 36-2010
Contract Technical Specifications
Relevant BIS/ASTM/ BS Standards/Codes cross-referred elsewhere in this
methodology.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
84
38.4 Construction Methodology:

Embankment/Sub grade Construction for widening portion of Existing


Carriageway: Construction of Embankment and Sub grade shall be done as per
the submitted methodology with the following additions.
1) Clearing and Grubbing: Existing road slope portion shall be cleared along with
the horizontal portion up to the toe of the proposed Carriageway.
2) Embankment: The existing road slope shall be benched by Grader side blade
and all loose and unsuitable material shall be removed. After that Embankment
operation shall be started as usual as per above referred methodology as
mentioned in New carriageway.
3) In works involving widening of existing pavements or providing paved shoulders,
the existing shoulders shall be excavated and removed to its full width up to Sub
grade bottom(As per CA widening of existing road both side) as per approved
cross section.However the cutting of shoulder excavation shall not be less than
roller width min 2.75m in the case of 1.5m widening(widening of existing road
width1.5m +1.0m for earthen shoulder) for The Sub grade shall be loosened to
depth of 500 mm and compacted as per clause 305 to a density not less than
97% of maximum dry density determined according to IS:2720(Part-8). Any
unsuitable material encountered in this portion of Sub grade shall be removed
and replaced with suitable material and compacted in accordance with clause
305.
Granular Sub Base (GSB)
The material to be used for GSB should be as per approved design In addition
where it is not possible lay GSB with motor grader; manual laying shall be done
with appropriate grade and camber and shall be compacted as per the approved
methodology. Earthen shoulder 1.0m shall be provided before laying of GSB
layer to avoid wastage of GSB and good confinement to GSB .The rolling shall
be done by vibrated roller of 80 to 100KN for GSB layer simultaneously
compacted with earthen shoulder to achieve 98% compaction of MDD for GSB
and 97% for shoulder. Where it is not possible to compact with vibrated roller,
suitable plate compactors shall be used to achieve the required degree of
compaction.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
85
Wet Mix Macadam (WMM)
The materials to be used for WMM, the methodology of construction and the
Inspection & Testing procedures shall be as per the methodology of WMM.
In addition, where the width of laying is more than 2.75 m, the mix shall be spread
by sensor paver. Otherwise, the mix shall be leveled by the motor grader.
Earthen shoulder 1.0m shall be provided before laying of WMM layer to avoid
wastage of WMM and good confinement .The rolling shall be done by vibratory
roller of 80 to 100KN for WMM layer simultaneously compacted with earthen
shoulder to achieve compaction 98% of MDD for WMM and 97% for earthen
shoulder. For portions where motor grader cannot be used, the same shall be
done manually.
The layer shall be compacted by vibratory roller of 80-100 KN static weight
following the appropriate method of compaction. Wherever, it is not possible to
compact with Vibratory roller i.e. near walls, Retaining walls, etc. it shall be
compacted by plate compactor. After completion of rolling, density shall be
checked in the field. No Vehicular traffic shall be allowed to ply on the prepared
WMM surface.

Prime Coat and Tack Coat


Immediately after successful completion of WMM layer, Prime coat shall be
applied over it with a rate of spray of 0.7 – 1.0 kg/sqm. The materials to be used,
application procedure, Plants and Equipment’s to be used shall be as per the
methodology for Prime coat and Tack coat. Tack coat shall be applied just before
laying of next bituminous layer at a rate of 0.25 – 0.30 kg/sqm. After completion
of DBM over the WMM, Tack coat shall be applied at a rate of 0.2 – 0.30 kg/sqm
just before laying of next DBM or BC layer as the case may be, if the existing
DBM surface is left open for more than 24 h after priming.
ProfileCorrective Coursewith Bituminous Macadam (BM)
Existing Bitumen surface levels shall be taken close interval and corrected level
sheet shall be prepared to find out the depth of profile corrective course as per
approved Plan & Profile. Width and thickness at suitable chainage intervals shall
be marked before start of the activity. The profile corrective course shall be
undertaken after diverting the traffic on the completed new Carriageway/Service

