Professional Documents
Culture Documents
RISK
CONTROL
No. ACTIVITIES
C L R
Physical hazard
while handling
material.
Working at height.
Struck by moving
vehicle.
Unskilled Labor
Mobilization of Unconditioned
Personnel, vehicles, / damaged Equipment
1 Equipments & Vehicle accident 5 3 15 A
Delivery of material
to job site.
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
RISK
USED
C L R
Compliance on PTW requirements to be Basic PPEs S P
ensured. (Safety helmet, =S =PE
Trained and competent person to be Safety Glass, UP RFO
monitored. Leather gloves, ER RM
Safety Shoe) VIS ER
Conduct TBT to all craftsmen involved in IO
the work activities. Full body
harness N
Compliance with GNFC safety
requirements to be ensured. Respirator
Only competent and licensed drivers to Dust
deliver material at site. coverall
3 1 3 C S
Driver to be made aware of
requirements and deliver to designated
area only.
Ensure all personnel are properly trained
and competent with appropriate PPE.
Ensure the equipment/trailer
Nature of the Job: Dismantling and erection of ammonia tank
Name of the Contractor: Projects & Development India limited
Name of the Safety Engineer: Mr. Tarik Vahora
Manual shifting
of Scaffold
Materials
Personnel injury 5 4 20 A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
and competent for rigging and tower Full body
crane operation. harness with
Ensure tower crane operator having 100% tie up of
valid license. lanyard
Tool Box Talks to be conducted before
starting the activity
Ensure tag line provided to avoid
oscillation.
Ensure tower crane inspected and
certified by the third party inspector.
Ensure no man movement underneath
the lifting area.
Ensure proper signal man provided for
the tower crane operator.
Ensure proper stacking of materials after
de-slinging
Proper supervision until the task
complete.
Provide proper PPEs for the workers.
Platform hand
rails Erection/
Dismantlin g
Fall of materials 5 5 25 A
Falling objects
Handling heavy
objects
Exposure to
chemicals
Personnel injury
Blinding & De Flammable gas
3
blinding
4 2 8 B
Toxic gas
Hit by objects.
Lifting work by
Vehicle accident.
using
Hydra/Cran e Failure of lifting
4 5 20 A
toppling tools & Tackle.
Trip / fall hazard
4 5 20 A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
is allowed for trailer driving.
Proper equipment should be
used to lift and shift the material.
Failure of lifting 5 4 20 A
tools.
5 3 15
Hit by object A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
lift plates.
One plate should be lifted at a time.
No plates should be lifted with forklifts.
Plates should not be pushed or pulled
from the trailer.
Area of lifting radius / material
movement should be barricaded
Loading and
Unloading of steel Hit to men or
5
plates using Hydra/ materials
5 5 25 A
Crane
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
handled directly.
Area of plate handling should be kept
barricaded to restrict the entry of
unwanted personnel.
Proper sign boards should be displayed.
No one should be allowed to work under
the suspended load.
5 5 25 A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
9.Provide proper tag line to avoid
oscillation.
Deploy trained signal man for proper
lifting
Ensure Sign boards should be provided.
Ensure hooks in the Sand Bucket should
be properly inspected before lifting
Ensure No man movement in the lifting
area
Ensure Proper supervision until the task
complete.
Ensure no person should work
underneath the Suspended load.
Barricade the Lifting area before starting
the work.
Hit by objects.
Vehicle accident.
Failure of lifting
tools & Tackle.
Trip / fall hazard
Lifting work by
using
Hydra/Cran e
5 5 25 A
toppling.
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
5.While loading the teeth of the VR hook
should be inserted fully in the
Avoid overloading.
Ensure Center of gravity should be stable
while loading and unloading.
Ensure proper supervision until the task
complete.
8. Provide proper PPEs for the work men
who work in the
activity.
Using Chain
block, Come
along, slings,
shackles
Defective or
damaged chain block, 4 3 12 A
Come along, slings,
shackles, wire rope
Failure of load
Unauthorized use of
forklift.
Forklift Unauthorized
Operations movement of forklift. 3 3 9 B
Speeding with
forklift.
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
Signal to the crane operator should be
given by rigger only and not by any
unauthorized person.
Required number of riggers should be
provided.
Electrocution 5 4 20 A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
line & vice versa.
Turn off cylinder valves when not in use.
Handle cylinders carefully and always
keep them in an upright position and
fasten them to prevent them from falling.
Drainage manhole near the location
must be cover by fire blanket.
Fire watcher must be at site while work
is in progress.
5 4 20 A
Fire 5 3 15 A
Crush injuries 5 4 20 A
Electrocution 5 4 20 A
Hot work
8 (welding, cutting Electrocution 5 5 25 A
,grinding)
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
crew to avoid communication gap. protective
clothing
Rolling machine should be placed at Basic PPEs
proper location. Full body
No one other than electrician should be harness
allowed to do the electrical maintenance Respirator
work for the machine.
Dust
Machine should be inspected on daily 1 1 1 C coverall S S P
basis and thoroughly on periodic basis for
identifying any
damages.
Fire 5 4 20 A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
conditions.
Machine should be inspected on daily
basis and thoroughly on periodic basis for
identifying any damages.
Cables should be protected from the
damages due to its exposure to sharp
edges.
Cables should be protected from hot
surfaces.
Plugs of welding machine should not be
inserted / removed from the sockets while
socket is live.
Naked electrical cable should not be
allowed.
Burn injuries 5 4 20 A
Damage to gas 5 5 25 A
cylinder & hoses
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
cables every day for identifying damages.
Electrical supply of welding machine
should be switched off
Fire extinguishers should be made
available at site and employees should be
trained to
use the same.
Fall of person 4 5 20 A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
cover before activating the foot
pedal/Hand lever.
Rods should be hold tightly while
cutting.
Provide proper PPEs for the work men
who work in the activity.
Adequate supervision until the task
completed.
4 5 20 A
Fall of person on
same level due to slip
& trip hazards
5 4 20 A
Lifting of roof
12 structure by Fall of lifted material 5 5 25 A
hydraulic jack due to failure of jacks
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
All area around the tank should be kept
barricaded while shell is being lifted &
proper warning
signs should be provided.
Hoses used for jacks should have proper
fittings & should sustain the required
pressure.
Spill kit should be made available &
employees should be trained to use the Basic PPEs
same. 2 2 4 C Spill kit S S P
Drip trays should be used while refilling PVC Suit
the oil.
Spilled oil must be cleaned off
immediately.
ND Testing – DP Exposure to
chemicals
13 Test, Radiography, 5 5 25 A
Vacuum Test Exposure to the
radiation
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
Spilled oil must be cleaned off
immediately.
Proper masks should be provided to
crew engaged in the DP test.
MSDS of chemicals used in the DP test
should be available and it should be
explained to the employees engaged in
the DP test.
Eye protection should be used to
prevent eye injuries.
Ensure radiography permit is obtained
Proper communication to be done to all
personnel working inside
Barricade and clear off all personnel in
the affected area. Basic PPEs
Ensure the standby man people at all the Eye
entry point to be effected area. 2 3 6 B protection
S S P
Confirm sign board is place at all entry Proper Mask
point.
Locate the flash light at prominent place.
Preferable time for the
Nature of the Job: Dismantling and erection of ammonia tank
Name of the Contractor: Projects & Development India limited
Name of the Safety Engineer: Mr. Tarik Vahora
Hazards associated 5 4 20 A
with radiography
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
radiography is break times and shift
change/over time.
No dye, chemicals should be sprayed on
the hot surfaces / open flames.
Cans of dye, chemicals used for DP
testing should be disposed at designated 1 3 3 C Basic PPEs S S P
locations & should
not be exposed to heat.
Painting work at
15 tank outer shell Fall of person from 5 5 25 A
(work at height) height
Exposure to paint 5 5 25 A
fumes
Fire, explosion 4 5 20 A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
Platform should be maintained uniform
& steps should be avoided.
Proper lighting arrangements should be
made at each
platform level of the scaffolding.
Injuries due to 5 4 20 A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
made available at site and
employees should be trained to use
the same.
Area of blasting should be isolated and
proper warning signs should be placed
around it.
All pressure hoses should be inspected
on daily basis before stating the job.
Whiplash arrestors should be used to
control the accidental movement of hoses
if unlocked from couplings.
To control the grits area around the
blasting should be isolated with GI sheets /
Tarpaulin.
Blaster should wear the required Basic PPEs
protective clothing.
B Full body S S P
Full body protective clothing is must for 3 2 6
protective
blaster. clothing
Moisture separator should be installed
on the air line supplying air to hood of the
blaster as moisture can restrict the vision
of blaster.
Only approved blaster should be
engaged in the job.
Noise exposure 5 4 20 A
Exposure to paint 5 4 20 A
fumes
Fire, explosion A
5 4 20
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
Automatic grit blasting machine should
be used to minimize the hazards of open
air grit blasting.
All employees engaged in the blasting
should be provided with ear plugs & its
use should be ensured.
Blasting activity should be carried out by Basic PPEs
scheduling it during particular intervals. 2 2 4 C Ear S S P
Compressors should be provided with Plug/Ear Muff
covers to reduce the noise and should be
checked on
regular basis.
Environmental
pollution due to paint
drums disposal &
grit disposal 5 4 20 A
Pressurized system
Bursting of hoses.
Personal injury
Torque
17
/tensioning
4 3 12 A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
Paint should be stored away from the
heat or sparks.
Empty pain drums should be disposed
properly & it should be disposed at
specified location.
Fire extinguishers should be made
available at site and employees should be
trained to
use the same.
Slip/trip/fall
Pinch hazards
Hydro Testing/
General Over pressurization
18 pneumatic test if requireme nts Personnel injury due
4 5 20 A
required.
to hose rupture.
Unauthorized entry
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
Secure the hoses with whiplash arrestor,
and remove the
defective hoses from location.
Valid work permit shall be obtained from
GNFC before start of work.
All employees/ workers should wear
necessary PPES.
Ensure proper housekeeping around the
area
Ensure TBT meeting before start of
work.
Inspect to all equipments before use at
site.
Barricade the work area.
Display related safety sign / caution
boards.
Use leather gloves 2 3 6 B Basic PPEs S/ P S P
Use calibrated and certified pressure
gauges only.
Use certified and pressure tested hoses
for hydro test.
Ensure the hose connected properly
with whip check and safety pin fixed.
Inform all adjacent groups prior to
starting pressure testing.
Ensure all hoses are arranged in
Nature of the Job: Dismantling and erection of ammonia tank
Name of the Contractor: Projects & Development India limited
Name of the Safety Engineer: Mr. Tarik Vahora
Releasing of
pressure Slip /trip/ fall
/ Dewatering of hazards
4 5 20 A
pipe
Blast of tank
Hand injury
Failure in identifying
blind(s) may leads to
process hindrance
Pressure testing &
19
Box up
5 4 20 A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
during testing period.
Display safety signage / caution boards.
Restrict others to not to enter into
pressure testing zone.
Ensure TBT for the crew.
Injuries due to
busting of pressure 4 5 20 A
lines
5 3 15 A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
pressure testing should be calibrated &
should be inspected prior to use at site at
the time of testing.
Continues monitoring is essential & test
area should not be left unattended.
The manifold should be fitted with
proper drains, vents, calibrated pressure
gauge & calibrated PSV to avoid the
blasting of tanks.
Obtain appropriate permit to work.
Use right and correct size of tools &
equipments for the job.
Wear hand gloves and other required
PPEs.
Supervise the de-blinding crew closely.
Entrapment of 3 5 15 A
person
Poor visibility A
4 4 16
Unavailability of first
aid facilities. 4 4 16 A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
depending on the type of material.
If the material to be suck is in solid form
it may generate dust like particles that will
be absorb by the body through inhalation.
Provide and used the appropriate PPE as
recommended by MSDS.
Ensure portable fire extinguishers fully
charged, sealed with inspection tags are
suitably placed,
Ensure that vacuum truck is not left
unattended whilst engine is
running.
Fatigue 4 3 12 A
Lack of amenities. 4 3 12 A
23 Housekeeping 4 3 12 A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
platform level of the scaffolding. 2 1 2
Ensure use of personal protective
equipments-Shoe- Helmet-Gloves. C S S P
Break needs to be taken at regular
intervals.
Full or alternative supervision
throughout the work. 3 1 3 C S S P
Emergency vehicles with driver should
be there through the work time.
Effective supervision will be made by
nominating designated decision making
person as in charge for night shift.
Drinking water, snacks and other
amenities will be available. 2 1 2 C S S P
RISK
CONTROL
No. ACTIVITIES
C L R
Layout of pilling Fall on the same
area and line level due to tripping
marking with chalk because of uneven
powder ground.
Dust entering eyes
and nose due to loose
soil & gusty winds
1 Skin irritation and 5 4 20 A
trip hazards.
RISK
USED
C L
Be cautious while walking on uneven Safety helmet,
ground surface. Safety Goggles,
Wear safety shoes for protection. Respirator
Removal of thorny plants, debris and Dust coverall,
other material if any before marking.
gloves,
Plan marking when the wind is low and
wear safety glasses and dust mask 3 1 3 C S S P
C Safety helmet,
Safety Goggles,
Before leveling clear the area. 2 1 2 Respirator S S P
Nature of the Job: Dismantling and erection of ammonia tank
Name of the Contractor: Projects & Development India limited
Name of the Safety Engineer: Mr. Tarik Vahora
ground, if any.
