THE ICON BY RISLAND

AT THANE
MASTER LIST OF DELIEVERABLES

Svc Stg Tsk-Dsc


mep 1 Design Basis Report (DBR)
mep 1 Inidcative Cost Estimates
m 2 HVAC Equipment Location with Schematic Sectional Details
m 2 HVAC Equipment Location with Schematic Sectional Details at Ground gloor
m 2 HVAC Equipment Location with Schematic Sectional Details at 1st podium
m 2 HVAC Equipment Location with Schematic Sectional Details at 2nd podium
m 2 HVAC Equipment Location with Schematic Sectional Details at 3rd podium

e 2 Electrical Equipment Location & Schematic Cable Routing with Sectional Details

e 2 Electrical Equipment Location & Schematic Cable Routing with Sectional Details at Ground floor

e 2 Block Schematic for Electrical Distribution System


e 2 Block Schematic for ELV Systems (i.e. Fire Alarm, PA, Security, Voice, Data Etc.)
2 Earhing Schematic drawing

p 2 Location of UGT & Pump Room with Schematic Layout & Sectional Details at basement
p 2 Location of STP with Schematic Layout & Sectional Details at basement
p 2 Schematic for External Water Supply Looping Layout at ground floor
p 2 Schematic for External Stormwater Drainage Layout at ground floor
p 2 Schematic for External Sanitary Drainage Layout at ground floor-If applicable
p 2 Schematic Water Distribution System
p 2 Location for Solid Waste Management System at ground floor
p 2 Water Bodies Utility Room at 3rd podium

ff 2 External Hydrant Layout


ff 2 Schematic for Fire Fighting System

mep 2 MEP Coordinated Shaft Schedule


mep 2 MEP Coordinated Shaft Schedule at ground floor
mep 2 MEP Coordinated Shaft Schedule at 1st podium
mep 2 MEP Coordinated Shaft Schedule at 2nd podium
mep 2 MEP Coordinated Shaft Schedule at 3rd podium
mep 2 MEP Services Layout at Ground Floor
mep 2 MEP Services Layout at 1st Podium
mep 2 MEP Services Layout at 2nd Podium
mep 2 MEP Services Layout at 3rd Podium
mep 2 MEP Coordinated Services Layout at Floor Level / External
mep 2 MEP Coordinated Services Layout at ground Floor Level

m 3 Detailed Drawing for HVAC Equipment Layout & Sectional Details


m 3 Detailed Drawing for HVAC Equipment Layout & Sectional Details at ground floor
m 3 Detailed Drawing for HVAC Equipment Layout & Sectional Details at 1st podium
m 3 Detailed Drawing for HVAC Equipment Layout & Sectional Details at 2nd podium
m 3 Detailed Drawing for HVAC Equipment Layout & Sectional Details at 3rd podium
m 3 Ventilation Layout
m 3 Pump room Ventilation Layout
m 3 STP Ventilation Layout
m 3 Pressurization System Layout - Staircase/ Lift Lobby & Lift Well
m 3 Pressurization System Layout at ground floor - Staircase/ Lift Lobby & Lift Well
m 3 Pressurization System Layout at 1st podium - Staircase/ Lift Lobby & Lift Well
m 3 Pressurization System Layout at 2nd podium - Staircase/ Lift Lobby & Lift Well
m 3 Pressurization System Layout at 3rd podium - Staircase/ Lift Lobby & Lift Well
THE ICON BY RISLAND
AT THANE
MASTER LIST OF DELIEVERABLES

e 3 Location of Electrical Equipment & Cable Routing With Sectional Details


e 3 Location of Electrical Equipment & Cable Routing With Sectional Details at ground floor
e 3 Single Line Diagram for Sub-Main LT Panel
e 3 Single Line Diagram for Sub-Main Distribution Boards
e 3 Electrical Meter Room Details Layout at ground floor
e 3 External Lighting & Power Layout at ground floor
e 3 Internal Lighting & Power Layout
e 3 Internal Lighting & Power Layout at ground floor
e 3 Internal Lighting & Power Layout at 1st podium
e 3 Internal Lighting & Power Layout 2nd podium
e 3 Internal Lighting & Power Layout 3rd podium
e 3 Cable Tray Layout
e 3 Cable Tray Layout at ground floor
e 3 Cable Tray Layout at podium-If applicable
e 3 Earthing Layout at ground floor (with Standard Details)
elv 3 Layout for ELV System (i.e. Fire Alarm, PA, Security, Voice & Data etc.)
elv 3 Layout for ELV System at ground floor (i.e. Fire Alarm, PA, Security, Voice & Data etc.)
elv 3 Layout for ELV System at 1st podium (i.e. Fire Alarm, PA, Security, Voice & Data etc.)
elv 3 Layout for ELV System at 2nd podium (i.e. Fire Alarm, PA, Security, Voice & Data etc.)
elv 3 Layout for ELV System at 3rd podium (i.e. Fire Alarm, PA, Security, Voice & Data etc.)
elv 3 IBMS Block Schematic Layout

