Name Capital Operating Replacement Salvage Resource Total
ABB MGS100 $2,183 $3,762 $926.12 -$174.31 $0.00 $6,697
CanadianSolar
All-Black
CS6K-290MS $21,079 $5,000 $0.00 $0.00 $0.00 $26,079
Grid $0.00 -$30,262 $0.00 $0.00 $0.00 -$30,262
System $23,262 -$21,500 $926.12 -$174.31 $0.00 $2,514
Production Summary
Component Production (kWh/yr) Percent
CanadianSolar All-Black
CS6K-290MS 458,683 96.3
Grid Purchases 17,575 3.69
Total 476,258 100
Consumption Summary
Component Consumption (kWh/yr) Percent
AC Primary Load 128,946 28.7
DC Primary Load 0 0
Grid Sales 320,195 71.3