Professional Documents
Culture Documents
ChaiPUB3123 PDF
ChaiPUB3123 PDF
Author
Chai, E. P. S., Ong, Dominic Ek Leong
Published
2016
Conference Title
Proceedings of the Young Geotechnical Engineers Conference 2016: Contributions of Young
Geotechnical Engineers to Nation Building
Version
Published
Copyright Statement
© 2016 Southeast Asian Geotechnical Society. The attached file is reproduced here in
accordance with the copyright policy of the publisher. Please refer to the conference's website
for access to the definitive, published version.
Downloaded from
http://hdl.handle.net/10072/376302
ABSTRACT: It is important to design a safe retaining system to facilitate the excavation works while imparting minimum impact to the
surrounding. Hence, the prediction of the excavation behaviour is very crucial in determining the type of retaining system to be adopted.
Nowadays this can be accomplished quite accurately by numerical modelling that is able to take into consideration the nature of the soil type,
geometry of the excavation and the possibility of ground water seepage. Further understanding can be attained by comparing the analysed
results with field readings from field instruments.
85
19th Southeast Asian Geotechnical Conference & 2nd AGSSEA Conference (19SEAGC & 2AGSSEA)
Young Geotechnical Engineers Conference, Kuala Lumpur, 30 May 2016
All CBP walls are designed as permanent basement walls. Gaps In order to improve the accuracy of the calculations, the
in between adjacent piles are sealed by 150mm grout columns to elements surrounding the retaining walls where high strain changes
minimize the seepage of ground water. This helps to prevent ground are expected, were further refined as shown in Figure 6.
water loss on the retained side. The idealised soil profile for Section
B-B is shown in Figure 4.
Since the nearest existing structure (the bungalow) to the earth
retaining structure system (ERSS) considered under this report is
less than 2 times the excavation depth, the allowable wall deflection
limits for Section B-B shall be 0.7% of the excavation depth (BCA).
86
19th Southeast Asian Geotechnical Conference & 2nd AGSSEA Conference (19SEAGC & 2AGSSEA)
Young Geotechnical Engineers Conference, Kuala Lumpur, 30 May 2016
surface capped by Mohr Coulomb criteria. The soil parameters 2.4 Anchor element
adopted in the design is tabulated in Table 1.
The basement slabs were modelled as fixed. Equivalent horizontal
Table 1 Soil parameters stiffness was modelled as a spring element with axial rigidity only.
Effective Young’s
Cohesion, Friction Dilation Poisson Table 3 Cast in-situ slab stiffness
Unit Modulus,
Soil Type c’, Angle, angle, λ Ratio, Anchor Axial Stiffness (kN/m)
Weight E’ 2)
(kN/m ø’ (ᵒ) (ᵒ) v’ 200mm THK Slab at L2 & L3 Level 5.40 x 106
(kNm3) (kN/m2)
600mm THK Slab at L1 Level 1.62 x 107
Firm Sandy
CLAY 18.0 11 667 7 20 0 0.3
2.5 Construction sequences and modelling process
(N=7)
Stiff Sandy The most critical analysis section is Section B-B due to its proximity
of the existing bungalow. In order to limit the impact of the
CLAY 18.0 28 333 8 25 0 0.3
excavation towards the integrity of the building, it is prevalent to
(N=17) adopt a very robust system. In the analysis, the “green field”
assumption was made whereby the building is assumed to have no
Hard SILT
20.0 166 667 10 30 0 0.3 stiffness and it conforms to the ground deformation. This is in-line
(N = 120) with the building damage category based on Boscardin and Cording
(1989), Mair, et al. (1996) and Boone (1999).
Very Dense
In the numeric analysis, each of the stage construction was
SAND 18.0 166 667 1 35 5 0.3 modelled to capture its wall deformation, bending moment and shear
(N =130) force. The followings show the construction stages in chronological
order.
Rock 22.0 500 000 20 30 0 0.3
Stage 1 – Installation of the CBP wall and kingpost.
