You are on page 1of 14

CONSIDERATIONS IN UNIT SUBSTATION DESIGN TO OPTIMIZE

RELIABILITY AND ELECTRICAL WORKPLACE SAFETY


By
David B. Durocher
Senior Member, IEEE
Industry Manager
Eaton Corporation
ABSTRACT

Many legacy low and medium-voltage unit substations installed today are based upon older designs that
took advantage of reduced first cost “opportunities” allowed by existing installation codes and standards.
Fast-forward to how these substation designs fair in safety and reliability today, particularly in industrial
process applications found in cement, pulp and paper, petroleum & chemical and others, some of the
exercised “opportunities” applied in the past begin to look more like liabilities than assets. Legacy
engineering decisions once thought to be prudent take on new meanings today, particularly when these
decisions are viewed through the lens of emerging new workplace safety standards. The critical issue of
addressing destructive arc-flash hazards associated with persons working on or around energized
electrical equipment must now be considered.

Because traditional substation designs often appeared to involve some compromise regarding both safety
and reliability, a design team of a major process industry user took a fresh look at unit substation design.
The design review took place in conjunction with construction of a Greenfield plant built in the spring of
2009 in the USA. This paper will review the design limitations of traditional unit substation configurations,
offer an overview of the alternatives considered by the Greenfield site project team, and discuss technical
and safety validation of the design that was ultimately selected and installed. Economic comparisons to
traditional designs, changes in the owner operating and safety procedures for plant personnel as a result
of the engineering design changes, and overall design acceptance by operations will also be reviewed in
this paper.

Index Terms – Process Industries, Power Distribution, Unit Substations, Design for Safety, Electrical
Workplace Safety.

INTRODUCTION

Low and medium voltage unit substations are applied universally across most every industry. At the tree-
top level, unit substations are used simply to transform medium-voltage, typically 15 to 25kV, to a lower
distribution voltage, typically 0.48 to 4.16kV, for application in supporting a host of various motor and
process equipment loads. Fig. 1 shows a typical low-voltage unit substation. In this case, the primary
assembly at the left is a medium-voltage fused load break switch. For this example, we will assume the
primary voltage is 13.8kV. For assemblies in North American industry, this assembly is typically designed
to metal-enclosed switchgear standard ANSI/IEEE Standard C37.20.3 [1]. This assembly includes a load-
break isolation switch with ratings of 600 or 1200 amperes and a medium-voltage current-limiting fuse,
appropriately sized to protect the transformer. The primary switchgear is close-coupled to a substation
transformer, either dry-type or liquid filled. The substation transformer is designed to ANSI/IEEE Standard
C.57.12 with wall-mounted primary and secondary bushings. There are many different substation
transformer design alternatives to choose from, beyond the scope of this paper. Good information on the
alternatives can be found in other technical papers, including [3]. In this case, the transformer rating is
shown at 2000kVA. With a secondary distribution voltage at 480Y/277 volts, the low-voltage bushings are
shown close-coupled to metal enclosed low-voltage switchgear. In Fig. 1, the low-voltage switchgear
consists of a 3200 ampere secondary main bus and secondary metering, with no secondary main circuit
breaker, connected to four 1200 ampere feeder circuit breakers. There are again variations on low-

978-1-4244-6409-8/10/$26.00 ©2010 IEEE


voltage switchgear designs. For process industry applications, most frequently these assemblies are
manufactured to UL1558 Standards [4].

This unit substation


assembly, installed indoor or
outdoors, remains the
480Y/277V
stalwart of power distribution
systems of today. In some 13.8kV 1200A

applications, the primary


metal-enclosed switchgear
3200A
and transformer may be 1200A

mounted outdoors and a 2000kVA


125E
secondary air terminal
5.75%Z
chamber at the transformer 1200A

will cable-feed to indoor low-


voltage switchgear. Without
a doubt, the integrated 1200A

design shown here has


been low cost and reliable Fig. 1: Typical Unit Substation today: Primary metal enclosed load interrupter
performer and in this switchgear, fused load-break switch. Transformer close-coupled liquid filled or
configuration, continues to dry/cast resin. Secondary switchgear metal enclosed with low-voltage power
be applied in many industrial circuit breakers, shown here with four feeders and no main breaker.
systems to this day.

DESIGN CONSIDERATIONS

In anticipation of the upcoming project, the design team for the Greenfield site took on the task of
investigating existing unit substation configurations carefully to identify where there may be some inherent
hidden flaws in the design. It is important to note that prevailing codes and standards regarding
installation of this equipment had an impact on the unit substation design. In the US, the prevailing
installation document that applies is the National Electrical Code (NEC) [5]. Let’s investigate two areas of
this code that impact the design and installation of the unit substation presented here.