Area clearance
and identificati
on of buried
cables, utilities
and chemicals
etc.
4 Driving of piles Damage to 4 5 20 A
underground utilities
Binding of
steels using
binding wire
Pinching hazard 4 4 16 A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
Ensure the machine is inspected by EHS
dept before entering to site and color
coded.
Ensure safety guard provided for the
rotating parts of machine.
Ensure the second stopper for
protection against struck by swing arm in
case of failure of first stopper.
Ensure pinching will happen by using
multiple rods.
While operating the machine stand front
to the machine to hold the rod to avoid
hit.
Ensure emergency switch is in working
condition.
Provide proper PPEs for the work men
who work in the activity.
Adequate supervision until the task
completed.
Shifting Of
fixed rods to Fall of materials on
working area men/hit the men
4 4 16 A
manually
Electrical
10
Operation Electrocution 5 4 20 A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
before start of the activity. gloves,
Use proper gloves to avoid pinching of
wires.
Ensure workers are free from heat
stress.
Adequate supervision until the task
completed.
Mechanical failure.
Lack of supervision.
Striking against
objects.
Improper
barrication.
Unguarded rotating
parts.
Spillage of concrete.
12 Concreting. Skin rashes. 4 4 16 A
Electrocution A
13 Vibrator Health hazard 5 5 25
Skin diseases
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
Ensure Reinforced materials erected and
proper support should be given.
Ensure workers worn proper PPEs like
Safety harness.
Ensure Proper supervision until the task
complete.
Burn injury.
Breathing problem
due to inhalation of
smoke.
Chance of fire.
Explosion.
Personal injury.
May cause severe
Injuries or prove
fatal.
Bitumen Property Damage.
15
Heating
5 5 25 A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
Proper PPE’s like gumboot and rubber Goggles,
gloves to be used while curing. Respirator
No Electrical wires to be in place while Dust coverall,
curing. Gumboots
Rubber gloves
4 5 20
Fire A
Date: 02/12/2020 Project No: PC-00187
Job Location: GNFC -1003A Project Bharuch Site
Contract Project manager: Mr.
Stacking of LPG shall be placed
separately in up right direction.
In case a fire breaks out, press fire alarm Basic PPEs
system and shout "Fire, Fire" Safety Goggles,
Keep buckets full of sand / fire Respirator
extinguishing equipment near hazardous
Face shield
locations
Leather gloves
Train people for using specific type of
fire fighting equipment’s under different FRC
classes of fire Cloths
Keep fire doors/shutters, passages and
exit doors unobstructed.
Maintain good housekeeping and first-
aid boxes
Don't obstruct assess to Fire
3 3 9 B S S P
extinguishers.
Do not use elevators for evacuation
during fire.
Maintain lightening arrestors for
elevated structures
Stop all electrical motors with internal
combustion.
'3 day' injury or illness Major injury or illness Fatality, disabling injury,
etc.
L = LIKELIHOOD / SEVERITY
Action
able but review task to see if risk can be reduced further.
Emergency planning is an integral part of the overall loss control programme and is essential for our o
important for effective management of an accident to minimize the losses to the people and property,
facility. The important aspect in emergency management is to prevent by technical and organizational
unintentional escape of hazardous materials out of the facility and minimize accidents and losses.
demonstrates the organizational commitment to the safety of employees and increases our organ
awareness.
An emergency in the factory has potential to cause serious injuries or loss of live or extensive damage
environment and serious disruption both inside and / or outside the works. In such cases someti
are required to call for help in handling the situation. The causative factors like plant / equipment fail
earthquake, sabotage etc. will normally manifest in various forms viz. Fire, Explosion, Toxic and Stru
In spite of best design and layout of plant, safe operating procedures and various preventive measur
disaster cannot be totally ruled out. During this event timely and organized action must be taken to co
minimize the damage or loss to the factory, human beings and environment hence, the need of a pro
Emergency Plan (EPRP)”. Such plan gives the guidelines for employees, contractors, transporters
EPRP not only defines the responsibilities but also inform about prompt rescue / evacuation
/co-ordination operations and some more.
WHY INTRODUCTION OF EMERGENCY PLANNING IS REQUIRED?
After the incident of Bhopal gas disaster, the Factories Act has been amended and a
new chapter i.e. Chapter IVA – provision relating to hazardous processes has been added to the Facto
new provisions sec 41A, 41B, 41C, 41D, 41E, 41G & 41H covering all hazardous process industries.
Sec 41B (4) every occupier shall with the approval of the Chief Inspector of Factories draw
Emergency Plan and detailed disaster control measures for his factory and make known to the w
and to the general public living in the vicinity of the factory the safety measures required to be taken i
accident taking place. This is the statutory provision laid
down in the act for preparation of On-site Emergency Plan to control disaster in the factories. Major a
emergency and it may lead to disaster, which
may cause heavy damage to plant, property and harm to person and create adverse affects on produc
like Bhopal gas tragedy, Chernobyl nuclear disaster etc. have occurred at many places in the world
life and property. Emergency situation arises all on a sudden and creates havoc and damage to
production and environment. Therefore such situations and risks should be thought in advance an
before hand to tackle them immediately and control them within the shortest time.
OBJECTIVE
The main objective of On-site emergency management plan (On-SEMP) is in emergency mana
ensure that everyone knows:
What are the hazards and risk in the plant
What and how to do in the event of an emergency; and
Preparations for potential and unexpected incidents at the workplace.
The types of emergencies to plan for include fire, explosion, toxic releases, injuries and rescues in the
improves local, district, state and national capacity to respond to disasters and public health emer
actions with vulnerable communities in health promotion, disease prevention and disaster risk re
As per our Indian regulations we have regulatory provisions that On-site Emergency Management Pl
prepared by industrial units and Off-site Emergency Management Plan (Off SEMP) by District Co
An occupier will prepare and keep an up-to date on-site emergency plan containing details of Manuf
Import of Hazardous Chemicals (MS&IHC) Rules 1989 and detailing how major accidents will be
which the industrial activity is carried on and that plan will include the name of the person who is resp
site and the names of those who are authorized to take action in accordance with the plan in case of an
occupier will ensure that the emergency plan prepared takes into account any modification mad
and that every person on the site who is affected by the plan is informed of its relevant provisions.
ing is an integral part of the overall loss control programme and is essential for our organization. The same is
ective management of an accident to minimize the losses to the people and property, both in and around the
ortant aspect in emergency management is to prevent by technical and organizational measures, the
ape of hazardous materials out of the facility and minimize accidents and losses. Emergency planning
organizational commitment to the safety of employees and increases our organization’s safety
the factory has potential to cause serious injuries or loss of live or extensive damage to the property and / or
serious disruption both inside and / or outside the works. In such cases sometimes outside agencies
ll for help in handling the situation. The causative factors like plant / equipment failure, human error,
age etc. will normally manifest in various forms viz. Fire, Explosion, Toxic and Structure collapse etc.
esign and layout of plant, safe operating procedures and various preventive measures the possibility of a
e totally ruled out. During this event timely and organized action must be taken to control the situation and to
mage or loss to the factory, human beings and environment hence, the need of a proper “On–Site
(EPRP)”. Such plan gives the guidelines for employees, contractors, transporters and Visitors etc. The
efines the responsibilities but also inform about prompt rescue / evacuation
erations and some more.
DUCTION OF EMERGENCY PLANNING IS REQUIRED?
of Bhopal gas disaster, the Factories Act has been amended and a
Chapter IVA – provision relating to hazardous processes has been added to the Factories Act with addition of
ec 41A, 41B, 41C, 41D, 41E, 41G & 41H covering all hazardous process industries. Under the provision of
ery occupier shall with the approval of the Chief Inspector of Factories draw up an On-site
n and detailed disaster control measures for his factory and make known to the workers employed therein
l public living in the vicinity of the factory the safety measures required to be taken in the event of an
lace. This is the statutory provision laid
or preparation of On-site Emergency Plan to control disaster in the factories. Major accidents may cause
may lead to disaster, which
damage to plant, property and harm to person and create adverse affects on production. Many disasters
tragedy, Chernobyl nuclear disaster etc. have occurred at many places in the world causing heavy loss of
. Emergency situation arises all on a sudden and creates havoc and damage to person, property,
nvironment. Therefore such situations and risks should be thought in advance and it should be planned
ackle them immediately and control them within the shortest time.
rgencies to plan for include fire, explosion, toxic releases, injuries and rescues in the hazardous events. Plan
istrict, state and national capacity to respond to disasters and public health emergencies, scaling up the
nerable communities in health promotion, disease prevention and disaster risk reduction.
regulations we have regulatory provisions that On-site Emergency Management Plan (On-SEMP) will be
ustrial units and Off-site Emergency Management Plan (Off SEMP) by District Collector.
prepare and keep an up-to date on-site emergency plan containing details of Manufacture, Storage and
dous Chemicals (MS&IHC) Rules 1989 and detailing how major accidents will be dealt with on the site on
ial activity is carried on and that plan will include the name of the person who is responsible for safety on the
s of those who are authorized to take action in accordance with the plan in case of an emergency. The
sure that the emergency plan prepared takes into account any modification made in the industrial activity
rson on the site who is affected by the plan is informed of its relevant provisions.
WHAT IS EMERGENCY?
An emergency is a situation, which may lead to or cause a large-scale damage or destruction to life
environment within or outside the factory. Sometimes emergency results into uncontrollable situ
towards the disaster. Such an unexpected severe situation may be too great for the normal wor
the plant. In any industry emergency can arise at any moment and this depends on the type of Structur
Machines / Plant, Nearby Industries etc.
A major emergency can be defined as an accident/ incident that have potential to cause serious injur
may cause extensive damage of property, serious disruption both in production and working o
adversely affect the environment. The following factors may cause major emergency.
The emergency has been identified and can be specified in one or more of the
followings with source and effect:
Sr. Emergency Source
No
Electrical Panels, Flammable oil
storage tanks, Compressors, coolants,
paints, etc.
1 Fire / Explosion
Natural calamities
7 such as storm, earthquakes, Nature
etc.
8 Structure collapse Office building, & Any Wall or part Of
Factory building.
9 Riots, Arson, Sabotaging Anti Social elements.
premises, it is called as Off-site
Effect
Fracture
Suffocation
This is the main center from where the operations to handle the emergency are directed and co-ordina
SITE CONTROLLER is the person who assumes absolute control of the Factory and determines the a
control the Emergency. He / She will wear a Red & White Helmet to confirm his identity. The General
controller. Site controller will ensure that all members of his/her team have been informed to collect
centre. He / She will then proceed to Emergency Control Centre to take charge.
After firsthand assessment of situation he/she will give necessary instructions to Emergency Control T
maintain a Log book of all the activities. He/she will keep in touch with the external communicat
ensure that information is sent to outside emergency services (Police and Fire Brigade). He/she w
Attend to telephone
Keep in touch with incident controller
Communicate with Assembly Points
Meet outside emergency services
Ensure proper flow of traffic and security
Meet media/ other people coming at site from outside.
Arrange for Medical Aid
INCIDENT CONTROLLER is the person who goes to the scene of emergency and supervises the
incident to overcome the Emergency. Shift Manager will act as Incident Controller. His responsibiliti
Direct all efforts to contain and control the incident.
Keep non-essential persons away from the site.
Guide outside emergency services at the site.
Arrange to remove any casualties at the site.
Keep in touch with Emergency Controller.
SECURITY IN-CHARGE WILL
Actuate the Emergency Siren, if not done already.
Send one guard to start the fire pump.
Attend to incoming telephone.
Await instructions from the Emergency Controller
COMMUNICATION OFFICER
Public Relations Officer will act as Communication Officer. On hearing alarm He will proceed to Emer
Maintains communication with Incident Controller and Deputy Incident Controller
Recruits suitable staff to act as messengers if telephone and other communications fail
Organizes all requirement of Emergency Control Centre
Arranges Food, Transport, Nursing Home etc
PERSONNEL MANAGER
He/she will work as Liaison officer. He should be positioned in the office near gate.
Will deal with police, media and outside enquiries in consultation with Site Controller.
Will keep in touch with Union
Will arrange for refreshments if required
Will control traffic movement inside the factory and arrange for alternative transport if required
Will keep a record of attendance of workers, staff, contractor’s personnel, and visitors at the Gate w
Assembly Point.
SAFETY OFFICER
Will assist the Incident Controller with his special knowledge on the safety
aspects in the factory. He will help to identify the hazardous chemicals,
hazard zones and zone of probable impact in different accident scenarios
Will select people with special training in safety matters to assist in the control activities
FIRE & SECURITY OFFICER
His/her main task is fire fighting and control
Announce through PAS about the incident zone and any other immediate information needed for t
Maintains liaison with the Fire Brigade team from outside
MEDICAL OFFICER
Will immediately open a First Aid Centre at Control Centre or at Assembly Point
Will take up the full responsibility of providing medical assistance during emergency
Will arrange for outside medical help if required.
