Professional Documents
Culture Documents
Table of Contents
Records . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
Right-of-Way Inspection and Maintenance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
Pressure-Control, Pressure-Limiting, and Pressure-Relieving Devices . . . . . . . . . . . . . . . 33
Change of Class Location and Crossings of Existing Pipelines . . . . . . . . . . . . . . . . . . . . . 35
Evaluation of Imperfections and Repair of Piping Containing Defects . . . . . . . . . . . . . . . . 37
Maintenance Welding . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
Pipeline Hot Taps . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53
Integrity of Pipeline Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
Change in Service . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
Upgrading to Higher Maximum Operating Pressures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56
Pressure Testing Existing Piping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57
Engineering Assessments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
Piping Deactivation and Reactivation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60
Abandonment of Piping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61
Detailed Site Specific Operations and Maintenance Procedures: . . . . . . . . . . . . . . . . . . . 61
A. Background Information Required . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61
B. Inspection and Monitoring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62
C. Preventative Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63
D. Pipeline Failure/Repair . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63
E. Record Retention Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
F. Decision Trees . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
G. Other Requirements: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
Sour Gas Pipeline Failure Decision Tree . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65
Pipeline Decision Tree for Internally Bare Pipe Failures . . . . . . . . . . . . . . . . . . . . . . . 66
Pipeline Decision Tree for Plastic and Cement Coated Pipe Failures . . . . . . . . . . . . . 67
Recommended Failure Follow Up Procedure: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
Pipeline Coupon/Sample Handling Procedure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
Summary of Pipeline Inspection and Repair Methods . . . . . . . . . . . . . . . . . . . . . . . . 70
Pipeline Design, Operations, and Maintenance Procedure Manual
Table of Contents
PREVIOUS
Pipeline Design, Operations and Maintenance Procedure Manual
1.1) This manual is applicable to all pipelines and pipeline facilities designed to transport oil,
gas, water, and liquid hydrocarbons. Pipelines in Canada are designed in accordance with
the latest edition of Canadian Standards Association (CSA) Z662 and the above ground
piping is designed as per American National Standards Institute (ANSI) B31.3. The
Alberta Energy Utilities Board (AEUB) considers all lease piping to be covered by CSA
Z662 unless the piping is on a manufactured skid which was constructed in accordance
with ANSI B31.3 and then trucked to the lease. The Amoco drawing A-TIP-120-07/ A-
TIP-120-08, included in this section, shows the boundaries for various codes that are
applicable for the construction of oil and gas pipelines.
1.2) When designing any pipeline or facility, the hierarchy of codes and requirements are:
1.3) Please refer to Table 1 for a listing of the applicable regulations, codes, and engineering
specifications. The regulations and codes are legal requirements that must be adhered to.
Deviations should be made following the requirements of Safety Health and Environment
Management System (SHEMS) Element 12.
1.4) When designing and constructing a pipeline system, the corrosiveness of the service
conditions is an important consideration that affects the design. When determining if the
service condition of a pipeline is classified as corrosive, the following guidelines taken
from CSA Z662, Clause 9.4.1 should be considered when determining if a gas is
corrosive:
1.4.1) Any gas whose water dew point is at all times below the minimum pipeline
operating temperature is considered to be non corrosive, unless tests and
experience indicate otherwise.
1.4.2) Any gas whose water dew point exceeds the minimum pipeline operating
temperature is considered to be corrosive, unless tests and experience indicate
otherwise.
1.4.3) Any gas containing hydrogen sulfide or carbon dioxide whose water dew point
exceeds the minimum operating temperature is considered corrosive, unless tests
or experience indicate otherwise.
3/15/00 3
Pipeline Design, Operations and Maintenance Procedure Manual
1.4.4) Any gas containing hydrogen sulphide or carbon dioxide whose water dew point
is maintained below the minimum operating temperature by dehydration, and is
suitably inhibited, is considered to be non corrosive, unless testes or experience
indicate otherwise.
1.4.1.5)Fluids that contain free water, bacteria, oxygen, hydrogen sulfide, carbon dioxide
or suspended or dissolved solids, singly or in combination, are considered to be
corrosive unless tests or experience indicate otherwise.
1.5) If it is possible that the production may turn sour during the production life or if there is
potential for this line to carry sour production in the future, consideration should be given
to designing and constructing the system to the sour service requirements of the pipeline
Regulations and code requirements. The cost associated with designing and constructing
to the sour service requirements are minimal when lines are being constructed; however,
after the line is built it can become expensive to upgrade for sour service.
1.6) Pipelines transmitting gas with a content of more than 10 moles of hydrogen sulfide gas
per kilomole of natural gas shall be designed so that the design stress shall not be greater
than 50% Specified Minimum Yield (SMYS) for above ground lines, and 60% SMYS for
below ground installations. (Pipeline Act, Clause 13)
1.7) Pipelines in corrosive service should be designed so that they can be inspected with
pipeline inspection tools. The radii of bends, and the inside diameter of transitions, and or
pups, must be large enough to ensure passage of an inspection tool.
1.7.1) When it is anticipated that the production will have solids, paraffin, and/or
asphaltene deposits; or low velocity laminar flow with a free water phase, the
system should be designed so that cleaning and inspection pigs can be run on a
regular basis. The frequency of the cleaning pig runs will be based on the service
conditions and system experience.
1.7.2) Pipelines in corrosive service will be designed and fabricated with chemical
injection facilities available and suitably sized for the anticipated production at
initial startup up.
1.8) A continuous, electrically insulated, metallic marker wire shall be installed in the ditch
adjacent to non-metallic pipelines; such markers shall not be positioned below the pipe.
3/15/00 4
Pipeline Design, Operations and Maintenance Procedure Manual
Government Regulations: • Provincial regulations, including (for Alberta) AEUB Pipeline Act,
Pipeline Regulations, Oil and Gas Conservation Act, Oil and Gas
Conservation Regulations, and interim directives.
• Conditions stipulated in the AEUB construction permits
• National Energy Board (NEB) regulations (for pipelines crossing
provincial border)
• Alberta Environmental Protection (including Forestry, Fish and Wildlife,
Water Resources Branch) regulations or equivalent regulations in other
provinces
• Alberta Occupational Health and Safety (OH&S) Regulations
• Alberta Safety Codes Act and Regulations
• Federal Coast Guard regulations (for navigable water crossings)
• Municipal by-laws (where applicable)
Standards and Codes: • CSA Standard Z662 (Oil & Gas Pipeline Systems)
• CSA Standard Z245.1 (steel line pipe)
• CSA Standard Z245.11 (fittings)
• CSA Standard Z245.12 (flanges)
• CSA Standard Z245.15 (valves)
3/15/00 5
Pipeline Design, Operations and Maintenance Procedure Manual
3/15/00 6
Pipeline Design, Operations and Maintenance Procedure Manual
3/15/00 7
Pipeline Design, Operations and Maintenance Procedure Manual
All new or replacement sour gas pipelines and pipelines in corrosive service must be constructed
so that it is possible to inspect them throughout their length or pig them should the need arise at
some point in their operating life. Lines must be constructed to ensure they are compatible with
available inspection tools, the most critical area being riser design. Lines constructed to ensure
inspection tool compatibility will also be piggable.
Note: If conditions are outside those specified or if clarification is required for specific conditions
contact the corrosion/inspection group.
3/15/00 8
Pipeline Design, Operations and Maintenance Procedure Manual
Notes:
3/15/00 9
Pipeline Design, Operations and Maintenance Procedure Manual
3/15/00 10
Pipeline Design, Operations and Maintenance Procedure Manual
Cement lined steel • prevents corrosion if • care required in cement • commonly used for 1.15
pipe installed properly coating application and produced water,
field installation emulsion or other
• restricts field bending corrosive applications.
