Professional Documents
Culture Documents
Steam Blowing Procedure PDF
Steam Blowing Procedure PDF
1
P Thermal Power Engg Pda College Of Engg Gulbarga Karnataka 585102 India
P
2
P Associate Professor, Department of Mechanical Engineering, PDA College of EngG. Gulbarga,
P
Abstract: This thesis attempts to present the supercritical thermal power plant 2x800 MW at
steam blowing activity of super critical boiler at YTPS Raichur being developed by Raichur
different steam circuits and it show the state of Power Corporation Ltd (RPCL) a joint venture of
the art of cleaning technology for life time Karnataka Power Corporation Limited (KPCL)
extension of Supercritical Thermal Power Plant and M/s BHEL. The plant is located at
for both the units of 2x800MW, YTPS , Raichur, Yeramarus Village, Raichur district, Karnataka
Karnataka, India. state, India.
Steam blowing dedicated to removal of all The plant is consists of various interconnected
welding debris and particles, after installation intricate systems, consisting multi corers of
and creation of propos conditions, for rupees investment but when it comes to
introduction of steam into the turbine without commissioning, a lukewarm approach is adopted
operation risk. which creates in perennial maintenance
problems. It has been realized that many
The purpose of each steam blowing is to protect problems of operations are caused due to
the downstream steam turbine, this process improper commissioning of the plant. To ensure
requires that the pertinent CFR is obtained and plant commissioning in orderly, A systematic
mechanical steam purity is steam purity proved commissioning of boiler, turbine and its
by means of target plate. Here by calculating it is auxiliaries with proper understanding hold the
found that actual value of CFR is 1.2 to 1.7 that key for getting standard result. Hence an
show the steam blowing is effective and the integrated approach needs to be followed to
target plate results are found to be satisfactory. minimize unscheduled losses. The various
commissioning activities of newly constructed
Keywords: Supercritical Thermal Power Plant, supercritical thermal power plant are HFO
Steam Blowing, Clean Force Ratio (CFR) And System, Regenerative Air Pre-Heater, ID Fan,
Target Plate. FD Fan, Scanner Air Fan, Boiler Final Hydraulic
Test, Boiler Alkali Boil Out (Chemical
I. INTRODUCTION Cleaning), Steam Blowing, PA Fan, Seal Air
Fan, Mills and Feeders.
1.1 General Introduction: The world over
energy resources are getting scarcer and In spite of maintaining higher standards of
increasingly exorbitant with time has resulted in erection cleanliness and doing a preoperational
enormous increase in power plant installation and chemical cleaning for the entire system a certain
in their size. So that thermal power plant is the quantity of debris in the form of scales, loose
main source of electrical energy generation in materials, weld spatter, etc. will remain in the
our country. Powers producers are looking for boiler and the pipe lines. Steam blowing
improve the efficiency of power plant and also completes the task of providing a cleaner system
grow concerns about the environmental impacts for passing steam into the turbine. In other words
of power generation. This demonstrates we attain steam of required quality standard by
technology up gradation of coal fired subcritical way of chemical cleaning and steam blowing.
power plant in the market. Introduction of Failure to remove debris may result in increased
supercritical / ultra SC technologies on thermal turbine erosion, blade damage and rapid
power plants can change in improve the deterioration of turbine efficiency, the measures
performance of power plant.In this project we are provided and the blowing steps are discussed
have gone through the newly constructed in detail to avoid the over high thermal stress
78
IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue 10, October 2016
ISSN (Online) 2348 – 7968 | Impact Factor (2015) - 4.332
www.ijiset.com
among the temporary pipes and some issues blowing operation cleans the system and
during blowing are also analyzed, which could be provided the steam of requisite purity for the
helpful and referenced for the similar units. plant.
