You are on page 1of 150

Introduction

Chapter 1
Introduction

B
uilding commissioning Building commissioning has
has often been likened to its roots in the Quality Control
commissioning of a ship, programs of the 1970s and is
where the Owners thor a direct product of the Total
oughly verify and prove the func Quality Management pro 1
tional performance of all parts – grams of the 1980s. Commis
engines, compasses, sonar, radar, sioning is a direct response to
radio, generators, potable water building Owners who com
systems, and so on – under all pos plain that their facilities do not
sible conditions and as a condition meet performance expecta
of acceptance before placing the tions, are extraordinarily ex
ship in service. And where the pensive to operate and
Owner checks the presence of sys maintain, lack valuable docu
tem operating and procedures mentation, and are staffed by
manuals and the availability of up- personnel who are unfamiliar
to-date navigation charts. And with and have never been
where the crew has been properly trained on the building’s highly
“Building commissioning has
and thoroughly trained on the ship’s complex operations and control sys
systems’ operations and emergency tems. often been likened to the
procedures. Commissioning is not commissioning of a ship.”
new – ships and aircraft have been Until now, many of us thought of
commissioned for years. building construction completion and
turnover as physically completing an
installation, throwing
the switch, making a
few adjustments,
Goals of Commissioning: spending minimal time
with the operators by
◆ Provide a safe and healthy facility.
pointing to the equip
◆ Improve energy performance and minimize ment with one hand
energy consumption. and a manufacturer-
◆ Reduce operating costs. supplied operations
◆ Ensure adequate O&M staff orientation and manual (that may or
training. may not match the
specific equipment)
◆ Improve systems documentation.
with the other, then
Introduction

walking away. We would return only ent sources and programs. So once
when the operating personnel or the construction was completed and
owner complained. beneficially accepted, the building
was handed off as rapidly as pos
A successful project was not neces sible, leaving building maintainers to
sarily the one with the most satisfied struggle with any residual construc
client, optimal indoor environment, tion or operational problems. In all
most reliable and efficient operation, fairness to the constructors, by this
or that would have had the lowest time the Owner was usually press
possible operating and maintenance ing to move into the building, either
costs. Typically, it was the one with oblivious to or willing to accept the
the fewest extras and change orders risks associated with a potentially
and the one with the shortest punch problematic facility.
list.
2 Most existing buildings have never
Further, the construction budget and undergone a formal commissioning
operating budget came from differ- or quality assurance process. Many
buildings are limping along ineffi
ciently in terms of performance.
Owners are unaware of deficiencies
Guidebook Objectives as long as the building is reasonably
comfortable and occupant com
◆ Provide an introduction to commissioning approaches to a
plaints do not reach a crescendo.
variety of professionals involved with the management, op-
eration, and maintenance of Federal buildings.
In reality, the building systems may
be becoming increasingly unreliable
◆ Illustrate case histories, including cautionary lessons learned. and inefficient through design, inef
fective maintenance and operations
procedures, outdated technologies,
◆ Provide guidance on commissioning best practices.
insufficient training, occupant habits,
mission changes, environmental
◆ Demonstrate how commissioning can help Federal facility changes, workplace configurations,
managers meet energy efficiency goals and LEED certifica- and more.
tion requirements.
All of that has now changed with
commissioning. As described by the
◆ Demonstrate how commissioning can be integrated in facil- Canadian Department of Public
ity management and O&M programs to make those programs Works, buildings now “leave port”
more efficient and effective. only when they are fully operational,
function as the owner intended, are
◆ Demonstrate how different types of commissioning (such as fine-tuned for maximum perfor
retrocommissioning and continuous commissioning) can be mance, staffed with “crews” who
incorporated into a variety of building types and applications, are fully trained in the regular and
above and beyond the most commonly understood commis- emergency operation of the facility,
sioning approaches. and furnished with a complete set of
relevant operations, maintenance,
Introduction

facility intent and design, and emer in terms of the systems to be com
gency procedures documentation. missioned (e.g., HVAC and electri
cal systems only). It is essentially a
SO… WHAT IS IT? subset, or a slice of the whole build
ing commissioning pie, and for the
Commissioning is a method of risk purposes of this document, the
reduction. terms will be used interchangeably.

The National Conference on Build WHAT ARE THE GOALS?


ing Commissioning has established
an official definition of total building The goals of commissioning are to:
commissioning as follows:
■ Provide a safe and healthy
“Systematic process of assuring facility.
by verification and documenta ■ Improve energy performance 3
tion, from the design phase to a and minimize energy consump
minimum of one year after tion.
construction, that all facilities ■ Reduce operating costs.
perform interactively in accor ■ Ensure adequate O&M staff
dance with the design documen orientation and training.
tation and intent, and in accor ■ Improve systems documenta
dance with the owner’s opera tion.
tional needs, including prepara
tion of operational personnel.” It’s purpose, however, is to provide
a framework for a quality-oriented
Total or whole building commis team effort that reduces project
sioning differs from “building com costs while delivering system reli
missioning” inasmuch as the former ability and quality. Thereby, it en
refers to the whole process from hances long-term value to the
the project planning to post-accep Owner.
tance, as well as to all of the build
ing systems that are integrated and
impact on one another, such as WHY DO WE DO IT?
HVAC, lighting, electrical, plumbing, Following the David Letterman
building envelope and their respec model, the following are the top ten
tive controls and technologies. reasons why people commission:
Building commissioning that is not 10. For the documentation
qualified as total or whole building
commissioning may be more selec 9. To ensure integration of building
tive in terms of the phases during systems
which the commissioning activities
actually take place (e.g., the Com 8. To prevent premature failure
missioning Agent may be hired to
commence work late in the design 7. For the transfer of knowledge
or during the construction phase) or
Introduction

to building operators and owner intended and as designed;


engineers and
■ Be what the Owner paid for.
6. For the performance testing of
complex systems These objectives are achieved by
verifying that the equipment perfor
5. To ensure equipment accessibil mance meets or exceeds the
ity designer’s intent as documented in
the project drawings, specifications,
4. To improve energy performance and design intent documentation.

3. For improved system and From the aspect of energy savings,


equipment reliability commissioning has proven itself time
and again. In existing buildings,
4 2. For project cost control whole-building energy savings aver
age about 15 percent at a cost of
1. To meet Owner expectations about $0.27 per square foot and with
a payback of about 8.5 months. In
Owners use commissioning’s sys new construction, commissioning
tematic, documented, and collabora costs about $1.00 per square foot
tive process to ensure that a building and pays back within about 4.8
and its components’ systems will: years.

■ Have high quality, reliability, In addition, consider the cost savings


functionality, and maintainability; associated with worker productivity,
■ Meet energy and operational detection of failed parts and impend
efficiency goals; ing failure, and other benefits not in
■ Operate and function as the cluded in these savings. These

A major university commissioned six major buildings totaling


260,000 square feet. More than 500 “completed” variable air
volume (VAV) boxes were tested with the following results:
◆ Nine were installed without the main supply air connected
◆ 52 had control programming problems
◆ 23 had control valve problems (including above-ceiling ac-
tuators not connected)
◆ 25 could not achieve the maximum air flow recorded by
the balancer (e.g., frozen dampers)
◆ Eight thermostats were in poor locations, such as near
diffusers and heat generating sources
(Source: S. Angle, Engineered Systems, January 2000.)
Introduction

numbers will be addressed again and workmanship quality, technical


later in greater detail. specifications adherence, and code
compliance. Quality control ensures
Examples of common problems that the installation will pass specified
commissioning addresses that drive tests (such as start-up, operating,
energy costs up but may or may not hydraulic, and leakage tests), and
cause discomfort or other visible ultimately, pass the final punch list.
problems include:
Commissioning is usually associated
■ Outside air dampers stuck in with dynamic and integrated me
the always open or always chanical, electrical, security, life- Commissioning objectives are
closed position. safety, conveyance, and other met by verifying that the
■ Adjustable speed drives that no systems and their controls. Today’s equipment performance meets
longer adjust properly. use of commissioning recognizes the or exceeds the designer’s in
■ Unconnected flexible ductwork. integrated nature of all building sys tent as documented in the 5
■ Malfunctioning control systems tems’ performance. Top concerns project drawings, specifica
components that do not properly are security, indoor air quality, and tions, and design intent docu
integrated life-safety. It also takes a mentation.
respond to their prescribed
control sequences. proactive approach toward the op
■ Incorrect sequences of opera eration and maintenance of the in
tion. stalled system.
■ Energy management systems
that have not been updated to In addition to ensuring that a system
reflect system modifications. is delivering the required flow and
■ Changed facility uses that pressure, commissioning tests the
affect personnel loading and entire integrated system from con
partition configuration changes trols to delivery; tests the interoper-
that affect air flow.
■ Controls sensors that are out of
calibration.
■ Controls that are permanently
overridden.
■ Heating and cooling systems
that fight each other.
■ Thermostats and other control
devices that are improperly
placed.

HOW DO WE DO IT?
Quality control has historically been
associated with static and individual
systems, such as piping, ductwork,
building aesthetics, air handlers, and
other standard punch list items. The
project inspector ensures material
Introduction

ability between systems; tests the and is heavily involved in the plan
condition and operation of key com ning, design, construction, and ac
ponents; ensures the completeness ceptance stages in between.
and quality of O&M manuals and
skills training; is mindful of maintain In existing buildings that have never
ability, accessibility, supportability, been commissioned before,
and reliability issues; and documents retrocommissioning can take place
the entire process. Typically, these at anytime, unless the facility and/or
are not high priority issues in a stan major equipment are programmed
dard quality control program. How for replacement in the immediate fu
ever, by design, commissioning ture. In that case, it is usually advan
includes these so that there is a high tageous to wait and commission the
degree of confidence that the facility as part of the construction
building’s systems have been in effort. Otherwise, commissioning an
6 stalled correctly and will operate as existing building will likely uncover a
required. multitude of deficiencies that affect
the building’s efficiency and ability
WHEN DO WE DO IT? to operate as required.

The widely held misconception is In existing buildings that have been


that commissioning is checking off previously commissioned, recom
the installation and start-up menu missioning is usually recommended
provided by the equipment manufac at about the 3-5 year point since the
turer. In reality, commissioning is re previous commissioning. However,
sults-oriented, comprehensive, and the most proactive programs com
emphasizes communication, inspec mission their buildings continuously,
tion, testing, and documentation. using and trending data from their
When properly executed, commis building management systems, in
sioning begins with pre-design plan stalled meters and sensors, and even
ning, continues into post-occupancy, utility data. In these cases, commis
sioning never really stops, as analy
sis is conducted continually to detect
impending failures, abnormalities,
and efficiency opportunities.

WHO DOES IT?


The Federal Government is in the
forefront of commissioning. The
Government’s landlord, the General
Services Administration, now re
quires all GSA capital improvement
projects to employ Total Commis
sioning practices as addressed in its
Building Commissioning Guide.
Introduction

The requirement is in GSA’s design commissioning their facilities. These


criteria document, Facilities Stan are typically available from Federal
dards for the Public Buildings and state entities, such as the New
Service (P-100). All new construc York State Energy Research and
tion for GSA must now employ Development Authority
commissioning, beginning with the (NYSERDA). For example,
project planning phase and conclud NYSERDA and the Department of
ing with the post occupancy evalua Energy provide a no cost, risk-free
tion phase. The cost for scoping study to Federal building op
commissioning is included as a line erators to determine the cost effec
item in the construction project bud tiveness of commissioning specific
get. Other Federal Agency real existing buildings. Some utility com
property owners will be establishing panies also provide rebates to Own
similar requirements to at least ers conducting commissioning in
some extent, if they have not al new and existing buildings, particu 7
ready. larly if LEED certification is
achieved.
Grants and special incentives are
available for Owners considering

STUDY QUESTIONS
1. How does commissioning change the traditional definition of a “successful” construction project?

2. What are the top ten reasons why people employ commissioning, and how could your facility benefit from
these reasons?

3. What is the difference between commissioning, and total or whole building commissioning?

4. How is the commissioning process different from a quality control process?

5. GSA is requiring commissioning to be implemented on its new construction projects. Is commissioning


required by your Agency or organization? How important is commissioning in your Agency or organization?
Introduction

8
This page left blank intentionally
Types of Commissioning

Chapter 2
Types of Commissioning

T
he first step in consider Retrocommissioning
ing or planning a com ■ Recommissioning
missioning program for ■ Continuous Commissioning “A leader takes people
your facility is to under where they want to go. A
stand the different types of commis
sioning available, and which types COMMISSIONING FOR NEW great leader takes people
where they don’t necessarily
9

of commissioning are best suited to CONSTRUCTION / MAJOR want to go but ought to be.”
your facility’s unique requirements.
RENOVATION
Rosalynn Carter
In general, a commissioning pro
gram is best applied during the fol
lowing: Commissioning is a systematic
process of ensuring that all building
■ During new construction or a systems perform interactively ac
major renovation of an existing cording to the design intent and the
building. Owner’s operational needs. The
process evaluates building equip
■ When an existing building is ment, subsystems, operation and
experiencing problems with maintenance (O&M) procedures,
operational performance, and performance of all building
energy efficiency, and/or components to ensure that they
occupant comfort and safety. function effi
ciently, and as
■ As a maintenance approach to designed, as a
ensure that equipment and system. This is
systems are operating at peak achieved by be
performance, energy efficiency ginning in the
is optimized, and occupant planning or
comfort and safety are high. early design
phase of a con
The types of commissioning that fit struction project
into these applications that will be with the docu
discussed in this and subsequent mentation of de
chapters are: sign intent, and
continuing
■ Commissioning for New through con
Construction/Renovation struction, ac
ceptance, and
Types of Commissioning

In this Chapter
◆ Commissioning for New Construction / Major Renovation
◆ Retrocommissioning
◆ Recommissioning
◆ Continuous Commissioning
◆ Best Practices

the warranty period with the actual the containment goals for fume
verification of each building hoods and bio-safety cabinets and of
system’s performance. primary and secondary barriers so
that their compliance with the re-
10 The commissioning process encom- quirements can be verified during
passes and coordinates the tradition the commissioning process.
ally separate functions of system
documentation, equipment startup, Often too, local fire marshals alone
control system calibration, testing are responsible for the inspection,
and balancing, performance testing, testing, and approval of all fire pre
and training. It defines a mainte vention and protection devices and
nance baseline against which future systems. In that case, commission
condition assessments and trending ing is coordinated with the fire
can be compared. marshal’s work, his efforts are ob
served by the CxA, and a copy of
Commissioning may include the the official fire marshal report is in
building envelope, the building cluded as part of the Final Commis
HVAC systems, controls, electrical, sioning Report.
conveyance, plumbing fixtures, life
safety, security, or any combinations The commissioning process does not
of these systems and others. take away from or reduce the re
sponsibility of the system designers
The specific person or organization or installing contractors to provide a
that conducts and oversees the com finished and fully functioning build
missioning process is the Commis ing. Commissioning does not take
sioning Authority (or Agent), the place of or reduce in any way
commonly referred to as the “CxA.” the contractor’s responsibilities for
conducting an active project quality
Often, the assistance of subject mat control program.
ter experts is required. Commission
ing of laboratories requires special The Commissioning
attention and involvement of the
Owner’s environmental health and
Process
safety (EH&S) staff as part of the Commissioning is systematic. It in
commissioning team. For example, cludes testing all items in all modes
they will help the CxA understand of operation. Equipment is first in
Types of Commissioning

spected while it is turned off to throughout the life of the project will
make sure that it is installed fully produce the best results. Each of
and correctly. Equipment is then en these will be discussed in greater
ergized, started, and tested under detail later:
controlled conditions. After this ini
tial testing and inspection, integrated Pre-design
systems are tested through all
■ Determine project objectives
cycles and scenarios, including
and develop Owner’s Criteria.
power failure and emergency alarm
■ Develop commissioning require
modes, to ensure they operate as
ments.
required and intended.
■ Hire or assign Commissioning
Authority (CxA).
In the course of commissioning, key
parameters and baseline information
of the systems are documented, or Design 11
ganized, and preserved in the Com ■ Design team develops project
missioning Report and O&M design; CxA reviews design
manual, as applicable. intent, basis of design docu
ments, and drawings and
Commissioning typically follows the provides feedback to design
phases of the new construction or team.
renovation project. Although it is not ■ CxA develops commissioning
necessary to perform commission plan.
ing tasks during each phase of con ■ Design team develops project
struction, implementing the process specifications; CxA develops

What Type of Commissioning Should I Choose?


My building is… Consider…
… going to be undergoing a major renovation in the Commissioning - Ideal for new construction or
next year. major renovation, and best implemented through
all phases of the construction project.
… old and experiencing a lot of equipment failures. Retrocommissioning - Ideal for older facilities that
have never been through a commissioning process.

… relatively new and was commissioned during its Recommissioning - Ideal to tune up buildings that
construction, but our energy costs have been climb have already been commissioned, bring them back
ing recently. to their original design intent and operating/energy
efficiency
… large and complex. We have a metering system Continuous Commissioning - Ideal for facilities
and a preventive maintenance program, but will still with building automation systems (BAS), advanced
struggle with high energy costs and tenant com metering systems, and advanced O&M organiza
plaints. tions.
Types of Commissioning

Commissioning’s Objectives
Commissioning is intended to achieve the follow-
ing specific objectives:
Verification...
◆ ... that applicable equipment and systems are
installed according to the manufacturer’s rec-
ommendations and to industry accepted mini-
mum standards
◆ ... that applicable equipment and systems re-
12 ceive adequate operational checkout by install-
ing contractors
◆ ... and documentation of proper performance of equipment and systems
under various conditions
◆ ... of the proper interactions between systems and subsystems
◆ ... that systems and O&M documentation left on site is complete
◆ ... that the building’s O&M staff has been adequately trained.

commissioning specifications. ■ CxA works with installing


contractors to verify start-up
Installation/Construction and perform verification to
ready systems and equipment
■ CxA gathers and reviews design
for FPT.
and project documentation.
■ CxA holds periodic commission
ing meetings to integrate the Acceptance
process and schedule into the ■ CxA directs and oversees
overall construction project. installing contractors’ perfor
■ CxA develops verification mance of FPT, observed by
checklists and functional Owner’s selected maintenance
performance test (FPT) forms. staff; deficiencies are reported.
■ CxA monitors construction ■ CxA validates building Testing
progress. and Balancing (TAB) report
■ CxA works with the Owner to data.
ensure selected maintenance ■ CxA directs and oversees
staff members are given the installing contractors’ perfor
training opportunity of observing mance of equipment condition
the installation and testing of acceptance testing, observed by
specific systems for which they Owner’s selected maintenance
will inherit maintenance respon staff; deficiencies are corrected
sibilities. and condition baseline data is
Types of Commissioning

included in the final Commis three-phase pump motor of a chiller


sioning Report and O&M system).
manual.
■ CxA works with installing For most equipment, the installing
contractors to reschedule FPT contractors execute the checklists
as needed when deficiencies on their own. The CxA requires that
are present; corrections to the procedures and results be docu
deficiencies are verified by mented in writing and usually wit
CxA. nesses only the verification testing
■ CxA reviews and verifies of the larger or more critical pieces
O&M manuals for complete of equipment. Other components
ness and applicability. are validated randomly by the CxA.
■ CxA oversees, Contractor
conducts, and Owner coordi Functional Performance Tests
nates prescribed training for the 13
Functional performance tests are a
O&M staff. series of tests of the function and
operation (and sometimes, condi
Post-acceptance/Warranty tion) of equipment and systems us
■ CxA prepares the Final Com ing manual (direct observation) or
missioning Report. monitoring methods. Functional per
■ CxA conducts site visits to formance testing is the dynamic
interview O&M staff on system testing of systems (rather than just
performance. components) under full operation
■ Deferred and/or seasonal (e.g., the chiller pump is tested in
testing is performed. teractively with the chiller functions
to see if the pump ramps up and
Types of Testing Used down to maintain the differential
pressure set point).
Verification Checks
Verifications checks are equipment Systems are tested under various
inspections that ensure proper in modes, such as during low cooling
stallation and configuration. This or heating loads, high loads, compo
testing employs checklists to verify nent failures, unoccupied condition,
that the equipment or system is varying outside air temperatures,
ready for initial start-up (e.g., flex fire alarm, and power failure. The
ible conduit is connected, belt ten systems are run through all the con
sion is correct, oil levels are trol system’s sequences of opera
adequate, labels are affixed, gauges tion, and components are verified to
are in place, and sensors are cali respond as the prescribed se
brated). Some verification checklist quences state. The CxA develops
items entail the simple testing of the the functional test procedures in a
function of a component, a piece of sequential written form, coordinates,
equipment, or system (such as mea oversees, and documents the actual
suring the voltage imbalance on a testing, which is usually performed
by the installing contractor or ven
dor.
Types of Commissioning

In addition, seasonal functional per warranties are still active and to es


formance tests may also be per tablish the condition baseline for the
formed, during which the installing ensuing maintenance program.
contractor and/or CxA performs the
functional performance test during Testing and Balancing (TAB)
different seasonal weather condi System testing and balancing may or
tions. may not be included as part of the
Functional performance test commissioning (that is, the TAB
ing determines the Functional performance testing also technicians may or may not work
operating parameters of may include procedures for condi for the CxA). However, validation
equipment and systems, while tion acceptance testing. Condition
condition acceptance testing
of the TAB results by random spot
acceptance testing uses condition checking actual output against the
determines the physical hid monitoring techniques, usually asso
den condition. documented TAB data normally will
ciated with reliability centered main be included in the commissioning
14 tenance, to identify latent process regardless of the TAB
manufacturing, transportation, and contractor’s relationship within the
installation defects that affect the commissioning team.
condition of the equipment at the
time of acceptance.
Advantages
The most common techniques will ■ Commissioning leads to im
use vibration analysis to inspect for proved system performance by
mechanical alignment and balance, ensuring that equipment and
softfoot, and internal and bearing de systems are properly designed,
fects; infrared thermography to de installed, maintained, and
termine the presence of high optimized to work together.
resistance and other problematic
electrical connections; ultrasound to ■ Commissioning can reduce
determine the presence of fluid change orders and improve
(e.g., compressed air, steam, gas) contractor performance and
leaks; lube oil analysis to determine awareness. Testing and monitor
the quality, condition, and appropri ing make contractors more
ateness of lubricating oils and their aware of the quality of their
additives; and/or motor testing and work.
electrical testing, where the condi
tion of the insulation is of major im ■ Commissioning can improve the
portance. overall construction process and
project turnover. The process
Not all commissioning programs in provides for better project
clude condition acceptance testing. communication and enhanced
However, there is no better time to conflict resolution. Commission
determine the physical hidden con ing also provides for follow-up
dition of the equipment (while func site visits to address any prob
tional performance testing looks at lems that may occur after
operating parameters) than as a project turnover.
condition for acceptance while the
Types of Commissioning

Double Checking the TAB Report


In a newly constructed health sciences laboratory and classroom facility at a major university, the CxA per-
formed a random validation check of the testing and balancing contractor’s TAB report. Starting with a random
check of 10% of the air registers, the CxA found an inordinate number of differences between the actual and
TAB-recorded readings. The CxA increased the sample to 25% and found an even greater difference. Further
investigation found that the TAB contractor failed to accurately test and balance the air and water system at all
and fraudulently recorded made up numbers on the official TAB report.

The contractor paid heavily as a result. The TAB was re-performed correctly by a reputable contractor. The
project acceptance was delayed for several weeks as a result of the required re-work. However, because of the
CxA’s testing and verification, the Owner ended up with a fully and properly functioning and balanced HVAC
system that would probably not have been realized until well after the facility became occupied, occupant 15
complaints drove a costly investigation, and payment had already been made for the original, fraudulent TAB
work.

■ A reduction in TAB related to indoor air quality (IAQ). This


construction/major renovation decreases mold-related prob
costs can occur because lems and “sick building” syn
systems and equipment are drome. Improved IAQ also
more likely to be properly impacts the Owner’s liability
balanced during start-up and relative to occupant health and
verification checks. comfort and increases worker
productivity.
■ Studies show that commis
sioned buildings typically save ■ Commissioning has been shown
10 to 20 percent of utility costs by the insurance industry to
compared to similar non reduce liability and losses
commissioned buildings by related to fire and wind damage,
working to ensure that system ice and water damage, power
components operate together failures, professional liability,
most efficiently. and health and safety. Reduced
risk and liability can also
■ Commissioning saves energy increase the asset value of the
and environmental emissions. It building.
is a required factor for points
toward Leadership in Energy ■ It is much easier and less
and Environmental Design expensive to maintain a building
(LEED) certification. that operates correctly than to
maintain one that does not.
■ Commissioning ensures that a Designs that have been re
building is pressurized and has viewed for maintainability and
correct fresh air changes for sustainability, and equipment
Types of Commissioning

that has been installed and flow and air quality, and lighting
tested properly and optimized levels to ensure that occupants
for maximum efficiency, will are comfortable, safe, and
experience fewer problems and productive in their work spaces.
require less unscheduled O&M
time. Disadvantages
■ Equipment condition-accepted ■ The first costs of commissioning
during commissioning verifies are construed by Owners as
the equipment condition prior to being high only to ensure that
expiration of its warranties and the contractor’s work is of a
provides a condition baseline for quality that he’s already con
the ensuing maintenance tracted to perform. There is little
program. quantifiable data on the potential
16 cost savings (both energy and
■ Commissioning can extend operational) that the commis
equipment life and reduce sioning process will generate for
warranty claims, leading to the specific, as-yet operational
fewer warranty claims, service building. Nor is there any way to
calls, reduced energy use, and benchmark in advance, energy
reduced potential for cata and operational performance in
strophic equipment failure. the case of new construction (in
which the “existing” conditions
■ Commissioning provides more do not yet exist).
useful O&M condition baseline
and performance data that is ■ There is no guarantee of
specific to the systems and savings. The commissioning
equipment installed. It details the process is designed to optimize
way the equipment should be all building system and equip
operated, outlines preventive ment operations to meet the
maintenance procedures and design intent; most of the
schedules, and provides infor savings occur through avoided
mation on warranties, vendor costs.
points of contact, and spare
parts. ■ If a quality assurance program
is already utilized by the A/E,
■ The maintenance staff is trained construction manager, and
on site by observing the work as installing contractors, commis
it progresses as well as by sioning may be perceived to be
formal instruction customized to redundant and/or confronta
the specific equipment and tional.
systems installed.

■ Commissioning addresses
RETROCOMMISSIONING
common occupant concerns Retrocommissioning is a system
such as thermal comfort, air atic process for improving and opti
Types of Commissioning

mizing building performance. Retro bring the building, its systems, and
commissioning applies to exiting equipment back to its original design
buildings that have never gone intent, this is not a requirement. The
through any type of commissioning original design intent documentation
or quality assurance process. Its fo may be lost or no longer relevant.
cus is usually on energy-using equip
ment such as mechanical equipment, The Retrocommissioning
lighting, and related controls.
Process
Like commissioning, retrocommis Retrocommissioning is not tied to a
sioning is concerned with how specific new construction or reno
equipment, systems, and subsystems vation project, and therefore does
function together, but it does not not necessarily follow the same pro
generally take a whole-building ap cess as commissioning.
proach to efficiency. The process 17
can identify and solve problems that Retrocommissioning typically fol
occurred at construction, but also lows a four-part process:
addresses problems that have devel
oped to this stage in the building’s 1. Planning
life. And while the goal of - Identify project objectives.
retrocommissioning may be used to - Decide which building

Type of Why? Who? When? How?


Commissioning
Commissioning Ensure that the building Independent CxA Once, during new con Verification and func
and its systems and hired by the Owner or struction or renovation tional performance
equipment operate as the project Construc testing
designed tion Manager

Retrocommissioning Identify and correct Facility O&M staff or in Once, in response to Diagnostic monitoring
problems and optimize dependent CxA specific problems or to and functional perfor
performance establish a commission mance testing
ing program

Recommissioning Ensure that the building Facility O&M staff or in Periodically as the Functional perfor
and its systems and dependent CxA building ages, or ongo mance testing
equipment continue to ing as part of the facility
operate as designed, or O&M program
meet current operating
needs

Continuous Identify and correct Facility O&M staff or in Ongoing as part of the Data monitoring and
Commissioning problems and optimize dependent CxA facility O&M program trending
performance
Types of Commissioning

systems should be analyzed controls, and trending or electronic


for improvements. data logging of pressure tempera
- Define tasks and assign tures, power, flows, and lighting lev
responsibilities. els and use.

2. Investigation In addition, both diagnostic monitor


- Determine how the selected ing and functional performance tests
systems are supposed to are performed to determine tem
operate, or how they could peratures, critical flows, pressures,
operate more efficiently. speeds, and currents of the system
- Perform tests to measure components under typical operating
and monitor how the conditions. Typical diagnostic moni
targeted systems currently toring methods employed include en
operate. ergy management control system
18 - Prepare a prioritized list of (EMCS) trend logging and stand
the operating deficiencies alone portable data logging. The
found and recommended retrocommissioning process involves
corrective actions. development of a diagnostic moni
toring plan and functional perfor
3. Implementation mance test plan, both including test
- Correct operating deficien forms.
cies (highest priority to
lowest). Advantages
- Perform tests to verify
proper and/or improved The advantages of retrocom
operation. misioning are nearly the same as
those of commissioning:
4. Hand-off
- Prepare a report of im ■ Improved system performance
provements made.
- Provide training and docu ■ Energy savings and optimal
mentation on how to sustain energy efficiency (commission
proper and/or improved ing is a required factor for points
operation. toward LEED-EB certification).

Types of Testing Used ■ Improved indoor air quality and


reduced liability.
The investigation
phase of retro
commissioning in
volves review of
current O&M
practices and ser
vice contracts,
spot testing of
equipment and
Types of Commissioning

■ Increased occupant comfort, process is designed to optimize


safety, and productivity. building system and equipment
operations to meet the design
■ Reduced O&M costs and intent or current building
fewer service calls. requirements. There is no
guarantee of savings, however
■ Extended equipment life and they are still a likely by-product
reduced warranty claims. that occurs through avoided
costs.
■ Increased system reliability. Based on three years of data,
■ There is a significant up-front a demonstrable 10-percent
reduction in energy use quali
■ Increased O&M training and workload when performing
fies for 1 LEED-EB point; a
improved documentation. retrocommissioning for the first
20-percent reduction qualifies
time. Documentation, including for 2 points; and a 30-percent
In addition, a retrocommissioning diagnostic test forms and reduction qualified for 3 19
program can result in increased in functional performance test points (maximum)
terest in facilities improvement and forms, that does not exist on site
asset management at all levels. must be compiled and/or
Commissioning can also comple developed.
ment an ongoing facilities manage
ment process improvement
program.
RECOMMISSIONING
Recommissioning refers to com
Disadvantages missioning of an existing building
that has already gone through the
Retrocommissioning and commis commissioning process. Why the
sioning also share many of the same need to commission again, particu
disadvantages: larly if the building was commis
sioned during its construction or a
■ The first costs of retrocom recent major renovation? Recom
missioning may be considered missioning provides additional op
by the Owner to be high and portunities to improve facility
unaffordable since it usually efficiency and addresses issues that
must compete with other may have arisen since the original
priorities from the facility’s commissioning, such as:
operating budget. To counter
this perception, retrocommis ■ Changes in the purpose or
sioning should be “sold” to occupancy of the facility that
Management as a profit center have occurred since the building
by demonstrating estimated was first commissioned.
energy, maintenance, and
productivity savings that will ■ Changed building configurations
result. and occupancy patterns since
the building was first commis
■ Savings may not be the primary sioned (e.g., is an original
focus. The retrocommissioning laboratory now being used for
Types of Commissioning

storage or conference room ten are the source of the biggest op


space?). erational problems and are thus
likely to produce the biggest cost
■ New higher efficiency systems savings. Results of testing are docu
and equipment that have mented, and recommendations for
become available since the improving performance are imple
building was first commissioned. mented.

