PAPER:
BILL OF QUANTITIES/TENDER DOCUMENTS PREPARATIONS
FACILITATORS
QS ADEREMI MURAINA, FNIQS, MRICS,
QS ADEWUMI AKINPELU, FNIQS, MRICS, mni
MAY, 2023
Amaquants Associates 1
COMPREHENSIVE ENGINEERING INFRASTRUCTURE OF A
DISTRICT
Amaquants Associates 2
Building and Engineering Standard Method of Measurement, 4th
Edition (Revised) BESMM4(R)
The preparation of Bill of Civil Engineering Works can be done by the
Quantity Surveyor who is specifically trained on how to do it.
q The cost associated with the adverse conditions under which some of
the work would be executed such as bodies of water, banks of rivers
or sea coast, low-lying marshy land etc.
Amaquants Associates 3
This is important because a truly useful Bill of Quantities (BoQ) should
reflect the nature of the work proposed and the circumstances under
which it will be executed.
Amaquants Associates 4
PREPARATION OF THE BILL OF QUANTITIES
Sections of the Bill of Quantities
A. List of Principal Quantities
B. Preamble
C. Daywork Schedule
D. Work Items:- 26 Parts (Work Classification Sections)
v Part 2A - General Items
v Part 2B - Ground Investigation
v Part 2C - Geotechnical and other specialist processes
v Part 2D - Demolition and Site Clearance
vPart 2E - Earthworks
v Part 2F - In-situ Concrete
v Part 2G - Concrete Ancillaries
Amaquants Associates 5
PREPARATION OF THE BILL OF QUANTITIES Cont’d
vPart 2H - Precast Concrete
v Part 2J - Pipework - Pipes
v Part 2K - Pipework – Fittings and Valves
vPart 2L - Pipework – Manholes and Pipe work Ancillaries
v Part 2M - Pipework Supports and Protection, Ancillaries
to laying and excavation
v Part 2N - Structural Metalwork
v Part 2P - Miscellaneous Metalwork
v Part 2Q - Timber
v Part 2R - Piles
v Part 2S - Piling Ancillaries
v Part 2T - Roads and Paving
Amaquants Associates 6
PREPARATION OF THE BILL OF QUANTITIES Cont’d
v Part 2U -
Rail track Construction
v Part 2V -
Tunnels
v Part 2W -
Brick work, block work and Masonry
v Part 2X -
Painting
v Part 2Y -
Waterproofing
v Part 2Z -
Miscellaneous Work
v Part 2AA -
Sewer and water main renovation and ancillary
works
v Part 2AB - Simple building works incidental to civil
engineering works
Section E - Grand Summary
Section F - Schedule of Rate Breakdown for work items
Amaquants Associates 7
PREPARATION OF THE BILL OF QUANTITIES
A. List of Principal Quantities
A list of principal components of the work with their estimated
Quantities shall be provided to assist the tenderers for a quick
assessment of the work
B. Preamble
The Preamble shall indicate the inclusiveness of the unit prices and
shall state the method of measurement that has been adopted in the
preparation of the Bill of Quantities (other than BESMM4)
C. Daywork Schedule
A day work Schedule shall be included if the probability of unforeseen
work, outside the items included in the Bill of Quantities, is relatively high
Amaquants Associates 8
PREPARATION OF THE BILL OF QUANTITIES
D Work Items
The items in the Bill of Quantities which are to be priced and to
contribute to the Tender Total may be arrange into numbered parts to
distinguish between these parts of the work of which the nature,
locations, access, limitation on sequence or timing or any other special
characteristics is thought likely to give rise to different methods of
construction or considerations of cost.
General items (2A) Common to all parts of the work shall be grouped
as a separate part of the Bill of Quantities.
Items in each part shall be in the general order of the work
classification.
9
Amaquants Associates
PREPARATION OF THE BILL OF QUANTITIES
E. Grand Summary
The Grand Summary shall contain a tabulation of the parts of the Bills
of Quantities with provision for insertion of the total of amounts
brought forward from the part summaries
Amaquants Associates 10
PREPARATION OF THE BILL OF QUANTITIES
Coding and Numbering of Items
i. Coding: For covenience of reference, each item in the work classification
has been assigned a code number consisting of a letter and not more than
3 digits.
The letter corresponds to the class in the work classification in which
the item occurs and the digits give the position of the item in the
first, second and third divisions of the class, for example code 2H 1.3.6
ii. Item Numbers: Code numbers may be used to number the items in
the Bill of Quantities, the items within the Bill of Quantities being listed
in order of ascending code number
Amaquants Associates 11
PREPARATION OF THE BILL OF QUANTITIES
iii. Coding of Unclassified Items: Where a feature of an item is not listed in the
work classification the Digit 9 shall be used in appropriate position in the code
number.
iv. Where there is an item to which a division of classification does not apply or for
which fewer than 3 divisions of classifications are given the digit 0 shall
be used in the appriate positions in the code number.
v. Numbering of items within additional description:
Where code numbers are used as item numbers, a suffix number shall be
used to distinguish items which have the same code number but different
additional description eg. 2H136.1
2H136.2
2H136.3
Amaquants Associates 12
PROJECT SPECIFIC BILL OF QUANTITIES
Amaquants Associates 14
COMPREHENSIVE ENGINEERING INFRASTRUCTURE OF A
DISTRICT
TAKE-OFF SHEETS
Amaquants Associates 15
LIST OF DRAWINGS
Roads
qLocation map
qLand use map
qGeneral Layout Roads
qRoad Layout Zone 1
qRoad Layout Zone 2
qRoad Layout Zone 3 - Zone 17
qGeneral Layout Setting out details
qSetting out details Zone 1
qSetting out details Zone 2
qSetting out details Zone 3 - Zone 17
Amaquants Associates 16
LIST OF DRAWINGS
q Plan and Profile Arterial 01 Sheet 01 - 04
q Plan and Profile Arterial 02 Sheet 01 - 02
q Plan and Profile Collector 01 Sheet 01 - 04
q Plan and Profile SILS 01 Sheet 01 - 02
q Plan and Profile ILS 01
q Plan and Profile LS 01
q Plan and Profile MAR 01
qTypical Cross Section Arterial Road.
