YSD P02 0208 HS WSP RP 00058 HSE Management Site Walk Report No. 004
YAS SOUTH-IDR
HSE MANAGEMENT SITE WALK REPORT
23 OCTOBER 2017
YAS SOUTH-IDR
HSE MANAGEMENT SITE
WALK REPORT
MIRAL
WSP
P.O. BOX 7497
DUBAI
UNITED ARAB EMIRATES
Management
Remarks
Site Walk 04
Signature
Checked by Shakil
Panniyottil
Signature
Signature
Document HSEQ-F04
Reference
Report number 4
The following items, in the inspection findings, were discussed in order to address and
identify the areas of concern and agree on improvements required to maintain the HSE
requirements for the site.
Overall, the report identifies an improvement of H&S standards on site, the contractor
needs to monitor and maintain the good practices and improve more by adopting
proactive approach and undertake a thorough review of current practices and deal with
the daily issues in a more robust and structured manner through the commitment and
engagement of Hilalco site supervision team.
The contractor safety team and supervision team must work together to maintain the
management processes to raise the standards on the project.