Professional Documents
Culture Documents
College of Architecture
Submitted to:
Submitted by:
ARC 214
March 1, 2024
Exercise 10: Full Specifications
Division 1: GENERAL REQUIREMENTS
Owner.
relevant rules and regulations that are enforced in the area, the National
Building Code of the Philippines (NBCP) and American Society for Testing
SCOPE
Structure.
must be met.
P a g e 2 | 89
Exercise 10: Full Specifications
writing. The Engineer will interpret and resolve the conflict in accordance
RELATED DOCUMENTS
1. Contract Drawing
2. Specifications
4. Change Orders
7. As-Built Drawings
SCHEDULE OF DRAWINGS
The following are Working Drawings and Project Manuals as reference for the
construction completion:
ARCHITECTURAL DRAWINGS
A-3 Elevations
P a g e 3 | 89
Exercise 10: Full Specifications
A-3.2 Rear Elevation
A-4 Sections
P a g e 4 | 89
Exercise 10: Full Specifications
STRUCTURAL DRAWINGS
PLUMBING DRAWINGS
P a g e 5 | 89
Exercise 10: Full Specifications
P-1.6 Floor Cleanout Construction Details
ELECTRICAL DRAWINGS
P a g e 6 | 89
Exercise 10: Full Specifications
E-1.4 Second Floor Lighting Layout
P a g e 7 | 89
Exercise 10: Full Specifications
CLEANING
completed (in each region of the Project), clean the unit or element to a
condition acceptable for occupancy and usage (as intended), and repair
minor or superficial damage. Replace units and pieces that are too
2. Clean and restore adjacent surfaces and other work that was dirty or
cannot be successfully restored. units and pieces that are too damaged to
be successfully restored.
During Construction
2. Clean up the work site and dispose of waste, rubbish, and debris at regular
intervals.
*End of Section*
P a g e 8 | 89
Exercise 10: Full Specifications
Division 2: EXSTING CONDITIONS
Site Clearing
Part 1: General
1. The work done under this consists of rubbish, debris, designated trees,
provisions.
slopes.
do not remove any material until the staking and cross sectioning of the site
is complete.
accordance with P.D 1096 Green Building Code Section 14: Site
Sustainability.
P a g e 9 | 89
Exercise 10: Full Specifications
RELATED DOCUMENTS
Part 2: Products
Materials
1. Tree protection
Insulation)
3. Backhoe loader
P a g e 10 | 89
Exercise 10: Full Specifications
Part 3: Execution
Preparation
construction activities.
construction.
the damaged vegetation. Remove any dense grass growth before stripping.
avoid soil erosion and the discharge of soil-bearing water runoff or airborne
requirements.
A. Remove any obstructions trees, shrubs, and other vegetation to make way
be relocated.
P a g e 11 | 89
Exercise 10: Full Specifications
B. Fill depressions created by clearing and grubbing operations with suitable
Topsoil Stripping
B. Strip topsoil so that it does not mix with underlying subsoil or other waste
items.
materials, and waste materials, including waste and debris, from the
site.
Earth Moving
Part 1: General
Provide all personnel, materials, and equipment required to execute all work as
detailed on the Drawings. The works included in this section are excavating and
filling for rough grading the site, preparing subgrades for walks, pavements, turf
and grasses and plants, subbase course for concrete walks and pavements,
subbase course and base course for paving, subsurface drainage backfill for walls
and trenches, and excavating and backfilling trenches for utilities and pits for
buried utility structures. Suitable fill from off-site if on-site amounts are insufficient
P a g e 12 | 89
Exercise 10: Full Specifications
or unsuitable, and legal disposal of excess fill off-site. After excavating
The work under this section comprises of executing all activities required to shape
the existing ground preparatory to the placement of the fill or surface material.
Grade trench bottoms accurately to give uniform bearing and support for each
section of pipe on undisturbed soil along its entire length. Make sure the pipe
subgrade has a smooth, uniform surface where the bedding material will be laid.
Excavation
dimensions are provided. Excavate the building pad to the stipulated dimensions
and depths in the approved site plan. Provide trenching and backfill for mechanical
and electrical work and utilities. Borrow materials are to be provided when off-site
suitable fill if on-site quantities are insufficient or undesirable, and legal off-site
disposal of excess fill. It must be ensured that the excavation does not extend
enough to allow for the appropriate installation and removal of concrete forms or
Excavated trenches must be wide enough to allow for adequate pipe, conduit, or
cable laying, and banks must be sloped to meet current safety standards.