qTypical Cross Section Collector
qTypical Cross Section SILS
qTypical Cross Section ILS
qTypical Cross Section LS
qTypical Cross Section MAR
Amaquants Associates 17
BRIDGE
2 - Span 2 - Lane Bridge (Bridge 1)
ØPlan and Profile at Bridge Section Interchange at CH.1 + 424
ØGeneral Arrangement for Bridges at Interchange Bridge at CH. 1 + 424
ØLongitudinal Profile (Bridge 1)
ØElemental Sections at Interchange bridge
ØPile Arrangement - Plan
ØGeneral Arrangement for Deck Slab at Interchange Bridge
ØGeneral Slab Reinforcement at Interchange Bridge (Sheet 1 - 2)
ØInternal Web Beam Reinforcement at Interchange Bridge
ØR.C Details of Cross Beams, Piers and Piers Base at Interchange Bridge
ØFormwork details for Abutments at Interchange Bridge
ØR.C. Details of Abutment at Interchange Bridge
Amaquants Associates
18
BRIDGE (Cont’d)
Amaquants Associates 19
STORM WATER
qLocation map
qHand use map
qLegend
qGeneral Layout Storm water Drainage
qStorm water Drainage Layout Zone 1
qStorm water Drainage Layout Zone 2
qStorm water Drainage Layout Zone 3 - 31
qStorm Manhole Data Sheet 01 - 07
qSand Trap Data
qTypical Storm Manhole Types A, B, C
qTypical Gulley Inlet and Sand Trap
qSchedule of Culverts
Amaquants Associates 20
STORM WATER (Cont’d)
q Plan and Section Culvert No. 01 - 25
q Box Culvert Details (1 No X 2m X 2m)
q Box Culvert Details (2 No X 2m X 2m)
q Box Culvert Details (3 No X 3m X 3m)
q Pipe Culverts Details (1 No. Dia. 900mm)
q Pipe Culverts Details (2 No. Dia. 900mm)
q Culvert Bending Schedule Sheet 1 - 3
Amaquants Associates 21
WATER DISTRIBUTION AND FOUL SEWARAGE NETWORKS
qGeneral Layout
qWater Distribution and Foul Sewerage Networks Zone 2
qWater Distribution and Foul Sewerage Networks Zone 3
qWater Distribution and Foul Sewerage Networks Zone 4 - 15
qWater Distribution Networks Washout Valve
qWater Distribution Networks Fire Hydrant
qWater Distribution Networks - Service Connection
qWater Distribution Networks - Bridge/Stream Crossing
qWatr Distribution Networks - Pipe Trench Details
qFoul Sewerage Networks - Manhole Details
qFoul Sewerage Networks - Fiffings and Trench Details
Amaquants Associates 22
ELECTRICITY AND TELECOMMUNICATION DUCT NETWORK
Duct Network
qElectricity & Telecommunication - General Layout
High Tension
qHigh Tension Layout - Zone 1
qHigh Tension Layout - Zone 2 - Zone 16
qHigh Tension Layout - 500KVA Package Transformer Schematic
qHigh Tension Layout - Transformer Installation Details
qHigh Tension Layout - Tee-off Pole Details
Amaquants Associates 23
ELECTRICITY AND TELECOMMUNICATION DUCT NETWORK (Cont’d)
Substation
qSchematic - 33/11KV Single Line Diagram - Zone A - C
qSubstation Building - Basement Floor Layout/Earthing, Ground Floor
Earthing, Roof Earthing
Amaquants Associates 24
ELECTRICITY AND TELECOMMUNICATION DUCT NETWORK (Cont’d)
Amaquants Associates 25
AREAS OF COMMON SHAPES IN CIVIL ENGINEERING WORKS
In the preparation of Bill for Civil Engineering works especially for items
measured in m, m2 and m3, different shapes are encountered and the
determination of the lenghts, areas and volumes of these figures
respectively are necessary to get the exact quantity of the materials
involved in the work. The common shapes encountered include:
26
Amaquants Associates
AREAS OF COMMON SHAPES IN CIVIL ENGINEERING WORKS Cont’d
S/No Figure Volume Surface Area
1 Square - (Side)2
2 Rectangle - Length X Breadth
3 Triangle - ½ x base x height or √s (s-a) (s-b) (s-c)
where s = ½ (a + b + c) where a,b, and c
are the length of the three sides
4 Hexagon - 2.6 X (side)2
5 Octagon - 4.83 x (side)2
6 Parallelogram - Base x Height
7 Trapezoid - Height x ½ (base + top)
8 Circle - πr2 or πD2 where r = radius of circle and
4
D = diameter of circle
9 Sector of circle - ½ length of arc x radius
10 Segment of - (Area of sector - area of triangle) or
circle (2/3 X base X height)
11 Prism Area of base X height Circumference of base X height
14 Sphere 4/
3 πr3 4 πr2
Amaquants Associates 27
AREAS OF COMMON SHAPES IN CIVIL ENGINEERING WORKS Cont’d
S/No Figure Volume Surface Area
15 Segment of πh X (3r3 + h2) 2πrh
sphere 6
16 Pyramid 1/ area of base x height
3
1/
2 circumference of base x slant height
17 Cone 1/
3πr
2h πrl
18 Frustrum 1/
3 x height (A + B + √AB) 1/
2 mean circumference of base x slant
pyramid where A is area of large end height
and B is area of small end
19 Frustrum of 1/ πh (R2 + r2 + Rr) where R
3 πl (R + r) where l is the slant height
cone is radius of large end and r is
radius of small end
20 Simpson’s rule 1/ total length x (area of first
3
section + area of last section + ___
4 (area of even cross sections)
+ 2 (areas of odd cross section)
21 Prismoid 1/ x total length x (area
6
formula of first section + 4 (area ___
of middle section) + area
of last section)
Amaquants Associates 28
COLLECTOR 02 - (ROAD)
Amaquants Associates 29
COLLECTOR 02 - (ROAD)
Road Layers Thickness
Carriageway/Parking
v40mm Wearing Course
v60mm Binder Course
v150mm Crushed Rock Base
v150mm Subbase (Natural occuring Laterite)
Amaquants Associates
31
COLLECTOR 02 - (ROAD)
Volume Calculation Methods
The three most common methods to estimate cut and fill volumes are:
ü The cross-section method or Average end area method
ü The grid method
ü Using specialist software
Cross-section method
The cross section method involves plotting cross sections of the existing
and proposed levels at regular intervals across the project site. For each
of the cross sections, the cut area and the fill area is determined. The
volume between each pair of sections is estimated by multiplying the
average cut or fill area of the two sections by the distance between them.
