Professional Documents
Culture Documents
Document Revision: Initial Date: 27th June 2019 Shore ID: 5860
The items noted below are to provide the Principal Contractor, Designers, End User or others with specific information on risks or other such hazards identified
during the Pre-Construction and Design stages of the project. Generic and standard risks or hazards, which should be obvious and manageable to a competent
contractor conversant with the type of work, have been omitted to avoid obscuring those of higher risk.
Ownership
Element of Design / Method(s) of Mitigation being Additional
ID Potential Risk Persons Affected of Residual
Work Considered Information
Risk
01 Demolition / alterations of Uncontrolled collapse Methodical approach to deconstruction of Contractors, Operators, Visitors Principal
existing building / structure. internal walls & partitions. Temporary works Contractor/
for any load-bearing works to be designed Structural
and installed by competent persons Engineer
02 Movement of Construction The pedestrian will be Ensuring the movement of materials is carried Operators, Passer-by’s Principal
materials through exposed to this activity, out before peak use of these areas. The Contractor
pedestrianised routes will have an increased deployment of a competent banksman to aid
risk of collision, the operator whilst moving these materials
entrapment other would be expected as good practice.
related injuries
03 Dust and Noise Though carrying out To reduce the likelihood of excessive dust Existing Tenants, Operators, Principal
construction related damping down or water suppression on the Visitors. Contractor
activities there is the surfaces before and during the activity. Noise,
reducing the length of noisy works, it would
04 Potential to identify Asbestos Uncontrolled fibre R&D Asbestos survey to be undertaken. Contractors, Operators, Visitors Client, Principal
release / Contamination Operatives to be awareness trained. Contractor
05 Existing services Striking hidden or Obtain plans of services if available. Contractors, Operators, Visitors Principal
unidentified services Contractor
within roof structure Engage a competent contractor to trace &
identify services, isolating or relocating as
required.
06 Unauthorised Access to the Non-contractual staff Ensure security measures are in place to Contractors, Operators, Visitors Principal
site working area entering the site area prevent access on to site. Plenty of signage Contractor
and being exposed to indicating that it’s a live site and the hazards
site hazards that are present.
07 Traffic Management, Vehicle Harm to adjacent Traffic Management Plan to be provided as Contractors, Operators, Visitors Principal
Movement in a small building occupants, or part of the CPP to cover how access will be Contractor
operating area the general public. Crush given to the property and via the shared side
and Entanglement access
injuries are heightened.
08 Manual Handling Musculoskeletal Injuries Specific manual handling assessment will be Client, Contractors, Operators, Principal
and/or Back Injuries carried out for any tasks that are deemed a Visitors Contractor
manual handling hazard e.g. glass installation
or heavy plant
10 Cleaning (Internal) Struck by Moving, Flying, Risk of falls and falling material. Ceiling Contractors, Operators, Visitors Access and Principal
Falling Objects heights vary. Height and location of lights, maintenance strategy Contractor
suspended ceilings, signs and associated statement to be
premises materials as indicated on reflected included in the H&S
ceiling plan drawings are planned and File. Include plant item
designed appropriately. weights in H&S File
All cleaning should be completed from ground
level unless instructed and planned for by the
client.
If mobile platforms and temporary access
equipment is required, this needs to be
assessed and planned independently.
12 Hazardous Materials Contact could cause Gas bottles and any fuels will be stored off site Contractors, Operators, Visitors Principal
harm to any site and in appropriate storage containers. Contractor
personnel, visitors to site Minimum amounts of gas and fuel to be
and members of public stored and used.
and or create fire or Storage locations are included within fire
explosion risk assessment and/or fire plan in the event
of fire out of hours;
14 Maintenance of plant and Faulty equipment could Correct tools and equipment will be provided Client, Contractors, Operators, Principal
equipment lead to falls, fires, for use and operatives will be trained / Visitors Contractor
electric shock to any site competent to operate;
personnel, visitors to All trade contractors equipment inc. band
site, members of public saws, woodworking power tools,
screw/threading machines and electrical
tools and leads must be PA tested and tagged,
maintained every 3 months and in accordance
with manufacturers guidance and inspected
regularly;
This register is not to be considered exhaustive, and any such items which members of the team identify at any stage of the project should be added to the
register and incorporated into a Residual Risk Register for inclusion in the Health & Safety File upon completion of the project.