You are on page 1of 8

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/277918051

Analysis and Design Approach for Concrete Plugs for Underground Storage
Caverns

Article  in  Practice Periodical on Structural Design and Construction · May 2015


DOI: 10.1061/(ASCE)SC.1943-5576.0000260

CITATIONS READS
0 900

4 authors:

Altaf Usmani G. Kannan


Engineers India Limited Indian Institute of Technology Delhi
28 PUBLICATIONS   59 CITATIONS    35 PUBLICATIONS   49 CITATIONS   

SEE PROFILE SEE PROFILE

A. Nanda ANIRBAN Mandal

44 PUBLICATIONS   67 CITATIONS   
Visvesvaraya National Institute of Technology
27 PUBLICATIONS   81 CITATIONS   
SEE PROFILE
SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Underground unlined rock caverns View project

Rock Salt mechanics View project

All content following this page was uploaded by ANIRBAN Mandal on 03 September 2015.

The user has requested enhancement of the downloaded file.


Analysis and Design Approach for Concrete Plugs
for Underground Storage Caverns
A. Usmani1; G. Kannan2; A. Nanda3; and A. Mandal4
Downloaded from ascelibrary.org by VISVESVARAYA NATL INST OF TECH on 07/07/15. Copyright ASCE. For personal use only; all rights reserved.

Abstract: In underground crude oil storage facilities, concrete plugs are mainly required to contain crude oil inside caverns and are
designed as gas-tight to prevent movement of any oil or vapor across the tunnel, either in a horizontal or vertical direction. Plugs are
retained in a key excavated in the rock surface, which provides sufficient bearing to the concrete mass under sustained loading conditions.
Construction of plugs involves mass concreting under the typically hot and humid conditions found in underground construction.
Therefore, the construction of plugs requires an engineering design that takes into account not only design loads and reinforcement, but also
the systematic cooling arrangement and efficient grouting mechanism so that the basic purpose of the plug design is not defeated. This
paper discusses the design and construction aspects involved in the construction of large tunnel and shaft plugs for an underground crude oil
storage project. DOI: 10.1061/(ASCE)SC.1943-5576.0000260. © 2015 American Society of Civil Engineers.
Author keywords: Plug; Tunnel; Shaft; Concrete; Cooling; Grouting.