80
IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue 10, October 2016
ISSN (Online) 2348 – 7968 | Impact Factor (2015) - 4.332
www.ijiset.com
3.11. Steam blowing of power station steam sample will be collected and tested for the
pipelines: Steam blowing allows power station above before steam admission into the turbine.
boilers and pipelines to ensure that during normal The steam should be clear without any noticeable
operation no adhering material in the super- solid particles. During the initial stages the steam
heaters, re-heaters, and steam pipelines will quality will be far form the above standard.
become dislodged, reach the turbine blades, and Results can be achieved in a reasonable period of
damage them. Puffing and continuous methods operation by dumping the steam to waste through
are mainly used for steam blowing. HP/LP bypass system. The boiler drum pressure
can be varied between 60 bar during the dumping
3.12 Definition of steam blowing: The blowing period. Higher flow will help in achieving the
of steam through piping to remove debris from target at a faster rate. Samples are taken at
the pipe, cleaning steam lines to a steam turbine, regular intervals and steam quality is closely
cleaning plant expansion lines, or new installs. monitored. Prescribed quality of steam once
As the definition says, to steam blow a pipe achieved to be ascertained in the subsequent 4 to
requires steam to blow through the pipe. This 5 samples collected in a period of 2 hours.
pipe can be attached to a boiler and the other end Values thus registered to be preferably in
of the pipe can be attached to a steam turbine. decreasing trend. Then the steam is admitted for
rolling the machine.
3.13. Why steaming blowing is done: The
steam blowing operation cleans all the debris in 3.18. Requirement of temporary line for steam
the super-heater, re-heater and the steam pipe blowing:
line connecting the turbine. During the 1) The temporary discharge piping may be of
maximum continuous rating load of the turbine carbon steel.
the drag force in the pipe line can dislodge 2) The diameter of temporary discharge piping
particles loosely adhering to the tubes internal shall not be less than the diameter of respective
surface, causing great damage to the turbine line to be steam blown.
blades. Guidelines given by various boiler 3) The through pieces should have an opening
designers and agencies, etc., to effectively carry equal to the diameter of the respective
out this operation focus on creating a drag force temporary pipe line.
created on the inside surface of tubes of pipes 4) For cold reheat line blowing at boiler end, the
which is much higher than that occurring during temporary discharge piping normal bore should
the maximum continuous rating load of the match the CRH line.
turbine. Ratio of the drag created during steam 5)The temporary discharge piping and jumper
blowing to the drag occurring during the shall withstand steam blowing parameters.
maximum continuous rating load is called CFR. 6)Temporary valves and lines are to be designed
3.14. How steam bowling is done: Steam for 90 bar and capable to withstand steam
blowing guidelines focus on creating a drag force blowing parameters.
on the surface of tubes or pipes much higher than
that which occurs during the maximum IV. METHODOLOGY
continuous rating load of the turbine. The ratio
of the drag created during steam blowing to the 4.1. Steam blow methods: There are two types
drag occurring during the maximum continuous of steam blow methods such as follows:
rating load is called the clean force ratio CFR.
Boiler designers and commissioning groups 1) Puffing or Shock blow Method
prefer to keep a CFR of about 1.2 to 1.7. 2) Continuous steam blow method
3.15. Steam blowing equipments: M/s BHEL 4.1.1. Puffing method: In this blow method, the
has invested in the equipment and expertise for steam pressure inside steam generator is raised to
steam blowing. This equipment are as follows a certain maximum required pressure; a
control valves, de-super-heater nozzles, flow temporary sacrificial valve is opened quickly.
elements, thermo wells pressure gauges, orifice During this pressure release the steam velocity is
plates, microsope, safety valves and instruments, reached, but for a short period of time. Due to
temporary steam blow piping, target inserters and release of the pressure and temperature, the
a reference list of previous steam blow projects steam generator has to start again. The steam
can be acquired on request. blowing operation carried within four to six
hours, including start-up and shutdown of the
3.17. Steam dumping: Prior to admitting steam steam generating plant. Normally not more than
into the turbine, the quality of the steam should one steam blowing operation should be effected
be ascertained and the steam can be admitted daily in order to ensure adequate cooling of the
only when it confirms to the following standards system, steam blowing at puffing method has
for initial rolling. Silica less than 50 ppm. Main
81
IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue 10, October 2016
ISSN (Online) 2348 – 7968 | Impact Factor (2015) - 4.332
www.ijiset.com
preferably been performed especially in natural by opening hand operate valve mounted in place
and assisted circulation boilers. of HP bypass valve. 1A end point will be
concluded by seeing target plate. 1A, 1B will be
4.1.2. Continuous steam blow method: In this combination blowing and would result in
method There is no pressure build up, but after effective blowing of CRHLS. However, 6 to 8
calculations, the CFR is reached continuously. blows will be given only through HP bypass to
During the continuous steam blow the target ensure cleanliness of the limb.
