Professional Documents
Culture Documents
Chapter 1
Introduction
B
uilding commissioning Building commissioning has
has often been likened to its roots in the Quality Control
commissioning of a ship, programs of the 1970s and is
where the Owners thor a direct product of the Total
oughly verify and prove the func Quality Management pro 1
tional performance of all parts – grams of the 1980s. Commis
engines, compasses, sonar, radar, sioning is a direct response to
radio, generators, potable water building Owners who com
systems, and so on – under all pos plain that their facilities do not
sible conditions and as a condition meet performance expecta
of acceptance before placing the tions, are extraordinarily ex
ship in service. And where the pensive to operate and
Owner checks the presence of sys maintain, lack valuable docu
tem operating and procedures mentation, and are staffed by
manuals and the availability of up- personnel who are unfamiliar
to-date navigation charts. And with and have never been
where the crew has been properly trained on the building’s highly
“Building commissioning has
and thoroughly trained on the ship’s complex operations and control sys
systems’ operations and emergency tems. often been likened to the
procedures. Commissioning is not commissioning of a ship.”
new – ships and aircraft have been Until now, many of us thought of
commissioned for years. building construction completion and
turnover as physically completing an
installation, throwing
the switch, making a
few adjustments,
Goals of Commissioning: spending minimal time
with the operators by
◆ Provide a safe and healthy facility.
pointing to the equip
◆ Improve energy performance and minimize ment with one hand
energy consumption. and a manufacturer-
◆ Reduce operating costs. supplied operations
◆ Ensure adequate O&M staff orientation and manual (that may or
training. may not match the
specific equipment)
◆ Improve systems documentation.
with the other, then
Introduction
walking away. We would return only ent sources and programs. So once
when the operating personnel or the construction was completed and
owner complained. beneficially accepted, the building
was handed off as rapidly as pos
A successful project was not neces sible, leaving building maintainers to
sarily the one with the most satisfied struggle with any residual construc
client, optimal indoor environment, tion or operational problems. In all
most reliable and efficient operation, fairness to the constructors, by this
or that would have had the lowest time the Owner was usually press
possible operating and maintenance ing to move into the building, either
costs. Typically, it was the one with oblivious to or willing to accept the
the fewest extras and change orders risks associated with a potentially
and the one with the shortest punch problematic facility.
list.
2 Most existing buildings have never
Further, the construction budget and undergone a formal commissioning
operating budget came from differ- or quality assurance process. Many
buildings are limping along ineffi
ciently in terms of performance.
Owners are unaware of deficiencies
Guidebook Objectives as long as the building is reasonably
comfortable and occupant com
◆ Provide an introduction to commissioning approaches to a
plaints do not reach a crescendo.
variety of professionals involved with the management, op-
eration, and maintenance of Federal buildings.
In reality, the building systems may
be becoming increasingly unreliable
◆ Illustrate case histories, including cautionary lessons learned. and inefficient through design, inef
fective maintenance and operations
procedures, outdated technologies,
◆ Provide guidance on commissioning best practices.
insufficient training, occupant habits,
mission changes, environmental
◆ Demonstrate how commissioning can help Federal facility changes, workplace configurations,
managers meet energy efficiency goals and LEED certifica- and more.
tion requirements.
All of that has now changed with
commissioning. As described by the
◆ Demonstrate how commissioning can be integrated in facil- Canadian Department of Public
ity management and O&M programs to make those programs Works, buildings now “leave port”
more efficient and effective. only when they are fully operational,
function as the owner intended, are
◆ Demonstrate how different types of commissioning (such as fine-tuned for maximum perfor
retrocommissioning and continuous commissioning) can be mance, staffed with “crews” who
incorporated into a variety of building types and applications, are fully trained in the regular and
above and beyond the most commonly understood commis- emergency operation of the facility,
sioning approaches. and furnished with a complete set of
relevant operations, maintenance,
Introduction
facility intent and design, and emer in terms of the systems to be com
gency procedures documentation. missioned (e.g., HVAC and electri
cal systems only). It is essentially a
SO… WHAT IS IT? subset, or a slice of the whole build
ing commissioning pie, and for the
Commissioning is a method of risk purposes of this document, the
reduction. terms will be used interchangeably.
HOW DO WE DO IT?
Quality control has historically been
associated with static and individual
systems, such as piping, ductwork,
building aesthetics, air handlers, and
other standard punch list items. The
project inspector ensures material
Introduction
ability between systems; tests the and is heavily involved in the plan
condition and operation of key com ning, design, construction, and ac
ponents; ensures the completeness ceptance stages in between.
and quality of O&M manuals and
skills training; is mindful of maintain In existing buildings that have never
ability, accessibility, supportability, been commissioned before,
and reliability issues; and documents retrocommissioning can take place
the entire process. Typically, these at anytime, unless the facility and/or
are not high priority issues in a stan major equipment are programmed
dard quality control program. How for replacement in the immediate fu
ever, by design, commissioning ture. In that case, it is usually advan
includes these so that there is a high tageous to wait and commission the
degree of confidence that the facility as part of the construction
building’s systems have been in effort. Otherwise, commissioning an
6 stalled correctly and will operate as existing building will likely uncover a
required. multitude of deficiencies that affect
the building’s efficiency and ability
WHEN DO WE DO IT? to operate as required.
STUDY QUESTIONS
1. How does commissioning change the traditional definition of a “successful” construction project?
2. What are the top ten reasons why people employ commissioning, and how could your facility benefit from
these reasons?
3. What is the difference between commissioning, and total or whole building commissioning?
8
This page left blank intentionally
Types of Commissioning
Chapter 2
Types of Commissioning
■
T
he first step in consider Retrocommissioning
ing or planning a com ■ Recommissioning
missioning program for ■ Continuous Commissioning “A leader takes people
your facility is to under where they want to go. A
stand the different types of commis
sioning available, and which types COMMISSIONING FOR NEW great leader takes people
where they don’t necessarily
9
of commissioning are best suited to CONSTRUCTION / MAJOR want to go but ought to be.”
your facility’s unique requirements.
RENOVATION
Rosalynn Carter
In general, a commissioning pro
gram is best applied during the fol
lowing: Commissioning is a systematic
process of ensuring that all building
■ During new construction or a systems perform interactively ac
major renovation of an existing cording to the design intent and the
building. Owner’s operational needs. The
process evaluates building equip
■ When an existing building is ment, subsystems, operation and
experiencing problems with maintenance (O&M) procedures,
operational performance, and performance of all building
energy efficiency, and/or components to ensure that they
occupant comfort and safety. function effi
ciently, and as
■ As a maintenance approach to designed, as a
ensure that equipment and system. This is
systems are operating at peak achieved by be
performance, energy efficiency ginning in the
is optimized, and occupant planning or
comfort and safety are high. early design
phase of a con
The types of commissioning that fit struction project
into these applications that will be with the docu
discussed in this and subsequent mentation of de
chapters are: sign intent, and
continuing
■ Commissioning for New through con
Construction/Renovation struction, ac
ceptance, and
Types of Commissioning
In this Chapter
◆ Commissioning for New Construction / Major Renovation
◆ Retrocommissioning
◆ Recommissioning
◆ Continuous Commissioning
◆ Best Practices
the warranty period with the actual the containment goals for fume
verification of each building hoods and bio-safety cabinets and of
system’s performance. primary and secondary barriers so
that their compliance with the re-
10 The commissioning process encom- quirements can be verified during
passes and coordinates the tradition the commissioning process.
ally separate functions of system
documentation, equipment startup, Often too, local fire marshals alone
control system calibration, testing are responsible for the inspection,
and balancing, performance testing, testing, and approval of all fire pre
and training. It defines a mainte vention and protection devices and
nance baseline against which future systems. In that case, commission
condition assessments and trending ing is coordinated with the fire
can be compared. marshal’s work, his efforts are ob
served by the CxA, and a copy of
Commissioning may include the the official fire marshal report is in
building envelope, the building cluded as part of the Final Commis
HVAC systems, controls, electrical, sioning Report.
conveyance, plumbing fixtures, life
safety, security, or any combinations The commissioning process does not
of these systems and others. take away from or reduce the re
sponsibility of the system designers
The specific person or organization or installing contractors to provide a
that conducts and oversees the com finished and fully functioning build
missioning process is the Commis ing. Commissioning does not take
sioning Authority (or Agent), the place of or reduce in any way
commonly referred to as the “CxA.” the contractor’s responsibilities for
conducting an active project quality
Often, the assistance of subject mat control program.
ter experts is required. Commission
ing of laboratories requires special The Commissioning
attention and involvement of the
Owner’s environmental health and
Process
safety (EH&S) staff as part of the Commissioning is systematic. It in
commissioning team. For example, cludes testing all items in all modes
they will help the CxA understand of operation. Equipment is first in
Types of Commissioning
spected while it is turned off to throughout the life of the project will
make sure that it is installed fully produce the best results. Each of
and correctly. Equipment is then en these will be discussed in greater
ergized, started, and tested under detail later:
controlled conditions. After this ini
tial testing and inspection, integrated Pre-design
systems are tested through all
■ Determine project objectives
cycles and scenarios, including
and develop Owner’s Criteria.
power failure and emergency alarm
■ Develop commissioning require
modes, to ensure they operate as
ments.
required and intended.
■ Hire or assign Commissioning
Authority (CxA).
In the course of commissioning, key
parameters and baseline information
of the systems are documented, or Design 11
ganized, and preserved in the Com ■ Design team develops project
missioning Report and O&M design; CxA reviews design
manual, as applicable. intent, basis of design docu
ments, and drawings and
Commissioning typically follows the provides feedback to design
phases of the new construction or team.
renovation project. Although it is not ■ CxA develops commissioning
necessary to perform commission plan.
ing tasks during each phase of con ■ Design team develops project
struction, implementing the process specifications; CxA develops
… relatively new and was commissioned during its Recommissioning - Ideal to tune up buildings that
construction, but our energy costs have been climb have already been commissioned, bring them back
ing recently. to their original design intent and operating/energy
efficiency
… large and complex. We have a metering system Continuous Commissioning - Ideal for facilities
and a preventive maintenance program, but will still with building automation systems (BAS), advanced
struggle with high energy costs and tenant com metering systems, and advanced O&M organiza
plaints. tions.