Once these volumes have been calculated for each pair of sections the
total cut and fill volumes are obtained by adding them all together.
Amaquants Associates
32
COLLECTOR 02 - (ROAD)
Average End Area Method
q The Area between the existing ground and proposed ground is
calculated at each cross-section
q The Area between two consecutive cross-sections is average
q The Area is multiplied by the distance between two cross-sections
Amaquants Associates 33
COLLECTOR 02 - (ROAD)
Amaquants Associates 34
COLLECTOR 02 - (ROAD)
GRID METHOD
The grid method involves drawing a uniform grid into a plan of the
earthworks project, and taking off the existing and proposed ground levels
at each node of the grid. With these values the average depth of cut or fill
required on each cell of the grid is calculated, and the volume for each cell
is obtained by multiplying the depth by the cell area. By adding the volumes
for each cell together the total cut and fill volumes for the project can be
estimated.
The cut or fill depth for each cell is found by substracting the average
existing level of the cell from the average proposed level. If the resultant
depth is positive then this is a fill cell, while a negative value indicates a cut
cell. In either case, the volume is calculated by multiplying the cut or fill
depth by the areas of the grid cell.
Amaquants Associates 35
COLLECTOR 02 - (ROAD)
A CELL
10m
Amaquants Associates 37
COLLECTOR 02 - (ROAD)
SOFTWARE
Modern computer software allows earthworks volumes to be calculated
quicker and more accurately than either of the two manual methods
described above. There are a number of software products available for
this purpose. These products vary greatly interms of complexity and price.
Amaquants Associates 38
PART - 1 - GENERAL ITEMS
General Items
Contractual Requirements
Sum Sum General items
Contractual requirements, performance bond
2A110
2A120
2A120.1
2A120.2
2A120.3 39
Amaquants Associates
PART - 1 - GENERAL ITEMS (Cont’d)
Ditto, other insurances required by law and local practice (The
Sum Sum tenderer shall separately list and price below)
2A190
Specified Requirements
Temporary site office for the contract Administrators staff
2A211.3
Amaquants Associates 40
PART - 1 - GENERAL ITEMS (Cont’d)
Temporary site office for the Employer’s staff
Sum Sum Establishment of office for the Employer’s staff
2A211.4
2A211.5
2A211.6
Amaquants Associates 41
PART - 1 - GENERAL ITEMS (Cont’d)
Material Testing
Laboratory
Sum Sum Establishment of site material testing laboratory
2A212.1
2A212.2
2A212.3
2A221.1
2A222.1
2A222.2
2A229.1
2A229.2
2A229.3
Amaquants Associates 43
PART - 1 - GENERAL ITEMS (Cont’d)
2A221.3
Testing of Materials
Sum Sum Specified tests for Bridge bearings
2A250.1
Sum Sum All testing relating to Duct Network for Telecommunication Network
2A250.11
Sum Sum Allow for any other testing required as per specification not listed
above (List and price separately)
2A250.13
Amaquants Associates 47
PART - 1 - GENERAL ITEMS (Cont’d)
Testing of Works
Testing of the Works, as specified
Sum Sum All testing relation to Earthworks
2A260.1
Sum Sum Ditto - Roads and Paving
2A260.2
2 2nr Establishment
2A279.1
2 2nr Removal
2A279.3
The list given below is for reference only and may or may not be
adopted by the Contractor
Amaquants Associates 50
PART - 1 - GENERAL ITEMS (Cont’d)
Accommodation and buildings for the Contractor
Item Item
2A31*
2A33*
2A34*
Amaquants Associates 51
PART - 1 - GENERAL ITEMS (Cont’d)
Temporary Works
Item Item
2A35*
Temporary Works
Item Item 2A36*
2A33*
2A990
Amaquants Associates 52
PART - 2 GROUND INVESTIGATION
Ground Investigation
Confirmatory Site Investigation where necessary
20 20Nr Trial pits and trenches, minimum plan size 1200 X 1200mm, number in
material other than rock, maximum depth 1 - 200mm
2B112
30.00 30m Trial pits and trenches, Depth in material other than rock
2B130
30.00 30m Ditto, Depth backfilled, with excavated material for reinstatement
2B160
Rotary drilled
Boreholes
Nominal diameter at base 150mm
Number of boreholes, sub-surface site investigation for Bridge
10 10Nr
2B310
Amaquants Associates 53
PART - 2 GROUND INVESTIGATION (Cont’d)
250 250m Depth with core recovery in holes of maximum depth 20 - 30mm
2B334
Samples
From the Surface or from trial pits and trenches
40 40Nr Undisturbed sample of soft material from the surface minimum 40kg
2B411
40 40Nr Disturbed sample of soft material from the surface, minimum 40kg
2B412
From Boreholes
10 10Nr Disturbed soil
2B422
Amaquants Associates 54
PART - 2 GROUND INVESTIGATION (Cont’d)
Site tests and observations
10 10Nr Site tests for Ground water level
2B512
Laboratory Tests
10 10Nr Moisture content
2B711
Professional Services
40 40Nr Engineer or Geologist, Principal or consultant, for preparation and
submission of laboratory tests reports
2B833
Amaquants Associates 55
PART - 2 GROUND INVESTIGATION (Cont’d)
2B841
Amaquants Associates
56
PART - 3 - SITE CLEARANCE AND EARTHWORKS
PART 3
SITE CLEARANCE AND EARTHWORKS
Length of Road = 500m
Width of Road = 46m
Limit of Road Reserve = 10m on either side (Assumed)
L = 500m
W = 46 + (2 X 10m) = 66m
Removal of Trees
45 45nr Demolition and Site clearance, Trees, Girth, 500 - 2m
2D210
PART 3
SITE CLEARANCE AND EARTHWORKS
Amaquants Associates 58
PART - 4 - EARTHWORKS
Cutting and Embankment (Collector Road 02)
INITIAL CALCULATIONS FOR DIMENSION
Cross-section Area/Average end Area
Since the cross-sections of Collector Road 02 are of fairly regular shape,
trapezoidal rule is used for the calculation of areas and volumes. However,
for an irregular cross-section, compute the cross-section area by dividing
in into triangles and trapezoids.