plates are inspected on impacts of particles. The
steam generating plant shall be operated while Stage-2A: 1A+ 1B plus re-heater, HRHL, IV
by-passing the turbine and blowing the steam strainer, temporary pipe of size 450 m.
exhaust into the atmosphere. The average
operational values range between 5 to 25 bar Stage-2B: 1A + 1B + 2A up to IV strainer + LP
steam pressure and 380 to 510 °C steam bypass up steam lines with temporary pipe
temperature at 20 to 40 % load. The main steam exhaust of size diameter 450.
stop valves shall be fully open during this
operation. 2nd stage blowing will be parallel blow in the
P P
Fig 4.1: Steam blowing circuit – 1A Fig 4.2: Steam blowing circuit – 1B
82
IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue 10, October 2016
ISSN (Online) 2348 – 7968 | Impact Factor (2015) - 4.332
www.ijiset.com
Fig 4.3: Steam blowing circuit – 2A Fig 4.4: Steam blowing circuit – 2B
V.EXPERIMENTATION& OBSERVATION
5.1. Commissioning procedure: The procedure of 4. Availability of lab facility for boiler water
steam blowing for unit#1 and unit#2 was conducted regime maintenance.
for a period of 3rd November 2015 to 14th January
P P P P 5. Availability of auxiliary steam.
2016 and 28th April 2016 to 9th June 2016
P P P P 6. Availability of manual feeding arrangement of
respectively. There are two stages for a single unit Ammonia & Hydrazine.
and each stage are steam blown individually this is 7. Availability of portable fire extinguishers at
called as steam blowing stages. For an every single selected locations.
day minimum two blows has been done. As per 8. Availability of required lighting /
agreement by M/s KPCL/RPCL efforts were made communication facility / manpower.
to conduct the steam blowing activity. Parameter 9. Availability of public addresses system or siren
such as day, date, steam blow stage, blow number, to communicate the commencement of steam
time of valve opening and closing, blow duration, blowing.
separator outlet pressure start of blow, separator 10.Availability of ambulance / fire tender in the
outlet pressure end of blow, main steam pressure power station premises.
start of blow, main steam pressure end of blow,
main steam temperature start of blow, main steam 5.7. Safety precautions:
temperature send of blow and target plate status.
The readings were observed for every blow for 1. Required quantities of safety gears such as
each day and same are presented through. Both the helmets, Asbestos hand gloves, Ear Mufflers etc
unit readings were compared for conclusion of are available.
efficient steam blowing. 2. First aid kit box available in control room
Service water shall be made available near the
5.2. Fuel consumption for steam blowing: activity area.
3. Required stair cases or platform or approaches
Unit#1 1st stage: Light Diesel Oil is 1327.42
P P
piping.
kiloliters; Heavy fuel oil is 1430.108 kiloliters. 5. Required number of sign boards to be put into
Unit#2 2ndstage: Light Diesel Oil is 306.6 kiloliters;
P P
83
IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue 10, October 2016
ISSN (Online) 2348 – 7968 | Impact Factor (2015) - 4.332
www.ijiset.com
be taken care of as if the unit is started to agreements shall be made regarding the assessment
synchronies the generator with the grid. of steam purity (impact of debris). 5.11.2
2. The procedure is to raise the boiler pressure to
60 bar. shut off firing and the same time open Location of target plate installation: When
temporary valve (EOTV). The steam lines which selecting the location of installation, the inlet
are being blown should be warmed up prior to conditions should be chosen such that an as
blowing. The opening of temporary valve allows uniform as possible impact velocity on the target
steam to escape to atmosphere at high velocity plate is ensured. Here, the specific local conditions
carrying with it loose and dislodged debris. To as being taken into account. The installation of
prevent thermal stresses in the thick walled shell target plates directly downstream of pipe bends
like separator and headers the saturation shall be avoided. Not less than 5 times the nominal
temperature change in separator is limited to 40 °C width of the line in which the target plate is
maximum. Hence, for the purpose of steam installed is considered the guide value for a
blowing of all critical piping the temporary valve undisturbed inlet section upstream of target plate.