p 3 Detailed Drawing of UGT With Pump Room Details at basement


p 3 Detailed Drawing of STP at basement
p 3 Detailed Drawing of OHT at 3rd podium-If applicable
p 3 Internal Water Supply & Drainage Layout
p 3 Internal Water Supply & Drainage Layout at ground floor
p 3 Internal Water Supply & Drainage Layout at 1st podium
p 3 Internal Water Supply & Drainage Layout at 2nd podium
p 3 Internal Water Supply & Drainage Layout at 3rd podium
p 3 Internal Storm Water Drainage
p 3 Internal Storm Water Drainage at 1st podium
p 3 Internal Storm Water Drainage at 2nd podium
p 3 Internal Storm Water Drainage at 3rd podium
p 3 Sanitary Diversion Layout
p 3 Sanitary Diversion Layout at podium-If applicable
p 3 Schematic for Sanitary Water Supply Downtakes
p 3 Schematic for Sanitary & Rain Water Downtakes
p 3 External Water Supply Detailed Drawing at ground floor
p 3 External Stromwater Detailed Drawing with RWH at ground floor
p 3 External Saintary Detailed Drawing at ground floor-If applicable
p 3 Proposed Water Bodies Utility Room at 3rd podium
ff 3 External Courtyard Hydrant Layout at ground floor
ff 3 Internal Fire Fighting Layout
ff 3 Internal Fire Fighting Layout at ground floor
ff 3 Internal Fire Fighting Layout at 1st podium
ff 3 Internal Fire Fighting Layout at 2nd podium
ff 3 Internal Fire Fighting Layout at 3rd podium
ff 3 Schematic for Wet Riser
ff 3 FF UGT & Pump Room Layout at basement
mep 3 Location of MEP Equipments with Schematic Layouts & Sectional Details
mep 3 Location of MEP Equipments with Schematic Layouts & Sectional Details at ground floor
mep 3 Location of MEP Equipments with Schematic Layouts & Sectional Details at 1st podium
mep 3 Location of MEP Equipments with Schematic Layouts & Sectional Details at 2nd podium
THE ICON BY RISLAND
AT THANE
MASTER LIST OF DELIEVERABLES

mep 3 Location of MEP Equipments with Schematic Layouts & Sectional Details at 3rd podium
mep 3 Coordinated External Services Layout at ground floor
mep 3 MEP Coordinated Layout at Floor Level
mep 3 MEP Coordinated Layout at Floor Level at ground floor
mep 3 MEP Coordinated Layout at Floor Level at 1st podium
mep 3 MEP Coordinated Layout at Floor Level at 2nd podium
mep 3 MEP Coordinated Layout at Floor Level at 3rd podium
mep 3 MEP Coordinated Services Layout at Ceiling Level
mep 3 MEP Coordinated Services Layout at ground Ceiling Level
mep 3 MEP Coordinated Services Layout at 1st podium Ceiling Level
mep 3 MEP Coordinated Services Layout at 2nd podium Ceiling Level
mep 3 MEP Coordinated Services Layout at 3rd podium Ceiling Level

m 4 BOQ for Air-Conditioning System


m 4 BOQ for Ventilation - System-wise
m 4 BOQ for Pressurisation System
m 4 Technical Specification for HVAC System
m 4 HVAC Tender Drawings

e 4 BOQ for HT System & Transformer


e 4 BOQ for DG Backup System
e 4 BOQ for LT System
e 4 Technical Specification of HT System & Transformer
e 4 Technical Specification of DG Backup System
e 4 Technical Specification of LT System
e 4 Electrical Tender Drawings
elv 4 BOQ for Fire Alarm System
elv 4 BOQ for Security System
elv 4 BOQ for Access Control System
elv 4 BOQ for PA System
elv 4 BOQ for IBMS System
elv 4 Technical Specification of Fire Alarm System
elv 4 Technical Specification of Security System
elv 4 Technical Specification of Access Control System
elv 4 Technical Specification of PA System
elv 4 Technical Specification of IBMS System
elv 4 ELV Tender Drawings