TELEPHONE OPERATOR
On hearing the emergency alarm, he/she will immediately contact Site Controller
On the advice of Site controller/Incident Controller/Security Officer will ring Fire brigade, Police
Keep telephone board free for urgent communications.
GENERAL EMPLOYEES
Who have not been specified a duty in case of emergency should proceed to/contact the Emerg
their area. Designated persons will carry out the actions detailed in the Individual Plant Emergency Pr
leader will hold a Roll call. Personnel not at their normal work place must go to the emergency
Personnel will remain at these points and await instructions from the Site Controller.
Essential Works and Team Leaders: During emergency the plants immediately affected o
determined by the Works Main Controller, need to be shut down for safety. In the area immediat
possible to isolate equipment from which flammable or toxic material is leaking. This work must be
by plant supervisors and essential operators.
Workers/ staffs need to be nominated to carry out the following essential works at the time of emerge
Extra first aid personnel to deal with casualties.
Emergency engineering works, provision of extra or replacement of light, isolation of equipm
electrical lines etc.
Moving tankers or other vehicles from area of risk.
To carry out tests on ambient air quality.
To act as runner in case of communication system fails.
The Works Main Controller will require a task force of suitable trained people for the following
i. Manning of assembly points to record the arrival of evacuated people.
ii. Assistance of casualty arrival areas to record details of casualties.
iii. Manning the factory entrance in liaison with security to direct emergency vehicle
e.g. ambulance, fire tenders etc.
For these essential jobs designated teams should be made available. The responsibilities
leader should be given. The essential work teams are-
1. Task Force and repair team.
2. Fire fighting team.
3. Communication team.
4. Security Team.
5. Transport Team.
6. First aid and medical team.
7. Safety team.
CONTRACTOR’S EMPLOYEES
Contractor's employees will be instructed in the Emergency Procedures before commencing work
report to the emergency assembly point on this site. Personnel Manager will guide them in case
evacuation from the factory is taken.
VISITORS
Infrequent visitors are registered on each visit. They will be given a Visitors pass which includes an em
statement. The responsibility for visitors in emergency situation rests with the person being visited.
RESPONSIBILITIES OUTSIDE GENERAL SHIFT HOURS SHIFT SUPERV
He/she will act as Site controller for the time being. As soon as becomes aware of the emergency and
proceed to the scene. He will assess the scale of the incident and direct operations within the affected
He/she will contact and inform the Site Controller and Incident Controller immediately. Till t
continue to perform their duties.
He/she will contact the departmental head to act as incident controller and guide
Safety Officer and Security Officers for containing the damage.
He/she will call the Medical Officer to the plant if necessary. Other staff with designated resp
instructed.
INFRASTRUCTURE:
FIRE FIGHTING FACILITIES:
The plant will have adequate fire fighting aids including fire hydrants close to the required locations.
Fire Extinguishers of different types and sizes are installed in specific places.
The factory siren will be used for raising the alarm and also for ALL CLEAR signal.
FIRST AID BOXES are provided in specific locations including at the Assembly point for administe
treatment. A number of employees are trained for first aid use.
EMERGENCY CONTROL CENTRE is the point from which the Site Controller directs the movem
Equipment during an Emergency.
The onsite emergency plan so prepared shall be documented in a printed form in sufficient cop
for knowledge, study and easy follow up. The emergency plan shall be rehearsed and practiced at
test efficiency of personnel, equipments co-ordinate efforts and to increase confidence and exper
plan
On-site emergency plan should contain -
1. Site plan and topographic plan.
2. Plan showing the fire fighting facilities.
3. Plan showing hazardous material storage area.
4. Material safety data sheets for hazardous chemicals.
5. Facilities available in main control center.
6. List of emergency equipment.
7. List of Safety Equipment.
8. Names and address & contact telephone number of Key Personnel
9. List of important telephone numbers and addresses.
i. Nearest hospitals and ambulance service center.
ii. Nearest fire station.
iii. Govt. Officials.
iv. Transport provider.
Fire protection and fire fighting facilities.
Emergency lighting and standby power.
Emergency equipment and rescue equipment –
i. Breathing apparatus with compressed air cylinder.
ii. Fire proximity suit.
iii. Resuscitator.
iv. Water gel Blanket.
v. Low temperature suit.
vi. First aid kit.
vii. Stretchers.
viii. Torches.
ix. Ladders.
Safety Equipment –
i. Respirators.
ii. Gum boots.
iii. Safety helmets.
iv. Asbestos Rubber hand gloves.
v. Goggles and face shield.
vi. Toxic gas measuring instruments.
vii. Explosive meter.
viii. Oxygen measuring instruments.
ix. Toxic gas measuring instrument.
x. Wind direction indicator.
EXTERNAL COMMUNICATION will be done by Site Controller. The following persons and
updated information as necessary and ask for necessary help.
SDO
Police
Fire Brigade
District Hospital
GPCB
Factory Inspector
Local Media
District Magistrate
Serious injury, Death
Serious injury, Death
Serious injury, Death
Serious injury, Death
Serious injury, Death
Poisoning, Death
Land Contamination
tory.
nufacturing records.
ter.
ne number etc.
es of industry, due to fire in a process area, tank form area, toxic
sels or piping network, or a bomb threat. The approach of the plan is to
hat may occur during an evacuation by undertaking following steps:-
ous situations;
regulations;
emergency;
is:
major accident
elevant components
ils about the site
dangerous substances.
of key personnel
ency control room
ardous chemicals at plant site:
tities and toxicological data)
if any, which could occur.
hazardous chemicals.
angers to the plant.
e effects of Accident
used during normal operation
and effect if any, of fire and explosion outside.
R ROLE FOR ONSITE EMERGENCY
and any other immediate information needed for the people nearby
m outside
stem fails.
k force of suitable trained people for the following works-
ival of evacuated people.
d details of casualties.
on with security to direct emergency vehicle containing the gate
ding fire hydrants close to the required locations. There will be Portable
e installed in specific places.
larm and also for ALL CLEAR signal.
ons including at the Assembly point for administering preliminary
rst aid use.
from which the Site Controller directs the movements of Personnel and
ups of employees.
ng.
ions.
ery).
nternal telephone and paging system, where people can wait in a
s from the Emergency Controller.
determined as assembly point
om the affected areas are to be assembled. The plant workers, contract
y point in case of emergency and the time office clerk should take
uring emergency.
ll depend on the size of the works area. Simple fire bell, hand
. Automatic alarm may be needed for highly hazardous nature of plant.
s a key component to control an emergency.
y should be different from the normal siren. The emergency siren should
emergency siren should be used only in case of emergency.
and every plant should be clearly marked. The escape route is the
area, which leads to assembly point. This route should be indicated
cy Plan.
vacuated from the emergency site. As soon as the emergency siren rings
o the assembly point. The plant shut down procedure in case of emergency
person should be nominated for the purpose.
king in the plant should be counted. Time office person should collect
point. These should be checked with the attendances of regular
day of emergency. The accident control should be informed and
ng person in the emergency affected area. The employees’ address,
ed in the time office so that during emergency relatives of those affected
n to the media and other agency.
y the Work Incident Controller will communicate to the works main
e main controller can declare all clear by instructing the time office to
n during an emergency.
erience gained.
conducted once in 6 months and sequence of events should be recorded
ite Emergency Planning should be monitored by Factory Inspectorate
an is reviewed every year.
ties should be provided in any factory to tackle any emergency at any
als.
of Key Personnel
es.
er.
er.
To carry out mock exercises and rehearsal of the off site plan to ensure its efficiency,
test and response, interaction and co-ordination of operators various service organizations
effectiveness and adequacy of the equipments and to gain experience and confidence to impleme
finalized disaster plan
shall be given to all concerned for implementation and rehearsal for preparedness.
ne Numbers
EXT.NO (INT)
ies:
e fighting facilities but during emergency, fire brigade may be
l for preparedness.
EMERGENCY RESPONSE DIAGRAM
Message to
Site Controller
Emergency
Works as Liaison
officer
Organizes all
requirements of
Emergency
Guides with
knowledge of
safety aspects
in the factory
Fire
Fighting
Deputy Incident controller will act as
assistant to Incident controller
Informs
Medical
Officer
Safety Security
Officer Officer
AMMONIA (NH3)
PURPOSE
The major use of ammonia is as a fertilizer. It can be applied directly to the soil or in the form of am
Ammonia is also used in the manufacture of commercial explosives (e.g., TNT, nitroglyce
In the textile industry, ammonia is used in the manufacture of synthetic fibers (e.g., nylon an
neutralizes acidic by-products of petroleum refining, and in the rubber industry it prevents the coagula
transportation from plantation to factory. Ammonia is used in various metallurgical processes, includi
sheets to harden their surfaces. Because ammonia can be decomposed easily to yield hydrogen
portable source of atomic hydrogen for welding. In addition, ammonia can absorb substantial am
its surroundings (i.e., one gram of ammonia absorbs 327 calories of heat), which makes it useful as a c
and air-conditioning equipment. Ammonia used commercially is often called anhydrous ammonia. Ho
solution of anhydrous ammonia (NH3) and water.
PHYSICAL & CHEMICAL PROPERTIES / DEFINITION OF CHEMICAL GROU
CAS: 7664-41-7
Class: Toxic, Compressed gas, Corrosive
Molecular Formula: NH3
Form (physical state): gas
Color: Colorless
Boiling Point: -33 °C
POTENTIAL HAZARDS / TOXICITY
Potential Health Effects
Target Organs: Lungs, Central nervous system, Liver, Kidney
Inhalation: May be harmful if inhaled. Material is extremely destructive to the tissue of the
mucous membranes and upper respiratory tract.
Skin: May be harmful if absorbed through skin. Causes skin burns.
Eyes: Causes eye burns.
Ingestion: May be harmful if swallowed.
PERSONAL PROTECTIVE EQUIPMENT (PPE)
RESPIRATORY PROTECTION: Use a full-face particle respirator with type N100 (US) respirator
Respirators should be used only under any of the following circumstances:
As a last line of defense (i.e., after engineering and administrative controls have been exhausted).
When Permissible Exposure Limit (PEL) has exceeded or when there is a possibility that PEL will
Regulations require the use of a respirator.
An employer requires the use of a respirator.
There is potential for harmful exposure due to an atmospheric contaminant (in the absence of PEL
As PPE in the event of a chemical spill clean-up process
HAND PROTECTION: Gloves must be worn. Use proper glove removal technique to avoid any skin
Neoprene gloves are recommended.
NOTE: Consult with your preferred glove manufacturer to ensure that the gloves you plan on usin
Ammonia.
EYE PROTECTION: Wear chemical splash goggles or a face shield to protect from splash hazards a
SKIN & BODY PROTECTION:
Flame resistant lab coat
Full-length pants
Closed-toe rubber or leather shoes
HYGIENE MEASURES: Avoid contact with skin, eyes, and clothing. Wash hands before breaks an
handling the product.
ENGINEERING CONTROLS: Handle using a chemical fume hood with good ventilation and electr
and equipment.
FIRST AID PROCEDURES
If inhaled…Move to fresh air and give oxygen. If the person is not breathing, give artificial respiratio
mouth contact.
In case of skin contact…Remove all contaminated clothing. Immediately (within seconds) flush a
FIFTEEN (15) minutes.
In case of eye contact…Remove any contact lenses. Use nearest emergency
eyewash immediately for at least 15 minutes. Continue eye rinse during transport to the hospita
If swallowed…DO NOT INDUCE VOMITING. Never give anything by mouth to an unconscious p
SPECIAL STORAGE & HANDLING REQUIREMENTS
STORAGE
Ensure the container is tightly closed at all times.
Keep in a dry, cool, and well-ventilated area.
Keep away from incompatible materials and conditions.
Keep cool and protect from sunlight.
HANDLING
The lab where the material is being handled has an approved / certified emergency eyewash and sa
Ensure you are wearing the following minimum PPE: tightly fitting safety goggles and fac
resistant lab coat, full length pants, close-toe rubber or leather shoes, gloves constructed with nitrile
Lab emergency contact information must be readily posted. Easy access to a cellular phone o
available.
Avoid inhalation and contact with skin and eyes.
Avoid inhalation of vapor or mist.
Avoid formation of dust.
SPILL AND ACCIDENT PROCEDURE
PERSONAL PRECAUTIONS: Avoid breathing vapors, mist or gas. Ensure adequate ve
personnel to safe areas. Do not attempt clean-up without minimum PPE. Beware of vapors
form explosive concentrations. Vapors can accumulate in low areas.
ENVIRONMENTAL PRECAUTIONS: Prevent further leakage or spillage – if safe to do so. Do n
enter drains. Discharge into environment must be avoided.
METHODS AND MATERIALS FOR CONTAINMENT AND CLEAN-UP: Consider
material compatibility prior to clean-up. Verify spill kit is available. Contain spillage and the coll
protected vacuum cleaner or by wet-brushing and place in container for disposal according to regulati
Immediately assess amount spilled, follow posted Emergency Response Guide procedu
materials incidents.
