Pictorial Pre-Task Form- 60

Briefing (JSA)
Rev. :00 Date: 21-02-2021

TASK: Lifting operations LOCATION: DATE:


SUPERVISOR: DESIGNATION:

Select applicable hazard(s)


       

       

Please select as necessary


        

Please select work equipment necessary


         

Please select working at height equipment necessary


        

Please select personal protective equipment necessary


        
Pictorial Pre-Task Form- 60
Briefing (JSA)
Rev. :00 Date: 21-02-2021

Hazard or potential
Job Step Safety measures
accident
Daily TBT must for all.
Lifting permit must be taken.
Personal risk of injury. Only trained and authorised persons are permitted to
Lifting Overturning Risk of damage of property operate the plant assess the ground conditions for
and equipment. stability to prevent subsidence.
Risk of injury of public The crane will be set up as close the lift area as
possible to avoid over reaching.
The crane operator will not attempt to lift outside the
specified crane capacity
The load should always be kept close to the ground
The crane operator should maintain a steady speed
during the operation
Personal risk of injury. Where possible an exclusion zone should be erected
Collision with structures or Risk of damage of property to segregate the work area from other plant.
mobile plant and equipment Setting up will be under the control of the banksman.
Risk of injury of public The banksman should ensure there is adequate space
Personal injury or damage due between the crane and any structures and take into
to failure during operation e.g. account the swing radius.
during lifting operations
Lack of equipment Financial and production loss Before starting the crane operator should carry out a
maintenance & certification due to damage trail run to ensure there is adequate room.
Financial and production loss Lifting equipment and accessories shall be fit for
due to quarantine of plant / purpose, certified .
vehicle

A lifting plan, complete with a schedule of common


lifts shall be prepared, at an early stage.
Personal risk of injury. A detail survey or crane positioning and overlapping
Lack of communication Risk of damage of property arcs shall be carried out by the competent lifting
and equipment supervisor
Risk of injury of public Anti-clash precautions shall be designed and
implemented
Communication between riggers / signallers and
crane operators shall be maintained at all time.
Where possible two-way radio shall be used. Where
local restrictions prevent the use of two-way radio,
alternative arrangements shall be devised and
implemented.

The crane operator will ensure that the plant is never


left running or a load suspended when he is not
Personal risk of injury. attendance.
Risk of damage of property The operator will ensure the key are removed and the
Unauthorised access and equipment cab doors locked when he is a break or the end of his
Risk of injury of public shift.
Place signage and banksman to control access way
while lifting.
Pictorial Pre-Task Form- 60
Briefing (JSA)
Rev. :00 Date: 21-02-2021

Work Site Sketch(as required)


Include access / egress, equipment set up etc. Alternatively add additional job / task details and proposed control
measures on this page.
Pictorial Pre-Task Form- 60
Briefing (JSA)
Rev. :00 Date: 21-02-2021

Name and Surname Position Company Signature


1

10

11

12

13

14

15

16

17

18

19

20

21

22

23