p 4 BOQ for Internal Plumbing Works


p 4 BOQ for External Plumbing Works
p 4 BOQ for Gravity feed System
p 4 BOQ for STP Work
p 4 BOQ for Solar / Central Hot Water System
p 4 Technical Specificaton of Internal Plimbing Works
p 4 Technical Specificaton of External Plimbing Works
p 4 Technical Specificaton of Gravity feed System
p 4 Technical Specificaton of STP Work
p 4 Technical Specification of Solar / Central Hot Water System
p 4 Plumbing Tender Drawings

ff 4 BOQ for Fire Fighting System


ff 4 Technical Specification For Fire Fighting System
ff 4 Fire Fighting Tender drawings
THE ICON BY RISLAND
AT THANE
MASTER LIST OF DELIEVERABLES

m 5 HVAC Equipment Layout & Sectional Details


m 5 HVAC Equipment Layout & Sectional Details at ground floor
m 5 HVAC Equipment Layout & Sectional Details at 1st podium
m 5 HVAC Equipment Layout & Sectional Details at 2nd podium
m 5 HVAC Equipment Layout & Sectional Details at 3rd podium
m 5 Pressurization System Layout - Staircase/ Lift Lobby & Lift Well
m 5 Pressurization System Layout at ground floor - Staircase/ Lift Lobby & Lift Well
m 5 Pressurization System Layout at 1st podium- Staircase/ Lift Lobby & Lift Well
m 5 Pressurization System Layout at 2nd podium- Staircase/ Lift Lobby & Lift Well
m 5 Pressurization System Layout at 3rd podium - Staircase/ Lift Lobby & Lift Well

e 5 Location of Electrical Equipment & Cable Routing With Sectional Details


e 5 Location of Electrical Equipment & Cable Routing With Sectional Details at ground floor
e 5 Location of Electrical Equipment & Cable Routing With Sectional Details at podium
e 5 Electrical Meter Room Details Layout at ground floor
e 5 External Lighting & Power Layout at ground floor
e 5 Internal Lighting & Power Layout
e 5 Internal Lighting & Power Layout at ground floor
e 5 Internal Lighting & Power Layout at 1st podium
e 5 Internal Lighting & Power Layout at 2nd podium
e 5 Internal Lighting & Power Layout at 3rd podium
e 5 Cable Tray Layout
e 5 Cable Tray Layout at ground floor
e 5 Cable Tray Layout at podium-if applicable
e 5 Earthing Layout at ground floor (with Standard Details)

p 5 Detailed Drawing of UGT With Pump Room at ground floor


p 5 Detailed Drawing of OHT at 3rd podium-If applicable
p 5 Internal Water Supply & Drainage Layout
p 5 Internal Water Supply & Drainage Layout at ground floor
p 5 Internal Water Supply & Drainage Layout 1st podium
p 5 Internal Water Supply & Drainage Layout 2nd podium
p 5 Internal Water Supply & Drainage Layout 3rd podium
p 5 Internal Storm Water Drainage
p 5 Internal Storm Water Drainage at 1st podium
p 5 Internal Storm Water Drainage at 2nd podium
p 5 Internal Storm Water Drainage at 3rd podium
p 5 Sanitary Diversion Layout at podium-if applicable
p 5 Schematic Water Supply Downtakes
p 5 Schematic Sanitary and Rain Water Downtakes
p 5 External Storm Water Detailed Drawing with RWH at ground floor
p 5 External Sanitary Detailed Drawing at ground floor- If applicable
ff 5 External Courtyard Hydrant Layout at ground floor
ff 5 Internal Fire Fighting Layout
ff 5 Internal Fire Fighting Layout at ground floor
ff 5 Internal Fire Fighting Layout at 1st podium
ff 5 Internal Fire Fighting Layout at 2nd podium
ff 5 Internal Fire Fighting Layout at 3rd podium
ff 5 Schematic Wet Riser
ff 5 FF UGT & Pump Room Layout at ground floor
mep 5 Shaft, Sleeve & Cut-Out Detailed Layout
mep 5 Shaft, Sleeve & Cut-Out Detailed Layout at ground floor
mep 5 Shaft, Sleeve & Cut-Out Detailed Layout at 1st podium
mep 5 Shaft, Sleeve & Cut-Out Detailed Layout at 2nd podium
THE ICON BY RISLAND
AT THANE
MASTER LIST OF DELIEVERABLES