■ Persistent high energy costs The Recommissioning


despite efforts made to monitor
and control energy consumption
Process
and demand. During recommissioning, the tests
that were performed during the
■ Equipment and systems that do original commissioning are per
20 not operate optimally, or too formed again, with the goal of en
often fail, despite a strong suring that the building is operating
facility operations and mainte as designed or according to newer
nance program. operating requirements. The devel
opment of new project documenta
■ Technologies are now available tion and testing procedures and
When was the last major that improve energy and opera
equipment change-out? Is
forms is not required. However,
tional efficiency, but there is these documents can be updated if
existing equipment relatively
new, or at the end of its use
little or no money programmed the building and its systems and
ful life? Is a major renova in the capital improvement equipment have changed dramati
tion on the horizon? These budget. cally since the original commission
questions will help you de ing.
cide whether or not your fa ■ Federal statute, Executive
cility can benefit from Order, or other requirement Recommissioning can be undertaken
existing building commis mandates that efforts be taken as an independent process in re
sioning. to achieve better energy and sponse to a specific requirement or
water savings and healthier concern (such as those listed
indoor environments. above), or periodically scheduled as
part of the building’s operations and
■ National recognition for energy maintenance program. In general,
and emissions reduction is being the more substantial changes that a
sought through the LEED-EB facility goes through, the more often
Green Buildings program. it should be recommissioned if a
continuous commissioning program
Like commissioning, recommission is not in place. If there are no
ing involves functional performance known substantial changes to the fa
testing of most or all major building cility and its operation, it is recom
systems including HVAC, building mended in general that the facility
automation, lighting, life safety, and be recommissioned every 3-5 years.
conveyance. Mechanical systems
operation and controls are most An independent CxA can be hired to
closely scrutinized because they of perform recommissioning, or the fa
Types of Commissioning

cility O&M staff can use the exist


ing test forms to perform recommis Advantages
sioning in house.
In addition to the advantages listed
Types of Testing Used under commissioning and retro
commissioning, recommissioning
Recommissioning starts with: also provides the following:

■ Site observation; ■ Periodic recommissioning can


■ Interviews with occupants; contribute to the persistence of
■ Analyses of energy metering commissioning savings and
data (if available); benefits, and will ensure that the
■ Review of current O&M building and its equipment and
practices and service contracts; systems remain in compliance
■ Spot testing of equipment and with original design intent. 21
controls; and
■ Trending or electronic data ■ Recommissioning affords
logging of pressure, tempera facility managers the opportu
tures, power, flows, and lighting nity to update building, system,
levels and use to determine and O&M documentation and
current conditions (this replaces to modify the design intent, if
verification checks). necessary, to reflect changes in
building requirements.
Recommissioning then uses the
same functional performance test ■ Functional performance test
forms that were developed during forms have already been
the initial commissioning process to developed and are ready for
test systems dynamically under full use.
operation. Systems are tested under
various modes, such as during low ■ Recommissioning can increase
cooling or heating loads, high loads, O&M knowledge and skills in
component failures, unoccupied diagnosing operating problems
conditions, varying outside air tem and determining and implement
peratures, fire alarm, and power ing corrective strategies.
failure. The systems are run
through all the control system’s se ■ Recommissioning can identify
quences of operation. Components problems not readily apparent
are checked for their responsive due to long-term storage of
ness to the prescribed sequences equipment, such as breakdown
and validated. of dielectrics, degraded fluids,
failed batteries, leaking seals,
Unlike commissioning, the bulk of and flattened bearings.
the functional performance testing
performed during recommissioning Disadvantages
may be carried out by the building
O&M staff. ■ Recommissioning may be an
Types of Commissioning

occasional event and may take Continuous commissioning requires


place many years after the initial benchmarking of energy use using
commissioning, depending on the available installed building automa
level of Management support tion systems and metering equip
and the availability of funds. ment. Data are continuously
gathered and compared against the
■ Recommissioning is often benchmark to measure building effi
implemented only in response to ciency and ensure that equipment
breakdowns in equipment or and systems operate at optimal lev
systems, and not as a proactive els throughout their useful lives.
tool to ensure building perfor
mance optimization. While continuous commissioning is
closely related to (and often inte
■ Recommissioning should not be grated into) a facility operation and
22 used as a substitute for major maintenance program, it goes be
equipment change-out or yond O&M to ensure that the build
systems redesign that may, in ing and systems operate optimally to
fact, be required. meet current requirements, evaluat
ing both building functionality and
■ There is a risk of facility equipment and system functions.
Management adhering to an
outdated design intent rather Continuous commissioning can be
than updating the design intent provided by a qualified third party
for a building’s current require CxA, or by well-trained members of
ments. the O&M staff.

CONTINUOUS The Continuous Commis


sioning Process
COMMISSIONING
Continuous commissioning is accom
Continuous commissioning, like plished in two phases: project devel
retrocommissioning, is a systematic opment, and implementation and
approach to identifying and correct performance verification. During
ing building system problems and op project development, the CxA or
timizing system performance in O&M team screens potential project
existing buildings. Any similarities targets, performs a project audit, and
between the programs end there, develops the project scope.
however. Continuous commissioning
is distinct because its primary focus During the second phase, the CxA
is on ensuring the persistence of or O&M team:
building systems optimization. It is
an ongoing process for existing ■ Develops the commissioning
buildings employed to resolve oper plan and forms the project team
ating problems, improve building ■ Develops performance
comfort and safety, optimize energy baselines
use, and identify retrofits. ■ Conducts system measurements
Types of Commissioning

Retrocommissioning, Recommissioning, Continuous


Commissioning… I’m Confused!
All three terms apply to commissioning of existing facilities, and all three aim to improve operating
performance, energy efficiency, and occupant comfort and safety. Here’s how they’re different:

?
Retrocommissioning
◆ A one-time event
◆ The building has not been previously commissioned
◆ May or may not adhere to building’s original design intent
◆ Utilizes diagnostic monitoring and functional performance tests
23
Recommissioning
◆ A one-time, periodic, or occasional event
◆ The building has been previously commissioned
◆ Adheres to building’s original design intent
◆ Utilizes previously developed functional performance tests
Continuous Commissioning
◆ Continuous monitoring with assessments performed at least quarterly
◆ The building may or may not have been previously commissioned
◆ Does not adhere to building’s original design intent – is concerned instead with trending relative
to a baseline and optimizing performance to meet current requirements
◆ Utilizes building automation system and/or metered energy trend data and/or condition accep-
tance tests

■ Develops and implements operation and operating and energy


proposed commissioning trends periodically to identify any
measures and problems and to develop improved
■ Measures, verifies, and docu operation and control schedules.
ments improvements and Energy data is reviewed at least
operational and energy savings. quarterly to identify the need for an
other commissioning tune-up. If
An important distinction in this form building energy consumption has in
of commissioning is that the process creased, or if the performance effi
is continuous: steps are taken to ciency of building equipment and
maintain the improvements to occu systems has decreased, the CxA or
pant comfort and safety, operational O&M staff performs an evaluation,
efficiency, and energy efficiency develops measures to restore the
that have been achieved. The CxA building energy and operational per
or O&M staff review the system formance, and implements the mea
Types of Commissioning

sures. Ongoing follow-up (at least commissioning. The process


quarterly) is essential to guarantee stresses gathering and analyzing
the persistence of savings and high considerable data on occupancy
levels of energy and operational effi patterns and building operation.
ciency over time. Instead of making sure the
systems work as designed,
Types of Testing Used continuous commissioning
ensures that systems run as
Apart from site observation and in efficiently as possible and
terviews with occupants, the bulk of produce optimal occupant
continuous commissioning testing is comfort for current conditions.
a combination of analysis of metered This results in significant savings
and recorded energy data and of if the system, as designed, has
condition monitoring. Condition poor efficiency or a negative
24 monitoring is one aspect of reliability impact on occupant comfort.
centered maintenance (RCM) and is
common to advanced preventive ■ Continuous commissioning is
maintenance programs. It differs proactive and can identify
from functional performance testing operational problems associated
(common to the other types of com with long-term storage of
missioning) in that it concentrates on equipment that are not readily
the current and predictive condition apparent, such as the break
of the equipment, rather than on the down of dielectrics, degraded
output parameters and perfor fluids, failed batteries, leaking
mance relative to its design and in seals, and flattened bearings.
tent.
■ Whether the continuous com-
Advantages missioning program is led by a
third party CxA or implemented
■ Persistence of benefits of the by the facility O&M staff, staff
commissioning process is the skills will inevitably increase as
most obvious advantage to a result. The O&M staff gains
continuous commissioning. The knowledge and skills in diagnos
process focuses on finding ing operating problems and
sustainable engineering solutions determining and implementing
based on engineering principles corrective strategies.
to address problems with
building operation, energy ■ The energy and cost savings
efficiency, and/or occupant resulting from continuous
comfort and safety. An added commissioning measures can be
benefit is a usual decrease in used for major systems and
O&M workload and costs. equipment upgrades. Continuous
commissioning has first costs
■ Superior operational, energy, associated with the training of
and comfort performance is the the O&M staff and the one-time
ultimate goal of continuous cost of installing a building
Types of Commissioning

automation/energy management intensive facilities, because a

control system or system sophisticated energy manage-

metering capability. Once these ment or metering system can

costs are covered, future also be used for load control

savings from operational and other energy management

measures can be applied to the applications.

installation of energy conserva

tion measures and other ■ Continuous commissioning is

authorized capital improve- most effective, and most cost

ments. In addition, the continu- effective, when implemented in

ous commissioning process a facility that already has in

identifies efficiency measures, place a preventive maintenance

reducing the need for additional program and a highly skilled and

audits and engineering analysis trained O&M staff. Lacking

when programming for major this, costs will rise to bring in a


25
retrofits. qualified CxA to perform the

continuous commissioning
Disadvantages activities and/or to train the
existing O&M staff on continu
■ Continuous commissioning does ous commissioning approaches
not consider design intent – and tests. High O&M staff
how were the installed equip- turnover is also a barrier.
ment and systems intended to However, the cost of training

operate? Facility uses and O&M personnel can also be a

occupancy change over time, wise investment, particularly in

and it is possible that the design larger, more complex, and more

intent is obsolete. It might be energy-intensive buildings.

beneficial to revise the design

intent and use it as a guiding

document for O&M; in continu

ous commissioning, there is no


such guide to building opera References
tions.
1. Continuous Commissioning Guidebook: Maximizing Building
■ The installation of a building Energy Efficiency and Comfort, Liu, Mingsheng, Ph.D., P.E., et.
automation system (BAS), al., October 2002.
energy management control 2. It’s Time to Shake Out the Mothballs in Your Mission-Critical Fa-
system (EMCS), or other cility, Soroka, Joe, Comminique (online newsletter of AFCOM),
metering system is required for March 2004.
the monitoring and verification 3. A Practical Guide for Commissioning Existing Buildings, Haasl,
that is essential for tracking the Tudi and Terry Sharp, April 1999.
persistence of engineering
4. Retrocommissioning Handbook for Facility Managers, Portland
measures. This can be cost
Energy Conservation, Inc., March 2001.
prohibitive to smaller facilities.
It can also be a good invest 5. Whole Building Design Guide, General Services Administration,
ment for larger, more energy- available at www.wbdg.org.
Types of Commissioning

BEST PRACTICES will help you decide whether or


not your facility can benefit
■ Carefully consider the short- from existing building commis-
and long-term plans for your sioning.
facility. When was the last
major equipment change-out? Is ■ Continuous commissioning adds
existing equipment relatively to your O&M costs, but can be
new, or at the end of its useful a good investment in large,
life? Is a major renovation on complex, and energy-intensive
the horizon? These questions buildings.

26

STUDY QUESTIONS
1. What type(s) of commissioning would you consider suitable for your facility?

2. For new construction or major renovation projects, at what phase of the project should the commissioning
process ideally start?

3. Under what circumstances would you consider including subject matter experts on the commissioning
team?

4. Does commissioning replace or reduce the contractor’s Quality Control responsibilities?

5. What are the primary objectives of commissioning?

6. Explain the differences between verification testing, functional performance testing, and condition accep-
tance testing.

7. Explain the major differences between new building commissioning, retrocommissioning, recommission-
ing, and continuous commissioning.

8. What is the relationship between any of the forms of commissioning and energy savings?

9. How would you describe the value of commissioning to the Owner? Building occupants and users? The
operations and maintenance staff?
Why Commission?

Chapter 3
Why Commission?

T
o better understand the it fit” are not uncommon. Equip-
benefits of commission- ment literally may self-destruct.
ing, consider how much
buildings and their sys- The consequence of most un-
tems have changed over the last commissioned buildings is that the 27
couple of decades. Control systems O&M staff inherits systems ripe
have become highly complex with with problems and inefficiencies.
the migration from pneumatic to di- An un-commissioned building
rect digital control systems; with may not operate correctly, and
more sophisticated building manage- without essential O&M informa-
ment system (BMS) hardware and tion, training, and baseline data,
software; and with automatic the O&M staff likely cannot re-
valves, dampers, actuators, and sen- spond adequately to occupant
sors. New technologies have been complaints. They respond to
introduced for life safety and secu- problem symptoms rather than
“If you always do what you’ve
rity systems. Buildings must operate correcting root causes. Automated
always done, you’ll always get
with optimal energy efficiency. In- systems become bypassed and
what you’ve always got;
door air environments have taken overridden. Occupants very quickly Change makes change.”
on a new importance with regards settle on low expectations and be-
to mitigation of mold, mildew, and come sensitized to (or very vocal Anonymous
new product emissions as they af- about) the poor building environ-
fect occupant health, comfort, and ment, which deteriorates steadily.
productivity. Energy efficiency suffers, and build-
ing performance falls short of the
Commissioning also has long-term Owner’s expectations. These costs
repercussions on maintainability. are high and well above those for
Systems may not be installed, ad- commissioning.
justed, and integrated to operate op-
timally. They may be installed with A team from the Lawrence Berke-
latent manufacturing, transportation, ley National Laboratory, Portland
and installation defects. Systems Energy Conservation, Inc., and the
designed and installed with struc- Energy Systems Laboratory of
tures that amplify destructive natu- Texas A&M University set out to
ral harmonics, that get damaged quantify the actual costs and im-
during transport, and that were det- pacts associated with commission-
rimentally modified on site to “make ing1 . The Cost-Effectiveness of
Why Commission?

In this Chapter
◆ Commissioning Costs and Return on Investment
◆ Cost Benefits of Commissioning
◆ Barriers and Management Buy-in
◆ Impact on Facility Operations and Maintenance
◆ Impact on Energy Consumption
◆ LEED Certification
◆ Best Practices

Commercial-Buildings Commis- overall HVAC system. The


sioning analyzed results from 224 median cost per building was
28 buildings across 21 states and in- about $34,000 for commissioning
volved 30.4 million square feet of (or $0.27/sf) and resulted in
commissioned floor area (73 percent savings of about $45,000
in existing buildings and 27 percent (median) per year or ($0.27/sf/
in new construction). Some results yr). Energy cost savings result-
were surprising: ing from the retro-commission
ing are estimated to be about
■ Among 85 existing buildings in 15-percent with a simple
the study that were being retro payback time of 0.7 years.
commisioned for the first time,
3,500 deficiencies were found. ■ Deficiencies are expected in
Approximately 85% of the older facilities that may have
deficiencies found related to the outdated, inefficient equipment

Excerpt from Mills, E., et.al.1 Existing Buildings New Construction


Sample Sample
Size Size

No. of Deficiencies Identified 3,500 85 3,305 35

Commissioning Cost ($1,000) 34 74


Commissioning Cost ($/sf) 0.27 102 1.00 69

Total Savings ($1,000/yr) 45 3


Total Savings ($/sk/yr) 0.27 100 0.05 33

Whole Building Energy Cost Savings (Median %) 15 74 Not Available

Simple Payback Standardized to U.S. Energy Prices (Yr) 0.7 59 4.8 35


Why Commission?

and systems. But the study also malfunctioning equipment, and de


found significant room for ferred maintenance have a host of
improvement in new construc ramifications, ranging from equip
tion projects. Among 35 new ment failure to compromised indoor
construction projects analyzed, air quality and comfort to unneces
the commissioning process sarily elevated energy use or under-
uncovered 3,305 deficiencies. performance of energy strategies.
Deficiencies with the air The “newness” of a building does
handling and distribution were not guarantee fewer deficiencies, as
most common, followed by the study demonstrates.
lighting, and HVAC combined
heating and cooling plant. For a The most frequently cited barrier to
median cost of $74,000 per new widespread use of commissioning is
building (or $1.00/sf), estimated decision-makers’ uncertainty about
savings were calculated at its cost-effectiveness. But because 29
about $3,000/year (or $0.05/sf/ deficiencies are common in both
yr) with a simple payback time new construction and existing build
of about 4.8 years because ings, the bigger financial cost may
most new construction projects come from not commissioning your
emphasized a small number of building.
corrective measures rather than
a whole-building effort that is
characteristic of existing
COMMISSIONING COSTS
building retro-commissioning. In AND RETURN ON INVEST
addition to energy savings,
owners in the study reported MENT
other benefits such as increased
Based on their study, the Lawrence
productivity and safety, better
Berkeley National Laboratory team
indoor air quality and thermal
was able to quantify the average
comfort, longer equipment life,
cost of commissioning as previously
and a reduction in change
presented:
orders and warranty claims.

As these results show, commission Retrocommissioning of Existing


ing can be viewed as invaluable to Buildings
detecting and correcting deficien ■ Cost of commissioning: $0.27/
cies in both new construction/major square foot
renovation projects, and in existing ■ Whole-building energy savings:
buildings. Deficiencies such as de 15 – 20 percent
sign flaws, construction defects, ■ Payback time: 0.7 year

1
Mills, E. et al. (2004) The Cost Effectiveness of Commercial Building Commissioning: A Meta-Analysis of
Energy and Non-Energy Impacts in Existing Buildings and New Construction in the United States. (http:eetd.lbl.gov/
emills/pubs/cx-costs-benefits.html)
Why Commission?

BOMA cost data for office buildings


New Construction/Renovation suggest that commissioning can save
Commissioning energy from 20-percent to 50-per
cent and additional maintenance
■ Cost of commissioning: $1.00/
savings from 15-percent to 35-per
square foot (0.6 percent of total
cent.
construction costs)
■ Whole-building energy savings:
The study found that commissioning
N/A
is cost-effective for both existing
■ Payback time: 4.8 year
buildings and for new construction,
across a range of building types,
Whole-building energy savings data
sizes, and energy use. The more
is not available for new construction
complex the building and its systems,
commissioning, as there is no bench-
the more cost savings commission-
mark upon which to measure energy
30 ing can achieve.
use before commissioning is applied
to the project.
Commissioning costs vary more ac-
cording to the complexity of the sys-
The Portland Energy Conservation,
tems, number of pieces of
Inc. (PECI) studies indicate that on
equipment, and objectives or scope
average the cost of operating a
of the project rather than by building
commissioned building range from 8
type. The following graph developed
percent to 20-percent below that of
by the Portland Energy Conserva-
a non-commissioned building.

Benchmark Commissioning Costs by Facility Type


Specialty – Very complex facilities; laboratory; prison; mission control center

$3.00 Complex – Moderate plus most of floor area in complex systems; hospitals;
clean rooms; non-HVAC systems included, such as Security, communications;
Commissioning Cost in $/square foot

involves high cost travel and cost of living areas

Moderate - More complex office, classrooms with some laboratories;


buildings with Building Automation Systems; more control strategies; fewer
packaged equipment; more systems such as fire, emergency power, envelope
$2.00 Simple – Office buildings, classrooms, packaged equipment and
controls; common systems; fewer pieces of equipment

Specialty

$1.00 Complex

Moderate

Simple

$0.00

50 100 200 300 400 500 600

PECI 2000 Floor Area in Thousands of Square Feet


Why Commission?

tion, Inc. (PECI) in 2000 illustrates technologies are becoming


the effects of building size and com increasingly more complex and
plexity on the cost of commission energy efficient. But increased
ing. system performance will not be
realized unless equipment and
For new construction and major systems are properly designed,
renovation projects, there is typi installed, maintained, and
cally a three- to five-percent contin optimized to work together in
gency budget for problems that may an integrated fashion.
arise during construction; commit
ting part of this contingency budget ■ Energy savings – Studies
to commissioning up front is a smart show that commissioned
move to decrease overall costs re buildings typically save 10 to 20
lated to construction deficiencies percent of utility costs com
and to ensure a more efficient build pared to similar non-commis 31
ing as an end product. sioned buildings by working to
ensure that system components
The recognized rule-of-thumb used operate together most effi
in the construction industry to esti ciently. In particular, properly Commissioned buildings typi
mate return on investment is a $3 optimized HVAC and control cally save 10 to 20 percent of
savings for each $1 spent on com systems often lead to the utility costs compared to simi
missioning. (More complex facilities greatest energy savings. In lar non-commissioned build
such as laboratories and hospitals, contrast, the lack of a commis ings.
may have greater return on invest sioning program may lead to
ment ranging from $3 to $11 for under-performance of energy-
each dollar spent on commissioning. efficient equipment.

Commissioning provides short- and ■ Improved thermal comfort –


long-term benefits, so the process Commissioning helps ensure
should be viewed as an investment thermal comfort. It provides for
rather than an expense. In terms of acceptable levels of tempera
total cost of ownership, it is impor ture and humidity, air movement
tant to consider equipment life-cycle and ventilation, and the ability
costs and energy efficiency in addi for occupants to modify condi
tion to the acquisition or first cost of tions. It provides a better work
building equipment and systems. environment with fewer occu
pant complaints and enhanced
COST BENEFITS OF productivity.

COMMISSIONING ■ Extended equipment life and


reduced warranty claims –
The following benefits are common Commissioning optimizes
for all types of commissioning: equipment and systems from
day one, meaning fewer
■ Improved system perfor
mance – Building systems and
Why Commission?

warranty claims, service calls, specific to the systems and


reduced energy use, and equipment installed, details the
reduced potential for cata- way the equipment should be
strophic equipment failure. operated, outlines preventive
Commissioning ensures that maintenance procedures and
equipment that is properly schedules, and provides infor
calibrated, and provides training mation on warranties, spare
and documentation to O&M parts, and vendors. In addition,
staff that will help achieve commissioning and particularly
extended equipment life. condition acceptance data
provide a baseline against which
■ Increased training for build- the ensuing maintenance
ing O&M staff – This is of program can be compared and
particular importance given the trended.
32 increasingly complex controls,
building management systems, ■ Renewed interest in more
and energy management closely monitoring facilities
systems being installed in maintenance and physical
today’s buildings. Inadequate assets – The commissioning
training can lead to sophisticated process requires a commitment
controls and management of internal resources even if the
systems being shut off, by- program is outsourced to a
passed, and/or not properly commissioning provider. The
programmed and calibrated, required program and team
reducing the energy savings, building can be a catalyst for an
safety, and operational efficien- increased interest in facilities
cies they were designed to improvement and asset manage-
provide. ment at all levels. Commission
ing can also complement an
■ Improved O&M documenta- ongoing facilities management
tion – Commissioning provides process improvement program.
more useful O&M data that is
■ Increased occupant comfort,
safety, and productivity –
If a building is designed to use 20-percent outside air to meet Commissioning addresses
IAQ code requirements, less outside air could result in the common occupant concerns
building being negatively pressurized. This can be condu- such as thermal comfort, air
cive to mold growth, cause occupants to become sick, affect flow and air quality, and lighting
productivity, and subject the building to excess energy use. If levels to ensure that occupants
outside air is greater than the prescribed 20-percent, an ex- are comfortable and safe in their
cessive amount of energy will be used with consequential work spaces. This can lead to
higher energy costs. Commissioning can ensure that a build- enhanced worker productivity,
ing is both efficient and healthy by verifying the functionality of fewer sick days, and a higher
the control system and the responsiveness of each of its as- building resale value. Equipment
sociated devices. and systems that are installed
Why Commission?

Conventional MEP Design MEP Design with Commissioning

◆ Component driven ◆ Integrated

◆ Focused on compliance ◆ Focused on systems and equipment


with codes and standards optimization in addition to codes and
standards compliance

◆ Based on first cost ◆ Based on life-cycle cost in addition to


first cost

and calibrated properly are also Equipment that has been


less likely to break down and installed and tested properly and 33
potentially injure O&M staff. optimized for maximum effi
ciency will experience fewer
■ Improved indoor air quality problems and requires less
– Commissioning ensures that a unscheduled O&M time. The
building is pressurized and has complete and accurate building
correct fresh air changes for documentation that commission
indoor air quality, which de ing provides will expedite
creases mold-related problems maintenance troubleshooting.
and “sick building” syndrome. It The training provided to O&M
can decrease energy costs as staff will increase skill levels
well. and staff effectiveness.

■ Reduced liability – Any ■ Incentives – Commissioning


measure that decreases insur has the potential to qualify
ance losses contributes to the buildings for utility program
bottom lines of both the insurer rebates and other Federal and
and the insured. Commissioning State incentives. The Federal
has been shown by the insur Energy Management Program
ance industry to reduce losses (FEMP) and organizations such
related to fire and wind dam as NYSERDA often provide
age, ice and water damage, seed money and financial
power failures, and health and assistance to those Agencies
safety. Reduced risk and seeking to commission their
liability can also increase the new or existing building.
asset value of the building.
■ Special laboratory pressur
■ Reduced O&M costs – It is ization and features – Labora
much easier and less expensive tories are comprised of many
to maintain a building that systems and subsystems bound
operates correctly than to together in complex ways to
maintain one that does not. provide required airflows and
Why Commission?

pressurization. Many air sys provides increased project


tems operate around-the-clock communication and enhanced
resulting in high operating conflict resolution. Project
energy costs. Consequently, turnover includes all functional
simple adjustments can yield test forms, O&M and systems
large savings. More importantly, documentation, warranty
negative or positive pressuriza information, and evidence of
tion is used to control the airflow training activities. Commission
to protect worker health and ing also provides for follow-up
safety and the environment. site visits to address any prob
Commissioning provides Commissioning will check and lems that may occur after
short- and long-term ben validate the actual pressure project turnover.
efits; the process should be gradients against the design
viewed as an investment intent documentation as well as ■ Decreased testing, adjusting,
34 rather than an expense. the functional performance of and balancing (TAB) costs –
interlocking systems to ensure A reduction in TAB costs can
the pressurization is maintained occur because systems and
if part of the system fails or is equipment are more likely to be
turned off. working properly during start-up
and verification checks. This
The following benefits can be allows the TAB contractor to
achieved in addition to those listed proceed uninterrupted.
above for new construction commis
sioning: It is much easier to quantify the
costs associated with commissioning
■ Reduced change orders and than to track and quantify the ben
improved contractor perfor efits. Benefits such as improved en
mance and awareness – ergy performance, extended
Change orders are reduced equipment life, improved indoor air
because many problems and quality, and reduced O&M costs, for
deficiencies are detected example, cannot be quantified easily.
through the commissioning However, these factors can lead to
process prior to functional significant cost if not adequately ad
performance testing. The dressed (which is what commission
process provides a mechanism ing is designed to do):
to correct problems and defi
ciencies before project turnover, ■ Lost productivity during a
thereby saving Contractor systems power failure.
warranty callbacks. Testing and ■ Construction delays due to
monitoring make contractors increased change orders.
more aware of the quality of ■ Litigation due to poor indoor air
their work. quality, leading occupants to get
sick.
■ Improved construction
process and project turnover The potential cost of each of these
– Commissioning done properly examples (and many others) cannot
Why Commission?

be quantified, but could be very 3. There is not a sense of “need”


large indeed. for commissioning services. On
new construction, quality
BARRIERS AND MANAGE- assurance support is already
being provided by the design
MENT BUY-IN and construction teams, and in
existing facilities, established
Commissioning is often viewed by O&M programs should be able
building decision makers as an to detect and correct problems
added cost. If commissioning was without a commissioning
free of charge, it would most likely process. The Federal Govern-
be easily adopted by facility owners ment’s new emphasis on LEED
and operators across the board. But certification for new and
cost is just one barrier to adoption existing buildings, which re-
that the commissioning process quires commissioning, is begin- 35
faces. Common barriers include: ning to increase its sense of
importance.
1. The first costs associated with
commissioning are viewed by 4. If a building already went

Owners as being relatively high through the commissioning

($0.27/square foot for an process during new construction

existing building; $1.00/square or a recent major renovation,


foot for a new construction there is a feeling of no addi

project). However, there is little tional benefit from repeating

quantifiable data in advance on that process. This attitude fails

the potential cost savings (both to realize that buildings, occu


energy and operational) that the pants, and missions change over

commissioning process will time, and any impact on the

generate. design intent can impact the

equipment’s and system’s


2. There is no guarantee of efficiency.
savings – The commissioning
process does not necessarily 5. The funding source is often a
have cost savings as its primary barrier to commissioning new
objective. It is designed to construction. Capital funding, if

optimize all building system and it does not have a line item for

equipment operation to meet the commissioning, is concerned

design intent (commissioning) or with delivering a finished project

current building requirements

(retrocommis-sioning). The bulk

of the actual cost savings

achieved through commission


Best Practice: “Give me your worst facility – I will make it work.”
ing is a by-product in the form
Tells the Owner that if you can correct its’ deficiencies and im-
of avoided costs.
prove its’ efficiency, then you could do wonders with everything
else.
Why Commission?

on time and within budget. If 1. Start with a pilot project,


commissioning is included, it either a retrocommissioning
often gets value-engineered out project with a set of desired
with little regard for the impact goals (i.e., to improve the
on maintenance after final building indoor air quality), or a
acceptance and turn over. commissioning process tied to a
Meanwhile, the O&M and planned renovation. A single
facility staff inherit a building pilot project will allow changes
that may be problematic for its identified through the commis
lifetime. sioning process to be monitored,
verified, and its benefits realized
Approaches and communicated to Manage
ment. Consistent commissioning
In addition to outlining the benefits to approaches and documentation
36 be achieved through the commis can then be developed for use
sioning process, some approaches on subsequent projects.
for overcoming barriers and obtain-
ing Management buy-in are sug 2. Develop a methodology for
gested: analyzing the costs and

So What are the Pitfalls? Some True Experiences:


◆ A university in Washington state contracted for a commissioning consultant but needed to redi-
rect significant resources from an in-house staff to bring the building’s systems on line. Facilities
management staff found the CxA to be non-responsive and troublesome. They support commis-
sioning to this day, but “not consultants who don’t know what they’re doing and don’t deliver value
added to the process.”
◆ The contractor for a new 180,000 SF facility in Idaho found a subcontractor adding $6,000 to his
bid because of the CxA oversight. The contractor was amazed that the subcontractor added
extra money to get the job done right! Does that mean that $6,000 can be deducted from his bids
if quality is not an issue? If the job is done right the first time, there is no added cost. Commission-
ing may even increase profits by reducing warranty callbacks.
◆ On a major renovation project, true commissioning was never fully completed because the:
- Owner wanted to move in and start operations
- Contractor wanted to get done and off site at the least cost
- A/E wanted to close the job
- Specifications were weak and
- “Punch List” became a “To Do” list for the maintenance staff
The ultimate effect was that the O&M staff had to divert resources from its preventive mainte-
nance program to correct deficiencies that should have been corrected as part of commission-
ing acceptance.
Why Commission?

benefits of the commission 5. For existing buildings, integrate


ing process throughout the life the commissioning program
of the project. This methodol into the facility’s overall
ogy should identify and record operations and maintenance
deficiencies that are found program (continuous commis
using the commissioning sioning).
process and estimate the cost
avoidance associated with 6. For existing buildings, prepare
correcting each deficiency. a comparison of facility
operating and energy costs
3. Keep a thorough record of with similar buildings in the
costs avoided by identifying area (close to or same age, use,
problems using the commission and square footage). A commis
ing process. Avoided costs to sioning program may be an
consider include repair, replace easier sell and support if similar 37
ment, installation, design, buildings have lower operating
energy, depreciation, mainte and energy costs.
nance, revenue loss, and
productivity loss. Base cost 7. Stress the importance of
avoidance estimates on the best persistent benefits when
data available, and be conserva addressing the need for recom
tive in how the data is applied . missioning. Subsequent changes
Wildly inflated cost savings in facility use or tenancy may
work against the goal of require a revision in design
establishing a consistent, long- intent. The addition of increas
term commissioning program by ingly complex energy and
making savings seem unattain building management systems
able. may require additional O&M
documentation and training.
4. Integrate the commissioning Setpoints and operating cycles
program with the facility’s may have been modified by
overall energy management facility O&M staff and/or
program. Commissioning occupants since the time the
benefits energy management by facility was last commissioned.
ensuring and optimizing the
performance of energy effi
ciency measures and by
IMPACT OF FACILITY
correcting problems that cause OPERATIONS AND
MAINTENANCE
higher than necessary energy
use. The energy management
program provides benchmarking
Systems and equipment that are
of energy consumption and
properly installed and calibrated, and
demand that makes the impact
fully optimized to work together, will
of commissioning activities easy
be easier for a facility’s O&M staff
to quantify during measurement
to maintain. This is one commission
and verification.
Why Commission?

