MS-CV-001 - Excavation and Backfilling
MS-CV-001 - Excavation and Backfilling
Method Statement
Excavation and Backfilling
1.0 Scope
This method of statement defines the procedures followed for excavation and backfilling in
order to achieve the project objective with safe work practices.
2.0 Purpose
The main purpose of this document is to ensure that the personnel carrying out the activities for
the above mentioned scope,
Carry out the work in a controlled and structured manner
Understand the risk and hazards associated with each activities in the sequence of work
Use the controls specified to reduce the risk of injury, ill health or damage
Carry out the work safely.
3.0 References
The Primary reference documents that should be used in conjunction with this document are,
I. Particular Specifications
II. Project Drawings
III. Project Contract Documents
IV. Materials / Submittals with respect to the scope that shall be available during the
project duration
V. Ministry of Communications – General Specifications for Road and Bridges Construction
VI. Ministry for Water and Electricity – Technical Specifications for Sewer Networks
4.0 Definitions
4.1 Risk: a situation involving exposure to danger.
4.2 Hazard: a potential source of danger
4.3 A1A, A1B, A24: AASHTO Soil Classification System Granular Materials (35% or less
passing the 0.075 mm sieve)
4.4
Creet International Contracting Company
Project: Shams Arriyadh Development
Method Statement for Installation of Sanitary Drainage Network
Ref: MS-ME-001
Page: 2 of 7
5.0 Hazards
5.3.2 Planned provision of and use of excavation support equipment, trench support
is to extend to 250mm from the bottom of the dig.
5.3.3 If ground conditions are that of solid state works may progress but any changes
e.g. Water ingress, loose ground the works must stop and be re assessed.
5.3.4 Excavations to be always backfilled as soon as practicable, if not warning
signage, inspections & adequate fencing used.
5.3.5 Soil and pipes, not to be placed at the edge of the excavation so as to surcharge
it.
5.3.6 Proper tied ladder access extending 1.05m above top of excavation, and placed
into the supported area of the excavation.
5.3.7 Only certified operators & lifting equipment to be used…..SWL is not to be
exceeded for the Excavator being used.
5.3.8 Excavator is banked during excavation work, and stops used on dumpers to
prevent vehicles over running the excavation.
below the ground. Services, wherever found shall be rerouted and protected to
place will not affect site activities.
Setting out – Creet Surveyor would conduct the site survey to mark/stake-out
the lines and levels of the objective excavation for foundations as per indicated
in the approved drawing.
6.6 Testing:
Creet International Contracting Company
Project: Shams Arriyadh Development
Method Statement for Installation of Sanitary Drainage Network
Ref: MS-ME-001
Page: 5 of 7