mep 5 Shaft, Sleeve & Cut-Out Detailed Layout at 3rd podium


mep 5 Location of MEP Equipments with Sectional Details (App. Floors)
mep 5 Location of MEP Equipments with Sectional Details at ground floor
mep 5 Location of MEP Equipments with Sectional Details at 1st podium
mep 5 Location of MEP Equipments with Sectional Details at 2nd podium
mep 5 Location of MEP Equipments with Sectional Details at 3rd podium
mep 5 Coordinated External Services Layout at ground floor
mep 5 MEP Coordinated Services Layout At the Floors Level
mep 5 MEP Coordinated Services Layout At the ground Floors Level
mep 5 MEP Coordinated Services Layout At the 1st podium Floors Level
mep 5 MEP Coordinated Services Layout At the 2nd podium Floors Level
mep 5 MEP Coordinated Services Layout At the 3rd podium Floors Level
mep 5 MEP Coordinated Services Layout At the Ceiling Level
mep 5 MEP Coordinated Services Layout At the ground Ceiling Level
mep 5 MEP Coordinated Services Layout At the 1st podium Ceiling Level
mep 5 MEP Coordinated Services Layout At the 2nd podium Ceiling Level
mep 5 MEP Coordinated Services Layout At the 3rd podium Ceiling Level
THE ICON BY RISLAND
AT THANE
MASTER LIST OF DELIEVERABLES

Date

Received

Received
Received
Received
Received

Received
Incomplete
Incomplete

Received
Received
Received
Received
Not Receieved
Not Receieved
Not Receieved
Not Receieved

Received
Received
Received
Received
Received
Incomplete
Received
Received
Received
THE ICON BY RISLAND
AT THANE
MASTER LIST OF DELIEVERABLES
THE ICON BY RISLAND
AT THANE
MASTER LIST OF DELIEVERABLES
THE ICON BY RISLAND
AT THANE
MASTER LIST OF DELIEVERABLES
THE ICON BY RISLAND
AT THANE
MASTER LIST OF DELIEVERABLES
THE ICON BY RISLAND
AT THANE
MASTER LIST OF DELIEVERABLES

Svc Stg Tsk-Dsc


m 2 HVAC Equipment Location with Schematic Sectional Details
m 2 HVAC Equipment Location with Sectional Details at Ground gloor
m 2 HVAC Equipment Location with Sectional Details at 1st podium
m 2 HVAC Equipment Location with Sectional Details at 2nd podium
m 2 HVAC Equipment Location with Sectional Details at 3rd podium
m 2 HVAC Equipment Location with Sectional Details at terrace floor

e 2 Electrical Equipment Location & Schematic Cable Routing with Sectional Details
e 2 Block Schematic for Electrical Distribution System
e 2 Block Schematic for ELV Systems (i.e. Fire Alarm, PA, Security, Voice, Data Etc.)

p 2 Location of OHT with Schematic Layout & Sectional Details at terrace floor
p 2 Schematic for External Water Supply Looping Layout at ground floor
p 2 Schematic for External Sanitary Drainage Layout at ground floor-If applicable
p 2 Schematic Water Distribution System
p 2 Location for Solid Waste Management System at ground floor
p 2 Location for Solar Water Heating at terrace floor

ff 2 Schematic for Fire Fighting System

mep 2 MEP Coordinated Shaft Schedule


mep 2 MEP Coordinated Shaft Schedule at ground floor
mep 2 MEP Coordinated Shaft Schedule at 1st podium
mep 2 MEP Coordinated Shaft Schedule at 2nd podium
mep 2 MEP Coordinated Shaft Schedule at 3rd podium
MEP Coordinated Shaft Schedule at typical floor (4th to 6th, 8th to 11th, 13th to 16th, 18th to
mep 2
21st, 23rd to 30th)
mep 2 MEP Coordinated Shaft Schedule at Refuse floor (7th, 12th, 17th, 22nd)