P a g e 13 | 89
Exercise 10: Full Specifications
Fill
Ensure that the excavations and areas to be filled are clear of loose dirt, trash,
and standing water. Cobbles, boulders, and rock fragments whose biggest
dimension exceeds the allowed limitations for each type of fill (usually less than
75 mm for structural fill and 125 mm for general fill) are not permitted to be
incorporated into the fill. The Earthworks Contractor should consider removing big
fragments and sending them through a crusher unit to reduce their size to a
suitable grading.
Backfill
Excavated soil that is devoid of frozen material, stumps, roots, brush, other organic
matter, debris, and other objects. Place backfilled material above embedment
the thickness required to provide the prescribed backfill density or to meet other
regulatory criteria.
Excavations include:
1. Topsoil Excavation
2. Footings Excavation
5. Trench Excavation
P a g e 14 | 89
Exercise 10: Full Specifications
Excess Excavation
Backfill any excavations taken that is wider than required specified for backfilling
and deeper than required with compacted material specified for backfilling.
Part 2: Products
- Excavator
- Trencher
- Loader
Geotextiles:
Materials:
P a g e 15 | 89
Exercise 10: Full Specifications
8. Impervious Fill: Gravel and sand mixture capable of compacting to a dense
state
Part 3: Execution
Preparation
Dewatering
prepared subgrades, and flooding the project site and surrounding region.
3. Surface water runoff should be diverted away from excavated areas. Allow
4. Excavate soil with a 0.6m diameter and 2.4m depth for shallow wells.
P a g e 16 | 89
Exercise 10: Full Specifications
Excavation
2. Excavate 300mm for the preparation of slab with 100mm topsoil thickness.
allow for sufficient drainage, and avoid stockpiling items within the drip line
of trees.
following:
supported walls
P a g e 17 | 89
Exercise 10: Full Specifications
5. Place a 100mm bedding course on trench bottoms as indicated. Form
bedding course to give continuous support for pipe bells, joints, and barrels,
6. Backfill voids with suitable soil while removing shoring and bracing. To
backfills under pipe haunches and with a 100mm allowance from pipes
uniformly up on both sides and along the whole length of piping or conduit.
Coordinate backfilling with utility testing. After that, place and compact final
ASTM D698:
for heavy equipment and no more than 100mm loose depth for hand
indicated
drainage.
conduit
P a g e 18 | 89
Exercise 10: Full Specifications
9. Grade regions uniformly to a smooth surface free of uneven surface
changes. Comply with compaction standards and grade to the given cross
*End of Section*
P a g e 19 | 89
Exercise 10: Full Specifications
Division 3: CONCRETE
Part 1: General
curing.
unique circumstances.
durability of all the concrete that is put at different locations throughout the
4. All applicable work shall be carried out in accordance with the ASTM
5. The contractor should offer all necessary measures to protect both existing
and new construction, such as bracing and shoring for imposed loads
during construction.
steels, miscellaneous iron, pre-cast concrete etc. Must be provided for the
9. All bar diameters and spacing are in millimeter unless otherwise noted.
P a g e 20 | 89
Exercise 10: Full Specifications
10. All slabs, beams, girders, and other structural elements that are not
complete the structural work in accordance with the intent of the plans and
It is known that the contractor offered and included all of these features in
their bid.
RELATED DOCUMENTS
A. Foundation
P a g e 21 | 89
Exercise 10: Full Specifications
2. All column footings must rest on a 100mm thick properly compacted
5. Plasticity Index shall not exceed 12% when tested in accordance with
ASTM D-424.
6. No more than 25% by weight an shall be finer than No, 200 Sieve when
B. Concrete
for Reinforced Concrete ACI 318 or the national structural code of the
2. The following is the minimal concrete cover for all reinforcing bars in
non-corrosive environments:
to earth or weather
P a g e 22 | 89
Exercise 10: Full Specifications
to weather nor in
structures—must be followed.
P a g e 23 | 89
Exercise 10: Full Specifications
9. Admixtures may be used to get the right slump and workability, but only
C. Slab-on-grade
the soil, subgrade, and fill layers beneath slabs-on-grade, paving, and
plans.
indicated on plan.
at 60mm O.C.
D. Reinforcing Bars
2. Bars must be free of anything that could weaken the binding, such as
be formed cold.
