You are on page 1of 4

THE PRESSURE NEWS

Volume 9, Issue 3, September 2004

F LARE L INES AND F LARE K NOCKOUTS


Flare lines, flare knockouts and Lines to the flare should be sloped corrosion and metal deterioration due
associated equipment are typically back to the flare knockout so that to high temperature from possible
open to atmosphere and exempted liquids will drain back to the flare flame impingement. Material
from the Safety Codes Act. However, knockout. selection for the construction of flare
if not installed, maintained and stacks is important. The flare pilot
operated properly, they could pose The flame arrestor should be checked should be checked to ensure that it
considerable safety hazards as well at every opportunity to ensure that it will be dependable.
as impacting on pressure equipment. is clean.
Flare systems should not be used as
Earlier this spring, a fatality occurred On some installations, a larger liquid collection systems. Many times
at a sour battery site. Investigation diameter line is installed at the base these liquids are corrosive. If the flare
noted that sour gas escaping from a of the flare. This line will act as a system tends to gather large amounts
manway on a flare knockout drum debris trap. This line should be of liquids, then the flare knockout
might have contributed to the incident. checked as it will eventually build up should be coated to protect it from
Flare knockout drums are designed with debris to the point where it could corrosion.
for limited pressure. Any restriction be blocked off.
downstream of the flare knockout There is always the question of
drum will result in a pressure buildup Most plants have a flare line that runs personal protective equipment
in the drum and possibly an over- the full length of the plant. The line in whenever working on gas and oil
pressure situation. The most common the plant needs to be sloped to the facilities. Personal gas monitors and
problems that occur at the bottom of knockout drum so that moisture does working in pairs are both important
the flare stacks are that the line might not stay in the line, causing freezing considerations.
freeze due to moisture in the line or or corrosion problems. In many
the flame arrester plugs off from cases, the discharges from the relief Remember that any restriction in the
carbon products generated from valves are tied into this line. Any flare line or flare stack may cause
combustion that occurs near the moisture that should happen to stay overpressure of the system, to the
flame arrestor. in the discharge port of the safety point where gases could be released
valve will cause corrosion of the relief from the flare knockout drum or
This article will point out some of the valve spindle to the point where the anywhere else in the system. Also
areas that should be checked during relief valve may seize and not backpressure in the system could
initial installation of flares and flare function when required. affect the operation of the relief
knockouts and also what should be valves that are discharging into the
checked during each turnaround. The flare stack itself should be flare line.
checked regularly for signs of

ABSA UPDATE SEMINAR


October 5 - Edmonton / October 7 - Calgary
Once again, ABSA is offering a seminar for the pressure equipment industry to address the impact of the most recent
ASME Code changes on designers, quality control inspectors and other users of the Codes. The 2004 ASME Boiler
and Pressure Vessel Codes are about to be published and will become mandatory on March 31, 2005.

The meetings have been set for October 5 at the Nisku Inn in Nisku, and October 7 at the Blackfoot Inn in Calgary.

As before, we will take the opportunity to discuss other items of interest such as findings from recent design reviews or
ASME shop reviews.
As seating may be limited, we would request that the number of attendees from any one company initially be restricted
to two. More openings may become available closer to the meeting dates. Registrations will be accepted on a first-
come, first-served basis. Applications may be obtained from your nearest ABSA office or from our website. The
deadlines for registration will be September 28 for Edmonton and September 30 for Calgary .