NEC Article 240.21(C)2 Overcurrent Protection

Article 240.21(C) of the NEC addresses required overcurrent protection, specifically related to transformer
secondary conductors. The article states that “a set of conductors feeding a single load… shall be
permitted to be connected to a transformer secondary, without overcurrent protection of the
secondary…”. The article defines six conditions, specified in 240.21(C)(1) through 240.21(C)(6), under
which secondary overcurrent protection is not required. Sorting through the six options for our close-
coupled unit substation example, points us to the condition outlined in 240.21(C)(2) which most closely
applies. This condition gets fairly involved, with four different sub-conditions, all which must apply in order
to satisfy the exception of no secondary protection. Relevant language in these sub-conditions includes:

“240.21(C)(2): Transformer Secondary Conductors Not over 3 m (10 ft) Long.

(1) The ampacity of the secondary conductors is


a). Not less than the combined calculated loads on the circuits supplied by the secondary
conductors
b). Not less than the rating of the device supplied by the secondary conductors or not less than the
rating of the overcurrent-protective device at the termination of the secondary conductors.”

The first item (1) a) above requires that the engineer perform calculations to determine the total conductor
load and then specify a conductor size to support the calculated load. Referring back to the Fig. 1
example, note that the secondary conductor is specified at 3200A. So, although the total connected rated
load of the secondary feeder breakers is 4800A (four breakers rated at 1200A each), the NEC allows the
designer to assume a load diversity and size the secondary bus as some lower value. The second item
(1) b. in essence states that the secondary conductor ampacity be either greater than the overcurrent
device at which the conductors terminate (in this configuration, there is no such device) or greater than
conductor or bus rating in the equipment where the conductors terminate. From this language, it seems
clear that secondary bus protection for the unit substation is not required. There is ongoing debate in
some circles regarding the word “device” in this article, as some see the term device to mean something
other then the switchgear. Interestingly, the NEC Code Making Panel supporting this Article is reviewing
this language and considering future revision to clarify the meaning. This aside, note also that Article
240.21(C) includes a Fine Print Note stating “For overcurrent protection requirements for transformers,
see 450.3.

NEC Article 450.3 Equipment – Transformers

Article 450.3 of the NEC addresses secondary overcurrent protection of transformers. Note 2 for Table
450.3(A) states: “Where secondary overcurrent protection is required, the secondary overcurrent device
shall be permitted to consist of not more then six circuit breakers or six sets of fuses grouped in one
location”. Traditionally referred to as the “six disconnect” or “six handle” rule, this provision allows the user
to forego secondary overcurrent protection in a unit substation, provided there are no more than six
feeder devices in the assembly. For the example shown in Fig. 1, this is clearly the case, so this assembly
could be installed without concern that the design would violate the applicable installation code.

APPLICATION WAKE-UP CALL

Although the “six feeders – no main” unit substation passes all requirements outlined in the applicable
standards, the unit substation equipment manufacturer and the project team investigating design
alternatives were not satisfied this was the best approach. Earlier experiences in industrial plants where
arc-flash studies have been performed as outlined in NFPA-70E [6] using calculation methods in
IEEE1584 [7] yielded some very revealing and disturbing results. In the event of a secondary bus fault,
the NFPA-70E standard requires that the upstream overcurrent protective device be used in determining
the available arcing current. In this case, the current-limiting fuse on the primary of the substation is the
device used in the calculation. Specifically, Fig. 2 below shows calculations revealing arc flash energies
2
at the secondary switchgear in excess of 700 calories/cm . These levels are defined in IEEE1584 as
UNAPPROACHABLE, where effectively no Personal Protective Equipment (PPE) would be adequate in
safeguarding personnel should a bus fault occur while persons were working on the energized substation.
In many existing facilities, unit substation feeder devices were used as a lockout/tagout point while
downstream equipment was being serviced or maintained. The elevated arc flash energies effectively
made it unsafe to rack-out a secondary feeder breaker while the secondary bus was energized. In
process industry applications where electrical workplace safety is paramount and energized
lockout/tagout is common, the “six feeders – no main” unit substation design was simply no longer a
practical option. A number of vintage unit substations that employed the configuration shown in Fig. 2,
have effectively been upgraded to improve reliability and electrical safety. Although beyond the scope of
this paper, one such upgrade is presented in the case study outlined in [8].

Returning to the primary current-limiting fuse in the unit substation shown in Fig. 2, selecting the rating of
this fuse to account for transformer inrush results in a melting time requirement up to 12X the transformer
rated primary current for 0.1 seconds. In the 2000kVA substation shown in Fig. 2, a 125E fuse is applied.
A bolted secondary fault would result in a primary current of less than 1000 amps, resulting in a fuse
clearing time of over 2 seconds. The example calculation assumes an arcing fault of 10,000 amperes on
the secondary bus, resulting in a fuse clearing time of 160 seconds. In either the case of a bolted fault or
an arcing fault, the secondary arc flash energy on the secondary bus of this unit substation design is
UNAPPROACHABLE. In addition, should a bus fault occur while this assembly was energized, the likely
result beyond extremely high arc flash energies would be extensive equipment damage caused by the
heat energy developed before the primary fuse would clear. In a process industry environment, this
translates to hours or perhaps days of downtime. In the end, the primary fuse in the 13.8kV fused load-
break switch shown in Fig. 2, is intended to protect the transformer, not the secondary bus. Adding a
secondary main circuit breaker would resolve this issue of protection in some applications. This would in
480Y/277V
13.8kV 1200A