HDPE lined steel pipe • prevents corrosion • not suitable for sour • suitable for produced 1.40
• a cost effective option application water pipelines
for rehabilitating • not suitable for fluids
existing pipelines with aromatics
Internally coated steel • prevents corrosion • special care required • a possible choice for 1.25
pipe with mechanical for installation. corrosive applications
joints (i.e. zap lock) • mechanical joints not
as reliable as welded
steel pipe
Fiberglass insert in • prevents corrosion • material not as • suitable for corrosive insufficient data
existing steel pipe homogeneous as steel applications where the
• poor ductility use of a fiberglass
• requires special care in insert of smaller
transportation and diameter than the steel
installation pipe is still adequate
• no field bending for the flow rate.
AEUB has recently
given permit to use
fiberglass inserts for
sour gas application on
an experimental basis
Nylon liners • prevents corrosion • several sour gas • limitations are yet to be insufficient data
• not effected by installations have been established
hydrocarbon gases or successfully installed
aromatics
Plastic pipelines • cost effective with • suitable for low insufficient data
plow in construction pressure and low flow
rate sweet fluids
3/15/00 11
Pipeline Design, Operations and Maintenance Procedure Manual
3.1) General:
Section 3 covers the requirements for the control of corrosion of steel pipeline systems
that are buried, submerged, or exposed to the atmosphere.
Operating Companies shall establish and maintain the procedures necessary to satisfy the
requirements of Section 3 except in those specific circumstances where the operating
experience has proven that specific corrosion control procedures are not justified; such
exceptions shall be documented.
3.2.1) Cathodic protection shall be applied as soon as practicable, but not later than one
year after installation, and shall be maintained during the useful life of the piping.
3.2.2) Existing Coated Piping: Cathodic protection shall be provided and maintained on
existing coated piping.
3.2.3) Existing Bare Piping: Investigations shall be made to determine the extent and
effect of corrosion on existing bare piping. Where such investigations indicate
that continuing corrosion will create a hazard, corrosion control measures or other
remedial action shall be undertaken.
3.2.4) Deactivated Piping: Cathodic protection shall be maintained on piping that is out
of service, but not abandoned.
3.2.5) Electrical Isolation: Where insulating devices are installed to provide electrical
isolation of piping to facilitate the application of corrosion control, they shall be
properly rated for temperature, pressure, and electrical properties, and shall be
resistant to the service fluid. Insulating devices shall not be installed in enclosed
areas where combustible atmospheres are likely to be present. See attached
“Appendix I”.
3/15/00 12
Pipeline Design, Operations and Maintenance Procedure Manual
3.2.6) Electrical Interference - Direct Current: Tests shall be carried out to determine the
presence or absence of stray direct currents. Where stray direct currents are
present, measures shall be taken to prevent external corrosion and other
detrimental effects.
Note: Tests for interference from impressed cathodic protection and other direct-
current-generating systems should be jointly arranged and conducted with the
owners of neighbouring foreign structures, and any detrimental effects mitigated.
Procedures for the detection of and protection against stray current corrosion are
given in CSA Standard C22.3 No. 4 and in Appendix C of CGA Recommended
Practice OCC-1.
I. Properties:
- Coatings shall:
(a) electrically isolate the external surfaces of the piping from the
environment
3/15/00 13
Pipeline Design, Operations and Maintenance Procedure Manual
- Attachments of test lead wires to the pipe shall be made without causing
harmful effects to the pipe, and such that they remain mechanically
secure and electrically conductive:
- Other methods of brazing to attach electrical test lead wires directly to the
pipe shall not be used.
- Bare test lead wires and attachments shall be coated with an electrically
insulating material compatible with the pipe coating and test lead wire
insulation.
3.2.10) Cathodic Protection Systems: Cathodic protection systems shall provide sufficient
current to satisfy the selected criteria for cathodic protection.
3/15/00 14
Pipeline Design, Operations and Maintenance Procedure Manual
3/15/00 15
Pipeline Design, Operations and Maintenance Procedure Manual
(c) the service, leak, and corrosion mitigation history of the piping
I. General:
- Any gas whose water dew point is at all times below the minimum pipeline
system operating temperature is considered to be noncorrosive, unless tests or
experience indicate otherwise.
- Any gas whose water dew point exceeds the minimum pipeline system operating
temperature is considered to be corrosive, unless tests or experience indicate
otherwise.
- Any gas containing hydrogen sulphide or carbon dioxide whose water dew point
exceeds the minimum operating temperature is considered to be corrosive, unless
tests or experience indicate otherwise.
- Any gas containing hydrogen sulphide or carbon dioxide whose water dew point
is maintained below the minimum operating temperature by dehydration, and is
suitably inhibited, is considered to be noncorrosive, unless tests or experience
indicate otherwise.
3/15/00 16
Pipeline Design, Operations and Maintenance Procedure Manual
- Fluids that contain free water, bacteria, oxygen, hydrogen sulphide, carbon
dioxide, and suspended or dissolved solids, singly or in combination, are
considered to be corrosive unless tests or experience indicate otherwise.
II. Mitigation:
III. Monitoring:
3/15/00 17
Pipeline Design, Operations and Maintenance Procedure Manual
Records of the internal and external corrosion control programs of active and deactivated
piping shall be maintained.
3/15/00 18
Pipeline Design, Operations and Maintenance Procedure Manual
Start Up Requirements
4.1) Ensure that there is a permit to operate from the AEUB and that there has been a
successful pressure test on the system.
4.2) Confirm removal of all test fluids and if the line is in corrosive service that there has been
an initial corrosion inhibitor batch treatment carried out on the line.
4.3) The line should be purged with inert or fuel gas prior to start up.
4.4) Start continuous or batch corrosion treatment on the system if required. The cathodic
protection of the pipeline must be initiated within 12 months of installation (P/L
Regulations 9.2.1.2)
4.6) Care must be exercised if start up problems are encountered to ensure that shut in periods
without pigging the system or taking special inhibition procedures do not exceed 24
hours.
4.7) On corrosive systems inhibition MUST BE initiated and maintained as soon as pipeline
operation is started.
3/15/00 19
Pipeline Design, Operations and Maintenance Procedure Manual
Requirements
(a) operate and maintain their pipeline systems in accordance with documented
procedures
(d) modify such procedures from time to time as experience dictates and as changes
in operating conditions require.
3/15/00 20
Pipeline Design, Operations and Maintenance Procedure Manual
Notes:
(3) Within the context of the overall management of safety and integrity,
risk analysis can provide a valuable tool in the assessment of the
significance of pipeline incidents. Appendix B in CSA Z-662 provides
basic guidelines for risk analysis of pipelines.
Communication facilities shall meet the requirements for safe operation and
maintenance of pipeline systems.
Note: Matters that should be considered include, but are not limited to, the
following:
(f) vegetation
3/15/00 21
Pipeline Design, Operations and Maintenance Procedure Manual
(j) aesthetics
- General:
Signs shall be installed to identify the presence of pipelines in order to reduce the
possibilities of damage and interference. Such signs shall be posted along pipeline
rights-of-way, as applicable, as follows:
3/15/00 22
Pipeline Design, Operations and Maintenance Procedure Manual
- Spacing:
Signs shall be located and spaced on the basis of consideration of the service
fluid, population density, land use, nature of terrain, fencing, potential for access
by the public to the rights-of-way, and the need for public awareness.
- Signs:
(a) signs include a statement such as "Call before you dig" or "Call for
locate"
Signs shall be installed where pipelines enter and exit road and railway rights-of-
way and, where practicable, shall be visible from the travelled roadway or track.