m 3 Detailed Drawing for HVAC Equipment Layout & Sectional Details


m 3 Detailed Drawing for HVAC Equipment Layout & Sectional Details at ground floor
m 3 Detailed Drawing for HVAC Equipment Layout & Sectional Details at 1st podium
m 3 Detailed Drawing for HVAC Equipment Layout & Sectional Details at 2nd podium
m 3 Detailed Drawing for HVAC Equipment Layout & Sectional Details at 3rd podium
m 3 Detailed Drawing for HVAC Equipment Layout & Sectional Details at terrace floor
m 3 Ventilation Layout
m 3 Pump room Ventilation Layout
m 3 STP Ventilation Layout- If applicable
m 3 Pressurization System Layout at ground floor - Staircase/ Lift Lobby & Lift Well (if App.)
m 3 Pressurization System Layout at 1st podium - Staircase/ Lift Lobby & Lift Well (if App.)
m 3 Pressurization System Layout at 2nd podium - Staircase/ Lift Lobby & Lift Well (if App.)
m 3 Pressurization System Layout at 3rd podium - Staircase/ Lift Lobby & Lift Well (if App.)
Pressurization System Layout at typocal floor (4th to 6th, 8th to 11th, 13th to 16th, 18th to 21st,
m 3
23rd to 30th) - Staircase/ Lift Lobby & Lift Well (if App.)
Pressurization System Layout at Refuse floor (7th, 12th, 17th, 22nd) - Staircase/ Lift Lobby &
m 3
Lift Well (if App.)

e 3 Location of Electrical Equipment & Cable Routing With Sectional Details


THE ICON BY RISLAND
AT THANE
MASTER LIST OF DELIEVERABLES

e 3 Location of Electrical Equipment & Cable Routing With Sectional Details at ground floor

e 3 Location of Electrical Equipment & Cable Routing With Sectional Details at podium-If applicable

e 3 Single Line Diagram for Sub-Main LT Panel


e 3 Single Line Diagram for Sub-Main Distribution Boards
e 3 Electrical Meter Room Details Layout at ground floor
e 3 External Lighting & Power Layout at ground floor
e 3 Internal Lighting & Power Layout
e 3 Internal Lighting & Power Layout at ground floor
e 3 Internal Lighting & Power Layout at 1st podium
e 3 Internal Lighting & Power Layout at 2nd podium
e 3 Internal Lighting & Power Layout at 3rd podium
Internal Lighting & Power Layout at typical floor (4th to 6th, 8th to 11th, 13th to 16th, 18th to
e 3
21st, 23rd to 30th)
e 3 Internal Lighting & Power Layout at Refuse floor (7th, 12th, 17th, 22nd)
e 3 Cable Tray Layout
e 3 Cable Tray Layout at ground floor
e 3 Cable Tray Layout at podium-If applicable
e 3 Earthing Layout at ground floor (with Standard Details)
e 3 Lighting Arrester Layout with Standard Details at terrace floor
elv 3 Layout for ELV System (i.e. Fire Alarm, PA, Security, Voice & Data etc.)
elv 3 Layout for ELV System at ground floor (i.e. Fire Alarm, PA, Security, Voice & Data etc.)
elv 3 Layout for ELV System at 1st podium (i.e. Fire Alarm, PA, Security, Voice & Data etc.)
elv 3 Layout for ELV System at 2nd podium (i.e. Fire Alarm, PA, Security, Voice & Data etc.)
elv 3 Layout for ELV System at 3rd podium (i.e. Fire Alarm, PA, Security, Voice & Data etc.)
Layout for ELV System at typical floor (4th to 6th, 8th to 11th, 13th to 16th, 18th to 21st, 23rd to
elv 3
30th) (i.e. Fire Alarm, PA, Security, Voice & Data etc.)
Layout for ELV System at Refuse floor (7th, 12th, 17th, 22nd) (i.e. Fire Alarm, PA, Security,
elv 3
Voice & Data etc.)
elv 3 IBMS Block Schematic Layout

p 3 Detailed Drawing of UGT With Pump Room Details at basement


p 3 Detailed Drawing of STP at basement
p 3 Detailed Drawing of OHTat terrace floor
p 3 Internal Water Supply & Drainage Layout
p 3 Internal Water Supply & Drainage Layout at ground floor
p 3 Internal Water Supply & Drainage Layout at 1st podium
p 3 Internal Water Supply & Drainage Layout at 2nd podium
p 3 Internal Water Supply & Drainage Layout at 3rd podium
Internal Water Supply & Drainage Layout at typical floor (4th to 6th, 8th to 11th, 13th to 16th,
3
18th to 21st, 23rd to 30th)
3 Internal Water Supply & Drainage Layout at Refuse floor (7th, 12th, 17th, 22nd)
p 3 Internal Storm Water Drainage
p 3 Internal Storm Water Drainage at 1st podium
p 3 Internal Storm Water Drainage at 2nd podium
p 3 Internal Storm Water Drainage at 3rd podium
p 3 Sanitary Diversion Layout
p 3 Sanitary Diversion Layout at podium-If applicable
p 3 Schematic for Sanitary Water Supply Downtakes
p 3 Schematic for Sanitary & Rain Water Downtakes
p 3 Water Supply Loop Layout at Terrace Level
THE ICON BY RISLAND
AT THANE
MASTER LIST OF DELIEVERABLES