will be opened at 60 bar and closed at 40 bar
separator pressure. Principally two locations are possible,
3. The water level in the separator swings beyond
visible limits at the start, during and at the end of 1) Installation of target plate in the inlet section of
steam blowing. There are chances of water droplets temporary pipe work
to carry over to the saturated steam pipes and low 2).Installation of target plate in the outlet section of
temperature super-heater. This can possibly be the steam line.
minimized by keeping the water level in the
separator at the lowest port (visible limit) before
the start of each steam blow off.
4. All the steam lines are purged in parallel and it is
a standard practices to limit number of blows per
day to 8 with an interval of 1-1 ½ hours for cooling
in addition to overnight cooling.
5. The furnace exit gas temperature should be
limited to 540 °C to safeguard super-heaters and re-
heaters.
6. Internal boiler water treatment to be carried out
with liquid ammonia and hydrazine hydrate only to
maintain pH value of 10.0 in boiler water and 5 to
25 ppm of N2H4 in feed water.
Fig 5.1: Target plate arrangement
7. Hot tightening of flanges, studs or bolts is to be
done wherever such connections have been made. 5.12. Cleanliness criteria: The turbine vendor of
8. During steam blowing. MS, CRH and HRH line the steam will generally specify the criteria to
drains are kept open to atmosphere without any which the system should be cleaned if steam is
valve for achieving free and uninterrupted flow. used in a turbo generator the following criteria is
9. Target Plates will be used for stages, Stainless generally used.
Steel target plates having mirror finish will be used 1) The successive target must result in mirror
in final stages. In the preceding stages target plates finished that meet the specified criteria.
are not being used. During steam blowing, pressure 2) After a cooling down period of at least 12 hours
and temperature readings at selected locations will two more successive steam blows must result in
be noted down for the purpose of determining CFR mirror surfaces that meet the specified criteria.
(Refer results and calculation chapter)
10. Completion criteria for all the stages of steam 5.13. Results: Indications for the result of each
blowing are given at the end. blowing are the number of pitting found on the
target plate mounted in the temporary exhaust pipes
5.11. Target plate Spesification nearer to the permanent line. The highest velocity
of steam is in the centre of the pipe. Hence,
5.11.1.Dimensioning and surface quality:
judgement should be made for the end point of
The result of steam blowing shall be checked by
steam blowing in this area. The area for the above
means of a target plate to consist of a holding
is 3 /4th the discharge pipe diameter at the centre. It
fixture to which a mirror-finished impingement
P P
84
IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue 10, October 2016
ISSN (Online) 2348 – 7968 | Impact Factor (2015) - 4.332
www.ijiset.com
1. For evaluating the cleanliness and termination Where,
point of the steam blowing, target plate of stainless k = 1.3 Constant
steel are to be used. g = Acceleration due to gravity is 9.81 in “m/sec2” P P
2. The result of the blowing operations can be A = Area of main steam line in “m2” P P
85
IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue 10, October 2016
ISSN (Online) 2348 – 7968 | Impact Factor (2015) - 4.332
www.ijiset.com
as Tons/Hour. In our project we are using M/s 1.3 𝑥 𝑃 x 9.81 x 10000 x (0.112)2