P a g e 24 | 89
Exercise 10: Full Specifications
DIAMETER OF BARS ASTM GRADE
4. Bar splices must be securely wired together and shown in details for
securely wired together stagger splices at least 600mm. Splice the top
bar at midspan and the bottom bar close to the support wherever it is
Part 2: Materials
B. Conform to the requirements for fine and coarse aggregates in ASTM C 33.
robust, resilient, and hard. Use clean water to wash each aggregate. We
- 25mm-40mm Aggregates
- 22 cu.m of Sand
- 44 cu.m of Gravel
E. Use clean water that satisfies ASTM C 94 standards and is devoid of any
specification.
- Water
F. Formulate concrete mix from cement, aggregate and water, all as specified
and approved. Do not add other ingredients without prior approval of the
Engineer.
- Concrete cylinders
G. Use spacer blocks made from cement, sand and small aggregate not
reinforcement to ensure that they are not displaced when the concrete is
poured. Make these of similar mix proportions and strength as the adjacent
concrete.
P a g e 26 | 89
Exercise 10: Full Specifications
Part 3: Execution
A. Formwork
1. Check centers, lines, and levels before starting the formwork. Verify that
2. Install formwork, shoring, and bracing in compliance with ACI 301 and
the structure. This could imply that they are occasionally moved to the
5. Align joints and ensure water tightness to stop concrete grout leaks.
7. In order to ensure precise alignment at the sides and a clean line at the
P a g e 27 | 89
Exercise 10: Full Specifications
B. Concrete Reinforcement
184, ASTM A 185, ASTM A 615, ACI 318, CRSI 63, and CRSI 65, as
3. Avoid straightening or re-bending cold wrought and hot rolled high yield
bars after they have been bent. To bend mild steel reinforcement cast
the bar.
4. After bending, bind bars together in bundles or groups and identify them
of any loose mill scale, rust, oil, grease, concrete, or other hazardous
material.
C. Concrete Mix
1. Conduct preliminary test for concrete mix ratio in accordance with the
within 7 days, 14 days, and 28 days; the remaining 3 are for spare.
P a g e 28 | 89
Exercise 10: Full Specifications
- 28 days = 99% of desired strength
3. Unless otherwise stated by the Engineer, mix concrete in 1:2:4 ratio for
Suspended slabs, footings, beams, footing tie beams, wall footings, and
6. Give the engineer at least 24 hours' notice before starting any operat
Make sure that while placing the concrete, the reinforcement, inserts,
Minimum 150 mm lap joints that are sealed airtight with taped ends and
edges.
8. Concrete when deposited shall have a temperature not less than 5°C
and not more than 28°C except with the approval of the Engineer.
than 300 mm, unless columns are included or the Engineer specifies
10. Protect freshly placed concrete from rainfall and from water running
over the surface until it is sufficiently hard to resist damage from this
cause.
strength.
P a g e 29 | 89
Exercise 10: Full Specifications
12. Use a curing procedure that protects exposed concrete surfaces from
following the last tamping, apply the curing in position. While the
concrete is still flexible, tamp the surface one more to seal any cracks
site.
*End of Section*
P a g e 30 | 89
Exercise 10: Full Specifications
Division 4: MASONRY
Part 1: General
2. The contractor will set up and complete all work required to accept and
RELATED DOCUMENTS
P a g e 31 | 89
Exercise 10: Full Specifications
l. S-2.6 Column Details
Part 2: Materials
3. CHB
Specification.
P a g e 32 | 89
Exercise 10: Full Specifications
▪ Eagle Cement Advanced Portland Cement, 40kg bag
▪ Sand
5. Reinforcing Steel
Part 3: Execution
Installation
1. Ensure that the surfaces supporting the masonry work are clear of dirt and
other harmful materials and that they are completed with the correct lines
2. The drawings will specify the horizontal and vertical spacing between
anchors that secure the masonry wall to the structural frame. You might
3. Assemble floors, walls, and other masonry structures using cavity and
P a g e 33 | 89
Exercise 10: Full Specifications
5. Use water-cooled or motor-driven dry-cutting saws to cut masonry units so
that the edges are crisp, clean, and undamaged. Cut pieces as needed to
fit adjacent work and to create continuous patterns. If at all feasible, use
6. Install units with cut surfaces and, if at all possible, with concealed cut
edges.
7. Units shall be placed while the mortar is soft and plastic. Any unit disturbed
to the extent that the initial bond is broken after initial positioning shall be
allowances.
9. Avoid letting mortar droplets or other debris harm sills, ledges, and offsets
during building. Utilize covers laid on the ground and over the wall surface
to shield the base of walls from rain-splattered mud and mortar. Lost grout
on face materials. When building, take care to avoid damaging door jambs
and corners.