Introduction design and construction aspect of tunnel and shaft plugs that were
adopted in an underground crude oil storage project site.
Concrete plugs in crude storage facilities (Fig. 1) are a critical
component used to contain the crude oil inside the rock cavern.
These plugs are designed as gas-tight to prevent any escape of oil Design Philosophy
or gas and to withstand differential pressure occurring on account
of different fluid pressures stored across the plugs. Barcena et al. Plugs are designed to resist failure mainly from five modes, viz,
(2005) suggested that a rough rock/plug interface is essential to mechanical jacking of rock surrounding the plug key, shear failure
provide a frictional bond and reduce the hydraulic gradient along through concrete along the contact rock, deep beam-flexure failure,
the interface. There are generally two types of plugs required in failure owing to excessive seepage around plug and long-term che-
underground storage; tunnel plugs and shaft plugs (Fig. 1). The mical/physical breakdown of concrete, grout, or surrounding
tunnel plug is vertically located at a point to isolate crude oil, rock. Thus, there are three stages of design for the concrete plug:
forming a separation between oil and water. On the other hand, the (1) structural analysis and concrete design for worst loading
shaft plug is horizontal in the section and is covered by a long conditions to transfer the load safely to the surrounding rock,
column of water or concrete, below which oil and vapor is re- (2) thermal analysis to study heat generation and cooling-system
tained. Plug construction involves a substantial volume of con- design, and (3) design of a grouting system that will provide
crete, which results in the development of a great amount of heat- desired long-term sealing for the plug. The concrete plug thickness
hydration. Therefore, the probability of cracks occurring owing to and reinforcement are designed to safely transfer the load coming
heat of hydration of the cement needs to be avoided. Provision is from the plug into the surrounding rock. This should be well sup-
made in the design stage as well as during the construction process ported by the cooling system, which is designed to reduce the risk of
to prevent the development of large temperature gradients caused thermal cracks that can develop during the strength gain in the
by hydration of cement using concrete cooling arrangements. To concrete followed by grouting arrangement to ensure gas-tightness of
ensure airtightness of the plug for prevention of any gas leakage, the plug (after shrinking of the concrete). Cooling systems are pro-
contact grouting of the plug is carried out at the concrete and rock vided first to limit the risk of thermal cracking during hardening of
interface until a proper seal is established. This paper addresses the the concrete and later to produce an injectable gap after shrinking
through which the grouting material can percolate; thus, grouting is
carried out to make the plug denser and ensure tightness of the plug.
1
Deputy Manager, Engineers India Ltd, New Delhi, India The total pressure acting on plug is transferred to the sur-
(corresponding author). E-mail: altaf_usmani@rediffmail.com rounding rock by means of a key that is cut into the rock surface
2
Deputy Manager, Engineers India Ltd, 1, Bhikaji Cama Place, New all along the periphery of the tunnel walls (Fig. 2). The plug is
Delhi, India. retained both because of the cut in the rock (key-in) and because of
3
Deputy General Manager, Engineers India Ltd, 1, Bhikaji Cama Place, the forces of friction and adhesion occurring along the contact
New Delhi, New Delhi, India. surface of concrete with the rock. The plug design is based on
4
Associate Professor, Dept. of Civil Engineering, VNIT Nagpur, long-term operational requirements as well as construction meth-
Nagpur, Maharashtra, India.
odology adopted specific to each plug, either in the vertical or
Note. This manuscript was submitted on November 9, 2014; approved
on February 27, 2015; published online on May 15, 2015. Discussion horizontal plane. Thus, the design philosophy is different in the
period open until October 15, 2015; separate discussions must be sub- case of a shaft plug versus a tunnel plug. Access tunnel plugs are
mitted for individual papers. This paper is part of the Practice Periodical designed for single-stage plug construction to avoid creation of
on Structural Design and Construction, © ASCE, ISSN 1084-0680/ any joint of weakness; hence, the construction sequence has no
04015004(7)/$25.00. impact on its design philosophy. However, the shaft plug is

© ASCE 04015004-1 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr.


constructed in two stages or more to avoid heavy shuttering re- Shaft Plug Design
quired to cater for several hundred tons of reinforcement, piping,
Shaft plugs are located at an interface at which crude oil is lo-
cooling, and grouting-pipe loads. The plugs are constructed in
cated in the lower zone below the plug, and the upper zone is
specially excavated plug key-ins designed for the purpose. Pri-
filled either by concrete or a water column. Shafts of 12 × 8 m
marily to construct stable plugs, plug key-in locations are chosen
sizes were considered in this study. This plug is designed to
in rock masses that are massive, less jointed, and have high rock
withstand differential pressures on either side and also to support
quality and Q-values. The selected location should have minimal-
the load of casing pipes that are connected to different seepage
to-no seepage. It should also not be very close to any tunnel/cavern
and crude oil pumps. These casings loads are quite large and vary
junction areas.
from 200 to 300 tons, which is an operational requirement of
storage structures. In this project, shaft plugs are designed to
Downloaded from ascelibrary.org by VISVESVARAYA NATL INST OF TECH on 07/07/15. Copyright ASCE. For personal use only; all rights reserved.