If a chemical exposure has occurred, a fellow worker shall call Emergency number and E
Don compatible gloves and other protective PPE if not already being worn.
Secure / restrict access to the area of the spill to prevent spread of the chemical.
Use the available spill kit to stop and contain the spill. Bag the collected materi
Label and tag as hazardous waste and submit a pick-up request to EH&S using EHS As
People working within the influence zone will be educated on the emergency in a
suitable manner. This can be achieved only through the Local and District Authorities. However, neces
extended to the Authority.
*******
STANDARD OPERATING PROCEDURE (EHS
PROJECT
(NH3)
s skin burns.
PPE)
cle respirator with type N100 (US) respirator cartridges.
ng circumstances:
dministrative controls have been exhausted).
ed or when there is a possibility that PEL will be exceeded.
urer to ensure that the gloves you plan on using are compatible with
ns.
L PROCEDURE
e tag to all waste containers as soon as the first drop of waste is added
n 90 days.
equest system.
***
G PROCEDURE (EHS)
ECT
PROJECT MANAGEMENT CONSULTANCY SERVICES F
REPLACEMENT OF SINGLE WALL AMMONIA STORAGE TANK B
WALL STORAGE TANK AT
GNFC AMMONIA PLANT, BHARUCH
OWNER
CONTENT
CY SERVICES FOR
ORAGE TANK BY DOUBLE
AT
ARUCH
RS & CHEMICALS
A
TANT
A LIMITED
PURA, VADODARA
1 .0
2 .0
3 .0
3.1
3.1 .1
3.1 .2
3.1 .3
3.1 .4
3.1 .5
3.1 .6
3.1 .7
3.1 .8
3.1 .9
3.1 .10
3.1 .11
3.1 .12
3.1 .13
3.1 .14
3.2
3.3
3 .3 .1
3 .3 .2
3 .3 .3
3 .3 .4
3 .3 .5
3 .3 .6
3 .3 .7
3. 3 .8
3.3 .9
3.3.2010
3.3.2011
3.3.2012
3.3.2013
3.3.2014
3.3.2015
3.3.2016
3.3.2017
3.3.2018
3.3.2019
TITLE PAGE
NO.
Scope 6
References 6
Requirement of Health, Safety and Environment (HSE) 7
Management System to be complied by Bidders
Management Responsibility 7
HSE Policy & Objective 7
Management System 7
Indemnification 7
Deployment & Qualification of Safety Personnel 7
Implementation, Inspection & Monitoring 10
Behavior Based Safety 12
Awareness & Motivation 14
Fire prevention & First-Aid 14
Documentation 15
Audit 15
Meetings 16
Intoxicating drinks & drugs and smoking 17
Penalty 18
Accident/Incident investigation 21
House Keeping 22
HSE Measures 23
Construction Hazards 23
Accessibility 25
Personal Protective Equipments (PPEs) 26
Working at height 27
Scaffoldings & Barricading 29
Electrical installations 30
Welding/Gas cutting 34
Ergonomics and tools & tackles 35
Occupational Health 36
Hazardous substances 37
Slips, trips & falls 38
Radiation exposure 38
Explosives/Blasting operations 39
Demolition/Dismantling 39
Road Safety 40
Welfare measures 41
Environment Protection 42
Rules & Regulations 42
Weather Protection 43
3.3.2020
3.3.2021
3.3.2022
3.3.2023
3.3.2024
3.3.2025
3.3.2026
3 .4
3 .5
3 .6
3 .7
3 .8
3 .9
4 .0
4 .1
4 .2
4 .3
APPENDICES
1. Standards/Codes on HSE Appendix-A
2. Details of First AID Box Appendix-B
3. Types of Fire Extinguishers & their Appln. Appendix-C
4. Indicative List of statutory Acts & Rules Appendix-D
5. Training subjects / topics Appendix-E
6. List of HSE procedures Appendix-F
ABREVATIONS
AERB : Atomic Energy Regulatory Board
ANSI : American National Standards Institute BARC : Bhabha Atomic Resea
BS : British Standard
PDIL : Projects & development India Limited ELCB : Earth Leakage Circuit
EPC : Engineering, Procurement and Construction
EPCC : Engineering, Procurement, Construction and Commissioning ESI :
Insurance
GCC : General Conditions of Contract GM : General Manager
GTAW : Gas Tungsten Arc Welding HOD : Head of Department
HSE : Health, Safety & Environment
HV : High Voltage
IS : Indian Standard
IE : Indian Electricity
JSA : Job Safety Analysis
LOTO : Lock Out & Tag Out
LPG : Liquefied Petroleum Gas
LSTK : Lump Sum Turn Key
MV : Medium Voltage
PPE : Personal Protective Equipment
RCM : Resident Construction Manager or Site-in-Charge, as applicable ROW :
SCC : Special Conditions of Contract
SLI : Safe Load Indicator
TBM : Tool Box Talks/Meeting
1.0 SCOPE
This specification establishes the Health, Safety and Environment (HSE) management
complied by Contractors/Vendors including their sub-contractors/sub vendors during work.
This specification is not intended to replace the necessary professional judgment needed to design
effective HSE system for construction activities and the contractor is expected to fulfill HSE requ
specification as a minimum. It is expected that contractor shall implement best HSE practi
mentioned in this specification.
Requirements stipulated in this specification shall supplement the requirements of HSE Managem
Act(s)/legislations, General Conditions of Contract (GCC), Special Conditions of Contract (S
(Technical) Specifications. Where different documents stipulate different requirements, the
most stringent shall apply.
REFERENCES
The document should be read in conjunction with following:
- General Conditions of Contract (GCC)
- Special Conditions of Contract (SCC)
- Building and other construction workers Act,
- Indian Factories Act
- Job (Technical) specifications
- Relevant International / National Codes
- Relevant State & National Statutory requirements.
- Operating Manuals Recommendation of Manufacturer of various construction M
3 .1.3 Indemnification
Contractor shall indemnify & hold harmless, Owner /PDIL & their representatives, free from any
out of non-fulfillment of HSE requirements
or its consequences.
A) Safety Steward
For every 250 workmen, one safety steward shall be deployed. As a minimum, he shall preferabl
Certificate (of Class XII with Physics & Chemistry etc.) and trained in fire-fighting as well
safety/occupational health related subjects, with minimum two year of practical experience
environment and preferably have adequate knowledge of the
language spoken by majority of the workers at the construction site.
B) Safety Supervisor
For every 500 workmen, one safety Supervisor shall be deployed. As a minimum, he shall posses
in Science (with Physics & Chemistry) or a diploma in Engineering or Technology with min
practical experience in construction work environment and should possess requisite skills
to deal with construction safety & fire related day-to-day issues.
D) HSE In-Charge
In case there is more than one Safety Officer at any project construction site, one of them, who
experience (in HSE discipline), may be designated as HSE In-Charge. Duties & responsibil
be commensurate with that of relevant statute and primarily to coordinate with top management
contractors. In case the statutory requirements i.e. State or Central Acts and / or Rules as
Building and Other Construction Workers’ Regulation of Employment and Conditions of S
State Rules (wherever notified), the Factories Act, 1948 or Rules (wherever notified), etc.
than above clarifications, the same shall be followed.
Contractors shall ensure physical availability of safety personnel at the place of
specific work location, where Hot Work Permit is required / granted. No work
shall be started at any of the project sites until above safety personnel & concerned Site
are physically deployed at site. The Contractor shall submit a HSE organogram clearly
of responsibility and reporting system and elaborate the responsibilities of safety personnel
The Contractor shall verify & authenticate credentials of such safety personnel and furnish
Curriculum Vitae of the safety personnel as above for PDIL/Owner’s approval, at least 1 mon
mobilization. The Contractor, whenever required, shall arrange submission of origin
testimonials/certificates of their Safety personnel, to PDIL /Owner (for verification
/scrutiny, etc.) Imposition / Realization of penalty shall not absolve the Contractor from his/her re
deploying competent safety officer at site. Adequate planning and deployment of safety personne
Contractor so that field activities do not get affected because of non-deployment of
competent & qualified safety people in appropriate numbers.
Contractor shall furnish their annual Inspection Plan, with regard to project issues /subj
performers to PDIL /Owner.
The Contractor shall regularly review inspection report internally and implement al
for improving the status continuously.
The Contractor shall ensure important safety checks right from beginning of works at every w
this effect “Daily Safety Check List” shall be prepared by field engineer & duly checked by
conformance.
The Contractor shall carry out inspection to identify various unsafe conditions of work sites/
as well as unsafe acts on the part of workmen/supervisor /engineer while carrying out dif
works.
Adequate records for all inspections shall be maintained by the Contractor and the same
PDIL /Owner, whenever sought.
The Contractor shall not carry-out work by engaging single worker anywhere without any sup
day or night.
To demonstrate involvement/commitment of site management of Contractor, at least one Sa
a month shall be carried out by Contractor’s head of site (along with his area manager/field en
shall be furnished to PDIL/Owner “Safety walk through report” followed by compliance for unsa
As a general practice lifting tools/tackles, machinery, accessories etc. shall be inspected, test
competent people (approved by concerned State authorities) before being used at site and als
(e.g. during replacement, extension, modification, elongation / reduction of machine / p
relevant statutes. Hydra, cranes, lifting machinery, mobile equipments / machinery / vehicl
inspected regularly by only competent / experienced personnel at site and requisite records
shall be maintained by every contractor.
Contractor shall also maintain records of maintenance of all other site
machinery (e.g. generators, rectifiers, compressors, cutters, etc.) & portable tools /equipments
related works (e.g. drills, abrasive wheels, punches, chisels, spanners, etc.). The Contractor sha
arbitrarily fabricated ‘derricks’ at project site for lifting / lowering of construction material
Site facilities /temporary installations, e.g. batching plant, cement go down, DG-room, t
panels/distribution boards, shot-blasting booth, fabrication yards, etc. and site welfare fac
colonies, canteen/pantry, rest-shelters, motorcycle/bicycle-shed, site washing facilities, First-aid
etc. should be periodically inspected by Contractor (preferably utilizing HR /Admin person
welfare
facilities) and records to be maintained.
Contractor through its own HSE committee shall implement the above
process.
The necessary procedures and reporting formats shall be developed by the contractor for ap
/Owner.
The HSE committee of contractor shall observe individual’s behavior for safe practices adap
/execution of work for following as a minimum:-
- PPE
- Tools & equipment
- Hazard Identification & control
- House keeping
- Confined space entry
- Hot works
- Excavation
- Loading & unloading
- Work at height
- Stacking & storage
- Ergonomics
- Procedures
Regular awareness programs and fabrication shop / work site meetings at least on mo
arranged on HSE activities to cover hazards/risks involved in various operations during con
Contractor to motivate & encourage the workmen & supervisory staff by issuing / awar
gifts/ mementos/ monetary incentives / certificates, etc.
Contractor shall assess & recognize the behavioral change of its site engineers / su
and constantly motivate / encourage them
to implement HSE practices at project works.
3 .1.9 Documentation
The Contractor shall evolve a comprehensive, planned and documented system
covering the following as a minimum for implementation and monitoring of the HSE requi
shall be submitted for approval by Owner/PDIL.
- HSE Organogram
- Site specific HSE Plan
- Safety Procedures, forms and Checklist.
- Inspections and Test Plan
- Risk Assessment & Job Safety Analysis for critical works.
The monitoring for implementation shall be done by regular inspections and compliance o
thereof. The Contractor shall get similar HSE requirements implemented at his sub-contrac
However, compliance of HSE requirements shall be the responsibility of the Contractor. A
PDIL /Owner shall not absolve contractor of his
responsibility /liability in relation to fulfilling all HSE requirements.
3 .1.10 Audit
The Contractor shall submit an Audit Plan to PDIL/Owner indicating the type of audits and cover
minimum:
Internal HSE audits regularly at least on quarterly basis by engaging internal qualified auditor
/Construction personnel having 5 years experience in construction safety and Lead Auditor C
certification).
External HSE audits regularly at least on every six months by engaging qualified exte
safety officers/Construction personnel having 10 years experience in construction safety and Le
Course :OSHA 18001 certification). All HSE shortfalls/non-conformances on HSE matters
brought out during review /audit shall be resolved forthwith (generally within a
week) by Contractor & compliance report shall be submitted to PDIL /Owner. In addition to
contractor, the contractor’s work shall be subjected to HSE audit by PDIL /Owner at a
during the pendency of contract. The Contractor shall take all actions required to comply with
Audit Report and issue regular Compliance Reports for the same to Owner /PDIL till all the
Report are fully complied. Failure to carry-out HSE Audits & its compliance (internal &
external) by Contractor, shall invite penalization.
3 .1.11 Meetings
The Contractor shall ensure participation of his top most executive at site (viz. Resident Cons
Resident Engineer / Project Manager / Site- in-Charge) in Safety Committee/ HSE Committee
PDIL/Owner usually on monthly basis or as and when called for. In case Contractor’s top
site is not in a position to attend such meeting, he shall inform PDIL/Owner in writing befor
such meeting indicating reasons of his absence and nominate his representative – failu
very stringent penalization against the specific Contractor, as deemed fit in Contract. T
compliance of any observations during the meeting shall be always time bound. The Contra
PDIL/Owner to achieve the targets set by them on HSE management during the project implemen
In addition, the Contractor shall also arrange internal HSE meetings chaired by his top most e
weekly basis and maintain records. Such internal HSE meetings shall essentially be attended
supervisors (& not by safety personnel only) of the Contractor and its associates. Records
meetings shall be maintained by
the Contractor for review by PDIL/Owner or for any HSE Audits.