10. Mortar should not be spread too far ahead of units, as it will stiffen and
loose plasticity, especially in hot weather. Mortar that has stiffened should
not be used. ASTM C270 requires that mortar be used within 2 ½ hours of
initial mixing.
P a g e 34 | 89
Exercise 10: Full Specifications
and every (3) CHB layers horizontally for rebars using 9m length steel
reinforcement.
2. Reinforcement shall be clean and free from loose, rust, scales, and any
3. When a foundation dowel does not connect with the vertical core to be
2. Plan your wall layout in advance to ensure that surface bond patterns are
movement-type joints, offsets, and returns are all located precisely. Less-
3. Lay-up walls with precise course spacing and coordination with other
4. Fill the space between hollow metal frames and masonry with mortar,
beneath bearing plates, beams, lintels, posts, and similar things, unless
otherwise specified.
P a g e 35 | 89
Exercise 10: Full Specifications
Mortar bedding and Jointing
of 10mm conforming to the current masonry codes standard for mortar joint
2. Install solid masonry units and fully-grouted hollow CMU with a filled bed
and head joint. Apply enough mortar to fill head joints and shove into place.
Make strike joints flush on surfaces that will be plastered, covered with
4. Remove any mortar that is protruding into the grouting cells or voids. Do
not allow mortar droppings to clog weep holes. Mortar should not be used
5. Remove any masonry components that were disturbed during the laying
process; clean and reset in fresh mortar. Avoid pounding jamb corners to
Construction Stability
1. Provide and install bracing that will ensure stability of masonry during
construction.
P a g e 36 | 89
Exercise 10: Full Specifications
2. Allow 16 hours after completing masonry columns and walls to place floor
sections.
professional Engineer.
6. Formwork shall not be removed until the reinforced masonry member has
cured enough to support its own weight and additional loads during
construction.
7. Allow at least the following time after completion of the member to remove
shores or forms, if proper curing conditions were attained during the curing
period:
Grouting
reinforcement.
2. Do not place grout until entire height of masonry to be grouted has attained
P a g e 37 | 89
Exercise 10: Full Specifications
4. Extend reinforcement beyond masonry as needed for splicing when
should be poured to within 1-1/2 inches of the initial pour's top course. Prior
to grouting, lay the masonry units and the reinforcement for the second
pour section once the grouted masonry has cured. If more pours are
Cleaning
1. When mortar is thoroughly set and cured, clean masonry by removing large
chisels.
2. Use a sample wall panel to test cleaning techniques; for comparison, leave
masking agent to shield nearby stone and non-masonry surfaces from the
cleaner.
5. Ensure that the unit masonry work is free of damage and deterioration at
*End of Section*
P a g e 38 | 89
Exercise 10: Full Specifications
DIVISION 5: METALS
Part 1: General
1. All structural steel must meet the necessary ASTM requirements for the
needed strength.
3. Specify shop primer painting for all steel and welds. Field touch-up
following erection.
METAL JOISTS
METAL FABRICATIONS
P a g e 39 | 89
Exercise 10: Full Specifications
Handrails
2. Design handrails to project beyond top and bottom steps of the stairs as
required by code.
3. Construct handrails with smooth shapes and return ends to the wall or
Grilles
1. Refer to the Door Schedule for the security and aesthetic requirements for
Part 2: Products
2. 380mmx12mm dia. Plain Bar w/ standard nuts & washers @ both ends:
Sagrod
GRILLES
MISCELLANOUS
5. Paint brush # 4
7. Paint Thinner
8. Hacksaw Blade
Part 3: Execution
1. Before starting work, verify the details and locations of the framing from
2. The Contractor shall take extreme care when unloading, handling, and
members.
3. The Contractor must plan and execute the erection in a way that
4. Tack welds must be ground smooth, and holes should be filled with weld
RAILINGS
tolerances.
P a g e 41 | 89
Exercise 10: Full Specifications
4. Weld connections that cannot be shop welded due to shipping size limits
and should not be left exposed. Do not weld, cut, or abrade the surfaces
connections.
6. After erection, remove any mud and filth that has accumulated on the
steelwork. Clean mud from visible areas, apply touch-up primer layer, and
GRILLE WORKS
1. Refer to the Door Schedule for the dimensions of the grille works.
*End of Section*
P a g e 42 | 89
Exercise 10: Full Specifications
Division 6: WOODS & PLASTICS
Part 1: General
the structure. The design and finish should prioritize flexibility, durability,
effectiveness.
2. The use of endangered or limited tree species for veneers or solid stock,
cost species.