Access Tunnel Plug Design resist the worst combination of pressure coming from the water/
concrete column, self-weight, and weight of the casings and
Tunnel plugs are dimensioned according to the size of the access
carrier pipes. Plugs consist of a trapezoidal-shaped bottom layer
tunnel, which is typically 8 × 8 m (D-shaped cross section in this
and top layer, as shown in Fig. 3, and are sealed in an enlarged
present study). Tunnel plugs are 3 m thick and extend into the rock
part of the shaft section known as the plug key. This widening
surface with a key depth of 1–2 m, as shown in Fig. 2. In under-
provides a good seat for the plug and distributes the unbalanced
ground storage projects, tunnel plugs are mainly designed to resist
load into the surrounding rock. Analysis is done assuming the
raw crude oil pressure, which also includes pressure of the gas
shaft plug as a simply supported slab that is supported on all four
above the oil surface, which is typically around 0.15 MPa. These
sides.
plugs are also designed to resist hydraulic pressure at the bottom of
The design of the tunnel and shaft plugs was carried out using a
the plug due to the water head (on other side of plug) used to
M40 Concrete Mix (IS 10262:2009) with sulfate-resisting cement
maintain hydraulic confinement around the caverns. In case of any
owing to its contact with the oil’s surface. Plug key-ins are ex-
explosion inside the caverns, plugs can be affected by the resulting
cavated inside the rock mass (e.g., gneiss, granite), which supports
pressure wave; hence, an accidental load of 1.0 MPa is also con-
the plug load by bearing and transfers the loads to sound rock
sidered during the design stage. Thus, the tunnel plug is designed
below. In the case of the tunnel plug, a governing load due to
to withstand maximum loads considering the preceding require-
water pressure for 45 m head of water per the tunnel plug elevation
ments. The tunnel plug design is checked for minimum crack-
was considered in this study. However, in the case of the shaft
width requirements prescribed for liquid retaining structures,
plug, total casing load of approximately 135 kN / m2 , plus that of
which is limited to 0.2 mm as per Cl. 4.4.1.2, IS 3370: Part 2
standing water above the plug, were considered in addition to live
(BIS 2009). A manhole in the center of the plug is also provided to
load and self-weight of the concrete. Because shaft plug con-
access the other side of the plug to facilitate removal of workers
struction is carried out in two stages of 1.5 and 2.5 m each for a
and machinery after completion of the plug.
4-m-thick shaft plug, the weight of second 2.5-m layer of concrete
is assumed to be taken care by the first layer of concrete during
design. The concrete plug is modeled as a four-noded plate ele-
ment using finite-element analysis. Plug reinforcement is calcu-
lated considering all final loads affecting the plug with the entire
Cavern plug thickness. Shear capacity of concrete (Timothy 2005) is

Shaft Plug
Shaft Plug Key
Tunnel

Water Curtain Tunnel


Shafts
Casings

Tunnel Plug

Fig. 1. Schematic layout of underground rock caverns Fig. 3. Plan and sectional view of a shaft plug along with casings

Plug Key

Plug

Manhole

Fig. 2. Plan, sectional, and three-dimensional view of a tunnel plug along with a circular manhole

© ASCE 04015004-2 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr.


checked against shear stresses developed after final loading and 70
Channel -1
after casting the total thickness of the plug. Further adequacy of 60 Channel -2
Channel -3
the reinforcement is also checked against moments and shear

Temperature (ºC)
Channel -4
forces developed after the casting the first layer of concrete with all 50
empty casing loads transferred to it. Because of the staged 40
construction methodology, a check is made for induced stresses 30
developed in the steel owing to the first and second layers of
concrete. If the total stress developed in the steel after casing the 20
final concrete layer is higher than the strength of steel, 10
reinforcement obtained earlier is revised accordingly. The plug 0
is also checked against the shear-transfer capacity between the first 0 50 100 150 200 250 300 350
Downloaded from ascelibrary.org by VISVESVARAYA NATL INST OF TECH on 07/07/15. Copyright ASCE. For personal use only; all rights reserved.