3/15/00 23
Pipeline Design, Operations and Maintenance Procedure Manual
- Urban Areas:
In heavily developed urban areas, signs shall not be required where the placing of
signs is impractical, or where they would not serve their intended purpose. In
such areas, alternative identification methods shall be considered.
- Property Boundaries:
- Water Crossings:
- Aerial Crossings:
Aerial pipeline crossings, other than those carried on bridges, that might pose a
hazard to air or water navigation shall be marked or lighted, or both, in
accordance with the Transport Canada "Standard Obstructions Markings" Manual.
- Sign Maintenance:
- Construction Sites:
Note: It is recommended that the colour yellow be used for such markings.
3/15/00 24
Pipeline Design, Operations and Maintenance Procedure Manual
3/15/00 25
Pipeline Design, Operations and Maintenance Procedure Manual
Records
5.3) Records covering the operation and maintenance of pipeline systems shall be prepared.
Such records shall be kept current and readily accessible to operating and maintenance
personnel requiring them.
(i) Pipes - locations and lengths for each pipe diameter installed,
noting wall thicknesses, grades and standards or specifications,
field test pressure, and where practical, burial depth.
(ii) Stations and other facilities - maximum operating limits, and the
specifications and nameplate data of major equipment.
3/15/00 26
Pipeline Design, Operations and Maintenance Procedure Manual
5.3.3) Leaks and Breaks: Records shall be prepared documenting any pipeline leaks or
breaks discovered and the repairs made breaks shall be recorded in detail. Records
shall also be prepared documenting failure investigations (see CSA Z-662 Clause
10.2.3). Such records, together with leakage survey records, line patrol records,
and other inspection records, shall be retained by the operating Company as long
as the affected portions of the pipeline system remain in operation.
3/15/00 27
Pipeline Design, Operations and Maintenance Procedure Manual
Safety
5.4.1) Training Programs: Operating Companies shall have safety training programs for
employees. Such programs shall be directed towards the operation and
maintenance of pipeline systems in a safe and effective manner and shall include
provision for the safety of the public.
5.4.3) Supervisor Responsibility: Supervisors shall instruct workers under their control
to work safely.
5.4.4) Hazards: Where conditions arise that present hazards, immediate steps shall be
taken to eliminate the hazards.
5.4.5) Security: Conditions that could adversely affect the security of the pipeline
system shall be corrected.
- The need for firefighting and other special equipment shall be assessed
and, where considered necessary by the operating Company, such
equipment shall be made available.
3/15/00 28
Pipeline Design, Operations and Maintenance Procedure Manual
5.4.8) In-Service Pipelines: Pipeline pressures shall be at safe levels when work is being
performed on in-service pipelines. Variables to be considered in the evaluation of
safe working pressures shall include, but not necessarily be limited to, pipe wall
thickness and material, stress level, and the conditions of flow and temperature of
the service fluid.
5.4.9) Smoking and Open Flames: Smoking and open flames in other than designated
safe areas shall be prohibited in facilities such as stations, terminals, and tank
farms, and at any site where flammable vapours or gases could exist. It shall be
permissible to perform welding and oxygen-cutting operations at such locations
only in the designated safe areas; such operations shall be performed under
controlled conditions.
Note: Designated safe areas are areas that have been designed to be intrinsically
safe, or have been tested for flammable vapours and approved as being safe by a
qualified person.
5.4.10) Additional Precautions for Pipeline Systems Transporting High Vapour Pressure
(HVP) Hydrocarbons:
Notes:
1) Methods and procedures for the repair and operation of crude oil and
product lines are generally applicable to the repair and operation of HVP
pipeline systems.
2) HVP vapours may be heavier than air and could tend to remain close to
the ground and accumulate in low places.
Note: Temporary lines bypassing the leak areas are recommended where
circumstances make them appropriate.
3/15/00 29
Pipeline Design, Operations and Maintenance Procedure Manual
Note: Such special precautions may include, but not necessarily be limited
to, the following:
Due to the toxic nature of sour fluids, special training shall be provided to
operating personnel to ensure the selection of appropriate equipment such as
suitable breathing apparatus and means of leak detection. Provisions shall be
included for safely disposing of blowdown gas, and for notifying the public of
potential hazards, including the posting of suitable notices.
Notes:
(2) Sour fluids are those fluids that upon release to the atmosphere can
reasonably be expected to result in hydrogen sulphide levels of 10 ppm
or greater.
Carbon dioxide, although nontoxic, has a specific gravity greater than that of air
and can accumulate in low-lying areas. Personnel working on in-service carbon
dioxide pipelines shall be trained in safe working procedures for oxygen-deficient
atmospheres.
3/15/00 30
Pipeline Design, Operations and Maintenance Procedure Manual
(c) erosion
(e) scour
(h) subsidence
(e) terrain
(f) weather.
5.5.2) Vegetation Control: Where the terms of the easement permit, vegetation on rights-
of-way shall be controlled to maintain clear visibility from the air and provide
ready access for maintenance crews.
3/15/00 31
Pipeline Design, Operations and Maintenance Procedure Manual
5.5.3) Exposed Facilities: Valves and other exposed facilities on pipeline rights-of-way
shall have access maintained and shall be protected to minimize the possibility of
unauthorized operation.
5.5.4) Crossings:
(c) railways
(d) roads
(e) water.
Water crossings in the company are inspected and managed through the
“Pipeline River Crossing Management System”
- Where required, temporary crossings for vehicular traffic over pipelines shall be
prepared and used to protect the pipeline from damage.
3/15/00 32
Pipeline Design, Operations and Maintenance Procedure Manual
(b) adequate from the standpoint of capacity and reliability for the service
in which they are employed
(d) properly installed and protected from dirt and other conditions that
might prevent their proper operation.
- Records of such tests and inspections, and the records of any corrective action
taken, shall be retained by the operating Company.
5.6.1) Valves:
- The open and closed positions of major valves shall be visually identifiable.
- Pipeline valves that might be required during an emergency shall be inspected and
partially operated at least once per calendar year, with a maximum interval of 18
months between such inspections and operations.
3/15/00 33
Pipeline Design, Operations and Maintenance Procedure Manual
5.6.2) Vaults: Regularly scheduled inspections shall be made of vaults housing pressure-
control, pressure-limiting, and pressure-relieving devices to confirm that they are
in good physical condition and adequately vented. Such inspections shall include
the testing of the atmosphere in such locations for combustible and toxic gases
and vapours. Any leaks found shall be repaired. The ventilating equipment shall
also be inspected to confirm that it is functioning properly. Ventilating ducts that
are obstructed shall be cleared. Vault and enclosure covers shall be carefully
examined for potential safety hazards.
3/15/00 34
Pipeline Design, Operations and Maintenance Procedure Manual
5.7) Change of Class Location and Crossings of Existing Pipelines shall be based on:
(c) type, proximity, and extent of the development that has increased
the class location, giving consideration to concentrations of people,
such as those associated with schools, hospitals, small
subdivisions, and recreation areas built near existing pipelines.
- Where the engineering assessment (see CSA Z-662 Clause 10.7.1.1) indicates that
the section of pipeline is satisfactory for the changed class location, no change to
the maximum operating pressure shall be required.
- Where the engineering assessment (see CSA Z-662 Clause 10.7.1.1) indicates that
the section of pipeline is not satisfactory for the changed class location, as soon as
practicable either the pipe shall be replaced or a revised maximum operating
pressure, calculated according to the requirements of CSA Z-662 Clause 8.5 for
the changed class location, shall be used.