COPE
This specification establishes the Health, Safety and Environment (HSE) management requirement to be
complied by Contractors/Vendors including their sub-contractors/sub vendors during work.
This specification is not intended to replace the necessary professional judgment needed to design & implement an
effective HSE system for construction activities and the contractor is expected to fulfill HSE requirements in this
specification as a minimum. It is expected that contractor shall implement best HSE practices beyond whatever are
mentioned in this specification.
Requirements stipulated in this specification shall supplement the requirements of HSE Management given in relevant
Act(s)/legislations, General Conditions of Contract (GCC), Special Conditions of Contract (SCC) and Job
(Technical) Specifications. Where different documents stipulate different requirements, the
most stringent shall apply.
REFERENCES
The document should be read in conjunction with following:
- General Conditions of Contract (GCC)
- Special Conditions of Contract (SCC)
- Building and other construction workers Act,
- Indian Factories Act
- Job (Technical) specifications
- Relevant International / National Codes
- Relevant State & National Statutory requirements.
- Operating Manuals Recommendation of Manufacturer of various construction Machineries
3 .1.3 Indemnification
Contractor shall indemnify & hold harmless, Owner /PDIL & their representatives, free from any and all liabilities arising
out of non-fulfillment of HSE requirements
or its consequences.
A) Safety Steward
For every 250 workmen, one safety steward shall be deployed. As a minimum, he shall preferably possess School leaving
Certificate (of Class XII with Physics & Chemistry etc.) and trained in fire-fighting as well as in
safety/occupational health related subjects, with minimum two year of practical experience in construction work
environment and preferably have adequate knowledge of the
language spoken by majority of the workers at the construction site.
B) Safety Supervisor
For every 500 workmen, one safety Supervisor shall be deployed. As a minimum, he shall possess a recognized Degree
in Science (with Physics & Chemistry) or a diploma in Engineering or Technology with minimum Two years of
practical experience in construction work environment and should possess requisite skills
to deal with construction safety & fire related day-to-day issues.
D) HSE In-Charge
In case there is more than one Safety Officer at any project construction site, one of them, who is senior most by
experience (in HSE discipline), may be designated as HSE In-Charge. Duties & responsibilities of such person shall
be commensurate with that of relevant statute and primarily to coordinate with top management of Client and
contractors. In case the statutory requirements i.e. State or Central Acts and / or Rules as applicable like the
Building and Other Construction Workers’ Regulation of Employment and Conditions of Service- Act,1996 or
State Rules (wherever notified), the Factories Act, 1948 or Rules (wherever notified), etc. are more stringent
than above clarifications, the same shall be followed.
Contractors shall ensure physical availability of safety personnel at the place of
specific work location, where Hot Work Permit is required / granted. No work
shall be started at any of the project sites until above safety personnel & concerned Site Engineer of Contractor
are physically deployed at site. The Contractor shall submit a HSE organogram clearly indicating the lines
of responsibility and reporting system and elaborate the responsibilities of safety personnel in their HSE Plan.
The Contractor shall verify & authenticate credentials of such safety personnel and furnish Bio-Data/ Resume/
Curriculum Vitae of the safety personnel as above for PDIL/Owner’s approval, at least 1 month before the
mobilization. The Contractor, whenever required, shall arrange submission of original
testimonials/certificates of their Safety personnel, to PDIL /Owner (for verification
/scrutiny, etc.) Imposition / Realization of penalty shall not absolve the Contractor from his/her responsibility of
deploying competent safety officer at site. Adequate planning and deployment of safety personnel shall be ensured by the
Contractor so that field activities do not get affected because of non-deployment of
competent & qualified safety people in appropriate numbers.
Contractor shall furnish their annual Inspection Plan, with regard to project issues /subjects, frequency and
performers to PDIL /Owner.
The Contractor shall regularly review inspection report internally and implement all practical steps / actions
for improving the status continuously.
The Contractor shall ensure important safety checks right from beginning of works at every work site locations and to
this effect “Daily Safety Check List” shall be prepared by field engineer & duly checked by safety personnel for
conformance.
The Contractor shall carry out inspection to identify various unsafe conditions of work sites/machinery/equipments
as well as unsafe acts on the part of workmen/supervisor /engineer while carrying out different project related
works.
Adequate records for all inspections shall be maintained by the Contractor and the same shall be furnished to
PDIL /Owner, whenever sought.
The Contractor shall not carry-out work by engaging single worker anywhere without any supervisor anytime during
day or night.
To demonstrate involvement/commitment of site management of Contractor, at least one Safety Walk through in
a month shall be carried out by Contractor’s head of site (along with his area manager/field engineers) and a report
shall be furnished to PDIL/Owner “Safety walk through report” followed by compliance for unsatisfactory remarks.
As a general practice lifting tools/tackles, machinery, accessories etc. shall be inspected, tested and examined by
competent people (approved by concerned State authorities) before being used at site and also at periodical interval
(e.g. during replacement, extension, modification, elongation / reduction of machine / parts, etc.) as per
relevant statutes. Hydra, cranes, lifting machinery, mobile equipments / machinery / vehicles, etc. shall be
inspected regularly by only competent / experienced personnel at site and requisite records for such inspections
shall be maintained by every contractor.
Contractor shall also maintain records of maintenance of all other site
machinery (e.g. generators, rectifiers, compressors, cutters, etc.) & portable tools /equipments being used at project
related works (e.g. drills, abrasive wheels, punches, chisels, spanners, etc.). The Contractor shall not make use of
arbitrarily fabricated ‘derricks’ at project site for lifting / lowering of construction materials.
Site facilities /temporary installations, e.g. batching plant, cement go down, DG-room, temporary electrical
panels/distribution boards, shot-blasting booth, fabrication yards, etc. and site welfare facilities, like labour
colonies, canteen/pantry, rest-shelters, motorcycle/bicycle-shed, site washing facilities, First-aid centers, urinals/toilets,
etc. should be periodically inspected by Contractor (preferably utilizing HR /Admin personnel to inspect site
welfare
facilities) and records to be maintained.
Contractor through its own HSE committee shall implement the above
process.
The necessary procedures and reporting formats shall be developed by the contractor for approval by PDIL
/Owner.
The HSE committee of contractor shall observe individual’s behavior for safe practices adapted for utilization
/execution of work for following as a minimum:-
- PPE
- Tools & equipment
- Hazard Identification & control
- House keeping
- Confined space entry
- Hot works
- Excavation
- Loading & unloading
- Work at height
- Stacking & storage
- Ergonomics
- Procedures
Regular awareness programs and fabrication shop / work site meetings at least on monthly basis shall be
arranged on HSE activities to cover hazards/risks involved in various operations during construction.
Contractor to motivate & encourage the workmen & supervisory staff by issuing / awarding them with tokens/
gifts/ mementos/ monetary incentives / certificates, etc.
Contractor shall assess & recognize the behavioral change of its site engineers / supervisors periodically
and constantly motivate / encourage them
to implement HSE practices at project works.
3 .1.9 Documentation
The Contractor shall evolve a comprehensive, planned and documented system
covering the following as a minimum for implementation and monitoring of the HSE requirements and the same
shall be submitted for approval by Owner/PDIL.
- HSE Organogram
- Site specific HSE Plan
- Safety Procedures, forms and Checklist.
- Inspections and Test Plan
- Risk Assessment & Job Safety Analysis for critical works.
The monitoring for implementation shall be done by regular inspections and compliance of the observations
thereof. The Contractor shall get similar HSE requirements implemented at his sub-contractors work site /office.
However, compliance of HSE requirements shall be the responsibility of the Contractor. Any review/approval by
PDIL /Owner shall not absolve contractor of his
responsibility /liability in relation to fulfilling all HSE requirements.
3 .1.10 Audit
The Contractor shall submit an Audit Plan to PDIL/Owner indicating the type of audits and covering following as
minimum:
Internal HSE audits regularly at least on quarterly basis by engaging internal qualified auditors (viz safety officers
/Construction personnel having 5 years experience in construction safety and Lead Auditor Course :OSHA 18001
certification).
External HSE audits regularly at least on every six months by engaging qualified external auditors (viz
safety officers/Construction personnel having 10 years experience in construction safety and Lead Auditor
Course :OSHA 18001 certification). All HSE shortfalls/non-conformances on HSE matters
brought out during review /audit shall be resolved forthwith (generally within a
week) by Contractor & compliance report shall be submitted to PDIL /Owner. In addition to above audits by
contractor, the contractor’s work shall be subjected to HSE audit by PDIL /Owner at any point of time
during the pendency of contract. The Contractor shall take all actions required to comply with the findings of the
Audit Report and issue regular Compliance Reports for the same to Owner /PDIL till all the findings of the Audit
Report are fully complied. Failure to carry-out HSE Audits & its compliance (internal &
external) by Contractor, shall invite penalization.
3 .1.11 Meetings
The Contractor shall ensure participation of his top most executive at site (viz. Resident Construction Manager /
Resident Engineer / Project Manager / Site- in-Charge) in Safety Committee/ HSE Committee meetings arranged by
PDIL/Owner usually on monthly basis or as and when called for. In case Contractor’s top most executive at
site is not in a position to attend such meeting, he shall inform PDIL/Owner in writing before the commencement of
such meeting indicating reasons of his absence and nominate his representative – failure to do so may invite
very stringent penalization against the specific Contractor, as deemed fit in Contract. The obligation of
compliance of any observations during the meeting shall be always time bound. The Contractor shall always assist
PDIL/Owner to achieve the targets set by them on HSE management during the project implementation.
In addition, the Contractor shall also arrange internal HSE meetings chaired by his top most executive at site on
weekly basis and maintain records. Such internal HSE meetings shall essentially be attended by field engineers /
supervisors (& not by safety personnel only) of the Contractor and its associates. Records of such internal HSE
meetings shall be maintained by
the Contractor for review by PDIL/Owner or for any HSE Audits.
ge Circuit Breaker
: Employee State
: Right of Way
agement requirement to be
ork.
d to design & implement an
HSE requirements in this
SE practices beyond whatever are
struction Machineries
nstruction Safety.
kers at the construction site.
gree or diploma in Industrial
Education of any Indian State)
s Safety Officer, in line with
red as Safety Officer, in case
em, who is senior most by
sponsibilities of such person shall
agement of Client and
Rules as applicable like the
ions of Service- Act,1996 or
ed), etc. are more stringent
his/her responsibility of
personnel shall be ensured by the
of
monitoring all HSE requirements
re that the HSE requirements
ls at site.
neers/supervisors, during the
ation activities. Physical
spot during the course of work
ork sites/machinery/equipments
g out different project related
ces as appropriate.
ctor for approval by PDIL
and
l.
asual) shall not be in a state of
& possession of intoxicating
No-Smoking” requirements of
or appliances as well as
nt
3 .1.13 Penalty
The Contractor shall adhere consistently to all provisions of HSE requirements. In case of non c
repeated failure in implementation of any of the HSE provisions, PDIL /Owner may impose stopp
cost & time implication to the Owner and/or impose a suitable penalty.
The amount of penalty to be levied against defaulted Contractor shall be up to a cumulative limit
of the contract value for Item Rate,
0 .5 % (Zero decimal five percent) of the contract value for LSTK, EPC, EPCC This penalty shal
other penalties specified elsewhere in the contract. The decision of imposing stop-work-ins
imposition of penalty shall rest with PDIL /Owner. The same shall be binding on
Imposition of penalty does not make the Contractor eligible to
continue the work in unsafe manner.
The amount of penalty applicable for the Contractor on different types of HSE
violations is specified below:
Sr. Violation of HSE norms
No.
For not using personal protective equipment (Helmet, Shoes,
1 Goggles, Gloves, Full body harness, Face shield, Boiler suit, etc.)
26 Poor Housekeeping
The Contractor shall make his field engineers/supervisors fully aware of the fact
that they keep track with the site workmen for their behavior and compliance of
various HSE requirements. Safety lapses /defects of project construction site shall be attribu
job supervisor /engineer of the Contractor, (who remains directly responsible for safely executing
repeated HSE violations, concerned job supervisor /engineer shall be reprimanded or appro
fit, shall be initiated (with information to PDIL & Owner) by the concerned Contractor.
Contractor shall initiate levy of mentioned cash fine and verbal warning shall be given to the w
his first HSE violation. A written warning shall be issued on second violation & Fine will
training shall be arranged / provided by the Contractor to enhance HSE awareness/skill including
mistakes/ flaws. Any further violation of HSE stipulations by the erring individuals sh
forthright debar from the specific construction site and fine will be 10 times higher. A record of
worker / employee shall be maintained by the Contractor, like by punching their cards / Ga
displaying their names at the Project entry gate. Warnings, penalizations, appreciations etc. shall
Committee meetings by site Head of the Contractor.
independently investigate such occurrences and the Contractor shall extend all necessary help an
regard. PDIL/Owner shall have the right
to share the content of this report with the outside world.