2.2 Ground water modelling
Stage 2 – Excavation to the Final Formation Level while leaving
Due to the hilly nature of the existing ground, the available SI report the soil passive berm abutting the CBP wall.
indicate that the groundwater table ranges from RL12.09m to
RL17.37m or 0.1m to 6.5m below ground. For design purpose, the Stage 3 – Casting of the Basement 2 and Basement 3 slab
groundwater table will be taken at 2m below ground for existing abutting to the CBP wall.
ground higher than RL16.00m or 0.5m below ground level for
existing ground with elevation at or less than RL16.00m based on Stage 4 – Excavation of the soil passive berm beneath Basement
local condition. In the analysis, the initial groundwater table adopted 2.
is at RL17.00m which is 2m below the existing ground level of
RL19.00m. The groundwater table was then created by steady Stage 5 – Complete construction of the basement.
seepage calculation for each excavation stage so as to capture the
variation in active groundwater regime with the progress of Plaxis 2D conveniently allows the size effect of the passive
excavation. berm as well as the associated passive wedge in enhancing the
embedded stability to be accurately modelled unlike the old-
2.3 Plate element fashioned methods of simplifying it as an equivalent surcharge or by
The retaining wall was modelled by one dimension Mindlin plate means of a raised effective formation level.
element with axial and bending rigidities. The bored piles in a CBP
system are spaced at consistent intervals. In order to obtain the
‘equivalent’ pile properties per meter run, the actual properties of a
3D pile are “smeared” in the plane-strain direction. This is done by
dividing the structural properties of the pile by its centre-to-centre
spacing. By doing so, this technique effectively converts the 3D
nature of the piles in a row to be represented by an ‘equivalent’ wall,
modelled by the structural plate element in the Plaxis software.
87
19th Southeast Asian Geotechnical Conference & 2nd AGSSEA Conference (19SEAGC & 2AGSSEA)
Young Geotechnical Engineers Conference, Kuala Lumpur, 30 May 2016
warning system so that appropriate mitigation measures can be relief. Over time, depending on its permeability, the negative pore
employed effectively and in a timely manner to prevent further water is able to dissipate. For excavation in residual soil, the drained
deterioration of the damaging situation. condition is thought to be more critical. Evidently, the field
measurements show that the movements kept increasing when the
3.1 Inclinometer counter berm was left over a long period of time.
Inclinometers are used to monitor subsurface lateral movements. An
inclinometer system has two components, mainly the inclinometer
casing and an inclinometer measurement system. The grooves inside
of the casing helped to control and guide the orientation of the
inclinometer sensor as well as provide a uniform surface for
measurements. Along Section B-B, the inclinometer casings were
attached to the bored pile reinforcement cage down to the toe level
and were cast inside of the CBP wall.
88
19th Southeast Asian Geotechnical Conference & 2nd AGSSEA Conference (19SEAGC & 2AGSSEA)
Young Geotechnical Engineers Conference, Kuala Lumpur, 30 May 2016
5 CONCLUSION
The existing soil condition, drainage condition, soil profile and
retaining system play a vital part in designing a safe and robust
system. In this paper, the berm excavation will depicts a cantilever
behaviour that attracts more movement at the top of the wall.
Analysis of retaining systems in residual soil need to consider
drained conditions to account for the worst possible scenarios.
6 REFERENCES
BCA Advisory Note 1/09 (2009). Earth Retaining and Stabilizing
System. Singapore.
Brinkgeve R.B.J., Broere, W. & Waterman, D. (2006). “PLAXIS 2D
version 8 – Finite Element Code for Soil and Rock
Analyses.” Netherlands.
BS 8002 (1994). Code of Practice for Earth Retaining Structures.
British Standard Institution, London.
CIRIA C580 Report (2003). Embedded Retaining Walls – Guidance
for Economic Design, Londaon, Clause 4.2.3.
Clough, G.W. & O’Rourke, T.D. (1990), Construction inducd
movements of in-situ walls. Proc. ASCE Specialty
Conference, Cornell. ASCE Geo Special Publication 25.
NAVFAC Design Manual 7.1 (1982), Soil Mechanics. Department
of Navy, Naval Facilities Engineering Command,
Washington, DC.
NAVFAC Design Manual 7.2 (1982), Foundation and earth
structures. Department of Navy, Naval Facilities Engineering
Command, Washington, DC.
Terzaghi, K. and Peck, R.B. (1967), Soil mechanics in engineering
practice. Wiley, New York, 2nd edn.
89