Approaches for Quantifying the Benefits of a


Commissioning Program
It is difficult to project in advance what cost savings will result
from implementing commissioning in a new construction/reno-
vation project or in an existing facility. There are several meth-
ods to employ during the course of the project, however, that will
allow you to calculate operational and energy savings when the
project is complete. These methods include:
◆ Collect building data and define Key Performance Indica-
38 tors (KPI) at the outset to pre-define measurement and per-
formance goals.
◆ Establish a metering system in the building to measure en-
ergy use. (A metering system has the added benefit of pro-
viding an automated exception report if systems are out of
tune.) If this is not feasible, use utility bills (previous 12
months) to establish an energy use baseline.
◆ Use an energy simulation program (such as DOE2, Trane TRACE, Carrier HAP, BLAST,
Energy Plus) to quickly organize and evaluate results gathered during measurement and
verification.
◆ Establish an automated maintenance tracking system that will provide data pre- and
post-commissioning on service calls, failure reports, maintenance schedules, etc.
◆ Develop a methodology that tracks the deficiencies that are found using the commis-
sioning process and estimates the cost avoidance associated with correcting each de-
ficiency. Include costs related to repair, replacement, installation, design, energy,
depreciation, maintenance, revenue loss, and productivity loss.
◆ Compare maintenance hours, operations cost, and energy use data in the commis-
sioned building or affected area with the same data from a similar, but un-commis-
sioned, facility. In the case of an existing building, compare the same data in the same
building or affected area, but before and after the retro- or re-commissioning. (Be careful
not to compare costs alone, as cost increases, such as increased energy tariffs, may
skew the comparison results.)
Develop an internal report that summarizes cost and benefit data, or have the CxA include the
data in the final Commissioning Report. Information gained through these methods will allow
you to model potential operational and energy savings on subsequence commissioning
efforts. Using this approach will facilitate powerful historical data and allow each project to be
evaluated in a value-based manner.
Why Commission?

A 2004 study conducted by Cornell University correlated worker productivity with indoor environmental con-
ditions. It found that workers produced 74-percent more mistakes and 46-percent less output based on
temperature alone when the temperature fell from 77oF to 68 oF. The study estimated that the decreased
productivity resulted in a 10-percent increase in labor costs per worker, per hour. “Our ultimate goal is to have
much smarter buildings and better environmental control systems in the workplace that will maximize worker
comfort and thereby productivity,” the professor overseeing the study said. Commissioning by its nature
supports that goal and optimizes those very systems. (source: http://ergo.human.cornell.edu/
CUEHEECE_IEQDown.html)

ing benefit that can profoundly im- such baselines, which include the
pact the O&M staff. Commission- following performance metrics:
ing does require input and effort 39
from the O&M staff. Most of the ■ System Capacity (actual
benchmarking and maintainability operation compared to full
issues associated with commission system utilization of plant or
ing are addressed throughout the equipment)
commissioning process during initial ■ Work Orders Generated and
planning, design reviews, verifica Work Orders Closed Out
tion inspections, functional perfor ■ Preventive Maintenance
mance, condition acceptance Backlog
testing, and training. The O&M ■ Safety Record
staff’s effort during commissioning ■ Energy Use
revolves around providing input and ■ Inventory Control
feedback as the project progresses, ■ Overtime Logs
observing the work in progress and ■ Environmental Record (air and
system testing, and receiving proper water discharge levels, non
and appropriate training and educa compliance situations)
tion on the new and modified in ■ Staffing: Absentee and Turn
stalled systems. over Rates

Establishing a building performance Commissioning should produce


and O&M program baseline is one measurable improvements in each
of the most important tasks for an of these performance categories.
O&M organization related to mea
suring the costs and benefits of a A fine-tuned O&M program is one
commissioning program. This allows of the keys to achieving persistent
the O&M organization to quantify commissioning benefits. Successful
operational, energy, and other ben O&M planning begins early in the
efits from commissioning, as well as commissioning process, often at the
identify unforeseen problems. Most design phase, during which O&M
O&M organizations that have staff should participate by providing
adopted common O&M best prac design recommendation input based
tices will already have established on their past hands-on experience.
Why Commission?

Tracking Energy Efficiency Improvements from Commissioning


It is important to identify and define desirable metrics before collecting energy efficiency improvement data on
your commissioning project. The following are sample metrics:

Building Characteristics and Demographics


❏ Building type (using DOE/CBECS definitions), age, location
❏ Year building commissioned: new construction/renovation or existing building commissioning
❏ Reasons for commissioning, deficiencies identified, corrections/improvements recommended
Energy Utilization
❏ Electricity: kWh/building/year or kWh/sq.ft./year
❏ Peak electrical power: kW/building or W/sq.ft.
40 ❏ Fuel: MMBTU/building or kBTU/sq.ft./year
❏ Purchased thermal energy: MMBTU/building/year or kBTU/sq.ft./year
❏ Total energy: MMBTU/building/year or kBTU/sq.ft./year
❏ Energy cost: $/building/year or $/sq.ft./year based on local or standardized energy prices (provide nomi-
nal and corrected for inflation) post-commissioning
❏ Percent energy use savings (total and by fuel) and total energy cost savings post-commissioning
❏ Persistence index: post-commissioning energy use in a given year/pre-commissioning energy use (unitless
ratio)
Commissioning Cost
❏ $/building or $/sq.ft. (based on nominal costs; can be gross value or net, adjusting for the quantified value
of non-energy impacts)
❏ Commissioning cost ratio for new construction: commissioning cost/total building or renovation con-
struction cost, expressed as a percentage
❏ Costs for CxA and other parties separately
❏ Allocation of costs by source of funds (agency capital funds, utility, grant, etc.)
❏ Total building construction cost (denominator for commissioning cost ratio)
Cost Effectiveness
❏ Undiscounted payback time (commissioning cost/annualized energy bill savings)
❏ Normalized to standard energy prices and inflation-corrected to a uniform year’s currency levels
Deficiencies and Corrections and/or Improvements
❏ Number of deficiencies and improvements per building or #/sq.ft.
❏ Number of combined deficiencies/corrections (per building or per square foot)
Non-Energy Impacts
❏ Type, quantified when possible: $/building/year or $/sq.ft./year
❏ One-time or recurring
Adapted from “The Cost-Effectiveness of Commercial-Buildings Commissioning,” Mills, Evan et. al., December 15, 2004.
Why Commission?

A maintenance program should be


in place (or be implemented) that
IMPACT ON ENERGY CON
includes the following commission SUMPTION
ing-related responsibilities:
Building performance today is com
■ Scheduled reviews of operating promised by a diverse array of
parameters, schedules, and physical deficiencies, as found by
sequences of operation. the Lawrence Berkeley National
■ Scheduled utility bill analysis, or Laboratory team in their study The
use of energy accounting Cost-Effectiveness of Commer
software, to review for unex cial-Buildings Commissioning.
pected changes in building HVAC systems present the most
energy use. problems, particularly air-distribution
■ Condition monitoring, including systems. In addition, sophisticated
vibration analysis, infrared energy management control sys 41
thermography, ultrasonic testing, tems installed in today’s newer fa
motor testing, and lube oil cilities often are not optimized and
analysis, as appropriate, that calibrated properly to deliver the en
tracks and trends condition ergy savings of which they are ca
parameters such as equipment pable.
alignment and balance, vibra
tion, high-resistance electrical Building commissioning is one of the
connections, motor condition, most cost-effective and far reaching
fluid leakage, and lubricant means of improving energy effi
condition. ciency in buildings. In the Lawrence
■ Tracking of scheduled and Berkeley National Laboratory study,
unscheduled maintenance for a sample of 150 existing buildings
each piece of equipment. found an average whole-building en
■ Periodic reviews of mainte ergy savings of 18 percent, with an
nance performance indicators average payback time of less than
and logs to determine if systems
and equipment require
tuning.
■ Building and O&M
documentation updates to
reflect changing building
requirements and equip
ment replacement.
■ Operator training updated
annually.
Why Commission?

one year, when commissioning was cies mandate that new and remod
applied. A sample of 74 new-con eled buildings meet a minimum level
struction projects found an average of sustainable design certification.
payback time of 4.8 years, although One of the most widely adopted pro
the addition of non-energy impacts grams used by the government to
can drastically reduce these pay assess building performance and ad
back times. There are cost-effective herence to sustainable design goals
results to be found in a wide range is the LEED™ (Leadership in En
of building types and sizes. ergy and Environmental Design)
certification system. LEED was
As it relates to energy efficiency created by the U.S. Green Building
goals, commissioning can be seen as Council (USGBC) and is now rec
a form of risk management. It helps ognized and accepted internationally
ensure that funds are spent wisely to assess building performance and
42 and that the intended energy savings adherence to sustainable design
targets are achieved in practice. goals.
Commissioning provides a method
Many Federal agencies man for defining measurable energy per The LEED Green Building Rating
date that new and remodeled
formance targets in the design System is a voluntary, consensus-
buildings meet a minimum
level of sustainable design phase, and for evaluating as-built based national standard for develop
certification. LEED is now and as-operated system conditions. ing high-performance, sustainable
recognized and accepted in buildings. Members of the USGBC,
ternationally to assess build As buildings and energy-efficient representing all segments of the
ing performance and technologies become more complex building industry, developed LEED
adherence to sustainable de and interconnected, the need for and continue to contribute to its evo
sign goals. commissioning to ensure optimized lution. LEED standards are available
energy performance will increase. or under development for:
The Lawrence Berkeley National
Laboratory study asserts that the ef ■ New construction and major
ficacy of energy efficiency pro renovation projects (LEED-NC)
grams is directly related to the ■ Existing building operations
extent to which they are coupled (LEED-EB)
with commissioning and quality as ■ Commercial interiors projects
surance in design and delivery. (LEED-CI)
■ Core and shell property (LEED
LEED CERTIFICATION ■
CS)
Homes (LEED-H) and
More and more government agen ■ Neighborhood development
cies are demanding “green” build (LEED-ND)
ings that incorporate meaningful
strategies for sustainable facility de To achieve a LEED rating, a whole-
sign. building approach must be used.
Credits must be earned in several
To reduce long-term facility costs categories, including site selection
and to become more environmen and configuration, water efficiency,
tally conscious, many Federal agen energy, indoor air quality, and sus
Why Commission?

tainable building materials. In addi- management and preventive


tion, the USGBC recognizes the ef- maintenance for a whole
fectiveness and benefits to building approach to operations,
whole-building efficiency that com- energy efficiency, and sustain
missioning can achieve, making able design.
commissioning a mandatory require
ment for LEED certification. ■ Green buildings that combine
energy efficiency, sustainability,
Understanding the LEED certifica- and commissioning are not only
tion ratings and how to achieve fa- good for the environment – their
cility certification with design, impact on occupant comfort,
construction, and operational credits satisfaction, and safety can
based on the system has become result in serious savings for the
imperative as government agencies facility operator.
look for ways to become more envi 43
ronmentally friendly, conserve en- ■ Resist value engineering
ergy, and decrease the operating commissioning out of projects
costs of their real estate. because of cost. The cost of
commissioning is such a small
Commissioning and the LEED ap- percentage of the overall
proach share a focus on moving be- project cost that it’s removal is
yond a first cost/lowest-cost unlikely to swing a project back
perspective to consider and account into budget. More importantly, it
for long-term, life-cycle building ex- is wrong to compromise quality
penditures. The LEED approach as a result of budget concerns.
considers a building’s real cost,
which includes not only the amount
spent to construct the facility but References
also the ongoing expenses required
for building operations and mainte 1. “The Cost-Effectiveness of Commercial-Buildings Commission-
nance, which can account for 60 to ing,” Mills, Evan, et. al., Lawrence Berkeley National Laboratory,
85 percent of a building’s actual December 15, 2004.
capital expenditures. 2. “Building Commissioning: The Key to Quality Assurance, “U.S.
Department of Energy.
BEST PRACTICES 3. “Persistence of Benefits from New Building Commissioning,”
Friedman, Hannah, et. al., August 2002.
■ Consider life cycle costs in
4. “Development of an Integrated Commissioning Strategy Cost
addition to first costs when
considering commissioning – Model,” Veltri, Anthony, National Conference on Building Com-
much of the value achieved by missioning, May 8-10, 2002.
commissioning comes from 5. “Quantifying the Cost Benefits of Commissioning,” Altwies, Joy E.
avoided costs rather than and Ian B.D. McIntosh, National Conference on Building Com-
quantifying cost savings. missioning, May 9-11, 2001.
6. “No Bugs: Use Commissioning to Make Sure Buildings Work,”
■ Integrate a continuous commis Coyne, Mike, Nashville Business Journal, December 13, 2004.
sioning program with energy
Why Commission?

STUDY QUESTIONS
1. What arguments would you offer to convince the owner that commissioning is the right thing for his facility?

2. What are the standard barriers against the commissioning process?

3. What are ten benefits derived from commissioning and explain how they are beneficial?

44
4. Explain how commissioning reduces the number of change orders in new construction?

5. How does commissioning contribute to new construction acceptance and project turnover?

6. How can commissioning reduce the cost of TAB?

7. How can the O&M program optimize the performance of your facility?

8. How does the LEED certification impact the quality of life of the building occupants?
Commissioning Management

Chapter 4
Commissioning Management

A
n emphasis on team There are three steps to de
building and teamwork veloping a strong internal
will lead to greater suc structure to support commis
cess from the commis sioning: determining the need
sioning process. It fosters a positive for commissioning, obtaining 45
approach to commissioning activi the support of various build
ties, rather than the attitude that the ing stakeholders, and defin
commissioning process creates ing an internal
more work or encourages “looking” commissioning team.
for problems that do not exist. Ef
fective commissioning management Step 1 - Determine the
encourages team members to work
Need for Commission
together to identify problems (exist
ing and potential) and help correct ing
these problems before they grow. Commissioning is becoming
more and more common, but
There are two teams that will be its value should still be care “What you always do before
discussed in this chapter: the inter fully evaluated and management you make a decision is con
nal management team that must be support for commissioning obtained. sult. The best public policy is
in place and prepared to support the For new construction and renova made when you are listening
commissioning process, and the tion projects, commissioning will to people who are going to
commissioning team that is as produce the biggest payoff if the fa be impacted. Then, once
sembled when a project is under cility and its systems/equipment are policy is determined, you
way. call on them to help you sell
very complex (laboratories, tele
it.”
communications, medical), and if the
DEVELOPING COMMISSION facility has a very large square foot Elizabeth Dole

ING STRUCTURE AND


age. Commissioning will not pro
duce the same level of savings for
MANAGEMENT SUPPORT simpler, smaller facilities.

A commissioning program has little In the case of retrocommissioning,


chance of achieving measurable there are several factors to con
success unless its goals and objec sider:
tives are clear and the program has
the full support of your internal ■ Are equipment and systems
management organization. programmed to be replaced
Commissioning Management

In this Chapter
◆ Developing Commissioning Structure and Management Support
◆ Commissioning Authority Options
◆ Commissioning Authority Qualifications
◆ Role and Responsibilities of the Commissioning Authority
◆ Roles and Responsibilities of Commissioning Team Members
◆ Best Practices in Commissioning Management

within a year or two? Hold off management structure to implement


on retrocommissioning until after a successful commissioning pro-
the change-outs are made. gram. One way to gain the approval
46 and support of Management is to
■ Are equipment and systems develop a written statement of com
continually failing, and major missioning objectives, goals, costs,
system design problems seem to and benefits. Approach commission
be the culprit? Forgo retro ing by equating it with increased
commissioning and focus on productivity, energy efficiency,
making commissioning a part of safety, and occupant satisfaction.
a redesign effort.
Commissioning is easier to integrate
■ Are equipment and systems into a new construction or major
outdated but not necessarily renovation project than in existing
broken (and not near the end of buildings. New projects involve sub
their useful life)? Retrocommis stantial capital expenditure, usually
sioning can tune up an old from a separate capital investment
system in a cost-effective budget, and Management will be in
manner. terested in methods of guaranteeing
quality assurance and getting the
■ Are the equipment and building best building for their investment.
systems relatively new but Also, the new construction or major
subject to periodic failure and renovation commissioning process
not operating efficiently? Retro does not involve intensive work on
commissioning can identify and the part of the Owner or facility
prioritize needed equipment O&M staff beyond their involve
repairs and improvements based ment in the project itself.
on their potential return on
investment. Retrocommissioning is more difficult
to sell to Management. Persistent
Step 2 - Obtain Support building equipment and system fail
ures, or energy and operational effi
Federal facility and O&M managers ciency losses are perceived to fall
must obtain full support from their under the scope of the existing
Commissioning Management

O&M program (“Why can’t main efficiency in buildings by as

tenance just fix the problem?”). The much as 15 percent.

following benefits can be outlined to


counter this: ■ Low First Costs –
retrocommissioning is typically a

■ Asset Management – one-time event, and does not

retrocommissioning increases necessarily involve all building

the ability of the O&M staff to systems and equipment. The

provide quality services to the retrocommissioning process

building’s occupants, and the involves evaluating building

building’s net operating income performance and choosing the


Benefits of
increases when it is operated as most high-priority (least effi

Retrocommissioning:
efficiently as possible. cient) systems and equipment

upon which to focus attention.


Asset Management
■ Risk Reduction – 47
Risk Reduction
retrocommissioning identifies Another stakeholder vital to imple
equipment and system deficien menting a successful commissioning Internal Benchmarking
cies that could lead to tenant program is the facility O&M staff. Energy Management
loss, decreased occupant Commissioning for new construction Low First Costs
productivity, reduced equipment and major renovation is again easier
life, reduced indoor air quality, to sell to the O&M staff, as they
“sick building” syndrome, will most likely appreciate thorough
unhealthy effects of mold and training and O&M documentation
mildew growth, and higher on newly installed equipment. For
utility bills. retrocommissioning, it is important
to stress that the process is there to
■ Internal Benchmarking – make their jobs easier, not harder.
retrocommissioning provides a
benchmarking tool for building If commissioning duties are handed
operational performance, over to the O&M organization,
allowing an ongoing record to make sure to stress that these ac
be kept of quality control, and tivities can and should be incorpo
for condition baselining to be rated into their regular preventive
used to measure and ensure maintenance program as part of
maintenance performance. continuous commissioning. If a third
party commissioning provider is
■ Energy Management – hired to perform retrocommission
retrocommissioning provides a ing, assure the O&M staff that the
low-cost method for obtaining process will identify equipment, sys
energy efficiency savings tems, and approaches that are not
without capital outlay (for working as well as they should.
instance, a chiller may not need
to be replaced, but rather its The end result will be a better build
controls recalibrated to optimize ing that is easier to maintain, with
its performance). Retrocommis less trouble calls and more time to
sioning can increase energy proactively implement preventive
Commissioning Management

maintenance tasks. Make the O&M age the process for the Owner.
staff a partner in the commissioning
process. For a new construction or major
renovation project, this team will in
Finally, the needs and desires of the clude the facility management staff
building’s occupants must be consid person who is acting as the Owner’s
ered. Conducting a survey of occu project manager for the project. If
pant satisfaction is a good place to this individual does not want to take
start (and can provide information on the responsibility of monitoring
for Management on areas of dissat the commissioning aspects of the
isfaction that may justify performing project, another person on the facil
retrocommissioning). Building occu ity management staff should be ap
pants will support a retrocommis pointed.
sioning program if it will lead to
48 better thermal comfort, air quality, It is vital that each party involved in
and lighting levels. the project have access to a single
point of contact for commissioning
Step 3 - Define an Internal issues who is also the Owner’s rep
resentative. In addition, a lead con
Commissioning Team
tact should be appointed from the
When the need for commissioning facility O&M organization to coordi
has been recognized and accepted nate O&M activities related to com
by Management, O&M, and occu missioning.
pants, define a team that will man
For a retrocommissioning project,
representatives from facility man-

Tip: Build a Building Performance Team


Many Federal agencies have voluntary energy management teams
at their facilities: groups representing different stakeholders that meet
and share ideas on improving energy efficiency. Consider expanding
this idea to overall building performance.

Solicit volunteers from Management, O&M, and tenants to meet pe-


riodically to discuss problems (such as comfort and safety) and op-
portunities to address these problems while increasing the building’s
energy and operational efficiency. To motivate participants, consider
applying for LEED™-EB or ENERGY STAR Label for Building certification:
both programs incorporate commissioning and provide public rec-
ognition for efficiency improvements.
Commissioning Management

agement and O&M should develop Owner and offers the most objec
an organization and define duties tive perspective of any of the other
based on the size and scope of the CxA options described in this sec
project. If a third party CxA is tion.
hired, facility management and
O&M should each provide the CxA For large or complex projects, and
with a single point of contact. in buildings with highly integrated
and sophisticated systems, potential
COMMISSIONING savings resulting from objective
commissioning will likely outweigh
AUTHORITY OPTIONS the cost of employing an indepen
dent third party commissioning pro
Put most simply the Commissioning vider. And in existing buildings, an
Authority (CxA; also sometimes independent third party CxA brings
called Commissioning Agent) is the a new perspective to the building, 49
designated person or company that has no investment in existing main
plans, coordinates, and oversees the tenance approaches, and therefore
commissioning process. This person may be more likely to find additional
or company directs the day-to-day opportunities for improvements and
commissioning activities of the savings.
project. The CxA does not have a
direct oversight role, like the con An independent third party provides
struction manager, but rather in an autonomous and independent
forms installing contractors, the judge of quality with minimum pos
construction manager, and the sible conflicts of interest.
Owner of observed deficiencies.
Mechanical or Electrical
There are several options for ob Contractor
taining the services of a CxA for a
project: Most appropriate for:
◆ Retrocommissioning of specific
systems (e.g., HVAC or
Independent Third Party electrical systems)
Most appropriate for: ◆ New construction or renovation
◆ New construction or major involving less than 20,000
renovation projects, square feet
retrocommissioning, and
recommissioning of all building Mechanical and electrical contract
types and system complexities ing firms may already perform com
prehensive performance tests and
An independent third party CxA is diagnostic procedures for equipment
the most common option for provid and systems they install. Expanding
ing commissioning services today, the scope of work of the mechani
and the one most often utilized and cal or electrical contractor to in
recommended by Federal agencies. clude commissioning is an
This person or firm is hired by the alternative when the project is small
Commissioning Management

and the requirements of commis greater cost advantage as the com


sioning already detailed clearly in the plexity and size of the project grows.
project specifications. Commissioning costs are not gener
ally included in the A/E’s profes
There are significant drawbacks to sional fee, so the scope of work and
consider, though. Contractors may bid specifications for the project de
have the knowledge to test the sign team will need to be expanded
equipment they install, but they may to include commissioning to ensure
not have experience in testing or di that the associated costs are cap
agnosing system integration prob tured in the A/E’s bid.
lems. Further, conflicts of interest
may arise from a mechanical or The biggest drawback to using the
electrical contractor appraising his A/E as the CxA is that the firm may
own work, as identifying deficien not have adequate experience in
50 An independent third party cies found through commissioning day-to-day construction processes,
provides an autonomous and may increase the contractor’s troubleshooting, and systems testing
independent judge of quality project costs. required to effectively provide com
with minimum possible con missioning services. Also, conflicts
flicts of interest. Another closely related option, with of interest may arise during the de
the same advantages and draw sign phase, as identifying potential
backs, is an independent division or design problems may increase the
subsidiary of the construction man A/E’s project costs. However, the
ager, mechanical contractor, or elec design professional has a fiduciary
trical contractor, an option that may relationship to the Owner and is le
be available from a substantially gally bound to act in the Owner’s
large contractor. best interests.

Design Professional In-house Facility Personnel


Most appropriate for: Most appropriate for:
◆ New construction or major ◆ Recommissioning and continu
renovation commissioning ous commissioning
involving more than 20,000
square feet, with complex Choosing to have in-house facility
design considerations management and O&M personnel
assume commissioning responsibili
A design firm (architect/engineer, or ties can be cost-effective and have
A/E) is typically already on board persistent results, particularly if your
when considering commissioning for facility already has progressive pre
a large, complicated new construc ventive maintenance and quality as
tion or major renovation project. surance programs in place
(continuous commissioning can be
The advantage of this option is that integrated easily into existing main
the A/E is already familiar with the tenance programs, for instance). In
design intent of the project, which house staff knowledge of equipment,
somewhat reduces the costs of systems, controls, operating strate
management. This presents a gies, and maintenance procedures
Commissioning Management

Are You Considering Bringing Commissioning In-House?


Most facility owners and managers find that the benefits of employing a highly qualified third party commis-
sioning authority outweigh the costs.
But in the case of continuous commissioning, recommissioning, and some retrocommissioning projects, it
may be most economically feasible to hire or appoint a Commissioning Manager to work in-house. Assigning
or hiring this role sends a message to the O&M staff that the commissioning program being undertaken is a
high priority for the organization, and gives facility management a go-to person to monitor and track progress
resulting from the commissioning program.
The Commissioning Manager hired or appointed must have a background in commissioning and condition
acceptance testing, and should have the skill and desire to develop and carry out all aspects of the commis-
sioning program.
51
If hiring or appointing a Commissioning Manager is cost prohibitive, consider hiring a qualified third party CxA
to develop and deliver a training program on the commissioning process and systems testing to your O&M
staff.

can minimize costs. The O&M staff available before commissioning


may already perform many of the should be considered.
tests required by recommissioning
and continuous commissioning. CXA QUALIFICATIONS
Familiarity with their own building Qualifications for the CxA will vary
can be a serious drawback to using depending on the type of commis
in-house facility management and sioning and size and scope of the
O&M staff to provide commission project. At a minimum, the CxA
ing services, however. In-house (which can be an individual or a
staff may be too “close” to how the company) should possess knowl
building currently operates to be edge and experience with develop
able to test and evaluate with full ing commissioning test plans and
objectivity. Additional training on directly coordinating and overseeing
testing for system integration may the commissioning process in prac
be required, as well as training on tice.
the full operational potential of so
phisticated building automation and The CxA qualifications presented in
energy management control sys this section should be modified to fit
tems. Finally, there should be some each particular project, but provide
incentive offered for assigning com a good start for evaluating CxA
missioning activities beyond regular candidates.
maintenance duties; the staff must
be experienced, motivated, and
Commissioning Management

CxA Qualifications
The individual or firm may also meet
The individual or firm should demon- the following optional requirements:
strate knowledge and experience in
the following areas: 1. Excellent verbal and writing
communication skills.
1. Designing, specifying, and/or 2. Highly organized and able to
installing building HVAC and work effectively with the
mechanical control systems. building management, design
2. Operation and troubleshooting team, installing contractors, and
of HVAC systems, energy the O&M staff.
management control systems, 3. Education and professional
and lighting controls systems, registration – the individual, or in
including field experience. the case of a company the lead
52 3. Controls systems, control individual proposed by the firm,
sequences, and integrated should have bachelor’s degree
operations. in an applicable area
4. Performing condition (mechanical engineering,
acceptance testing to detect electrical engineering, etc.), as
latent manufacturing, well as either Professional
transportation, and installation Engineer licensure or other
defects. technical training and past
5. Writing functional performance commissioning and field
test plans. experience.
6. Designing energy-efficient 4. Depth of experienced, qualified
equipment and systems and personnel, and capability to
optimizing control strategies. sustain loss of assigned
7. Providing building operation and personnel without compromising
maintenance and O&M training. quality and timeliness of
8. Testing and balancing of both air performance.
and water systems. 5. Status as an independent
9. Monitoring and analyzing contractor – the individual or
system operation using energy firm chosen to provide
management control system commissioning services should
trending and stand-alone data not be an employee or
logging equipment. subcontractor of the general
10. Testing instrumentation. contractor, construction
11. Inspecting and testing electrical manager, design team, or any
power distribution and other contractor on the project.
generation equipment and
systems. The Past Experience Evaluation
12. Developing quality processes form provided on the following page
and preventive maintenance provides a helpful guide to evaluat
approaches. ing the experience and qualifications
13. Familiarity with LEED point of the CxA candidate. Also be sure
criteria and requirements. to ask for specific project experi
Commissioning Management

Past Experience Evaluation


The following questions should be asked when evaluating the CxA candidate’s past experience providing
commissioning services (and should be modified to fit each particular project). These questions can apply
to individuals or companies:

1. What is the overall percentage of your business that is devoted to providing commissioning services?

2. How long have you offered commissioning services?

3. How many commissioning projects have you performed in the last five years? How many commission-
ing projects similar in size and scope to the project being procured have you performed in the last five 53
years?

4. If applicable, how many LEED projects have you commissioned in the last five years?

5. Are you a registered engineer (individual)? How many registered engineers on staff have directed
commissioning projects (company)?

6. How many engineers on staff have performed commissioning projects (company)?

7. How many technicians on staff have performed commissioning projects (company)?

8. Indicate your experience in the following:

❏ Package or split HVAC ❏ Building envelope


❏ Chilled water systems ❏ Fire and life safety
❏ Heating water systems ❏ Plumbing
❏ Building automation systems (BAS) ❏ Elevators
❏ Variable frequency drives (VFD) ❏ Compressed air systems
❏ Lighting controls ❏ Data and communications
❏ Daylighting ❏ Steam systems
❏ Electrical ❏ Clean rooms
❏ Occupancy sensor (lighting controls) ❏ Steam rooms
❏ Energy power generation ❏ Other:
Commissioning Management

ence information if your project in- the CxA’s primary tasks generally
volves complex system require- include the following:
ments, such as those found in
laboratories, medical facilities, tele- ■ Developing a commissioning
communications, computer rooms, plan. This includes a preliminary
etc. commissioning schedule for
inclusion with the bid documents
ROLE AND RESPONSIBILITIES and coordinated with the
construction schedule.
OF THE CXA
■ Preparing commissioning
It is the CxA’s responsibility to work specifications that identify the
with all team members to accom- roles and responsibilities of all
plish the goals set forth in the com- contractors and project team
54 missioning plan. The CxA is not members. This includes helping
responsible for design concept, de- the Owner’s representative
sign criteria, compliance with codes, incorporate commissioning
design, or general construction specifications in the bid docu
scheduling, cost estimating, or con- ments.
struction management. The CxA
may assist with problem-solving de- ■ Reviewing design and construc
ficiencies or non-conformance, but tion documents, drawings, and
ultimately that responsibility resides submittals for commissioning
with Owner and the construction and O&M considerations, as
manager/general contractor. well as for energy performance,
water performance, maintain-
The primary role of the CxA is to ability, sustainability, indoor
develop and coordinate the execu- environmental quality, and
tion of a testing plan, and to observe environmental impacts. This
and document performance to verify includes providing comments to
that systems are functioning in ac- the Owner and A/E and con
cordance with the documented de- ducting follow-up meetings to
sign and the contract documents. ensure that comments are
The installing contractors provide all addressed.
tools or the use of tools to start,
verify, and functionally test equip- ■ For retrocommissioning projects,
ment and systems, except for speci- performing an assessment of
fied testing with portable operation and maintenance
data-loggers that are supplied by the procedures and energy use for
CxA. existing systems. This includes
providing an assessment of
Although the scope of the CxA’s various systems’ operational
role varies for different types of costs relative to maintenance
projects (new construction commis- and utilities, including equipment
sioning, retrocommissioning, etc.), life cycle and project energy
savings.
Commissioning Management

■ Conducting commissioning contractor and vendor responsi


team meetings and providing bilities as defined by the con-
meeting minutes, including tract documents, including
project coordination and commissioning criteria, proce
contractor schedules. This dures, report formats, functional
includes ensuring that other performance testing and
commissioning team members acceptance criteria, bench-
understand their specified marking installations, documen
commissioning responsibilities. tation, and training require
ments. This includes notifying
■ Establishing project communi- commissioning team members
cation and documentation of these requirements.
controls and protocols relative
to commissioning. ■ Developing diagnostic test
plans, writing verification and 55
■ Identifying and documenting functional performance test

Commissioning Documentation
The requirements of commissioning documentation vary widely depending on the type of commis-
sioning project. Documentation that is vital to the commissioning process, and should be required by
the owner depending on project scope, include:
◆ Pre-construction deficiency list and impact
◆ Commissioning plan, updated as the project progresses
◆ Complete commissioning specification describing commissioning activities and roles and re-
sponsibilities of all parties
◆ Current and updated commissioning schedules
◆ Test forms and report formats
◆ Final commissioning reports
◆ Equipment condition baseline data for on-going maintenance
◆ Contractor performance evaluation reports
◆ Documentation pertaining to benchmarking, testing, and
training
◆ Deficiency reports, updated weekly
◆ Equipment and systems O&M cost report identifying im-
pact to the project and facility
◆ Updated as-built drawings
◆ Systems manuals
◆ Operation and maintenance manuals
Commissioning Management

forms, and establishing testing cies, deviations, change orders,


schedules and sequences. and maintainability issues. This
includes monitoring A/E re
■ Overseeing and witnessing sponses to requests for informa
start-up, verification, and tion (RFI) and change orders for
functional performance tests; potential impact on system
verifying test results; consulting operation and maintenance, as
on problem resolution; providing well as tracking and reporting on
recommendations and dispute commissioning punch list items.
resolution; and recommending
acceptance to the Owner. These items should be compiled
and submitted as periodic
■ Assisting the Owner and A/E in commissioning progress reports
finding and achieving the to the Owner’s representative
56 requisite points needed for and the project construction
LEED certification, as appli manager.
cable.
■ Reviewing operation and
■ Coordinating and overseeing all maintenance manuals; ensuring
testing and balancing (TAB) and that they adequately consolidate
duct pressure testing. This all O&M, as-built, warranty, and
includes reviewing and approv commissioning data.
ing preliminary and final TAB
reports. ■ Identifying training requirements
and organizing, coordinating, and
■ Tracking and reporting project participating in O&M personnel
progress, including all deficien training.