Have you visited us on the Internet yet? - www.absa.ca


The Pressure News Page 2 Volume 9, Issue 3, September 2004

SPECIAL CONSIDERATIONS FOR A LTERNATIVE Company Annual


L EAK T ESTING FOR CLOSURE W ELDS OF Renewal
of
PRESSURE PIPING F ABRICATED TO ASME B31.3 Power Engineering
In a previous article (Testing Pressure a written test procedure must be Certificates of Competency
Piping, Volume 2, Issue 4, August prepared to address fully the
1997) we explained the regulatory technical and safety considerations In 1994, the annual renewal of Power
requirements for pressure testing for the test, Engineer and Operator Certificates of
piping systems, as well as some of the owner of the piping system Competency came into legislation in
the considerations for alternative must review the circumstances and the Engineers Regulations and that
testing or waiving of the hydrostatic decide to accept the risk of not requirement continues in the Power
test. This article provides more hydrostatically testing the piping Engineers Regulation (AR 85/2003).
information about alternative leak system, Power engineers are responsible for
testing. We also explain the an ABSA SCO must have an the renewal of their certificates. Plant
application in Alberta of special opportunity to review and accept owners are responsible for ensuring
provisions for closure welds published the proposed written alternative test that the requirements of the Act and
in the ASME B31.3. procedure prior to testing, as regulations are met including that the
required by Sections 58(3) and power engineers are holding valid
Leak testing of pressure piping 7(2)(f) of the Design, Construction certificates. Some companies set up
systems is performed prior to placing and Installation of Boilers and a group renewal with ABSA and pay
the system in service. The purpose of Pressure Vessels Regulations. the annual renewal fee for their
the leak test is to verify the integrity of employees.
the piping system. The test is the last In addition to the listed alternative test
physical quality test in the fabrication methods, ASME B31.3 includes ABSA has changed the process for
process to verify the system is safe to provisions for exempting certain welds company renewals and the new
operate. from the required leak test. Paragraph process is as follows.:
345.2.3(c) states:
The hydrostatic test method is Annually, a company may initiate
preferred mainly due to safety "Closure Welds. renewal of their employees
considerations and for ease of finding The final weld connecting piping certificates by providing, to ABSA, the
leaks. Hydrostatic testing is required systems or components which following information on ABSA Form
by regulation and by B31.3, unless have been successfully leak AB-73 (Annual Renewal of Engineers
specific approval to use another type tested in accordance with para. and Operators Certificates) for each
of test procedure or to waive the leak 345 need not be leak tested employee :
test has been accepted by ABSA and provided the weld is examined in-
the Owner. Compared with air, water process in accordance with para. File Number
at ambient temperature has less 344.7 and passes with 100% Name of Employee
stored energy per unit of volume at radiographic examination in Date of Birth
equal pressures. Should a component accordance with para. 344.5 or
Class of Certificate
fail during a hydrostatic test, the 100% ultrasonic examination in
Certificate Number
energy stored in the water is quickly accordance with para. 344.6".
Home Address
dissipated. Conversely, in view of the
As with the alternative leak test E-mail address
considerable stored energy involved
procedures discussed above, use of Signature of Employee
with air testing, the consequence of
failure of a system under a pneumatic this exemption in Alberta requires
specific acceptance of the written ABSA will accept renewals for a
test can be significant.
procedure by an ABSA Safety Codes maximum of 3 years in advance. The
Officer. The company responsible for renewal cards will be sent to the
It is recognised that there may be
construction of the pressure piping individual. The certificate holder is
occasions when it is impracticable to
system must request acceptance prior responsible to post the card with his/
conduct a hydrostatic test. Therefore,
to construction. Requests are her certificate at the plant.
Alberta regulations allow for, and
ASME B31.3 provides, alternatives. reviewed by ABSA on a case-by-case
Alternative test methods include basis. The review includes verification
pneumatic testing and sensitive leak that all Code requirements will be CORRECTION
testing. Certain conditions must be satisfied, and that the ultimate owner
Volume 9, Issue 2, June 2004
satisfied if an alternative test is to be is in agreement with the proposed
Incident Involving Over-
used in lieu of the required hydrostatic alternative.
Pressure
test:
In-process examination in accordance
with B31.3 para. 344.7 necessitates Under the 3rd paragraph .....
there must be valid technical
that there be accept-reject criteria plant air at over 100 psig
justification for selecting an
established for the things that are (1034)kPa to the tank .... should
alternative test. For example, if
being examined. Unlike RT or UT, read ..... plant air at over 100
water would contaminate the
process, such criteria have not been psig (689 kPa) to the tank ....
(Continued on page 3)
The Pressure News Page 3 Volume 9, Issue 3, September 2004