CH 0 + 000 (Cut)
Step 1: Calculate the depth (depth at centre of the road)
Deduct Ground level from Grade level. The resultant is depth. A negative
resultant indicates Cut. A positive resultant indicates Fill.
Amaquants Associates 59
PART - 4 - EARTHWORKS (Cont’d)
q Grade level = 397.650m
q Ground level = 398.110m
q Depth at centre = - 0.460m (Cut)
Amaquants Associates 60
PART - 4 - EARTHWORKS (Cont’d)
61
Amaquants Associates
PART - 4 - EARTHWORKS (Cont’d)
Repeat the above steps for all CUT Areas
CH0 + 025
Cross-section Area - 18.24m2 Cut
CH0 + 050
Cross-section Area - 14.877m2 Cut
CH0 + 075
Cross-section Area - 11.625m2 Cut
CH0 + 100
Cross-section Area - 3.739m2 Cut
Amaquants Associates 62
PART - 4 - EARTHWORKS (Cont’d)
Amaquants Associates 63
PART - 4 - EARTHWORKS (Cont’d)
Amaquants Associates 64
PART - 4 - EARTHWORKS (Cont’d)
Repeat the above steps for all FILL Areas
CH0 + 150
Cross-section Area - 40.54m2 (Fill)
CH0 + 175
Cross-section Area - 38.818m2 (Fill)
CH0 + 200
Cross-section Area - 30.60m2 (Fill)
CH0 + 225
Cross-section Area - 32.058m2 (Fill)
CH0 + 250
Cross-section Area - 29.143m2 (Fill)
Amaquants Associates 65
PART - 4 - EARTHWORKS (Cont’d)
CH0 + 275
Cross-section Area - 36.507m2 (Fill)
CH0 + 300
Cross-section Area - 42.52m2 (Fill)
CH0 + 325
Cross-section Area - 80.714m2 (Fill)
CH0 + 350
Cross-section Area - 129.309m2 (Fill)
CH0 + 375
Cross-section Area - 150.796m2 (Fill)
CH0 + 400
Cross-section Area - 128.845m2 (Fill)
Amaquants Associates 66
PART - 4 - EARTHWORKS (Cont’d)
CH0 + 425
Cross-section Area - 69.404m2 (Fill)
CH0 + 450
Cross-section Area - 51.509m2 (Fill)
CH0 + 475
Cross-section Area - 37.047m2 (Fill)
CH0 + 500
Cross-section Area - 24.557m2 (Fill)
Amaquants Associates 67
PART - 4 - EARTHWORKS (Cont’d)
ROAD PROFILE FOR COLLECTOR 02
CHAINAGE GROUND GRADE ROAD SLOPE CUT FILL DEPTH X-SECTION
(m) LEVEL (m) LEVEL (m) WIDTH 1:2 (m) AREA OF
(m) CUT/FILL
0 + 000 398.110 397.650 46m 1:2 CUT - - 0.460 21.58m2
0 + 025 395.998 395.608 46m 1:2 CUT - - 0.390 18.24m2
0 + 050 393.886 393.567 46m 1:2 CUT - - 0.319 14.877m2
0 + 075 391.775 391.525 46m 1:2 CUT - - 0.250 11.625m2
0 + 100 389.663 389.582 46m 1:2 CUT - - 0.081 3.739m2
0 + 125 387.551 387.837 46m 1:2 - FILL +0.286 13.32m2
0 + 150 385.438 386.288 46m 1:2 - FILL +0.850 40.54m2
0 + 175 384.123 384.938 46m 1:2 - FILL +0.815 38.82m2
0 + 200 383.137 383.784 46m 1:2 - FILL +0.647 30.60m2
0 + 225 382.152 382.829 46m 1:2 - FILL +0.677 32.06m2
0 + 250 381.456 382.073 46m 1:2 - FILL +0.617 29.14m2
0 + 275 380.751 381.519 46m 1:2 - FILL +0.768 36.51m2
0 + 300 380.278 381.168 46m 1:2 - FILL +0.890 42.52m2
0 + 325 379.381 381.019 46m 1:2 - FILL +1.638 80.71m2
0 + 350 378.541 381.073 46m 1:2 - FILL +2.532 129.31m2
0 + 375 378.419 381.329 46m 1:2 - FILL +2.910 150.80m2
0 + 400 379.263 381.787 46m 1:2 - FILL +2.524 128.84m2
0 + 425 381.027 382.448 46m 1:2 - FILL +1.421 69.40m2
Amaquants Associates 68
PART - 4 - EARTHWORKS (Cont’d)
DEFINITION RULES
i. Excavation of Cuttings - Excavation below Embankments
ii. Excavation of Foundations - Is that accommodates Foundations
iii. General Excavation - (a) Covers excavation to reduce levels or
formation level of a structure
(b) Excavation from within Borrow pit shall be
classed as general excavation.