■ Writing a final commissioning


report to document the evalua
tion of the system’s capabilities
with respect to the Owner’s
needs and the documented
design intent.

■ Coordinating and supervising


required seasonal and deferred
testing and deficiency correc
tions.

■ Performing a site visit 10


months into the 12-month
warranty period to review with
O&M staff the current building
operation and the status of
outstanding issues related to the
Commissioning Management

original and seasonal commis has important roles to play that help
sioning. This includes: determine the success of the com
missioning program.
- Interviewing facility staff
and identify problems or All parties of the commissioning
concerns they have operat team are responsible for ensuring
ing the building as originally that equipment and systems are in
intended. stalled in a quality manner and that
any problems are identified as early
- Making suggestions for as possible. Each individual worker
improvements and record has the authority and responsibility
ing any changes into the to identify poor quality workmanship
O&M manuals. and to recommend stopping work if
serious problems are discovered.
- Identifying areas that may 57
come under warranty or A commissioning team differs from
under the original construc the construction team, as it is made
tion contract. up of representatives from various
organizations and trades that serve
- Assisting the facility staff to as commissioning points of contact.
develop reports, documents The participants will vary: a retro
and requests for services to commissioning project may involve
remedy any outstanding only the Owner and/or facility man
problems. ager and the facility O&M staff,
while a new construction or major
■ If requested, assisting in the renovation commissioning team will
development of a preventative expand to include the design team
maintenance plan, a detailed (A/E), construction manager or gen
operating plan, an energy and eral project manager, installation
resource management plan, contractors, controls contractor, and
and/or as-built documentation. TAB contractor.

ROLES AND RESPONSIBILI A commissioning scoping meeting is


the first step to establishing the
TIES OF OTHER commissioning team. The CxA, act

COMMISSIONING TEAM
ing as a representative for the
Owner (and with the Owner’s in
MEMBERS put) will use this meeting to describe
each commissioning team members’
The CxA is responsible for the suc roles and responsibilities. The com
cess of the commissioning program, missioning process is described, and
but the formation of a committed the schedule for commissioning ac
commissioning team is critical for tivities is presented.
integrating the commissioning pro
cess into the project at hand. Each The CxA should review the scope
member of the commissioning team of the project and advise the Owner
Commissioning Management

on how roles may be modified ac A/E Design Team


cording to the complexity and size of An architect/engineer (A/E) design
the project. Therefore, the roles and team is normally not used for exist
responsibilities presented in this sec ing building commissioning projects,
tion are general suggestions, and but is a vital team member in new
should be modified to fit the unique construction and major renovation
requirements of each commissioning projects. Specific commissioning re
project. sponsibilities include:

Owner/Facility Manager ■ Documenting the Owner’s


The Owner, or the facility manager design intent.
acting as the Owner’s representa ■ Including commissioning activi
tive, is responsible for appointing the ties in the bid specifications.
CxA, developing goals for the com ■ Providing any design narrative
58
missioning project, and communicat and sequences documentation
ing these goals to the other requested by the CxA.
commissioning team members. Spe ■ Clarifying (along with the
cific commissioning responsibilities installing contractors) the
All parties are responsible include: operation and control of com
for ensuring that equip missioned equipment in areas
ment and systems are in ■ Hiring or appointing the CxA where the specifications, control
stalled in a quality manner and other members of the drawings, or equipment docu
and that problems are project team. mentation are not sufficient for
identified as early as pos ■ Determining and clearly com writing detailed testing proce
sible. municating to the A/E and CxA dures.
the building project expectations, ■ Revising project design, if
objectives, and focus. necessary, based on input from
■ Working with the CxA to define CxA design review on commis
the goals of the commissioning sioning and O&M consider
program. ations, energy performance,
■ Determining the project budget, water performance, LEED
schedule, and operating require certification, maintainability,
ments. sustainability, indoor environ
■ Assigning commissioning roles mental quality, and environmen
and responsibilities to the in tal impacts.
house O&M staff. ■ Monitoring construction activi
■ Facilitating communication ties and informing commission
between the CxA and other ing team members of change
project team members. orders and A/E responses to
■ Approving verification and RFIs.
functional performance tests ■ Documenting any new systems
upon completion (and as recom and controls.
mended by the CxA). ■ Reviewing and approving
■ Attending O&M training project documentation, including
sessions, as appropriate. shop drawings, operation and
Commissioning Management

maintenance manuals, submit functional performance, and


tals, and as-built drawings. conditioning acceptance tests.
■ Reviewing the commissioning ■ Working with the CxA to
plan and functional perfor compile and organize O&M
mance test plans for design documentation and coordinate
issues. O&M training sessions.
■ Working with the CxA to
Construction Manager/General prepare O&M manuals, includ
Contractor ing clarifying and updating the
original sequences of operation
The construction manager (CM) or
to as-built conditions.
general contractor (GC) is hired by
■ Ensuring that installing contrac
the Owner to manage and construct
tors execute seasonal and
the project. Like the A/E, the CM/
deferred functional perfor Condition acceptance testing
GC is not used normally for existing
mance testing, and that any includes vibration analysis, 59
building commissioning projects, but
necessary adjustments are alignment, balance, infrared
is a vital team member in new con
made to the O&M manuals and thermography, oil analysis,
struction and major renovation
as-built drawings for applicable etc.
projects. The CxA represents the
issues identified in during
owner, but on the project communi
seasonal and deferred testing.
cates directly with the CM/GC.
Specific commissioning responsibili
ties include: Installing Contractors
Installing contractors (mechanical,
■ Coordinating and facilitating electrical, controls, HVAC, fire pro
interaction between the com tection, etc.) have the following
missioning team and other commissioning responsibilities:
project team members.
■ Providing a copy of all con ■ Assisting with the development
struction documents, addenda, of functional performance tests.
change orders, approved ■ Along with the A/E, clarifying
submittals, and shop drawings the operation and control of
related to commissioned commissioned equipment in
equipment and systems to the areas where the specifications,
CxA. control drawings, or equipment
■ Including written requirements documentation are not sufficient
for submittal data, O&M data, for writing detailed testing
commissioning activities, and procedures.
training when hiring installing ■ Using test plans and forms
contractors, and ensuring that provided by the CxA for
each installing contractor meets equipment and system start-up,
these requirements as the verification, functional perfor
project progresses. mance, and condition accep
■ Working with the CxA and tance testing (performed by the
installing contractors to coordi installing contractor and wit
nate and schedule verification, nessed by the CxA).
Commissioning Management

■ Participating in the resolution of nating training by the


equipment or system deficien manufacturer’s representative).
cies, non-compliance, and/or ■ Participating in seasonal and/or
non-conformance identified deferred testing.
during commissioning; providing
re-testing services if needed. Equipment and Systems
■ Attending commissioning team Suppliers/Manufacturers
meetings and providing input into
The suppliers and manufacturers
the commissioning schedule.
provide specified systems, compo
■ Adjusting building systems and
nents and equipment to the contrac
documenting system start-up.
tor and subcontractors. To facilitate
■ Providing complete operation
commissioning, suppliers and manu
and maintenance manuals for
facturers should be asked to conduct
installed equipment as soon as
factory and site performance tests
60 all of the submittal documenta
and provide O&M documentation
tion has been approved (at or
and training for specific equipment.
about 60 percent project
Specific commissioning responsibili
completion).
ties include:
■ Providing training for the
building O&M staff (or coordi
■ Providing all requested submittal
data, including detailed start-up
procedures and specific respon
The Contributions of Building Occupants sibilities, to keep warranties in
and Users Are Invaluable force.
■ Assisting with equipment testing
On a project to commission a building at a U.S. Armed Forces if required by (and per agree
service academy, representatives from the intended building ment with) installing contractors.
occupants and users participated in a series of commissioning ■ Providing any special tools and
meetings during the early project planning and design stages. instruments (only available from
vendor, specific to a piece of
equipment) required for testing.
They provided valuable information and insight that could have
otherwise required costly change orders or post-
project modifications. Examples include the court-
room staff identifying the mandated location of an
evidence vault, which required special flooring struc-
tural reinforcement and extraordinary security modi-
fications; occupants pointing out that the planned
dumpster pad/loading dock location is below and
downwind of the building’s proposed conference
area and ventilation outside air intake; and occu-
pants and users identifying preferred locations for
copy machines because of noise and kitchen/mi-
crowave oven areas because of odors, noise, and
accessibility.
Commissioning Management

■ Providing information requested planning meetings (as the design in


by the CxA regarding equip tent and early design layouts are de
ment sequence of operation and veloped) to identify special
testing procedures. requirements and concerns to the
■ Reviewing test procedures for owner.
equipment installed by factory
representatives.
■ Providing detailed O&M
BEST PRACTICES IN
manuals and related information COMMISSIONING
MANAGEMENT
specific to the installed equip
ment and systems as soon as all
of the submitted documentation
■ Build the team to succeed – the
has been approved (at or about
importance of a well-defined
60 percent project completion).
internal commissioning manage
61
ment team and an integrated
Facility Operations and project commissioning team
Maintenance Staff cannot be overstated.
The building O&M staff provide
continual services to effectively op ■ Make facility management
erate and maintain building systems, staff, O&M staff, and building
subsystems, and equipment. Spe occupants stakeholders in
cific commissioning responsibilities building performance, and solicit
include: their input into the commission
ing process.
■ Assisting where required in
defining and reviewing main ■ Set commissioning goals with
tainability requirements in the input from your internal com
design intent and defining missioning management team in
training requirements in the areas of operations and mainte
commissioning plan and specifi nance, safety and comfort,
cations. energy efficiency, sustainable
■ Observing and assisting with as design, and LEED certifica
much of the functional perfor tions.
mance and condition accep
tance testing as possible, and ■ Make careful evaluation of your
using the baseline data collected new construction project,
to establish or refine the renovation project, or existing
maintenance program. building to determine the
■ Attending all O&M training appropriate level of commis
sessions. sioning for the various systems
and equipment.
Building Occupants and Users
■ In almost all cases, hire a
A representative of each building
occupant and user organization qualified, independent third
should participate in early project party CxA through a competi
Commissioning Management

tive bid process. Consider thorough training on commis


carefully their approach, qualifi sioning processes and systems
cations, and what they have to testing procedures.
offer in terms of expertise,
inclusions, and deliverables. ■ Facilitate the integration of
Carefully weigh the drawbacks commissioning into the normal
if choosing to obtain commis design and construction process
sioning services through a for new construction or renova
different option. tion projects in order to minimize
potential scheduling conflicts
■ If assigning any commissioning and time delays.
duties to the O&M staff, or
instructing the O&M staff to ■ Foster teamwork and coopera
add continuous commissioning tion from all commissioning
62 and/or condition monitoring team members to minimize
elements to the O&M program, adversarial relationships and
make sure that they receive maximize teamwork.

References
1. “Building Commissioning: The Key to Quality Assurance,” U.S. Depart-
ment of Energy.
2. “A Practical Guide for Commissioning Existing Buildings,” Haasl, Tudi
and Terry Sharp, April 1999.
3. “O&M Best Practices: A Guide to Achieving Operational Efficiency,” Sullivan,
G.P. et. al., May 2002.
4. “15 O&M Best Practices for Energy-Efficient Buildings,” Portland Energy
Conservation, Inc. December 1999.Best Practices in Commissioning Man-
agement.
Commissioning Management

STUDY QUESTIONS
1. Occupants in an existing 20-year old, 100,000 square foot building are complaining about poor indoor air
quality conditions (temperature and humidity). Private space heaters are common during the winter, mold
is apparent on some exterior walls, and documents occasionally get damaged from moisture dripping from
duct systems. These problems have been pretty continuous for at least a year and little seems to be done,
in the occupants’ eyes, to mitigate the situation. What are some situations where retrocommissioning
would not be appropriate?

2. Recognizing that commissioning adds up-front cost to the project, what do O&M managers have to do to
gain the support of their management organization to commission their facilities?

63
3. Why is retrocommissioning of existing buildings commonly more difficult to sell to Management than is
commissioning of new buildings?

4. What are five points that can be made to management to counteract the “Why can’t maintenance just fix the
problem?” mentality?

5. What are the qualifications a Commissioning Authority should possess?

6. Discuss the questions you would ask a Commissioning Authority candidate.

7. What are the benefits and drawbacks of performing commissioning services in-house with your existing
operations and maintenance team acting as Commissioning Authority?

8. What are the aspects of a new construction or renovation project for which the CxA is not responsible?

9. How does the commissioning team differ from the construction team?

10. Define the role of the Owner or facility manager in the commissioning process.

11. On your new building commissioning project, who would you include as your commissioning team mem-
bers, and why?

12. Who would you have on the team to retrocommission an existing building system(s), and why?
Commissioning Management

64
This page left blank intentionally

Commissioning Process

Chapter 5
Commissioning Process

T
he overall responsibility facility Management
of the Commissioning and O&M staff. If
Authority (CxA) during this is your case, the
any and all phases of a CxA will indicate
commissioning project is to coordi the senior 65
nate and direct the commissioning member(s) of your
activities in a logical, sequential, and facility Manage
efficient manner. This is done using ment/O&M staff
consistent protocols and forms, cen that is assigned the
tralized documentation, clear and duties of the CxA.
regular communications, and con Recommendations
sultations with all involved parties. on hiring a CxA
consultant versus
The commissioning approaches de bringing CxA duties
scribed in this guide are as different in-house are provided for each type “The pessimist sees difficulty
as they are similar. This chapter of commissioning. in every opportunity. The op
breaks each commissioning ap timist sees the opportunity in
every difficulty.”
proach down by phase.
COMMISSIONING FOR NEW Winston Churchill
As used in this chapter, Owner can CONSTRUCTION AND RENO
refer to the building owner, the
owner’s project manager or techni VATION
cal representative, and/or the facil
Commissioning is a systematic pro
ity manager. It is any person who is
cess of ensuring that all building
authorized to make decisions re
systems and equipment installed as
garding the commissioning project
part of new construction or renova
and regularly communicates with
tion perform interactively according
the other project team members on
to the design intent and the owner’s
the owner’s behalf.
operational needs. This is achieved
Commissioning Authority (CxA)
generally refers to an independent, This chapter describes the process for implementing commis-
third party commissioning provider. sioning in new construction and major renovation projects. Chap-
In some instances, it is cost effec ter 6 covers the retrocommissioning process, Chapter 7 covers
tive and appropriate to assign the the recommissioning process, and Chapter 8 covers continuous
duties of the CxA to the qualified commissioning.
Commissioning Process

In this Chapter
◆ Commissioning for New Construction and Renovation
◆ Pre-Design Phase
◆ Design Phase
◆ Installation / Construction Phase
◆ Acceptance Phase
◆ Post-Acceptance Phase
◆ Best Practices

by beginning in the design phase of a Duties related to commissioning are


construction project with the docu- performed by the owner during the
66 mentation of design intent, and con- project pre-design phase. The owner
tinuing through construction, hires the architect/engineer (A/E)
acceptance, and the warranty period design team and works with the A/E
with actual verification of perfor to determine the design intent and
mance. The commissioning process project objectives.
encompasses and coordinates the
traditionally separate functions of The Owner also determines the
system documentation, equipment commissioning requirements for the
startup, control system calibration, project (Will commissioning be part
testing and balancing, performance of all phases of the construction
testing, and training. project? Will the CxA be brought in
only during installation?). The
Commissioning typically follows the Owner then hires the CxA, prefer
phases of the new construction or ably through a competitive process.
renovation project. Although it is not
necessary to perform commissioning The Owner’s criteria is the only
tasks during each phase of construc commissioning-related documenta
tion, implementing the process tion that is developed during pre-de
throughout the life of the project will sign. This document captures
produce the best results. These requirements of the project, includ
phases, described in detail in this ing design objectives and con
section, are 1) Pre-design, 2) De straints; space, capacity, and
sign, 3) Installation / Construction, 4) performance requirements; flexibility
Acceptance, and 5) Post-accep and expandability requirements; and
tance / Warranty. budgetary limitations. The Owner’s
criteria is used by the A/E to de
PRE-DESIGN PHASE velop the formal design intent and
basis of design documentation, and
Documentation Requirement: is also used by the CxA to review
◆ Owner’s Criteria the design documentation.
Commissioning Process

The starting point for developing the


design intent and basis of design is
the identification of the Owner’s
needs. The design team needs to Commissioning Process
accurately interpret and record the
Owner’s vision of the facility itself,
how the facility will be used and op Pre-Design
erated, and the Owner’s perfor Determine project objectives and commissioning
requirements
mance goals and objectives. This Develop Owner's criteria
vision must be realistic and consider Determine CxA
budget restraints, schedules and
other limitations.

Technically, considerations should


include the use of the facility, the Design 67
user needs, occupancy require CxA reviews design intent, basis of design, drawings and
ments, the type of construction, sys provides feedback to A/E
CxA develops commissioning plan and commissioning
tem functions, the expected specifications
performance criteria (e.g., energy,
air quality, power quality, security,
and biohazard and environment),
maintainability, supportability, reli
ability and simplicity.
Installation / Construction
CxA develops all test forms and checklists
The Owner will expect the A/E to CxA works with installing contractors to verify start-up and
deliver a design that meets the perform verification checks
Owner’s identified requirements.
The owner will expect the contrac
tor to build the facility in a work
manlike manner in accordance with
general accepted construction prac
tices, to use quality materials that Acceptance
CxA works with installing contractors to perform functional
are defect-free, to deliver the work performance tests
on schedule at the agreed price, and Deficiencies are reported, systems and equipment are
retested until they pass
to pay the contractor’s subcontrac CxA reviews and verifies O&M manuals and staff training
tors and suppliers in a timely man
ner (no liens).

DESIGN PHASE Post-acceptance / Warranty


CxA conducts site visit at 10 months
Deferred and/or seasonal testing is performed
Documentation Requirements: CxA prepares final commissioning report
◆ Project Objectives Document
◆ Design Documentation –
Design Intent, Basis of Design,
Drawings
Commissioning Process

◆ Project and Commissioning the project design for commissioning


Specifications considerations. The CxA may also
◆ Commissioning Plan (draft) coordinate input from the facility us-
ers and occupants regarding building
During design, the A/E designs the features that are of importance to
project and produces design docu- them for integration into the design
mentation, while the CxA reviews documentation. The CxA’s pres-

Maintainability Factors
1. Accessibility – Consider access to machine room, machine, and machine compo-
nents.
68
2. Visibility – Is the component visible from the floor? Nameplate data? Shadow ef-
fects?
3. Simplicity – Keep it simple; the more complex, the more difficult and costly.
4. Interchangeability – In an emergency, it is nice to “borrow” a critical part from a less
critical component to keep operations up and running.
5. Standardization – Fewer manufacturers and models minimizes spare parts, train-
ing, and special tooling.
6. Ease of Monitoring and Testing – Where are the test points located? Gauges?
Meters?
7. Human Factors – Can the parts be lifted? Should a chainlift be installed to assist
removal of over-sized components, if needed?
8. Safety Concerns – Always paramount.

Supportability Factors
1. Parts Availability – Minimize repair time; con-
sider if parts are locally available or can be or-
dered via internet for next day delivery. Consider
the impact if parts must be special ordered or
customized?
2. Repair Capability – Minimize repair time and
cost; consider availability of local repair capa-
bility. Does a representative need to be flown in
from across the country?
3. Training and Skills – Ensure that training and
education is available commensurate with the
complexity of the equipment being installed.
4. Technical Data – Ensure that all technical sup-
port data is available and provided.
Commissioning Process

ence at bre-bid and pre-construction of the building systems. This allows


conferences acquaint potential con team members to perform their re
tractor personnel with the commis spective responsibilities regarding
sioning process. the design, construction, and opera
tion of the building.
Project Objectives Docu
Design documentation consists of
ment
design intent and basis of design,
The project objectives document is and the detail of both increases as
prepared by the CxA. This docu the design process progresses. At
ment is based on the Owner’s Cri the outset of the project, the design
teria, and it identifies project documentation required is primarily
requirements relative to energy per a narrative of the building system
formance, water performance, descriptions, objectives, and how the
LEED certification intentions, main systems will meet those objectives. 69
tainability, sustainability, indoor envi As the design process progresses,
ronmental quality, and the design documentation includes
environmental impacts. This docu the basis of design, a specific de
ment is used by the CxA as a guide scription of the systems and compo
when performing design review for nents, their function, how they relate
commissioning. to other systems, sequences of op
eration, operating control param
Design Documentation eters, and the assumptions made in
the design.
Design Intent and Basis of
Design The A/E coordinates the integration
of design documentation from each
The design documentation provides
contributing designer to develop the
a narrative description of the sys
full design documentation by the de
tem or issue, as well as clear and
sign team. The A/E, CxA, and
useful background information. De
Owner each review, comment on,
sign documentation explains how
and approve the submissions.
design and operating objectives will
be accomplished. Design documen
The approved full design intent and
tation includes information from the
basis of design is provided to the
conceptual design phase and from
CxA at the beginning of the con
the design and construction pro
struction phase for use as a guide
cesses, necessary to guide the de
and baseline reference during start
sign, verify compliance during
up, verification, and functional per
construction, and aid building opera
formance testing. Since the job of
tions.
the CxA is to assure that compo
nents and systems have been in
Identifying and developing the de
stalled and operate as intended per
sign intent and basis of design pro
the Owner’s needs, the CxA needs
vides each party involved, at each
both the Design Intent, based on the
respective state, an understanding
A/E’s knowledge of the Owner’s
Commissioning Process

needs, and the design itself that 8. Restrictions and limitations of


shows the specified solution. A final system or facility.
as-built copy of the full design intent 9. Special considerations, such as
and basis of design should be pre pursuit of LEED-(level) certifi
pared and included in the O&M cation.
manuals at the end of the construc
tion phase. The design intent should also include
design criteria, including at a mini
Design intent documentation for mum:
other systems and components, such
as structural, interior design, land 1. Indoor dry bulb temperature and
scaping, furnishings, etc. may also relative humidity.
be required, although not a part of 2. Outdoor dry bulb and wet bulb
the commissioning process. This temperatures.
70 should be decided on a project-by 3. Occupancy, hours of operation,
project basis. and degree of activity.
4. Lighting and miscellaneous
Design Intent power.
The design intent provides an expla 5. Ventilation - recirculation and
nation of the ideas, concepts, and outside air.
criteria that are considered to be im 6. Internal and special loads.
portant to the owner. It is initially the 7. Insulating R-values for roof,
outcome of the conceptual design wall, glass, etc.
phase. The design intent narrative 8. Percentage of glass - fenestra
should cover the following, for each tion, and types of glass, including
system, major component, facility, coatings and solar coefficients.
and area: 9. Building pressurization and
infiltration.
1. General system description. 10. Building mass.
2. Objectives and functional use of 11. Code requirements and impact
the system, equipment, or on criteria.
facility. 12. Air quality design criteria, i.e.,
3. General quality of materials and ASHRAE 62-91.
construction. 13. Noise criteria.
4. Occupant requirements. 14. Fire and life safety.
5. Indoor environmental quality 15. Energy efficiency and cost.
(space temperature, relative 16. Maintainability.
humidity, indoor air quality, noise
level, illumination level, etc.). Basis of Design
6. Performance criteria (general The basis of design provides the pri
efficiency, energy and toler mary ideas and assumptions behind
ances of the indoor environmen design decisions that were made to
tal quality objectives, etc.). meet the design intent. The basis of
7. Budget considerations and design describes the systems, com
limitations. ponents, conditions, and methods
chosen to meet the design intent. It
Commissioning Process

explains how certain systems and lighting power density, ventila


space arrangements were chosen tion, and infiltration rates, etc.;
by the design team to meet the outdoor conditions; and glazing
needs of the Owner. fraction, U-value, and shading
coefficient.
The following should be included in
the basis of design for major equip The basis of design should also in
ment: clude operations descriptions, in
cluding at a minimum:
1. Specific description of systems,
components, and methods for 1. Design intent.
achieving the design intent 2. Basic system type and major
objectives (for instance, why a components.
given system was chosen; 3. Interrelation of components.
details of that system’s size, 4. Capacity and sizing criteria. 71
efficiencies, area served, 5. Redundancy and diversity.
capacity control; integration 6. Automatic temperature control
with other system, sequences of and sequence of operation.
operation under all modes of 7. Intended operation under all
operation, control strategies, seasonal loads.
etc.). 8. Changeover procedures.
2. Equipment maintainability. 9. Part-load strategies.
3. Fire, life, and safety criteria, 10. Occupied/unoccupied modes of
strategy narrative, and detailed operation.
sequences.
4. Emergency power
control and function.
5. Energy performance.
6. Ventilation strategies
and methods.
7. Complete sequences
of operation, including
set points and control
parameters.
8. Schedules.
9. Applicable codes and
standards.
10. Primary load and
design assumptions,
including sizing;
occupant density and
function; indoor
conditions such as
space temperature,
relative humidity,
Commissioning Process

11. Design setpoints of control overall engineering design that may


systems with permissible be construed as second guessing the
adjustments. design engineer. The goal of the
12. Operation of system compo CxA’s review is to assure that the
nents in life-safety modes. system can be verified as working
13. Energy conservation proce correctly and that the system can be
dures. maintained in that condition. The
14. Any other engineered opera CxA reviews the schematic design
tional mode of the system. and construction documents for the
following issues at the phases
Design Documentation Format checked for each system commis
The format of the design intent/basis sioned:
of design documentation should ad
■ Commissioning Facilitation –
here to the following general outline:
72 Review for effects of specified
1. General design narrative systems and layout toward
describing the system and/or facilitating the commissioning
components. process (equipment accessibility
2. Objectives and functional use of for testing, controls, etc.; see
each system and/or compo Commissioning Facilitation
nents. Review on page 74).
3. Full sequence of operations
■ Energy Efficiency – Review
under all modes and conditions.
4. Set points and operating param efficiency of system types and
eters. components for specified
5. Performance criteria and systems.
applicable codes and standards.
■ Control System and Strategies –
Review specified systems’
Design Review sequences of operation for
The CxA performs reviews of the adequacy and efficiency.
design intent, basis of design, sche
matic design drawings and specifi ■ Operations and Maintenance
cations, and the construction (O&M) – Review for effects of
document design drawings and specified systems and layout
specifications, as described in this toward facilitating O&M
section. (equipment accessibility, system
control, etc.).
Design Review Scope
■ Indoor Environmental Quality –
The CxA is not responsible for nor
Review to ensure that systems
encouraged to check the design for
relating to thermal comfort,
engineering approach, system selec
visual, acoustical, air quality, and
tion, equipment specification, life
air distribution maximize comfort
cycle costs, or other parts of the
and are in accordance with the
Commissioning Process

Indoor Air Quality Commissioning Checklist


Design phase IAQ review to be performed:
1. Determine indoor air quality (IAQ) requirements and confirm that these are included in the Project
Objectives document.
2. Review expected occupant activity, density, and locations where special attention is needed; review
exhaust systems or increased supply air capacity that may be required:
❏ Kitchens ❏ Material storage rooms
❏ Break rooms ❏ Conference rooms
❏ Photocopying and/or printing rooms ❏ Locker rooms
73
❏ Janitorial rooms ❏ Parking garage
❏ Laboratories ❏ Other:

3. Ensure that IAQ objectives are included in the design.


4. Review carbon dioxide sensor locations and control sequences to ensure the system is properly de-
signed to maintain acceptable CO2 levels.
5. Determine how adequate ventilation rates will be maintained during all occupied modes of operations,
particularly during VAV terminal box turn-down.
6. Review air intakes and exhausts for short-circuiting and exterior pollution sources (such as garages,
loading docks, and cooling towers).
7. Review potential impact of office partition configurations on ventilation effectiveness.
8. Review filtration type and design, materials, and location.
9. Review HVAC material specifications and application for potential for airflow erosion, corrosion, and
microbial contamination (HVAC insulation materials, etc.).
10. Review air supply system to ensure control and minimization of free water and microbial contamination
(condensate trays, humidifiers, etc.).
11. Verify the suitability of access doors and inspection ports to all chambers and components of air
handling system plenums (accessibility for proper cleaning of both sides of coils, condensate pans
and/or humidifier reservoirs, and future duct cleaning).
12. Identify products specified in the contract documents that may contribute to indoor pollutants.
13. Confirm that the specifications specify proper methods and conditions for operating the HVAC system
prior to full control and occupancy to minimize dirt and unwanted moisture entering the duct work, coils,
building cavities, and any occupied portions of the building.
Commissioning Process

Project Objectives document ■ Commissioning Specifications –


and Owner’s Criteria. (See Verify that bid documents
Indoor Air Quality Commis- adequately specify building
sioning Checklist.) commissioning, including testing
requirements by equipment type.
■ O&M Documentation – Verify
adequate building O&M docu- ■ Project Objectives Document –
mentation requirements. Verify that the design complies
with the project objectives
■ Training – Verify adequate document.
operator training requirements.
■ Mechanical Systems – Review
mechanical design and concepts
for enhancements.
74
Sample Organization of Commissioning ■ Electrical Systems – Review
Specification electrical design and concepts
for enhancements.
1.1 Commissioning Description
1.2 Commissioning Project Coordination Commissioning Facilitation
1.3 Commissioning Process
Review
1.4 Related Work The CxA reviews the design docu
ments for the following issues:
1.5 Responsibilities
1.6 Definitions 1. Clear design documentation,
1.7 Systems to be Commissioned including detailed and complete
sequences of operation for
specified equipment.
2.1 Test Equipment 2. HVAC fire response matrix that
lists all equipment and compo
3.1 Meetings nents (air handling units, damp
3.2 Reporting ers, valves, etc.) with their
status and action during a fire
3.3 Submittals alarm or emergency.
3.4 Startup, Verification, and Initial Checkout 3. Maintainability and supportabil
3.5 Phased Commissioning ity.
3.6 Functional Performance Testing 4. Required isolation valves,
dampers, interlocks, piping, etc.
3.7 Documentation, Non-Conformance, and Approval of Tests to allow for manual overrides,
3.8 Operation and Maintenance (O&M) Manuals simulating failures, seasons, and
3.9 Training of Owner Personnel other testing conditions.
3.10 Deferred Testing 5. Sufficient monitoring points in
the building automation system
3.11 Written Work Products (BAS), including those beyond
that necessary to control the
Commissioning Process

systems, to facilitate perfor Commissioning Specifica


mance verification and O&M.
tion
6. Adequate trending and report
ing features in the BAS. The CxA prepares commissioning
7. Pressure and temperature (P/ specifications specific to the project
T) plugs close to controlling requirements in Divisions 1, 15, 16,
sensors for verifying calibration. and 17. Commissioning specifica
8. Pressure gauges, thermom tions that should be prepared and
eters, and flow meters in added to the project specifications
strategic areas to facilitate include:
verifying system performance
and ongoing O&M. ■ SECTION 01810 – Extra
9. Adequacy and location of General Requirements.
vibration sound discs/test points ■ SECTION 15995 – Mechanical
and lube oil sampling ports, as Systems Commissioning 75
applicable. (including plumbing and
10. Rationale for location for the HVAC).
variable air volume (VAV) duct ■ SECTION 16995 – Electrical
static pressure sensor and Systems Commissioning
chilled water differential (including fire alarm and
pressure sensor. protection).
11. Adequate balancing valves and ■ SECTION 17100 – Commis
flow meters to facilitate reliable sioning Requirements.
testing and balancing (TAB) of
the HVAC systems. The commissioning specifications
12. Uniform inlet connection should be reviewed and commented
requirements to VAV terminal on by the Owner. Each should in
boxes. clude, as a minimum, the following:
13. Energy efficiency and reduced
emissions in support of current 1. Detailed description of the
Federal energy statutes and responsibilities of all parties.
Executive Orders. 2. Detailed description of the
14. Maximization of points toward commissioning process.
LEED certification, as appli 3. Reporting and documentation
cable. requirements, including formats.
15. Clear and complete commis 4. Alerts to coordination issues.
sioning specifications for the 5. Deficiency procedures and
construction phase. resolutions.
16. Complete O&M documentation 6. Construction checklists and
requirements in the specifica start-up requirements.
tions. 7. Functional performance testing
17. Complete training requirements procedures, organized by
in the specifications. equipment and system.
8. Specific functional performance
testing requirements, including
testing conditions and accep
Commissioning Process

tance criteria for each piece of ■ Project Organization Chart


equipment being commissioned.
Roles and Responsibilities
Commissioning Plan ■ General Management Plan
■ Roles and Authority
The CxA develops the commission
- All Parties
ing plan during design, but the plan is
- Commissioning Authority
updated and revised as necessary
- Owner / Project Manager
throughout the construction phase to
- Architect / Engineer Design
reflect any approved changes or
Team
equipment substitutions. The com
- General Contractor / Con
missioning plan provides additional
struction Manager
guidance to project team members
- Building O&M Personnel
in the execution of the commission
- Manufacturers and Vendors
76 ing program.

