Professional Documents
Culture Documents
Worked Example-Pavement Design-Tanzania - 281119 PDF
Worked Example-Pavement Design-Tanzania - 281119 PDF
Worked Example-Pavement Design-Tanzania - 281119 PDF
Worked Examples
Pavement and Materials Design Manual -1999
Summary of axle load survey and equivalency factors. Assessment of axles heavier than
13 tonnes. (Chapters 4.2.2, 4.2.3 and 4.2.4 )
D irection 1 D irection 2
Vehicle
Avg. Avg. Total E80 from all E80 from Avg. Avg. Total E80 from all E80 from axles
category Gross VEF No. of axles axles heavi er Gross VEF No. of axles heavi er than
wt.(ton) (80 kN) veh. than 13 tonnes wt.(ton) (80kN) veh. 13 tonnes
From the heaviest loaded direction, proportion of E80 made up from axles heavier than 13tonnes (in direction 2):
= (b/a) x 100 = (895.26/3730.60) x 100 = 24%
This value is less than 50%, thus the Traffic Load Class will not be denoted heavy (-H) and no special measures are
required in the pavement design or design of improved subgrade.
Traffic growth and design traffic loading (Chapters 4.2.5 and 4.2.6)
D irection 1 D irection 2
D ai ly counts 13 19 10 20 13 21 11 20
Use the heaviest direction in axle loading for calculating the traffic loading, in this case direction 2. The cumulative
number of standard axles, E80 = 365 x t1 x (1 + I)N - 1
i
where: t1 = average daily number of standard axles in the year of traffic survey
i = annual growth rate expressed as a decimal fraction
N = calculated period in years
Substituting: t1 = 468
i = 0.035 for all heavy vehicle categories
The cumulative number of E80 for the design period and the time from present until completed pavement
construction is calculated using (20 + 3) = 23 years, and let be denoted as E8023.
E8023 = 365 x 468 x (1 + 0.035)23 1 = 5.9 million E80
0.035
The cumulative E80 for the time from present to completion of pavement construction is calculated using 3 years,
and let be denoted as E803.
E803 = 365 x 468 x (1 + 0.035)3 1 = 0.5 million E80
0.035
Input data
n Traffic: TLC 3.
n Climate: Moderate.
n Alignment: Shallow embankment or cuttings throughout the route.
n Subgrade CBR: 3, 4, 5, 5, 6, 7, 7, 8, 8, 8, 9,10, 6, 8, 9, 9, 9, 11, 12, 12, 14
The use of standard deviation in a normal distribution ( MEAN - 1.3 x std.dev ) gives excessively conservative
results. A direct use of the measured CBR values and exclusion of 10% of the number of tests shall be the applied
method.
For cuttings, use the lowest CBR value for the section (Chapter 5.2.3)
Section 2 in a cutting has a CBR of 7% as its lowest.
150mm
Lower layer G7 not required
4
CBR(%)
The CBRdesign value is obtained by normal rounding off the 90%-ile value.
Section 2
Cutting, lowest CBR is used as CBRdesign.
Section 3
CBR values plotted
in ascending order
16
CBR data
14
6
8 12
CBR(%)
9 10
9 8
9
6 n = 9 tests
11 90%-ile d = 0.1 x (n-1)
12 7,6 4 = 0.8
d=0.8
12 CBR DESIGN 2
14 8% 0
1 2 3 4 5 6 7 8 9
Test
The CBRdesign value is obtained by normal rounding off the 90%-ile value.
B C
Chainage Rutting Difference CUSUM
Plotting of CUSUM against Chainage
measured from average (Accumulated
[Km] [mm] (A - B ) values of C )
1 14 -1,2 -1,2
2 13 -0,2 -1,4 Homogenous sections
3 15 -2,2 -3,6
4 14 -1,2 -4,8
5 13 -0,2 -5,0 10
6 14 -1,2 -6,2 5
7 7 5,8 -0,4
0
CUSUM
8 9 3,8 3,4
9 8 4,8 8,2 -5
10 13 -0,2 8,0 -10
11 15 -2,2 5,8 -15
12 18 -5,2 0,6 -20
13 14 -1,2 -0,6 0 2 4 6 8 10 12 14 16 18 20 22 24 26
14 16 -3,2 -3,8
15 14 -1,2 -5,0 Chainage
16 14 -1,2 -6,2
17 15 -2,2 -8,4
18 18 -5,2 -13,6 Interpretation of data:
19 14 -1,2 -14,8
15 A change of slope indicates change of conditions along
20 -2,2 -17,0
the data. Four distinct homogenous sections can be seen
21 9 3,8 -13,2 in the above chart.