PRESSURE PIPING CONSTRUCTION D OCUMENTS


Despite their being in use for many form is to be completed by the pressure, but also that the necessary
years, questions still arise about the contractor when the final pressure controls, instrumentation and
use of Construction Data Report for test specified in the engineering safety devices have been installed
Piping Systems forms (ABSA form design has been completed. and verified as functional to maintain
AB-83) and the Completion of the conveyed fluid within safe
Construction Declaration forms What if the contractor is only operating parameters.
(ABSA form AB-81). Here are some building part of the piping
common questions. system? When is the AB-81 form to be
completed?
Who completes the forms? In the case of piping spools
fabricated by third parties The AB-81 is to be completed before
AB-83 forms are to be completed by (subcontractors) and shipped to the the pressure piping system is put into
the contractor and delivered to the job site for assembly and testing by operation.
owner. the primary contractor, and no
pressure test has been specified in When is a pressure piping system
AB-81 forms are to be completed by the engineering design (to the considered to be in operation ?
the person responsible for the subcontractor), then the AB-83 would A pressure piping system is " in
construction, installation, testing and be completed as a "partial data operation " any time it is being used
inspection of the pressure piping report" by the subcontractor when the to convey, for any purpose, an
system and forwarded to the subcontractor's work is complete and expansible fluid under pressure after
Administrator/Chief Inspector. provided to the primary the final pressure test specified in the
contractor. The primary contractor engineering design has been
What is the purpose of the would then sign off a final data completed.
Construction Data Report for report when the final pressure test
Piping Systems (AB-83)? specified in the engineering design What happens to the completed
The purpose of the AB-83 document has been completed.
forms?
is to provide assurance that pressure
What is the purpose of the The owner must retain completed
piping has been constructed, tested
Completion of Construction AB-83 the forms on file for a period
and inspected in accordance with the
Declaration (AB-81) of not less than 5 years and produce
contractors quality system,
them on request of a Safety Codes
engineering design, construction The purpose of the AB-81 is to Officer. Completed AB-81 forms are
code and Safety Codes Act provide assurance the system is safe retained on file by ABSA. Copies of
requirements. to operate. This means not only that these completed forms must also be
the system has been constructed, maintained in accordance with the
When is the AB-83 to be inspected and tested in accordance contractors quality system.
completed? with the engineering design, thus
A construction and test data report deemed safe to be placed under

(Continued from page 2) CHANGES TO THE


established by Code and must be
realistically established by the I NFORMATION B ULLETINS W EB PAGES
designer. Note also that para. 342.2
states For in-process examination, The Information Bulletins web pages Background
the examinations shall be performed (www.absa.ca / Technical
by personnel other than those Information) have been revised to The Chief Inspector and Administrator
performing the production work. provide clearer information. We have issues Variances, Directives and
That is to say that the welder cannot categorized the bulletins and Interpretations regarding pressure
assess his own fit-up, etc. identified the bulletins that are equipment under the Safety Codes
outdated or are no longer relevant. Act.
Pressure piping systems can present The information bulletins have been
a very significant safety hazard so it categorized into six (6) types: Alert, Since 1998, a total of 42 Variances,
Directive, Exemption, Information, Directives, Interpretations, Alerts and
is extremely important that their
Interpretation and Variance. As well, other information were issued as
design, construction, installation,
where applicable, related regulations Information Bulletins. Some
operation, inspection and testing be
are identified. Information Bulletins are outdated or
carried out in strict accordance with
are no longer relevant due to changes
recognized standards. When In addition, the Act and Regulation in the Act and Regulations, ASME
considering any alternative to the web page will be revised to reference Codes, or other codes and standards.
hydrostatic test prescribed under the the applicable information bulletins. People have difficulty identifying
Safety Codes Act, all risks and This page is a good resource to check which Information Bulletins are still
consequences must be carefully and whether you are using the latest valid and associating them with the
thoroughly evaluated. regulation and also to see if there are applicable regulations.
any variances that can apply to a
(Continued on page 4)
specific regulation.
The Pressure News Page 4 Volume 9, Issue 3, September 2004