4. Cabinet and millwork tops, sides, dividers, and shelving must be at least
3/4" stock. Stained veneer materials must meet AWI custom grade
accessibility requirements.
7. Shelving, whether built-in or free-standing, should not exceed 6' from the
thickness.
P a g e 43 | 89
Exercise 10: Full Specifications
Part 2: Products
1. Lumber
▪ Size: ½” X 2” X 12’
▪ Size:1” X 2” X 12’
Part 3: Execution
1. Install work plumb, level, securely in place and with tightly fitted joints.
anchorage devices and cover with solid plugs that match the surrounding
*End of Section*
P a g e 44 | 89
Exercise 10: Full Specifications
Division 7: THERMAL MOISTURE AND PROTECTION
Part 1: General
manufacturer directions.
membrane so that the installer of the membrane can properly seal them.
Refrain from adding extra sleeves, and when you do install them, give
Scope
ROOFING INSULATION
P a g e 45 | 89
Exercise 10: Full Specifications
SEALANTS
before, during, and after application. Allow surfaces to dry after rain
1. Refer to Sheet No. A-2.3 Roof Plan for the details and specifications.
2. Design a roof system that can withstand walking loads without causing
square-inch pad situated in the middle of the panel flat without rib buckling
3. Air Infiltration: Not over 0.09 cfm per square foot at a static air pressure
difference of 4.0 lbf/sq. ft. when tested in accordance with ASTM E1680.
inward acting, wind-load design pressure of not less than 6.24 lb/sq. ft.
P a g e 46 | 89
Exercise 10: Full Specifications
Part 2: Products
ROOF INSULATION
Aluminum Foil)
JOINT SEALANTS
50mm)
OTHER ROOFING
P a g e 47 | 89
Exercise 10: Full Specifications
Part 3: Execution
3. Surfaces should be clean, devoid of holes and defects, smooth, and dry
project. To waterproof the space, plug all drains and create temporary
point. Keep the water for at least 24 hours. Immediately address any
indication of leaking.
ROOF INSULATION
projections that will (impede adhesive bond or) damage insulation board.
P a g e 48 | 89
Exercise 10: Full Specifications
3. Install insulation without gaps or voids.
1. Lay down the ribbed roofing sheet starting from the end opposite the
prevailing wind.
2. Install the first sheet with the turned-down edge facing outside of the
covered area.
3. Overlay the next sheet with the exposed edge down and the covered
edge up.
brochure.
5. Secure the roofing sheets to the steel purlins with straps riveted to the
*End of Section*
P a g e 49 | 89
Exercise 10: Full Specifications
Division 8: DOORS AND WINDOWS
Part 1: General
1. Fenestration for the Two-storey Residential Project shall comply with all the
provisions:
alternative material with the same specification as the material that will be
4. Wood doors should often only be utilized for interior openings. You can
only use solid core wood doors for exterior openings and hollow core for
interior openings.
specified.
6. Glazing for private areas and rooms must be tinted or reflective to ensure
7. Door openings should have fire door certification or should pass the fire
door requirements.
RELATED DOCUMENTS
P a g e 50 | 89
Exercise 10: Full Specifications
Part 2: Products
1. Doors
Materials
MATERIAL SPECIFICATIONS
Link: • Dimension: 2 x 4 x 8
https://www.topmosthardware.ph/produ
ct/kd-s4s-wood-tanguile/
https://www.topmosthardware.ph/produ
ct/pvc-door-with-louver-white/
Link:
P a g e 51 | 89
Exercise 10: Full Specifications
https://www.theprojectestimate.com/stai
nless-steel-plate-price-list/
Hardwares
BRAND SPECIFICATIONS
Leverset
Link:
https://shop.wilcon.com.ph/privacy-
leverset-0384.html • Size: 4” x 4”
Link:
https://shop.wilcon.com.ph/ball-bearing-
hinge-284400004225.html
BEDROOM (D1, mm
https://www.vhmanila.com/handles-1
P a g e 52 | 89
Exercise 10: Full Specifications
Link: • Material: Stainless Steel
https://shop.wilcon.com.ph/ball-bearing-
hinge-284400004225.html
https://shop.wilcon.com.ph/privacy-
leverset-0384.html
• Size: 4” x 4”
- Direct Hardware Ball Bearing
• Finish: Satin
Hinge
• Material: Stainless Steel
Link:
https://shop.wilcon.com.ph/ball-bearing-
hinge-284400004225.html
2. Windows
Frames
MATERIALS SPECIFICATIONS
W5)
PrimoBoard PVC
-
Link:
https://primoboard.com.ph/what-is-
primoboard/
P a g e 53 | 89
Exercise 10: Full Specifications
• AWNING WINDOW W/
TRANSOM (W2)
https://www.apmc.ph/products/al
uminum/sheets-plates
CORNER WINDOW
https://www.apmc.ph/products/al
uminum/sheets-plates
WINDOW
PrimoBoard PVC
-
Link:
https://primoboard.com.ph/what-
is-primoboard/
• AWNING WINDOWS
Link:
• Dimensions: 0.051” x 4’ x 8’
https://www.apmc.ph/products/al
uminum/sheets-plates
• Glazing
P a g e 54 | 89
Exercise 10: Full Specifications
o Tinted Glass
o Clear Glass
o Reflective Glass
Link: https://www.pfg.com.ph/products/tintedfloat.html
• Hardwares
TYPE Materials
e%202019.pdf • bundle
• top/bottom mohair
• Hardmesh
P a g e 55 | 89
Exercise 10: Full Specifications
Link: https://onesky.ph/wp- • Forebar Center/Side Open
e%202019.pdf
e%202019.pdf
Awning Window
• 368B Camhandle
Link: https://onesky.ph/wp-
• Forebar Center/Side Open
content/themes/onesky/assets/ca
(8”, 10”, 12”, 14”) 202 & 304
talog-
stainless steel
download/Aluminum%20Brochur
• YC 38 Bubble Vinyl
e%202019.pdf
P a g e 56 | 89
Exercise 10: Full Specifications
Part 3: Execution
and prepared.
moving further.
attaining the optimum results for the substrate under the project conditions.
8. Before field finishing, ensure that all doors are fully hung, with all hardware
installed, tested, and adjusted for a precise fit. Dismount doors, remove
*End of Section*
P a g e 57 | 89
Exercise 10: Full Specifications
Division 9: FINISHES
Part 1: General
referring:
bundles, or containers.
and their products which will be used. Approval of the manufacturers and
RELATED DOCUMENTS
2. A-3 Elevations
PLASTER
1. 3 (three) coat cement plaster with smooth finish coat to receive paint and
wallpaper. 2 (two) coat cement plaster with smooth finish coat to receive
work is being performed so that the cement plaster can cure properly.
fluctuations.
CEILING
1. Do not install a wood ceiling until all wet construction work is completed
and the moisture content of the ambient air in the installation room has been
stabilized.
P a g e 59 | 89
Exercise 10: Full Specifications
4. Ceilings must be freely accessible for maintenance and other needs,
expenses, buildings should employ a consistent ceiling tile, tile size, and
PAINT
1. Before applying paint, finish one whole surface of each color scheme,
workmanship.
throughout building.
Architect and apply finishes on identical type materials to which they will be
applied on job.
4. Identify each sample as to finish, formula, color name and number, and
combustion.
P a g e 60 | 89
Exercise 10: Full Specifications
8. No paint shall be applied to surfaces structurally or superficially damps and
manufacturer.
Building Code.
FLOORING
1. Tile concrete bases must have a floating finish rather than a steel trowel
finish.
3. Nonskid ceramic tiles for areas with heavy duty use and liquid exposure
4. Installation of tile should wait until the spaces are finished being
constructed and the relative humidity and temperature are kept at the levels
are cited.
1. Tile adhesive should be both applicable for indoor and outdoor application.
2. Grout should match or be a shade darker than the color of the tiles.
3. Use an antibacterial grout material that has anti-mold properties for grouted
tiles.
P a g e 61 | 89
Exercise 10: Full Specifications
Part 2: Products
1. Ceilings
• CF-1
▪ Thickness: 3.5mm
▪ Dimensions: 19 × 25 × 5000 mm
▪ Thickness: 0.4mm
• CF-2
▪ Finish: Matte
▪ Material: Pvc
▪ Dimensions: 19 × 25 × 5000 mm
▪ Thickness: 0.4mm
• CF-3
▪ Thickness: 10.0mm
▪ Color: Bronze
P a g e 62 | 89
Exercise 10: Full Specifications
o CARRYING CHANNEL
▪ Thickness: 1.00 mm
2. Walls
• WF-1
▪ Color: White
• WF-2
▪ Color: White
• WF-3
▪ Color: White
• WF-4
(Thickness)
P a g e 63 | 89
Exercise 10: Full Specifications
Figure 1. https://homeu.ph/products/copy-of-flex-30-series-mdf-slat-fluted-wall-panel
1Gal.