Types of Commissioning
Commissioning’s Objectives
Commissioning is intended to achieve the follow-
ing specific objectives:
Verification...
◆ ... that applicable equipment and systems are
installed according to the manufacturer’s rec-
ommendations and to industry accepted mini-
mum standards
◆ ... that applicable equipment and systems re-
12 ceive adequate operational checkout by install-
ing contractors
◆ ... and documentation of proper performance of equipment and systems
under various conditions
◆ ... of the proper interactions between systems and subsystems
◆ ... that systems and O&M documentation left on site is complete
◆ ... that the building’s O&M staff has been adequately trained.
The contractor paid heavily as a result. The TAB was re-performed correctly by a reputable contractor. The
project acceptance was delayed for several weeks as a result of the required re-work. However, because of the
CxA’s testing and verification, the Owner ended up with a fully and properly functioning and balanced HVAC
system that would probably not have been realized until well after the facility became occupied, occupant 15
complaints drove a costly investigation, and payment had already been made for the original, fraudulent TAB
work.
that has been installed and flow and air quality, and lighting
tested properly and optimized levels to ensure that occupants
for maximum efficiency, will are comfortable, safe, and
experience fewer problems and productive in their work spaces.
require less unscheduled O&M
time. Disadvantages
■ Equipment condition-accepted ■ The first costs of commissioning
during commissioning verifies are construed by Owners as
the equipment condition prior to being high only to ensure that
expiration of its warranties and the contractor’s work is of a
provides a condition baseline for quality that he’s already con
the ensuing maintenance tracted to perform. There is little
program. quantifiable data on the potential
16 cost savings (both energy and
■ Commissioning can extend operational) that the commis
equipment life and reduce sioning process will generate for
warranty claims, leading to the specific, as-yet operational
fewer warranty claims, service building. Nor is there any way to
calls, reduced energy use, and benchmark in advance, energy
reduced potential for cata and operational performance in
strophic equipment failure. the case of new construction (in
which the “existing” conditions
■ Commissioning provides more do not yet exist).
useful O&M condition baseline
and performance data that is ■ There is no guarantee of
specific to the systems and savings. The commissioning
equipment installed. It details the process is designed to optimize
way the equipment should be all building system and equip
operated, outlines preventive ment operations to meet the
maintenance procedures and design intent; most of the
schedules, and provides infor savings occur through avoided
mation on warranties, vendor costs.
points of contact, and spare
parts. ■ If a quality assurance program
is already utilized by the A/E,
■ The maintenance staff is trained construction manager, and
on site by observing the work as installing contractors, commis
it progresses as well as by sioning may be perceived to be
formal instruction customized to redundant and/or confronta
the specific equipment and tional.
systems installed.
■ Commissioning addresses
RETROCOMMISSIONING
common occupant concerns Retrocommissioning is a system
such as thermal comfort, air atic process for improving and opti
Types of Commissioning
mizing building performance. Retro bring the building, its systems, and
commissioning applies to exiting equipment back to its original design
buildings that have never gone intent, this is not a requirement. The
through any type of commissioning original design intent documentation
or quality assurance process. Its fo may be lost or no longer relevant.
cus is usually on energy-using equip
ment such as mechanical equipment, The Retrocommissioning
lighting, and related controls.
Process
Like commissioning, retrocommis Retrocommissioning is not tied to a
sioning is concerned with how specific new construction or reno
equipment, systems, and subsystems vation project, and therefore does
function together, but it does not not necessarily follow the same pro
generally take a whole-building ap cess as commissioning.
proach to efficiency. The process 17
can identify and solve problems that Retrocommissioning typically fol
occurred at construction, but also lows a four-part process:
addresses problems that have devel
oped to this stage in the building’s 1. Planning
life. And while the goal of - Identify project objectives.
retrocommissioning may be used to - Decide which building
Retrocommissioning Identify and correct Facility O&M staff or in Once, in response to Diagnostic monitoring
problems and optimize dependent CxA specific problems or to and functional perfor
performance establish a commission mance testing
ing program
Recommissioning Ensure that the building Facility O&M staff or in Periodically as the Functional perfor
and its systems and dependent CxA building ages, or ongo mance testing
equipment continue to ing as part of the facility
operate as designed, or O&M program
meet current operating
needs
Continuous Identify and correct Facility O&M staff or in Ongoing as part of the Data monitoring and
Commissioning problems and optimize dependent CxA facility O&M program trending
performance
Types of Commissioning
?
Retrocommissioning
◆ A one-time event
◆ The building has not been previously commissioned
◆ May or may not adhere to building’s original design intent
◆ Utilizes diagnostic monitoring and functional performance tests
23
Recommissioning
◆ A one-time, periodic, or occasional event
◆ The building has been previously commissioned
◆ Adheres to building’s original design intent
◆ Utilizes previously developed functional performance tests
Continuous Commissioning
◆ Continuous monitoring with assessments performed at least quarterly
◆ The building may or may not have been previously commissioned
◆ Does not adhere to building’s original design intent – is concerned instead with trending relative
to a baseline and optimizing performance to meet current requirements
◆ Utilizes building automation system and/or metered energy trend data and/or condition accep-
tance tests
reducing the need for additional program and a highly skilled and
continuous commissioning
Disadvantages activities and/or to train the
existing O&M staff on continu
■ Continuous commissioning does ous commissioning approaches
not consider design intent – and tests. High O&M staff
how were the installed equip- turnover is also a barrier.
ment and systems intended to However, the cost of training
and it is possible that the design larger, more complex, and more
26
STUDY QUESTIONS
1. What type(s) of commissioning would you consider suitable for your facility?
2. For new construction or major renovation projects, at what phase of the project should the commissioning
process ideally start?
3. Under what circumstances would you consider including subject matter experts on the commissioning
team?
6. Explain the differences between verification testing, functional performance testing, and condition accep-
tance testing.
7. Explain the major differences between new building commissioning, retrocommissioning, recommission-
ing, and continuous commissioning.
8. What is the relationship between any of the forms of commissioning and energy savings?
9. How would you describe the value of commissioning to the Owner? Building occupants and users? The
operations and maintenance staff?
Why Commission?
Chapter 3
Why Commission?
T
o better understand the it fit” are not uncommon. Equip-
benefits of commission- ment literally may self-destruct.
ing, consider how much
buildings and their sys- The consequence of most un-
tems have changed over the last commissioned buildings is that the 27
couple of decades. Control systems O&M staff inherits systems ripe
have become highly complex with with problems and inefficiencies.
the migration from pneumatic to di- An un-commissioned building
rect digital control systems; with may not operate correctly, and
more sophisticated building manage- without essential O&M informa-
ment system (BMS) hardware and tion, training, and baseline data,
software; and with automatic the O&M staff likely cannot re-
valves, dampers, actuators, and sen- spond adequately to occupant
sors. New technologies have been complaints. They respond to
introduced for life safety and secu- problem symptoms rather than
“If you always do what you’ve
rity systems. Buildings must operate correcting root causes. Automated
always done, you’ll always get
with optimal energy efficiency. In- systems become bypassed and
what you’ve always got;
door air environments have taken overridden. Occupants very quickly Change makes change.”
on a new importance with regards settle on low expectations and be-
to mitigation of mold, mildew, and come sensitized to (or very vocal Anonymous
new product emissions as they af- about) the poor building environ-
fect occupant health, comfort, and ment, which deteriorates steadily.
productivity. Energy efficiency suffers, and build-
ing performance falls short of the
Commissioning also has long-term Owner’s expectations. These costs
repercussions on maintainability. are high and well above those for
Systems may not be installed, ad- commissioning.
justed, and integrated to operate op-
timally. They may be installed with A team from the Lawrence Berke-
latent manufacturing, transportation, ley National Laboratory, Portland
and installation defects. Systems Energy Conservation, Inc., and the
designed and installed with struc- Energy Systems Laboratory of
tures that amplify destructive natu- Texas A&M University set out to
ral harmonics, that get damaged quantify the actual costs and im-
during transport, and that were det- pacts associated with commission-
rimentally modified on site to “make ing1 . The Cost-Effectiveness of
Why Commission?
In this Chapter
◆ Commissioning Costs and Return on Investment
◆ Cost Benefits of Commissioning
◆ Barriers and Management Buy-in
◆ Impact on Facility Operations and Maintenance
◆ Impact on Energy Consumption
◆ LEED Certification
◆ Best Practices
1
Mills, E. et al. (2004) The Cost Effectiveness of Commercial Building Commissioning: A Meta-Analysis of
Energy and Non-Energy Impacts in Existing Buildings and New Construction in the United States. (http:eetd.lbl.gov/
emills/pubs/cx-costs-benefits.html)
Why Commission?
$3.00 Complex – Moderate plus most of floor area in complex systems; hospitals;
clean rooms; non-HVAC systems included, such as Security, communications;
Commissioning Cost in $/square foot
Specialty
$1.00 Complex
Moderate
Simple
$0.00
optimize all building system and it does not have a line item for
A 2004 study conducted by Cornell University correlated worker productivity with indoor environmental con-
ditions. It found that workers produced 74-percent more mistakes and 46-percent less output based on
temperature alone when the temperature fell from 77oF to 68 oF. The study estimated that the decreased
productivity resulted in a 10-percent increase in labor costs per worker, per hour. “Our ultimate goal is to have
much smarter buildings and better environmental control systems in the workplace that will maximize worker
comfort and thereby productivity,” the professor overseeing the study said. Commissioning by its nature
supports that goal and optimizes those very systems. (source: http://ergo.human.cornell.edu/
CUEHEECE_IEQDown.html)
ing benefit that can profoundly im- such baselines, which include the
pact the O&M staff. Commission- following performance metrics:
ing does require input and effort 39
from the O&M staff. Most of the ■ System Capacity (actual
benchmarking and maintainability operation compared to full
issues associated with commission system utilization of plant or
ing are addressed throughout the equipment)
commissioning process during initial ■ Work Orders Generated and
planning, design reviews, verifica Work Orders Closed Out
tion inspections, functional perfor ■ Preventive Maintenance
mance, condition acceptance Backlog
testing, and training. The O&M ■ Safety Record
staff’s effort during commissioning ■ Energy Use
revolves around providing input and ■ Inventory Control
feedback as the project progresses, ■ Overtime Logs
observing the work in progress and ■ Environmental Record (air and
system testing, and receiving proper water discharge levels, non
and appropriate training and educa compliance situations)
tion on the new and modified in ■ Staffing: Absentee and Turn
stalled systems. over Rates
one year, when commissioning was cies mandate that new and remod
applied. A sample of 74 new-con eled buildings meet a minimum level
struction projects found an average of sustainable design certification.
payback time of 4.8 years, although One of the most widely adopted pro
the addition of non-energy impacts grams used by the government to
can drastically reduce these pay assess building performance and ad
back times. There are cost-effective herence to sustainable design goals
results to be found in a wide range is the LEED™ (Leadership in En
of building types and sizes. ergy and Environmental Design)
certification system. LEED was
As it relates to energy efficiency created by the U.S. Green Building
goals, commissioning can be seen as Council (USGBC) and is now rec
a form of risk management. It helps ognized and accepted internationally
ensure that funds are spent wisely to assess building performance and
42 and that the intended energy savings adherence to sustainable design
targets are achieved in practice. goals.