and second layers of concrete, and if required, shear links between Time (h)
the two layers of concrete are provided. Similarly, other
construction sequences that can affect design considerations Fig. 4. Temperature variation of sensors during adiabatic test
mainly include size of the ring beam adopted to support plug
shuttering, shuttering and arrangement of sleeves, and casting of
the first layer of the concrete plug. the center and three on the side-faces of the cube. One sensor was
The plug is analyzed as simply supported around its periphery placed outside the cube to measure ambient temperature, which
along the rock surface, and is modeled as a plate using plain stress maintained a constant 30–31°C. The temperature of concrete in the
analysis. The reinforcement of the plug is established from the adiabatic box was monitored on an hourly basis continuously for
plate tress model, on the basis of a slice of 1 m centered on the axis 7 days, as shown in Fig. 4, for four sensors. It is observed from the
of the plugs. This model provides the main support reactions from figure that max temperature rise was noted in Sensor 1, located in the
which distribution of the uniform pressure both horizontally and center of the cube; this reached a maximum of 64°C, and on the side
vertically is determined. Plug reinforcement is determined from the face, the maximum value reached 57°C.
distribution of tensile and compressive forces on the entire thickness Many previous researchers have reported that several dele-
of the plug. Most of the reinforcement is confined around the per- terious reactions occur in concrete during the hardening stage,
iphery of the plug surface owing to concentration of tensile forces as which can jeopardize durability of the concrete structure. One
the load is transferred to the rock through the key. However, some of those damage mechanisms is the so-called delayed ettringite
minimum compressive reinforcement is also provided along the formation (DEF) (Ji 2008), which is a result of too-high tempe-
middle layers to counteract large compressive forces. rature while the concrete hardens. Delayed ettringite formation
may result in internal cracking of the concrete, even years after
construction. For this reason, construction codes in many
Cooling Design countries restrict the maximum concrete temperature during
hardening or setting of concrete. Different standards around the
world define the maximum allowable limits for temperature to
Introduction
prevent cracking. For example, British Standard BS 8007 (BSI
It is well known that heat is produced during hydration of con- 1987) recommends that maximum concrete temperature must not
crete. The temperature continues to rise within the structure as exceed 65°C, French standard NF EN 1992 recommends 70°C,
long as the rate of heat development is higher than the rate of Irish standard IS 326 (National Standards Authority of Ireland
dissipation to its surroundings. The structure will expand in vo- 2004) recommends 60°C, and American Concrete Institute (ACI)
lume during this initial phase, and later it will contract as it cools. 207.2R (ACI 2007) allows a maximum temperature of 70°C.
It is observed that volumetric changes within such a structure do Thus, for different types of concrete plugs, DEF has to be avoided,
not take place freely owing to the presence of different restraints especially because of the risk of additional sulfate attack, to ensure
that would also result in thermal stresses. Therefore, restraint, in the functionality and tightness of the plug. Thus, maintaining the
addition to the previously mentioned mechanisms, determines the temperature of the concrete below 60°C during and after the
risk of thermal cracking. Restraint is often differentiated into in- concrete casting is extremely important for durable plug design.
ternal and external restraint, with restraints such as reinforcement Heat-hydration analysis of the concrete plug and subsequent
(in the case of tunnel plugs) and reinforcement and piping (in the cooling design was carried out using numerical analysis program
case of shaft plugs) playing a major role in restricting this free MIDAS Civil (2011). MIDAS Information Technology Co., Ltd. as
expansion of concrete along the rock surface. shown in Fig. 5. This exercise was conducted to evaluate analy-
To ensure plug tightness, the risk of thermal cracking is re- tically the effect of casting temperature on the heat of hydration in
duced by using cooling arrangements in the plug concrete during a mass-concrete plug constructed using sulfate-resistant Portland
and after casting of concrete until the concrete temperature reduces cement. The concrete plug is modeled using three-dimensional
to ambient levels. Plug tightness is also achieved through a elements, and analysis is carried out using the software’s heat-
combination of cooling arrangements used to shrink the concrete transfer module, which entails the process of calculating the
plug (as part of secondary cooling) followed by grouting to fill any change of nodal temperatures with time due to heat source/con-
gap created while the concrete cools. vection. The modulus of elasticity of the concrete mix (M40) is
To study the behavior of concrete in confined conditions, a set assigned as 3:16 × 1010 N/ m2 ; Poisson ratio = 0:2; thermal coef-
of semiadiabatic temperature tests was carried out on 1 × 1 × 1-m3 ficient = 1:0 × 10 −5 / °C; and density = 2:6 × 104 N / m3 . An am-
samples onsite in confined conditions, with the concrete filling in a bient temperature of 30°C is considered for the analysis carried out
box closed on all four sides. Cube samples were made of M40 mix according to ACI 2007, with a compressive strength of 40 MPa
(BIS 2000), and a water–cement ratio of 0.32 was considered per the at 28 days. The heat-source function for the analysis was given
actual concrete mix design recommended for plug construction. according to test reports of temperature monitoring of a concrete
Four temperature sensors were placed inside the cube, with one at cube tested with the same mix condition. Three-dimensional

© ASCE 04015004-3 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr.