3200A
1200A

2000kVA
125E
5.75%Z
1200A

1200A

Arc Flash & PPE


Bus Fault at 480V Switchgear NFPA70E: Fault at 480V Switchgear Bus
• 10kA Secondary Arcing Fault • 31.8kA Symmetrical Fault current
• At 13.8kV = 348A primary fault • 1167” AF Boundary
125E fuse clearing time = 160 seconds • 702.4 cal/cm2 @ 18”
• UNAPPROACHABLE
NFPA70E-2009: Category 4 is
highest category @ 40 cal/cm2

Fig. 2: Limitations of existing unit substation designs have been identified for existing plants after arc-flash hazard
assessments in accordance with IEEE1584 have been performed. In this example, an arcing fault at the unit
2
substation secondary bus results in a calculated incident energy of 702.4 cal/cm .

effect protect the secondary bus downstream of the main breaker. However, the bus from the transformer
secondary terminals up to the main is still not adequately protected.

In applications where the primary assembly and transformer are outdoors and cable connected to the
secondary switchgear, the secondary bus protection issue becomes more problematic. Clearly, an
opportunity existed for the project design team to consider design alternatives that would offer better
performance, both in reliability and workplace safety.

A PATH FORWARD VIA PRODUCT TECHNOLOGY

Recognizing the limitations of the legacy unit substation design, the project team worked with the power
distribution equipment supplier to review alternative designs that might offer improved performance.
Because of the extreme hazard and potential for extended outage time, the group quickly dismissed the
age-old approach of installing unit substations based on the “six feeders - no main” design. The strategy
was to look at designs that included a secondary main overcurrent protective device (in this case, a low-
voltage power circuit breaker) and then investigate design alternatives that might offer advantages to this
design approach. The group recognized that adding a secondary main device would add cost and was
interested in alternatives that might perform as well, or better, than the secondary main design.

The group considered several emerging technologies that might offer improved performance. Three
technologies were considered and ultimately applied. These are discussed below:
15kV Vacuum Primary Circuit Breaker
One technology that appeared promising was in the area of medium-voltage vacuum circuit breakers. The
group believed that application of a low-cost circuit breaker in the primary of the unit substation, providing
both primary and secondary current protection, would be a desirable alternative to the traditional fused
load-break switch. Although vacuum circuit breakers have traditionally involved higher space and cost
than a fused switch, some manufacturers had developed newer vacuum breakers that looked promising.
Fig. 3 shows and example of one such design available. In the North American markets, vacuum circuit
breakers are manufactured to ANSI Standard C37.20 [9]. Inspired in part by a trend toward global design
standards, traditional designs have given way to newer offerings that are smaller, lighter, and have
improved functionality. As is shown in Fig. 3, although the newer design vacuum breakers are only
available in limited ratings, most offer a smaller size with fewer parts. Notably different from traditional
vacuum circuit breakers,
the new design includes
an integral trip unit with
linear trip actuator. This
actually offers improved
performance with reduced
clearing times, in part due
to the smaller sized
component. Where
traditional vacuum circuit
breakers require 5 cycles
total clearing time, the
newer vacuum breaker 15kV Vacuum Circuit Breaker 15kV Vacuum Circuit Breaker
can in some applications, ‹25”H X 20”W X 18” D, 330 lbs ‹ 31”H X 29.5W X 25”D, 460 lbs
clear a fault within 3 ‹ANSI C37.20 Rated at 25 and 40kA ‹ ANSI C37.20 Rated at 25, 40 and 50kA
cycles. In unit substation ‹600, 1200,2000 and 2500A ratings ‹ 1200, 2000, 3000 and 5000A ratings
Integral trip unit with linear trip actuator
applications where higher ‹
‹ External relay required
‹2-step stored energy mechanism 2-step stored energy mechanism
ratings are not as ‹

important as in medium- Fig. 3: Newer design 15kV class vacuum circuit breakers are manufactured to
voltage switchgear line- the same standards as previous versions, but are smaller, lighter, and have
ups, the newer design increased functionality. Shown above is a comparison of the newer design at
breaker offers a viable left and traditional design at right. The new design shown includes an integral
alternative. multifunction trip unit.

Zone Selective Interlocking

Zone selective interlocking for low and medium-voltage circuit breakers has been an available technology
for many years and most all manufacturers offer this feature as a standard offering for low-voltage power
circuit breakers. The application is reviewed here and discussed relative to Fig. 4 below. Fig. 4 shows the
configuration of a typical low-voltage switchgear assembly in a low-voltage substation with a main power
circuit breaker and three feeder circuit breakers. Zone selective interlocking is a functionality of the circuit
breaker tripping system. In
this example, all four M1