Commissioning provides a method
Many Federal agencies man for defining measurable energy per The LEED Green Building Rating
date that new and remodeled
formance targets in the design System is a voluntary, consensus-
buildings meet a minimum
level of sustainable design phase, and for evaluating as-built based national standard for develop
certification. LEED is now and as-operated system conditions. ing high-performance, sustainable
recognized and accepted in buildings. Members of the USGBC,
ternationally to assess build As buildings and energy-efficient representing all segments of the
ing performance and technologies become more complex building industry, developed LEED
adherence to sustainable de and interconnected, the need for and continue to contribute to its evo
sign goals. commissioning to ensure optimized lution. LEED standards are available
energy performance will increase. or under development for:
The Lawrence Berkeley National
Laboratory study asserts that the ef ■ New construction and major
ficacy of energy efficiency pro renovation projects (LEED-NC)
grams is directly related to the ■ Existing building operations
extent to which they are coupled (LEED-EB)
with commissioning and quality as ■ Commercial interiors projects
surance in design and delivery. (LEED-CI)
■ Core and shell property (LEED
LEED CERTIFICATION ■
CS)
Homes (LEED-H) and
More and more government agen ■ Neighborhood development
cies are demanding “green” build (LEED-ND)
ings that incorporate meaningful
strategies for sustainable facility de To achieve a LEED rating, a whole-
sign. building approach must be used.
Credits must be earned in several
To reduce long-term facility costs categories, including site selection
and to become more environmen and configuration, water efficiency,
tally conscious, many Federal agen energy, indoor air quality, and sus
Why Commission?
STUDY QUESTIONS
1. What arguments would you offer to convince the owner that commissioning is the right thing for his facility?
3. What are ten benefits derived from commissioning and explain how they are beneficial?
44
4. Explain how commissioning reduces the number of change orders in new construction?
5. How does commissioning contribute to new construction acceptance and project turnover?
7. How can the O&M program optimize the performance of your facility?
8. How does the LEED certification impact the quality of life of the building occupants?
Commissioning Management
Chapter 4
Commissioning Management
A
n emphasis on team There are three steps to de
building and teamwork veloping a strong internal
will lead to greater suc structure to support commis
cess from the commis sioning: determining the need
sioning process. It fosters a positive for commissioning, obtaining 45
approach to commissioning activi the support of various build
ties, rather than the attitude that the ing stakeholders, and defin
commissioning process creates ing an internal
more work or encourages “looking” commissioning team.
for problems that do not exist. Ef
fective commissioning management Step 1 - Determine the
encourages team members to work
Need for Commission
together to identify problems (exist
ing and potential) and help correct ing
these problems before they grow. Commissioning is becoming
more and more common, but
There are two teams that will be its value should still be care “What you always do before
discussed in this chapter: the inter fully evaluated and management you make a decision is con
nal management team that must be support for commissioning obtained. sult. The best public policy is
in place and prepared to support the For new construction and renova made when you are listening
commissioning process, and the tion projects, commissioning will to people who are going to
commissioning team that is as produce the biggest payoff if the fa be impacted. Then, once
sembled when a project is under cility and its systems/equipment are policy is determined, you
way. call on them to help you sell
very complex (laboratories, tele
it.”
communications, medical), and if the
DEVELOPING COMMISSION facility has a very large square foot Elizabeth Dole
In this Chapter
◆ Developing Commissioning Structure and Management Support
◆ Commissioning Authority Options
◆ Commissioning Authority Qualifications
◆ Role and Responsibilities of the Commissioning Authority
◆ Roles and Responsibilities of Commissioning Team Members
◆ Best Practices in Commissioning Management
Retrocommissioning:
efficiently as possible. cient) systems and equipment
maintenance tasks. Make the O&M age the process for the Owner.
staff a partner in the commissioning
process. For a new construction or major
renovation project, this team will in
Finally, the needs and desires of the clude the facility management staff
building’s occupants must be consid person who is acting as the Owner’s
ered. Conducting a survey of occu project manager for the project. If
pant satisfaction is a good place to this individual does not want to take
start (and can provide information on the responsibility of monitoring
for Management on areas of dissat the commissioning aspects of the
isfaction that may justify performing project, another person on the facil
retrocommissioning). Building occu ity management staff should be ap
pants will support a retrocommis pointed.
sioning program if it will lead to
48 better thermal comfort, air quality, It is vital that each party involved in
and lighting levels. the project have access to a single
point of contact for commissioning
Step 3 - Define an Internal issues who is also the Owner’s rep
resentative. In addition, a lead con
Commissioning Team
tact should be appointed from the
When the need for commissioning facility O&M organization to coordi
has been recognized and accepted nate O&M activities related to com
by Management, O&M, and occu missioning.
pants, define a team that will man
For a retrocommissioning project,
representatives from facility man-
agement and O&M should develop Owner and offers the most objec
an organization and define duties tive perspective of any of the other
based on the size and scope of the CxA options described in this sec
project. If a third party CxA is tion.
hired, facility management and
O&M should each provide the CxA For large or complex projects, and
with a single point of contact. in buildings with highly integrated
and sophisticated systems, potential
COMMISSIONING savings resulting from objective
commissioning will likely outweigh
AUTHORITY OPTIONS the cost of employing an indepen
dent third party commissioning pro
Put most simply the Commissioning vider. And in existing buildings, an
Authority (CxA; also sometimes independent third party CxA brings
called Commissioning Agent) is the a new perspective to the building, 49
designated person or company that has no investment in existing main
plans, coordinates, and oversees the tenance approaches, and therefore
commissioning process. This person may be more likely to find additional
or company directs the day-to-day opportunities for improvements and
commissioning activities of the savings.
project. The CxA does not have a
direct oversight role, like the con An independent third party provides
struction manager, but rather in an autonomous and independent
forms installing contractors, the judge of quality with minimum pos
construction manager, and the sible conflicts of interest.
Owner of observed deficiencies.
Mechanical or Electrical
There are several options for ob Contractor
taining the services of a CxA for a
project: Most appropriate for:
◆ Retrocommissioning of specific
systems (e.g., HVAC or
Independent Third Party electrical systems)
Most appropriate for: ◆ New construction or renovation
◆ New construction or major involving less than 20,000
renovation projects, square feet
retrocommissioning, and
recommissioning of all building Mechanical and electrical contract
types and system complexities ing firms may already perform com
prehensive performance tests and
An independent third party CxA is diagnostic procedures for equipment
the most common option for provid and systems they install. Expanding
ing commissioning services today, the scope of work of the mechani
and the one most often utilized and cal or electrical contractor to in
recommended by Federal agencies. clude commissioning is an
This person or firm is hired by the alternative when the project is small
Commissioning Management
CxA Qualifications
The individual or firm may also meet
The individual or firm should demon- the following optional requirements:
strate knowledge and experience in
the following areas: 1. Excellent verbal and writing
communication skills.
1. Designing, specifying, and/or 2. Highly organized and able to
installing building HVAC and work effectively with the
mechanical control systems. building management, design
2. Operation and troubleshooting team, installing contractors, and
of HVAC systems, energy the O&M staff.
management control systems, 3. Education and professional
and lighting controls systems, registration – the individual, or in
including field experience. the case of a company the lead
52 3. Controls systems, control individual proposed by the firm,
sequences, and integrated should have bachelor’s degree
operations. in an applicable area
4. Performing condition (mechanical engineering,
acceptance testing to detect electrical engineering, etc.), as
latent manufacturing, well as either Professional
transportation, and installation Engineer licensure or other
defects. technical training and past
5. Writing functional performance commissioning and field
test plans. experience.
6. Designing energy-efficient 4. Depth of experienced, qualified
equipment and systems and personnel, and capability to
optimizing control strategies. sustain loss of assigned
7. Providing building operation and personnel without compromising
maintenance and O&M training. quality and timeliness of
8. Testing and balancing of both air performance.
and water systems. 5. Status as an independent
9. Monitoring and analyzing contractor – the individual or
system operation using energy firm chosen to provide
management control system commissioning services should
trending and stand-alone data not be an employee or
logging equipment. subcontractor of the general
10. Testing instrumentation. contractor, construction
11. Inspecting and testing electrical manager, design team, or any
power distribution and other contractor on the project.
generation equipment and
systems. The Past Experience Evaluation
12. Developing quality processes form provided on the following page
and preventive maintenance provides a helpful guide to evaluat
approaches. ing the experience and qualifications
13. Familiarity with LEED point of the CxA candidate. Also be sure
criteria and requirements. to ask for specific project experi
Commissioning Management
1. What is the overall percentage of your business that is devoted to providing commissioning services?
3. How many commissioning projects have you performed in the last five years? How many commission-
ing projects similar in size and scope to the project being procured have you performed in the last five 53
years?