• Color: White
• WF-5
▪ Dimension: 53x100cm
▪ Material: Non-Woven
Figure 2.
https://dqvd9g622ecnq.cloudfront.net/media/catalog/product/cache/5bc9fafbd097fcac6ea36e150ae65605/2/8/284
400000397-1.jpg
P a g e 64 | 89
Exercise 10: Full Specifications
▪ Color: White
• WF-6
▪ Color: White
• WF-7
▪ Color: White
• WF-8
▪ Dimension: 53x100cm
▪ Material: Pvc
P a g e 65 | 89
Exercise 10: Full Specifications
Figure
3.https://dqvd9g622ecnq.cloudfront.net/media/catalog/product/cache/5bc9fafbd097fcac6ea36e150ae65605/2/8/2
84400000385-1.jpg
3. Tiling
a. FF-1
o Series: Chadler
b. FF-2
o Color: Caramel
c. FF-3
o Color: Mocha
d. FF-7
P a g e 66 | 89
Exercise 10: Full Specifications
o Size: 30cm x 30cm
o Texture: Non-skid
e. FF-10
f. FF-11
Mounted
4. Flooring
• FF-4
▪ Color: Acacia
• FF-5
• FF-6
• FF-8
• FF-9
• FF-12
5. Grout
6. Tile Adhesive
o Color: White
Part 3: Execution
CEILING
carrying channels, and no more than 50mm from the perimeter walls.
P a g e 68 | 89
Exercise 10: Full Specifications
WALLS
1. Plaster
c. Apply cement plaster using two coat system and three coat system
respectively as indicated.
2. Panels
grease and other foreign matter that may affect the effectiveness of
P a g e 69 | 89
Exercise 10: Full Specifications
b. Measure and mark the surface where the panels will be attached
d. Apply the panels onto the marked wall and ensure that the panels
are straight.
3. Wallpapers
out.
4. Tiles
i. Make sure the substrates used to set tile are firm, dry, clean, free
ii. Check that the concrete substrates for tile floors laid with thin set
b. Installing should only begin after poor conditions have been fixed.
Ceramic Tile" ANSI A108 series that are applicable to the types of
installation standards:
d. Unless otherwise specified, extend tile work into nooks and under or
aligned joints, carefully grind the cut edges of tile that abut trim,
P a g e 71 | 89
Exercise 10: Full Specifications
fit tile tightly to electrical outlets, pipework, fixtures, and other
penetrations.
pattern. Arrange the tile work and place the tile fields in the middle
of each room or along each wall. Reduce the amount of parts that
are less than half of a tile when laying out tile work. Provide
grout joints in tile flooring. Wipe excess sealer and sealer from tile
faces with a soft cloth as soon as the sealer has reached the grout
joints.
5. Exterior Walls
Preparation
b. Examine and fix any pertinent surface flaws (such as gaps and
needed.
Application
a. Apply the mixture thinly to the surface with a steel trowel, pressing
down firmly on the concrete with the trowel's edge until it covers the
entire area.
P a g e 72 | 89
Exercise 10: Full Specifications
b. Allow it to cure for at least 60 minutes before applying the second
the surface, tilt the steel trowel to 45º and press hard on all covered
regions.
e. Allow at least seven (7) days of cure time before applying the clear
coat.
*End of Section”
P a g e 73 | 89
Exercise 10: Full Specifications
Division 15: PLUMBING
Part 1: General
1. All plumbing work must be built in line with the most recent appliance laws,
Any differences between designs or drawings and the site must be reported
3. All pipes must be put at the locations specified in the designs. Any
relocation required for the appropriate execution of other trades must have
4. The proposed sanitary installation has to stick to the actual location and
Contractor.
5. All horizontal drain slopes must be at least 1%, unless otherwise specified
in the Drawing.
6. The sizes of water supply pipes to fixtures must be consistent with the
manufacturer's recommendations.
7. The Contractor must verify all existing utilities on site and coordinate the
work with the sewage line effluent disposal point and the water service
connection point.
8. All pipes sizes are in millimeters and lengths are in meters unless otherwise
stated.
P a g e 74 | 89
Exercise 10: Full Specifications
RELATED DOCUMENTS
P a g e 75 | 89
Exercise 10: Full Specifications
Part 2: Products
1. Cold (potable) and non-potable water lines for risers, downfeeds, and
complying to DIN requirements DIN 8077 and DIN 8078 or ASTM 2389,
2. Soil, Waste and Vent Pipes - shall be Polyvinyl Chloride (PVC) pipes
4. Storm Drainage Lines – shall be Polyvinyl Chloride (PVC) pipes series 1000
reinforced concrete drain pipes (RCP), tongue and groove, mortar joints for
sizes 300 mm diameter and larger conforming to ASTM C-76 Class IV Wall
B.