breakers (the main and


thee feeders) are
connected together with a ZSI
SD=
common zone control Control
0.5S
circuit. The main and wires
feeders are selectively
coordinated so that the (2) Bus Fault
breaker nearest the fault F1 F2 X F3
clears first. A slightly
longer short time delay
setting for the main SD= SD= SD=
breaker is used to assure 0.2S 0.2S 0.2S
the system is selectively
coordinated. In the event
of a downstream fault
shown at (1) on Fig. 4, the X (1) Downstream Fault
feeder breaker nearest the
fault would trip, following Fig. 4: A block diagram example of unit substation low-voltage switchgear is
the short-time delay setting shown with zone selective interlocking applied. In the event of a bus fault,
the ZSI controls will trip the main breaker with no intentional delay.
of 0.2 seconds or 12.5
cycles on a 60 hertz system. If however a bus fault shown at (2) on Fig. 4 occurred, the main circuit
breaker would be called upon to clear the fault. Without zone selective interlocking, the breaker short-time
delay trip setting of 0.5 seconds or 30 cycles would dictate the clearing time. A zone selective interlocking
(ZSI) control connection between all circuit breakers adds intelligence to this system. When a bus fault
occurs, ZSI allows the main breaker to interrogate the feeder breakers in the zone to determine if they
“see” a fault as well. If all report back that there is now downstream fault, then the main breaker will trip
with no intentional delay.

The ZSI feature is simple to enable and can offer significant advantages in reducing potential arc flash
hazards described previously. For a typical low-voltage system capable of delivering 35,000 amperes
symmetrical fault current, calculations in accordance with IEEE1584 show that adding ZSI can reduce the
2 2
incident energy from 43.7 calories/cm to 7.0 calories/cm . The NFPA70E Standard for Electrical Safety in
the workplace defines the first condition above as UNAPPROACHABLE and the second as Hazard Risk
Category 2, a significant difference.

Multiple Settings Groups

One final technology applied in today’s power distribution systems is a newer capability offering multiple
settings group capability for protective relays used with circuit breakers. Although this capability has been
a feature for several years on a few higher-end protective relays used in medium-voltage systems,
several tripping systems applied in integral trip units of low-voltage power circuit breakers now also
include this feature. In a similar concept described above in ZSI applications, use of multiple settings
groups for circuit breaker tripping enables the tripping system to respond differently for different system
conditions. Again, referring to Fig. 4, if a downstream fault condition existed, the feeder circuit breaker
setting would dictate that the 0.20 second short-time delay setting time out before the breaker trips. The
power systems engineer determines this setting to assure coordination with downstream overcurrent
protective devices and system loads so that the device nearest the fault trips first. In some cases for
instance, large downstream motors may have high inrush currents or long acceleration times that will
affect the short-time setting of the feeder breakers in the unit substation. As discussed previously, adding
an intentional delay to a breaker clearing time comes at the cost of higher incident energy and arc-flash
hazards. When personnel are working in downstream equipment, such as a low-voltage motor control
center, the opportunity for a dropped tool or accidental contact of a tool or probe between an energized
conductor and ground is increased. As this could lead to a higher incident of short circuits or arc-flash
incidents, it is often prudent to reduce trip settings to enable the upstream circuit breaker to trip faster.

Multiple settings groups effectively allow for the power systems engineer to establish one group of
protective settings during normal operations and another “maintenance mode” setting that can be used
while personnel are working in downstream equipment. Fig. 5 illustrates application of the multiple setting
group technology. At the left of Fig. 5, the integral Long-time, Short-time, Instantaneous & Ground (LSIG)
integral trip unit mounted in the low-voltage power circuit breaker is equipped with an on-off switch that
enables a second “group” of settings. In the normal mode, the power systems engineer settings are
based on a selectively coordinated system, while in the maintenance mode, the LSIG settings are
replaced with an instantaneous only setting, effectively disabling the normal short-time settings. The
result is a faster clearing time of the circuit breaker should a downstream fault occur. At the right of Fig. 5,
note that the before and after coordination curves are shown to demonstrate the impact of the
maintenance setting. The selectively coordinated curves set at the left shows the main and feeder circuit
breaker curves and plots a short-circuit current of 5,600 amperes. Note that due to the short-time delay
setting for the feeder circuit breaker, the time to clear this lower level fault is extended. The curve set on
the far right shows the maintenance mode enabled, which effectively shifts the instantaneous setting of
the feeder breaker to the left. The result in this example is a reduction in arc-flash energy from 11
2 2
calories/cm to less than 4 calories/cm . This demonstrates the advantage of the multiple setting group
feature.

The maintenance (or instantaneous only) mode actually allows for faster clearing times than the normal
instantaneous settings, in part because the tripping system responds to peak currents as opposed to the
normal RMS or root mean squared currents. Since the tripping system is not burdened with the additional
RMS calculation before sending a signal to the circuit breaker to trip on overcurrent, the time to actually
open the breaker contacts during a fault is reduced. Typically, instantaneous clearing times can occur in 3
cycles rather than the standard 5-cyle trip for this class of circuit breaker. Although clearing in an
additional 2 cycles (32 milliseconds) seems insignificant, this actually can mean a difference in the
Hazard Risk Category, typically reducing the hazard from HRC2 to HRC1.