4. If applicable, how many LEED projects have you commissioned in the last five years?
5. Are you a registered engineer (individual)? How many registered engineers on staff have directed
commissioning projects (company)?
ence information if your project in- the CxA’s primary tasks generally
volves complex system require- include the following:
ments, such as those found in
laboratories, medical facilities, tele- ■ Developing a commissioning
communications, computer rooms, plan. This includes a preliminary
etc. commissioning schedule for
inclusion with the bid documents
ROLE AND RESPONSIBILITIES and coordinated with the
construction schedule.
OF THE CXA
■ Preparing commissioning
It is the CxA’s responsibility to work specifications that identify the
with all team members to accom- roles and responsibilities of all
plish the goals set forth in the com- contractors and project team
54 missioning plan. The CxA is not members. This includes helping
responsible for design concept, de- the Owner’s representative
sign criteria, compliance with codes, incorporate commissioning
design, or general construction specifications in the bid docu
scheduling, cost estimating, or con- ments.
struction management. The CxA
may assist with problem-solving de- ■ Reviewing design and construc
ficiencies or non-conformance, but tion documents, drawings, and
ultimately that responsibility resides submittals for commissioning
with Owner and the construction and O&M considerations, as
manager/general contractor. well as for energy performance,
water performance, maintain-
The primary role of the CxA is to ability, sustainability, indoor
develop and coordinate the execu- environmental quality, and
tion of a testing plan, and to observe environmental impacts. This
and document performance to verify includes providing comments to
that systems are functioning in ac- the Owner and A/E and con
cordance with the documented de- ducting follow-up meetings to
sign and the contract documents. ensure that comments are
The installing contractors provide all addressed.
tools or the use of tools to start,
verify, and functionally test equip- ■ For retrocommissioning projects,
ment and systems, except for speci- performing an assessment of
fied testing with portable operation and maintenance
data-loggers that are supplied by the procedures and energy use for
CxA. existing systems. This includes
providing an assessment of
Although the scope of the CxA’s various systems’ operational
role varies for different types of costs relative to maintenance
projects (new construction commis- and utilities, including equipment
sioning, retrocommissioning, etc.), life cycle and project energy
savings.
Commissioning Management
Commissioning Documentation
The requirements of commissioning documentation vary widely depending on the type of commis-
sioning project. Documentation that is vital to the commissioning process, and should be required by
the owner depending on project scope, include:
◆ Pre-construction deficiency list and impact
◆ Commissioning plan, updated as the project progresses
◆ Complete commissioning specification describing commissioning activities and roles and re-
sponsibilities of all parties
◆ Current and updated commissioning schedules
◆ Test forms and report formats
◆ Final commissioning reports
◆ Equipment condition baseline data for on-going maintenance
◆ Contractor performance evaluation reports
◆ Documentation pertaining to benchmarking, testing, and
training
◆ Deficiency reports, updated weekly
◆ Equipment and systems O&M cost report identifying im-
pact to the project and facility
◆ Updated as-built drawings
◆ Systems manuals
◆ Operation and maintenance manuals
Commissioning Management
original and seasonal commis has important roles to play that help
sioning. This includes: determine the success of the com
missioning program.
- Interviewing facility staff
and identify problems or All parties of the commissioning
concerns they have operat team are responsible for ensuring
ing the building as originally that equipment and systems are in
intended. stalled in a quality manner and that
any problems are identified as early
- Making suggestions for as possible. Each individual worker
improvements and record has the authority and responsibility
ing any changes into the to identify poor quality workmanship
O&M manuals. and to recommend stopping work if
serious problems are discovered.
- Identifying areas that may 57
come under warranty or A commissioning team differs from
under the original construc the construction team, as it is made
tion contract. up of representatives from various
organizations and trades that serve
- Assisting the facility staff to as commissioning points of contact.
develop reports, documents The participants will vary: a retro
and requests for services to commissioning project may involve
remedy any outstanding only the Owner and/or facility man
problems. ager and the facility O&M staff,
while a new construction or major
■ If requested, assisting in the renovation commissioning team will
development of a preventative expand to include the design team
maintenance plan, a detailed (A/E), construction manager or gen
operating plan, an energy and eral project manager, installation
resource management plan, contractors, controls contractor, and
and/or as-built documentation. TAB contractor.
COMMISSIONING TEAM
ing as a representative for the
Owner (and with the Owner’s in
MEMBERS put) will use this meeting to describe
each commissioning team members’
The CxA is responsible for the suc roles and responsibilities. The com
cess of the commissioning program, missioning process is described, and
but the formation of a committed the schedule for commissioning ac
commissioning team is critical for tivities is presented.
integrating the commissioning pro
cess into the project at hand. Each The CxA should review the scope
member of the commissioning team of the project and advise the Owner
Commissioning Management
References
1. “Building Commissioning: The Key to Quality Assurance,” U.S. Depart-
ment of Energy.
2. “A Practical Guide for Commissioning Existing Buildings,” Haasl, Tudi
and Terry Sharp, April 1999.
3. “O&M Best Practices: A Guide to Achieving Operational Efficiency,” Sullivan,
G.P. et. al., May 2002.
4. “15 O&M Best Practices for Energy-Efficient Buildings,” Portland Energy
Conservation, Inc. December 1999.Best Practices in Commissioning Man-
agement.
Commissioning Management
STUDY QUESTIONS
1. Occupants in an existing 20-year old, 100,000 square foot building are complaining about poor indoor air
quality conditions (temperature and humidity). Private space heaters are common during the winter, mold
is apparent on some exterior walls, and documents occasionally get damaged from moisture dripping from
duct systems. These problems have been pretty continuous for at least a year and little seems to be done,
in the occupants’ eyes, to mitigate the situation. What are some situations where retrocommissioning
would not be appropriate?
2. Recognizing that commissioning adds up-front cost to the project, what do O&M managers have to do to
gain the support of their management organization to commission their facilities?
63
3. Why is retrocommissioning of existing buildings commonly more difficult to sell to Management than is
commissioning of new buildings?
4. What are five points that can be made to management to counteract the “Why can’t maintenance just fix the
problem?” mentality?
7. What are the benefits and drawbacks of performing commissioning services in-house with your existing
operations and maintenance team acting as Commissioning Authority?
8. What are the aspects of a new construction or renovation project for which the CxA is not responsible?
9. How does the commissioning team differ from the construction team?
10. Define the role of the Owner or facility manager in the commissioning process.
11. On your new building commissioning project, who would you include as your commissioning team mem-
bers, and why?
12. Who would you have on the team to retrocommission an existing building system(s), and why?
Commissioning Management
64
This page left blank intentionally
Commissioning Process
Chapter 5
Commissioning Process
T
he overall responsibility facility Management
of the Commissioning and O&M staff. If
Authority (CxA) during this is your case, the
any and all phases of a CxA will indicate
commissioning project is to coordi the senior 65
nate and direct the commissioning member(s) of your
activities in a logical, sequential, and facility Manage
efficient manner. This is done using ment/O&M staff
consistent protocols and forms, cen that is assigned the
tralized documentation, clear and duties of the CxA.
regular communications, and con Recommendations
sultations with all involved parties. on hiring a CxA
consultant versus
The commissioning approaches de bringing CxA duties
scribed in this guide are as different in-house are provided for each type “The pessimist sees difficulty
as they are similar. This chapter of commissioning. in every opportunity. The op
breaks each commissioning ap timist sees the opportunity in
every difficulty.”
proach down by phase.
COMMISSIONING FOR NEW Winston Churchill
As used in this chapter, Owner can CONSTRUCTION AND RENO
refer to the building owner, the
owner’s project manager or techni VATION
cal representative, and/or the facil
Commissioning is a systematic pro
ity manager. It is any person who is
cess of ensuring that all building
authorized to make decisions re
systems and equipment installed as
garding the commissioning project
part of new construction or renova
and regularly communicates with
tion perform interactively according
the other project team members on
to the design intent and the owner’s
the owner’s behalf.
operational needs. This is achieved
Commissioning Authority (CxA)
generally refers to an independent, This chapter describes the process for implementing commis-
third party commissioning provider. sioning in new construction and major renovation projects. Chap-
In some instances, it is cost effec ter 6 covers the retrocommissioning process, Chapter 7 covers
tive and appropriate to assign the the recommissioning process, and Chapter 8 covers continuous
duties of the CxA to the qualified commissioning.
Commissioning Process
In this Chapter
◆ Commissioning for New Construction and Renovation
◆ Pre-Design Phase
◆ Design Phase
◆ Installation / Construction Phase
◆ Acceptance Phase
◆ Post-Acceptance Phase
◆ Best Practices
Maintainability Factors
1. Accessibility – Consider access to machine room, machine, and machine compo-
nents.
68
2. Visibility – Is the component visible from the floor? Nameplate data? Shadow ef-
fects?
3. Simplicity – Keep it simple; the more complex, the more difficult and costly.
4. Interchangeability – In an emergency, it is nice to “borrow” a critical part from a less
critical component to keep operations up and running.
5. Standardization – Fewer manufacturers and models minimizes spare parts, train-
ing, and special tooling.
6. Ease of Monitoring and Testing – Where are the test points located? Gauges?
Meters?
7. Human Factors – Can the parts be lifted? Should a chainlift be installed to assist
removal of over-sized components, if needed?
8. Safety Concerns – Always paramount.
Supportability Factors
1. Parts Availability – Minimize repair time; con-
sider if parts are locally available or can be or-
dered via internet for next day delivery. Consider
the impact if parts must be special ordered or
customized?
2. Repair Capability – Minimize repair time and
cost; consider availability of local repair capa-
bility. Does a representative need to be flown in
from across the country?
3. Training and Skills – Ensure that training and
education is available commensurate with the
complexity of the equipment being installed.
4. Technical Data – Ensure that all technical sup-
port data is available and provided.