3. 2 House Keeping
The Contractor shall ensure that a high degree of housekeeping is maintained and shall ensu
All surplus earth and debris are removed /disposed off from the working areas to designated l
Unused /surplus cables, steel items and steel scrap lying scattered at different places wi
are removed to identify locations.
All wooden scrap, empty wooden cable drums and other combustible packing materials, shall
place to identified locations.
Roads shall be kept clear and materials like pipes, steel, sand, boulders, concrete, chips
be allowed on the roads to obstruct free movement of men & machineries.
Fabricated steel structural, pipes & piping materials shall be stacked properly for erection.
Water logging on roads shall not be allowed.
No parking of trucks /trolleys, cranes and trailers etc shall be allowed on roads, which
movement.
Utmost care shall be taken to ensure over all cleanliness and proper upkeep of the working ar
Trucks carrying sand, earth and pulverized materials etc. shall be covered while moving
/these materials shall be transported with top surface wet.
The contractor shall ensure that the atmosphere in plant area and on roads is
free from particulate matter like dust, sand, etc. by keeping the top surface wet for ease in b
At least two exits for any unit area shall be assured at all times – same arrangement
pits /trench excavation /elevated work platforms /confined spaces etc.
Welding cables and the power cable must be segregated and properly stored and used .The sa
from the area of movement and shall be free from obstruction.
Schedule for upkeep /cleaning of site to be firmed up and implemented on regular bas
standard of housekeeping and maintain
records for the same.
3. 3 HSE Measures
3 .3.1 Construction Hazards
The Contractor shall ensure identification of all Occupational Health, Safety & Environme
of work he is going to undertake and enlist mitigation measures. Contractor shall carry out J
(JSA) /Risk
Analysis specifically for high risk jobs /critical jobs like.
Working at height (+2.0 Mts height) for cold (incl. colour washing, painting, insulation etc
Work in confined space,
Deep excavations & trench cutting (depth > 2.0 mts.)
Operation & Maintenance of Batching Plant.
Shuttering / concreting (in single or multiple pour) for columns, parapets & roofs.
Erection & maintenance of Tower Crane.
Erection of structural steel members /roof-trusses /pipes at height more than 2.0 Mts. with
Erection of pipes (full length or fabricated) at height more than 2.0 Mts. height with Crane
All lifts using 100T Crane plus mechanical pulling.
All lifts using two cranes in unison (Tandem Lifting).
Any lift exceeding 80% capacity of the lifting equipments (hydra, crane etc.).
Lying of pipes (isolated or fabricated) in deep narrow trenches– manually or mechanically
Maintenance of crane /extension or reduction of crane-boom on roads or in yards.
Erection of any item at >2.0 Mts. height using 100T crane or of higher capacity
Hydrostatic test of pipes, vessels & columns and water-flushing.
Radiography jobs (in-plant & open field)
Work in Live Electrical installations / circuits
Handling of explosives & Blasting operations
Demolishing / dismantling activities
Welding / gas cutting jobs at height (+2.0 Mts.)
Lifting / placing roof-girders at height (+2.0 Mts.)
Lifting & laying of metallic / non-metallic sheet over roof /structures.
Lifting of pipes, gratings, equipments/vessels at heights (+2.0 Mts) with & without using c
Calibration of equipment, instruments and functional tests at yards / work- sites.
Operability test of Pump, Motors (after coupling) & Compressors.
Cold or Hot works inside Confined Space.
Transportation & shifting of ODC consignments into project areas.
Working in “charged /live” elect. Panels
Stress Relieving works (Electrically or by Gas-burners).
Pneumatic Tests
Card board blasting
Chemical cleaning and take feedback from PDIL /Owner. The necessary HSE measures de
place, prior to start of an activity & also shall be maintained during the course of works, by th
such JSAs shall be kept available at work sites by the
Contractor to enable all concerned carrying out checks /verification.
Accessibility
The Contractor shall provide safe means of access(in sufficient numbers) & efficient exit to
including provisions of suitable and sufficient scaffolding at various stages during all operation
safety of his workmen and PDIL /Owner.
The Contractor shall implement use of all measures including use of “life line”, “fall arresters
arresters” , “safety nets” etc. during the course of using all safe accesses & exits, so that in no cas
at risk of slip & fall during their travel.
The access to operating plant /project complex shall be strictly regulated. Any
person or vehicle entering such complex shall undergo identification check, as per the proced
/requirement of PDIL /Owner.
Working at height
The Contractor shall issue permit for working (PFW) at height after verifying and certifying t
also undertake to ensure compliance to the conditions of the permit during the currency of
adherence of personal protective equipments. Contractor’s Safety Officer shall verify com
items of permit document after implementation of action is completed by Contractor’s e
engineers at work site. Job Safety Analysis (JSA) for specific works at height duly commented b
be kept attached with particular Permit for Work (PFW) at site for ready reference & fol
shall be initially issued for one single shift or expected duration of normal work and exten
duration, if required. PDIL /Owner can devise block-permit system at any specific area, in consul
specific HSE Committee to specify the time-period of validity of such PFW or
its renewal. This permit shall be applicable in areas where specific clearance
from Owner’s operation Dept. / Safety Dept. is not required. PDIL /Owner’s field Engineers
Area Coordinators may verify and counter sign this permit (as an evidence of verification
of the job.
All personnel shall be medically examined & certified by registered doctor, confirming
working at height. The fitness examination shall be done once in six months.
In case work is undertaken without taking sufficient precautions as given in the permit,
Engineers may exercise their authority to cancel such permit and stop the work till satisfa
/rectification is arranged made. Contractors are expected to maintain a register for issuance of pe
thereof including preserving the used permits for verification during audits etc.
The Contractor shall arrange (at his cost) and ensure use of Fall Arrester Systems by h
are to be used while climbing
/descending tall structures or vessels /columns etc. These arresters should lock automaticall
line, restricting free fall of the user. The device is to be provided with a double security opening s
attachment or release of the user at any point of rope. In order to avoid shock, the system shoul
keeping the person in vertical position in case of a fall.
The Contractor shall ensure that Full body harnesses conforming EN361 and having authoriz
by all personnel while working at height. The lanyards and life lines should have enough
take the load of the worker in case of a fall. One end of the lanyard shall be firmly tied with the
other end with life line. The harness should be capable of keeping the workman vertical in cas
him to rescue himself.
The Contractor shall provide Roof Top Walk Ladders for carrying out activities on sloping ro
chances of slippages and falls.
The Contractor shall ensure that a proper Safety Net System is used wherever the haza
present. The safety net, preferably a knotted one with mesh ropes conforming to IS 5175 /ISO 11
rope & tie cord of minimum 12mm dia. The Safety Net shall be located not more than 6.0 meters
surface extending on either side up to sufficient margin to arrest fall of persons working at differe
In case of accidental fall of person on such Safety Net, the bottom most portion of Sa
any structure, object or ground.
The Contractor shall ensure positive isolation while working at different levels like in the pipe
working platforms with toe boards & hand rails shall be sufficiently strong & shall have sufficien
workmen and tools & tackles including the equipments required for executing the job. Such wor
have mid-rails and top-rails, to enable people
work safely in sitting posture.
- OISD STD 173: Fire prevention & protection system for electrical installations
- SP 30 (BIS) : National Electric Code
All electrical installations shall be approved by the concerned statutory authorities.
All temporary electrical installations/facilities shall be regularly checked by the licensed/com
the Contractor and appropriate records shall be maintained. Inspection of temporary electri
project construction site”. Such inspection records are to be made available to
PDIL /Owner, whenever asked for.
3.3.6.2 The following features shall also be ensured for all electrical
installations during construction phase by the contractor:
Each installation shall have a main switch with a protective device, installed in an enclosure a
point. The operating height of the main switch shall not exceed 1.5 M. The main switch sha
point of supply by means of armored cable.
The outgoing feeders shall be double or triple pole switches with fuses/ MCBs. Loads
shall be balanced as far as possible and load on neutral should not exceed 20% of load in the phas
The installation shall be adequately protected against overload, short circuit and earth leakag
protective devices. Fuses wherever used shall be HRC type. Use of re-wired fuses shall be strictly
leakage device shall have an operating current not exceeding 30 mA.
All connections to the hand tools / welding receptacles shall be taken through proper switches
All single phase sockets shall be minimum 3 pin type only. All unused sockets shall be provid
Only 3 core (P+N+E) overall sheathed flexible cables with minimum
conductor size of 1.5 mm copper shall be used for all single phase hand tools.
Only metallic distribution boxes with double earthing shall be used at site. No wooden boxes
All power cables shall be terminated with compression type cable glands. Tinned copper lugs
strand wires / cables.
Cables shall be free from any insulation damage.
Minimum depth of cable trench shall be 750 mm for MV & control cables and 900 mm for
cables shall be laid over a sand layer and covered with sand, brick & soil for ensuring m
Cables shall not be laid in waterlogged area as far as practicable. Cable route markers sha
every 25 M of buried trench route. When laid above ground, cables shall be properly cleared o
poles of at least 2.1 M high. Minimum head clearance of 6 meters shall be provided at road cross
road crossings for cables shall be avoided to the extent feasible. In any case no underground
allowed to cross the roads without pipe sleeve.
An independent earthing facility should preferably be established within the temporary
All appliances and equipment shall be adequately earthed. In case of armored cables, the ar
the earthing system.
All cable joints shall be done with proper jointing kit. No taped /temporary joints shal
All cables and wire rope used for earth connections shall be terminated through tinned
In case of local earthing, earth electrodes shall be buried near the supply point and ea
shall be connected to local earth plate for further distribution to various appliances. Al
earth connection shall have insulation of green colour.
Separate core shall be provided for neutral. Earth /Structures shall not be
used as a neutral in any case.
ON / OFF position of all switches shall be clearly designated /painted for easy
isolation in emergency.
3 .3.7 Welding / Gas cutting
Contractor shall ensure that flash back arrestors conforming to BS: 6158 or equivalent are ins
cylinders as well as at the torch end of the gas hose, while in use. All cylinders shall be mou
provided with a closing key. Empty & filled-up gas cylinders shall be stored separately with TAG
direct sun or rain. Minimum 2 nos. of Portable DCP type fire extinguishers (10 kg) shall be main
stores. Stacking & storing of compressed gas cylinders shall be arranged away from DG set
Panels /Elec. boards, etc
The burner and the hose placed downstream of pressure reducer shall be equipped with
/Non Return Valve device.
The hoses for acetylene and oxygen cylinders must be of different colours. Their conne
burners shall be made with a safety collar.
At end of work, the cylinders in use shall be closed and hoses depressurized.
Cutting of metals using gases, other than oxygen & acetylene, shall require written concurren
All welding machines shall have effective earthing at least at distinctly isolated two points. In
good housekeeping, and to reduce fire hazard, live electrode bits shall be contained safely and sh
on the ground.
The hoses of Acetylene and Oxygen shall be kept free from entanglement & away from comm
and preferably be hanged overhead in such a manner which can avoid contact with cranes, hydra
construction machinery.
Hot spatters shall be contained /restricted appropriately (by making use of effective fir
and their flying-off as well as chance of contact with near-by flammable materials shall be st
The Contractor shall arrange adequate systems & practices for accumulation
/collection of metal & other scraps and remnant electrodes and their safe disposal at regula
maintain the fabrication and other areas satisfactorily clean & tidy.
All gas cylinders must have a cylinder cap on at all times when not in use.
3 .3.20 Communication
All persons deployed at the work site shall have access to effective means of communica
incident can be reported immediately and assistance sought by them. All health & safety
communicated in a simple & clear language easily understood by the local workforce. For
typical subjects that should be communicated
are: -
- Number of Safety Inductions carried-out at site (for workmen & staff members)
- Number of HSE inspections carried out.
- Number of “Safety Walk Through” carried-out by site-head.
- Number of HSE shortfalls / lapses identified per contractor & closed-out in time.
- Number of Safety Meetings conducted (in-house / with contractors)
- Number of HSE Audits made (internal & external) vis-à-vis non conformances raised
- Number of HSE Trainings conducted at site for supervisors & workmen
- Number of HSE Awareness / Motivational program conducted by contractors
- Study of Near miss case reported
- Encouragements /Awards /Recognitions to workmen, job supervisors & field engineers.
- Suggestions for improvement
3 .3.26 Excavation
The Contractor shall obtain permission from competent authorities prior to excavation wher
Contractor shall locate the position of buried utilities (water line, cable route, etc.) by referrin
drawing / in consultation with PDIL /Owner. The Contractor shall start digging manually
position of buried utilities & thereafter use mechanical means. The Contractor shall keep soil h
from edge or a distance equal to depth of pit (whichever is more).
The Contractor shall maintain sufficient “angle of repose” during excavation – shall also pr
bench as decided by PDIL /Owner.
The Contractor shall arrange “battering” or “benching” wherever required for preventing co
excavations.
The Contractor shall identify & arrange de-watering pump or well-point system to prevent earth c
rain /influx of underground water.