It is important to understand that the multiple settings group capability does represent a trade-off on two
different fronts. First, depending on the instantaneous setting selected, selective coordination of the
system may be compromised. In the Fig. 5 example, note that the curve to the far left of the plot (brown in
color) represents an across-the-line start of the largest motor fed by this substation feeder breaker. In the
selectively coordinated setting, starting this motor would assure this motor could be started without a
feeder breaker trip. However, in the maintenance mode, note from the curve set at the right that the
feeder breaker would indeed trip. Second, application of multiple settings group functionality dictates that
facility maintenance practices be revised and then adhered to. Maintenance persons will need to adopt a
process where the maintenance mode could be safely engaged while downstream energized work is
being performed, and also be assured that the protective settings were returned to normal after
maintenance is completed. It would be typical for the maintenance mode settings to be enabled with a
lockable switch and door-mounted light so this alternative maintenance setting could be included in the
facility lockout/tagout procedure.

Finally, it is important to note that the Occupational Safety and Health Administration (OSHA) clearly
prohibits work on energized equipment. Specifically, OSHA 29 Code of Federal Regulations (CFR) Part
1910.333 (a)(1) [9] requires that live parts be deenergized before an employee works on or near them.
There is simply no argument that turning the power off results in the safest working condition. However, in
some process industry environments, deenergizing the power system is simply not practical and at times
can result in an even greater hazard.

LSIG Trip Unit

AF Current = 5.6kA AF Current = 5.6kA


HRC = 3 (11 cal/cm2) HRC = 1 (< 4 cal/cm2)
Fig. 5: Newer designs of stand-alone and integral circuit breaker trip units include capabilities for multiple settings
groups. Selectively coordinated settings can be overridden by an instantaneous only setting while downstream
maintenance is being performed. At the center are the selectively coordinated coordination curves. At the right, the
feeder breaker instantaneous setting is shifted, enabling the breaker to clear the fault faster during a lower level
arcing fault.
THE GENESIS OF A NEW SUBSTATION DESIGN

Application of the various technologies discussed in the previous section came to fruition in upgrading
several existing unit substations at an integrated pulp and paper mill in the Western United States.
Following a facility wide effort to update power systems studies to achieve compliance with NFPA70E, the
site engineering team discovered that most of the areas of very high or UNAPPROACHABLE incident
energies as calculated by the system study were at the secondary bus of low-voltage unit substations. In
fact, the results of the study include actual calculated incident energy values for one of the 2000kVA
substations reviewed previously with the results as shown in Fig. 2. In this facility, since most existing unit
substations were already installed, adding new protective devices such as a secondary main low-voltage
circuit breaker was not practical. There simply was no room to add new assemblies. Fig. 6 shows what
was ultimately installed. The existing unit substation was upgraded by removing the medium-voltages
fuses in the existing fused load-break switch, and replacing them with a new fixed-mount vacuum circuit
breaker. Adding a vacuum breaker with an integral overcurrent trip unit at the primary allowed the ability
to add secondary current sensors at the transformer secondary spade connections, resulting in
secondary bus overcurrent protection. In addition to the integral trip unit, a second overcurrent protective
relay along with primary current transformers was added to protect the transformer, a necessary addition
after the primary fuses were removed to make room for the vacuum breaker. In this application, the site
engineering team elected to add multiple settings group functionality to the vacuum breaker integral trip
unit. This allowed for an additional maintenance setting that could be used when necessary. In this case,

Improved Unit Substation Design 15kV Vacuum Breaker

LV Substation with Retrofit Vacuum Primary Breaker

50/51
Relay

86

ST
Integral
50/51 Relay

Before After
Arc Flash Study Results
Sym. Fault at 480V Switchgear Bus 31.8kA 31.8kA
AF Boundary 1167” 18”
2
Cal/cm 702.4 1.4
NFPA70E HRC Unapproachable 1

Fig. 6: Unit substation retrofit included a vacuum breaker installed at the primary. Both primary and secondary
overcurrent protection was installed, reducing incident energy at the secondary switchgear main bus from 702.4
2 2
cal/cm to 1.4 cal/cm .

the maintenance setting was used primarily when the existing secondary draw-out power circuit breakers
were being racked onto or off of the energized secondary bus. The site routinely used the secondary
feeder breakers as a convenient systems location to perform lockout/tagout of downstream loads. In a
continuous process environment, it was not practical to deenergize the unit substation to perform this
work. Before the substation upgrade, the extremely high incident energies at the secondary bus
effectively prohibited removal of secondary feeder breakers. Further details outlining this unique solution
that improved both the safety and reliability of unit substations at this mill site are explained in the award
winning paper referenced previously [8].

THE GREENFIELD SITE DESIGN SELECTION

Drawing upon new technologies and unit substation retrofit experiences described previously, the design
team for the Greenfield industrial plant drove toward the optimum design. The group determined early-on
that secondary bus protection, either via a secondary main circuit breaker, or from a vacuum primary
breaker with secondary current sensors was required. Past experience proved that selection and
application of a primary fuse to protect the transformer and expect this device would also adequately
protect the secondary bus, was a poor design approach.