3/15/00 35
Pipeline Design, Operations and Maintenance Procedure Manual
- Where the engineering assessment (see CSA Z-662 Clause 10.7.1.1) reveals that
the pipeline is in satisfactory condition, it shall be permissible to use any crossing
design (such as casing, change in pipe specification, suitable depth of cover, or
load- distributing structure) that results in combined pipe stresses in accordance
with the requirements of CSA Z-662Clause 4.6, as determined from the detailed
engineering analysis (see CSA Z-662 Clause 10.7.2.1(b)).
3/15/00 36
Pipeline Design, Operations and Maintenance Procedure Manual
5.8) Evaluation of Imperfections and Repair of Piping Containing Defects shall be based on:
- Where imperfections are found in steel piping, evaluations shall be made in order
to determine the suitability of such piping for continued service. Where
considered appropriate, evaluations of imperfections shall include inspection
methods capable of detecting cracks.
- External coatings that conform to the requirements of CSA Z-662 Clause 9.2.8
shall be applied following cleaning, evaluation, and repair operations.
- Where piping is not qualified for continued service at the established operating
pressure due to the presence of defects, either the piping shall be operated at
pressures that are determined by engineering assessment to be acceptable, or the
affected piping shall be repaired in accordance with the applicable requirements
of CSA Z-662 Clauses 10.8.2 to 10.8.6 inclusive. The engineering assessment
shall include consideration of service history and loading, anticipated service
conditions (including the effects of corrosive and chemical attack), the
mechanism of defect formation, defect dimensions, defect growth mechanisms,
failure modes, and material properties (including fracture toughness properties).
- Pipe containing leaks shall be repaired by using one or more of the following
methods:
(a) The section of pipe containing the leak shall be replaced in accordance
with the requirements of CSA Z-662 Clause 10.8.5.3.
3/15/00 37
Pipeline Design, Operations and Maintenance Procedure Manual
5.8.1) Imperfections in Pipe: For pipeline systems that are likely to contain internal
corrosion imperfections, the assessment of external imperfections shall include an
assessment for any coincident internal corrosion imperfections.
A. Corrosion Imperfections:
- Corroded areas that have a depth greater than 10%, up to and including
80%, of the nominal wall thickness of the pipe shall be permitted,
provided that the longitudinal length of the corroded area (see Figure
10.1) does not exceed L, as determined by the following equation:
L 1.12B(DT)½
where
3/15/00 38
Pipeline Design, Operations and Maintenance Procedure Manual
c⁄t
-------------------------------
2
= - – 1
1.1c ⁄ t – 0.15
where
- Pipe containing corroded areas that exceed the depth or length limits specified in
CSA Z-662 Clauses 10.8.2.2.3 and 10.8.2.2.4 shall be repaired using one or more
of the following methods:
(b) The corroded area shall be removed by hot tapping in accordance with
the requirements of CSA Z-662 Clause10.8.5.5.
(c) The section of pipe containing the corroded area shall be replaced in
accordance with the requirements of CSA Z-662 Clause 10.8.5.3.
3/15/00 39
Pipeline Design, Operations and Maintenance Procedure Manual
Longitudinal
Length
Maximum depth of
corroded area
c
t
G
G
Longitudinal
Axis
Notes:
(1) Corroded areas in close proximity are considered to interact if the distance between them, G, is less that the longitudinal
length of the smallest area.
(2) The longitudinal length in all cases is measured along the longitudinal axis of the pipe.
(3) For areas of internal corrosion, c Should be increased and G decreased to compensate for any uncertainty in
measurement.
Figure 10.1
Method of Deriving Longitudinal Length of Corrosion
3/15/00 40
Pipeline Design, Operations and Maintenance Procedure Manual
- Where internal corrosion growth has not been arrested, the determination of the
repair method shall include an engineering assessment that considers corrosion
abatement effectiveness, the reinspection interval, and, where a repair sleeve is
considered, the need for a steel pressure-containment repair sleeve that is in
accordance with the requirements of CSA Z-662 Clause 10.8.5.4.2.
Bmax, B1max=4.0
4.0
3.5
3.0
2.5
B
2.0
B1
1.5
1.0
0.5
0.0
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8
c/t
Figure 10.2
Relationship between B, B1 and c/t
Note: For gouges, grooves, or arc burns in dents, see CSA Z-662 Clause
10.8.2.4.1.
-Where such a defect is located on the pipe body or a mill weld, the pipe
containing the defect shall be repaired using one or more of the
following methods:
(b) The defect shall be removed by hot tapping in accordance with the
requirements of CSA Z-662 Clause 10.8.5.5.
3/15/00 41
Pipeline Design, Operations and Maintenance Procedure Manual
- Where such a defect is located on a field weld, the pipe containing the
defect shall be repaired using one or more of the following methods:
C. Dents:
(c) Except for such defects located on a field weld, the defect shall be
removed by hot tapping in accordance with the requirements of CSA
Z-662 Clause 10.8.5.5.
3/15/00 42
Pipeline Design, Operations and Maintenance Procedure Manual
- Dents that are located on the pipe body and exceed a depth of 6 mm in
pipe 101.6 mm OD or smaller, or 6% of the outside diameter in pipe larger
than 101.6 mm OD, shall be considered to be defects. Pipe containing
such defects shall be repaired using one or more of the following methods:
(b) The defect shall be removed by hot tapping in accordance with the
requirements of CSA Z-662 Clause 10.8.5.5.
- Dents that are located on a mill or field weld and exceed a depth of 6 mm
are considered to be defects. Pipe containing such defects shall be
repaired using one or more of the following methods:
(b) Where the defect is located on a mill weld, the defect shall be removed
by hot tapping in accordance with the requirements of CSA Z-662
Clause 10.8.5.5.
3/15/00 43
Pipeline Design, Operations and Maintenance Procedure Manual
(b) The defect shall be removed by hot tapping in accordance with the
requirements of CSA Z-662 Clause 10.8.5.5.
Note: Pipe body surface cracks include stress corrosion cracks (cracks that
result from the interaction of tensile stress and corrosion). For cracks in
dents above.
- Where flammable mixtures are present, pipeline cuts shall be made with
mechanical cutters.
3/15/00 44
Pipeline Design, Operations and Maintenance Procedure Manual
-----------------------------------------
Minimum replacement
----------------------------------------
168.3-610 incl. 2 x OD
----------------------------------------
(a) the repair sleeves are not less than 100 mm long and extend
longitudinally at least 50 mm beyond the ends of the defects
3/15/00 45
Pipeline Design, Operations and Maintenance Procedure Manual
iv)adequatesupportoftherepairsleevesduringinstallationandoperation
(e) Steel reinforcement repair sleeves not welded to the pipe shall
meet the following supplementary requirements:
(iii) Electrical continuity shall be ensured between the pipe and the
steel reinforcement repair sleeve.
3/15/00 46
Pipeline Design, Operations and Maintenance Procedure Manual
(i) they are designed for, and constructed of, material that is suitable
for welding
(ii) they are fillet welded to the pipe and seal welded to have the
ability to contain pipeline pressure within the sleeve in accordance
with the design requirements.
(a) The sleeve system shall be tested and qualified to satisfy the following:
(ii) Cathodic disbondment tests shall verify that the sleeve system is
compatible with cathodic protection systems.
3/15/00 47
Pipeline Design, Operations and Maintenance Procedure Manual
(i) The combined nominal load-carrying capacity of the sleeve and the
remaining pipe wall shall be at least equal to that of the originally
installed pipe.
(iii) The sleeve system shall be designed to operate over the full
temperature range expected during operation of the pipeline.
(c) The repair sleeve shall be handled and installed to satisfy the
following:
(iii) Sleeves shall not be used to repair leaks defects where metal loss
exceeds 80% of nominal wall thickness dents or gouges, grooves,
arc burns, or cracks that have not been removed by grinding.
(a) The location, orientation, width, and length of the defect shall be
determined by visual and nondestructive inspection.