The Contractor shall arrange protective fencing / barricading with warning signal around excavat
along with minimum 2 (two) entries, exits / escape ladders.
The Contractor must avoid “underpinning” /under-cutting to prevent collapse of chunk of e
The Contractor shall use “stoppers” to prevent over-run of vehicle wheels at the edge of excavate
The Contractor shall arrange strengthening of “shoring” & “strutting” proactively to avoid collap
vehicular movement in close proximity of
excavated areas /pits /trenches, etc.
ract value for LSTK, EPC, EPCC This penalty shall be in addition to all
ract. The decision of imposing stop-work-instruction and
IL /Owner. The same shall be binding on the Contractor.
Contractor eligible to
Penalty Amount
To be decided by PDIL/Owner.
n
PDIL / Owner at least telephonically by Contractor immediately and in
Contractor. Thereafter, a Supplementary Accident / Incident investigation
r within 72 hours. Near Miss incidents, Dangerous accidents / incident
he accident/ incident shall be investigated by a team of Contractor’s
arge or at least by his deputy) for establishing root-cause and
s. Findings shall be documented and suitable actions taken to avoid
nd the Contractor shall extend all necessary help and cooperation in this
side world.
gree of housekeeping is maintained and shall ensure the followings:
disposed off from the working areas to designated locations.
steel scrap lying scattered at different places within the working areas
ums and other combustible packing materials, shall be removed from work
s like pipes, steel, sand, boulders, concrete, chips and bricks etc shall not
ment of men & machineries.
materials shall be stacked properly for erection.
ed.
and trailers etc shall be allowed on roads, which may obstruct the traffic
al jobs like.
r cold (incl. colour washing, painting, insulation etc.) & hot works.
2.0 Mts.)
(+2.0 Mts.)
llic sheet over roof /structures.
vessels at heights (+2.0 Mts) with & without using cranes.
and functional tests at yards / work- sites.
coupling) & Compressors.
ace.
ignments into project areas.
ls
by Gas-burners).
rom PDIL /Owner. The necessary HSE measures devised shall be put in to
all be maintained during the course of works, by the Contractor. Copies of
work sites by the
g out checks /verification.
(PPEs)
taff, workers and visitors including
ecords to be kept) & wear appropriate PPEs like nape strap type
of industrial HDPE), safety shoes
body harness (CE marked and conforming to EN361), protective
ective devices, etc. All these gadgets shall conform to applicable IS
tional standards. The Contractor shall implement a regular regime of
being issued /used by the workmen of their own & also its sub-agencies and
placed forthwith.
ve color scheme for helmets to be used by various agencies. The
the Owner /PDIL and shall choose any colour other than white (for Owner)
eferably wear dark green band on their helmet so that workmen can
ncies. HSE personnel shall preferably wear such dresses with
uring night, when light falls on them.
ve face shield and helmets, gauntlet and protective clothing is mandatory.
vant IS Specification.
all provide PPEs (new) of all types to PDIL & Owner's personnel, at his
life jacket at all time.
is given under Appendix-A.
age of following safety equipments/ accessories (conforming to applicable
men & visitors including their subcontractors all through the span of
mmissioning:-
gloves, Safety Shoes, etc)
ess than 8.0 mm)
ngths)
pe) – 6 kg capacity
with eyelets)
king (PFW) at height after verifying and certifying the checkpoints. He shall
onditions of the permit during the currency of the permit including
ts. Contractor’s Safety Officer shall verify compliance status of the
ntation of action is completed by Contractor’s execution / field
SA) for specific works at height duly commented by PDIL /Owner, shall
Work (PFW) at site for ready reference & follow-up. Such PFW
t or expected duration of normal work and extended further for balance
block-permit system at any specific area, in consultation with project
eriod of validity of such PFW or
areas where specific clearance
t. is not required. PDIL /Owner’s field Engineers /Safety Officers /
sign this permit (as an evidence of verification) during the execution
ned & certified by registered doctor, confirming their ‘medical fitness for
all be done once in six months.
ing sufficient precautions as given in the permit, PDIL /Owner
cancel such permit and stop the work till satisfactory compliance
re expected to maintain a register for issuance of permit and extensions
its for verification during audits etc.
st) and ensure use of Fall Arrester Systems by his workers. Fall arresters
mns etc. These arresters should lock automatically against the anchorage
e is to be provided with a double security opening system to ensure safe
of rope. In order to avoid shock, the system should be capable of
se of a fall.
harnesses conforming EN361 and having authorized CE marking is used
The lanyards and life lines should have enough tensile strength to
ne end of the lanyard shall be firmly tied with the harnesses and the
d be capable of keeping the workman vertical in case of a fall, enabling
alk Ladders for carrying out activities on sloping roofs in order to reduce the
per Safety Net System is used wherever the hazard of fall from height is
ne with mesh ropes conforming to IS 5175 /ISO 1140 shall have a border
afety Net shall be located not more than 6.0 meters below the working
nt margin to arrest fall of persons working at different heights.
such Safety Net, the bottom most portion of Safety Net should not touch
ion while working at different levels like in the pipe rack areas. The
ls shall be sufficiently strong & shall have sufficient space to hold the
uipments required for executing the job. Such working platforms shall
ple
workmen for all works that cannot be safely done from the ground or from
ork that can be safely done using ladders or certified (by 3rd party competent
d, an extra workman shall always be engaged for holding the ladder.
affolds used during construction activities shall be strong enough to take
ays furnish duly approved construction-design details of scaffold &
charge, before they are being installed /constructed at site. Owner
following requirements:
) for providing connection to each equipments & machinery and the same
ed on the front face of DBs (distribution boards) /JBs (Junction boxes) at
ent including tools & tackles used during construction phase are
intained as per provisions of the latest revision of the Indian
ns.
ans for proper & safe installation and for regular inspection of
points including their earthing. A copy of the license shall be
or triple pole switches with fuses/ MCBs. Loads in a three phase circuit
n neutral should not exceed 20% of load in the phase.
cted against overload, short circuit and earth leakage by the use of suitable
be HRC type. Use of re-wired fuses shall be strictly prohibited. The earth
t not exceeding 30 mA.
g receptacles shall be taken through proper switches, sockets and plugs.
m 3 pin type only. All unused sockets shall be provided with socket caps.
ed flexible cables with minimum
d for all single phase hand tools.
ble earthing shall be used at site. No wooden boxes shall be used.
compression type cable glands. Tinned copper lugs shall be used for multi-
amage.
50 mm for MV & control cables and 900 mm for HV cables. These
covered with sand, brick & soil for ensuring mechanical protection.
ea as far as practicable. Cable route markers shall be provided at
aid above ground, cables shall be properly cleared or supported on rigid
learance of 6 meters shall be provided at road crossings. Underground
to the extent feasible. In any case no underground power cable shall be
.
preferably be established within the temporary installation premises.
dequately earthed. In case of armored cables, the armor shall be bonded to
be kept free from entanglement & away from common pathways /walkways
manner which can avoid contact with cranes, hydra or other mobile
ed appropriately (by making use of effective fire retardant cloth/fabric)
ontact with near-by flammable materials shall be stopped.
tems & practices for accumulation
mnant electrodes and their safe disposal at regular interval so as to
actorily clean & tidy.
on at all times when not in use.
that can adversely affect the health of its workers and issue & implement
ting shall not be permitted even if not explicitly stated elsewhere in the
electrodes used for Gas Tungsten Arc Welding shall not contain
s health.
& falls.
s
per latest Explosive Rules (Indian / International) with prior permission.
f Controller of Explosives (CCOE) for collection, transportation, storage
ng operations.
thod statement (in cognizance with statutory requirements) for diffusing
e carrying out actual task. Nowhere blasting shall be carried out by the
ent of competent supervisor and
ractor must arrange clearance of all the routes, roads, access. The
of traffic controllers at project site routes /roads /accesses, to alert
as well as pedestrians.
d to carry workers within the plant area and also to & from the labour
e at site.
y provisions, if any
lls
rts)
ging studies plan for PDIL/ Owner approval prior to lifting equipment
pprox. 100 Ton capacities due to constraints of its dimensions, location
Contractor shall generate the format for “Permit for heavy lift /critical
ontractor shall check the validity of the crane inspection certificate issued by
ent shall also apply to all rigging equipments utilized for the job.
nsible for all rigging activities.
s of all workmen who are engaged
tc. and such fitness checks shall be carried-out every six months interval
ner & record shall be maintained Adequate safety measures such as positive
t to work, etc. shall be taken during all heavy or critical lifts.
ape, size or volume), at any height, it is always advisable to prepare a
ideration hazards & risks associated therein – this can enable people to put
& side-by-side establish a practical method for risk-free erection /lifts. The
nt the same, when risks are identified as “medium” or “high”
ent /qualified engineer.
th leading & trailing indicators for statistical and performance
o key performance indicators are covered in Monthly HSE Report. The
ir record and strive for its continual improvement.
Remarks, in any
Contractor shall obtain permits for hot work, Cold work, Excavation, Confined Space, Liftin
Height, Electrical work and Radiography work from Owner.
The contractor shall monitor record and compile list of his workers entering the operatio
day and ensure & record their return after completing the job.
Contractor’s workers and staff members shall use designated entrances and proceed by desig
areas only assigned to them. The workers shall not be allowed to enter units' area, tanks
etc. without work authorization permit.
Work activities shall be planned in such a way so as to minimize the disruption of oth
carried out in an operational plant/unit and activities of other contractors.
The contractor shall submit a list of all chemicals /toxic substances that are intended to be us
prior approval of the Owner.
Specific training on working in a hydrocarbon plant shall be imparted to the work force and m
carried out for Rescue operations /First- Aid measures.
Proper barricading /cordoning of the operational units /plants shall be done before start
activities. No unauthorized person shall be allowed to trespass. The height and overall design
structure shall be finalized in consultation with the Owner and shall be got approved from t
Care shall be taken to prevent hitting underground facilities such as electrical cables, hydroca
execution of work.
Barricading with water curtain shall be arranged in specific /critical areas where hydro
likely to be present such as near Horton spheres or tanks. Positioning of fire tenders (fro
ensured during execution of critical activities.
Emergency evacuation plan shall be worked out and all workmen shall be apprised ab
Mock drill operations may also be conducted.
Flammable gas test shall be conducted prior to any hot work using appropriate
Sewers, drains, vents or any other gas escaping points shall be covered with flame retardant ta
Respiratory devices shall be kept handy while working in confined zones where there
inhalation of poisonous gases. Constant monitoring of presence of Gas /Hydrocarbon shall b
Clearance shall be obtained from all parties before starting hot tapping,
patchwork on live lines and work on corroded tank roof. Positive isolation of
line/equipment by blinding for welding/cutting/grinding shall be done. Closing of valve will not b
for isolation.
Welding spatters shall be contained properly and in no case shall be allowed to fall on the gro
Similar care shall be taken during cutting operations.
The vehicles, cranes, engines, etc. shall be fitted with spark arresters on the exhaust pipe and
Safety Department of the Owner.
Plant air should not be used to clean any part of the body or clothing or use to blow off dirt on
Gas detectors should be installed in gas leakage prone areas as per requirement of Own
personnel.
Experienced full time safety personnel shall be exclusively deployed to
monitor safety aspects in running plants.
3. 8 HSE Promotions
The contractor shall encourage his workforce to promote HSE efforts at workplace
workshops /seminars /training programs, celebrating HSE awareness weeks & National Safe
quizzes & essay competitions, distributing pamphlets, posters & material on HSE, providing ince
good HSE practices and granting incentives /bonus for
completing the job without any lost time accident.
3. 9 Lock Out and Tag out (LOTO) for isolation of energy source
Contractor shall follow the LOTO /Isolation procedure of owner for all energy source isolatio
purview by /of owner i.e. “Brown field” For the other entire energy source (not under purview of
“Green field” Contractor shall develop a system to ensure the isolation of equipments, pipelines,
from the energy source covering following as minimum:-
- Identification of all energy source viz electrical, mechanical, hydraulic, pneumatic, chem
gravitational, radiation and other forms of stored or kinetic energy.
- Establishing the energy isolation devices viz: manually operated electrical circuit breakers, dis
blind flanges, etc
- Lock Out and Tag out log book
- Installation of Lock Out devices for preventing the inadvertent release of stored energy and Ta
(“Danger”, “Do Not operate” or Do not Remove” tags) to indicate that testing, maintenance
underway and the device cannot be operated until the tag out device is removed.
- Permit for isolation and de-isolation of energy source.
- Availability of competent persons like experienced operators at substations, pum
supervisors, etc.
Contractor shall ensure that all the sources are locked out and tagged properly before givin
job.
After the completion of job, contractor shall ensure all tools and tackles are removed and nobod
working area and signing on LOTO log book.
Only on confirmation of above the contractor will remove their lock and tag from the isolat
instructions for energizing the same. Only the person carrying out the task shall himself carry the
/Lock out.
APPENDIX-A
A. IS CODES ON HSE
- SP: 53 Safety code for the use, Care and protection of hand operated
tools.