The following information, as a mini Commissioning Plan


mum, should be included in the com ■ Commissioning Scoping Meeting
missioning plan: ■ Scheduled Commissioning
Meetings
Overview and General Information ■ Management and Communica
tion Protocols
■ General Building Information
■ Progress Reporting and Logs
■ Definitions and Abbreviations
■ Site Observation
■ Purpose of the Commissioning
■ Initial Submittals and Documen
Plan
tation
■ Commissioning Scope
- Standard Submittals
■ Equipment and Systems to be
- Special Submittals, Notifica
Commissioned
tions and Clarifications
■ Development of Functional Test
Construction and Commissioning
and Verification Procedures
Team Members - Scope of Testing
■ Points of Contact - Development Process
■ Verification Checks, Tests and
Startup
- Execution
- Sampling Strategy
- Deficiencies and Non-
Conformance
- Testing, Adjusting, and
Balancing (TAB)
- Controls Checkout Plan
■ Functional Performance Testing
- Overview and Process
- Sampling Strategy
- Deficiencies and Retesting
Commissioning Process

- Facility O&M Staff Partici ◆ Functional Performance Test


pation Forms
■ O&M Manuals and Warranties ◆ Commissioning Progress
- Post of System Operating Reports / Deficiency Logs
Instructions ◆ Controls Checkout and TAB
- Standard O&M Manuals Plans
- Commissioning Record ◆ Commissioning Plan (update as
■ O&M Orientation and Training necessary)
- Training Requirements
- Schedule During construction, the installing
■ Warranty Period contractors (mechanical, HVAC,
electrical, controls, etc.) install the
Written Work Products designed equipment and systems
■ List of deliverables under the direction of the owner and
the owner’s general contractor or 77
construction manager (GC/CM).
Commissioning Schedule
The CxA develops commissioning
■ Project and commissioning test procedures and forms, wit
schedules, updated regularly nesses equipment and systems
start-up, and verifies that equipment
Appendices and systems are ready for func
■ Design Intent and Basis of tional performance testing per
Design formed during the acceptance
■ Verification Checklists phase. Deficiencies are tracked and
■ Functional Performance Test reported, and the CxA schedules re
Forms testing until the equipment and sys
tems are ready for functional
Pre-Bid Meeting performance testing.

Often bidders will have questions Commissioning Meetings


regarding their roles in the commis
sioning process. These questions The CxA keeps minutes from all
should be answered by the CxA at commissioning meetings for distribu
the pre-bid meeting. Contractors tion to the commissioning team. It is
generally accept the process much the CxA’s responsibility to schedule
more readily if they understand it and conduct commissioning meet
and if the CxA exhibits a positive, ings.
helpful, and cooperative approach
right from the start. Commissioning Scoping Meeting
The CxA conducts a commissioning

INSTALLATION /
scoping meeting soon after the start
of construction. In attendance are
CONSTRUCTION PHASE the identified commissioning team
members and other key individuals
Documentation Requirements: from the project team (Owner,
◆ Verification Checklists
Commissioning Process

CxA, GC/CM, A/E design team, in resolution.


stalling contractors, TAB, facility ■ Review with commissioning
O&M, manufacturer/vendor repre team members commissioning
sentatives). The commissioning plan, responsibilities and answer any
process, and schedule are reviewed questions or concerns they may
by the CxA, including each party’s have on the commissioning
role and responsibilities. process.

The outcome of the meeting is an The frequency of the commissioning


increased understanding by all par meetings depends on the project
ties of the commissioning process schedule, but meetings should be
and their respective responsibilities. held at least bi-weekly during start
The meeting provides the CxA addi up and functional performance test
tional information needed to finalize ing.
78 the commissioning schedule.
Controls Coordination Meeting
Commissioning Meetings The CxA may schedule and conduct
The CxA holds regular commission a meeting to address integration is
ing team meetings during the project sues between equipment, systems,
construction and acceptance phases. and disciplines to ensure that inte
Regular commissioning meetings are gration issues are addressed and re
intended to accomplish the following: sponsibilities are clearly defined.
Integration issues and suggested
■ Review and update commission remedies/responsible parties should
ing schedule based on any be documented and submitted to the
changes to the project schedule. Owner and GC/CM.
■ Report observed deficiencies or
other problems, discuss problem Project Meetings
The CxA also attends regular
project progress meetings, if pos
sible, in order to remain informed on
the project progress and to update
parties involved in the commission
ing. Project meetings provide the
CxA with information on substitu
tions, change orders, and Architect’s
Supplemental Instructions (ASI) that
may affect commissioning equip
ment and systems or the commis
sioning schedule. (It is the
responsibility of the GC/CM to pro
vide this information to the CxA if
the CxA misses a project meeting.)
Commissioning Process

The CxA reviews construction ■ Labels are affixed.


meeting minutes, change orders, ■ Gauges are ergonomically in
and Requests for Information (RFI) place.
for the same purpose. ■ Correct valves are installed and
are accessible. A sample Verification Check
Submittals Review ■ Sensors and instrumentation are list is provided in Appendix A,
calibrated and installed per the Sample Commissioning
As the contractors make equipment engineering requirements (such Forms.
submittals to the design team and as duct pressure sensors
project manager, copies are routed located three-fourths of the
to the CxA for information. The distance to the furthest point in
CxA is not responsible for approv a VAV duct system).
ing the submittals (that is the ■ Correct interlocks and interfac
designer’s responsibility), but the ing between HVAC equipment,
CxA reviews submittals for appli systems, subsystems, and other 79
cable systems being commissioned building systems.
for compliance with commissioning ■ Drain piping is properly sloped.
requirements. The CxA reports to ■ Proper sheave alignment,
the design team if there is anything connection to power and other
in the submittals that appears seri utilities, vibration isolation, and
ously wrong. pipe and duct support.
■ Completion of testing and
Verification Checklists balancing (TAB) work.
Verification checklists are devel Some verification checklist items
oped by the CxA to guide the start entail simple testing of the function
up process and ensure that of a component, a piece of equip
equipment and systems are pre ment, or system (such as measuring
pared for functional performance the voltage imbalance on a three-
testing. phase pump motor of a chiller sys
tem). Verification checklists
Verification checklists are primarily augment and are combined with the
static procedures to prepare the manufacturer’s start-up checklist.
equipment or system for initial op
eration. In general this includes fac Verification checklists are important
tors such as: to ensure that the equipment and
systems are hooked up and opera
■ Equipment is located according tional and that functional perfor
to plans and practicality, such as mance testing may proceed without
full accessibility for mainte unnecessary delays. In general, the
nance. verification testing for a given sys
■ Lubrication levels are accept
tem must be successfully completed
able. prior to formal functional perfor
■ Fan belt tension is in accor
mance testing of equipment or sub
dance with manufacturer systems of the given system.
requirements.
Commissioning Process

Many of the problems found during ■ Balance valves not installed.


verication are associated with equip ■ Pump flow fittings and gauges
ment maintainability and accessibil located too close to pipe bends,
ity. Most common are: suction diffusers, or other pipe
characteristic that makes their
■ Equipment cabinet doors reading inaccurate.
blocked by piping or structural ■ Equipment nameplate data is not
members. visible.
■ Ceiling spaces are too crowded
to allow access to the equip Installing contractors typically al
ment. ready perform some, if not most, of
■ Terminal air distribution devices the verification checklist items the
installed too high above sus CxA will recommend. However,
pended grids to allow safe few contractors document in writing
80 access by ladder. the execution of these checklist
items.

Development of Verification
Case Study: Commissioning in Action Checklists
An A/E firm formed a joint venture to design an energy plant to The CxA requests and reviews rel
serve two hospitals. The facility was to produce and pump chilled evant information prior to system
water through a network of pipes and coils within the air-condi- start-up and verification, including
tioning system of both hospitals. The plant experienced several O&M materials and manufacturer’s
pump failures, pipe fractures, and excessive energy consump- start-up and check-out procedures.
tion by the air-conditioning system. This led to a claim by the
hospitals against the joint venture. To mitigate the damages, Before start-up, the CxA gathers
the joint venture agreed to commission the plant. After an exten- and reviews current control se
sive review, the joint venture was able to prove that the alleged quences and interlocks and works
damages were the result of ineffective maintenance, defective with each installing contractor and
maintenance systems, and failed standard service items. The the design team to verify that the
claim was settled for $30,000. functional testing procedures that
are in the commissioning specifica
Had commissioning services been provided during construc- tions are appropriate.
tion, the team probably would have identified potential system
failures prior to occupancy. Neither the Owner nor the joint The CxA writes and distributes veri
venture would have had claim-related expenses. The com- fication checklists to each installing
missioning would have provided a documented benchmark contractor for equipment to be com
against which future system performance could be trended and missioned. The original checklists
compared. (Source: Planning to Avoid Commissioning and are often organized in a binder and
Facility Management Claims; Constructive Comments, Num- left at the job site in the custody of
ber 4, 2005, Victor O. Schinnerer & Company, Inc., the GC/CM so that they are acces
www.Schinnerer.com) sible and can be annotated as work
completion progresses.
Commissioning Process

Personal digital assistants (PDAs) and the CxA consolidates the forms
offer an alternative to paper check later.
lists. The checklists are produced
electronically and downloaded onto The CxA documents systems start
the PDA. Data is entered onto the up by reviewing each installing
PDA directly, real time as the test contractor’s completed verification
ing progresses, then downloaded in checklists and by selected site ob
a permanent file for archiving and servation. Site visits are conducted
analysis. This eliminates the need to by the CxA during equipment instal
maintain paper or reenter data re lation to verify the commissioned
dundantly into the computer, which equipment and systems are installed
increases the likelihood of human according to the manufacturer’s
error. recommendations and to industry
accepted standards, and that equip
Execution of Verification ment has received adequate opera 81
Checklists tional checkout by the installing
contractors. The CxA also wit
Four weeks prior to start-up, install
nesses a sampling of ductwork test
ing contractors and vendors sched
ing and cleaning to be confident that
ule start-up and initial checkout with
proper procedures have been fol
the GC/CM and CxA. The start-up
lowed.
and initial checkout are directed and
executed by the installing contractor
Documentation of all system start
or vendor using the checklists pro
up and verification activities should
vided by the CxA. The CxA ob
be included in the Commissioning
serves and validates the results for
Report (described in the Post-Ac
each type of primary equipment.
ceptance / Warranty section).
To document the process of startup
and checkout, the site technician Deficiencies and Non-
performing the line item task checks Conformance
off items on the verification and The installing contractors clearly list
manufacturer field checkout sheets at the bottom of the procedure form
as they are completed. The install or on an attached sheet any out
ing contractors and vendors execute standing items of the initial start-up
the checklists and submit a signed and verification procedures that
copy of the completed verification were not completed successfully.
checklists to the CxA. The respective contractor provides
the procedure forms and deficien
On smaller equipment or projects, cies to the CxA within two days of
the checklists (which contain more test completion. The CxA works
than one trade’s responsibility) may with the installing contractors and
be passed around to the contractors vendors to correct and retest defi
to complete. For larger equipment, ciencies or uncompleted items, in
each trade may need a full form volving the GC/CM, if necessary.
Commissioning Process

The installing contractors or vendors Controls Checkout Plan


correct all areas that are deficient or
incomplete according to the check The controls contractor develops
lists and tests. The CxA recom and submits a written step-by-step
mends approval of the start-up and plan to the CxA that describes the
initial checkout of each system to process to be followed in checking
the Owner and GC/CM. the control system and the forms to
be used to document the process.
Commissioning Progress
The controls contractor also meets
Reports / Deficiency Logs with the testing, adjusting, and bal
The CxA provides the Owner and ancing (TAB) contractor prior to the
GC/CM with weekly commissioning start of TAB. They review the TAB
progress reports that include: plan to determine the capabilities of
82 the control system for use in TAB.
■ An update of the commissioning The controls contractor provides the
schedule, including schedule TAB contractor with any necessary
changes and new items added to unique instruments for setting termi
the schedule. nal unit boxes (i.e., hand held control
■ An update of the commissioning system interface for use around the
progress (start-up verified and building during TAB) and instructs
complete). the TAB contractor in their use.
■ A list of new and outstanding
deficiencies. The controls contractor also pro
■ A list of deficiencies that have vides a technician qualified to oper
been resolved. ate the controls to assist the TAB
contractor in performing TAB.

Prior to substantial completion, the


CxA reviews detailed software
documentation prepared by the con
trols contractor for all direct digital
control (DDC) systems. This in
cludes reviews of vendor documen
tation, the programming approach,
and the specific software routines
applied to project facility compo
nents and building systems.

All required controls verification


checklists, calibrations, and start-up
of the system should be completed
and approved by the CxA prior to
TAB. The controls contractor ex
Commissioning Process

ecutes the assigned tests and trend Functional Performance


logs, and remains on site for assis
Test Forms
tance for mechanical system func
tional tests as specified. The CxA The CxA oversees functional per
verifies and documents the effec formance testing during the accep
tive operation of these interlocking tance phase, but the test plans and
control systems. forms are developed during the con
struction phase (or earlier). Func
Testing, Adjusting, and tional testing includes operating the
Balancing (TAB) Plan system and components through the
significant modes of operation, in
The TAB contractor submits the cluding:
outline of the TAB plan and ap
proach to the CxA and the controls 1. Each of the written sequences
contractor eight weeks prior to of operation. 83
starting the TAB. Included in the 2. Start-up and shut-down.
approach is an explanation of the 3. Unoccupied mode.
intended use of the building control 4. Manual mode.
system during testing. The CxA re 5. Staging.
views the plan and approach for un 6. Miscellaneous alarms.
derstanding and coordination issues 7. Power failure.
and may comment The controls 8. Interlocks with other systems or
contractor reviews the feasibility of equipment.
using the building control system for
assistance in the TAB work. The systems performance is evalu
ated for:
The TAB contractor submits
weekly written reports of discrep ■ Input and output capacities.
ancies, contract interpretation re ■ Flow and distribution perfor
quests, and lists of completed tests mance.
to the CxA and GC/CM. This facili ■ Control system performance,
tates quicker resolution of problems accuracy, and adherence to
and will result in a more complete sequences of operation.
TAB before functional testing be ■ Minimum or part/load opera
gins. tions and capabilities.
■ Interface with other equipment
Commissioning Plan and/or systems.
■ Emergency response
The CxA continues to update and
revise the commissioning plan Actual physical responses must be
throughout the construction phase to observed. Reliance on control sig
reflect any approved changes or nals and other indicators is unac
equipment substitutions. ceptable.
Commissioning Process

Equipment and system functional manuals for later use by operations


performance testing begins only af staff.
ter the affected systems have been
fully and successfully verification The CxA reviews the factory or re
tested and the system has been quired Owner acceptance tests and
A sample Functional Perfor tested and balanced (TAB). Sensors determines what further testing may
mance Test form is provided and actuators are calibrated by the be required to comply with the
in Appendix A, Sample Com installing contractors prior to func specifications.
missioning Forms. tional testing, and checked by the
CxA. Functional testing is per The CxA reviews proposed testing
formed using conventional manual procedures and report formats and
methods, control system trend logs, observes sufficient field testing to
and stand-along data loggers to pro confirm that all I/O points have been
vide a high level of confidence in properly tested.
84 proper system function.

Systems and subsystems are tested ACCEPTANCE PHASE


under full load, where possible and
applicable, and under part load con Documentation Requirements:
ditions as specified in the Cx Plan. ◆ Commissioning Progress
Reports / Deficiency Logs
Tests on HVAC equipment are per ◆ O&M Manuals
formed during both heating and cool ◆ Commissioning Plan (finalized)
ing seasons (see Deferred and ◆ Commissioning Record
Seasonal Testing).
During acceptance, the installing
Development of Test Forms and contractors perform functional per
formance tests on equipment and
Procedures
systems, which are witnessed by the
The CxA, based on input from other CxA. Deficiencies are tracked and
team members, develops the func reported, and the CxA schedules re
tional performance test procedures. testing until the equipment or sys
This is to ensure all aspects of sys tems operate and interact as
tem operation are fully explored and designed. Operations and mainte
documented. The CxA obtains clari nance (O&M) manuals are orga
fication, as needed, from installing nized and reviewed, and O&M staff
contractors and the A/E regarding training is scheduled and executed.
the sequences of operation. Prior to The project is finalized and handed
execution, the CxA provides a copy over to the owner.
of the primary equipment tests to
each installing contractor or vendor,
Functional Performance
who reviews the tests for feasibility,
safety, warranty, and equipment pro Testing
tection. Blank copies of the proce The CxA schedules, oversees, wit
dures are included in the O&M nesses, and documents the func
tional performance and condition
Commissioning Process

Test Sampling and Deficiencies


Multiple pieces of identical equipment can be functionally tested using a sampling strategy. In functional
performance testing, should 10% of the sampled systems verified fail to meet the design criteria, another
10% should then be tested. If those additional 10% of the systems also fail to meet the design criteria, the
entire system in question should be re-examined by the responsible contractor. The cost to commission that
particular system should be borne by the responsible contractor.

acceptance testing of all equipment for accuracy as prescribed in the


and systems according to the com- Cx Plan. If a substantial failure rate
missioning specifications and the is encountered, all should be cor-
Commissioning Plan. The installing rected and a larger and different
85
contractors or vendors execute the sample chosen for a repeat test at
tests. the contractor’s expense. For ex
ample, 20 percent of all terminal de
The control system is tested before vices such as grilles and registers
it is used to verify performance of may be selected for output verifica
other components or systems. The tion. If the output of 10 percent of
air balancing and water balancing is these differ significantly from the
completed and debugged before reported values, all should be re
functional testing of air- or water- jected, corrective action taken by
related equipment or systems. Test the contractor, and a new sample of
ing proceeds from components to 25 percent (or more) randomly se
subsystems to systems and finally to lected devices selected for re-verifi
interlocks and connections between cation.
systems. In addition to the verifica
tion of sequences during normal op During the functional performance
erating conditions, testing also testing, the CxA looks for four fea
includes any abnormal scenarios tures relative to the test data:
during which the equipment may be
expected to operate, such as during ■ Repeatability – How well
failure and recovery, standby power, does the component consistently
and alarm and alert situations. replicate a desired output, such
as control sequences and
The CxA also observes, photo resulting pressure or flow?
graphs or video captures, and docu
ments the actual performance of ■ Stability – How well does the
safety shutoffs in real or closely component or system maintain a
simulated failure condition. desired condition despite
changing outside influences?
A sample of redundant items in
cluded in the contractor’s test and ■ Responsiveness – How well
balance (TAB) report is checked do the components work
Commissioning Process

together in an integrated fashion Owner and GC/CM. Installing con


to react to changing outside tractors correct the noted deficien
influences while maintaining the cies and notify the CxA, who
desired outcome? schedules re-testing.

■ Accuracy – Does the system Decisions regarding deficiencies and


achieve the desired outcome corrections are made at as low a
within an acceptable tolerance? level as possible, preferably between
CxA, GC/CM, and installing con
When the functional performance tractors. For areas in dispute, final
testing is completed, every mode of authority, besides the Owner’s, re
each operation of a system, each sides with the A/E design team. The
piece of equipment, every item in CxA makes final recommendations
the control sequence description, ev to the Owner for acceptance of
86 ery emergency response, and every each test after a review of the final
zone or subsystem will have been functional performance test. The
proven to operate as required and Owner gives final approval on each
specified in the design intent and de test.
sign documents.
Building O&M Staff Participation
Deficiencies and Re-testing The building’s O&M staff is strongly
The CxA documents the results of encouraged to attend and participate
each functional performance and in the testing process.
condition acceptance test. Correc
tions of minor deficiencies (e.g., fix Condition Acceptance
ing a controller, adjusting alignment)
Testing
identified can be made by the re
spective contractor during the tests Some CxAs integrate condition ac
at the discretion of the CxA. ceptance testing into their commis
sioning programs as part of the
In general, no applicable systems or functional performance testing.
subsystems are accepted until all Commissioning uses verification and
items of equipment have been suc functional performance testing to
cessfully functionally performance ensure that systems are installed
and condition tested. After all defi correctly and operate properly, and
ciencies have been corrected, the to validate output parameters such
entire functional performance test as air output, flow, temperature,
for the equipment, system, or sub pressure, system balance, control
system is repeated. sequences, and energy consumption.
The entire system is evaluated
The CxA records the results of the through all control modes and in
test on the procedure or test form. cludes testing of the ductwork, pip
Deficiencies or non-conformance ing, valves, and actuators.
issues are noted and reported to the
Commissioning Process

Commissioning does not evaluate, lation resistance testing, motor cur


however, the actual condition of rent analysis, ultrasound, and oil
the equipment. Whereas functional analysis (as appropriate). It evalu
performance testing will normally ates the installed system to ensure
tell you that a fan is pushing out a that the equipment is properly
certain CFM, it will not tell you if aligned and balanced; that the cor
the fan and driver are properly rect lubricants are provided, are
aligned, if the fan is balanced, or if clean, and have the correct required
there are loose, high resistance additives; that electrical connections
electrical connections. This is are tight and proper; that motors are
where a reliability centered mainte free of internal defects and are
nance-based condition acceptance phase balanced and have insulation
element to the commissioning pro resistance within specific toler
gram comes in. ances; that the equipment has no in
ternal damage from the factory, 87
Condition acceptance testing may from handling and transport, or from
be integrated with the functional the installation; or that the installa
performance testing. The results tion meets ISO quality standards.
are that:
Rarely are these factors looked at
■ Latent manufacturing and during “equipment start up” and in
installation defects are detected evitably, they become problematic
early in the process while the for the maintenance staff the day
contractor is still on site. after the warranty expires. Condi
■ Warranties are enforceable by tion acceptance testing provides a
documenting the precise baseline for each unit of equipment
condition and performance of against which future data from con
the system at the time of dition monitoring can be compared,
acceptance. trended, and an alert made before
■ Because problems are detected equipment failure. Necessary re
and corrected at the system, pairs, then, can be scheduled at an
rather than component level, opportune, non-critical time after
synergy is assured, resulting in parts and materials have been or
greater system reliability, fewer dered and received and labor has
recurring problems after been scheduled.
acceptance, and reduced life
cycle costs. Commissioning Progress
■ The baseline documentation
Reports / Deficiency Logs
generated becomes the founda
tion of the maintenance pro The CxA continues to provide the
gram for the life of the facility. Owner and GC/CM with weekly
commissioning progress reports that
Condition acceptance testing uses include:
technology such as vibration moni
toring, infrared thermography, insu ■ An update of the commissioning
schedule, including requested
Commissioning Process

schedule changes and new 6. Functional performance test


items added to the schedule. procedures and results, blank
■ An update of the commissioning test forms, and recommended
progress (functional perfor- schedule for re-testing.
mance and condition acceptance 7. Recommendations for
tests completed). recalibration frequency for
■ A list of new and outstanding sensors and actuators by type
deficiencies. and use.
■ A list of deficiencies that have 8. Single-line diagrams of commis
been resolved. sioned systems (as-built from
construction documents).
Operation and Maintenance 9. Troubleshooting table for
ongoing achievement of project
Manuals
objectives.
88 The CxA compiles and reviews the 10. Guidelines for continuous
operation and maintenance data pro- maintenance of the project
vided by installing contractors, objectives, design intent, and
manufacturers, and vendors for basis of design.
thoroughness. The CxA also gathers 11. Equipment warranties informa
and reviews as-built drawings for tion, including warranty start and
equipment and systems that were end dates, and verification that
commissioned to verify compliance all requirements to keep the
with the specifications. The CxA warranty valid are clearly
takes the lead in inspecting and ap- stated. All warranty information
proving the O&M manual as to con- is consolidated in a single
tent and organization. The following section of the O&M manuals.
information should be included in the 12. A consolidated listing of all
final O&M manuals: manufacturer and vendor points
of contact, including representa
1. Project objectives document. tive name, company name and
2. Design intent and basis of address, phone numbers, e-mail
design documents. addresses, and web address for
3. Sequences of operation (up- quick reference.
dated to as-built from contract
documents), equipment opera- It is good practice to aim for the
tion schedules, and point lists completion of the O&M manual as
with initial set-points and ranges. soon as possible after the last con
4. TAB data. tractor submittal is approved. By this
5. Instruction for operation for time, all equipment should have been
each piece of equipment, ordered and O&M information ac
including seasonal adjustment, cumulated. Each contractor should
start-up and shut-down check- have assembled and completed the
lists, and instructions for energy O&M manuals by about the time all
savings operations and strate- equipment is physically on site. Con
gies. sequently, receipt of the completed
O&M manuals should be a factor in
Commissioning Process

approving each contractor’s 60- to


90-percent progress payments.

Final Commissioning Plan


The CxA finalizes the Cx Plan after
functional performance testing is
complete and there are no more
changes or equipment substitutions
planned.

Commissioning Record
The CxA compiles, organizes, and
indexes commissioning data by 89
equipment for inclusion in the O&M
manuals. The correspondence,
meeting minutes and progress re
■ Formal manufacturer and
ports, miscellaneous notes, etc. kept
installer training sessions.
during the project will not be re
tained into this record, but stored in
It is highly advantageous for the
a separate volume.
maintenance technicians to see ca
bling, piping, ductwork, and other
Operation and Maintenance normally hidden systems prior to
Staff Training their being covered and obstructed
by insulation, ceilings and drywall.
Operations and maintenance staff
In addition, the O&M staff must be
training actually begins early in the
walked through emergency proce
commissioning process through the
dures and various operational se
participation of select representa
quences under all possible
tives on the commissioning team.
scenarios.
As the project progresses, the
O&M staff becomes more and
The O&M staff must become fa
more acquainted with the building’s
miliar with the building’s control sys
features. Designated representa
tem:
tives visit the job site during se
lected time periods including:
■ How the control system works,
including the sequence of
■ System installation.
operations.
■ System verification.
■ The control system structure –
■ Hands on equipment startup.
what is connected to what.
■ Hands on functional perfor
■ The control system components
mance testing.
and their proper nomenclature
■ Hands on condition acceptance
(e.g., actuators, sensors, valves,
testing.
terminal boxes).
Commissioning Process

■ The control system monitor, its training plan and in coordinating and
various screens, and the infor scheduling the overall training for
mation the software is capable the commissioned systems. The
of providing. CxA develops criteria for determin
■ Alerts, alarms, and emergency ing that the training has been satis
procedures. factorily completed, including
attending some of the training.
The CxA is responsible for oversee
ing and approving the content and The CxA recommends approval of
adequacy of formal training of the training to the Owner, who gives
O&M personnel for commissioned approval when acceptable training
equipment. The GC/CM is respon has been conducted.
sible for training coordination and
scheduling and ultimately for ensur Scheduling a brief presentation by
90 ing that training has been completed. the design engineer is a good prac
The GC/CM and installing contrac tice that informs the O&M staff of
tors actually present the training ma the idiosyncrasies and features of
terial. The CxA attends all training the installed systems. It also allows
sessions and sees to it that important the staff to ask questions that re
issues are raised. main after the construction process
and were never really completely
Each installing contractor and ven clear on the design drawings.
dor responsible for training submits a
written training plan to the CxA for Video-taping the training is another
review and approval prior to train good practice for archiving the infor
ing. The plan should cover the fol mation and for training new employ
lowing elements: ees as they come on board. Good
sound is as important as good pic
■ Equipment included in training. ture, so if hands-on and other train
■ Intended audience. ing is taking place in the actual
■ Location of training. equipment rooms, then some mitiga
■ Objectives. tion of equipment noise (such as
■ Subjects covered (description, turning off air compressors) may be
duration of discussion, special required.
methods, etc.).
■ Duration of training on each Special Training and Orientation
subject. The following are additional special
■ Instructor for each subject and
training and orientation sessions that
instructor’s qualifications. may be requested by the Owner:
■ Methods (classroom lecture,
video, site walk-through, actual ■ Recommissioning - The CxA
operational demonstrations, provides instruction on the use
written handouts, etc.). of blank functional test forms
for periodic recommissioning of
The CxA assists the GC/CM and equipment and systems, per the
Owner in developing an overall specification.
Commissioning Process

■ Architect/Engineer - The A/
E provides a general overview
POST-ACCEPTANCE /
of the facility, its use, special WARRANTY PHASE
features, tenant and public
considerations, etc. Documentation Requirement:
◆ Final Commissioning Report
■ Mechanical Design Engi
neer - The mechanical de The CxA returns to the project ap
signer provides an overview of proximately 10 months into a 12
the major systems and equip month warranty period. During this
ment in the facility, including for visit(s), the CxA reviews with the
each system: the design intent, facility staff the quality and reliabil
why the system was chosen, an ity of the current building operation.
overview of its operation and The status of outstanding issues re
interactions with other systems, lated to the original and seasonal 91
any special areas to be aware commissioning is also addressed.
of, issues regarding future The CxA interviews facility staff
expansion and remodeling, etc. and to identify problems or concerns
that they have operating the building
■ Electrical Design Engineer as originally intended. Issues dis
The electrical designer provides cussed may include:
an overview of the major
systems and equipment in the 1. Current building operation.
facility, including for each 2. Any outstanding issues related
system: the design intent, why to the project and the commis
the systems was chosen, an sioning process.
overview of its operation and 3. Any problems or concerns with
interactions with other systems, operating the building as
any special areas to be aware originally intended and designed.
of, issues regarding future 4. Suggestions for improvements
expansion and remodeling, etc. and for recording enhancements
in the O&M manuals and final
■ Vendors and Manufacturers Commissioning Report.
- The vendor or manufacturer 5. Areas that may come under
of any item that is commis warranty or under the original
sioned provides an overview of construction contract.
that particular piece of equip 6. Documentation of reports and
ment in the facility, including for documents, and requests for
each item its physical make-up, services to remedy outstanding
capabilities and interactions problems.
with other systems, test points
for condition monitoring (if Deferred and Seasonal
applicable), any special areas to Testing
be aware of, and issues regard
ing expansion capabilities or During the warranty period, sea
adding capacities. sonal testing (tests delayed until
Commissioning Process

weather conditions are closer to the ■ Equipment meeting project and


system’s design) are scheduled and commissioning specifications.
executed under the coordination of ■ Equipment installation.
the CxA. Tests are executed, docu ■ Functional performance and
mented, and deficiencies corrected efficiency.
by the appropriate contractors, with ■ Equipment documentation and
building O&M staff and the CxA design intent.
witnessing. Any final adjustments to ■ O&M staff training.
the O&M manuals and as-built
drawings due to the testing should All outstanding non-compliance
be made by the responsible contrac items should be specifically listed.
tor. Also included are training records,
test schedules, construction check
If any check or test cannot be com lists, and recommendations for im
92 pleted due to the building structure, provement to equipment or
required occupancy condition, or operations, future actions, and com
other deficiency, execution of func missioning process changes. Each
tional performance testing may be non-compliance issue is referenced
delayed upon approval of the to the specific functional test, in
Owner. These tests will be con spection, trend log, and design speci
ducted as soon as possible in the fication requirement where the
same manner as the seasonal tests, deficiency is documented.
and the services of necessary par
ties will be negotiated. The functional performance and ef
ficiency section for each piece of
Final Commissioning Re equipment includes a brief descrip
tion of the verification method used
port
(e.g., manual testing, BAS trend
The final commissioning report in logs, and/or data loggers), and ob
cludes a summary report of partici servations and conclusions from the
pants and their roles, building testing.
description, project objectives, an
overview of the commissioning and The Final Commissioning Report is a
testing scope, and a general descrip collection of project documentation.
tion of testing and verification meth Typically, it includes:
ods.
■ Design Intent and Basis of
For each piece of commissioned Design
equipment, the report contains the ■ Commissioning Plan
disposition of the CxA regarding the ■ Signed checklists
adequacy of the equipment, docu ■ Signed functional performance
mentation, and training relative to test results
the contract documents in the fol ■ Requests for information (RFIs)
lowing areas: ■ Deficiency reports / Corrective
actions
■ TAB data
Commissioning Process

■ Equipment condition baseline


data
■ Planned off-season testing

BEST PRACTICES
■ In nearly all cases, it is easier
and in the long run more cost
effective to hire an independent,
third-party commissioning
authority to guide the commis
sioning project.

■ Ongoing monitoring and verifi


cation of energy and operational 93
performance are essential to
maintaining persistence of
improvements and ensuring that
equipment and systems are
operating at optimal efficiency.

■ A well-trained O&M staff with


adequate resources is crucial to
the success of any commission
ing program.

■ Problems, deficiencies, and


complaints should be carefully
recorded by the facility man
agement and O&M staff.
Often, problems can be grouped
into categories (design, opera
tion, maintenance, installation,
comfort and safety) that can be
analyzed for more significant
trends.

■ The documentation required by


each commissioning process
can be daunting, but will prove
an invaluable resource for
building management, O&M,
and future commissioning
efforts.
Commissioning Process

STUDY QUESTIONS
1. What are the commissioning documentation requirements for each phase of construction? Why are these
documentation requirements so important to the overall commissioning program?