(b) The entire defect shall be contained within the metal that is removed by
hot tapping.
3/15/00 48
Pipeline Design, Operations and Maintenance Procedure Manual
- Mechanical leak clamps and bolt-on split sleeves that meet the applicable
requirements of CSA Z-662 Clause 10.8.5.4 shall be permissible as
temporary repair devices. Where special conditions prevent permanent
repairs from being made within one year, sufficient periodic inspections
shall be made to confirm that the defective condition corrected by the
temporary repairs has not extended, that leaks have not recurred, and
that the temporary repair device has not deteriorated.
3/15/00 49
Pipeline Design, Operations and Maintenance Procedure Manual
Steel
Steel Fiberglass
Grinding Pipe Pressure Hot Welding
Defect Type Reinforcing Reinforcing
Repair Replace contain. Tap Repair
Sleeve Sleeve
Sleeve
Corrosion Defect
external x 0 0 0 1 0 x
Internal x 0 0 0 1 0 x
Dent Defect
Weld Defect
in a circ weld 0 0 0 x x x 0
in a seam weld 0 0 0 x x 0 x
Grind Defect x 0 0 0 1 0 x
Leak x 0 0 x x x x
Notes:
0 = there is no limitation
1 = This repair method is not acceptable for defects with metal loss in excess of 80% of the nominal wall thickness
2= The stress concentrator(gouge, groove, arc burn, or crack) shall be removed by grinding prior to the application of the sleeve
3= The stress concentrator (gouge, groove, arc burn, or crack) shall be removed by grinding prior to the dent being assessed for
acceptability accordance with the applicable requirements, with the depth of the ground area being excluded from the dent depth
3/15/00 50
Pipeline Design, Operations and Maintenance Procedure Manual
Maintenance Welding
- Fillet welds shall be made using a low hydrogen welding practice (see
CSA Z-662 Clause 7.2.2.7).
3/15/00 51
Pipeline Design, Operations and Maintenance Procedure Manual
- An increase in the carbon equivalent of more than 0.02% from that of the
material used for the welding procedure qualification shall be considered
to be an essential change, and shall necessitate requalification of the
welding procedure or establishment and qualification of a new welding
procedure.
3/15/00 52
Pipeline Design, Operations and Maintenance Procedure Manual
5.10.1) Hot tap connections shall be made in accordance with established procedures.
Such connections shall be considered to be permanent facilities, provided that the
attachments are completed in accordance with procedures that comply with the
requirements of CSA Z-662 Clauses 10.9 and 10.10.
- It shall be permissible that branch-to-run pipe welds and hot- tap cuts
pass through the run pipe seam however, such welds and cuts shall not
pass through welds repairs or circumferential welds.
- For hot-tap connections on steel pipelines, the affected areas of the run
pipes (including the pipe seams) shall be inspected for defects.
5.10.4) Parameters:
(a) the size, grade, and wall thickness of the run pipe
(c) the flow and temperature conditions of the service fluid in the run
pipe
3/15/00 53
Pipeline Design, Operations and Maintenance Procedure Manual
- Where the operating company becomes aware of conditions that may lead to
failure in it’s pipeline systems, it shall conduct an engineering assessment to
determine which portions may be susceptible to failures and whether such
portions are suitable for continued service.
- Where the operating company intends to operate the pipeline system at a pressure
that is significantly higher than the established operating pressure, and which may
therefore lead to failures in the pipeline system, it shall conduct an engineering
assessment to determine which portions may be susceptible to failures, and
whether such portions are suitable for the intended operating pressure.
- Where the engineering assessment indicated that portions of the pipeline system
may be susceptible to failures, the operating company shall implement such
corrective measure as may be necessary to prevent such failures, or operate the
system under conditions that are determined by an engineering assessment to be
acceptable.
Note: Examples of corrective measures include pressure testing (see CSA Z-662
Clause 10.11.5), repair, and replacement of sections of the pipeline system.
3/15/00 54
Pipeline Design, Operations and Maintenance Procedure Manual
Change in Service
- Where the engineering assessment indicates that the pipeline system would not be
suitable for the new service fluid, the operating company shall implement such
corrective measures as may be necessary to make it suitable before the change in
service.
Note: Examples of corrective measures include pressure testing (see CSA Z-662
Clause 10.11.5) and repair or replacement of portions of the pipeline system.
3/15/00 55
Pipeline Design, Operations and Maintenance Procedure Manual
- Where the engineering assessment indicated that the pipeline system would not be
suitable for service at the proposed higher maximum operating pressure, the
operating company shall implement such changes as may be necessary to make it
suitable, and shall, except where allowed by CSA Z-662 Clause 10.11.4.4,
pressure test the piping in accordance with the applicable requirements of CSA Z-
662 Clauses 8 and 10.11.5.
- Where the engineering assessment indicates that the pipeline system would be
suitable for service at the proposed higher maximum operating pressure, the
operating company shall, except where allowed by CSA Z-662 Clause 10.11.4.4,
pressure test the piping in accordance with the applicable requirements of CSA Z-
662 Clauses 8 and 10.11.5.
- For gas pipeline systems where pressure testing is not practicable, it shall be
permissible to upgrade to a higher maximum operating pressure as follows:
(i) 80% of the design pressure permitted for new piping having the
same design and material; and
(ii) repair or replace any piping that is found to be inadequate for the
upgraded pressure;
(iii) for service lines, install suitable devices to control and limit the gas
pressure in accordance with the applicable requirements of CSA Z-
662 Clause 12.4.7; and adequately reinforce or anchor any offset,
bends, and dead ends in coupled pipe to prevent movement of the
3/15/00 56
Pipeline Design, Operations and Maintenance Procedure Manual
(a) determine whether it can sustain the proposed test pressure; and
(b) establish appropriate pressure test limits so that the pressure test will
not adversely affect the integrity of the piping.
(d) critical imperfection size, growth rate, growth process, and failure
criterion;
Notes:
3/15/00 57
Pipeline Design, Operations and Maintenance Procedure Manual
5) Since failures may occur during pressurization, the pressure rise should
be closely monitored.
3/15/00 58
Pipeline Design, Operations and Maintenance Procedure Manual
Engineering Assessments
Notes:
2) Risk Analysis (see CSA Z-662 Appendix B) can provide valuable information
for the engineering assessment.
Note: Examples of such inspection and testing include in-line inspection (see
CSA Z-662 Appendix D), pressure testing (see CSA Z-662 Clause 10.11.5), test
excavations to verify coating type and condition, and testing pipe samples for
mechanical properties.
3/15/00 59
Pipeline Design, Operations and Maintenance Procedure Manual
- Deactivation of Piping:
(a) isolate the piping, using blind flanges, weld caps, or blanking plates;
(c) fill the piping with a suitable medium, having regard to the intended
duration of the deactivation, the effects of the medium on the integrity
of the piping, and the potential consequences of a leak.