Commissioning Process
INSTALLATION /
scoping meeting soon after the start
of construction. In attendance are
CONSTRUCTION PHASE the identified commissioning team
members and other key individuals
Documentation Requirements: from the project team (Owner,
◆ Verification Checklists
Commissioning Process
Development of Verification
Case Study: Commissioning in Action Checklists
An A/E firm formed a joint venture to design an energy plant to The CxA requests and reviews rel
serve two hospitals. The facility was to produce and pump chilled evant information prior to system
water through a network of pipes and coils within the air-condi- start-up and verification, including
tioning system of both hospitals. The plant experienced several O&M materials and manufacturer’s
pump failures, pipe fractures, and excessive energy consump- start-up and check-out procedures.
tion by the air-conditioning system. This led to a claim by the
hospitals against the joint venture. To mitigate the damages, Before start-up, the CxA gathers
the joint venture agreed to commission the plant. After an exten- and reviews current control se
sive review, the joint venture was able to prove that the alleged quences and interlocks and works
damages were the result of ineffective maintenance, defective with each installing contractor and
maintenance systems, and failed standard service items. The the design team to verify that the
claim was settled for $30,000. functional testing procedures that
are in the commissioning specifica
Had commissioning services been provided during construc- tions are appropriate.
tion, the team probably would have identified potential system
failures prior to occupancy. Neither the Owner nor the joint The CxA writes and distributes veri
venture would have had claim-related expenses. The com- fication checklists to each installing
missioning would have provided a documented benchmark contractor for equipment to be com
against which future system performance could be trended and missioned. The original checklists
compared. (Source: Planning to Avoid Commissioning and are often organized in a binder and
Facility Management Claims; Constructive Comments, Num- left at the job site in the custody of
ber 4, 2005, Victor O. Schinnerer & Company, Inc., the GC/CM so that they are acces
www.Schinnerer.com) sible and can be annotated as work
completion progresses.
Commissioning Process
Personal digital assistants (PDAs) and the CxA consolidates the forms
offer an alternative to paper check later.
lists. The checklists are produced
electronically and downloaded onto The CxA documents systems start
the PDA. Data is entered onto the up by reviewing each installing
PDA directly, real time as the test contractor’s completed verification
ing progresses, then downloaded in checklists and by selected site ob
a permanent file for archiving and servation. Site visits are conducted
analysis. This eliminates the need to by the CxA during equipment instal
maintain paper or reenter data re lation to verify the commissioned
dundantly into the computer, which equipment and systems are installed
increases the likelihood of human according to the manufacturer’s
error. recommendations and to industry
accepted standards, and that equip
Execution of Verification ment has received adequate opera 81
Checklists tional checkout by the installing
contractors. The CxA also wit
Four weeks prior to start-up, install
nesses a sampling of ductwork test
ing contractors and vendors sched
ing and cleaning to be confident that
ule start-up and initial checkout with
proper procedures have been fol
the GC/CM and CxA. The start-up
lowed.
and initial checkout are directed and
executed by the installing contractor
Documentation of all system start
or vendor using the checklists pro
up and verification activities should
vided by the CxA. The CxA ob
be included in the Commissioning
serves and validates the results for
Report (described in the Post-Ac
each type of primary equipment.
ceptance / Warranty section).
To document the process of startup
and checkout, the site technician Deficiencies and Non-
performing the line item task checks Conformance
off items on the verification and The installing contractors clearly list
manufacturer field checkout sheets at the bottom of the procedure form
as they are completed. The install or on an attached sheet any out
ing contractors and vendors execute standing items of the initial start-up
the checklists and submit a signed and verification procedures that
copy of the completed verification were not completed successfully.
checklists to the CxA. The respective contractor provides
the procedure forms and deficien
On smaller equipment or projects, cies to the CxA within two days of
the checklists (which contain more test completion. The CxA works
than one trade’s responsibility) may with the installing contractors and
be passed around to the contractors vendors to correct and retest defi
to complete. For larger equipment, ciencies or uncompleted items, in
each trade may need a full form volving the GC/CM, if necessary.
Commissioning Process
Commissioning Record
The CxA compiles, organizes, and
indexes commissioning data by 89
equipment for inclusion in the O&M
manuals. The correspondence,
meeting minutes and progress re
■ Formal manufacturer and
ports, miscellaneous notes, etc. kept
installer training sessions.
during the project will not be re
tained into this record, but stored in
It is highly advantageous for the
a separate volume.
maintenance technicians to see ca
bling, piping, ductwork, and other
Operation and Maintenance normally hidden systems prior to
Staff Training their being covered and obstructed
by insulation, ceilings and drywall.
Operations and maintenance staff
In addition, the O&M staff must be
training actually begins early in the
walked through emergency proce
commissioning process through the
dures and various operational se
participation of select representa
quences under all possible
tives on the commissioning team.
scenarios.
As the project progresses, the
O&M staff becomes more and
The O&M staff must become fa
more acquainted with the building’s
miliar with the building’s control sys
features. Designated representa
tem:
tives visit the job site during se
lected time periods including:
■ How the control system works,
including the sequence of
■ System installation.
operations.
■ System verification.
■ The control system structure –
■ Hands on equipment startup.
what is connected to what.
■ Hands on functional perfor
■ The control system components
mance testing.
and their proper nomenclature
■ Hands on condition acceptance
(e.g., actuators, sensors, valves,
testing.
terminal boxes).
Commissioning Process
■ The control system monitor, its training plan and in coordinating and
various screens, and the infor scheduling the overall training for
mation the software is capable the commissioned systems. The
of providing. CxA develops criteria for determin
■ Alerts, alarms, and emergency ing that the training has been satis
procedures. factorily completed, including
attending some of the training.
The CxA is responsible for oversee
ing and approving the content and The CxA recommends approval of
adequacy of formal training of the training to the Owner, who gives
O&M personnel for commissioned approval when acceptable training
equipment. The GC/CM is respon has been conducted.
sible for training coordination and
scheduling and ultimately for ensur Scheduling a brief presentation by
90 ing that training has been completed. the design engineer is a good prac
The GC/CM and installing contrac tice that informs the O&M staff of
tors actually present the training ma the idiosyncrasies and features of
terial. The CxA attends all training the installed systems. It also allows
sessions and sees to it that important the staff to ask questions that re
issues are raised. main after the construction process
and were never really completely
Each installing contractor and ven clear on the design drawings.
dor responsible for training submits a
written training plan to the CxA for Video-taping the training is another
review and approval prior to train good practice for archiving the infor
ing. The plan should cover the fol mation and for training new employ
lowing elements: ees as they come on board. Good
sound is as important as good pic
■ Equipment included in training. ture, so if hands-on and other train
■ Intended audience. ing is taking place in the actual
■ Location of training. equipment rooms, then some mitiga
■ Objectives. tion of equipment noise (such as
■ Subjects covered (description, turning off air compressors) may be
duration of discussion, special required.
methods, etc.).
■ Duration of training on each Special Training and Orientation
subject. The following are additional special
■ Instructor for each subject and
training and orientation sessions that
instructor’s qualifications. may be requested by the Owner:
■ Methods (classroom lecture,
video, site walk-through, actual ■ Recommissioning - The CxA
operational demonstrations, provides instruction on the use
written handouts, etc.). of blank functional test forms
for periodic recommissioning of
The CxA assists the GC/CM and equipment and systems, per the
Owner in developing an overall specification.
Commissioning Process
■ Architect/Engineer - The A/
E provides a general overview
POST-ACCEPTANCE /
of the facility, its use, special WARRANTY PHASE
features, tenant and public
considerations, etc. Documentation Requirement:
◆ Final Commissioning Report
■ Mechanical Design Engi
neer - The mechanical de The CxA returns to the project ap
signer provides an overview of proximately 10 months into a 12
the major systems and equip month warranty period. During this
ment in the facility, including for visit(s), the CxA reviews with the
each system: the design intent, facility staff the quality and reliabil
why the system was chosen, an ity of the current building operation.
overview of its operation and The status of outstanding issues re
interactions with other systems, lated to the original and seasonal 91
any special areas to be aware commissioning is also addressed.
of, issues regarding future The CxA interviews facility staff
expansion and remodeling, etc. and to identify problems or concerns
that they have operating the building
■ Electrical Design Engineer as originally intended. Issues dis
The electrical designer provides cussed may include:
an overview of the major
systems and equipment in the 1. Current building operation.
facility, including for each 2. Any outstanding issues related
system: the design intent, why to the project and the commis
the systems was chosen, an sioning process.
overview of its operation and 3. Any problems or concerns with
interactions with other systems, operating the building as
any special areas to be aware originally intended and designed.
of, issues regarding future 4. Suggestions for improvements
expansion and remodeling, etc. and for recording enhancements
in the O&M manuals and final
■ Vendors and Manufacturers Commissioning Report.
- The vendor or manufacturer 5. Areas that may come under
of any item that is commis warranty or under the original
sioned provides an overview of construction contract.
that particular piece of equip 6. Documentation of reports and
ment in the facility, including for documents, and requests for
each item its physical make-up, services to remedy outstanding
capabilities and interactions problems.
with other systems, test points
for condition monitoring (if Deferred and Seasonal
applicable), any special areas to Testing
be aware of, and issues regard
ing expansion capabilities or During the warranty period, sea
adding capacities. sonal testing (tests delayed until
Commissioning Process
BEST PRACTICES
■ In nearly all cases, it is easier
and in the long run more cost
effective to hire an independent,
third-party commissioning
authority to guide the commis
sioning project.
STUDY QUESTIONS
1. What are the commissioning documentation requirements for each phase of construction? Why are these
documentation requirements so important to the overall commissioning program?
2. What is the role of the CxA in verification and functional performance testing? What is the role of the
installing contractors? The CM/GC?
3. What are some factors to bear in mind when evaluating maintainability and supportability during design
review?
4. How are the design intent and basis of design different? What part does the Owner’s project requirements
94 document play in both the design intent and basis of design?
5. What issues should be checked for each commissioned system during design review?
7. How is the commissioning specification different from the commissioning plan? Which party(ies) prepares
each document?
8. Who conducts commissioning meetings during the installation/construction phase of the project? How do
these meetings relate to regular construction team meetings?
9. When is verification testing performed, and by whom? When is functional performance testing performed,
and by whom? When is deferred and/or seasonal testing performed, and by whom?
10. What is the process for reporting and correcting deficiencies and non-comformance issues?
11. How does the TAB contractor fit into the commissioning program on a construction project?
12. What are some of the tools and instrumentation used by the installing contractors and CxA to accomplish
functional performance testing?
13. When should test sampling be utilized during functional performance testing?
14. What are the benefits of performing condition acceptance testing in addition to functional performance
testing?