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
86
road. No Traffic shall be allowed on freshly laid surface. All necessary
precautions shall be taken to prohibit vehicular movement by erecting barriers
and fixing well displayed Diversion boards.
The construction of BM, Inspection and Testing procedure shall be as per the
approved .Profile corrective course over the existing Carriageway Bitumen top,
with required camber for 2.75 to3.5 m width shall be done with BM, as the case
may be in one or two layers depending on the thickness. It shall be laid by grader/
manually, if the width of laying is less than 2.75 m, otherwise this shall be done
by sensor Paver.
DBM for the widened portion (about 1.5 – 2.25 m width) shall be done by grader/
manually and shall be compacted by smooth wheel Vibratory roller and
Pneumatic tyre rollers to achieve the required degree of compaction. After
completion of DBM over the widened portion, the whole width of the Carriageway
i.e. 10 m shall be done with DBM& BC Layer.After completion of bituminous
layer, earthen shoulder shall be provided in one layer of full depth of bituminous
layer and shall be compacted by vibratory roller of 80 to 10 KN to achieve the
degree of compaction.

Bituminous Concrete (BC)

The methodology of construction of BC shall be as per the submitted


methodology.

38.5Safety Measures:
 All workman and staff involved for the rectification work shall use necessary
PPE.
 Area of rectification shall be demarcated properly to avoid any kind of
accident.
 Site safety plan shall be followed in general.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
87
WMS / 38
METHOD STATEMENT FOR CONSTRUCTION OF RBI GRADE-81 SOIL
STABILIZER IN GRANULAR SUB-BASE

9.1 Scope:
 This work shall consist of Granular sub base construction with approved
materials.
9.2 References:
 MoRT&H Specifications, Clause no: 401, Technical specifications of Contract.
9.3 Equipment’s:
 Excavator/ Back hoe, Dozer, Motor Grader, Dumpers, Vibratory roller, Water
tanker, Auto Level.
9.4 Tools:
 Hammer, crow bar, spade, line rope, pegs, and lime powder, measuring tape,
etc.
9.5 Materials:
 The material to be used for the work shall be natural sand, crushed gravel, and
crushed stone, crushed slag or combination thereof depending upon the grading
required. If the water absorption of the aggregates determined as per
IS:2386(part:3) is greater than2%,the aggregates shall be tested for wet
aggregate impact value(AIV)IS:5640: 40% maximum
9.6 Procedure:

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
88
 Toe width of GSB shall be marked before commencement.
 The material shall satisfy table 400-1 Grading- I requirement of MoRT&H Rev. 5
 GSB layer shall be constructed on the sub grade top layer, which is already
constructed as per MoRT&H clause 305.
 Calculated quantity of GSB material shall be placed on the entire bed. If any
segregation is observed, the same is rectified by processing with the help of
grader blade. GSB material gradation shall be checked at QC lab.
 Material shall be spread uniformly with the help of motor grader.
 Required amount of water will be sprinkled, calculation based on OMC (+1% to
-2% tolerance limits).
 Final grading shall be done carefully as per required slope and level without
segregation.
 The graded material shall be thoroughly compacted to the specified densities by
vibratory roller having a static minimum weight of 8-10 tons.
 Rolling shall be commenced at the lower edge and proceeded towards the upper
edge longitudinally with overlapping of one third of roller drum width for each
passes for areas of unidirectional cross fall (camber) and super elevation.
 The number of heavy vibratory passes shall be established after doing trial
stretch to achieve required density.
 All the depressions, high spots, segregated locations shall be made correct
during initial rolling itself.
 Camber shall be checked and corrected if required before final rolling.
 Finally one plain pass shall be given on the entire length of the stretch.
 Speed of the roller shall be maintained uniformly (not exceeding 5km/hr.) during
rolling.
 After rolling compaction test shall be carried out to check its degree of
compaction by any suitable method.
 Levels shall be checked and recorded in the format no. A/F 03 for the top layer.
9.7 Acceptance criteria:
 The Field Dry density shall be more than 98% of MDD
 The tolerance on the surface level shall be +_10mm
 Surface Regulatory shall not be more than 8 mm

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
89
9.8 Safety Measures:
 All tippers /tankers /graders shall be provided with reverse horn.
 Flagman shall be provided at all exit points of the trucks/tippers.
 The speed of the vehicles plying in the work area shall be restricted to 40 kmph
maximum.
 Leveling staff shall be made of wood.
 If night work is to be carried out the area shall be sufficiently provided with
lighting.

Revision No R0 R1
Date 18.08.2014 27.01.2015
Prepared By
90

You might also like