Downloaded from ascelibrary.org by VISVESVARAYA NATL INST OF TECH on 07/07/15. Copyright ASCE. For personal use only; all rights reserved.

Fig. 5. Heat of hydration analysis for tunnel plug

modeling and analysis of the plug is carried out, first with a heat the restraining rock foundation. In the case of the tunnel plug,
source in terms of a heat function, and then under a cooling-pipe analysis revealed that in the bottom part of the tunnel plug, close
system. Temperatures due to the heat of hydration can be obtained to the restraining rock foundation, cooling pipes are placed at
by examining the hourly time-step results. It is observed from the a dense array (distance of approximately 400 mm) for effective
results that the greatest temperature rise occurs after 35–40 h of cooling. It is observed that owing to the low heat-transfer
heat-source application, as noted in Fig. 4. capability of concrete, a larger distance between the individual
cooling pipes would result in an increased temperature between
the cooling pipes and thus a higher risk for thermal cracking.
However, higher up in the tunnel plugs, the crack risk lowers
Different Stages of Cooling Arrangement
owing to the larger distance from the restraining border (elastic
Many different solutions to the problem of thermal cracking are resilience, according to high-beam theory). In these parts of
practiced today. A reduction in cement content of the concrete in the tunnel plugs, the distance between the individual cooling
combination with a reduction of the fresh concrete-mix temperature pipes is increased up to 700 mm, as shown in Fig. 6. Thus,
could be used to lower the maximum temperature during hardening the maximum temperature in between the individual cooling
to some extent. However, the cracking problem associated with pipes and the geometry of the plugs is a significant factor for
thermal gradients and ineffective grouting continues even after cooling design. In the case of the tunnel plug, the geometry of
adopting the previously discussed measures. However, as tunnel the plugs and the properties of the concrete allow for a maximum
and shaft plugs in an underground storage facility constitute the spacing of 800 mm. The required distribution of the cooling
most vital part, no risk to the life of these concrete structures is system into individual cooling coils calls for a maximum length
allowed. Hence, design of a compatible cooling system is seen as of 60–80 m of cooling pipes. The required flow in a cooling
the only practical solution in such types of plugs. The advantage coil is set between 20 and 27 (× 10 −3 ) m3 / min to limit the
of using these cooling pipes is twofold: first, to limit the risk of increase of water temperature in the coil. However, when the
thermal cracking occurred during hardening of the concrete, and length of the coils increased, the flow and, consequently, the
later, to produce an injectable gap for the grouting process to ensure operating pressure had to be increased to achieve the desired
plug tightness. cooling effect. This would largely increase the cost for achieving
Design of the cooling system is carried out according to the a watertight cooling system, especially because of the more
results of the numerical analysis along with specific project re- complicated joints. A typical rise of temperature inside a full 8-m
quirements; however, the final system of pipe arrangement is plug, along with time at four different sensor locations, is shown
governed by availability of space and construction sequence. The in Fig. 7. All of the sensors were placed at four locations, as
standards ACI 207.4R-93 (ACI 1993) and ACI 207.2R-07 (ACI shown in Fig. 7. It is observed from the figure that owing to the
2007) both suggest a basic methodology for calculation of flow arrangement of the cooling pipes, for the same concrete mix,
and cooling-pipe arrangements for mass concrete structures, which the maximum temperature in the concrete has only reached 54°C,
is based on an old but good detailed investigation conducted which is less than the limits prescribed by different standards for
during the construction of dams and other mass concreting works. DEF, which can result in the cracking of concrete. Soon after the
However, this approach does not take into account the effect of concrete in the tunnel plugs is mature (28 days of hardening), the
restraint, which is considerable for tunnel and shaft plugs. surfaces of the plugs are isolated and the cooling temperature is
The arrangement of the cooling pipes is chosen both from slowly reduced in the tunnel plugs. The reduction in temperature
experience and an iterative process. A denser array of cooling will result in thermal contraction of the tunnel plug and will
pipes has to be placed in the bottom of the tunnel plugs close to widen the gap between rock and concrete at the top and sides of

© ASCE 04015004-4 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr.