(a) maintain external and internal corrosion control in accordance with the
requirements of CSA Z-662Clause 9;
(d) for piping that is deactivated for more than 18 months, annually
confirm the suitability of the deactivation methods used, the corrosion
control, and other maintenance activities
3/15/00 60
Pipeline Design, Operations and Maintenance Procedure Manual
Abandonment of Piping
Detailed site specific operations and maintenance procedures are required as laid out in the
following tables for all operating pipeline systems (applicable items only):
2. Description of the system and the Include physical and chemical properties of the substance transmitted.
substance transmitted
3/15/00 61
Pipeline Design, Operations and Maintenance Procedure Manual
Reporting
Category Frequency Requirements & Accountability
Record Location
Preventative pressure testing
Aerial reconnaissance
Leak detection:
• measurement
• gas leak survey
• Tec-scent
Electromagnetic inspection
Video inspections
Corrosion monitoring:
• coupons
• probes
3/15/00 62
Pipeline Design, Operations and Maintenance Procedure Manual
C. Preventative Maintenance
Reporting
Category Details Requirements
& Responsibilities
Corrosion inhibition program
• continuous
batch
Valves
D. Pipeline Failure/Repair
Reporting
Category Details Requirements
& Responsibilities
Failure: •Incident review
(Failure follow up and sample • follow SHEMS Element 3 for methodology
handling procedures attached) • include failure analysis and recommendations
•Recording and retention of all information related to leaks
and break
3/15/00 63
Pipeline Design, Operations and Maintenance Procedure Manual
Category Duration
ROW Inspection and leak surveys 2 years
Radiographs
• interpretations • Life of pipeline
• x-rays • 2 years
F. Decision Trees
Suggested Decision Trees for Inspection and Repair and a Summary of Inspection and Repair
Method
G. Other Requirements:
4. Emergency procedures manual for sour and high vapour pressure pipelines
3/15/00 64
Pipeline Design, Operations and Maintenance Procedure Manual
Internally Bare
Gathering Pipelines
Initial Failure
Analysis
Log
3/15/00 65
Pipeline Design, Operations and Maintenance Procedure Manual
AEUB Spill
Amoco Spill Report
Report
and AEUB Notification
Technical Analysis
Mechanical Corrosion Initial Failure Back to Economic Analysis
Risks and
Cause Cause Analysis Production Consequences
Mandatory Pass
Pressure Test
Produce As Is
Second
Failure
Check Flow Rate
3/15/00 66
Pipeline Design, Operations and Maintenance Procedure Manual
Pipeline Decision Tree for Plastic and Cement Coated Pipe Failures
Cement or Plastic
Coated Produced H2O
Injection and Oil
Gathering Lines
Operating
Failure
Determine Cause
of Failure
Mechanical
Damage e.g., Rock or
construction damage
Corrosion
Damage
Isolated Failure
(two damaged areas Extensive Damage
or less) and/or Degradation
Economics
Repair
Pressure Test
Return to Service
3/15/00 67
Recommended Failure Follow Up Procedure:
After notifying the AEUB, all failures shall be excavated and the samples handled as per the
attached procedure. Once the cause of the failure is determined (following methodology in
SHEMS Element #3) the failure review team shall assess the risk of additional failures in the line
in question as well as other lines operating under the similar conditions. If the potential for failure
is high, the line in question and lines in similar operating conditions shall be inspected and the
extent and severity of damage defined.
Based on the results of the inspection, decisions on line repair or replacement and/or the
implementation of preventative programs will be made. A final report shall be prepared and filed
documenting the cause of failure, costs incurred both direct and indirect, spill report and the
economics and program details if a preventative program is implemented.
The failure review team should consist of a foreman, the BU corrosion technologist and someone
from production or facilities engineering.
1. Excavate line as per local safety practices. Care must be taken to ensure external deposits
are not disturbed.
3. Mark top of line and direction of flow using some form of permanent identification
(centre punch or paint stick). TOP ➯ FLOW
4. Remove coupon/sample from line using local safety procedures. Cold cut line one foot on
either side of failure.
3/15/00 69
Pipeline Design, Operations and Maintenance Procedure Manual
Applicability
Recommended Applicability Applicability
for
Inspection for for Produced Purpose
Gathering
Methods Flowlines Water Lines
Lines
Electromagnetic Yes. Perform Not suitable Not suitable for Determine the extent and severity of internal and external
Inspections (EMI) on selected for cement cement lined corrosion on the body wall of pipelines
failed or high lined pipelines pipelines
risk pipelines
Coating Survey Yes Yes Yes Locate potential areas of external coating damage on pipelines
Video Inspection Yes for visual Yes Yes To evaluate the condition of cement and plastic internal
verification of coatings and locate and visually verify extent of internal defect
defects and
line condition
Preventative Yes Yes Yes Test pipelines to 1.25 time MOP with fresh water to identify
Pressure Testing and repair weak spots so as to minimize operational failures
and spillages
River Crossing Yes Yes Yes Collect site data to facilitate risk evaluation of crossings and
Survey plan follow-up inspection and re-medial work
Gas Leak Survey Yes Yes Yes - line has to Suitable for locating small failures and for use on sweet and
be displaced to a low pressure systems. Will detect and locate very low levels of
combustible gas combustible gas
Tec Scent - patented Yes Yes Yes Extremely sensitive for locating very small leaks
odorant
Fiberglass Repair Yes. Yes. Yes. Especially Prevent further external corrosion and restore pressure
Pads Especially on Especially on on risers or integrity of isolated corroded pipe sections. Suitable for
risers or shrink risers or shrink shrink sleeve isolated areas of external corrosion at locations such as risers
sleeve sleeve locations and joints. Maximum temperature: 93ûC
locations locations
Fiberglass Liner Yes - for lines Suitable for Not suitable Install inside the corroded steel pipe. A less expensive option
in oil or water pipelines compared to constructing new steel pipelines. Maximum
service without temperature: 98ûC
cement liner
High Density Not suitable Not suitable Suitable for bare Install inside steel line to prevent further internal corrosion.
Polyethylene Liner due to due to lines. Needs to be Not suitable for pipelines carrying hydrocarbon gases or
(HDPE) presence of presence of evaluated for aromatics. Maximum temperature: 60ûC
hydrocarbon hydrocarbon cement coated
gases gases lines
Nylon Liner Yes Yes Yes Good alternative to HDPE. Not affected by hydrocarbon gases
or aromatics. Higher cost, has proven serviceable in sour gas
applications
Replaced with New Yes Yes Yes Only if other less expensive options are not available
Steel Pipe
Replaced with New Yes Yes Yes Good option for replacement lines in corrosive service - not
Free Standing approved for sour service - pressure and temperature
Fiberglass Line restrictions
3/15/00 70
Pipeline Design, Operations and Maintenance Procedure Manual
Major Concerns
1. No pipeline shall transport a substance other than the one authorized (P/L Act: A - 23).
Site specific procedures and approval requirements are needed for: resumption of
operation, change of substance and change of Maximum Operating Pressure (MOP).
3/15/00 71
7.0 Suspension and Abandonment:
Major Concerns
- abandoning a pipeline.
Pipeline Design, Operations and Maintenance Procedure Manual
Non-piggable 24 hours to 3 days. 3 days to 30 days. Greater than 30 days After 6 months -
Double injection rate Lower pressure and but less than 6 months - formally suspend P/L
for 24 hours prior to sweep line with sweet install temp pigging by completing
shut in and lower P/L fuel gas and inhibited facilities and dry P/L. application to
pressure to reduce methanol slug. *1 Isolate and tag. *2 discontinue operation
partial pressure. to the AEUB.
Other Pipelines:
Piggable Less than 90 days - do Greater than 90 days - After 6 months - N/A
nothing. batch inhibit P/L to formally suspend P/L
remove all corrosive by completing
fluids using sweet dry application to
gas, inert gas or dry discontinue operation
compressed air. Isolate to the AEUB.
and tag line. *1 & *2
Non-piggable If less than 90 days and Greater than 90 days - After 6 months -
P/L is on continuous install temp. pigging formally suspend P/L
inhibitor program - facilities and pig using by completing
double inj. rate prior to inhibited methanol slug application to
shut in. If no inhibition and sweet fuel gas, discontinue operation
program - do nothing. inert gas or dry to the AEUB.
compressed air to
remove corrosive
fluids. Isolate and tag.
*1 & *2
*1 Inhibition and lay-up procedures need to be developed on a line specific basis between
operations and BU corrosion personnel. AEUB review and approval of procedure is
required for long term suspension of P/Ls.