p 3 Rain Water Drainage at Terrace Level


p 3 External Water Supply Detailed Drawing at ground floor
p 3 External Stromwater Detailed Drawing with RWH at ground floor
p 3 External Saintary Detailed Drawing at ground floor-If applicable
p 3 Solar Water System at Terrace Level
p 3 Proposed Water Bodies Utility Room at 3rd podium

ff 3 External Courtyard Hydrant Layout at ground floor


ff 3 Internal Fire Fighting Layout
ff 3 Internal Fire Fighting Layout at ground floor
ff 3 Internal Fire Fighting Layout at 1st podium
ff 3 Internal Fire Fighting Layout at 2nd podium
ff 3 Internal Fire Fighting Layout at 3rd podium
Internal Fire Fighting Layout at typical floor (4th to 6th, 8th to 11th, 13th to 16th, 18th to 21st,
ff 3
23rd to 30th)
ff 3 Internal Fire Fighting Layout at Refuse floor (7th, 12th, 17th, 22nd)
ff 3 Hydrant Loop Layout at The Terrace Level
ff 3 Schematic Wet Riser
ff 3 FF UGT & Pump Room Layout at basement

mep 3 Location of MEP Equipments with Schematic Layouts & Sectional Details
mep 3 Location of MEP Equipments with Schematic Layouts & Sectional Details at ground floor
mep 3 Location of MEP Equipments with Schematic Layouts & Sectional Details at 1st podium
mep 3 Location of MEP Equipments with Schematic Layouts & Sectional Details at 2nd podium
mep 3 Location of MEP Equipments with Schematic Layouts & Sectional Details at 3rd podium
mep 3 Coordinated External Services Layout at ground floor
mep 3 MEP Coordinated Layout at Floor Level
mep 3 MEP Coordinated Layout at ground floor Level
mep 3 MEP Coordinated Layout at 1st podium Level
mep 3 MEP Coordinated Layout at 2nd podium Level
mep 3 MEP Coordinated Layout at 3rd podium Level
MEP Coordinated Layout at typical floor Level (4th to 6th, 8th to 11th, 13th to 16th, 18th to 21st,
mep 3
23rd to 30th)
mep 3 MEP Coordinated Layout at Refuse floor Level (7th, 12th, 17th, 22nd)
mep 3 MEP Coordinated Services Layout at Ceiling Level
mep 3 MEP Coordinated Services Layout at ground Ceiling Level
mep 3 MEP Coordinated Services Layout at 1st podium Ceiling Level
mep 3 MEP Coordinated Services Layout at 2nd podium Ceiling Level
mep 3 MEP Coordinated Services Layout at 3rd podium Ceiling Level
MEP Coordinated Services Layout at typical floor (4th to 6th, 8th to 11th, 13th to 16th, 18th to
mep 3
21st, 23rd to 30th) Ceiling Level
mep 3 MEP Coordinated Services Layout at Refuse floor (7th, 12th, 17th, 22nd) Ceiling Level

m 4 BOQ for Air-Conditioning System (as App.)


m 4 BOQ for Ventilation - System-wise
m 4 BOQ for Pressurisation System
m 4 BOQ for Smoke Evacuation System (If App.)
m 4 Technical Specification for HVAC System
m 4 HVAC Tender Drawings
e 4 BOQ for HT System & Transformer (If App.)
e 4 BOQ for DG Backup System
THE ICON BY RISLAND
AT THANE
MASTER LIST OF DELIEVERABLES

e 4 BOQ for LT System


e 4 Technical Specification of HT System & Transformer (If App.)
e 4 Technical Specification of DG Backup System
e 4 Technical Specification of LT System
e 4 Electrical Tender Drawings
elv 4 BOQ for Fire Alarm System
elv 4 BOQ for Security System
elv 4 BOQ for Access Control System
elv 4 BOQ for PA System
elv 4 BOQ for IBMS System
elv 4 Technical Specification of Fire Alarm System
elv 4 Technical Specification of Security System
elv 4 Technical Specification of Access Control System
elv 4 Technical Specification of PA System
elv 4 Technical Specification of IBMS System
elv 4 ELV Tender Drawings
p 4 BOQ for Internal Plumbing Works
p 4 BOQ for External Plumbing Works
p 4 BOQ for Hydropnematic System (if App.)
p 4 BOQ for STP Work (if App.)
p 4 BOQ for Solar / Central Hot Water System (if App.)
p 4 Technical Specificaton of Internal Plimbing Works
p 4 Technical Specificaton of External Plimbing Works
p 4 Technical Specificaton of Hydropnematic System (if App.)
p 4 Technical Specificaton of STP Work (if App.)
p 4 Technical Specification of Solar / Central Hot Water System (if App.)
p 4 Plumbing Tender Drawings
ff 4 BOQ for Fire Fighting System
ff 4 Technical Specification For Fire Fighting System
ff 4 Fire Fighting Tender drawings