Retrocommissioning Process
Chapter 6
Retrocommissioning Process
■
R
etrocommissioning is a It’s a
systematic process for prerequisite
improving and optimizing for LEED
building performance in EB (Existing
an existing building that has never Buildings). 95
gone through any type of commis
sioning or quality assurance pro Like commis
cess. Its focus is usually on sioning,
energy-using equipment such as retrocommis
mechanical equipment, lighting, and sioning seeks to
related controls. However, building identify and cor
envelope is an increasing retrocom rect the root
missioning issue, particularly in causes of prob
humid areas where mold is a par lems, not the
ticular problem. symptoms (e.g.,
“the room is hot”). Also like com “It is far easier and less ex
The most common reasons why an missioning, retrocommissioning is pensive to maintain a build
ing that operates correctly
Owner may want to retrocommis concerned with how equipment,
than to maintain one that
sion a facility include: systems, and subsystems function does not.”
together, but it does not generally
■ It addresses the gap between a take a whole-building Rusty Ross
building that does not work as approach to efficiency.
intended and an already over
burdened maintenance and Retrocommissioning does not in
engineering staff. clude the replacement of significant
■ The building is not providing an HVAC and other system compo
adequate work environment. nents. Rather, it focuses on the veri
■ There are indoor air quality fication of the proper controls
issues. strategies, sequences of operation,
■ Mold is present in the building.
■ The building’s energy costs are
too high compared with similar This chapter describes the process for implementing
facilities. retrocommissioning in new construction and major renovation
■ Equipment and systems are projects. Chapter 5 covers the commissioning process, Chapter 7
sustaining damage over the long covers the recommissioning process, and Chapter 8 covers con-
term from the indoor environ tinuous commissioning.
ment.
Retrocommissioning Process
Control systems have become so sophisticated that few end users really understand fully how to use them to
optimize system performance. Typically, they are not programmed or calibrated correctly on the front end,
and maintenance professionals often bypass them completely to address exigencies.
In addition, any opportunities for the Master List as a guide, the Owner
installation of energy conservation determines which recommended im-
measures or adoption of more effi- provements to implement. Items
cient procedures and practices ob- should be prioritized according to
served during the investigation cost effectiveness, criticality, and
process, related to the retrocom- how effectively they meet the
missioned systems or not, are also project objectives. It is likely that
be identified. many of the recommendations will
have no cost/low-cost solutions, 103
In the final report, the CxA orga such as personnel habits, that can
nizes the deficiencies on the Master be implemented right away.
List into categories, such as design,
installation, maintenance, and opera To aid in the decision making, the
tion. This allows the Owner to iden CxA provides economic analyses
tify trends that are contributing to (estimated cost, savings, payback,
problems in certain areas. and return on investment) on those
items that can be quantified.
The retrocommissioning team also
performs “quick fixes” during the If substantial modifications or capi
discovery phase. These are simple tal improvements are required, for
repairs and adjustments, such as mal commissioning of the affected
connecting an unconnected section systems should be included during
of flex duct, unblocking a duct, the various construction phases as
tightening a fan belt, and cleaning a described in Chapter 5.
coil. Though relatively insignificant
in nature, these may be masking a
real problem.
PROJECT HAND-OFF
Documentation Requirements:
CORRECTIVE PHASE ◆ Updated Building Documenta
tion
Documentation Requirement: ◆ Final Retrocommissioning
◆ Master List of Deficiencies and Report
Improvements
During project hand-off, equipment
During this phase, cost-effective and systems are tested again to
opportunities are selected for imple confirm the operational and energy
mentation. Based on the findings of performance of the installed im
the site assessment and diagnostic provements.
monitoring and testing, and using the
Retrocommissioning Process
“It has been estimated that 70- to 80-percent of all unplanned shutdowns (of electrical systems) are due to
human error, meaning that only 20- to 30-percent of unplanned shutdowns are due to equipment malfunc-
tions or poor design.” Source: A Practical Guide for Electrical Reliability, EC&M (Oct 2004).
Retrocommissioning Process
■ Retrocommissioning plan
BEST PRACTICES
■ Master List of Deficiencies and ■ Keep the retrocommissioning
Improvements scope focused on the facility’s
■ Cost/savings analyses for each mission.
implemented recommendation
■ Site assessment results ■ Concentrate on only the essen
■ Diagnostic monitoring and tials.
testing results (pre- and post-
implementation) ■ Collect only important and
■ Controls sequences and block especially useful information. Over the span of a few years, it
diagrams indicating component is highly likely that the build
functions and relationships ■ Link the retrocommissioning to ing systems have been modi
■ Updated TAB data the facility’s operating and fied. While modifying systems
■ Equipment condition baseline business objectives: is not a problem in itself, the 105
data lack of documentation can be.
■ All completed functional - It documents performance
performance test forms criteria and data for track
■ Recommended frequency for ing, evaluating, and improv
recommissioning ing systems.
■ Recommended frequency for
recalibration of sensors and - It correlates system perfor
actuators mance to monetary indices
■ Documentation of implemented through energy savings,
recommendations improved maintenance,
■ Energy saving features and improved worker productiv
strategies used in the building ity, and occupant satisfac
■ Listing of all user adjustable set tion.
points and reset schedules
■ Recommended frequency for ■ The documentation required by
review of set points and reset each commissioning process
schedules can be daunting, but will prove
■ Photographs of every defi an invaluable resource for
ciency found building management, O&M,
and future commissioning
Turning the Report into efforts.
Action
It is crucial for the facilities team to
buy into the report and results for it
to succeed, then for the documenta
tion to be used and maintained. It is
good practice to develop a checklist
of action items that can be ad
dressed, confirmed, filed, and refer
enced.
Retrocommissioning Process
STUDY QUESTIONS
1. What are the documentation requirements for each phase of a retrocommissioning project? Why are these
documentation requirements so important to the overall success of the retrocommissioning project?
2. What system and equipment are the best candidates for retrocommissioning investigation, and why?
3. How do the steps involved in retrocommissioning differ from the steps involved in new construction com-
missioning?
4. If building documentation already exists, is there a need to further develop or refine documentation during
106 retrocommissioning of that building?
5. What are the methods of investigation used during the retrocommissioning discovery phase?
6. What documents make up the final commissioning report developed at the conclusion of the
retrocommissioning project?
7. What role does the O&M staff play in retrocommissioning? The Owner? Is it necessary to hire an indepen-
dent CxA?
Recommissioning Process
Chapter 7
Recommissioning Process
R
ecommissioning refers to particularly if
commissioning of an ex they have been
isting building that has problematic or
already gone through the highly energy
commissioning process. It is per inefficient. 107
formed long after the facility is con However, re
structed and placed into service. commissioning
Some sources and providers use the is most often
term “recommissioning” synony applied to the
mously with “retrocommissioning” existing
to collectively address the commis building’s
sioning of existing buildings. HVAC, refrig
eration, and
Like all other forms of commission electrical sys
ing, the goal of recommissioning is tems and their
to ensure that all power-using and controls, which
power-conserving systems in a often are the
building work together to meet the sources of the
needs of the current occupants and biggest opera
the actual performance require tional problems: “Perserverance is the hard
ments of the Owner. work you do after you get
■ Increased occupant complaints tired of doing the hard work
Recommissioning provides addi ■ Increased or fluctuating energy you already did.”
tional opportunities to improve facil use Newt Gingrich
ity efficiency and addresses issues ■ Increased maintenance calls
that may have arisen since the origi
nal commissioning. It can help re Corrected, these systems also are
duce energy consumption, maximize likely to produce the biggest cost
the efficiency and output of the air savings. Recommissioning provides
and water distribution systems, en a systematic approach for finding,
hance performance, and enhance
the occupants’ working environment
and comfort. Like commissioning, This chapter describes the process for implementing recommis-
recommissioning may involve func sioning in existing buildings. Chapter 5 covers the commissioning
tional performance testing of most process, Chapter 6 covers the retrocommissioning process, and
or all major building systems, Chapter 8 covers continuous commissioning.
Recommissioning Process
Recommissioning generally in
cludes:
Recommissioning Process
■ Communicating among the
commissioning team and facility
staff, occupants, and users to Project Planning
uncover building system Determine project objectives
problems and opportunities. Determine commissioning scope: whole building or
targeted on problem equipment / systems?
■ Establishing that the original Hire CxA or assign duties to O&M personnel
basis of design (if available) and
operation plan are still appropri
ate for the use, occupancy, and
occupant mission of the build
ing. Design Review
■ Reviewing and benchmarking Review original design intent, basis of design, and 109
drawings and update if necessary for changes
key systems operations/ in building use, occupancy, etc.
performance against the Review original commissioning plan and commissioning
previous commissioning specifications and update if necessary
recommendations and
baselines.
■ Identifying past and current
persistent problems. Implementation and Verification
■ Reviewing maintenance Develop performance baselines
program procedures, schedules, Measure current equipment and system performance
Perform functional performance tests to verify that equipment
and protocols and verifying their and systems operate as designed
effectiveness against actual Make adjustments and retest if deficiencies are found
Review and update O&M manuals and staff training
equipment observations. Document energy and operational savings and comfort
■ Reviewing the operators’ and improvements in updated commissioning report
maintainers’ technical capabili
ties relative to the building’s
needs and to the training
program (or contractual re
quirements). Periodic Review
Site visits, interviews, energy use analysis, etc.
■ Performing energy analysis of Note substantial changes in facility use, occupancy, etc.
available data, including utility Write follow-up project report at 1 year
bills.
■ Identifying specific energy
conservation measures, particu
larly no-cost and low-cost ■ Validating and/or modifying the
solutions. operations/controls sequencing
■ Performing a condition assess as appropriate for optimum
ment using condition monitoring operations.
technologies. ■ Conducting testing, adjusting,
■ Recommending repairs and and balancing (TAB) on the
modifications to optimize HVAC air and water distribu
building performance. tion systems, as required.
Recommissioning Process
Appendix A.
