Professional Documents
Culture Documents
METHOD STATEMENT
Preparation/Safety
All students and staff will undergo a site safety induction on the first day
At the beginning and end of each following day all students and staff will attend a site safety
briefing
All team members will be required to wear appropriate PPE (personal protective equipment)
at all times including: a hardhat, hi-visibility jacket, work boots, work gloves, and safety
goggles
Organising Reinforcement
The reinforcement cages will be transported from the work area to the site of the
foundations by inserting lifting rods
Reinforcement will positioned in formwork prior to pouring concrete
The setting out team are responsible for setting out the line of the RC decks and A-frame
The formwork team and site supervisor will erect shutters for the RC decks and A-frame,
using traditional methods
A suspended frame will be erected to fix the steel reinforcement
Reinforcement will be fixed according to drawings P16.03 and P16.05 and specific bending
schedules on the casting deck
When fixing the A-frame connection more reinforcement may be required, and will be cut
and bent as required
Reinforcement will positioned in formwork by machine prior to pouring concrete
The A-frame will be provisionally placed into foundation 2 using a 30 ton excavator and
adequate temporary works
PROJECT: BREWERY WHARF BRIDGE
METHOD STATEMENT
The RC decks will be provisionally installed using a mobile crane and adequate temporary
works
The tension cables will be installed with their full structural engagement under the
supervision of the site manager
The temporary works will be removed and a quality assessment carried out by the site
supervisor
Quality Control
Check to ensure that there is proper cover distance and that the steel is fixed properly to the
drawings provided.
PROJECT: BREWERY WHARF BRIDGE
METHOD STATEMENT
A FRAME COLUMN
Risk Assessment
Risk
Risk Evaluation
What are the Who might Rating
Control measures in
hazards? be harmed? What are the risks place to eliminate or Conseq Likelih Overall Low,
Corrective actions
reduce the risks? uence ood risk Medium
required
or High
(1 – 3) (1 – 3) (C x L)
Everyone Tripping over objects Make sure there is Ensure that the work
that’s or equipment on site enough cautions signs area is kept tidy.
and slipping due to Ensure proper cable 2 2 4 Medium
working on available wherever it’s
Slips/trips site. slippery floors. slippery. management.
Lifting and Everyone If the frames and Use the correct Make sure someone
dropping that’s decks are not lifted procedure of lifting using is directing the
working on using the correct the right machinery and person that’s lifting
site equipment or machine equipment. Also make the frame. And 2 2 4 Medium
it could harm the sure that the area is placing it at the right
PROJECT: BREWERY WHARF BRIDGE
METHOD STATEMENT
Risk
Risk Evaluation
What are the Who might Rating
Control measures in
hazards? be harmed? What are the risks place to eliminate or Conseq Likelih Overall Low,
Corrective actions
reduce the risks? uence ood risk Medium
required
or High
(1 – 3) (1 – 3) (C x L)
Manual Everyone Workers could cut Making sure the workers Making sure workers
Handling that’s using their hand due to not are wearing gloves when are wearing the
an equipment wearing the correct joining the rebar and that correct PPE at all
PPE, or be injured the only people who times and only 1 1 1 Low
due to not having the handle powered handle the
correct training. equipment have the equipment for which
proper training. they are trained.
Plant and Everyone The plant and Make sure that the plants Making sure nothing 1 1 1 Low
vehicle working on vehicles could fail and are checked before use. is on the way of the
movement site cause harm to plants and vehicles.
workers on site.
PROJECT: BREWERY WHARF BRIDGE
METHOD STATEMENT
RISK MATRIX
Potential consequence of harm
1 – Unlikely
(injury rare, though 1 – Low 2 – Low 3 – Medium
possible)
2 – Possible
Likelihood
(injury could occur 2 – Low 4 – Medium 6 – High
of harm
occasionally)
3 – Probable
(injury likely to occur, can 3 – Medium 6 – High 9 – Extreme
be expected)
PROJECT: BREWERY WHARF BRIDGE
METHOD STATEMENT
RISK EVALUATION
This is calculated by multiplying the likelihood against the consequence e.g. taking a likelihood of 1, which is classified as Unlikely and
multiplying this against a Potential Consequence of 2, which is classified as Significant Injury, would give you and overall Risk Rating of 2,
which would result in an overall evaluation as a low risk.
1 to 2 = Low risk
Low risks are largely acceptable, monitor periodically to determine situation changes which may affect the risk, or after
significant changes
3 to 4 = Medium risk
Medium risks at the upper end of this band should only be tolerated for the short-term and then only whilst further control measures to
mitigate the risk are being planned and introduced, within a defined time period. Risks on the lower end should be reduced if practicable.
6 = High risk
High risks activities should cease immediately until further control measures to mitigate the risk are introduced. The continued effectiveness
of control measures must be monitored periodically.
9 = Extreme Risk
Work should not be started or continued until the risk has been mitigated. Immediate action is required to reduce exposure. A
detailed mitigation plan must be developed, implemented and monitored by senior management to reduce the risk before work
is allowed to commence.