Cooling Pipes 25 mm diameter
3000

1000
700
700

8000

8000
Downloaded from ascelibrary.org by VISVESVARAYA NATL INST OF TECH on 07/07/15. Copyright ASCE. For personal use only; all rights reserved.

600

500

Primary Cooling
8000
Secondary Cooling
1000

Fig. 6. Plan and sectional view of cooling arrangement with cooling pipes

60.0
Sensor-1
Sensor-2
50.0 Sensor-3
Temperature (ºC)

Sensor-4
40.0 Sensor-5

30.0

20.0

10.0

0.0
0.0 50.0 100.0 150.0 200.0 250.0 300.0
Time (h)

Fig. 7. Temperature measurement inside a tunnel plug during concrete pouring

the plug. This temperature reduction has to be done slowly to Although casting the plug, several measures are taken to avoid
avoid cracking in this phase. When the complete plug has been shrinkage cracks within the concrete; however, contact between
cooled down to the desired temperature, grouting needs to be the rock mass and the concrete may not be tight owing to several
performed. Once the grout has hardened, the plug will be re- reasons, viz, differential expansion of rockmass and concrete
stored to ambient temperature, which will result in compressed during casting of plug; shrinkage of concrete plug; uneven contact
plugs. surface between plug and the rock mass; gaps created in the
contact, especially at the crown, owing to gravity settling of ce-
ment during casting; and gaps created in the contact possibly
Grouting Procedure due to improper compaction, which is practically difficult to
achieve at times.
These gaps in the contact are grouted after casting of the plug
Introduction to achieve watertightness and gastightness of the plug. Therefore,
Grouting is performed in tunnel and shaft plugs after completion for the purpose of contact grouting, grout-injection tubes are
of plug-casting to achieve complete gas-tightness of the plug. embedded inside the plug before casting.
Once the plug key is excavated per the design requirements, rock- Once the concrete plug attains its design strength (28 days after
mass grouting is performed to grout all the blast-induced cracks casting), it is cooled again to 5°C. The embedded cooling-pipe
near the key-in surface in the excavated damaged zone. The rock networks used for the primary cooling are also used for the sec-
mass surrounding a minimum 5 m of the plug area on all sides is ondary cooling. This reduced temperature will allow the plug to
grouted with higher pressure of up to 2.0 MPa, as shown in Fig. 8. shrink and create more gaps artificially in the contact between the
Ordinary Portland cement (OPC) cement is used for this purpose; cast plug and the rock mass. Two consecutive stages of contact
depending on the rock type, microcement may also be used. Rock- grouting are performed at this stage. Grout is injected in the gaps
mass grout holes are spaced 0.5 m on all sides. The packer should between the concrete plug and rock mass during cooling and once
be put as close to the surface of the holes (approximately 50 cm in set, the cooling stops and the plug attains normal ambient tem-
depth). perature. At this stage, the plug expands to its normal size and the

© ASCE 04015004-5 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr.


Downloaded from ascelibrary.org by VISVESVARAYA NATL INST OF TECH on 07/07/15. Copyright ASCE. For personal use only; all rights reserved.