Amaquants Associates 69
PART - 4 - EARTHWORKS (Cont’d)
EARTHWORKS
CUTTING - EMBARKMENT
Strip topsoil
Filling (Embankement)
Bottom width
CH0 + 125 47.14m
CH0 + 150 49.40m
CH0 + 175 49.26m
CH0 + 200 48.59m
CH0 + 225 48.71m
CH0 + 250 48.47m
CH0 + 275 49.07m
CH0 + 300 49.56m
CH0 + 325 52.55m
CH0 + 350 56.13m
CH0 + 375 57.64m
CH0 + 400 56.10m
CH0 + 425 51.68m
CH0 + 450 50.28m
CH0 + 475 49.12m
CH0 + 500 48.09m
811.79m
Strip topsoil
Excavation of cuttings, topsoil, commencing from
existing ground level; excavated surface 250mm
below original surface 2E211
16/ 25.00
50.74
0.25 5074 (Filling Areas)
25.00
4/ 47.2 1180
0.25 6254m3 (Cutting Areas)
Amaquants Associates 71
PART - 4 - EARTHWORKS (Cont’d)
Cutting
Volume = 1/2 (A1 + A2) X Length
Amaquants Associates 72
PART - 4 - EARTHWORKS (Cont’d)
4/ 25.00 Ddt
47.20
0.25 1180m3 abd (Top soil excavation)
CH0 + 000 - CH0 + 100
2E222
Amaquants Associates 73
PART - 4 - EARTHWORKS (Cont’d)
Excavation Ancillaries
Triming of Excavated Surfaces
CH0 + 000 - CH0 + 100
Calculate the width of side slope
Y Y
X D D X Slope 1:2
Width
CH0 + 000 = X2 = D 2 + Y2
X2 = (0.46)2 + (0.92)2
X2 = 0.21 + 0.846
X2 = 1.056
Length = 4/25.00m
Average slope length = 0.671m X 2 (both sides)
Amaquants Associates 75
PART - 4 - EARTHWORKS (Cont’d)
4/ 25.00 Excavation Ancillaries, Preparation of excavated
32.00 32.00m2 surfaces to receive permanent works, materials
other than top soil, rock or artificial hard material
2E522
Amaquants Associates 76
PART - 4 - EARTHWORKS (Cont’d)
Double Handling to Topsoil (Verge + Median)
L = 500m
Width
Verge = 12m
Median = 2m
14m
Thickness = 150mm
Amaquants Associates 77
PART - 4 - EARTHWORKS (Cont’d)
FILLING EMBANKMENTS
Volume = 1/2(A1 + A2) X Length
Earthworks, Filling, Embankment, selected excavated
material other than rock or topsoil
6.66 m2 2E624
25.00 165m3 CH0 + 100 - 0.125
26.94 m2
CH0 + 125 - 0.150
25.00 673.5m3
39.69 m2
25.00 992.25m3 CH0 + 150 - 0.175
34.71 m2
25.00 867.75m3 CH0 + 175 - 0.200
31.33 m2
25.00 783.25m3 CH0 + 200 - 0.225
30.60 m2
25.00 765m3 CH0 + 225 - 0.250
32.83 m2
25.00 820.75m3
CH0 + 250 - 0.275
Amaquants Associates 78
PART - 4 - EARTHWORKS (Cont’d)
39.52 m2
25.00 988m3 CH0 + 275 - 0.300
61.62 m2
25.00 1540m3 CH0 + 300 - 0.325
105.01 m2
25.00 2627.50m3 CH0 + 325 - 0.350
140.05 m2
25.00 3501.25m3 CH0 + 350 - 0.375
139.83 m2
25.00 3495.75m3 CH0 + 375 - 0.400
99.13 m2
25.00 2478.25m3 CH0 + 400 - 0.425
60.46 m2
25.00 1511.50m3 CH0 + 425 - 0.450
44.28 m2
25.00 1107m3 CH0 + 450 - 0.475
30.81 m2
25.00 770.25 CH0 + 475 - 0.500
23,087.5
Amaquants Associates Assume: 65% of excavated material are suitable to be re-used for filling embankment 79
PART - 4 - EARTHWORKS (Cont’d)
Add Replacement of Topsoil excavated
16/ 25.00
50.74 Filling to embankment, selected excavated material other than rock
0.25 or topsoil
5074m3 (Topsoil replacement)
2E624
Imported Filling
By Adjustment
Gross cutting = (1435.50 - 1180m3) = 255.5m3
Usable Excavated Soil = 255.5 X 65% = 166.07m3
Less: Gross
filling required = (23,087.50 + 5074m3) = 28,161.50m3
Imported materials = 27,995.42m3
500.00
2.00 1000.00 (median)
7000.00m2 2E645
500.00
2.00 (median)
0.15 150m3 2E621
1050m3
125.00 Filling to stated depth, 50mm thick sand layer over geotextile
53.94 CH0 + 300 - CH0 + 425
6742.50m2 2E645
Amaquants Associates 81
PART - 4 - EARTHWORKS (Cont’d)
Filling Ancillaries
Trimming of filled surfaces
Slope 1:2
X X
FILL
Amaquants Associates 82
PART - 4 - EARTHWORKS (Cont’d)
Repeat the process for the filled slope
Surfaces
CH0 + 150 - 1.90m
CH0 + 175 - 1.82m
CH0 + 200 - 1.45m
CH0 + 225 - 1.51m
CH0 + 250 - 1.38m
CH0 + 275 - 1.72m
CH0 + 300 - 1.99m
CH0 + 325 - 3.66m
CH0 + 350 - 5.66m
CH0 + 375 - 6.51m
CH0 + 400 - 5.64m
CH0 + 425 - 3.18m
CH0 + 450 - 2.39m
CH0 + 475 - 1.74m
CH0 + 500 - 1.17m
42.36m
16
Average slope length of one side = 2.65m
Amaquants Associates 83
PART - 4 - EARTHWORKS (Cont’d)
2/16 25.00 Filling ancillaries Trimming of filled surfaces to receive