2. What is the role of the CxA in verification and functional performance testing? What is the role of the
installing contractors? The CM/GC?

3. What are some factors to bear in mind when evaluating maintainability and supportability during design
review?

4. How are the design intent and basis of design different? What part does the Owner’s project requirements
94 document play in both the design intent and basis of design?

5. What issues should be checked for each commissioned system during design review?

6. What commissioning facilitation issues should be addressed during design review?

7. How is the commissioning specification different from the commissioning plan? Which party(ies) prepares
each document?

8. Who conducts commissioning meetings during the installation/construction phase of the project? How do
these meetings relate to regular construction team meetings?

9. When is verification testing performed, and by whom? When is functional performance testing performed,
and by whom? When is deferred and/or seasonal testing performed, and by whom?

10. What is the process for reporting and correcting deficiencies and non-comformance issues?

11. How does the TAB contractor fit into the commissioning program on a construction project?

12. What are some of the tools and instrumentation used by the installing contractors and CxA to accomplish
functional performance testing?

13. When should test sampling be utilized during functional performance testing?

14. What are the benefits of performing condition acceptance testing in addition to functional performance
testing?
Retrocommissioning Process

Chapter 6
Retrocommissioning Process

R
etrocommissioning is a It’s a
systematic process for prerequisite
improving and optimizing for LEED
building performance in EB (Existing
an existing building that has never Buildings). 95
gone through any type of commis
sioning or quality assurance pro Like commis
cess. Its focus is usually on sioning,
energy-using equipment such as retrocommis
mechanical equipment, lighting, and sioning seeks to
related controls. However, building identify and cor
envelope is an increasing retrocom rect the root
missioning issue, particularly in causes of prob
humid areas where mold is a par lems, not the
ticular problem. symptoms (e.g.,
“the room is hot”). Also like com “It is far easier and less ex
The most common reasons why an missioning, retrocommissioning is pensive to maintain a build
ing that operates correctly
Owner may want to retrocommis concerned with how equipment,
than to maintain one that
sion a facility include: systems, and subsystems function does not.”
together, but it does not generally
■ It addresses the gap between a take a whole-building Rusty Ross
building that does not work as approach to efficiency.
intended and an already over
burdened maintenance and Retrocommissioning does not in
engineering staff. clude the replacement of significant
■ The building is not providing an HVAC and other system compo
adequate work environment. nents. Rather, it focuses on the veri
■ There are indoor air quality fication of the proper controls
issues. strategies, sequences of operation,
■ Mold is present in the building.
■ The building’s energy costs are
too high compared with similar This chapter describes the process for implementing
facilities. retrocommissioning in new construction and major renovation
■ Equipment and systems are projects. Chapter 5 covers the commissioning process, Chapter 7
sustaining damage over the long covers the recommissioning process, and Chapter 8 covers con-
term from the indoor environ tinuous commissioning.
ment.
Retrocommissioning Process

sustainability, indoor environmental


In this Chapter quality, and environmental impacts.
This will serve as guidance when
◆ Planning Phase deciding which equipment and sys-
◆ Discovery Phase tems are targeted for analysis and
◆ Corrective Phase potential improvement.
◆ Project Hand-Off
◆ Best Practices Guiding questions that should be
asked to help determine what sys-
tems should be retrocommissioned
control component functionality, op-
include:
erations and maintenance proce-
dures and strategies, and other
Where have problems consistently
building optimization opportunities.
occurred?
96
Retrocommissioning is not tied to a There is no reason to propagate a
specific new construction or renova- recurring and costly headache. Sys-
tion project and therefore does not tem reliability should be a primary
follow the same process as commis- focus. The only way to ensure this is
sioning. Sampling is not performed in to determine and correct forever the
Loose electrical connections root cause of the problem. This
retrocommissioning. Instead, 100
or insulation damage may
percent of the applicable compo- knowledge can then be applied to
not show up until more
nents and systems are evaluated. other systems experiencing the
equipment increasingly
comes on line and electrical same symptoms.
loads increase – usually well The four phases that retrocommis-
after building acceptance. sioning follows, described in detail in What are the risks of system
this chapter, are planning, discovery, malfunction?
correction, and hand-off. Consider the risks that failure has on
mission, on personnel productivity,
on operational production and on
PLANNING PHASE other factors such as security,
safety, environment, and energy.
Documentation Requirements: Consider the impact of redundant
◆ Project Objectives Document and backup systems and parts avail-
◆ Design Intent Document ability and technical supportability.

Identify Project What are the political implications


Objectives and Scope of poor system performance?
The Owner identifies the objectives Consider the purpose and location of
for the retrocommissioning project, the system. Higher priority would
including in the areas of operational probably be given to a fan-coil unit
improvement, energy performance, in the Owner’s office than it would
water performance, maintainability, in a warehouse office space.
Retrocommissioning Process

How will deficiencies be found


without retrocommissioning?
There are several possibilities. Retrocommissioning Process
However, it usually depends on how
much risk you are willing to tolerate
and how much cost you can afford.
Planning
Determine project objectives
Deficiencies can be found by doing Decide which equipment and systems will be
nothing, thereby risking failure at analyzed for potential improvements
Hire CxA or assign duties to O&M personnel
any time and paying higher repair
costs when it fails and higher oper
ating and energy costs until that
time. Deficiencies can also be
found with a proactive maintenance Discovery
program that combines failure Determine how selected equipment and systems are intended
to operate (design intent), or how they could operate more 97
modes and effects analysis and root efficiently given current building conditions
cause failure analysis with obser Measure and monitor how targeted equipment and systems
vant preventive maintenance and currently operate
Prepare a prioritized list of deficiencies / corrective actions
repair activities. They can also be
found through trend analysis of op
erations, energy, and key perfor
mance data.

So consider, for each system being Correction


considered for retrocommissioning, Correct operating deficiencies (highest priority to lowest)
their affordability, labor commit Perform functional performance tests to verify proper and/or
improved operation
ment, and degree of risk relative to
their commissioning or non-commis
sioning.

Determine the Hand-off


Prepare a report of improvements made
Commissioning Team Provide training and documentation on how to sustain
proper and/or improved operation
During the planning phase, the
Owner will hire an independent,
third-party CxA. The CxA will
work closely with the Owner, the
building Management and O&M CxA cuts down significantly on
staff, and any necessary additional O&M staff workload related to the
contractors and vendors (e.g., con retrocommissioning process. If
trols vendor). choosing this option, the Owner
must designate a team of senior
Retrocommissioning, particularly for members of the facility Manage
less complex, smaller buildings, can ment and O&M staff to take on the
also be accomplished in-house with duties of the CxA.
facility O&M staff, although using a
Retrocommissioning Process

It is beneficial to involve the O&M commissioning strategy and process


staff in retrocommissioning for nu that will be followed. This plan iden
merous reasons: tifies the commissioning team mem
bers, and is updated and revised as
■ They know the building sys necessary throughout the
tems. retrocommissioning project.
■ They have access to all the
sections of the buildings. The Owner, based on the project ob
■ They have logs and service jectives and current requirements
records. (which may have changed since the
■ They know the equipment and original design intent was devel
system Standard Operating oped), draws up a list of equipment
Procedures (SOP) that must be and systems that will be targeted for
followed and personnel protec investigation during the
98 tive equipment that must be retrocommissioning project. The
worn. most likely candidates are HVAC,
■ They have access to additional mechanical, and lighting systems, in
and specialized equipment. which deficiencies and problems are
■ They know how the control common and low-cost improvements
system operates. can have big impacts.
■ They can make on-the-spot
minor repairs. The following information, as a mini
mum, should be included in the
All involved need to realize, how retrocommissioning plan:
ever, that theirs is not a fault-finding
mission. Rather, it is to work collec Overview and General Information
tively to optimize and improve the ■ General Building Information
building’s efficiency and working ■ Definitions and Abbreviations
conditions. ■ Retrocommissioning Objectives
■ Purpose of the Retrocommis
Retrocommissioning Plan sioning Plan
■ Retrocommissioning Scope
The CxA develops a retrocommis
■ Equipment and Systems to be
sioning plan that lays out the retro-
Investigated for Potential
Improvements

The Goal of Retrocommissioning Commissioning Team Members


The goal of new building commissioning should be a 100 percent ■ Points of Contact
perfect operating facility. The goal of retrocommissioning is not nec- ■ Project Organization Chart
essarily a 100 percent perfect facility, since the existing facility may
not meet the current operating goals of the occupants. Instead, the Roles and Responsibilities
goal may be to raise a facility’s operating efficiency above the 90- ■ Commissioning Authority (if one
percent mark with little or no extra remedial cost. The remaining 10 is used on the project)
percent depends on cost/benefit analysis. ■ Owner / Project Manager
Retrocommissioning Process

■ Building O&M Personnel Document Collection


■ Others
The retrocommissioning team col
Retrocommissioning Plan lects general facility and equipment
Strategy and Process and system-specific data during this
phase. With the caveat that many of
■ Energy and Operational Analy the original documents may not exist
sis and Establishment of or may be out-of-date, the following
Performance Baselines documents should be collected and
- Utility bill analysis and made available, if possible, to the
benchmarking retrocommissioning team:
- Trend analysis and building
modeling ■ Available construction docu
- Documenting master list of ments, including plans, inspec
findings All involved need to realize
tion reports, and O&M manu that theirs is not a fault-find 99
- Energy and operational cost als. ing mission. Rather, it is to
savings estimating ■ Equipment baseline data. work collectively to optimize
■ Document Review ■ Utility bills (previous 12 to 24 and improve the building’s
- Available construction months) and energy data. efficiency and working condi
documents
■ Equipment inventory, including tions.
- O&M Manuals
size, capacity, and age data.
■ Staff Interviews ■ Equipment maintenance infor
- Maintenance Staff mation.
- Occupants ■ Control sequences of operation.
■ Implementation ■ TAB reports.
- Implementing O&M and ■ Equipment or operations
Capital Improvements benchmark, key performance
- System Documentation indicator, and trending informa
(Control Sequences) tion.
- O&M and Systems Manu
als
■ Functional Performance Testing DISCOVERY PHASE
- Overview and Process
- Sampling Strategy Documentation Requirements:
- Deficiencies and Retesting ◆ Retrocommissioning Plan
■ Monitoring and Verification ◆ Master List of Deficiencies and
- Monitoring System Perfor Improvements
mance ◆ List of Improvements Selected
- Measuring Energy Savings for Implementation
■ Project Final Report
During the investigation phase, the
Written Work Products CxA works with the facility man
agement and O&M staff to investi
■ List of deliverables gate the building and its equipment
and systems. The result of this in
vestigation is a prioritized list of im-
Retrocommissioning Process

The CxA reviews the documentation


Case Study: Retrocommissioning developed and/or compiled during
the planning phase. An analysis is
in Action conducted to look for signs of equip-
ment and system deterioration or
The air conditioning system at a converted (from a shopping
sub-optimal performance. Mainte-
center facility) telephone call center with 250 operators was not
nance histories and operations
providing sufficient comfort. The cost for a new air conditioning
trends relative to baseline informa-
system was $250,000. The Owner had called in an air-condi-
tion will be indicative of problems
tioning contractor, mechanical engineer, and controls contrac-
that may have root causes initiated
tor to correct the problem, and each was unsuccessful. Finally,
with system design, maintenance
during retro-commissioning it was discovered that return air
procedures, personnel qualifications
grilles were missing from the newly renovated facility and the and training, scheduling, changed
building was starving for return air. The air-conditioning con- conditions resulting in over- or un-
100 tractor, mechanical engineer, and controls contractor failed der-sizing, controls, component fail-
because they focused on their specific areas of expertise and ure, or other deficiencies.
overlooked the simple.
Review and analysis of energy data
and utility bills likewise indicate
provements to make during the problematic trends, as well as oppor
implementation phase. tunities where both energy and en
ergy cost savings may be achieved.
Document Review
Personnel Interviews
When implementing retrocommis
sioning, the original design intent or Personnel interviews with at least
up-to-date construction documents two specific groups of personnel are
(particularly drawings) may not be invaluable to the retrocommissioning
available. Even if they are, the team during the investigation phase
Owner’s requirements may have – the maintenance staff and the
changed since these documents building occupants.
were originally prepared due to rea
sons such as mission changes, occu Interviews with the maintenance
pancy reassignments, installation or staff will help determine their per
removal of interior walls and parti ception of current problems that
tions, and introduction of new tech may be associated with the equip
nologies. If these documents exist, it ment and systems, the facility O&M
is essential that the retrocommis culture, O&M practices, or other in
sioning team review them for com fluential factor on system efficiency
parison with the Owner’s current and reliability. The interviews will
requirements and existing conditions also help the retrocommissioning
to determine if the original size and team better understand operating
capacity units can provide the cur strategies and equipment condition.
rent required output.
Records of the interviews should be
maintained for future reference. The
Retrocommissioning Process

interviewers need to be aware that tion. The site assessment addresses


the information may be factual, the following major issues:
hearsay, perceived, or even political
in nature. Look for patterns. ■ Building occupancy and space
utilization.
Similarly, interviews with building ■ System and equipment condi
occupants will help determine their tion.
perception of current problems that ■ Overall building energy use and
may be associated with equipment demand.
and systems, facility design, Owner ■ Areas of highest energy use
response, and the operations and and demand.
maintenance culture. Ask if they ■ Utility bill analysis and
hear “strange sounds” or “noise” benchmarking (bills from
from the mechanical and ventilation previous 12 to 24 months).
systems. Look for patterns. ■ Air and water flow rates, 101
calibrations, and flow coeffi
As before, interview records should cients.
be maintained and the interviewers ■ Actual control sequences for
need to be attuned to the fact that each piece of equipment and
the information may be factual, each system included in the
hearsay, perception, or politically- project and their functionality.
influenced. ■ Equipment nameplate informa
tion.
Site Assessment ■ Equipment maintenance ap
proaches and issues.
According to NFPA Standard 70B, ■ Facility zone temperature and
“as soon as new (electrical) equip humidity levels.
ment is installed, a process of nor ■ Facility lighting and CO2 levels
mal deterioration begins. ■ All significant control and
Unchecked, the deterioration pro operational problems.
cess can cause malfunction or an ■ All significant occupant comfort
electrical failure.” The same holds problems.
true for mechanical systems.

The CxA conducts a site assess


ment to evaluate how and why Effective Interviewing
building equipment and systems are
currently operated and maintained. ◆ Do not readily accept the first thing anybody tells you – they will
The CxA identifies for further in be telling you symptoms or results.
vestigation any significant problems
◆ Ask the same question three different ways to drill down beyond
reported by the O&M staff and
their concern to the root cause.
building occupants. The site assess
ment for retrocommissioning also ◆ Be patient.
includes a facility survey to deter ◆ Allow for silence – people are uncomfortable with silence and
mine occupancy and space utiliza will begin talking.
Retrocommissioning Process

■ Locations of building trouble component failures, unoccupied,


spots. varying outside air temperatures, fire
■ Current O&M practices. alarm, power failure, etc. The sys
tems are run through all of the con
Diagnostic Monitoring and trol system’s sequences of
operation. Components are verified
Testing
to be responsive per the prescribed
Diagnostic monitoring and testing sequences.
provides information on tempera
tures, critical flows, pressures, The findings of diagnostic monitoring
speeds, and currents under typical and testing are analyzed and com
operating conditions. By analyzing pared with the site assessment data.
this information, the CxA determines Any resultant changes are added to
whether the systems are operating the Master List of Deficiencies and
102 correctly and in the most efficient Improvements.
manner. The following diagnostic
methods are commonly used: energy Master List of Deficiencies
management control system and Improvements
(EMCS) trend logging, stand-alone
portable data logging, and manual The survey information is reviewed
functional performance testing. by the CxA. Based on the input
from the site assessment, the CxA
The CxA schedules the implementa develops corrective strategies and
tion of the diagnostic monitoring and prepares a Master List of Deficien
testing. The CxA works with the cies and Improvements. This forms
O&M staff to make sure equipment the basis of the project decision
and systems are ready for testing. It making and problem prioritizing pro
will be necessary for the Control cess. Specific solutions to the prob
technician to assist with the EMCS lems found are identified.
trend logging.
Every problem, deficiency, or oppor
The CxA oversees functional per tunity for increased efficiency that is
formance testing, which is per found during the investigation phase
formed by the O&M staff. is summarized on the Master List,
Functional testing is the dynamic including any minor adjustments and
testing of systems (rather than just repairs that are made during the
components) under full operation. course of the investigation process.
For example, the chiller pump would The list should include, for each
be tested interactively with the identified issue, the name of the af
chiller to see if the pump ramps up fected equipment or system, a de
and down to maintain the differential scription of the deficiency or
pressure set point. Systems are problem, and recommended
tested under various modes - low action(s).
cooling or heating loads, high loads,
Retrocommissioning Process

Control systems have become so sophisticated that few end users really understand fully how to use them to
optimize system performance. Typically, they are not programmed or calibrated correctly on the front end,
and maintenance professionals often bypass them completely to address exigencies.

In addition, any opportunities for the Master List as a guide, the Owner
installation of energy conservation determines which recommended im-
measures or adoption of more effi- provements to implement. Items
cient procedures and practices ob- should be prioritized according to
served during the investigation cost effectiveness, criticality, and
process, related to the retrocom- how effectively they meet the
missioned systems or not, are also project objectives. It is likely that
be identified. many of the recommendations will
have no cost/low-cost solutions, 103
In the final report, the CxA orga such as personnel habits, that can
nizes the deficiencies on the Master be implemented right away.
List into categories, such as design,
installation, maintenance, and opera To aid in the decision making, the
tion. This allows the Owner to iden CxA provides economic analyses
tify trends that are contributing to (estimated cost, savings, payback,
problems in certain areas. and return on investment) on those
items that can be quantified.
The retrocommissioning team also
performs “quick fixes” during the If substantial modifications or capi
discovery phase. These are simple tal improvements are required, for
repairs and adjustments, such as mal commissioning of the affected
connecting an unconnected section systems should be included during
of flex duct, unblocking a duct, the various construction phases as
tightening a fan belt, and cleaning a described in Chapter 5.
coil. Though relatively insignificant
in nature, these may be masking a
real problem.
PROJECT HAND-OFF
Documentation Requirements:
CORRECTIVE PHASE ◆ Updated Building Documenta
tion
Documentation Requirement: ◆ Final Retrocommissioning
◆ Master List of Deficiencies and Report
Improvements
During project hand-off, equipment
During this phase, cost-effective and systems are tested again to
opportunities are selected for imple confirm the operational and energy
mentation. Based on the findings of performance of the installed im
the site assessment and diagnostic provements.
monitoring and testing, and using the
Retrocommissioning Process

Monitoring and Verification including guideline for imple


menting an energy accounting
Diagnostic monitoring and testing is and tracking system with
performed again after the recom performance benchmarks.
mendations have been implemented. ■ Preventive maintenance plan, or
Post-implementation data is com a guideline to implementing a
pared to pre-implementation data to preventive maintenance plan if
confirm that the improvements are one does not exist.
integrated and working properly to ■ New condition baselines estab
gether and have the desired effect lished for the maintenance
on building performance. program.
Heating is becoming a big
issue in HVAC. Lighting heat ■ Operation and maintenance
load historically has been Diagnostic monitoring and testing is staff training materials, including
designed into HVAC load also used to benchmark the perfor list of operational strategies and
104 calculations. Now with effi mance of the improvements. This operational assessment.
cient lighting, there is a establishes parameters for measur
problem getting some spaces
warm enough.
ing the performance of the improve O&M Staff Training
ments throughout the life of the
equipment and systems. If a building is overly sophisticated,
the staff’s maintenance capabilities
Update Building Documen need to be aligned with that sophisti
cation.
tation
The following building documenta The CxA will provide additional
tion is updated by the Owner or by training, or arrange for training with
the CxA, depending on the scope of appropriate vendors, if warranted by
the service agreement, to reflect the improvements made to the
changes made to equipment and equipment and systems.
systems during the
retrocommissioning process: Final Retrocommissioning
Report
■ One line drawing schematics for
each system affected by the The final retrocommissioning report
improvements. includes a summary report of par
■ Operation and maintenance ticipants and their roles, building de
manuals and system operations scription, project objectives, an
manuals (including updated overview of the retrocommissioning
sequences of operation for scope, and a general description of
equipment). testing methods. The following items
■ Energy management plan, typically are also included:

“It has been estimated that 70- to 80-percent of all unplanned shutdowns (of electrical systems) are due to
human error, meaning that only 20- to 30-percent of unplanned shutdowns are due to equipment malfunc-
tions or poor design.” Source: A Practical Guide for Electrical Reliability, EC&M (Oct 2004).
Retrocommissioning Process

■ Retrocommissioning plan
BEST PRACTICES
■ Master List of Deficiencies and ■ Keep the retrocommissioning
Improvements scope focused on the facility’s
■ Cost/savings analyses for each mission.
implemented recommendation
■ Site assessment results ■ Concentrate on only the essen
■ Diagnostic monitoring and tials.
testing results (pre- and post-
implementation) ■ Collect only important and
■ Controls sequences and block especially useful information. Over the span of a few years, it
diagrams indicating component is highly likely that the build
functions and relationships ■ Link the retrocommissioning to ing systems have been modi
■ Updated TAB data the facility’s operating and fied. While modifying systems
■ Equipment condition baseline business objectives: is not a problem in itself, the 105
data lack of documentation can be.
■ All completed functional - It documents performance
performance test forms criteria and data for track
■ Recommended frequency for ing, evaluating, and improv
recommissioning ing systems.
■ Recommended frequency for
recalibration of sensors and - It correlates system perfor
actuators mance to monetary indices
■ Documentation of implemented through energy savings,
recommendations improved maintenance,
■ Energy saving features and improved worker productiv
strategies used in the building ity, and occupant satisfac
■ Listing of all user adjustable set tion.
points and reset schedules
■ Recommended frequency for ■ The documentation required by
review of set points and reset each commissioning process
schedules can be daunting, but will prove
■ Photographs of every defi an invaluable resource for
ciency found building management, O&M,
and future commissioning
Turning the Report into efforts.
Action
It is crucial for the facilities team to
buy into the report and results for it
to succeed, then for the documenta
tion to be used and maintained. It is
good practice to develop a checklist
of action items that can be ad
dressed, confirmed, filed, and refer
enced.
Retrocommissioning Process

STUDY QUESTIONS
1. What are the documentation requirements for each phase of a retrocommissioning project? Why are these
documentation requirements so important to the overall success of the retrocommissioning project?

2. What system and equipment are the best candidates for retrocommissioning investigation, and why?

3. How do the steps involved in retrocommissioning differ from the steps involved in new construction com-
missioning?

4. If building documentation already exists, is there a need to further develop or refine documentation during
106 retrocommissioning of that building?

5. What are the methods of investigation used during the retrocommissioning discovery phase?

6. What documents make up the final commissioning report developed at the conclusion of the
retrocommissioning project?

7. What role does the O&M staff play in retrocommissioning? The Owner? Is it necessary to hire an indepen-
dent CxA?
Recommissioning Process

Chapter 7
Recommissioning Process

R
ecommissioning refers to particularly if
commissioning of an ex they have been
isting building that has problematic or
already gone through the highly energy
commissioning process. It is per inefficient. 107
formed long after the facility is con However, re
structed and placed into service. commissioning
Some sources and providers use the is most often
term “recommissioning” synony applied to the
mously with “retrocommissioning” existing
to collectively address the commis building’s
sioning of existing buildings. HVAC, refrig
eration, and
Like all other forms of commission electrical sys
ing, the goal of recommissioning is tems and their
to ensure that all power-using and controls, which
power-conserving systems in a often are the
building work together to meet the sources of the
needs of the current occupants and biggest opera
the actual performance require tional problems: “Perserverance is the hard
ments of the Owner. work you do after you get
■ Increased occupant complaints tired of doing the hard work
Recommissioning provides addi ■ Increased or fluctuating energy you already did.”
tional opportunities to improve facil use Newt Gingrich
ity efficiency and addresses issues ■ Increased maintenance calls
that may have arisen since the origi
nal commissioning. It can help re Corrected, these systems also are
duce energy consumption, maximize likely to produce the biggest cost
the efficiency and output of the air savings. Recommissioning provides
and water distribution systems, en a systematic approach for finding,
hance performance, and enhance
the occupants’ working environment
and comfort. Like commissioning, This chapter describes the process for implementing recommis-
recommissioning may involve func sioning in existing buildings. Chapter 5 covers the commissioning
tional performance testing of most process, Chapter 6 covers the retrocommissioning process, and
or all major building systems, Chapter 8 covers continuous commissioning.
Recommissioning Process

Preventive maintenance in itself is


In this Chapter not enough because its procedures
tend to focus on specific component
◆ Project Planning care and not on an integrated sys-
◆ Design Review tem. The operations side of O&M
◆ Implementation and involves observing and monitoring
Verification the building’s systems to determine
◆ Periodic Review how and when they operate and if
◆ Best Practices they are producing and delivering
the desired result. However, in the
typical facility, other priorities take
verifying, documenting, and correct- precedence on the time-strapped
ing their deficiencies. staff and eventually even this good
intention may become neglected be-
108 Recommissioning can be undertaken yond periodic gauge readings and
as an independent process in re monitoring of energy management
sponse to a specific requirement or system output parameters. That is,
concern, or periodically scheduled as there is little-to-no trending or analy
part of the building’s operations and sis conducted that could be indica
maintenance program. Systems tend tive of sub-optimal conditions or
Recommissioning every five
to shift from their as-installed condi emerging problems.
years is required of all State
tions over time due to normal wear,
of California buildings
larger than 50,000 square user requests, and facility modifica During recommissioning, the tests
feet. tions. that were performed during the
original commissioning are repeated
Since a considerable investment has to check for persistence in results
already been made in the initial com against the baselines established at
missioning of the facility, it is recom that time. The objective is to ensure
mended that it be recommissioned that the building is operating as de
about every three to five years, as signed or according to newer
scheduled and as part of the preven operating requirements.
tive maintenance (PM) protocol.
One-third to one-fifth of the The development of new project
building’s applicable systems could documentation and testing proce
be recommissioned each year on a dures and forms is not required.
rotating basis. In that way, However, these documents can be
recommissioning is cost- and per updated if the building, its systems,
sonnel-budgeted as “business as equipment, and mission and
usual” and is not a special event. occupancy habits have changed
dramatically since their initial com
In general, the more substantial missioning. Nameplate data, inven
changes that a facility goes through, tory lists, training curriculum, and
the more often it should be recom as-built drawings should be updated
missioned if a continuous commis in any event, as part of the mainte
sioning program is not in place. nance program.
Recommissioning Process

Recommissioning generally in
cludes:
Recommissioning Process
■ Communicating among the
commissioning team and facility
staff, occupants, and users to Project Planning
uncover building system Determine project objectives
problems and opportunities. Determine commissioning scope: whole building or
targeted on problem equipment / systems?
■ Establishing that the original Hire CxA or assign duties to O&M personnel
basis of design (if available) and
operation plan are still appropri
ate for the use, occupancy, and
occupant mission of the build
ing. Design Review
■ Reviewing and benchmarking Review original design intent, basis of design, and 109
drawings and update if necessary for changes
key systems operations/ in building use, occupancy, etc.
performance against the Review original commissioning plan and commissioning
previous commissioning specifications and update if necessary
recommendations and
baselines.
■ Identifying past and current
persistent problems. Implementation and Verification
■ Reviewing maintenance Develop performance baselines
program procedures, schedules, Measure current equipment and system performance
Perform functional performance tests to verify that equipment
and protocols and verifying their and systems operate as designed
effectiveness against actual Make adjustments and retest if deficiencies are found
Review and update O&M manuals and staff training
equipment observations. Document energy and operational savings and comfort
■ Reviewing the operators’ and improvements in updated commissioning report
maintainers’ technical capabili
ties relative to the building’s
needs and to the training
program (or contractual re
quirements). Periodic Review
Site visits, interviews, energy use analysis, etc.
■ Performing energy analysis of Note substantial changes in facility use, occupancy, etc.
available data, including utility Write follow-up project report at 1 year
bills.
■ Identifying specific energy
conservation measures, particu
larly no-cost and low-cost ■ Validating and/or modifying the
solutions. operations/controls sequencing
■ Performing a condition assess as appropriate for optimum
ment using condition monitoring operations.
technologies. ■ Conducting testing, adjusting,
■ Recommending repairs and and balancing (TAB) on the
modifications to optimize HVAC air and water distribu
building performance. tion systems, as required.
Recommissioning Process

Recommissioning is not a redesign to energy performance, water


process. performance, maintainability,
sustainability, indoor environmental
PROJECT PLANNING quality, and environmental impacts.

Documentation Requirements: The Owner’s operating require


◆ Project Objectives Document ments are also an important part of
◆ Original and Revised Commis this document. For example, the
sioning Reports need to maintain a strict range of
humidity levels may require an air
During project planning, the Owner handling system to stay “on” at all
determines the project objectives times, when otherwise it could be
and recommissioning scope. The shut down during nights and week
Owner determines the recommis ends.
110 sioning team, including hiring an
independent, third party CxA or as If a specific system is identified, this
signing CxA duties in-house. document will include a list of com
ponents that require functional test
Project Objectives ing. For example, if the cooling
system is identified as problematic,
Document all system components would be
The Project Objectives document is listed for functional testing: chiller
prepared by the Owner. It provides condenser, chilled water pumps,
a general introduction of why the strainers, water treatment, heat ex
building is being recommissioned, changer, and controls.
and typically lists concerns, prob
lems, and occupant complaints. It The Project Objectives document is
also identifies requirements relative used by the commissioning team as
a guide and to stay focused when
conducting the recommissioning
tasks and in updating the building
Common Recommissioning Findings documentation.