WATER SUPPLY
Pipes
Valves
Fittings
12. 2" x 3/4 (63mm x 25mm) ICON Minde PPR Male Adapter
Fixtures
Appliances
P a g e 77 | 89
Exercise 10: Full Specifications
3. Hayward DE3620 Pool Filter - Pro-Grid® Series Vertical Grid D.E. Filter
6. 1.5 HP Adelino Acm Centrifugal Water Pump (1" or 25mm inlet & outlet)
SANITARY
Pipes
Fittings
P a g e 78 | 89
Exercise 10: Full Specifications
STORM DRAINAGE
Pipes
Fittings
Fixtures
P a g e 79 | 89
Exercise 10: Full Specifications
Part 3: Execution
1. The drainage and venting system must have pluggable apertures that allow
water to fill up to the topmost stack vent or vent stack above the roof.
2. The system must hold the water for 30 minutes, with no drop exceeding
100 mm.
3. If the Engineer requires additional tests, such as air or smoke tests on the
expense.
evaluation.
4. Drawing plans, schematics, and diagrams show the general location and
expansion, pump sizing, and other design factors. Install piping according
7. Each section of pipeline shall be gradually filled with water, and the
the highest point of the pipe under test, and the taps shall be tightly shut
when the test is completed, unless otherwise indicated. During testing, all
checked. If found broken or damaged, the Contractor will replace them with
sound materials at their expense. The test will be repeated until satisfactory
1. After completing the pressure test, the leakage test will examine all
exposed joints for leaks and assess the overall leaking of the pipeline.
2. The pressure to be maintained during the test shall be the designed working
3. Leakage tests must be conducted at least 24 hours after the pipe has been
4. The duration of each leakage test shall be two hours unless otherwise
5. Fill each pipe line gradually with water and apply the appropriate test
6. Before beginning the leakage test, all air must be released from the pipe.
During testing, all exposed pipes, fittings, valves, and joints should be
P a g e 81 | 89
Exercise 10: Full Specifications
DEFECTIVE WORK
2. The Contractor is responsible for repairing piping with new materials at their
expense.
CLEANING
1. All exposed metal surfaces shall be free of grease, dirt of other foreign
materials.
3. Clean all equipment, pipes, valves, and fittings of any accumulated grease
*End of Section*
P a g e 82 | 89
Exercise 10: Full Specifications
Division 16: ELECTRICAL
Part 1: General
1. Provide all personnel, materials, and equipment required by the plans and
comprises both the work indicated in this division and the equipment
RELATED DOCUMENTS
4. Protect products and tools from loss or damage throughout the contract.
6. During construction, use manufactured seals to cap all conduit runs. Keep
7. Do not cut or notch any structural member or building surface without prior
consent from the Engineer. Carefully cut, channel, chase, or drill floors,
8. All work will be done by skilled and experienced staff, with ongoing
supervision.
P a g e 84 | 89
Exercise 10: Full Specifications
PERMITS
1. To proceed with the electrical installation, get and pay for all necessary
TEMPORARY INSTALLATION
2. Pay for temporary electricity services and use rates until the project is done.
Part 2: Products
outdoor receptacles.
C. Use THHN/THWN 14-gauge wire for lamps, lighting fixtures, and lighting
circuits.
PVC, Black
Connection Boxes
P a g e 85 | 89
Exercise 10: Full Specifications
Wires
Switches
Convenience Outlets
2. Circuit Breaker
Lighting Fixtures
1. Alphalux LED Ceiling Lamp 500mm (Daylight, Warm White, and Cool
White)
P a g e 86 | 89
Exercise 10: Full Specifications
3. CYMAX L.E.D. Ceiling Lamp (100cm x 90cm x 20cm) Tri-color
Heads
Light Bulbs
P a g e 87 | 89
Exercise 10: Full Specifications
Part 3: Execution
INSTALLATION
the exact locations of conduit, cable routing, and equipment placement will
to identify the precise routing and positioning of all raceways, cables, and
Wirings should be 2mm THHN/THWN for light fixtures and lighting circuits
specifications.
CLEAN-UP
P a g e 88 | 89
Exercise 10: Full Specifications
2. Thoroughly clean all cabinets, panels, boxes, wiring devices, cover plates,
etc. before accepting. Replace any fixtures that are broken or tarnished.
*End of Section*
P a g e 89 | 89