2.65 2120m2 permanent works, material other than, topsoil, rock or artificial
hard material, inclined at an angle of 10 - 45 degrees to the
horizontal (side slopes) 2E712
Amaquants Associates 84
PART - 4 - EARTHWORKS (Cont’d)
Unsuitable soil (swampy Areas)
CH0 + 300 - CH0 + 425
Length = 125m
Average width = 53.94m
Amaquants Associates 85
PART - 4 - EARTHWORKS (Cont’d)
Landscaping
500.00 Landscaping, turfing, to surfaces at an angle not exceeding 10 degrees
12.00 6000.00 to the horizontal
m2 2E810
(verge)
500.00
2.00 1000m2 (median)
7000.00
m2
Slope Protection
Embankment (filled slopes)
Stone - Pitching
Stone pitching, 150mm thick, on embankment filled slopes, as specified
2/16 25.00 X900
2.65 2120m2
86
Amaquants Associates
PART - 5 ROADS AND PAVINGS
Roads and Pavings
Collector 02 Road
Carriageway
Length of the road = 500m
Width = 20m
Bellmouth - A = 3/14 R2
R Collector 2 Road
R = 20m
Arterial 01 Road
Junction
Unbound Sub base and Road Base
Road and paving unbound
500.00 Sub-base Type 1 unbound
20.00 10,000m2 Mixtures (Natural occurring laterite), Depth
100 - 150mm (Carriageway)
2T114
2/ 3/14 / 20.00 171.42m2 (Bellmouth)
20.00 10,171m2 &
Road and paving, Unbound Road base, Type 2 unbound
mixtures (crushed rock base), Depth 100 - 150mm
2T124
87
Amaquants Associates
PART - 5 ROADS AND PAVINGS (Cont’d)
&
Amaquants Associates 88
PART - 5 ROADS AND PAVINGS (Cont’d)
CYCLE PATH & WALKWAYS
Length = 500m
Width
* Cycle path = 6m
*Walkways = 6m
Bellmouth - A = 3/14 R2
2m Quadrant
Amaquants Associates 91
PART - 5 ROADS AND PAVINGS (Cont’d)
Surface Marking:
Thermo Plastic marking as specified
1 1Nr Surface markings, Non-reflective road studs, Type Nr
2T821
16/ 350 5600m Surface markings, continuous lines white/yellow lines, 100mm
wide, Type -
2T824.1
4/ 500 2000m
Ditto white continuous line 300mm Type
2T824.2
Amaquants Associates 92
PART - 5 ROADS AND PAVINGS (Cont’d)
2/ 25.00 Ditto, white parking lines, 100mm wide,
50m Type 2T824.3
16/ 100.00 Surface markings, white intermittent lines, 100mm wide, Type
1600m 2T825.1
PAINTING KERB
TYPE A
L = 1003m
Width = 0.55m
TYPE B
L = 1040m
Width = 0.30m
93
Amaquants Associates
PART - 5 ROADS AND PAVINGS (Cont’d)
TYPE C
L = 1091m
Width = 0.2m
PAINTING
Kerbs
1003.00 Painting Kerbs, non-reflectorised, including
0.55 551.65 preparing the surface, painting of kerb with
specified colour material (Type A)
1040.00
0.30 312 (Type B)
4091.00
0.20 818.2 (Type C)
1682m2
2T829.1
Amaquants Associates 94
PART - 6 BRIDGE WORKS
GENERAL NOTES
2-Span Bridge
The Bridge Structure
ü The total length of the bridge is 40metres (2-span)
ü The carriage way is 8.0 metres flanked by 950 metres
walkway with a precast parapet wall on both sides.
ü The superstructure consists of Ten (10) 20m span precast
concrete rectangular beams of 1300mm deep and 450mm
width. The Beams are spaced 2000mm apart and topped by a
precast slab of 50mm deep as permanent formwork and
composite with an in-situ slab of 230mm thick.
Amaquants Associates 95
PART - 6 BRIDGE WORKS (Cont’d)
Amaquants Associates 96
PART - 6 BRIDGE WORKS (Cont’d)
MATERIALS
ü Precast beam to grade 40 (40N/mm2)
ü In-situ slab to grade 30 (30N/mm2)
ü Substructure to grade 30 (30N/mm2)
ü Steel to grade 410 (410N/mm2)
ü Cover to all steel =30mm
Amaquants Associates 97
PART - 6 BRIDGE WORKS (Cont’d)
PROPOSED 2 - SPAN BRIDGE FOR MABUSHI INTERCHANGE
2 - Span Bridge
*Length = 40,000mm
*Width =
Walkway 2/950 = 1900mm
Carriage way = 8,000mm
Width = 9.900m
Demolition &
Site Clearance - 2D
Assumed
L = 100,000mm
W = 40,000mm
Earthworks - 2E
Cutting
470.277
- 468.990
Depth 1.287m
99
Amaquants Associates
PART - 6 BRIDGE WORKS (Cont’d)
Length of Bridge = 40,000mm
Add Return wall
2/4000 = 8,000mm
48,000mm
L = 48,000mm
W = 9,900mm
D = 1.287mm
Type A
* 13450mmX4500X1000mm
Type B
* 8800mmX4500X1000mm
Excavation Ancillaries
2/ 13.45 Excavation ancillaries, preparation of excavated surfaces,
4.50 121.05 material other than topsoil, rock or artificial hard material.