The project kick-off meeting brings informed and brought into the pro with thermostats, sensors, and
the recommissioning team together cess to minimize disruptions to diffusers, and introducing de
to review the Commissioning Plan. themselves and to the testing. vices such as portable heaters,
contribute to the inefficiency
At a minimum, the CxA, TAB pro
vider and controls technician (as ap Document Review of a building’s HVAC systems.
plicable), Owner and/or designated
The document review includes re
representatives, and O&M Man
viewing work orders and trouble
ager should attend. Each team
calls from the building Owner, occu
member is introduced and their re
pants, and users to identify and sur
sponsibilities are stated. The
vey recurring, persistent, and/or
Owner’s expectations, goals, and
serious problems. Comments such
objectives are reiterated. Communi
as hearing “loud noises” from
cation protocols, schedules, and
ductwork or feeling walls vibrate
safety issues are discussed.
whenever an AHU kicks on are in
valuable in determining root causes
The kick-off meeting is also a good
of problems.
opportunity to conduct an interview
of occupants, users, operators, and
The commissioning team studies the
maintainers to determine the scope
building’s documented problems and
and degree of problematic condi
looks for trends and links. Mainte
tions from their perspectives (are
nance records, operating cost
the persistent hot and cold calls a
records, and energy use information,
systematic problem. The interview
as available, will prove helpful.
survey may take any form, but
should follow a prescribed outline.
As-built drawings are reviewed to
Sample interview questionnaires for
understand system configurations
building and maintenance
and modifications from the original
Management are included in
design documents. The building his
tory is also reviewed to check on
Recommissioning Process
ous modes and conditions over time. pressure, current, light levels and du
Variables often trended include en rations, and similar information.
ergy, temperatures, pressures, flow
rates, weather data, and set points. A utility bill analysis, conducted early
By analyzing trends, the recommis in the project, gives the commission
sioning team characterizes perfor ing team a good understanding of
mance and validates whether or not how the building is consuming en
the systems operate correctly. ergy and the direction toward which
they should target their efforts.
Trending may be conducted by re
viewing and plotting BAS and All major equipment and systems
EMCS data over time. The commis are checked to record current oper
sioning provider may require assis ating parameters and to verify the
tance from the controls vendor, correct operation of their parts. This
114 particularly in developing, download is analogous to the verification
ing, and formatting system data for checks in new construction and
analysis. renovation commissioning. Verifica
tion checklists that were developed
Dataloggers also provide a trending when the building was first commis
capability. These are small, portable, sioned can be used again.
battery-operated devices utilize soft
ware that can be downloaded onto a This is also an appropriate time to
laptop and easily graphed and ana check the equipment condition, if it
lyzed. Data collected typically in is not already done in a Reliability
cludes temperatures, humidity, Centered Maintenance (RCM) pro
gram, using available condition and
predictive technologies such as in
frared thermography, vibration
analysis, equipment alignment, air
borne ultrasonic leak detection, oil
analysis, insulation testing, and motor
analysis.
Functional Performance
Testing Recommissioning In Action
The CxA schedules, oversees, wit- A middle school was experiencing severe indoor air quality prob-
nesses, and documents the func- lems and the school district requested the help of a commissioning
tional performance testing of all consultant. Recommissioning found that among other things, all of
equipment and systems according to the building’s fresh air vents were closed and systems were not
the Commissioning Plan. The facil- operating as originally intended. Since the original controls con-
ity O&M staff executes the tests, tractor had gone out of business, each time an occupant com-
which use the same protocols and plained about the building’s comfort level over the years, the
forms that were developed when maintenance staff responded by closing the offensive vent, thereby
the building was last commissioned. addressing the symptom, not the root cause.
Functional testing includes operating
the system and components through The commissioning team confirmed that the HVAC systems, when
the significant normal and emer- new, had been installed correctly. The facility would have most likely 115
gency modes of operation, including: functioned adequately had the support staff understood from the
start the control system, its maintenance requirements, and how it
1. Each of the written sequences functions. (Source: E. Thomas Lillie, “Better Late than Never,” Engi-
of operation neered Systems Magazine, May 25, 2000.)
2. Start-up and shut-down
3. Unoccupied mode
4. Manual mode gers to provide a high level of confi
5. Staging dence in proper system function.
6. Miscellaneous alarms
7. Power failure Building Management
8. Interlocks with other systems
or equipment Systems (BMS)
Recommissioning the BMS is one of
A sample functional performance the most cost effective building and
test form is included at the end of energy performance measures that
Appendix A, Sample Commission can be undertaken. The operational
ing Forms. status and correct programming of
each strategy of the BMS is veri
Simple repairs and adjustments, fied. This requires trending of the
such as belt replacement, damper BMS data over time to see if the
adjustment, and sensor calibration, strategies are actually controlling
not detected earlier and found dur the equipment as they should. The
ing the investigation may be done at cause of malfunctioning control
this time to maximize system effi strategies is then determined. For
ciency and to enable system testing, example, is the system not operat
adjusting, and balancing. ing’ correctly because of a software
programming error? Overridden
Functional testing is accomplished control strategy? Ineffective sensor
using a combination of conventional locations? Malfunctioning compo
manual methods, control system nents?
trend logs, and stand-alone data log-
Recommissioning Process
combination of these, and the data gas, and chilled and hot water are
compared to the initial baseline data. reviewed for long-term monitoring.
This new baseline data becomes the
baseline against which future Final Commissioning Plan
recommissioning activities will be
compared. The CxA finalizes the updated Com
missioning Plan after functional per
Monitoring and Verification formance testing is complete,
recommended improvements have
The impact of the minor adjustments been implemented, and there are no
made during the functional perfor more changes or equipment substitu
mance testing and of any imple tions planned.
mented improvements is
monitored over a reasonable time to Commissioning Report
verify their impact on occupant
comfort, on operational and energy The fmal Commissioning Report is a
performance, and on control se record of the recommissioning ac
quences and schedules. tivities and measures implemented
and recommended for implementa
Room-by-room measurements are tion. It incorporates a summary re
made using hand-held meters or por port of participants and their roles,
table dataloggers. Energy model building description, project objec
data is collected using the short-term tives, an overview of the commis
methods discussed previously. Utility sioning scope, and a general
bills and meter data for electricity, description of testing methods and
results. The Commissioning Report
Recommissioning Process
list of DDC inputs and outputs, their Owner. Since staff members who
associated component, sensor or ac lack systems expertise are often the
tuator type, and alarm limits. Se root cause of many problems that
quences of operation should be necessitate recommissioning ser
updated for each HVAC and lighting vices in the first place, the training
system, with the rationale for any should be given high priority.
changes and deviations hi-lighted for
the Operator’s understanding. Up
dated system diagrams also assist
PERIODIC REVIEW
the operators and maintainers by de Documentation Requirement:
picting the entire system in sche ◆ First-Year Report
matic format rather than in
component bits and pieces. The CxA performs follow-up site
visits and interviews at periodic, pre
120 O&M Staff Training scribed intervals with Facility Man
agement and O&M staff to review
Training should actually be hands-on the system operation, identify any
and take place throughout the re operating problems, and recommend
commissioning process. further improvements.
The CxA provides additional train
ing, or coordinates and arranges for Energy data is reviewed periodically,
training with appropriate vendors in if not continuously, to assess the
conjunction with the recommission need for further recommissioning.
ing, if the improvements made to the At this time, increased building en
equipment and systems warrant ad ergy consumption and decreased
ditional familiarization or emphasis performance efflciency is flagged.
or if a particular operation or prac The CxA then works with the O&M
tice is of a particular concern to the staff to perform an evaluation, de-
References
1. Retro-Commissioning’s Greatest Hits, Haasl, Tudi et aI, Pacific Northwest National Laboratory, March
2000.
2. A Practical Guide for Commissioning Existing Buildings, Haasl, Tudi and Terry Sharp, April 1999.
3. Energy Star Buildings Manual.
4. Commissionpedia, U.S. Army Corps of Engineers; available online at www.cecer.army.mil/KD/HVAC/
index.cfm?chn_id=1136.
5. Project Planning Tools, U.S. General Services Administration; available online at
www.projectplanningtools.org.
6. State of California Guide to Commissioning Existing Buildings, California Commissioning Collaborative,
February 2006; available online at www.CACX.org.
Recommissioning Process
ing energy and operational perfor provide from the initial commis
measures.
■ Recommission the entire
Building staff play a key role in building every three to five
tracking the measures after they years, or put in place an ap
have been implemented to ensure proach in which one-third to
that they work properly. This avoids one-fifth of the building’s
the need for the CxA to make a re systems are recommissioning
turn visit to verify that savings are each year, on a rotating basis.
persisting. This makes recommissioning
“business as ususal” rather than
A first-year report is developed by a special event.
the CxA. It documents measured 121
energy savings, recommends any ■ The more substantial the
additional changes or building im changes a facility endures, the
provements, provides recommen more frequently it should be
dations for ongoing O&M staff recommissioned.
training, and establishes a schedule
for future recommissioning, if a ■ Integrate recommissioning into
continuous commissioning program the facility’s preventive mainte
is not established. The more fre nance program to improve the
quently the building undergoes performance of both ap
changes in facility use and occu proaches.
pancy patterns, the more often the
building should be recommissioned. ■ When recommissioning with a
limited budget, focus first on
BEST PRACTICES HVAC, refrigeration, and
electrical systems and their
■ Employ recommissioning to controls, which are often the
improve facility efficiency and sources of the biggest opera
address issues that may have tional problems.
arisen since the original com
missioning. ■ Focus also on low- and no-cost
recommedations, as these can
■ Keep recommissioning in mind have a surprisingly big impact
when performing initial building on the facility’s bottom line.
commissioning: the more forms
Recommissioning Process
STUDY QUESTIONS
1. What building systems are most often involved in recommissioning, and why?
2. How long after initial building commissioning should one wait to recommission the facility? What factors go
into determining how long to wait before recommissioning?
3. How does recommissioning differ from retrocommissioning? How are the two processes similar?
122 5. What are typical items to look for during the design review phase of the recommissioning process?
6. How important is it to establish a performance baseline, and what are some typical methods for baseline
development?
