TIMAS ONSHORE DIVISION

STANDARD OPERATIONAL PROCEDURE

PEMERIKSAAN DAN PENGENCANGAN/PENGUNCIAN


SWING BEARING MOUNTING BOLT FOCO

Doc. No. : TSON-SOP-PSD-HSSE-026


Rev. No. / Date : 00 / 24 January 2018
Review Date :-

© This document is the property of PT. Timas Suplindo. Reproduction or transmission of this document, in whole or in part,
without the prior consent of PT. Timas Suplindo is prohibited.
PT. Timas Suplindo is committed to continuous improvement. If you have any constructive feedback in how to make this
procedure more effective to improve performance, please do not hesitate to contact PT. Timas Suplindo.
To obtain permission for reproduction/transmission and to send feedback, email to: qmr@timas.com
Doc. No TSON-SOP-PSD-HSSE-026

Rev. No / Date 00 / 24 Jan 2018


Standard Operational Procedure Review Date -
PEMERIKSAAN DAN PENGENCANGAN/PENGUNCIAN Page 1 of 4
SWING BEARING MOUNTING BOLT FOCO
REVISION INDEX AND AUTHORIZATION

REVISION DATE DESCRIPTION PREPARED REVIEWED APPROVED


NO
00 24 Jan Initial issue ....................... .................... ...................

2018 .
Adek Kurniawan Reno Petra
Sr. Supv HSSE Coord Ridwan
AM

© This document is the property of PT. Timas Suplindo. Reproduction or transmission of this document, in whole or in part,without the
prior consent of PT. Timas Suplindo is prohibited.
Doc. No TSON-SOP-PSD-HSSE-026

Rev. No / Date 00 / 24 Jan 2018


Standard Operational Procedure Review Date -
PEMERIKSAAN DAN PENGENCANGAN/PENGUNCIAN Page 2 of 4
SWING BEARING MOUNTING BOLT FOCO

1. TUJUAN
PURPOS
E
SOP ini digunakan oleh karyawan PT Timas khususnya untuk PEMERIKSAAN DAN
PENGENCANGAN/PENGUNCIAN SWING BEARING MOUNTING BOLT FOCO

RUANG LINGKUP
SCOPE
1.1 Peralatan yang digunakan :
Yearly Form Inspection Foco & Kunci Torsi

1.2 Alat pelindung diri yang digunakan :


2.2.1 APD mandatory
Baju keselamatan (FRC), Topi keselamatan, Kaca mata keselamatan, Pelindung
telinga, Sepatu keselamatan & Sarung tangan

2. TANGGUNG JAWAB DAN WEWENANG


RESPONSIBILITY AND AUTHORITY
2.1Pimpinan / Atasan tidak langsung/langsung
2.1.1 Melengkapi formulir ijin kerja yang dibutuhkan dan disetujui
2.2 Karyawan
2.2.1 Melengkapi formulir safety administrasi sebelum bekerja.
2.2.2 Melengkapi dokumen pendukung yang dibutuhkan / dipersyaratkan
2.3Personil yang dibutuhkan
Sr. Supervisor, Supervisor Mechanic, Mechanic

3. REFERENSI
REFERENC
E
3.1Manual Book Unic Hydroulic Crene URV 290 (Operation and Maintenance Manual)
3.2Spesifikasi Kunci Torsi : Tekiro QLE1400N2
3.3Pelumas : Gunakan API servis GL-4 Oli Gear
1. Chevron, THUBAN GL4 90 atau
2. SHELL, SHELL Spirax EP 90
3.4 Kunci Socket

4. PROSEDUR PELAKSANAAN
IMPLEMENTATION PROCEDURE

4.1 Persiapan
4.1.1 Pastikan Pre job Meeting, Verbal JSA, dilakukan bersama team terkait dalam
proses pekerjaan yang akan dilakukan.
© This document is the property of PT. Timas Suplindo. Reproduction or transmission of this document, in whole or in part,without the
prior consent of PT. Timas Suplindo is prohibited.
Doc. No TSON-SOP-PSD-HSSE-026

Rev. No / Date 00 / 24 Jan 2018


Standard Operational Procedure Review Date -
PEMERIKSAAN DAN PENGENCANGAN/PENGUNCIAN Page 3 of 4
SWING BEARING MOUNTING BOLT FOCO

4.2 Langkah Pekerjaan


4.2.1 Pastikan kesiapan Tools & kendaraan, dengan kondisi layak/baik
4.2.2 Pastikan kondisi mesin sudah dalam keadaan mati
4.2.3 Pasang Lotto di setiap Sumber Energi
4.2.4 Lepaskan penutup pada lubang pemeriksaan
4.2.5 Lakukan Swing Boom sampai masing-masing baut mounting berada di pusat lubang
untuk di lakukan nya pengecekan

4.2.6 Lakukan pemeriksaan kelonggaran dan penguatan baut 530-590 N.m / 5450
kgf.m pada Mounting Sleewing Bearing hingga tidak terdapatnya rongga antara
baut dengan bantalan dengan menggunakan Kunci Torsi
4.2.7 Berikan pelumas (Chevron Thuban GL-4 90 atau Shell Spirax EP 90) pada sleewing
bearing sebelum di lakukan pemasangan penutup pada Sleewing
4.2.8 Pasang penutup Sleewing setelah melakukan pemeriksaan dan pastikan
pemasangan penutup slewing rapat untuk menghindari masuknya pasir atau
material kecil yang keras.

Peringatan :

Jika terjadi kerusakan pada baut di Slewing Bearing ,yang sebabkan kecelakaan seperti
terkena benturan yang mana terjadi kerusakan pada Crane. Maka dilakukan pemeriksaan
kerapatan / kekencangan baut setiap 6 bulan.

4.3 Pekerjaan selesai

Jika pekerjaan selesai dan dan semua baut telah dilakukan pengecekan terakhir dengan
torsi 530-590 N.m / 5450 kgf.m, lakukan House keeing dan pastikan semua
peralatan telah tersimpan dalam Tool Box.