*2 Tags to indicate date, how P/L was suspended, contents and pressure left in line.
3/15/00 73
Pipeline Design, Operations and Maintenance Procedure Manual
Non-piggable 24 hours to 3 days. 3 days to 30 days. Greater than 30 days After 6 months -
Double injection rate Lower pressure and but less than 6 months - formally suspend P/L
for 24 hours prior to sweep line with sweet install temp pigging by completing
shut in and lower P/L fuel gas and inhibited facilities and dry P/L. application to
pressure to reduce methanol slug. *1 Isolate and tag. *2 discontinue operation
partial pressure. to the AEUB.
Other Pipelines:
Piggable Less than 90 days - do Greater than 90 days - After 6 months - N/A
nothing. batch inhibit P/L to formally suspend P/L
remove all corrosive by completing
fluids using sweet dry application to
gas, inert gas or dry discontinue operation
compressed air. Isolate to the AEUB.
and tag line. *1 & *2
Non-piggable If less than 90 days and Greater than 90 days - After 6 months -
P/L is on continuous install temp. pigging formally suspend P/L
inhibitor program - facilities and pig using by completing
double inj. rate prior to inhibited methanol slug application to
shut in. If no inhibition and sweet fuel gas, discontinue operation
program - do nothing. inert gas or dry to the AEUB.
compressed air to
remove corrosive
fluids. Isolate and tag.
*1 & *2
*1 Inhibition and lay-up procedures need to be developed on a line specific basis between
operations and BU corrosion personnel. AEUB review and approval of procedure is
required for long term suspension of P/Ls.
*2 Tags to indicate date, how P/L was suspended, contents and pressure left in line.
3/15/00 74
Pipeline Design, Operations and Maintenance Procedure Manual
Appendix I
3/15/00 75
Pipeline Design, Operations and Maintenance Procedure Manual
Scope
The following guideline shall be followed on all Engineering and Construction Projects to ensure
that cathodic protection insulating gaskets are suitable for use in Amoco Canada and have been
installed as per the manufacturer’s recommendations.
Acceptable Manufacturers
There are several manufacturers of insulating gaskets who produce products that are acceptable to
Amoco Canada. To ensure consistency in construction projects, and to reduce hazards associated
with incorrect installation, the Engineering & Construction Safety Committee have selected an
insulating gasket manufactured by Pipeline Seal and Insulator Inc. The preferred gasket is
referred to as a “Linebacker G-10/viton seal, type F”.
This gasket was selected as an alternative to the commonly used phenolic/flat faced neoprene
gaskets due to its higher compression strength. The Linebacker gasket has compression strength
of 350 Mpa and will be less susceptible to damage due to incorrect installation. This insulating
gasket can be used on installations with a maximum operating temperature of 120×C and is
suitable for use on flat, raised face, ring joint or any combination of these flange types.
Installation Kit
Each installation kit will include a Linebacker Pyrox G-10 insulating gasket with a viton 0-ring,
one Pyrox G-10 insulating washer for each bolt, two zinc plated washers for each bolt and one full
length mylar sleeve for each bolt. In addition to the physical components, when specified for use
on an Amoco site, each package shall also include a Flange Make-up Procedure and suggested
bolt torque and pattern.
Installation Procedures
An incorrectly installed or damaged insulating gasket may result in the failure to electrically
insulate facilities, and / or leak at the flange connection. To avoid the problems associated with
incorrect installation, the manufacturer’s installation procedures, including recommended bolt
torque, must be followed. The Contractor’s Supervisor shall be responsible to ensure that all
workers understand the manufacturer’s installation procedures and that they are followed.
2. Check nuts and bolts to make sure threads are not damaged. Apply non-conductive
lubricant to all threads and flange side of nuts. Many lubricants are slightly conductive
and if small amounts are used there should not be a problem. A check to confirm lack of
electrical continuity will confirm correct installation.
3. Align flanges so that they are concentric and parallel and carefully install the gasket. DO
NOT use lubricant on the gasket or flange face.
3/15/00 76
5. Insert mylar bolt sleeves. No force should be required to insert. Follow-up with studs,
nuts and washers, placing the lubricated face of the nut next to the steel washer. The
insulating washer should be placed on the unprotected side of the assembly between the
flange and steel washer.
7. Check that there is no gap or separation between gasket and flanges. A flashlight, caliper,
or feeler gauge will be necessary to do this check. If there is a gap, the flanges are not
parallel and corrective action is required. Loosen nut, even if only finger tight, 180°
opposite the widest part of gap. Return to segment with gap and tighten until both flanges
are in contact with gasket retainer. Failure to follow this procedure will cause
exceptionally high flange to gasket loading with possible damage to the gasket retainer.
8. Retighten loosened nuts and proceed with torque of bolts to 10%-15% of suggested
torque value. Bolts should be tightened in accordance with tightening sequence
instructions found in each package. Tighten bolts in pairs, 180° opposite each other. As
an example, using clock positions to illustrate, snug the bolt at 11 o’clock and then at 4
o’clock. Skip the adjacent bolt to the last one tightened and proceed in a clockwise
direction tightening sequential bolts pairs. (i.e. 6-12, 2-8, 10-5, 7-1, 3-9) When torquing
bolts, only tighten the nut without the insulating washer, otherwise there is a tendency for
the bolt to shift causing the threads to cut into the mylar sleeve and short the kit.
11. On completion go completely around the flange to check for proper bolt torque.
12. All tightening must be done using a torque wrench. Improper torque values can
damage gaskets.
13. The following are the recommended torque values for the most commonly used pressure
ratings and sizes. Where necessary, additional technical information may be obtained
from the distributor Martech Marketing. (403-640-7797 or 780-454-2006).
Pipeline Design, Operations and Maintenance Procedure Manual
3/15/00 78
Pipeline Design, Operations and Maintenance Procedure Manual
Appendix II
3/15/00 79
Purpose
The following guidelines shall be followed on all Canadian Gas Business Unit projects to ensure
that shop and field applied coatings are suitable for their intended service. Amoco has
experienced significant problems with field applied coatings so special attention shall be taken to
strictly adhere to both this guideline and the coating manufacturer’s instructions for
installation. Where instructions supplied with the field coating material appear to be in conflict
with normal field installation practices, the Amoco Representative shall contact the supplier and
clarify requirements.
Responsibilities
The Project Engineer shall provide the Purchaser with project requirements and anticipated
maximum operating temperature during the life of the system to ensure that the correct material is
ordered. The Purchaser shall be responsible for ordering pipe with suitable coating, the correct
number and type of sleeves, and sufficient repair materials to correct any holidays in the coating
that occur during construction.
The Construction Contractor shall be responsible for receiving all materials on site. The
Construction Contractor shall verify that the number and type of sleeves is correct and any
discrepancies in quantity or quality shall be reported to the on-site Amoco Representative. If the
quality of the sleeve is in question or the type of material does not comply with the project
requirements, the Amoco Representative shall report the discrepancy to the Project Engineer and
shall not allow the Contractor to substitute coating materials without engineering approval.
Materials
Shaw/Canusa supplies the materials in the attached table, which are commonly used by Amoco
Canada. There are other materials supplied by both Shaw and other manufacturers that are
acceptable for the applications below; however because of their limited use in Amoco Canada,
alternative materials are not identified in the table.
Industry’s experience with field applied tape coatings has been poor. Failure of the tape allows the
ingress of water to the bare pipe, the disbonded tape acts as a barrier to the cathodic protection
current, and failure of the pipe through external corrosion is inevitable. Because of the dangers to
the environment and costs associated with clean up and pipeline rehabilitation, hand applied cold
tape shall not be used for either shop or field coatings. Heat-shrink tape may be used for the
inner coating of joints on insulated lines and for coating of curved sections in non insulated lines
where sleeves cannot be properly applied. Special attention shall be paid by both the contractor
and the Amoco representative to ensure that heat shrink tape is applied following the
manufacturer’s recommendations.