Fig. 8. Plan and sectional view of postgrouting arrangement around a tunnel plug

Outer injection tube for grouting (Inner diameter 10 mm minimum)


Inner/Central injection tube for grouting (Inner diameter 10 mm minimum)
Minimum 54 mm diameter semiflexible
grouting pipe 500 c/c
2500
4000

30°

GI Pipes drilled 50 cm inside rock


1500

Minimum 45 diameter borehole


500 c/c (Rock mass grouting)

Fig. 9. Sectional view of contact grouting-pipe arrangement around a tunnel plug

grouted contact between the plug and rock mass are further sealed, three peripheral rows in contact with the rock at 1 m interspacing
resulting in tight plug. distance. These pipes are laid not more than 5 m in length. They
Two stages of contact grouting are performed to ensure com- are overlapped to cover the entire perimeter in each row. These
plete gastightness of the concrete plug. The first stage is carried out pipes are made of PVC, which can withstand the high pressure
with ordinary Portland cement and later with microcement. The created by the hardened concrete. They have an outer protective
first-stage contact grouting acts more as backfill concreting and layer that prevents cement slurry entering the grout pipes during
fills any large voids, such as those created in the roof and upper casting of the plug. Although grouting, the grout pressure of 0.3
wall area of the plugs. These are implemented by embedded gal- MPa from inside the tubes opens the protective layer covering the
vanized iron (GI) pipes inserted approximately 50 cm inside the perforations and allows the grout to flow out of the tubes in
rock mass. These pipes are placed at 0.5-m spacing all along the contact.
sides, similar to rock-mass grout holes. The leftover hole portion In the case of the shaft plugs, secondary cooling is not performed
used for rock mass grouting can be used for this grouting instead during contact grouting. Here, because gravity causes the plug to be
of fresh drilling through the GI pipe into the rock mass. During the horizontal, the lower contact gets better tightness than its tunnel-
secondary cooling of the plug, the gaps created by shrinkage in the plug counterpart. However, the same procedure for contact grouting
contact are filled primarily with this grout at 0.5 MPa pressure. is followed as outlined previously for tunnel plugs.
During grouting of these pipes, the grout first fills the GI pipes and
the hole, and the annular space between pipe and the hole in the rock
Plug-Tightness Testing
mass, which then overflows and the grout spreads along the contact
between the plugs and rock mass. Foam or thin mortar is applied to Before second-stage contact grouting with microcement, water is
the opening of the annular space during the casting of plug to pre- injected through perforated grout-injection tubes to check the in-
vent cement slurry from entering the annular space. Large grout jection tube function and quantify the volume of leak and void
consumption is expected because leakage can be found from the space in the contact. This is called as tightness test and is carried
contact on both sides of the plug. Hence, OPC is used. Quick-set out through the central tube at 0.3 MPa pressure, as shown in
cement is applied on the leak surface along with some textile fiber to Fig. 9 using water. This is performed using specially designed
stop the leakage and make the grout successful. perforated grout-injection tubes embedded in the plug that are 5 m
Second-stage contact grouting starts once the first-stage grout is long, overlapped, and placed at 1 m interspacing distance, as ex-
completed and has gained strength under secondary cooling plained earlier in the grouting section. Central pipes are numbered
(normally after 2 days). This is performed with microcement, as C1–C10 and placed along the periphery of the plug, as shown in
which penetrates the leftover small spaces of the first-round con- Table 1. The tightness test is conducted in two stages, one before
tact grout with OPC. For this, specially designed perforated grout- and one after the second-stage contact grouting. Table 1 lists the
injection tubes are embedded inside the plug. They are placed in amount of leakage observed through the various sets of pipes. It is

© ASCE 04015004-6 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr.


Table 1. Tightness Test for Tunnel Plug
Center tube
Excess/leakage volume of water (× 10 −3 m3 )
Serial
number Description C1 C2 C3 C4 C5 C6 C7 C8 C9 C10
1. Initial water test before contact grouting 6.9 18 22 28 27.2 20.5 14.0 16.9 24.2 20.5
2. Final watertightness test after contact grouting 0.4 0.1 0.2 1.1 0.1 0.0 0.5 0.1 01 0.3

observed that whereas initially the leakage volume is higher before around the plug periphery. Construction sequence also pays a
Downloaded from ascelibrary.org by VISVESVARAYA NATL INST OF TECH on 07/07/15. Copyright ASCE. For personal use only; all rights reserved.