22 10 2,8 -10,4
23 9 3,8 -6,6
24 12 0,8 -5,8
25 9 3,8 -2,0
26 11 1,8 -0,2
Average: A = 12,8
Input data:
Two homogenous sections of a pavement rehabilitation project with granular base course have the following
deflection data after more than 20 measurements had been taken on each section:
Section 1:
n mean: 0.73 mm standard deviation: 0.029 mm
Section 2:
n mean: 0.79 mm standard deviation: 0.086 mm
Design deflection:
Calculate design deflection for each homogenous section:
Section 1: (mean deflection) + 1.3 x (standard deviation)
= 0.73 + 1.3 x 0.029 = 0.77 mm
Section 2: (mean deflection) + 1.3 x (standard deviation)
= 0.79 + 1.3 x 0.086 = 0.90 mm
Residual life
Section 1: Residual life = expected life past traffic loading
= (4 2) million E80 = 2 million E80.
Section 2: Residual life = expected life past traffic loading
= (3 2) million E80 = 1 million E80.
Strengthening of the pavement is required since the residual life is less than the future design traffic loading.
Target deflection
Sections 1 and 2: Future traffic loading of 8.0 million E80 plus 2.0 million E80 past traffic loading gives a target
deflection = 0.53 mm /Figure 9.5/
Input data:
CBR = 8%
Old AC a1 = 0.18 t1 = 60mm SNdiff = SNrequired - SNexist = 2.35 - 043 =1.92 (highest, i.e. critical)
SNrequired = 2.35 /Table 9.5/ for TLC 10 and CBR=40
Among the values of SNdiff (1.92 - 1.42 - 1.69) calculated at different levels in the existing pavement, 1.92 is the
highest and becomes the value for which rehabilitation design is carried out.
Rehabilitation options
Using SNdiff = 1.92 as input to /Table 9.7/ the nearest value of SNdiff in the table is 2.00 The following overlay
alternatives are given in the table:
1) The appropriate type of bituminous base course shall be selected depending on traffic load class according to
/Table 8.7/ in /Chapter 8 Pavement Design - New Roads/.
2) Best suited for roads with low traffic speed such as urban roads. For roads with high traffic speed a levelling course made
of a bituminous mix may be necessary to provide satisfactory riding quality.
3) Limited to the conditions given in /Tables 8.4/ and /8.5/ in / Chapter 8 Pavement Design - New Roads/ with regards to
traffic loading and climate. Consideration shall be given to reprocessing of the existing pavement.
Overlay alternatives
The nearest value for SNdiff has been selected.
SNdiff
Asphalt concrete Bituminous mix Penetration Granular base
overlay for base course macadam course
1) 2) AC 50 mm 3)
PM 80 125 mm
Alternatively:
ST
2,00 AC 50 mm
PM 60 100 mm
AC 50 mm
CRR 00 mm
Bit. 100 mm PM 60 100 mm
Discussion
Overlays
n Overlays with a bituminous mix is not considered viable due to the high risk of reflective cracking from the
severely cracked AC surfacing of the existing pavement, unless specialised interlayer systems are employed.
n Overlay with granular base course and AC surfacing could be employed, but reprocessing of the existing
pavement is advisable if there is deformation in the existing pavement.
n Penetration macadam will arrest reflective cracking, but on a high speed road surface dressing alone on a
penetration macadam is not well suited.
n The following overlay alternative is appropriate, provided site conditions such as severe deformation in the
existing pavement, does not prohibit this construction method.
AC 50 mm
PM 80 125 mm
Partial reconstruction
If deformation of the existing surface is severe it is likely that partial reconstruction is the most viable rehabilitation
option. i.e. to reprocess the existing surface and base course to subbase in the new pavement /Chapter 9.3.2/.
New surfacing
New base course and surfacing to be selected in compliance with
New base course /Chapter 8.3.2/ depending on achieved quality of the new subbase.
Exitsing AC reprocessed, or removed, depending on chosen method.
Reprocessed AC
Existing base course (and subbase) reprocessed to subbase
Existing base course (and subbase) in the new pavement.
Method: Join A to C
Read average least dimension on B
/Table 10.5/ There is no correction of spray rate for the 1st layer.
/Table 10.6/ There is no correction of spray rate for the 2nd layer.
Design of a combined seal using single surface dressing and a sand cover seal
/Chapter 10.4.2/
Input data:
n double surface dressing, new road, dry, primed base course
n AADT = 200, two lane road with surfaced width of 6.5 m
n 20% heavy vehicles
n 14 mm chipping: ALD = 8.0 mm
n river sand in combination as 2nd layer
n 0.15% passing 0.075 mm (not dusty), water absorption: 0.7%
n flat terrain
/Table 10.3/ There is no correction of spray rate for the 1st layer.
Bitumen spray rate for sand seal 2nd seal /Chapter 10.4.1/
/Table 10.11/ The binder for sand seals shall be cutback bitumen of type MC3000.
The hot spray rate of MC3000 cutback bitumen ranges between 0.80 l/m2 and 1.00 l/m2 to be
determined on site depending on the surface texture of the underlying seal.