Due to the numerous factors that must be considered when specifying coatings for water and road
crossings, directional drill requirements shall be project specific and shall be determined by the
Project Engineer. In choosing the type of coating and sleeves, the Project Engineer shall consider
location, maximum operating temperature, type of fluid service, length of direction drill, potential
risks associated with failure, etc. Thrust bore kits (TBKs) may be necessary for sleeving of joints
for directional drills. TBKs would normally be considered if additional precautions, such as two
coats of polyethylene, have been applied to the directional drill section. Where TBKs are
supplied, special care must be taken to ensure that they are ordered to meet the operating
condition requirements and that the contractor is specifically trained in their application. If the
direction drill section is epoxy coated, the joints should also be protected using epoxy coatings.
Where rock shield is required, special care must be taken that any supplied material will allow the
cathodic protection current to get to the pipe. There are materials on the market, including some
types of foam protectors, which act as a barrier to the current and prevents the cathodic protection
current from doing its job. Before ordering any rock shield materials, review the product
specifications and confirm that the material will not interfere with cathodic protection current.
Where coating systems other than those identified may be required to meet project requirements
or where acceptable materials are not available, the Project Engineer in consultation with the team
leader of the Corrosion Group, shall select acceptable coating and sleeving materials.
Training
The correct application of sleeves and repair of coating holidays is one of the most critical
components to the integrity of the coating and the long-term serviceability of the pipeline. To
minimize the risks associated with improperly applied field coatings; all persons who install
coatings must be properly trained and qualified. The Construction Contractor shall ensure that the
sleeve manufacturer has trained all applicators for each type of coating or sleeve they are required
to apply. A valid performance card, issued within one year by the sleeve manufacturer to the
coating applicator, must be available on site. The Amoco Representative shall be responsible to
ensure that the Construction Contractor has documented installation procedures readily available
to installation crews and shall review all applicator’s qualifications and shall only permit those
properly trained with valid performance cards to install field coatings and sleeves.
Inspection
The Construction Contractor shall carry out holiday detection of both the shop coating and
applied sleeves using an electronic holiday detector. The voltage of the inspection instrument
shall be set within the range recommended by the supplier of the coating. Pinholes in the coating
(1.0 mm and smaller) on non-insulated pipe do not require repair as the cathodic protection is
designed to protect these small areas. Larger holidays shall be repaired using the supplied repair
materials and following the manufacturer’s installation procedures. All holidays in the both the
inner and external coatings on insulated pipe shall be repaired using the acceptable repair
materials.
The Amoco Representative shall carry out random inspections of sleeve installations and repair of
holidays on a daily basis. As a minimum, one sleeve for each installer shall be subjected to a peel
test to ensure that the mastic under the sleeve has properly flowed and sufficient adhesion is
obtained. The peel test shall be performed by cutting a strip in the sleeve measuring
approximately 25mm wide by 150mm long. The strip shall be peeled back and examined. When
sleeves have been correctly applied, the mastic shall adhere to the substrate. Depending on
temperature conditions, some mastic may be present on the peeled back strip, however that is also
acceptable. When the peel test shows the mastic not adhering to the substrate, or voids in the
mastic on the substrate are observed, it can be assumed that the sleeves are not installed correctly.
Where the results of the peel test are unsatisfactory or the installation procedure is found to be
incorrect, all sleeves or repairs carried out on that day by the installer in question shall be removed
and new sleeves or repairs applied using the correct procedure.
Revision 0
New Construction on Lines with Yellow Jacket as Mainline Coating
OPERATING COATING PIPE CANUSA SLEEVE REQUIRED REQUIRED SURFACE PREP.
TEMP (C) TYPE DIA PREHEAT ON STEEL ON COATING COMMENTS Repair Materials
<50C YJ <12" Tube type: PLA or 60C pwr wire brush must abrade fastest to apply, best patch kit c/w mastic for repairs
sleeve for 2" - 6", smaller than 75mmx 75mm. KTS
sleeves for larger areas
Wrap type: KTS 65C pwr wire brush must abrade general purpose sleeve, same as above
widely used 2" -12"
>12" Wrap type: KLS 65C pwr wire brush must abrade general purpose sleeve, same as above
over 12"
<85C YJ II 2"-16" Wrap Type: KLNN 90C pwr wire brush must abrade general purpose KLNN sleeves- no repair
materials available to handle
higher operating temperature
13"-16" Wrap Type: KLS 65C pwr wire brush must abrade operating temp on KLS sleeve or patch kit c/w for
insulate is low, KLS is small repairs
good reliable sleeve
Note: The required preheat and required surface preparation are essential for proper installation.
Note: Canusa specs show KTON is shown suitable for 65C operating temperature for new construction.It can be used as an inner sleeve under insulate at 85C as the
lack of soil stress allows the temperature rating to increase.
SCC has been identified as an issue affecting the integrity of pipelines in recent years. Due to
failures on National Energy Board regulated pipelines and a report they issued on SCC, the
Alberta Energy Utilities Board has requested that individual producers establish mitigation and
monitoring measures for SCC. We are required to maintain documentation of all SCC
investigations and report these to Canadian Association of Petroleum Producers (CAPP) for entry
into their data base. The purpose of these field investigations is to determine the extent of SCC on
Pipelines under the EUB’s jurisdiction.
SCC investigations are required if the system has a history of SCC or if the following conditions
exist:
• external coating is polyethylene tape, asphalt, coal tar or disbonded coatings such as yellow
jacket
• the operating hoop stress is greater than 45% of Specified Minimum Yield Stress of the pipe
• age of the pipeline
• potent environment at the pipe surface (this involves soil conditions and cathodic protection
levels)
The following procedure is to be used for the investigation of SCC for all pipelines in the Gas BU.
Investigation procedure:
Note: This procedure is limited to visual inspection for coating disbondment and wet magnet
particle testing (WMPT) to locate SCC.
1. Every time a pipeline is exposed for tie-ins, repairs, crossings, inspection and / or logging
the pipeline shall be inspected for coating disbondment (pay particular attention to tape
repairs and tape at joints).
2. Where disbondment is observed, the disbonded coating shall be removed back to sound
coating.
3. The entire section that has been exposed is to be cleaned by washing, light buffing, water
or sand blasting. Care must be taken to coordinate the cleaning and inspection procedures
so as to ensure that the clean pipe surface does not deteriorate prior to the SCC
inspections.
4. Inspect the exposed area using a wet magnetic particle inspection technique. If SCC is
found, perform an engineering assessment on extent of damage using ultrasonics to
define extent of damage as required. Repair by grinding out the defect if damage is within
corrosion allowance or replace affected section as required.
5. Repair coating using most recent joint / coating repair procedure.
6. Fill out attached SCC Inspection Form and submit necessary documentation to Corrosion
Engineering for all SCC investigations whether damage is found or not.
BP Amoco Canada Petroleum Company Ltd. - Stress Corrosion Cracking (SCC)
Inspection Form
This form is to be completed and forwarded to Corrosion Engineering for every pipeline
excavation site that has been checked for SCC.
❐ No ❐ Body of Pipe
❐ Coating Repair in Body of Pipe
❐ No
If SCC found: Ultrasonic Test? ❐ Yes
❐ No
❐ No
Repairs Required? ❐ Yes
❐ No
Type of repair performed:
Type of wrapping used for recoating:
Please show the approximate position of the SCC found:
Indicate the location of the ERW seam
top top
bottom bottom