Chapter 8
Continuous Commissioning
Process
Process
detect any
Project Development
Decide which equipment and systems will be
analyzed for potential improvements
Conduct commissioning audit and develop project
scope
Hire CxA or assign duties to O&M personnel
Develop detailed work plan and form project team
Periodic Review
Continue to track, trend and analyze energy and
performance data for anolmolies
Follow-up site visits and interviews
Write follow-up project report at 1 year
These automated systems are typi cell phone, and a service technician
cally a facility’s building automation responds as necessary. Some sites
system (BAS) or energy manage incorporate an enterprise energy
ment and control system (EMCS), management system (EEMS), which
which provide local, remote-capable, uses the Internet to connect all ma
system alarm, control, and archiving jor energy-consuming devices in a
information. They allow Facility facility or group of facilities, for ad
Management to monitor, manage, ditional analysis and problem solu
and control mechanical systems and tions.
lighting remotely. Consumption and
control parameters are trended and If it is found that continuous com
compared. Alarms are indicated, missioning has merit, the process
usually communicated to a pager or continues with the formation of the
126
Decision
Fault No Fault
Detection
Tolerate Request
Repair
No Action Proactive and
Fault Required Diagnosis Continue
Tolerate? NO
Measurements
Fault
Reconfigure
Diagnosed Controls?
Reconfigure
Fault Evaluation
• Safety
• Availability
• Energy/Cost Impact Operate
• Comfort Alarm/
• Environment Impac Shutdown
Continue to NO
Operate?
( (
Equipment used so that the effort stays fo-
Condition cused, coordinated, and thoroughly
- Meet Output documented.
Continuous
Requirements
Cx
- Optimize Efficiency
IMPLEMENTATION PHASE
Documentation Requirements:
considered during the commis- ◆ List of Improvements Selected
sioning analyses. for Implementation
■ Conducts field measurements. ◆ Commissioning Report
■ Helps interpret collected data,
128 as required. The assessment may only identify
■ Implements mechanical, electri suspected areas for improvement.
cal, control, and systems There may be a need to obtain more
software changes recommended complete and exact data on when
by the Systems Engineer. and how systems are actually oper
ating. Using the most recent
Work Plans baseline data from previous commis
sioning efforts, the commissioning
Appendices J and K of PECI/ team compares it to the actual col
ORNL’s A Practical Guide for lected data manually or automati
Commissioning Existing Buildings cally.
provide good examples of detailed
work plans. These plans document
and maintain a focus on the systems
Step 1 - Fault Detection
being monitored and at what points, Diagnostic monitoring allows the
the devices performing the monitor commissioning team to observe criti
ing, their settings and locations to cal parameters such as inside and
ensure continuity, minimum and outside temperatures, humidity,
maximum allowable parameters, and flows, pressures, speeds, noise lev
recommended actions in the case of els, light levels and intensities, and
non-compliance or alarm situations. more under typical operating condi
They also include identification of tions. Three of the most common di
involved personnel, general informa agnostic monitoring methods are
tion narratives, special instructions, BMS/EMCS/EEM trend logging,
and step-by-step procedures, as ap standalone data logging, and manual
propriate. functional performance testing.
team ensures that system documen must be reconciled during the com
tation is updated to reflect changes, missioning analysis.
such as to control sequences.
O&M Staff Training
An improved and a more consis
tently managed indoor air environ Since continuous commissioning is
ment leads to a more comfortable likely to be an in-house function, it is
and healthier workplace. The result necessary for the responsible per
will be increased productivity. Also, sonnel to be trained in and to have a
since monitoring system operations good understanding of the BAS/
and output parameters contributes to EMCS software and monitoring
the equipment condition data under equipment capabilities, data analysis,
an RCM program, system reliability data collection techniques, and stan
and maintainability, and its associ dard operating procedures (SOP) to
136 ated costs, will also improve. be followed when disturbing data
and trends are detected.
One drawback is that improving in
door air quality and comfort may ac
tually increase building energy BEST PRACTICES
consumption. For example, increas
ing the minimum building outside air ■ It may be easier and in the long
will increase the air-conditioning run more cost effective to hire
load in the summer and the heating an independent, third-party
load in the winter. This trade-off Commissioning Authority to set
the commissioning project in
motion and to train and mentor
the in-house staff as needed
until the comfort and technical
levels required of the staff are
References achieved.
1. Retrocommissioning Handbook for Facility Managers, Portland
■ Ongoing monitoring and verifi
Energy Conservation, Inc., March 2001.
cation of energy and operational
2. Liu, Mingsheng, Ph.D., P.E., et. al., Continuous Commissioning performance are essential to
Guidebook: Maximizing Building Energy Efficiency and Com- maintain persistence of improve
fort, October 2002. ments and to ensure that
3. Haasl, Tudi and Terry Sharp, A Practical Guide for Commis- equipment and systems are
sioning Existing Buildings, April 1999. operating at optimal efficiency.
4. Culp, Charles H., et al, Continuous Commissioning in Energy
Conservation Programs, http://energysystems.tamu.edu). ■ A well-trained O&M staff with
adequate resources is crucial to
5. Mahling, Dirk K. and Lehman, Keith, Enterprise Energy Man-
the success of any commission
agement, HPAC Engineering, December 2005.
ing program.
6. Methods for Automated and Continuous Commissioning of
Building Systems, Portland Energy Conservation, Inc. and
Battelle Northwest Division, April 2003.
Continuous Commissioning Process
137
STUDY QUESTIONS
1. What are the documentation requirements for each phase of the continuous commissioning process? Why
are these documentation requirements important to the overall success of the continous commissioning
process?
2. How does continuous commissioning differ from new construction/renovation commissioning? How does
it differ from a typical preventive maintenance program?
3. Who are the continous commissioning team members, and how do their roles differ from a new construc-
tion/renovation commissioning team?
4. What are the four steps involved in the implementation phase of continuous commissioning?
5. What are the methods of investigation used during the continuous commissioning implemention phase?
7. What are the factors involved in developing an approach to correcting detected anomalies?
8. How would you prioritize and implement improvements recommended through the continuous commis-
sioning process?
Continuous Commissioning Process
138
This page left blank intentionally
Sustainable Commissioning
Chapter 9
Sustainable Commissioning
A
successful commission purchase billions of dollars of mate
ing program takes thor rials for operations, maintenance,
ough planning and expert repair, and renovation.
execution, but several
additional considerations are impor The collective impact that commis Don’t blow it - good planets
139
tant to the success of commission sioning could have on building oper are hard to find!
ing, including developing a good ating and maintenance costs, energy Environmental Corollary
measurement and verification pro usage, and environmental impacts is
gram and ongoing operations and tremendous, and this potential is not
maintenance staff training. going unrecognized. In fact, com
missioning – as has been discussed
In addition, the Federal government throughout – is now a mandatory
has demonstrated a commitment to requirement for the acceptance of
sustainable design, and commission many sustainable or “green” build
ing has a central role to play in the ings.
building and maintenence of
“green” buildings as well. And this leads us to LEED – Lead
ership in Energy and Environmental
COMMISSIONING FOR Design.
VERIFICATION OF THE
system and fuel type.
■ Summarize the operation
COMMISSIONING PROGRAM ■
schedules of systems.
Describe the efficiency of all
Adopting measurement and verifica systems in your facility.
tion (M&V) approaches will help in ■ Identify operation, scheduling
dicate the effectiveness of the and maintenance efficiency
commissioning program, both as it opportunities.
unfolds and at project completion. ■ Describe opportunities for off-
the-shelf efficiency technolo
The easiest way to quantify equip gies.
ment and system performance be ■ Describe engineered energy
fore and after retrocommissioning is efficiency solutions.
Sustainable Commissioning
■ Describe in detail the cost and TRACE, Carrier HAP, BLAST, and
energy cost savings of any Energy Plus.
capital investments recom
mended. There are also free resources avail
■ Identify opportunities that will able online, such as the benchmark
require further design. ing spreadsheets for office buildings
provided by the Oak Ridge National
The three basic methods for estab Laboratory. The benchmarking
lishing an EUI baseline are: spreadsheets provided allow you to
identify where your specific office
1. Energy Calculations, which building ranks relative to others.
incorporate information about They calculate the EUI of your
and energy consumption history building, provide the typical (me
of energy-using building sys dian) EUI for office buildings with
tems and equipment. the same characteristics as yours, 143
and identify where your building’s
2. Regression Analysis, a statisti performance ranks compared to
cal technique that uses histori others (percentile of EUI).
cal data derived from meters to
isolate one or more variables The benchmarking spreadsheets go
that affect energy use (result beyond the customary normalization
ing, for instance, in an equation by floor area and account for per
that relates energy use to formance differ
weather or building use vari ences due to
ables). When historical, me variations in
tered data are available, worker density,
regression analysis defines the number of
energy use relative to the entire personal com
building and allows greater puters, operating
flexibility in making recommen hours, occu
dations related to energy pancy type, and
efficiency. heating fuel
types. Beyond
3. Simulation, a sophisticated set floor area, these
of engineering calculations that characteristics
attempts to forecast energy use were found to
on the basis of a building’s size be the most
and shape, equipment, levels of common and
insulation, types of windows most important
and doors, etc. drivers of elec
tric and non
There are many software packages electric energy
available to help your facility de use in U.S. of
velop an EUI for benchmarking im fice buildings.
provements, including DOE2, Trane Location effects
are accounted
Sustainable Commissioning
1. Initial training
There are several common prob- on new or
lems that hinder this vital process, renovated
however. Although O&M staff equipment and
training is cited as a requirement for systems upon
most commissioning projects, the completion of
actual training is often an after- the commis-
thought as the project nears sioning pro-
completion. Too often training is cess. This
poorly coordinated, loosely-struc- training is
tured, informal, lacking in well-de- optimally
fined objectives, and too tightly provided by the
scheduled. Training is often handed CxA or each
over to equipment manufacturers, responsible
who can certainly provide adequate installing 145
information on their own products contractor to
mechanical,
to Implement
all training during the project
147
STUDY QUESTIONS
1. What is LEED certification and why is it so important to Federal facility owners and managers?
3. What are some of the methods typically used to develop an annual energy use index (EUI)? What is the
benefit of developing an accurate EUI for your facility?
4. What are some of the resources available to help when trying to measure and verify building performance?
5. What are some of the mistakes typical of an incomplete O&M training approach?
148
This page left blank intentionally