CFR = 2592.7 𝑥 1000 2
ALSTOM super critical boiler 800X2MW Capacity [ ] x 0.0132
3600
were installed at YTPS Raichur. It is designed into 1599.736 x P
=
518679.39 x 0.0132
three categories like boiler capacity of SH main
steam EOTV is Qmcr = 2592.7 T/Hr or 720 kg/sec, CFR = 0.233 x P
CRH pressure at outlet is Qmcr = 2069.2 T/Hr Or
574 kg/sec and HRH pressure at outlet is Qmcr = Since, Main Steam Line at HRH Exit Pressure is
2069.2 T/Hr or 574 kg/sec, at maximum continuous 6.12 ≈ 6.2 kg/cm2 P
employ the puffing blow method, temporary piping d = 0.748 m (Diameter of main steam cold Re-
has to be properly engineered. Heat)
𝜋𝑑 2 𝜋 𝑥 (0.748)2
𝐴= = = 0.439 m2
4 4
P
specific volume the first one is the designed 358.3 °C P = Main steam line exit pressure at CRH
specific volume. Here it works due to the fact that
high temperature steam at low pressure has a much 1.3 𝑥 𝑃 x 9.81 x 10000 x (0.439)2
CFR = 2069.2 𝑥 1000 2
higher specific volume than a corresponding [ ] x 0.0415
3600
temperature steam at high pressure. A reduction in
24577.709 x P
steam pressure can also cause an increase in =
(574.77)² x 0.0415
specific volume and, for a given mass flow, an
increase in velocity. When the steam pressure is CFR = 1.79 x P
reduced during the steam blowing the velocity will Since, Main Steam Line at HRH Exit Pressure is
increase for a given output. 0.79 kg/cm2 ≈ 0.8 kg/cm2
P P P
= 1.79 x P
I. Unit # 1 (Stage 1A) = 1.79 x 0.7
CFR = 1.38
1. Super heaters (SH) Hence, CFR = 1.38 > 1.2 (Cold Re-Heat)
CFR = =
d = 0.378 m (Diameter of main steam line Q2 MCR x VMCR 𝑄2 mcr x Vmcr
at SH)
𝜋𝑑 2 𝜋 𝑥 (0.378)2
Where: k = 1.3 Constant
𝐴= = = 0.112 m2 g = 9.81 in m/ sec2
4 4
P
P
Qmcr = 2592.7 T/Hr or 720 kg/sec (SH) d = 0.748 m (Diameter of main steam line
Vmcr = 0.0132 m/sec; from, steam table, at HRH)
mollier diagram at P = 255 kg/cm2 or 250 𝜋𝑑 2 𝜋 𝑥 (0.748)2
P P
𝐴= = = 0.439 m
bar, T = 568 °C 4 4
Qmcr = 2069.2 T/Hr or 574 kg/sec (HRH)
P = Main steam line exit pressure at SH
86
IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue 10, October 2016
ISSN (Online) 2348 – 7968 | Impact Factor (2015) - 4.332
www.ijiset.com
Vmcr = 0.0653 m/sec; from, Steam tables or temporary steam blow valve. The target area in the
Mollier diagram at P = 60.8 kg/cm2 or 59.62 bar P P plate is determined to be 1600mm2. P P
and T = 596 °C
6.2.2. Acceptance criteria: The cleaning is
P = Main steam line exit pressure at HRH successfully completed when the target plate
examination fulfils the following criteria:
1.3 𝑥 𝑃 x 9.81 x 10000 x (0.439)2 No impacts ≥ 1 mm dia in an area of 1600mm2.
CFR = 2069.2𝑥 1000 2
P P
[
3600
] x 0.0653 Less than, 4 impacts ≥ 0.5mm dia in an area of
1600mm2
24577.709 x P
P
87
IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue 10, October 2016
ISSN (Online) 2348 – 7968 | Impact Factor (2015) - 4.332
www.ijiset.com
pipe regularly fails due to metallurgical defect and
welding defects. Unit # 2 M/s BHEL boiler
consumes less LDO and HFO hence takes lesser
number of blows which intern reduces number of
blowing days that is because we have taken care of
temporary pipe welding and metallurgical aspects.
More obtainable cleaning results and consequence
a minimum risk of damage is achieved more
effective keeping to scheduled set of dates is
possible. The puffing is the most preferred method
of steam blowing hence at YTPS Raichur we
adopted puffing method which as given more
effectiveness on the boiler. CFR what we have
achieved for 1st blow that we have achieved for
P P
VIII. REFERENCES
88