Because the new site required both low-voltage (480Y/277V secondary) and medium-voltage
(4160Y/2400V secondary) unit substations, the design team decided to move to application of a primary
load-break switch over a fixed mounted vacuum circuit breaker at the primary as a standard platform for
both low and medium-voltage unit substations. A product was commercially available that was configured
as shown in Fig. 7. Note from the section-view at the right that the incoming power enters at the top-rear
of the assembly. The incoming cable termination is designed to accommodate a typical drip loop and also
has room so that medium-voltage cables can be looped in and out of the assembly to feed an adjacent
unit substation. Above the load-break switch is a distribution class lightning arrestor to protect the
incoming of each substation. Bus runbacks on the load-side of the switch include current transformers,
connected at the vacuum breakers to support primary overcurrent protection of the transformer. The
vacuum breaker in the lower compartment includes an integral trip unit. Note also at the lower rear of the
assembly is a snubber network, the purpose for which is described below.

LA

Line

LB
Switch

Vac Bkr

Snubber

Load

Fig. 7: Greenfield site included 11 low and medium-voltage unit substations, each with a primary load-break
switch over a fixed mounted vacuum circuit breaker configured as shown. This replaced previous fused load-
break switch designs, adding secondary bus overcurrent protection.

Vacuum Interrupters and Chop Currents


One phenomenon which is not widely discussed or understood is the potential for voltage transients that
occur when the vacuum interrupter in a vacuum circuit breaker opens an inductive load. One of the
physical characteristics of all vacuum interrupters (VI) is a phenomenon called chop current. When the
contacts of a VI open, current continues to flow through the arc drawn across the contacts within the
vacuum bottle. In an ac sine-wave, as the current approaches zero, the energy across the arc cannot be
sustained within the vacuum. When the arc energy reaches a low current level, the arc is immediately
quenched and the current is driven to zero nearly instantaneously. The current value where the energy
collapses to zero for a VI is known as the chop current. All VI’s have this chop current characteristic and
this value will typically be published by the VI manufacturer. Often on the order of 6 to 10 amperes, chop
current is a function of the VI design itself, including geometry, material composition, hardness of the
contact surface and other physical characteristic. Because energy cannot be created or destroyed
instantaneously, driving current to zero with very high di/dt results in corresponding voltage transient
dv/dt, when switched into an inductive load. Although VIs are typically applied in medium-voltage
switchgear and motor controllers where hundreds of feet of cable connect the vacuum breaker element to
the supported load, in this unit substation application the vacuum circuit breaker is often within 10 feet of
the transformer primary winding.

Transient studies performed by the equipment manufacturer’s power systems engineering group proved
that voltage transients caused failure of the primary winding of a number of substation transformers. Fig.
8 shows one such transformer, a vacuum pressure impregnated (VPI) dry-type design that failed turn-to-
turn at the first primary winding. In this application, voltage transients caused due to VI current chop
exceeded the Basic Impulse Level (BIL) of the transformer design. Fig. 9 shows the results of a transient
study with the VI opening as a chop current of 6 amperes as shown at the left, resulted in a
corresponding voltage transient as shown at the right. Note from Fig. 9 that the negative peak voltage
transient is nearly 150kV, exceeding the 95kV BIL rating of most 15kV class substation transformers.
Transformer Failure On VI De-Energization

Flash/Burn Marks

Coil to Coil Failure

Fig. 8: Unit substation dry-type transformer field failure likely caused by VI switching transients.

Current Waveforms Without Snubbers Voltage Waveforms Without Snubbers


150

60
Ichop 100
40

50
20
+6 amps
0 0

- 20
- 50

- 40
- 100

- 60
-150kV!
- 150

Fig. 9: Chop current of the vacuum interrupter shown at left result in very high voltage transients shown at right.

To curtail the severe voltage transients caused due to the VI in close proximity to the transformer
inductive load, the equipment manufacturer designed a simple Resistor-Capacitor AC snubber network.
This snubber, comprised of three single-phase 15kV class capacitors and series connected resistor
elements, was connected on the load terminals of the vacuum breaker assembly. The snubber assembly
was mounted as a component in the substation primary medium-voltage load break switch and fixed
vacuum breaker assembly. Fig. 10 shows a photo of one of the three-phase snubbers at the center and
three single-phase assemblies at the far right. At the left, the resulting impact from adding the R-C
snubber as calculated from the transient study shows that the peak voltage transients have been
significantly reduced – in this example to a level below 30kV.

Voltage Waveforms With Snubbers


30

20

10

- 10

- 20

- 30 -30kV

Fig. 10: Addition of an R-C snubber assembly installed in the primary metal-enclosed switchgear to attenuate
voltage transients. A single-phase resistor capacitor snubber shown at center and three of these assemblies
mounted in the switchgear at right.