- IS: 838 Code of practice for safety & health requirements in electric and gas welding an
- IS: 1179 Eye & Face precautions during welding, equipment etc.
- IS: 1860 Safety requirements for use, care and protection of abrasive grinding wheels.
- IS: 1989 (Pt -II)Leather safety boots and shoes
- IS: 2925 Industrial Safety Helmets
- IS: 3016 Code of practice for fire safety precautions in welding & cutting operation.
- IS: 3043 Code of practice for earthing
- IS: 3764 Code of safety for excavation work
- IS: 3786 Methods for computation of frequency and severity rates for industrial injuries
industrial accidents
- IS: 3696 Safety Code of scaffolds and ladders
- IS: 4083 Recommendations on stacking and storage of construction materials and comp
- IS: 4770 Rubber gloves for electrical purposes
- IS: 5121 Safety code for piling and other deep foundations
- IS: 5216 (Pt-I) Recommendations on Safety procedures and practices in electrical works
- IS: 5557 Industrial and Safety rubber lined boots
- IS: 5983 Eye protectors
- IS: 6519 Selection, care and repair of Safety footwear
- IS: 6994 (Pt-I) Industrial Safety Gloves (Leather & Cotton Gloves)
- IS: 7293 Safety Code for working with construction Machinery
- IS: 8519 Guide for selection of industrial safety equipment for body protection
- IS: 9167 Ear protectors
- IS: 11006 Flash back arrestor (Flame arrestor)
- IS: 11016 General and safety requirements for machine tools and their operation
- IS: 11057 Specification for Industrial safety nets
- IS: 11226 Leather safety footwear having direct molded rubber sole
- IS: 11972 Code of practice for safety precaution to be taken when entering a sewerage s
- IS: 13367 Code of practice-safe use of cranes
- IS: 13416 Recommendations for preventive measures against hazards at working place
AP
en.
G INSIDE A
t:
yed to
ough self
ities for continual improvement in the HSE
E activities.
E requirements.
s.
L/Owner representative.
s do not
or probability of “fire” incident exists.
es)
ody protection
their operation
ole
n entering a sewerage system
NSI Z 49.1
Gases in cylinders 1235 Jefferson Davis
APPENDIX-B
DETAILS OF FIRST AID BOX
Sr. No. DESCRIPTION
1 Small size Roller Bandages, 1 Inch Wide (Finger Dressing small)
2 Medium size Roller Bandages, 2 Inches Wide (Hand & Foot Dressing)
3 Large size Roller Bandages, 4 Inches Wide (Body Dressing Large)
4 Large size Burn Dressing (Burn Dressing Large)
5 Cotton Wool (20 gms packing)
6 Antiseptic Solution Dettol (100 ml.) or Savlon
7 Mercurochrome Solution (100 ml.) 2% in water
8 Ammonia Solution (20 ml.)
9 Pair of Scissors
10 Adhesive Plaster (1.25 cm X 5 m)
11 Eye pads in Separate Sealed Pkt.
12 Tourniquet
13 Safety Pins
14 Tinc. Iodine/ Betadin (100 ml.)
15 Polythene Wash cup for washing eyes
16 Potassium Permanganate (20 gms.)
17 Tinc. Benzoine (100 ml.)
18 Triangular Bandages
19 Band Aid Dressing
20 Iodex/Moov (25 gms.)
21 Tongue Depressor
22 Boric Acid Powder (20 gms.)
23 Sodium Bicarbonate (20 gms.)
24 Dressing Powder (Nebasulf) (10 gms.)
25 Medicinal Glass
26 Duster
27 Booklet (English & Local Language)
28 Soap
29 Toothache Solution
30 Vicks (22 gms.)
31 Forceps
32 Note Book
33 Splints
34 Life Saving/Emergency/Over-the counter Drugs As decided at site
Note: The medicines prescribed above are only indicative. Equivalent medicines can
also be used. A prescription, in this regard, shall be required from a qualified Physician.
AP
QUANTITY
6 Pcs.
6 Pcs.
6 Pcs.
4 Pkts.
4 Pkts.
1 Bottle
1 Bottle
1 Bottle
1 Piece
1 Spool
4 pcs.
1 No.
1 Dozen
1 Bottle
1 No.
1 Pkt.
1 Bottle
2 Nos.
5 Pcs.
1 Bottle
1 No.
2 Pkt.
1 Pkt.
1 Bottle
1 No.
1 No.
1 No. each
1 No.
1 No.
1 Bottle
1 No.
1 No.
4 Nos.
can
sician.
APPENDIX-C
TYPE OF FIRES VIS-À-VIS FIRE EXTINGUISHERS
Fire Extinguisher Water Foam CO2
Fire
Electrical fires X X D
LEGEND:
D: CAN BE USED
X: NOT TO BE USED
Note: Fire extinguishing equipment must be checked at least once a year and after every use by
The equipment must have an inspection label on which the next inspection date is given. Type of exti
be marked on it.
APPENDIX-D
LIST OF STATUTORY ACTS & RULES RELATING TO HSE
- The Indian Explosives Act and Rules
- The Motor Vehicle Act and Central Motor Vehicle Rules
- The Factories Act and concerned Factory Rules
- The Petroleum Act and Petroleum Rules
- The Workmen Compensation Act
- The Gas Cylinder Rules and the Static & Mobile Pressure Vessels Rules
- The Indian Electricity Act and Rules
- The Indian Boiler Act and Regulations
- The Water (Prevention & Control & Pollution) Act
- The Water (Prevention & Control of Pollution) Cess Act
- The Air (Prevention & Control of Pollution) Act
- The Atomic Energy Act
- The Radiation Protection Rules
- The Indian Fisheries Act
- The Indian Forest Act
- The Wild Life (Protection) Act
- The Environment (Protection) Act and Rules
- The Hazardous Wastes (Management & Handling) Rules
- The Manufacturing, Storage & import of Hazardous Chemicals Rules
- The Public Liability Act
- The Building and Other Construction Workers (Regulation of Employment And Condition of se
- Other statutory acts Like EPF, ESIS, and Minimum Wage Act.
APPENDIX-E
TRAINING SUBJECTS / TOPICS (For contractors’ personnel)
1. The Law & Safety – Statutory Requirement / Applicable statutes / Duties of
employer / employee
2. Policy & Administration – Why HSE? / Duties & Responsibilities of Safety Personnel at proje
incentive on accident prevention
3. HSE & Supervision – Duties of Supervisor / HSE integrated supervision / who should be held
accidents?
4. Safety Budget /Cost of Accidents – Direct costs /Indirect costs
5. Hazard Identification /Type of hazards /HIRAC
6. Behavioral Safety & Motivation
7. Housekeeping – Storage /Stacking /Handling of materials /Hydra handling
8. Occupational Health in Construction sector
9. Personal Protective Equipments – Respiratory & Non- respiratory
10. Electricity & Safety – ELCB /Fuse /Powered tools /Project illumination
11. Handling of Compressed Gas – Transportation /Storage /FBAs /Fire prevention
12. Machine Safety – Machine guarding /Maintenance
13. Transportation – Hazards & risks in transp. of materials /ODC consignments
14. Cranes & Other Lifting machinery – Legal requirements vis-à-vis essential safety requiremen
15. Communication – HSE Induction /TBTs /Safety Committee /Safety meeting / Safety propaga
16. Excavation – Risks & Dangers /Safety measures
17. Working at Heights – Use of ladder /Work on roofs /Scaffolds /Double harness lanyards /Life
/Safety Nets /Floor openings
18. Hazards in Welding & important safety precautions
19. Gas Cutting – Hazards & safety measures
20. Fire prevention & fire protection
APPENDIX-F LIST OF PROCEDURES (MINIMUM) TO BE FORMING PART OF HSE PL
A. HSE Management Procedures:
HSE Risk Management (including JSA/HIRA)
HSE Legal Compliance and Other Requirements
HSE Objectives & Performance
HSE Training and Competence (including Induction)
HSE Motivation & Award Scheme
HSE Audits
HSE Meetings
HSE Sub Contractor Management
HSE Emergency Management
HSE Incidents Reporting and Management
HSE Reports
HSE Management System Review
HSE Change Management
HSE procedure for Behavior based Safety
First Aid & Management
Roles, Responsibility, accountabilities and Authorities
B. Job procedures /Safe Operating procedures
Setting Up Site & Signage’s
Handling of Electrical Appliances
Working at Height
Confined Space Entry
Permit to Work (including hot works)
Housekeeping
Lifting Operations
Transportation of materials including Manual Handling
Compressed Air Tools and Units
Earthmoving Operations & excavation
Scaffolding
Fire Prevention/Protection
Hazardous Substance handling & Storage
Radiation Hazard
Personal Protective Equipment
********
RE EXTINGUISHERS
Dry Powder Multi
purpose
(ABC)
Can control D
minor surface
fires
D D
D D
D D
RELATING TO HSE
es
ct
es
hemicals Rules
rect costs
n- respiratory
roject illumination
/Storage /FBAs /Fire prevention
1 Accident/Incident Prevention 21
5 Back Safety 25
7 Blinding Safety 27
8 Breathing Apparatus 28
12 Chemical Safety 32
15 Crane Operation 35
16 De-blinding Safety 36
19 Electrical Safety 39
41 Falling Objects 66
ETY TALK TOPICS
SAFETY TALK TOPICS
Importance of Checklist
Incident reporting
Ladder Safety
Personal behavior
Personal Hygiene
Pinch Points
45 Fire Safety 69
46 Forklift Safety 71
47 General Safety 72
48 Grounding of Equipments 73
51 Hazard Recognition 76
52 Hearing Safety 77
53 Heat Stress 78
56 Horseplay 81
63 Responsibilities of Rigger 88
64 Excavation Safety 89
Risk Assessment
Scaffold Safety
Short cuts
Sleeping at site
Smoking safety
Static Electricity
Traffic Safety
Working at Height
CLASSIFICATION OF LIFTING APPLIANCES
LIFTING APPLIANCES
Why TPI? –
Carrying out TPI of Lifting Equipment and Lifting Tools & Tackles is Statutory Norm / Require
Factories Act.
Safety Level of the Equipment is enhanced, as competent person shall note down the loop hole
inspection & testing and recommend or suggest corrective measures.
Equipment Manufacturer shall issue Mfr. Test Certificate by Self Attested way and define prod
However, as per the Law: Obtain ‘Form-10’ (In Gujarat it is ‘Form-10’) Certificate issued by TPI (Com
the date of installation or from the date when product is First Taken for Use.
Procedure:
Procedure of Inspection & Testing is carried out strictly as per checklist developed individually. Compete
their service as per the scope of work:
‘Form-10’ Certificate as per govt. Format is issued on successful Inspection & Testing of the
products.
Note: Form-10 Certificate is issued by Competent Person as per State Govt. Format in Gujarat State. Ho
Form No. is different.
Interval for Inspection & testing:
As directed in the Section-29 of Factories Act, these Tests are carried out annually and Register
should be maintained for every product to keep record regarding Health of the Products.
No lifting machine and no chain, rope or lifting tackle shall, except for the purpose of test, be
safe working load which shall be plainly marked thereon together with an identification mark an
prescribed register; and where this is not practicable, a table showing the safe working loads of
lifting machine or chain, rope or lifting tackle in use shall be displayed in prominent position on
While any person is employed or working on or near the wheel track of a traveling crane in
would be liable to be struck by the crane, effective measures shall be taken to ensure tha
approach within 63[six meters] of that place.
2. The State Government may make rules in respect of any lifting machine or any chain, rope
or lifting tackle used in factories -
Prescribing further requirements to be complied with in addition to those set out in this secti
Providing for exemption from compliance with all or any of the requirements of this section,
such compliance is unnecessary or impracticable.
3. For the purposes of this section a lifting machine or a chain, rope or lifting tackle shall be deemed to
examined if a visual examination supplemented, if necessary, by other means and by the dismantling of
been carried out as carefully as the conditions permit in order to arrive at a reliable conclusion as to the
examined.
Explanation:
In this section, -
"lifting machine" means a crane, crab, winch, teagle, pulley block, gin wheel, transporter or runway;
64(b) "lifting tackle" means any chain sling, rope sling, hook, shackle, swivel, coupling, socket, clamp
appliance, whether fixed or movable, used in connection with the raising or lowering of persons, or load
machines.
********
IFTING APPLIANCES
ackles
ad such as
tent person shall note down the loop holes during the
ve measures.
cate by Self Attested way and define products’ attributes.
is ‘Form-10’) Certificate issued by TPI (Competent Person) from
st Taken for Use.
. i.e. Brakes, Limit Switches, Wire Rope, Hook Blocks and other
per State Govt. Format in Gujarat State. However, state wise this
e carried out annually and Register
rding Health of the Products.
AND TACKLES
with in respect of every lifting machine (other than a hoist and lift)
ising or lowering persons, goods or materials :-
ovable, of every lifting machine and every chain, rope or lifting
ackle shall, except for the purpose of test, be loaded beyond the
reon together with an identification mark and duly entered in the
e, a table showing the safe working loads of every kind and size of
shall be displayed in prominent position on the premises;
near the wheel track of a traveling crane in any place where he
tive measures shall be taken to ensure that the crane does not
****