the second-stage contact grouting, it reduces significantly after the major role in construction of these plugs; specifically in case of the
second-stage contact grouting. This second-stage contact grouting shaft plug, in which reinforcement and concrete have to be cast
is first performed only in two outer-row injection tubes leaving the through a set of already installed casing pipes. Thus, the con-
central row empty, as shown in Fig. 9. The grout is injected struction of such large plugs in underground storage conditions
through each individual injection tube, which has both inlet and presents a challenge both to the designers and the site team to
outlet hoses coming out of the plug. They are properly numbered build a sound and durable concrete structure that is completely
and labeled. Grout left in the pipes is removed by flushing at a airtight and watertight.
pressure less than the pore-opening pressure of these injection
tubes, before the initial set of microcement. After the grout sets in
the rock mass, secondary cooling stops. Once the plug attains the
normal temperature, a watertightness test is performed in the References
central row injection tubes at 0.3 MPa water pressure. If the central
pipes are found to be leaking through the contact, or water is ACI (American Concrete Institute). (1993). “Cooling and insulating
seeping across the plug through the blast cracks, grouting is per- systems for mass concrete.” ACI 207.4R-93, Farmington Hills, MI.
formed through the outer-row tubes again at normal temperature. ACI (American Concrete Institute). (2007). “Report on thermal and
The grout-injection tubes are specially designed for regrouting for volume change effects on cracking of mass concrete.” ACI 207.2R-07,
this purpose. Every time immediately after grouting, the grout Farmington Hills, MI.
material inside the tubes is flushed at low pressure so that the pipes AFNOR (Association Francaise de Normalisation). (2005). “Design of
concrete structures: Part 1-1.” NF EN 1992-1-1 Standard: Eurocode 2,
can be used for regrouting. Thus, the plug tightness is achieved
France.
through contact grouting. Finally, after successive tightness tests,
Barcena, B. I., Llamas, M. B., Bueno, D. J., Garcia-Sineriz, M. J. L., Suso,
the central-row injection tubes are also grouted with microcement L. J., and Arduengo, B. (2005). “Plug construction to isolate active
at 0.7 MPa pressure. zones of inactive zones in coal mine. WATERCHEM Project.” Proc., 9th
Int. Mine Water Association, Oviedo, Asturias, Spain, 229–252.
BIS (Bureau of Indian Standards). (2000). “Code of practice for plain and
Conclusions reinforced concrete.” Indian code IS 456, New Delhi, India.
BIS (Bureau of Indian Standards). (2009). “Code of practice for design of
This paper presents a study on different aspects involved in the concrete structures for storage of liquids.” IS 3370: Part 2, New Delhi,
design and construction of large concrete plugs constructed for an India.
underground storage facility. These plugs are mainly required to BSI (British Standards Institution). (1987). “Code of practice for design of
separate crude oil and water and are designed as airtight to prevent concrete structures for retaining aqueous liquids.” BS 8007, London.
flow of any vapor across the tunnel either in a horizontal tunnel or Ji, G. (2008). “Cracking risk of concrete structures in the hardening
through a vertical shaft. The design philosophy of these plugs is phase.” Ph.D. thesis, Norwegian Univ. of Science and Technology,
based on the mechanical jacking of a concrete surface inside a Trondheim, Norway.
National Standards Authority of Ireland. (2004). “Concrete: Code of
V-shaped key, and bonding is developed owing to forces of fric-
practice for the structural use of concrete.” IS 326 National Standards
tion and adhesion occurring along the contact surface of concrete Authority of Ireland, Ireland, Dublin.
along the rock surface. Because mass concreting is involved in the Timothy, E. B. (2005). “Horizontal shear transfer between ultra high
construction of these plugs, suitable arrangements for the cooling performance concrete and light weight concrete.” Ph.D. thesis, Virginia
of concrete from inside are carried out to prevent development of Polytechnic Institute and State University, Blacksburg, VA.
high temperatures inside the cores. Finally, leakproof tightness of MIDAS Civil [Computer software]. MIDAS Information Technology Co.,
the plug is achieved by use of rock mass and contact grouting LTD.

© ASCE 04015004-7 Pract. Period. Struct. Des. Constr.

View publication stats Pract. Period. Struct. Des. Constr.

You might also like