Putting it all Together

Since the site would apply cast resin coil design transformers, the entire unit substation assembly was
designed for close-coupled indoor application. A rigorous analysis of several alternative unit substation
configurations was completed as a part of the process. Particular focus on the unit substation first cost for
various alternatives was reviewed to assure the improved design alternatives were not adding
significantly to the cost. Table I shows the first cost of several alternative designs considered. Note that
the values shown are estimates, as the relative magnitude comparing one design versus another is the
relevant issue. Because the economic modeling suggested that applying a primary load-break switch over
a fixed mounted vacuum circuit breaker with an integral trip unit was the best overall selection, the design
team elected to establish this approach as the Greenfield site standard for both low-voltage and medium-
voltage unit substations. The team selected a metal-enclosed assembly at the primary of each unit
substation, built to the ANSI Standard C37.20.3 [10]. As shown in Table I, a metal-clad assembly, built to
the ANSI Standard C37.20.2 [11] was also considered. This design included a draw-out vacuum breaker
and no visible load-break switch. Ultimately, the metal-clad draw-out design was dismissed, as it proved
more costly and lacked the feature of a visible blade incoming disconnect device, a valuable feature
which was used as a part of the company lockout/tagout safety procedure.

TABLE I
SUBSTATION ALTERNATIVES PRIMARY SUBSTATION SECONDARY TOTALS
SWGR XFMR SWGR
2000kVA: 13.8kV TO 480Y/277V, 600A LB SW & $19,000 $90,000 $88,000 $197,000
FUSE, LIQ TRX, 3200A MCB, 4-800A FCB’S
2000kVA: 13.8kV TO 480Y/277V, 600A LB SW & $31,000 $90,000 $72,000 $193,000
VAC BKR, LIQ TRX, 3200A BUS, 4-800A FCB’S
2000kVA: 13.8kV TO 480Y/277V, 600A LB SW & $17,000 $165,000 $86,000 $268,000
FUSE, CAST TRX, 3200A MCB, 4-800A FCB’S
2000kVA: 13.8kV TO 480Y/277V, 600A LB SW & $29,000 $165,000 $70,000 $264,000
VAC BKR, CAST TRX, 3200A BUS, 4-800A FCB’S
5000kVA: 13.8kV TO 4160Y/2400V, 600A LB SW $19,000 $175,000 $118,000 $312,000
& FUSE, LIQ TRX, 1200A MCB, 2-1200A FCB’S
5000kVA: 13.8kV TO 4160Y/2400V, 600A LB SW $31,000 $175,000 $85,000 $291,000
& VAC BKR, LIQ TRX, 3200A MCB, 4-800A FCB’S
THE NEXT GENERATION OF UNIT SUBSTATION DESIGN

The design team selected the new unit substation design based on leveraging power distribution
equipment technologies to improve system safety and reliability. The selected design was applied to 11
new unit substations installed at the plant site; two medium-voltage unit substations (10MVA and 5MVA
with a secondary voltage of 4160V) and nine low-voltage substations (all at 2000kVA with a secondary
voltage of 480Y/277V. Both medium-voltage and low-voltage substations were installed with high
resistance grounding systems, application described in [12] and [13], which eliminated the possibility of a
phase to ground fault, further enhancing system safety and reliability. A typical low-voltage substation
one-line diagram is shown in Fig. 11. In this application, the project team applied the smaller, low-cost
vacuum circuit breaker technology and also zone selective interlocking as described in Section IV above.
From Fig. 11, note that the 15kV class vacuum breaker is connected to primary bus current sensors, and
a separate overcurrent relay with current transformers mounted at the secondary bus is set-up to shunt
trip the primary vacuum breaker in the event of a secondary bus fault. In this configuration, the multiple
settings group capability of the vacuum breaker integral trip unit was not used. Instead, the team elected
to opt for a zone selective interlocking scheme, with control connections between the separate
overcurrent relay and the secondary low-voltage power circuit breaker trip units. In this scheme, a bus
fault would result in the primary vacuum breaker tripping with no intentional short-time delay. The design
team made the choice to not take advantage of the faster clearing times available with the multiple setting
group capability discussed previously, primarily because the company felt that revising their established
safety procedures for lockout/tagout could potentially cause confusion for plant operators. By definition,
the multiple setting group approach required that the system studies be run in two different protection

Substation One-Line
As-Installed Primary Protection

(3) 200:1 CURRENT SENSORS

MV
VCB 50
L,S,I 51
600AF
200AT
50 ZSI
OC Relay 51

(3) 3200:5 CT

(3) 3200:5 CT

LV LV LV LV
ZSI PCB ZSI PCB ZSI PCB ZSI PCB
L,S,I L,S,I L,S,I L,S,I
800AF 800AF 800AF 800AF
800AT 800AT 800AT 800AT

Fig. 11: Greenfield site installed unit substation design. Metal enclosed primary switchgear; 15kV load-break switch over
a fixed mounted vacuum circuit breaker. Integral breaker trip unit used for primary transformer protection, separate
overcurrent relay mounted in the secondary switchgear with 86 lockout relay and shunt-trip used for secondary bus
protection. ZSI connection between secondary overcurrent relay and all 480V low-voltage power circuit breakers.
modes and required that operators would engage the instantaneous only mode during maintenance and
also remember to switch things back to the normal settings after maintenance was performed.