◆ Variable speed drives no longer modulate properly. Determine the Recommis


◆ Controls are manually overridden. sioning Team
◆ Improper sequences of operation result in inefficient or ineffec-
The recommissioning team consists
tive machine operation.
of the Owner, CxA, Facility Man
◆ Building configuration, use, and/or occupancy have changed agement, O&M staff, any necessary
without considering the impact on HVAC and other systems. additional contractors (such as for
◆ Equipment is inadequately maintained, and observation of its controls and TAB support), and ven
condition does not necessarily match what is indicated on the dors. An independent CxA can be
PM checklist. hired to perform recommissioning, or
◆ Technician training has not kept pace with the fast-paced, the function can be assigned in
constantly evolving technology. house, using previous commissioning
Recommissioning Process

Appendix A.

guidance and data, existing test Procedures


forms, and knowledgeable staff.
Unlike commissioning, recommis
sioning involves testing and inspec
In either case, a work plan must be
tion that occurs in occupied spaces.
established that identifies required
This can have significant impact
support and training. The work plan
during testing, since operating se
includes a work schedule with mile
quences need to be tested and the
stones and target dates. If the work
building’s working environment con
is done in-house, the staff should be
ditions will be changed temporarily.
dedicated to the effort through its
Access to equipment in occupied
completion with no or minimal regu
spaces will also be a challenge, par
larly-assigned O&M work duties
ticularly if ladders and access to
and interruptions.
overhead units, air distribution com
Building occupants will
ponents, and lighting fixtures are re
Kick-off Meeting quired. The occupants need to be
modify their personal space to
achieve comfort. Tampering
111

The project kick-off meeting brings informed and brought into the pro with thermostats, sensors, and
the recommissioning team together cess to minimize disruptions to diffusers, and introducing de
to review the Commissioning Plan. themselves and to the testing. vices such as portable heaters,
contribute to the inefficiency
At a minimum, the CxA, TAB pro
vider and controls technician (as ap Document Review of a building’s HVAC systems.
plicable), Owner and/or designated
The document review includes re
representatives, and O&M Man
viewing work orders and trouble
ager should attend. Each team
calls from the building Owner, occu
member is introduced and their re
pants, and users to identify and sur
sponsibilities are stated. The
vey recurring, persistent, and/or
Owner’s expectations, goals, and
serious problems. Comments such
objectives are reiterated. Communi
as hearing “loud noises” from
cation protocols, schedules, and
ductwork or feeling walls vibrate
safety issues are discussed.
whenever an AHU kicks on are in
valuable in determining root causes
The kick-off meeting is also a good
of problems.
opportunity to conduct an interview
of occupants, users, operators, and
The commissioning team studies the
maintainers to determine the scope
building’s documented problems and
and degree of problematic condi
looks for trends and links. Mainte
tions from their perspectives (are
nance records, operating cost
the persistent hot and cold calls a
records, and energy use information,
systematic problem . The interview
as available, will prove helpful.
survey may take any form, but
should follow a prescribed outline.
As-built drawings are reviewed to
Sample interview questionnaires for
understand system configurations
building and maintenance
and modifications from the original
Management are included in
design documents. The building his
tory is also reviewed to check on
Recommissioning Process

During the design review phase, the


Case Study: No-Cost Measures Can Bring commissioning team reviews the
original design and subsequent com-
Big Savings missioning documentation to update
and reflect, if necessary, changes or
The building management system (EMS) of a corporate office
concerns such as:
complex in Massachusetts was programmed to allow after-
hours employees to dial a code to turn on a small (2,000 SF)
■ Different use or occupancy
area of lights as needed. However, over time the dial-in codes
patterns of the facility since its
were misplaced, so security staff would manually turn on the
previous commissioning.
lights for an entire floor. Typically, this meant that two floors of
■ How people interact to operate
lights (216,000 SF) would be illuminated for perhaps five night
the building systems from day to
owls. day.
To address this problem, the dial-in codes were redistributed to ■ Outmoded equipment or sys-
112 all staff members and posted in their appropriate zones. This tems.
no-cost measure resulted in annual cost savings of about ■ Equipment or systems that do
$45,000. (Source: Haasl, T. et aI, Pacific Northwest National not operate optimally and have
Laboratory, Retro-Commissioning’s Greatest Hits, March 2000.) high failure rates.
■ Persistent high energy costs.
■ Occupant complaints.
■ Need for the building to achieve
impacts caused by changes to the greater energy and water
internal configuration (new parti savings and a healthier indoor
tions?), occupancy (now 150 occu environment (e.g., for LEED
pants in the space, up from 75?), EB certification).
and mission (former warehouse con
verted into a laboratory or IT Cen Unfortunately, original information
ter?). O&M manuals are reviewed sources, such as calculations and
to ensure that product descriptions equipment specifications and submit
and recommended maintenance tals, may no longer be available and
schedules and procedures are accu may need to be developed.
rate for the equipment now in place.
Good O&M manuals include only The CxA reviews changes made to
applicable O&M guidance and data the design documentation for com
specific to the equipment installed – missioning facilitation, energy effi
not non-applicable models or ciency, control system optimization
manufacturer advertising. and strategies, operations and main
tenance effectiveness, indoor
DESIGN REVIEW environmental quality, O&M docu
mentation, training, and potential en
Documentation Requirements: hancements to the mechanical and
◆ Updated Design Documentation electrical systems. This creates the
◆ Updated Commissioning Plan benchmark against which all inspec
tion and test data is compared.
Recommissioning Process

Commissioning Plan ◆ Functional Performance


Checklists
The changes made to the design
documentation necessitates updat During the implementation and veri
ing the most recent Commissioning fication phase, the CxA measures
Plan as well. The Commissioning current equipment and systems per
Plan is updated to include informa formance and develops perfor
tion specific to the current recom mance baselines. Functional
missioning: commissioning performance tests are performed to
objectives, identification of equip verify that equipment and systems
ment and systems being commis operate as required. Selected im
sioned, commissioning team provements are made, and im
members, project organization, cur provements and operational and
rent conditions and changes since energy savings are verified and
the previous commissioning, and ap documented. The CxA also reviews 113
parent and declared problems and and recommends (or performs, as
opportunities that need further veri applicable) updates to O&M manu
fication and investigation. Areas of als and staff training.
emphasis may include:
Performance Baselines and
■ Heat exchangers
■ Heating and cooling systems Equipment and Systems
■ Air delivery and ventilation Measurements
systems
Baseline energy models of building
■ Control systems
performance are established to
■ Air and water system testing,
document a performance profile be
adjusting, and balancing (TAB)
fore and after recommissioning.
■ Lighting
Baseline energy models are estab
■ Building envelope
lished using anyone or combination
of the following data:
Recommendations focus on opti
mizing the performance of equip
■ Short-term measured data from
ment and systems in place.
dataloggers, building automation
Upgrades to include new technolo
system (BAS), or energy
gies and energy efficient measures
management and control system
may be recommended resulting
(EMCS).
from the recommissioning effort,
■ Metered long-term hourly or is-
but are treated as a separate action.
minute whole building energy
data.
IMPLEMENTATION AND ■ Historic utility bills for electric

VERIFICATION ity, gas, steam, and chilled or hot


water.
Documentation Requirements:
◆ Commissioning Report Trending allows the recommission
◆ Commissioning Plan (Final) ing team to observe performance
and output parameters under vari
Recommissioning Process

ous modes and conditions over time. pressure, current, light levels and du
Variables often trended include en rations, and similar information.
ergy, temperatures, pressures, flow
rates, weather data, and set points. A utility bill analysis, conducted early
By analyzing trends, the recommis in the project, gives the commission
sioning team characterizes perfor ing team a good understanding of
mance and validates whether or not how the building is consuming en
the systems operate correctly. ergy and the direction toward which
they should target their efforts.
Trending may be conducted by re
viewing and plotting BAS and All major equipment and systems
EMCS data over time. The commis are checked to record current oper
sioning provider may require assis ating parameters and to verify the
tance from the controls vendor, correct operation of their parts. This
114 particularly in developing, download is analogous to the verification
ing, and formatting system data for checks in new construction and
analysis. renovation commissioning. Verifica
tion checklists that were developed
Dataloggers also provide a trending when the building was first commis
capability. These are small, portable, sioned can be used again.
battery-operated devices utilize soft
ware that can be downloaded onto a This is also an appropriate time to
laptop and easily graphed and ana check the equipment condition, if it
lyzed. Data collected typically in is not already done in a Reliability
cludes temperatures, humidity, Centered Maintenance (RCM) pro
gram, using available condition and
predictive technologies such as in
frared thermography, vibration
analysis, equipment alignment, air
borne ultrasonic leak detection, oil
analysis, insulation testing, and motor
analysis.

Any significant problems found dur


ing equipment and systems
measurements are noted and cor
rected by the O&M staff prior to
functional performance testing.

Sensors and actuators should be


calibrated prior to functional testing,
and checked by the CxA.

How not to repair a leak (actual example taken in the field).


Recommissioning Process

Functional Performance
Testing Recommissioning In Action
The CxA schedules, oversees, wit- A middle school was experiencing severe indoor air quality prob-
nesses, and documents the func- lems and the school district requested the help of a commissioning
tional performance testing of all consultant. Recommissioning found that among other things, all of
equipment and systems according to the building’s fresh air vents were closed and systems were not
the Commissioning Plan. The facil- operating as originally intended. Since the original controls con-
ity O&M staff executes the tests, tractor had gone out of business, each time an occupant com-
which use the same protocols and plained about the building’s comfort level over the years, the
forms that were developed when maintenance staff responded by closing the offensive vent, thereby
the building was last commissioned. addressing the symptom, not the root cause.
Functional testing includes operating
the system and components through The commissioning team confirmed that the HVAC systems, when
the significant normal and emer- new, had been installed correctly. The facility would have most likely 115
gency modes of operation, including: functioned adequately had the support staff understood from the
start the control system, its maintenance requirements, and how it
1. Each of the written sequences functions. (Source: E. Thomas Lillie, “Better Late than Never,” Engi-
of operation neered Systems Magazine, May 25, 2000.)
2. Start-up and shut-down
3. Unoccupied mode
4. Manual mode gers to provide a high level of confi
5. Staging dence in proper system function.
6. Miscellaneous alarms
7. Power failure Building Management
8. Interlocks with other systems
or equipment Systems (BMS)
Recommissioning the BMS is one of
A sample functional performance the most cost effective building and
test form is included at the end of energy performance measures that
Appendix A, Sample Commission can be undertaken. The operational
ing Forms. status and correct programming of
each strategy of the BMS is veri
Simple repairs and adjustments, fied. This requires trending of the
such as belt replacement, damper BMS data over time to see if the
adjustment, and sensor calibration, strategies are actually controlling
not detected earlier and found dur the equipment as they should. The
ing the investigation may be done at cause of malfunctioning control
this time to maximize system effi strategies is then determined. For
ciency and to enable system testing, example, is the system not operat
adjusting, and balancing. ing’ correctly because of a software
programming error? Overridden
Functional testing is accomplished control strategy? Ineffective sensor
using a combination of conventional locations? Malfunctioning compo
manual methods, control system nents?
trend logs, and stand-alone data log-
Recommissioning Process

the building configuration, use, and/


Countdown of the Seven Most Common BMS or occupancy; and the need for the
maintenance staff to frequently ad-
Problems just the HVAC components.
7 – The BMS operator does not have a good understanding of A TAB analysis involves the
energy conservation. measurement and verification of air
6 – Failed components are not replaced. system flow rates, water system
5 – The full sequence of controls is not verified at the time of (HVAC) flow rates, temperatures of
system acceptance. heating and cooling delivery sys-
4 – Control devices and sensors are disabled “temporarily” to tems, positions and functionality of
delivery system flow control de-
satisfy immediate occupant complaints.
vices, settings and operation of the
3 – Disabled energy conservation features, such as by power controls system and components,
116 outage, are never reset. and fan and pump speeds and pres-
2 – The BMS is not properly programmed. sures. Observations are made
1 – The maintenance staff does not have the time, or is inad- against the building’s design docu
equately trained, to thoroughly diagnose BMS problems. mentation and are documented in a
formal Test and Balance Report.

All analog and digital in- and out Maintenance Program


points are verified. Heating and
cooling setpoints and setbacks are In existing facilities, a review of the
checked, and heating and cooling re maintenance practices and observa
set schedules are checked for accu tion of the actual equipment appear
racy. ance and operation may uncover
deficiencies in the program. Recom
missioning provides an opportunity to
Testing, Adjusting, and
review the program, identify defi
Balancing (TAB) ciencies, recommend improvements,
Testing, adjusting, and balancing establish best practices, identify
may or may not be part of the re training needs, and document a new
commissioning process. TAB is the program, as required.
process of adjusting HVAC system
components to supply air and water Deficiencies and Retesting
flows to match the requirements. In
Each equipment and system tested
ordinate indoor temperature fluctua
must pass its functional performance
tions, excessive drafts, and improper
test to ensure that it is installed and
air distribution causing hot and cold
operating according to the current
spots lead to occupants’ discomfort
requirements. Corrections of minor
and excessive energy use. Indica
deficiencies (e.g., fixing a controller,
tions that TAB is required include
adjusting alignment) identified can
frequent occupant complaints of dis
be made by the O&M staff during
comfort due to hot and cold spots;
the tests at the discretion of the
cardboard taped over air registers at
CxA.
workstations; a significant change in
Recommissioning Process

The highest priority is to solve exist


The CxA records the results of the ing problems with no- and low-cost
test on the procedure or test form. measures. Typical examples include:
Deficiencies or non-conformance
issues are noted and reported to the ■ Calibration of building controls,
Owner on the Master List of Find such as thermostats and
ings or Findings Log. This is per occupancy sensors.
haps the most important tool of the ■ Adjusting BMS schedules to
recommissioning process and as ensure that equipment runs only
sists the Owner in prioritizing when necessary.
recommended and needed correc ■ Checking for and replacing
tive measures. The list identifies ev malfunctioning steam traps.
ery finding detected, including fixes ■ Cleaning condenser, evaporator,
that are made in the field, estimated and boiler heat exchanger
costs, savings, and paybacks. The tubes. 117
list may appear in any order, but
categories such as no cost/low cost, Implementing higher cost corrective
medium cost/ short term, and high measures and non-remedial im
cost/long term have proven to be provements that optimize equipment
valuable for prioritizing, budgeting, and systems follows. The Owner’s
and project programmmg. approach to implementing improve
ments depends on in-house capabili
Systems are retested after the defi ties, life-cycle cost analysis,
ciencies are corrected to ensure available funding, and the Owner’s
that they do, in fact, operate and de degree of comfort with the recom
liver the desired outcome as mendations relative to the impact on
needed. operations and mission.

Implementation of Once the improvement


is completed, the sys
Improvements
tem documentation is
Many changes that are made will updated to reflect
be no- or low-cost. For recom changes to affected
mended major improvements, such control sequences.
as replacing an old boiler system Also, it is important to
with an energy-efficient modulating retest the equipment
type with reheat or installing a new and systems to ensure
building automation system, infor that the improvements
mation on costs, estimated energy are working as ex
savings, payback, and return on in pected. The retesting
vestment are prepared. In addition, can take the form of
an A/E and specialized contractors utility trending, observa
may need to be consulted for com tion, datalogging, func
plicated improvements. tional testing, or as a
Recommissioning Process

Case Study - Finding the Optimal Solution


The recommissioning of a 300,000 SF hospital in California indicated that triple duty valves on the building’s
condenser pumps were only 20% open. They were throttled back because the pumps were significantly
oversized and pumping too much water. Throttled valves reduce water flow, but also add pressure drop to the
system, thereby wasting energy.
In most cases, water flow is best reduced by trimming the pump impellers and opening the valves at the pump
discharge. If pumps (and fans) are equipped with variable speed drives (VSD), it is tempting to balance the
system by slowing the pump down with a drive rather than trimming the impellers. While better than throttling,
the result is not optimal since drive efficiency drops as a function of load and drive speed.
A recommissioning recommendation may be to best optimize the system’s overall efficiency by adjusting the
impeller size so the pump delivers the design flow when the drive is at full speed, and then using the VSD to
118 match actual load conditions. (Source: Haasl, T. et al, Pacific Northwest National Laboratory, Retro-
Commissioning’s Greatest Hits, March 2000.)

combination of these, and the data gas, and chilled and hot water are
compared to the initial baseline data. reviewed for long-term monitoring.
This new baseline data becomes the
baseline against which future Final Commissioning Plan
recommissioning activities will be
compared. The CxA finalizes the updated Com
missioning Plan after functional per
Monitoring and Verification formance testing is complete,
recommended improvements have
The impact of the minor adjustments been implemented, and there are no
made during the functional perfor more changes or equipment substitu
mance testing and of any imple tions planned.
mented improvements is
monitored over a reasonable time to Commissioning Report
verify their impact on occupant
comfort, on operational and energy The fmal Commissioning Report is a
performance, and on control se record of the recommissioning ac
quences and schedules. tivities and measures implemented
and recommended for implementa
Room-by-room measurements are tion. It incorporates a summary re
made using hand-held meters or por port of participants and their roles,
table dataloggers. Energy model building description, project objec
data is collected using the short-term tives, an overview of the commis
methods discussed previously. Utility sioning scope, and a general
bills and meter data for electricity, description of testing methods and
results. The Commissioning Report
Recommissioning Process

includes and is a formal, permanent Operation and Maintenance


record of the following:
Manuals
■ Executive summary. As a function of the recommission
■ Commissioning Plan (updated). ing effort and continuous improve
■ Current building performance. ment, the CxA reviews the
■ Description of existing system operation and maintenance manuals
conditions. and updates the manuals as needed.
■ Functional performance test Particular attention is given to re
results, including a list of vised as-built drawings, design intent
deficiencies found and cor modifications, changed sequences
rected. of operation, new and updated
■ Description of implemented operating instructions, functional
improvements and their impact performance test procedures and
on system performance. results, new condition baselines, 119
■ Description of implemented guidelines for continuous mainte
operation and control proce nance, improved maintenance
dures and their impact on schedules and checklists, updated
system performance. manufacturer and vendor contact
■ Cost/savings analyses for each lists, training requirements, and any
implemented recommendation. new warranty information. The
■ Modifications to O&M prac manuals are also re
tices and guidelines. viewed mindful of any
■ Monitoring and verification changes to the system
results. function and to user Sources for Help
■ Recommended frequency for and occupancy pat
Some Federal and state agencies
recommissioning. terns.
maintain electronic libraries available
■ Additional recommendations.
through the Internet that can assist the
■ Estimated energy savings in Equipment and user in recommissioning their facilities.
MBtu/SF and $/SF.
■ Estimated cost and payback
Controls Docu These libraries include tools, specifi-
calculations for recommenda mentation cations, regulations, publications, case
tions not implemented at the studies, commissioning plans, sample
Similarly, inventory lists reports, and other often-needed infor-
time of the recommissioning.
are updated for the mation. Two good Federal resources
building’s main energy are the U.S. Army Corps of Engineers’
It is very important for the Owner
consuming equipment. Commissionpedia - Electronic
and facility staff to receive ad
Important information Sourcebook for Building Commission-
equate documentation and training
typically includes ing and the General Services
to enable them to make the recom
nameplate data, equip Administration’s Project Planning
mended improvements. The Com
ment identification and Tools. The Califiornia Commissioning
missioning Report becomes new
location, and the date
documentation for the building’s his Collaborative also provides this infor-
installed. Updated con
torical files and for implementing, mation and more. All resources are
trol system documenta
operating, and maintaining the mea listed in the references at the end of
tion should include a
sures and prescribed operating pa this chapter.
full and complete point
rameters.
Recommissioning Process

list of DDC inputs and outputs, their Owner. Since staff members who
associated component, sensor or ac lack systems expertise are often the
tuator type, and alarm limits. Se root cause of many problems that
quences of operation should be necessitate recommissioning ser
updated for each HVAC and lighting vices in the first place, the training
system, with the rationale for any should be given high priority.
changes and deviations hi-lighted for
the Operator’s understanding. Up
dated system diagrams also assist
PERIODIC REVIEW
the operators and maintainers by de Documentation Requirement:
picting the entire system in sche ◆ First-Year Report
matic format rather than in
component bits and pieces. The CxA performs follow-up site
visits and interviews at periodic, pre
120 O&M Staff Training scribed intervals with Facility Man
agement and O&M staff to review
Training should actually be hands-on the system operation, identify any
and take place throughout the re operating problems, and recommend
commissioning process. further improvements.
The CxA provides additional train
ing, or coordinates and arranges for Energy data is reviewed periodically,
training with appropriate vendors in if not continuously, to assess the
conjunction with the recommission need for further recommissioning.
ing, if the improvements made to the At this time, increased building en
equipment and systems warrant ad ergy consumption and decreased
ditional familiarization or emphasis performance efflciency is flagged.
or if a particular operation or prac The CxA then works with the O&M
tice is of a particular concern to the staff to perform an evaluation, de-

References
1. Retro-Commissioning’s Greatest Hits, Haasl, Tudi et aI, Pacific Northwest National Laboratory, March
2000.
2. A Practical Guide for Commissioning Existing Buildings, Haasl, Tudi and Terry Sharp, April 1999.
3. Energy Star Buildings Manual.
4. Commissionpedia, U.S. Army Corps of Engineers; available online at www.cecer.army.mil/KD/HVAC/
index.cfm?chn_id=1136.
5. Project Planning Tools, U.S. General Services Administration; available online at
www.projectplanningtools.org.
6. State of California Guide to Commissioning Existing Buildings, California Commissioning Collaborative,
February 2006; available online at www.CACX.org.
Recommissioning Process

velop measures to restore the build and documentation you can

ing energy and operational perfor provide from the initial commis

mance, and implement the sioning process, the better.

measures.
■ Recommission the entire
Building staff play a key role in building every three to five
tracking the measures after they years, or put in place an ap
have been implemented to ensure proach in which one-third to
that they work properly. This avoids one-fifth of the building’s
the need for the CxA to make a re systems are recommissioning
turn visit to verify that savings are each year, on a rotating basis.
persisting. This makes recommissioning
“business as ususal” rather than
A first-year report is developed by a special event.
the CxA. It documents measured 121
energy savings, recommends any ■ The more substantial the
additional changes or building im changes a facility endures, the
provements, provides recommen more frequently it should be
dations for ongoing O&M staff recommissioned.
training, and establishes a schedule
for future recommissioning, if a ■ Integrate recommissioning into
continuous commissioning program the facility’s preventive mainte
is not established. The more fre nance program to improve the
quently the building undergoes performance of both ap
changes in facility use and occu proaches.
pancy patterns, the more often the
building should be recommissioned. ■ When recommissioning with a
limited budget, focus first on
BEST PRACTICES HVAC, refrigeration, and
electrical systems and their
■ Employ recommissioning to controls, which are often the
improve facility efficiency and sources of the biggest opera
address issues that may have tional problems.
arisen since the original com
missioning. ■ Focus also on low- and no-cost
recommedations, as these can
■ Keep recommissioning in mind have a surprisingly big impact
when performing initial building on the facility’s bottom line.
commissioning: the more forms
Recommissioning Process

STUDY QUESTIONS
1. What building systems are most often involved in recommissioning, and why?

2. How long after initial building commissioning should one wait to recommission the facility? What factors go
into determining how long to wait before recommissioning?

3. How does recommissioning differ from retrocommissioning? How are the two processes similar?

4. How can recommissioning be integrated with an existing preventive maintenance program?

122 5. What are typical items to look for during the design review phase of the recommissioning process?

6. How important is it to establish a performance baseline, and what are some typical methods for baseline
development?

7. What role does TAB play in recommissioning?


Continuous Commissioning Process

Chapter 8
Continuous Commissioning
Process
Process

detect any

ontinuous commissioning abnormal

is a form of remote intel conditions –

ligence. The primary fo the fault

cus of continuous detection


123
commissioning is ensuring the per phase.

sistence of building systems optimi


zation. It is an ongoing process for ■ If an abnormal
existing buildings, employed to re condition is
solve operating problems, improve detected, then
building comfort and safety, opti fault diagnosis
mize energy use, and improve sys is used to
tem reliability. evaluate the
fault and
As in recommissioning, continuous diagnose the
commissioning takes place only cause of the
when the facility has been previ abnormal condition. A resting body tends to stay
ously commissioned, since it needs at rest and a body in motion
tends to stay in motion un
a baseline for comparison. Its ob ■ Following diagnosis, during the less acted upon by an outside
jectives are essentially the same – fault evaluation phase, the force.
identifying and correcting building magnitude and impact of the
system problems and optimizing fault on factors such as energy Law of Physics
systems performance and reliability use, system reliability, and plant
in existing buildings. The major dif operations is determined.
ference between recommissioning
and continuous commissioning is in ■ Finally a decision is made on
the degree of persistence. how to react to the fault.

A typical continuous commissioning In many cases, detection of faults is


approach can be viewed as having relatively easier than diagnosing
four distinct functional processes as
shown below: This chapter describes the process for implementing continuous
commissioning in an existing facility. Chapter 5 covers the commis-
■ The first of the functional steps sioning process for new construction and major renovation, Chap-
is to monitor the building ter 6 the retrocommissioning process, and Chapter 7 the
system(s) or subsystem(s) and recommissioning process.
Continuous Commissioning Process

as 50 percent to allow for contingen-

In this Chapter cies and possible growth. The end


result is oversized units running at
inefficient part loads. Continuous
◆ Project Development Phase commissioning seeks to mitigate
◆ Implementation Phase those situations.
- Step 1 - Fault Detection
- Step 2 - Diagnosis Continuous commissioning is closely
- Step 3 - Fault Diagnosis related to (and often integrated into)
- Step 4 - Fault Reaction a facility RCM program. By mea-
◆ O&M Staff Training suring output parameters (e.g., tem-
◆ Best Practices peratures, pressures, volumes) and
trending them over time or tracking
them relative to alarm limits, im-
124 them or determining their impacts. pending problems can be investi-
For those familiar with Reliability gated and averted.
Centered Maintenance (RCM), the
process of detection, diagnosis, risk The subtle difference is that instead
analysis, and outcome is similar to of emphasizing a system or
While commissioning focuses RCM’s decision logic tree. component’s current condition and
on bringing the building op predicting an impending failure like
eration to the design intent, This process is both “continuous” RCM, continuous commissioning
continuous commissioning (uninterrupted) and “continual” (re emphasizes optimal building and sys
focuses on optimizing HVAC curring regularly and frequently). tems operation to meet current out
system operation and control Ensuring that building systems re put requirements. Where RCM is
for the existing building con
main optimized continuously re heavily reliant on predictive tech
ditions.
quires: nologies, continuous commissioning
incorporates the permanent installa
■ Benchmarking of energy, tion of metering equipment, software
operations, and output data, and building automation sensors.
■ Continuously gathering new (RCM also incorporates this avail
data, able output information as one of its
■ Making comparisons between many analytical tools.) On-going pe
that new information and the riodic (hourly) output and energy
benchmark data and against metering, monitoring, and analysis is
pre-established metrics and conducted automatically to detect
trends, and proactively when some event, defi
■ Establishing new baselines. ciency, or impending failure is im
pacting a system’s efficiency.
Continuous commissioning also in
volves finding opportunities that will Continuous commissioning is re
make the building run better and to ported to have produced typical sav
its maximum efficiency without sac ings of 20 percent with payback
rificing occupant comfort require under three years (often one to two
ments. Designers historically have years) in more than 130 large build
oversized HVAC units by as much
Continuous Commissioning Process

Continuous Commissioning Process

Project Development
Decide which equipment and systems will be
analyzed for potential improvements
Conduct commissioning audit and develop project
scope
Hire CxA or assign duties to O&M personnel
Develop detailed work plan and form project team

Process begins again when


Implementation and Verification periodic review indicates 125
Develop performance baselines that the building,
Measure current equipment and system performance and equipment, and/or systems
develop recommended improvements are not operating at optimal
Track, trend and analyze energy and performance data for levels (anomalies are
anolmolies found)
Implement recommended improvements
Document energy and operational savings and comfort
improvements

Periodic Review
Continue to track, trend and analyze energy and
performance data for anolmolies
Follow-up site visits and interviews
Write follow-up project report at 1 year

ings according studies by Texas involves conducting a needs assess


A&M University. ment where a walkthrough is made
by Building Management to identify
PROJECT DEVELOPMENT and discuss the Owner’s expecta
tions for comfort performance,
PHASE building energy performance, and
known problems. It also involves a
Documentation Requirement: facility survey, review of equipment
◆ Project Work Plan performance data and histories, and
an assessment of the available auto
The first step of continuous com mated system tools, which are es
missioning is performing an assess sential for the continuity of the
ment of whether continuous commissioning program, and their
commissioning makes sense. This capabilities.
Continuous Commissioning Process

These automated systems are typi cell phone, and a service technician
cally a facility’s building automation responds as necessary. Some sites
system (BAS) or energy manage incorporate an enterprise energy
ment and control system (EMCS), management system (EEMS), which
which provide local, remote-capable, uses the Internet to connect all ma
system alarm, control, and archiving jor energy-consuming devices in a
information. They allow Facility facility or group of facilities, for ad
Management to monitor, manage, ditional analysis and problem solu
and control mechanical systems and tions.
lighting remotely. Consumption and
control parameters are trended and If it is found that continuous com
compared. Alarms are indicated, missioning has merit, the process
usually communicated to a pager or continues with the formation of the

126

Automated and Continuous Commissioning Flow Chart

Building System Component

Decision

Fault No Fault
Detection
Tolerate Request
Repair
No Action Proactive and
Fault Required Diagnosis Continue

Tolerate? NO
Measurements

Passive Fault Pro-Active


Diagnosis/ Diagnosis for
Isolation Fault Reconfigure
NO
Resolution the Controls

Fault
Reconfigure
Diagnosed Controls?
Reconfigure

Fault Evaluation
• Safety
• Availability
• Energy/Cost Impact Operate
• Comfort Alarm/
• Environment Impac Shutdown

Continue to NO
Operate?

Adapted from: Methods for Automated and


Continuous Commissioning of Building Systems –
PECI/ Battelle April 2003
Continuous Commissioning Process

commissioning team and develop ■ Provides information / commis


ment of the work plan. sioning reports to Management,
obtains “buy-in” and approval,
Commissioning Team and provides feedback and
guidance back to the team.
Continuous commissioning is usually ■ Follows up on the implementa
implemented and conducted in tion of recommended changes.
house with facility O&M staff, or
the data can be transmitted elec Commissioning or Systems
tronically to an independent analyti Engineer
cal laboratory where it is captured,
■ Develops automatic monitoring
stored, and analyzed on a subscrip
tion basis. and field measurement plans.
■ Establishes and maintains
The continuous commissioning team system performance baselines.
127
■ Monitors and interprets data
consists of at least three individuals:
the Facility Manager or Owner’s and trends.
■ Diagnoses the causes of faults
Representative (Commissioning Au
thority); a systems engineer (Com and their impacts.
■ Conducts engineering analyses.
missioning Engineer); and a systems
■ Develops system improvement
technician (Commissioning Techni
cian). Each has a distinct role in the measures.
■ Develops improved sequences
continuous commissioning process:
of operation, control schedules,
and set-points.
Commissioning Authority /
■ Directs programming changes
Facility Manager
to the BAS/EMCS/EEM
■ Prepares a team charter and software.
ensures responsibilities and ■ Estimates potential energy
authorities are properly re savings and costs to implement
flected in the appropriate recommended measures.
position descriptions (contract ■ Develops implementation
document if the function is schedules.
outsourced). ■ Provides guidance to the
■ Coordinates the activities of the technicians implementing
commissioning team. recommended changes.
■ Establishes team objectives ■ Documents findings and
relative to the Owner’s require periodically updates the com
ments. missioning reports.
■ Determines metrics to be
achieved. Commissioning or Systems
■ Establishes and maintains Technician
schedules and milestones.
■ Provides input based on knowl
■ Reviews results and approves
remedial actions within his or edge and experience, and
her authority. building, system, and equipment
histories to the engineer to be
Continuous Commissioning Process

Sample Commissioning Forms at the


- Reliability end of this guidebook. Plans similar
RCM - Predict Failure to these should be developed and

( (
Equipment used so that the effort stays fo-
Condition cused, coordinated, and thoroughly
- Meet Output documented.
Continuous
Requirements
Cx
- Optimize Efficiency
IMPLEMENTATION PHASE
Documentation Requirements:
considered during the commis- ◆ List of Improvements Selected
sioning analyses. for Implementation
■ Conducts field measurements. ◆ Commissioning Report
■ Helps interpret collected data,
128 as required. The assessment may only identify
■ Implements mechanical, electri suspected areas for improvement.
cal, control, and systems There may be a need to obtain more
software changes recommended complete and exact data on when
by the Systems Engineer. and how systems are actually oper
ating. Using the most recent
Work Plans baseline data from previous commis
sioning efforts, the commissioning
Appendices J and K of PECI/ team compares it to the actual col
ORNL’s A Practical Guide for lected data manually or automati
Commissioning Existing Buildings cally.
provide good examples of detailed
work plans. These plans document
and maintain a focus on the systems
Step 1 - Fault Detection
being monitored and at what points, Diagnostic monitoring allows the
the devices performing the monitor commissioning team to observe criti
ing, their settings and locations to cal parameters such as inside and
ensure continuity, minimum and outside temperatures, humidity,
maximum allowable parameters, and flows, pressures, speeds, noise lev
recommended actions in the case of els, light levels and intensities, and
non-compliance or alarm situations. more under typical operating condi
They also include identification of tions. Three of the most common di
involved personnel, general informa agnostic monitoring methods are
tion narratives, special instructions, BMS/EMCS/EEM trend logging,
and step-by-step procedures, as ap standalone data logging, and manual
propriate. functional performance testing.