m 5 HVAC Equipment Layout & Sectional Details


m 5 HVAC Equipment Layout & Sectional Details at ground floor
m 5 HVAC Equipment Layout & Sectional Details at 1st podium
m 5 HVAC Equipment Layout & Sectional Details at 2nd podium
m 5 HVAC Equipment Layout & Sectional Details at 3rd podium
m 5 HVAC Equipment Layout & Sectional Details at terrace floor
m 5 Pressurization System Layout - Staircase/ Lift Lobby & Lift Well
m 5 Pressurization System Layout at ground floor - Staircase/ Lift Lobby & Lift Well
m 5 Pressurization System Layout at 1st podium - Staircase/ Lift Lobby & Lift Well
m 5 Pressurization System Layout at 2nd podium - Staircase/ Lift Lobby & Lift Well
m 5 Pressurization System Layout at 1st podium - Staircase/ Lift Lobby & Lift Well
Pressurization System Layout at typical floor (4th to 6th, 8th to 11th, 13th to 16th, 18th to 21st,
m 5
23rd to 30th) - Staircase/ Lift Lobby & Lift Well
Pressurization System Layout at Refuse floor (7th, 12th, 17th, 22nd) - Staircase/ Lift Lobby &
m 6
Lift Well

e 5 Location of Electrical Equipment & Cable Routing With Sectional Details


e 5 Location of Electrical Equipment & Cable Routing With Sectional Details at ground floor

e 5 Location of Electrical Equipment & Cable Routing With Sectional Details at podium-If applicable
THE ICON BY RISLAND
AT THANE
MASTER LIST OF DELIEVERABLES

e 5 Electrical Meter Room Details Layout at ground floor


e 5 External Lighting & Power Layout at ground floor
e 5 Internal Lighting & Power Layout
e 5 Internal Lighting & Power Layout at ground floor
e 5 Internal Lighting & Power Layout at 1st podium
e 5 Internal Lighting & Power Layout at 2nd podium
e 5 Internal Lighting & Power Layout at 3rd podium
Internal Lighting & Power Layout at typical floor (4th to 6th, 8th to 11th, 13th to 16th, 18th to
e 5
21st, 23rd to 30th)
e 5 Internal Lighting & Power Layout at Refuse floor (7th, 12th, 17th, 22nd)
e 5 Cable Tray Layout
e 5 Cable Tray Layout at ground floor
e 5 Cable Tray Layout at podium-if applicable
e 5 Earthing Layout at ground floor (with Standard Details)
e 5 Lighting Arrester Layout with Standard Details at terrace floor

p 5 Detailed Drawing of UGT With Pump Room at ground floor


p 5 Detailed Drawing of OHT at terrace floor
p 5 Internal Water Supply & Drainage Layout
p 5 Internal Water Supply & Drainage Layout at ground floor
p 5 Internal Water Supply & Drainage Layout at 1st podium
p 5 Internal Water Supply & Drainage Layout at 2nd podium
p 5 Internal Water Supply & Drainage Layout at 3rd podium
Internal Water Supply & Drainage Layout at typical floor (4th to 6th, 8th to 11th, 13th to 16th,
p 5
18th to 21st, 23rd to 30th)
p 5 Internal Water Supply & Drainage Layout at Refuse floor (7th, 12th, 17th, 22nd)
p 5 Internal Storm Water Drainage
p 5 Internal Storm Water Drainage at 1st podium
p 5 Internal Storm Water Drainage at 2nd podium
p 5 Internal Storm Water Drainage at 3rd podium
p 5 Sanitary Diversion Layout at podium-if applicable
p 5 Schematic Water Supply Downtakes
p 5 Schematic Sanitary and Rain Water Downtakes
p 5 Water Supply Loop Layout at Terrace Level
p 5 Rain Water Drainage at Terrace Level
p 5 External Storm Water Detailed Drawing with RWH at ground floor
p 5 External Sanitary Detailed Drawing at ground floor- If applicable