An alternate configuration that takes advantage of the multiple setting group capability is shown in Fig.
12. In this case, secondary bus protection is supported by current sensors connected to the vacuum
circuit breaker integral trip unit, and primary protection is accomplished via a separate overcurrent relay
connected to primary current transformers. There is a slight advantage in applying this configuration as
opposed to the selected configuration discussed above and shown in Fig. 12. Using the multiple settings
group capability in a maintenance mode improves the primary breaker clearing time from 5-7 cycles down
to 3 cycles – thus, reducing the downstream arc flash energy should a bus fault occur. The tradeoff here
is of course that maintenance and operations need to embrace this approach and be willing to adopt new
lockout/tagout procedures to support this.

Results from this new approach were very significant. After the power systems design studies were
completed and all settings were completed in the field, the facility was outfitted with arc flash and shock
hazard labels. The studies confirmed that the entire electrical system, both low and medium-voltage,
delivered arc flash hazards below 8 cal/cm2, or a Category 2 PPE requirement. This was very welcome
news to plant operations, since the facility PPE standards included company provided Category 2 PPE for
all electrical maintenance personnel. So, no special PPE was necessary on the rare occasion that work
be required on energized equipment anywhere in the facility. The design team was very pleased with
these results.

Substation One-Line
Alternate Primary Protection

(3) 200:5 CT

MV ZSI 50
VCB 50 51
L,S,I 51
600AF OC Relay
3150AT

(3) 3150:1 CURRENT SENSORS

(3) 3200:5 CT

LV LV LV LV
ZSI PCB ZSI PCB ZSI PCB ZSI PCB
L,S,I L,S,I L,S,I L,S,I
800AF 800AF 800AF 800AF
800AT 800AT 800AT 800AT

Fig. 12: Alternate unit substation design. Metal enclosed primary switchgear; 15kV load-break switch over a fixed
mounted vacuum circuit breaker. Integral breaker trip unit with multiple settings group maintenance feature used for
secondary bus protection, separate overcurrent relay mounted in the primary switchgear with 86 lockout relay and
shunt-trip used for primary transformer protection. ZSI connection between integral overcurrent relay and all 480V low-
voltage power circuit breakers.
CONCLUSIONS

As new challenges emerge in power distribution systems reliability and electrical workplace safety, it is
the responsibility of the systems designer to seek out new approaches and solutions that address them.
Stepping back and looking at the big picture, the systems designer has an onerous responsibility in
specifying or selecting the best designs. Design decisions made today will impact cost, safety and
serviceability of the installed systems for 40 or 50 years during the useful life for the owner. Studies have
shown that this cost is an order of magnitude of 7 to 10 times the installed cost of the power distribution
equipment.

The work by the project design team in this effort is considered a significant step forward in innovation in
unit substation design. In the current environment of emerging codes and standards such as NFPA70E,
focused on improved electrical workplace safety, the obvious first choice for any power systems designer
is to design the hazard out. Industry must continue to increase focus on Safety By Design as the most
effective approach in minimizing electrical hazards while improving system reliability. Developments such
as those described in this paper are considered a driving force in establishing accomplishing this
objective.

REFERENCES

[1] American National Standards Institute ANSI/IEEE Standard for Metal-Enclosed Interrupter
Switchgear, November 2001
[2] American National Standards Institute ANSI/IEEE Standard for Three Phase Power Transformers,
March 2000 (?)
[3] Considerations in Application and Selection of Unit Substation Transformers, IEEE Transactions on
Industry Applications, Volume 38, May-June 2002, pgs 778-787.
[4] UL1558 Standard for Metal-Enclosed Low-Voltage Power Circuit Breaker Switchgear, February
1999.
[5] National Fire Protection Agency NFPA70 – National Electrical Code, 2008 Edition.
[6] National Fire Protection Agency NFPA70E Standard for Electrical Safety in the Workplace, 2009
Edition
[7] Standard 1584, IEEE Guide for Performing Arc-Flash Hazard Calculations. September 2002
[8] Distribution Equipment Modernization to Reduce Arc Flash Hazards, Hopper, W.S, Etzel, B.L., IEEE
Transactions on Industry Applications, Volume 38, Volume 44, Issue 3, May-June 2008, pgs 940-948
[9] 29CFR1919.301 to .399, OSHA Sub Part S, Electrical Installations, National Archives and Records
Administration, Washington DC, 2007
[10] American National Standards Institute ANSI C37.20.3-2001, IEEE Standard for Metal-Enclosed Load
Interrupter Switchgear, November 2001.
[11] American National Standards Institute ANSI C37.20.2-1999, IEEE Standard for Metal-Clad
Switchgear, October 1999.
[12] R. Beltz, I. Peacock, W. Vilcheck, “Application Considerations For High Resistance Ground
Retrofits”, Conference Record, 2000 IEEE IAS PPIC, pgs X-XX.
[13] A.S. Locker, M.S. Scarborough, “Advancements in Technology Create Safer & Smarter HRG
Systems”, Conference Record, 2008 IEEE IAS PPIC, Pgs X-XX

You might also like