(Continued from page 3) ABSA is committed to providing the


latest information regarding pressure ABSA OFFICES
ABSA is committed to providing equipment safety to the public. To
information help us to serve you better, you can Edmonton - Head Office
provide your feedback and #200, 4208 - 97th Street
Effective communication between the suggestions to ABSA by emailing Edmonton, Alberta T6E 5Z9
public and ABSA is essential to Tel (780) 437-9100
webmaster@absa.ca. Fax (780) 437-7787
promote pressure equipment safety.
Calgary
Tower 3, #590 1212-31st Avenue N.E.
Calgary, Alberta T2E 7S8
PRESSURE E QUIPMENT SAFETY T RAINING Tel (403) 291-7070
Fax (403) 291-4545

As the pressure equipment safety assessment on the training page. Fort McMurray
authority, ABSA is committed to Industry and individual input is critical #204, 9913 Biggs Avenue
Fort McMurray, Alberta T9H 1S2
helping individuals and industry meet to identifying training requirements Tel (780) 714-3067
their training needs in pressure and we value your comments and Fax (780) 714-2380
equipment safety. ABSA currently feedback. To put forward ideas for
future training, to contact us for Grande Prairie
hosts seminars by the National Board #203, 10109 - 97th Avenue
of Boiler and Pressure Vessel customized training sessions or if you Grande Prairie, Alberta T8V 0N5
Inspectors and provides seminars, have any concerns with regard to Tel (780) 538-9922
with the use of ABSA subject training, please contact the training Fax (780) 538-9400
specialists, on topics such as the department at training@absa.ca. Lethbridge
upcoming Pressure Equipment Safety #300, 515 - 7th Street South
th
Legislation Seminar on October 26 Please indicate if you or your Lethbridge, Alberta T1J 2G8
th
and 27 . For course information and company would like to be included on Tel (403) 394-1011
Fax (403) 327-2483
upcoming training inquiries, please our electronic mailing list to be
see our listings on the absa.ca notified of upcoming seminars and Medicine Hat
website. training programs. Keep watching #103, 346 - 3rd Street S.E.
The Pressure News for Medicine Hat, Alberta T1A 0G7
Tel (403) 529-3514
We are developing the ABSA training announcements from the training Fax (403) 529-3632
page to be introduced with our department, and look for the
redesigned website, and will be revamped website launch! Red Deer
including an industry needs #304, 4406 Gaetz Avenue
Red Deer, Alberta T4N 3Z6
Tel (403) 341-6677
Fax (403) 341-3377

CONTENTS St. Paul


Please note that our St. Paul office has
been closed. All services will be provided
Flare Lines and Flare Knockouts .................................................................... 1 through the Edmonton Office.
ABSA Update Seminar ................................................................................... 1
Special Considerations for Alternative Leak Testing and Closure Welds ........ 2
Internet address
Company Annual Renewal of Power Engineering Certificates ....................... 2 http://www.absa.ca
Pressure Piping Construction Documents ...................................................... 3
Changes to the Information Bulletins Web Pages .......................................... 3
Pressure Equipment Safety Training .............................................................. 4

This Newsletter is a publication of #200, 4208-97 Street


Alberta Boilers Safety Association Edmonton, Alberta
(ABSA). ABSA grants readers T6E 5Z9
permission to make photocopies of
this Newsletter for free distribution to
employees and business associates. Return undeliverable Canadian
addresses to the above address
Articles may be copied in part or in
whole provided credit be given to
ABSA.

Subscription Change
If the newsletter subscriber s status with
your company has changed, please advise
ABSA by:
phone (780) 437-9100
fax (780) 437-7787, or
e-mail webmaster@absa.ca

You might also like