Diagnostic monitoring, trending, and BMS/EMCS/EEM Trend Logging


functional performance test plans
Facility performance data are gath
are reproduced in Appendix A,
ered from the building’s BAS or
Continuous Commissioning Process

EMCS using open protocols and


software algorithms. Automatic Case Study: Continuous Commissioning
trend logging can provide a wealth
of system information using minimal in Action
human effort and with reasonable
A medical center in Texas was commissioned in 1992, recom-
accurancy. It also can automatically
missioned in 1993, and produced savings of $145,000 and
alert when conditions approach ab-
$62,500 respectively. Continuous commissioning techniques
normal.
were applied in 1994 and obtained an additional $195,000 per
year savings on the same systems that had been previously
However it is important that the
commissioned to design specifications. (Source: Culp, Charles
sensors’ calibration be maintained
H. et al, Continuous Commissioning in Energy Conservation
and that the user has confidence in
the accuracy of the collected data. Programs, http://energysystems.tamu.edu.)
Another drawback of relying solely
on the BMS/EMCS/EEM for diag- 129
nostics is that its sensors are per
manently mounted and installed, and Functional Performance Testing
taking measurements at other loca Manual functional performance
tions is not possible. testing may be conducted to verify a
system’s correct operation and to
Some sites have outsourced their pinpoint problems. It involves putting
BMS/EMCS/EEM functions to re each system or piece of equipment
mote providers. Many of these have through a series of tests that check
moved beyond alarm response and the operation under various modes
troubleshooting to trending and iden and conditions. The condition can be
tifying system deficiencies and op simulated or a mode of operation
portunities for improved efficiency. can be forced manually. Data are
This information is then used to gathered by taking spot measure
make better informed design deci ments using hand-held instruments
sions in the future. such as multi-meters, ammeters, in
frared cameras, and light meters.
Portable Data Logging The data is then compared against
Portable data loggers are good for the baseline, other diagnostic results,
short term diagnostic and monitoring and/or design or desired require
activities. These are small, battery- ments.
powered devices that are easily in
stalled, often with magnets, and It is beneficial to conduct all three
removed without disruption to the diagnostic methods simultaneously,
building occupant. While some indi if possible. For example, if the func
cate current real-time conditions, tional performance testing is con
others are highly sophisticated and, ducted while data loggers are still in
when downloaded on a laptop or place, the results will be perma
other device, will trend, graph, and nently recorded and can be graphed
analyze the collected data. Manual and analyzed. At the same time, the
testing and spot observations do not EMCS can be used to view the
provide this level of accuracy. various responses as they occur.
Continuous Commissioning Process

rithms to detect and diagnose prob


Trend logs are vital tools to aid diag lems in the equipment. They reduce
nostics. They frequently reveal un the significant time burden of gath
expected results. Some recorded ering, downloading, and converting
examples include: data into a suitable format for analy
sis and reduce the analysis time as
■ Boilers firing for short spurts well. They also reduce the required
during the summer cooling skill level of the person conducting
season for no apparent reason. the testing, since most of the techni
■ Energy spikes occurring at cal expertise is required up front in
about 2:00 a.m. each day over a setting up and then maintaining the
month’s time with no known software. Examples of semi-auto
cause. mated diagnostic tools are:
■ Control dampers and valves
130 completely recycling every five Whole Building Diagnostician
or ten minutes. (WBD) developed by Pacific North
west National Laboratory - The
Step 2 - Diagnosis Whole Building Diagnostician has
two modules: Overall Energy Use
Semi-automated diagnostic tools are and Economizer Optimization. The
available that rely on data that is col Overall Energy Use Module calcu
lected by the BAS and portable data lates the total building energy use as
loggers and then use internal algo- a function of outside air temperature
and other key parameters. Over
time, when the total energy use ex
ceeds a pre-established alert level, it
Common Problems Detected by alarms the user. The Economizer
Module periodically measures the
Diagnostic Tools condition parameters of air flows,
◆ Uncalibrated and failed sensors outside conditions, and status data to
determine the operating state of
◆ Simultaneous heating and cooling AHUs. Both modules detect faulty
◆ Leaking valves or misplaced sensors and estimate
◆ Unoccupied periods energy and cost impacts of all prob
◆ Inadequate ventilation rate lems found. The economizer module
further identifies probable causes of
◆ Economizer opportunities the problem and recommends reme
◆ Improper terminal outputs dial measures.
◆ Setpoint deviations
◆ Incorrect of ineffective sequencing Performance and Continuous Re
commissioning Analysis Tool
◆ Poor efficiency (PACRAT) developed by Facility Dy
◆ Excessive cycling namics Engineering - The PACRAT
◆ Excess energy use relative to the provides trend data recorded and
baseline stored by a BMS/EMCS, data log
Continuous Commissioning Process

gers, or metering system. Compar-


ing collected data to a baseline, it A properly implemented continuous commissioning program will:
diagnoses system problems and
poor performance, and identifies en- ◆ Reduce energy usage and costs through monitoring and
ergy wastes. It integrates weather management
data as necessary. It includes “ex- ◆ Improve comfort, health, and safety of building occupants by
pert” advice on the possible cause maximizing the air quality of their working spaces
of the anomaly and how to correct ◆ Improve the condition and reliability of the building operating
it. It identifies energy waste, why it systems
is occurring, and suggests how to
◆ Facilitate compliance with the EPAct and current energy Ex-
remedy it.
ecutive Orders.
ACRx Palm Pilot tools developed
by Field Diagnostic Services
- The ACRx Palm Pilot tools allow 131
for the field testing of HVAC equip
Baselines
ment and controls. Using thermody The CxA refers to the original and
namic principles, these tools detect any subsequent commissioning
and diagnose HVAC problems, per baseline data. Then, using data from
form short term monitoring of the BAS/EMCS and other installed
HVAC parameters, and monitor meters and data loggers, compares
long term controls performance. the results.

AEC ENFORMA - This software The baseline performance criteria is


programs data loggers to gather and re-evaluated at least annually, since
process performance data. It assists settings tend to drift away over
in setting up optimum data points time. Changed building uses, mis
and provide the user with graphs of sions, occupant changes, configura
the collected data. Trend analysis tions, and even weather patterns all
remains primarily a manual process. will have some impact. For ex
ample, a previously unoccupied
Manufacturers also provide diag space may become occupied or the
nostic capabilities in many of their building may have had a mission
equipment controllers. For example, change from an administrative cen
chiller controllers have long had di ter to a conference area. It is pos
agnostic capabilities through a hu sible that due to these changes, the
man interface and digital display baseline may no longer even be
that show operating and diagnostic achievable, the systems operation
codes, compressor status, setpoints, and efficiency no longer optimal,
specified temperatures, specified and higher energy costs may likely
pressures, and enable/disable fea be the result.
tures and options. Faults and oper
ating conditions are identified and In addition to the system perfor
percent load and percent kW are mance and output data, it is also
displayed that indicate the loading necessary to look at energy infor
condition and efficiency of the mation. Comparative energy data
chiller.
Continuous Commissioning Process

may be accumulated using any one tem to measure space temperatures


or a combination of the following: and reduce duct static pressure
gradually until the lowest static pres
■ Short-term measured data from sure that maintains occupant com
data loggers, BAS, or EMCS. fort is found. That setting would
■ Metered long-term hourly or 15 remain until it is again adjusted
minute whole building energy manually.
data.
■ Historic electricity, gas, and Continuous commissioning performs
steam utility bills. that same procedure, but with nec
essary adjustments, over and over
The Facility Manager reviews the again several times a day. Instead of
energy data at least quarterly. If the finding a single optimum setpoint, the
Continuous monitoring al building energy consumption has in BMS/EMS/EEMS is used to find the
132 lows the Owner to observe creased relative to established most appropriate setting under
energy consumption patterns metrics and baselines, the systems changing conditions – morning ver
and see how they change un
engineer investigates to determine sus afternoon, summer versus win
der varying conditions,
thereby helping the Owner its possible causes, with input as ter, and so forth. The end result is
make informed utility pur needed from the operations staff. that energy usage is held in check
chasing decisions, such as without sacrificing comfort and
peak shaving and interrupt The building annual Energy Use In health.
ible service. dex (EUI) is the common bench
mark used to make building energy As anomalies, inefficiencies, and de
use comparisons. It is expressed in ficiencies are detected, the Commis
terms of energy use per square foot sioning Engineer develops a detailed
of floor area (Btu/ft2 or kWh/ft2 ). measurement cut-sheet for each
Increased energy use over time in major system, listing all parameters
the same building area may signal to be more carefully measured and
the need for an energy audit and re all parts to be more accurately
medial action. In addition, because it checked.
is normalized to the floor area, com
parisons can also be made between Continuous commissioning does not
similar buildings or buildings with overlook its most important resource
similar functions, but with different – people. Occupant feedback,
floor areas. coupled with the results from data
collection devices, may be able to
Step 3 - Fault Diagnosis shed some light on possible causes
of building anomalies and deficien
Monitoring BMS/EMCS/EEMS data cies. It also identifies comfort prob
produces real-time information and lems in specific areas attributed to
specialized reports that permit the temperature, humidity, noise, odors,
facilities staff to recommission build air flow, and lack of outside air. In
ings continuously. For example, typi formation from the building mainte
cally the building operations staff nance staff reveals operational
would use the building’s control sys problems, recurring problems, and
the need to frequently replace parts,
Continuous Commissioning Process

which is indicative of bigger prob trained on replacing belts on that


lems. specific equipment, then the failures
will recur at continued downtime,
In some cases, more detailed root cost and discomfort.
cause failure analysis should be per
formed. Plant equipment may fail Root Cause Failure Analysis
repeatedly or the work environment (RCFA), a fundamental tool of
may always be uncomfortable. RCM, can be used to proactively
These failures eventually become seek the fundamental causes that
accepted as a normal condition. Re lead to equipment failure, excessive
curring problems, such as short energy use, and poor working condi
bearing life, loud noises in the tions. Its goals are to:
ductwork, and mold are symptoms
of more severe problems. However, ■ Find the cause of the problem
maintenance personnel often only quickly, efficiently, and eco 133
fix the symptomatic problems and nomically.
continue with the frequent repairs ■ Correct the cause of the
or adjustments necessary to amelio problem, not just the effect.
rate the problem for the moment. ■ Provide information that can
Repeated failures and uncomfort help prevent the problem from
able conditions result in high costs recurring.
for parts and labor and decreased ■ Instill a mentality of “fix for
occupant productivity. Further, unre ever.”
liable equipment and poor indoor
work environments may pose a Detailed instruction on how to con
continuing personnel health and duct a RCFA is beyond the scope
safety hazard. here. However, ample guidance is
available through
While continuous commissioning internet search en
can identify equipment faults at gines on the topic of
such an early stage that they never Root Cause Failure
lead to actual equipment failure, it Analysis and/or Reli
often does not include discovering ability Centered
the underlying reason for the faults. Maintenance.
For example, an air handling unit
may not be delivering the correct Step 4 - Fault
quantity of conditioned air to a
Reaction
space. Commissioning may likely
recognize that a belt is badly worn Using these measure
or broken and needs replacement. ments and other
But if nobody recognizes that the input, the Commis
sheave is bent and is causing pre sioning Engineer and
mature belt wear or that the techni Commissioning Au
cian used a screwdriver to pry the thority conduct an en
belt over the sheave and bending it gineering analysis and
because he or she was not properly
Continuous Commissioning Process

risk assessment, respectively, to de the start of a system degrada


termine their impacts on energy con tion and its functional failure is
sumption, system reliability, mission, unacceptable.
operations output, budget, and on
other concerns to the Owner. A de ■ Predictability – The measure
cision is made to either take immedi ment of degradation is obvious
ate remedial measures (such as to the system operator or user.
equipment shut-down or emergency
repairs), to schedule remedial mea ■ Cost – Compare the relative
sures or improvements, or to accept costs of monitoring against the
the risk and tolerate the existing anticipated benefits.
conditions. Remedial measures may
be as simple as adjusting control ■ Process Time – Determine if
schedules and setpoints or as drastic the time between data collection
134 as making capital improvements to and analysis is critical to opera
improve energy efficiency. tions.

The approach selected should be ■ Accessibility to Monitoring


based on an evaluation of the fol Locations – For example,
lowing factors: consider critical air handling
units where the starting and
■ Consequences of Failure – stopping of fans would be
Consider the impact of a failure required to safely and accu
(actual or impending) on safety, rately take measurements. This
security, environment, health, situation is a good candidate for
mission, productivity, cost, and remote monitoring.
morale/political impact. If there
is no impact, then there is no Monitoring and Verification
justification for monitoring the The impact of the minor adjustments
conditions at all. made during the functional perfor
mance testing and of any imple
■ Probability of Failure – mented improvements are monitored
Consider the maintenance immediately following their imple
history and the reputation of the mentation to verify their impact on
systems being monitored. occupant comfort, on operational
and energy performance, and on
■ Redundancy – Evaluate control sequences and schedules.
whether or not there is a single
point of failure that can shut Room-by-room measurements are
down operations. made using hand-held meters or por
table data loggers. Energy model
■ Time Path for Failure – data is collected using the short-term
Based on the operating environ methods established earlier. Utility
ment, load, tolerances, and bills and meter data for electricity,
location, consider whether the gas, steam, and Btus are reviewed
projected time period between for long-term monitoring. The out
Continuous Commissioning Process

come is updated details on energy


consumption, use patterns, trends,
and new baseline data.

If the monitored data shows no ab


normalities or disturbing trends, it is
good practice for the building man
ager to check with key occupants
and maintenance personnel semi
annually to ensure that there are no
comfort or operational problems be
ing experienced that are not other
wise detected by the BMS/EMCS/
EEM.
135
Implementation of Improvements
During each recommissioning cycle,
a report is prepared by the commis
sioning engineer and approved by
the commissioning authority that
summarizes the results of the en
ergy performance baseline mea
surements and the system on implementation costs and sav
measurements. The purpose of the ings. This report is presented to the
report is to provide data interpreta Owner or Owner’s representatives
tion and action plans – not just per to obtain approval to implement rec
formance charts and graphs. ommendations beyond the authority
of the CxA and/or Facility Manager
An executive summary includes a and to obtain their “buy-in” and on
summary of participants and their going program support.
roles, building description, project
objectives, an overview of the com Upon approval by the Owner, the
missioning scope, and a general de commissioning team works with the
scription of testing methods. The building O&M staff and any ven
report includes lists of existing con dors, as necessary, to implement the
trol sequences and set points for all selected cost-effective improve
major equipment, disabled control ments. The highest priority is to
sequences, and malfunctioning solve existing problems. Mea
equipment and control devices. sures that optimize (not correct)
equipment and systems and improve
The report addresses performance operation and control schedules fol
relative to pre-established metrics. low next. Life-cycle cost analyses
It includes a list of recommended are performed, if possible, to iden
improvements and operation and tify where the biggest benefits rela
control procedures and their esti tive to cost lie. While making
mated impact on performance and improvements, the commissioning
Continuous Commissioning Process

team ensures that system documen must be reconciled during the com
tation is updated to reflect changes, missioning analysis.
such as to control sequences.
O&M Staff Training
An improved and a more consis
tently managed indoor air environ Since continuous commissioning is
ment leads to a more comfortable likely to be an in-house function, it is
and healthier workplace. The result necessary for the responsible per
will be increased productivity. Also, sonnel to be trained in and to have a
since monitoring system operations good understanding of the BAS/
and output parameters contributes to EMCS software and monitoring
the equipment condition data under equipment capabilities, data analysis,
an RCM program, system reliability data collection techniques, and stan
and maintainability, and its associ dard operating procedures (SOP) to
136 ated costs, will also improve. be followed when disturbing data
and trends are detected.
One drawback is that improving in
door air quality and comfort may ac
tually increase building energy BEST PRACTICES
consumption. For example, increas
ing the minimum building outside air ■ It may be easier and in the long
will increase the air-conditioning run more cost effective to hire
load in the summer and the heating an independent, third-party
load in the winter. This trade-off Commissioning Authority to set
the commissioning project in
motion and to train and mentor
the in-house staff as needed
until the comfort and technical
levels required of the staff are
References achieved.
1. Retrocommissioning Handbook for Facility Managers, Portland
■ Ongoing monitoring and verifi
Energy Conservation, Inc., March 2001.
cation of energy and operational
2. Liu, Mingsheng, Ph.D., P.E., et. al., Continuous Commissioning performance are essential to
Guidebook: Maximizing Building Energy Efficiency and Com- maintain persistence of improve
fort, October 2002. ments and to ensure that
3. Haasl, Tudi and Terry Sharp, A Practical Guide for Commis- equipment and systems are
sioning Existing Buildings, April 1999. operating at optimal efficiency.
4. Culp, Charles H., et al, Continuous Commissioning in Energy
Conservation Programs, http://energysystems.tamu.edu). ■ A well-trained O&M staff with
adequate resources is crucial to
5. Mahling, Dirk K. and Lehman, Keith, Enterprise Energy Man-
the success of any commission
agement, HPAC Engineering, December 2005.
ing program.
6. Methods for Automated and Continuous Commissioning of
Building Systems, Portland Energy Conservation, Inc. and
Battelle Northwest Division, April 2003.
Continuous Commissioning Process

■ Equipment, sensors, and data comfort and safety) that can be


collectors must be accurately analyzed for more significant
calibrated to ensure the validity trends.
of the collected data.
■ The documentation required by
■ Problems, deficiencies, and each commissioning process
complaints should be carefully can be daunting, but will prove
recorded by the facility Man an invaluable resource for
agement and O&M staff. building management, O&M,
Often, problems can be grouped and future commissioning
into categories (design, opera efforts.
tion, maintenance, installation,

137

STUDY QUESTIONS
1. What are the documentation requirements for each phase of the continuous commissioning process? Why
are these documentation requirements important to the overall success of the continous commissioning
process?

2. How does continuous commissioning differ from new construction/renovation commissioning? How does
it differ from a typical preventive maintenance program?

3. Who are the continous commissioning team members, and how do their roles differ from a new construc-
tion/renovation commissioning team?

4. What are the four steps involved in the implementation phase of continuous commissioning?

5. What are the methods of investigation used during the continuous commissioning implemention phase?

6. How and why should energy and performance baselines be established?

7. What are the factors involved in developing an approach to correcting detected anomalies?

8. How would you prioritize and implement improvements recommended through the continuous commis-
sioning process?
Continuous Commissioning Process

138
This page left blank intentionally

Sustainable Commissioning

Chapter 9
Sustainable Commissioning

A
successful commission purchase billions of dollars of mate
ing program takes thor rials for operations, maintenance,
ough planning and expert repair, and renovation.
execution, but several
additional considerations are impor The collective impact that commis Don’t blow it - good planets
139
tant to the success of commission sioning could have on building oper are hard to find!
ing, including developing a good ating and maintenance costs, energy Environmental Corollary
measurement and verification pro usage, and environmental impacts is
gram and ongoing operations and tremendous, and this potential is not
maintenance staff training. going unrecognized. In fact, com
missioning – as has been discussed
In addition, the Federal government throughout – is now a mandatory
has demonstrated a commitment to requirement for the acceptance of
sustainable design, and commission many sustainable or “green” build
ing has a central role to play in the ings.
building and maintenence of
“green” buildings as well. And this leads us to LEED – Lead
ership in Energy and Environmental
COMMISSIONING FOR Design.

LEED CERTIFICATION The LEED Green Building Rating


System™ is a voluntary, onsensus-
This document was developed by
the U.S. Department of Energy
(DOE) Federal Energy Manage
ment Program (FEMP) to help Fed
eral facilities managers, their staffs,
and their consultants understand the
basics of commissioning and to ap
ply its practice to opportunities
within their own organizations. The
Federal facilities managers, staffs
and consultants toward whom these
materials are directed manage sev
eral hundred thousand facilities
worldwide in about three billion
square feet of floor space. They
Sustainable Commissioning

imperative as government agencies

In this Chapter look for ways to become more envi-


ronmentally friendly, conserve en-
ergy, and decrease the operating
◆ Commissioning for LEED costs of their real estate. Indeed,
Certification current Federal Laws, Executive
◆ Measurement and Verification Orders, and Executive Memoranda
of the Commissioning direct Federal Government facility
Program managers to reduce the energy and
◆ Post-Commissioning Training environmental impacts of the build-
Program ings they manage.
◆ Best Practices
Commissioning all building en-
ergy systems is a prerequisite for
140 based national standard for develop- every LEED project. Any building
ing high-performance, sustainable can benefit from commissioning.
buildings. Administered by the U.S. However, it is even more important
Green Building Council, the LEED in energy efficient buildings as ad
program represents all segments of vanced control strategies become
LEED certification aims to the building industry, and provides increasingly complex. Beyond
improve occupant well-be standards for new commercial con HVAC, commissioning has become
ing, environmental perfor struction and major renovation invaluable to assessing the integrity
mance, and economic returns projects, existing building operations, of the building envelope to ensure
of buildings using estab commercial interiors projects, core comfort, weighing in on manufac
lished and innovative prac and shell projects, homes, and neigh turer claims of building materials ap
tices, standards, and
borhood development. It has further propriateness, and in confirming any
technologies.
developed guidance for specific ap equipment condition relative to pos
plications in retail, multiple buildings sible latent manufacturing, transpor
and campuses, schools, healthcare, tation, and installation defects.
laboratories, and lodging.
The USGBC firmly believes that
LEED provides a complete frame third-party commissioning is invalu
work for assessing building perfor able to the building Owner – so
mance and meeting sustainability much, in fact, that in addition to it
goals. The certification program em being a requirement for certification,
phasizes state-of-the-art strategies additional points can be attained by
for sustainable site development, conducting optional commissioning
water savings, energy efficiency, activities. This commissioning, as
materials selection, and indoor envi discussed earlier, starts during the
ronmental quality. planning and design stages, through
construction, and well into the post-
Understanding the LEED certifica construction and warranty phases.
tion ratings and how to achieve fa LEED requires the commissioning
cility certification with design, of the facility’s static and dynamic
construction, and operational credits elements, particularly any that affect
based on the system has become
Sustainable Commissioning

energy efficiency and the indoor en-


vironmental quality. LEED Certification Benefits
Commissioning Often cited reasons for building owners and facility managers to
Components design, construct, and manage their facilities to meet LEED crite-
ria:
Specific prerequisite and optional
commissioning requirements can be ◆ Easier operation and maintenance that meet the user’s con-
found at the USGBC LEED stantly changing needs
website (www.usgbc.org) and will ◆ Bragging rights for high performance buildings that are “Show-
not be repeated here to maintain case Facilities”
currency with the constantly evolv- ◆ Superior indoor air quality
ing applications. However, in gen- ◆ Comfortable indoor environment with emphasis on thermal,
eral, LEED requires commissioning,
visual, and noise conditions
including thorough documentation, 141
of building integrated HVAC sys ◆ Improved system reliability
tems and controls, ductwork and ◆ Efficient use and selection of materials and supplies to maxi-
pipe insulation, renewable and alter mize recycling and minimize disposal
native energy technologies, lighting ◆ Maximized use of natural sunlight
controls and daylighting systems,
◆ Conservation of water and minimized water waste
waste heat recovery systems, and
other advanced technologies. It also ◆ Thorough documentation and performance baselines
includes testing, adjusting, and bal ◆ Maximized energy efficiency and use of renewable energy
ancing (TAB) verification. Certain
site features, such as alternative fu
eling stations and exterior lighting, sign intent of the building has been
are also required to be commis achieved.
sioned for LEED points. Water sys
tems such as irrigation systems, The additional commissioning cred
plumbing fixtures, and plumbing in its focus on reviews of the building
frastructure are also commissioned design and construction documents
under LEED. to identify potential problems and
opportunities for improvement, on
To demonstrate the successful establishing a program for future-
completion of the commissioning re year recommissioning, and in contin
quirements, the applicant must pro ued energy measurement and
vide a copy of the project’s verification after turnover to help
Commissioning Plan that highlights the Owner manage and recoup sav
each of the fundamental best prac ings.
tices commissioning procedures
used, and a signed letter of certifi Documentation required from these
cation from the CxA confirming that activities include an excerpt from
the Commissioning Plan has been the commissioning plan describing
successfully executed and the de these activities, a copy of the design
reviews, and a signed letter from
Sustainable Commissioning

by measuring energy performance.


Case Study: Potential Cost Savings of LEED A problem that is identified and cor-
rected may result in reduced trouble
Certification call time for your O&M staff, but
this savings is hard to assign a dollar
The Costs and Financial Benefits of Green Buildings, A Re-
value to, and may not be noticed un-
port to California’s Sustainable Building Task Force (Greg
til well after the retrocommissioning
Kats, Oct 2003) identified cost savings resulting from pursu-
project is complete.
ing LEED certification on 33 buildings. The report identified
a financial benefit of $50 to $70 per square foot over a 20
The establishment of an annual en-
year life of these buildings. An estimated $8.47 per square
ergy use index (EUI) provides a
foot is attributed to O&M savings resulting from commis-
baseline to estimate energy savings
sioning. Factoring in the implementation costs of the sus-
when proposing a retrocommis-
tainable design concepts, there was a 10-to-1 payback. sioning project, and to calculate ac-
142 (Source: Berning, Michael, Commissioning for LEED tual savings after project
Projects, Engineered Systems, January 2006.) implementation. The baseline should
be sophisticated enough to differen
tiate between only those energy re
the CxA stating that all of these ductions that result from the
tasks were completed successfully. retrocommissioning project and not
For the continued energy measure reductions that occur from changes
ment and verification, the Owner in building use, weather, etc., and
must further comply with the DOE should be flexible enough to accom
M&V procedures, provide an M&V modate changes that occur after the
plan, identify a schedule of instru project is underway.
mentation and controls input and
output data to be collected, and in A thorough energy analysis of your
clude cutsheets of the sensors and facility will:
data collection devices that will be
used. ■ Evaluate and describe all energy
end uses.
MEASUREMENT AND ■ Identify energy consumption by

VERIFICATION OF THE
system and fuel type.
■ Summarize the operation
COMMISSIONING PROGRAM ■
schedules of systems.
Describe the efficiency of all
Adopting measurement and verifica systems in your facility.
tion (M&V) approaches will help in ■ Identify operation, scheduling
dicate the effectiveness of the and maintenance efficiency
commissioning program, both as it opportunities.
unfolds and at project completion. ■ Describe opportunities for off-
the-shelf efficiency technolo
The easiest way to quantify equip gies.
ment and system performance be ■ Describe engineered energy
fore and after retrocommissioning is efficiency solutions.
Sustainable Commissioning

■ Describe in detail the cost and TRACE, Carrier HAP, BLAST, and
energy cost savings of any Energy Plus.
capital investments recom
mended. There are also free resources avail
■ Identify opportunities that will able online, such as the benchmark
require further design. ing spreadsheets for office buildings
provided by the Oak Ridge National
The three basic methods for estab Laboratory. The benchmarking
lishing an EUI baseline are: spreadsheets provided allow you to
identify where your specific office
1. Energy Calculations, which building ranks relative to others.
incorporate information about They calculate the EUI of your
and energy consumption history building, provide the typical (me
of energy-using building sys dian) EUI for office buildings with
tems and equipment. the same characteristics as yours, 143
and identify where your building’s
2. Regression Analysis, a statisti performance ranks compared to
cal technique that uses histori others (percentile of EUI).
cal data derived from meters to
isolate one or more variables The benchmarking spreadsheets go
that affect energy use (result beyond the customary normalization
ing, for instance, in an equation by floor area and account for per
that relates energy use to formance differ
weather or building use vari ences due to
ables). When historical, me variations in
tered data are available, worker density,
regression analysis defines the number of
energy use relative to the entire personal com
building and allows greater puters, operating
flexibility in making recommen hours, occu
dations related to energy pancy type, and
efficiency. heating fuel
types. Beyond
3. Simulation, a sophisticated set floor area, these
of engineering calculations that characteristics
attempts to forecast energy use were found to
on the basis of a building’s size be the most
and shape, equipment, levels of common and
insulation, types of windows most important
and doors, etc. drivers of elec
tric and non
There are many software packages electric energy
available to help your facility de use in U.S. of
velop an EUI for benchmarking im fice buildings.
provements, including DOE2, Trane Location effects
are accounted
Sustainable Commissioning

for by specifying the census division metrics and benchmarking software


corresponding to your building loca program like Metracker, a prototype
tion. computer tool designed to demon
strate the specification, tracking, and
In addition, the EPA’s ENERGY STAR visualization of building performance
Label for Building also offers an objectives and their associated
online benchmarking tool called metrics across the complete life
Portfolio Manager. Portfolio Man cycle of a building (developed by the
ager can generate a Statement of Lawrence Berkeley National Labo
Energy Performance for any build ratory). Performance objective
Commissioning is now a ing in your portfolio. This document metrics established during pre-de
mandatory requirement for communicates information about a sign planning can be used to guide
the acceptance of many sus building’s energy performance in a and evaluate design decisions and
tainable or “green” build format that is both understandable can be updated to reflect the in
144 ings, and is a prerequisite for and easy-to-use in business transac tended performance of the final de
LEED certification. tions. The Statement of Energy Per sign. These design intent metrics
formance can help you formalize can then be used as benchmarks
performance expectations to support during commissioning and updated
leasing, building sales, appraisals, in again to act as benchmarks for
surance, staff management, and O&M diagnostics. The history of
commissioning, energy, and O&M building performance documented
service contracts. can ultimately be used to better plan
for, design, and operate future build
Also, DOE’s Federal Energy Man ings. Such a methodology may also
agement Program offers the Build prove to be useful in documenting
ing Life-Cycle Costs (BLCC) and tracking compliance with
software programs can help you cal emerging commercial building rating
culate life-cycle costs, net savings, systems.
savings-to-investment ratio, internal
rate of return, and payback period
for Federal energy and water con
POST-COMMISSIONING
servation projects funded by agen TRAINING PROGRAM
cies or alternatively financed. The
BLCC programs also estimate emis An essential element to the
sions and emission reductions. An sustainability of the results of any
energy escalation rate calculator commissioning effort is the proper
(EERC) computes an average esca training of the operations and main
lation rate for ESPC contracts when tenance (O&M) staff. The O&M
payments are based on energy cost staff must be thoroughly trained on
savings. how new or renovated equipment
and systems are designed to work
To measure and verify other building (design intent), how to properly op
performance data (apart from en erate and maintain them, and how to
ergy), consider using a performance maintain operational and energy effi
ciency results through continuous
commissioning approaches.
Sustainable Commissioning

1. Initial training
There are several common prob- on new or
lems that hinder this vital process, renovated
however. Although O&M staff equipment and
training is cited as a requirement for systems upon
most commissioning projects, the completion of
actual training is often an after- the commis-
thought as the project nears sioning pro-
completion. Too often training is cess. This
poorly coordinated, loosely-struc- training is
tured, informal, lacking in well-de- optimally
fined objectives, and too tightly provided by the
scheduled. Training is often handed CxA or each
over to equipment manufacturers, responsible
who can certainly provide adequate installing 145
information on their own products contractor to

but have no idea about the overall cover equip

building design intent and how their ment and

equipment should operate in concert systems in all

with the entire building. relevant areas:

mechanical,

To be truly effective, the Owner electrical, HVAC, controls, etc.

and CxA must work together to de


velop and implement an O&M Oftentimes training is left to the

training program that is ongoing, equipment manufacturers.

thorough, and adaptable. Training Although this approach can

must be thought of as a dynamic, work, it is essential that the

open-ended component of the com CxA reviews the training

missioning process, not a one-time materials and provides supple

event at the conclusion of the com mentary training in systems and

missioning process. equipment integration with the

rest of the building.

Types of Training Programs


It is highly recommended that

to Implement
all training during the project

A comprehensive training program completion process be profes

will involve different types of train sionally videotaped; this will

ing at different stages in the com provide both a good guide to

missioning process. The best subsequent new hires as well as

program will provide an integration an instant “refresher” course

of ongoing O&M training in com for the future.

missioning and preventive mainte


nance/RCM approaches. Typical 2. Initial systems training subse
training program components will quent to project completion for
include: new hires.
Sustainable Commissioning

3. Periodic “refresher” training for erly operate and maintain complex


the entire O&M staff. Re and interdependent building systems,
fresher training, scheduled for as well as provide a means to pass
perhaps once a year, is also a that knowledge base on to succeed
good opportunity for the Facility ing O&M staff.
Manager to review any changes
to equipment and systems and
implement any new training
BEST PRACTICES
required to address these ■ Commissioning should be seen
changes. as an ongoing process, not a
distinct event, that will reap the
4. Proficiency training to improve most benefits if carefully
overall O&M staff expertise. planned and implemented for the
life of the building.
146 5. Cross-training to provide
staffing flexibility and encourage ■ Just as commissioning is a
the entire O&M staff to think of process and not an event,
the building’s systems and training of the building’s opera
equipment holistically, rather tions and maintenance staff
than focuses solely on their area must also been viewed as an
of expertise. ongoing process.

6. Certification and re-certification ■ Videotape training sessions to


training to meet external regula maintain a record for future
tory requirements. generations of O&M staff, and
review training requirements
An integrated and ongoing systems and materials at least once per
approach to O&M staff training will year to ensure their relevancy
provide existing staff with the and appropriateness.
knowledge base they need to prop-
■ Some landlords, who recognize
the benefits of meeting the
stringent LEED criteria but do
References not want to to pay associated
LEED expenses and are willing
1. Greening Federal Facilities – An Energy, Environmental, and
to forego the LEED certification
Economic Resource Guide for Federal Facility Managers and
recognition, still specify compli
Designers, National Renewable Energy Laboratory, 2nd Edi-
ance with the LEED criteria in
tion, May 2001.
their Design Intent and Basis of
2. “Elements of an Effective Post-Commissioning Training Pro- Design. Doing so (and building
gram,” Sebesta Blomberg & Associates, 2002. to it) ensures that their building
3. Berning, Michael, Commissioning for LEED Projects, Engi- will still be commissioned and
neered Systems, January 2006. will have the quality and reliabil
4. USGBC LEED Application Guides available at http:// ity benefits that go with it, that it
www.usgbc.org/DisplayPage.aspx?CMSPageID=276&. will be energy efficient, and that
Sustainable Commissioning

it will be environment-friendly project cost. Allowing it to be


without some of the expenses value-engineered out is similar
and management requirements to foregoing all the quality
associated with the actual control checks that a new car
certification. goes through. If you needed to
stay within the budget on a new
■ Commissioning should always car purchase, isn’t it wiser to
be included as a mandatory forego the leather seating or
project line item and should not chrome wheels rather than
be allowed to be value-engi delete the testing of its inte
neered out. The cost of com grated systems to make sure
missioning is very small relative that they operate as they
to its benefits and the overall should?

147

STUDY QUESTIONS
1. What is LEED certification and why is it so important to Federal facility owners and managers?

2. In general, what are the commissioning requirements for LEED certification?

3. What are some of the methods typically used to develop an annual energy use index (EUI)? What is the
benefit of developing an accurate EUI for your facility?

4. What are some of the resources available to help when trying to measure and verify building performance?

5. What are some of the mistakes typical of an incomplete O&M training approach?

6. How often should O&M staff receive training on commissioned systems?


Sustainable Commissioning

148
This page left blank intentionally

You might also like