1/ 8.80
4.50 2E.5.2.2
39.60
160.65m2
1/ 8.80
4.50
1.00 39.60
160.65m3
Avg. = 3,500mm
Landscaping
2/2/1/2/ 5.00 Earthworks, Landscaping Turfing
7.00 70.00m2
2E.8.1.0
Bridge Foundation
Piling - 2R
Bored Pile
*No of piles = 30
*Size of pile = 1200mm Diameter
*Depth(Bored) =20m
Piling Ancillaries - 2 S
30/ 19.00 Pile ancillaries, cast-in-place piles, pre-boring, Diameter 1200mm
570.00m 2S.1.1.6
Pile Cap
Type A (2 Nos)
13.45mX4.5mX1.0m
Type B - (1Nr)
8.8mX4.5mX1.0m
In-situ Concrete
1/ 8.80
4.50
0.10 3.96
16.08m3
1/ 8.80
4.50
0.10 3.96
16.08m3
Concrete Ancillaries
Bridge Substructure
Pier, Abutment and Return-walls
Piers
Diam = 1200mm
Ht = 6200mm
No = 2
Abutment (2 Nos)
L = 10450mm
W = 1000mm
Ht = 5300mm
Return Walls(4Nos)
Thickness 500mm
800mm
2/ 1300mm
650mm
Ht = 7000mm
L = 2000mm
W = 650mm
Ht = 2300mm
L = 2400mm
W = 650mm
2/ 10.45
1.00 (Abutment)
5.30 110.77
2/ 10.45
0.75 (Abutment)
2.46 38.56
4/ 2.00
0.65 (Return wall)
7.00 36.40
4/ 2.40
0.65
2.30 14.35 (Return wall)
235.32m3
Amaquants Associates 112
PART - 6 BRIDGE WORKS (Cont’d)
Placing of Concrete, reinforced, walls, thickness exceeding
200.08 500mm
m3 2F.7.4.4
45.24 Ditto, Reinforced columns and piers, cross sectional area 0.25-
m3 1m2
2F.7.4.4
Concrete Ancillaries
2/22/7/ 1.20 Concrete ancillaries, fair finish, curved to one radius in one place,
6.20 width 0.4-1.22m.
46.77m2 2G2.5.4 (Piers)
2/2/ 10.45
2.46 102.83
324.37m2
Amaquants Associates 113
PART - 6 BRIDGE WORKS (Cont’d)
2/4/ 2.00 Ditto, fair finish, plane vertical 0.4-1.22m (Return wall)
7.00 2G.2.4.4
112.00
2/4/ 2.40
2.30
44.16
156.16m2
Concrete Ancillaries
Formwork: Fair finish, plane horizontal width 0.4-1.22m
m2 (Edges of abutment + Return walls)
2G.2.1.4
Reinforcement
Concrete Ancillaries, Reinforcement, deformed yield steel bars,
Nominal size 12/16mm (Piers)
Inserts
2/ 15 Concrete accessories, inserts, other inserts 75mm UPVC pipe
30Nr (weep-holes) 1100mm long
2G.8.8.2
Precast
Size = 9900X1200X1200mm
Size 19950X450X1300mm
L= 40,000mm
20,000mm
20 Nos
In-situ Concrete
40.00 Provision of Concrete, Designed concrete, strength C25/30,
9.90 maximum aggregate size 20mm (Bridge deck)
0.18 2F.1.5.2
71.28 (Approach slab)
2/ 9.45
5.00
0.20
18.90
90.18m3
Amaquants Associates 118
PART - 6 BRIDGE WORKS (Cont’d)
2/ 8.00 Provision of Concrete. Prescribed mix 1:4:8, 100mm thick blinding to
5.00 Approach slab
0.10 8m3 2F 4.0.0
2/ 9.45
5.00
0.20 18.90
90.18m3
Concrete Ancillaries
2/ 18.00 Concrete ancillaries, formwork: Fair finish, plane vertical, width 0.2-
36.00m 0.4m
(Edges of Approach slab)
2G.2.4.3
Joints
3/ 9.90 Joints, open surface plain , average width not exceeding 0.5m
29.70m ( 50mm thick Thermal joint as the flexible joint at expansion gag)
2G.6.1.1
120
Amaquants Associates
PART - 6 BRIDGE WORKS (Cont’d)
Precast Slab
Formwork 8cm thick
No of Plinths = 20Nrs
*Size of plinth =
*400X350mmX125mm (avg)
Placing of Concrete
20/ 0.40 Placing of Concrete, reinforced, bases, footings, pile caps, thickness
0.35 not exceeding 150mm
0.13 0.36m3 2F.7.2.1
Concrete Ancillaries
Formwork: Fair finish, for concrete components of constant cross
20/ 1.50 section, 400X350mmX125mm thick, plinth
30m 2G2.8.4
Concrete Ancillaries
Reinforcement, deformed high steel bars, nominal size 12mm
0.36 m3
_____ X 40 kg/m3 = 0.01 t
2S.5.2.4
Amaquants Associates 122
PART - 6 BRIDGE WORKS (Cont’d)
Bridge Bearings
Nr = 20Nos
Approach Slab
L = 8,000mm
W = 5,000mm
2/ 8.00
5.00 80.00
400.00m2
Guard stones
2/2 5.00 Miscellaneous works; fences, road restraint system; - precast crash
20m barriers Height 1.0-1.25m
2Z.1.8.2
Bridge Railing
2/ 50.00 Miscellaneous metalwork, Miscellaneous framing, Tabular section -
100.00m one tube steel hand rail
2P.1.6.4
Amaquants Associates
125
PART - 6 BRIDGE WORKS (Cont’d)
Bridge Drainage
2/ 60.00 120.00m Miscellaneous work, drainage to structures above ground 150mm
diameter cast iron down pipes
2Z3.2.2.2
Inlet Grating
2/ 5 Cast iron inlets grating fixed in Bridge deck.