ff 5 Internal Fire Fighting Layout


ff 5 Internal Fire Fighting Layout at ground floor
ff 5 Internal Fire Fighting Layout at 1st podium
ff 5 Internal Fire Fighting Layout at 2nd podium
ff 5 Internal Fire Fighting Layout at 3rd podium
Internal Fire Fighting Layout at typical floor (4th to 6th, 8th to 11th, 13th to 16th, 18th to 21st,
ff 5
23rd to 30th)
ff 5 Internal Fire Fighting Layout at Refuse floor (7th, 12th, 17th, 22nd)
ff 5 Hydrant Loop Layout at The Terrace Level
ff 5 Schematic Wet Riser
ff 5 FF UGT & Pump Room Layout at ground floor
mep 5 Shaft, Sleeve & Cut-Out Detailed Layout
mep 5 Shaft, Sleeve & Cut-Out Detailed Layout at ground floor
THE ICON BY RISLAND
AT THANE
MASTER LIST OF DELIEVERABLES

mep 5 Shaft, Sleeve & Cut-Out Detailed Layout at 1st podium


mep 5 Shaft, Sleeve & Cut-Out Detailed Layout at 2nd podium
mep 5 Shaft, Sleeve & Cut-Out Detailed Layout at 3rd podium
Shaft, Sleeve & Cut-Out Detailed Layout at typical floor (4th to 6th, 8th to 11th, 13th to 16th,
mep 5
18th to 21st, 23rd to 30th)
mep 5 Shaft, Sleeve & Cut-Out Detailed Layout at Refuse floor (7th, 12th, 17th, 22nd)
mep 5 Location of MEP Equipments with Sectional Details
mep 5 Location of MEP Equipments with Sectional Details at ground floor
mep 5 Location of MEP Equipments with Sectional Details at 1st podium
mep 5 Location of MEP Equipments with Sectional Details at 2nd podium
mep 5 Location of MEP Equipments with Sectional Details at 3rd podium
Location of MEP Equipments with Sectional Details at typical floor (4th to 6th, 8th to 11th, 13th
mep 5
to 16th, 18th to 21st, 23rd to 30th)
mep 5 Location of MEP Equipments with Sectional Details at Refuse floor (7th, 12th, 17th, 22nd)
mep 5 Coordinated External Services Layout at ground floor
mep 5 MEP Coordinated Services Layout At the Floors Level
mep 5 MEP Coordinated Services Layout At the ground Floors Level
mep 5 MEP Coordinated Services Layout At the 1st podium Floors Level
mep 5 MEP Coordinated Services Layout At the 2nd podium Floors Level
mep 5 MEP Coordinated Services Layout At the 3rd podium Floors Level
mep 5 MEP Coordinated Services Layout At the Ceiling Level
mep 5 MEP Coordinated Services Layout At the ground Ceiling Level
mep 5 MEP Coordinated Services Layout At the 1st podium Ceiling Level
mep 5 MEP Coordinated Services Layout At the 2nd podium Ceiling Level
mep 5 MEP Coordinated Services Layout At the 3rd podium Ceiling Level
MEP Coordinated Services Layout At the typical floor Ceiling Level (4th to 6th, 8th to 11th,
mep 5
13th to 16th, 18th to 21st, 23rd to 30th)
mep 5 MEP Coordinated Services Layout At the Refuse floor Ceiling Level (7th, 12th, 17th, 22nd)
Sr No
1

2
3
4

6
7
8
9
10
11
12
13
14
15
15
16
17
18
19
Activity
store room allocation to lift vendor

scaffolding material delivery date


compltion of scaffolding erection
status of lift erection permission from PWD

lift shaft handover with whitewash and electrical work, smoke window, I beam for lifting machines to lift vendor
material deleivery date for B2 wing 2 nos of lift

template installation
guide rail support installation
guide rail installation
machine installation in LMR
lift ELV cableing in shaft
lift cart bottom frame installation
Buffer installation
lift door frame installation
lift jams installation by civil agency
cutouts making for landing plate and service box in brick work
lift cart installation
rope installation
slow speed
testing and commissioning
Remark
lift material will require large space, better to be
given near respective lift shaft

all required document alredy shared with lift vendor


dependent activity-painting vendor,electrical
vendor,civil vendor

( one lift in B1 wing if fire lift ,and one lift from


B2 wing is fire lift ) need inform liasoing team
,architet

dependent activity-civil vendor


dependent activity need FFL in lift lobby

dependent activity