10Nr
Collector 02 Road
* Length RHs = 492.15m - 10/1.50m (MH Internal dimension)
RHs = 491.83 - 10/1.50m (MH Int. dimension)
* Gulley = 60 Nos
* Pipe = 600mm Diameter CP
* Storm manholes = 20Nrs
60/ 1.50 90m Pipes, PVC pipes, nominal bore 200mm in trenches not
exceeding 1.5m 2J522
Gullies
Precast concrete trapped, as drawings no......., cover
and frame to BS 497 grade A, ref GA1450
60/ 1 60nr Gullies, precast concrete trapped
2L360
60/ 1.50 90.00 Surrounds, mass concrete, nominal bore 300 - 600mm
1044m 2M543
X900.5
Amaquants Associates 132
PART - 8 FOUL WATER SEWERAGE NETWORK
FOUL WATER SEWERAGE NETWORK
MAR 12 ROAD
2J512
Amaquants Associates 135
PART - 8 FOUL WATER SEWERAGE NETWORK
Pipework - Fittings and Valves
19nr 19nr Fittings and valves, PVC fittings, Junction and branches,
Norminal bore not exceeding 200mm
2K421
Excavation in rock
Assumed
FM12.4 - FM9.5
L = 54.00
Depth = 230mm
2K421.3
20 20nr PVC pipe fittings, Bends, 32mm diameter Nominal bore not
exceeding 200mm
2K411
Fire Hydrant
2/ 1 2nr Provide and Install Fire Hydrants complete with stand pipe and
fittings ND 80mm
X900
20/ 1 20nr Manhole, Precast concrete, size 1.0 X 1.0m, depth not
exceeding 1.5m (House connection meter)
2L151.1
2L151.2
2M531
200.00 200m Beds, 150mm thick, mass concrete, Nominal bore, not
exceeding 200mm
(Road crossing)
2M341
200.00 200m Surrounds, 150mm thick, mass concrete, Nominal bore, not
exceeding 200mm
(Road crossing)
2M541
Note
*Anchor block is applied to reducers and valves
2M780
X900.2
X900.3
Plot Manhole
Provide and tap for House connection
20 20nr Ferule saddle ND 100 X 32mm
X900.4
X900.5
X900.7
X900.8
X900.9
13/ 1 13Nr Supply and install cable connection box mounted to the
poles according to specifications and relevant drawings,
box with 1MCB L 16A for 2 cables 4 X 16mm2
X900.5
Lantern
Supply and install 1 X 400Watt high pressure sodium
13/ 2 26Nr Lanterns
X900.6
LOW VOLTAGE
Feeder pillar & Lighting Control Cabinet
X900.7
X900.8
X900.9
13/ 14.50 189m 3C X 2.5mm2 copper, PVC flexible rubber lantern cable
X900.13
Collector 02 Road
* 8 way PVC manhole = 4
* Type 1 Telecommunication Duct
= 8 Nos of 100mm ɸ
PVC pipe
* Road crossing = 25m
* Length = 500m
Road Crossing
Beds and Surrounds mass concrete, including warning
tape
Surrounds to Type 1 duct, 8 - way duct, nominal bore not
25.00 25.00m exceeding 200mm
2M541
Amaquants Associates 158
PART - 10 NEW WORK SECTION
Pipework - Manholes and Pipework Ancillaries
Manholes
2L153
2L233
L = 55.43m
Add:
Headwalls = 2/0.20
Apron = 2/1.80
59.43m
W = Width of Apron
= 6.75m
Depth
Road level = 381.165
Invert level = 378.343
2.822m
Less
Road structure thickness 0.400
Depth 2.422m
Amaquants Associates 161
PART - 12 CULVERTS (Cont’d)
Earthworks
59.43 Excavation for foundation, material other than topsoil rock or
6.75 artificial hard material, depth 2 - 5m
2.42 2E325
970.8m2
2E522
2/ 57.43 Ddt
2.10 241.20m abd
2E522
(Recesses)
2E533
Amaquants Associates 163
PART - 12 CULVERTS (Cont’d)
Excavation below the Final surface
Apron
1/ (a + b) X H
2
1/ (2.70 + 6.75) X H
2
1/ (9.45m) X 1.8m
2
FILLING
2/ 57.43 Filling to structure imported natural material other than
2.10 rock or top soil
2.42 583.72m3 (Recesses)
2E615
Amaquants Associates 164
PART - 12 CULVERTS (Cont’d)
Filling Ancillaries
2/ 57.43 Preparation of filled surfaces to receive permanent work, material
2.10 other than topsoil, rock or arterial hard material
241.2m2 (Recesses)
2E722
218.57m3 2F142
2/1/2 9.45
1.80 (Apron)
0.20 3.40
4/ 1.03
1.80 (Wingwall)
0.15 1.11
2/ 2.70
0.40 0.43 (Headwalls)
Amaquants Associates 166
0.20 6.90m3 2F142
PART - 12 CULVERTS (Cont’d)
Placing of Concrete
55.83 Mass, blinding, thickness not
2.70 exceeding 150mm
0.05 7.54 2F611
2/1/2 9.45
1.80
0.05 0.85
8.39m3
2/ 12.27 Reinforced, Bases, footings and
0.20 ground slabs, thickness 150 -
0.40 300mm
2/ /2 9.45
1 (Toe Beam and
1.80 apron)
0.20 3.40 2F722
5.36m3
4/
1.03 Reinforced, walls, thickness 150 -
1.80 300mm (wingwall &
0.15 1.11 Headwall)
2/
2.70 2F742
0.40 0.43
0.20 1.54m3
Mass, Bases, footings and ground
55.83 slabs, thickness exceeding 500mm
2.70 (concrete
1.45 218.57m3 surround)
2F624 167
Amaquants Associates
PART - 12 CULVERTS (Cont’d)
Ddt
2/22/7/ 0.53 abd
0.53
55.83 (2no - 900ɸ pipe)
98.55m3
Concrete Ancillaries
Formwork
2/2 12.27 Formwork, rough finish, plane vertical, width 0.2 - 0.4m
0.40 19.63m2 (Toe beam)
2G143
2/ 12.27 24.54m Formwork, fair finish, plane vertical, width 0.1 - 0.2m
(Apron edges)
2G242
2/ 55.83 Ditto, width exceeding 1.22m
1.45 161.90
(Concrete surround)
2/ 2.70 2G245
1.45 7.83 168
Amaquants Associates
169.73m2
PART - 12 CULVERTS (Cont’d)
4/2/ 1.03 Ditto plane slopping, width exceeding 1.22mm
1.80 14.83
2G225
4/1/ 0.80 (wingwalls)
0.15 0.48
15.31m2
(Toe, Apron,
wingwalls and
Headwalls)
Miscellaneous work
Fences
2/ 2.70 Aluminium parapets with metal posts, Height not exceeding 1m
5.40m (Headwalls)
2Z191